FLiDAR - Neart na Gaoithe (NNG) Validation Campaign: RESULTS for web/SMI S Presentasjonar/B...
Transcript of FLiDAR - Neart na Gaoithe (NNG) Validation Campaign: RESULTS for web/SMI S Presentasjonar/B...
[email protected] | www.flidar.com | April 2015
FLiDAR - Neart na Gaoithe (NNG) Validation Campaign:
RESULTS
FLiDAR Technology Overview
2
FLiDAR technology Overview
3
• WindCube on gimbal system
• Motion of LiDAR decoupled
from buoy motion
Data quality independent from
buoy movement
Possible to validate
independent from sea state
Buoy structure no influence
on measurements
V0.9 Buoy
Replaced with
V1.0 Buoy
Unchanged
Gimbal
Unchanged LiDAR
& Software version
FLiDAR technology Overview
Design Improvements from V0.9 to V1.0
4
• Buoy structure changed to a Mobilis platform:
• Significant weight reduction (~ 6 Ton)
• Improved handling during O&M, symmetrical hull
• 4 independent floating compartments
• Faster/cheaper multi-cat crane deployment (<10 ton)
• Uses two point mooring:
• Adds redundancy in case of failure
• Keeps the buoy aligned on a N-S axis = more
efficient use of PV panels, less yaw compensation
• Switch to Li-Ion batteries:
• Increased capacity by 70%
• No changes to core measurement system (LiDAR,
software algorithm & gimbal mechanical compensation)
V0.9
V1.0
MRP-NNG campaign & FLiDAR technology Overview
Design Improvements V1.1
5
• Symmetrical design
• Upgraded energy system
• Increased PV production by 70%
• Added 1 extra WTG
• Possible to install Fuel Cell
• Increased redundancy and reliability
on sensor and PC loggers
• Upgraded satellite and GPRS
systems
MRP-NNG campaign & FLiDAR technology Overview
FLiDAR construction
6
Month 1 2 3 4 5
Buoy structure construction
Electrical systems installation
Communication system installation
Sensor configuration and commissioning
Factory Acceptance Test (FAT)
Phase 1: Validation Results
7
Pre-Validation System & Data Availability
8
• Data availability (Light Green)
unaffected up to met mast top
(103m), >85% at 200m
• Easily exceeds roadmap acceptance
Roadmap Acceptance Criteria
Availability Type Monthly Overall
System Availability ≥ 90% ≥ 95%
Data Availability ≥ 80% ≥ 85%
Campaign phase 1: Pre-Validation
Accuracy – 103m Wind Speed & Direction
9
Roadmap Guidance Actual
Results Key Performance Indicator Best Practice Minimum
Mean Wind Speed - Slope X
4 to 16 m/s0.98 – 1.02 0.97 – 1.03 1.008
Mean Speed – Coefficient R2
4 to 16 m/s>0.98 >0.97 0.992
Wind Direction – Coefficient R2 >0.97 >0.95 0.999
Campaign phase 1: Pre-Validation
Accuracy – Wind Speed & direction
10
Phase 1 results (3 months) DNV validation report
Pre-Validation Metocean Conditions Experienced
11
• Waves (Hs) up to 4.2m Wave Period 2 -9 seconds
• Tidal range +/-3m
• Wave steepness up to 0.08
• Low current flow up to 0.8 m/s
• Dominant Wave Direction Parallel to coast line - long fetch waves
• Wide range of wave climates typical of North Sea Conditions
• No Discernable Trends for Wind speed or TI Error vs wave period, steepness, Hs
Phase 3 results (1 month) DNV validation report
Campaign phase 3: Post-Validation
12
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
MRP-NNG Post Validation Campaign
Data Quality System Availability
Phase 3 Availability
Availability Type Monthly
System Availability 99.3%
Data Availability 94.5%
• High Availability for the 1 month
Q & A (3 mins)
13
[email protected] | www.flidar.com | April 2015
Thank you!