SBQ 3314 BUILDING MEASUREMENT III
DR. SARAJUL FIKRI MOHAMEDDEPARTMENT OF QUANTITY SURVEYING
FACULTY OF BUILT ENVIRONMENT
UNIVERSITI TEKNOLOGI MALAYSIA
FIRE FIGHTINGINSTALLATION
-
8/2/2019 Fire Fighting Note
2/125
Fire Fighting InstallationSystemMeasurement Rules
SECTION Q
PLUMBING AND MECHANICALENGINEERING INSTALLATIONS
-
8/2/2019 Fire Fighting Note
3/125
Measurement Rules
Section Q
Q.1 Information
Q.2 Clasification Of Work
Q.3 Location of works
Pipeworks
Q.7 Generally
Q.8 Pipe and Fittings
Q.9 Special Connection, etc
Q.10 Labour
Q.11 Sundries
Q.12 Pipework Support
Q.13 Connection
Equipment and Ancillaries
Q.19 Generally
Q.20 Antivibration and sound insulation
Q.21. Equipment support
Q.22. Jointing
Q.24. Identification plates
Builders Work
Q.31 Generally
Q.32. Particularly
-
8/2/2019 Fire Fighting Note
4/125
FIRE FIGHTING SYSTEMCOMPONENTS
1. Builders Work
2. Hose Reel System Swing hose- reel, Water storage tank, Electrical duty pump, Diesel
duty pump, Piping: incoming pipe -rising pipe, distribution pipe
3. Fire Alarm panel Manual Break Glass, Fire Alarm Bell, Batteries, Batery Charger
4. Brasswork Air release valve, Gate valve, Check valve, Strainer valve, Flexible
joint
5. Portable Fire Extinguisher6. Equipment and Ancillaries Concrete plinth7. Pipe Support Pipe hanger8. Sundries
Testing
-
8/2/2019 Fire Fighting Note
5/125
R.2 Clasification of Work
D.Fire Fighting Installation
Fire Fighting Installation
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
6/125
FIRE FIGHTING INSTALLATION
Standpipe Sprinkler Portable
DryStandpipe
WetStandpipe
Hose Reel
Wet PipeSystem
Dry PipeSystem
Pre-actionSystem
DelugeSystem
- Water tank
- Pump
- Pipes
- Sprinkler
- Alarm
- Water tank
- Pump
- Pipes
- Sprinkler
- Fire Detector
- Alarm
-
8/2/2019 Fire Fighting Note
7/125
GENERALLYQ.1 INFORMATION
FIRE FIGHTING INSTALLATION
GenerallyQ.1. Information1 Particulars of the following shall be given :
a) Regulation, etc.
b) Kind and quality of material.c) Gauge, thickness or substance of material.d) Any tests, etc.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
8/125
THE FIRE PROTECTION SYSTEM INSTALLED ARE INFULL COMPLIANCE AND REGULATIONS
1. The British Standards Institution 750 For Fire Hydrant
2. The British Standards Institution 5839 Part 1, 1980For Fire Alarm System
3. The Requirements Of The Chief Inspectorate Of The
Fire Services Malaysia.
-
8/2/2019 Fire Fighting Note
9/125
Q.1.2 Assembling and jointing together the componentparts of composite units and providing anynecessary connecting flanges and jointing
materials shall be deemed to be included withthe items concerned. Where composite units aresupplied by the Employer, particulars shall begiven of the assembly work involved.
Q.1.3 Patterns, moulds, templets and the like shall bedeemed to be included with the items.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
10/125
Q.1.4 Priming and painting off-site and proprietaryfinishes or surface treatment applied as part ofthe production process shall be describedstating whether applied before or after
fabrication or assembly.
Q.1.5 Except where otherwise stated the method offixing and the provision of nails, bolts, nuts,
holes, screws, plugs, shot-fired pins and the likeshall be given in the description of the work.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
11/125
FIRE FIGHTING INSTALLATIONS
-
8/2/2019 Fire Fighting Note
12/125
Q.1.6 The nature of the background to which work is tobe fixed shall be given in the description. Anynecessary drilling of the backgrounds shall bedeemed to be included. Backgrounds shall beclassified as follows :
a) Building-board which shall be deemed toinclude hardboard, compressed cement sheet,plasterboard, fibreboard and similar materialswhich do not grip woodscrews.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
13/125
Q.1.6 The nature of the background.
b) Timber which shall be deemed to includesoftwood, hardwood, blockboard, plywood and
similar materials which will grip wood-screws whena lead-hole has been drilled.
c) brickwork, concrete or stone work
d) plain metal
e) glass
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
14/125
Q.1.7. Temporary work shall be so described.Removing temporary work and making goodafter shall be deemed to be included with the
item.
1.8. Connecting to existing services shall bedescribed
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
15/125
GENERALLY
Q.2. CLASSIFICATION OF WORK
Q.2.1 Work together with its metalwork, supports andthe like (unless associated with more than oneinstallation) shall be classified as follows andgiven under an appropriate heading :
d) Fire Fighting Installation
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
16/125
Q.3. LOCATION OF WORK
Location of works :
a. Internallyb. Externally
c. In plant rooms
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
17/125
PIPE WORKSQ.7 GENERALLY1. Purpose-made pipes and purpose-made pipe
fittings shall be described.2. Pipes and pipe fittings which are wrapped, coatedor lined by the manufacturer shall be so describedstating the type of treatment.
3. Pipework required to be temporarily fixed in
position, dismantled for chromium-plating or otherspecial finishing and subsequently refixed shall beso described.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
18/125
Q.8 PIPE AND FITTING1. Pipes (measured over all pipe fittings, short
running lengths and branches) shall be given inmetres stating the type and the normal size.
Purpose-made pipe shall be so described andgiven separately. Curved pipes shall be sodescribed stating the mean radius.
Joints in the running length shall be given in thedescription stating the method of jointing.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
19/125
-
8/2/2019 Fire Fighting Note
20/125
SETS OF FIRE FIGHTING EQUIPMENT
Hose Reel
Portable FE
-
8/2/2019 Fire Fighting Note
21/125
Q.8 PIPE AND FITTING3. Flexible pipes and extensible pipes (measured as
fully extended) shall each be so described.
4. Pipes laid or fixed in ducts, trenches and chases orembedded in in-situ concrete or screeds shall eachbe so described.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
22/125
Pipe fittingsPIPE FITTINGS
Piping inside
switch room
Heat detector
Hose reel pipe
Conduit
-
8/2/2019 Fire Fighting Note
23/125
Q.9. SPECIAL CONNECTIONS, ETC.1. Special connections and special joints in pipes shall
each be enumerated separately (except wheregiven in the description of another enumerated item)stating the nominal size and kind of pipe concernedand the method of jointing. Classification shall be asfollows :
a) Connections between pipes of differing materialsand differing grades of the same material.
b) Connections between pipes and appliances or
equipment.
c) Connections to existing pipes.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
24/125
Q.10.LABOURS
Labours on pipes (e.g. made bends, made springs,made offsets, beaded ends, ornamental ends, etc.)shall be deemed to be included with the pipes on which
they occur.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
25/125
Q.11 SUNDRIES
6. Pipe-sleeves through walls, floors ceilings shall beenumerated stating the type, lengths, the nominalsize and kind of pipe passing through and the type
of packing required, and if to be supplied for fixingby other trades, this shall be so described.
7. Wall, floor or ceiling plates shall be groupedtogether as plates and enumerated stating the
type and size.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
26/125
PIPE-SLEEVES
-
8/2/2019 Fire Fighting Note
27/125
Q.12 PIPEWORK SUPPORTS
12.1 Standard pipe supports shall be given in thedescription of the pipes stating the type and
spacing of the supports.
12.2. Non-standard pipe supports shall be describedand enumerated (no).
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
28/125
Q.12 PIPEWORK SUPPORTS
4. Components or assemblies of components (e.g.clips, saddles, pipe-hooks, holderbats, brackets,rollers, chairs and hangers or black-plates and
girder-lugs) used to fix supports for more thanone pipe shall be enumerated separately statingthe type and size of components. Springcompensated components shall be so described
stating the loading and movement to beaccommodated.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
29/125
PIPEWORK SUPPORTS
-
8/2/2019 Fire Fighting Note
30/125
PIPE SUPPORT
-
8/2/2019 Fire Fighting Note
31/125
Q.13 CONNECTIONS
Connections to public mains, making good publichighway and any other work which may only be
carried out by a Public Undertaking or LocalAuthority shall be given as a provisional sum.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
32/125
EQUIPMENT AND ANCILLARIESQ.19 Generally
1. Unless otherwise stated, equipment such as boilers,generators, heaters, water treatment plant, tankscylinders, calorifiers, pumps, coolers, air-handlingunit, fans, refrigerator equipment, meters, sanitaryfittings, etc. and ancillaries such as soot doors toboilers, valves and cocks, gauges, automaticcontrols etc. shall be enumerated and related to thespecification referred to in clause Q.1.1.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
33/125
EQUIPMENT AND ANCILLLARIESQ.19 Generally
2. Shall be described in conjunction with amanufacturers detailed specification (Q.19.2)
3. Any limiting dimensions on the size shall begiven. (Q.19.3)
4. Electrical connection shall be given in
accordance with section R . (Q.19.4)
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
34/125
DIESEL PUMP
Pengganti apabila pam operasi elektrik tidak dapat berfungsi. Stanby pump. 135 main flow, 40 m tekanan dan 2900 rpm Equipments and ancillaries, Q.19.kecuali dinyatakan peralatan
seperti tangki, silinder pam serta injap dan pili perlu di nyatakan.
Unit NO
-
8/2/2019 Fire Fighting Note
35/125
Carbon dioxide fire extinguishing systems are usedbecause of the most efficient extinguishing agents
It is situated at the switch room
It removes the oxygen and covers the surroundingatmosphere and literally strangles the fires to death.
Advantages:
a) odorless and non-toxic
b) dry, inert gas, it will not conduct electricityc) cannot damage clothes or equipment nor
contaminate liquids or food
CO2 Fire Extinguishing Systems
-
8/2/2019 Fire Fighting Note
36/125
HOSE REEL SYSTEM:
WET PIPE
-
8/2/2019 Fire Fighting Note
37/125
HOSE REEL SYSTEM
Pressurised using 1 unit of electrical pumpset as duty pump& 1 unit diesel engine pumpset as standby
Designed to operate an automatic mode (Pressure switch)& manual mode (manual starting from the pumpsets control
panel)
Standard coil length 30m, 36m or 100m.
Specification :-Working Pressure : 220Psi (15 Bar)
Minimum Burst Pressure : 696Psi (48 Bar)Test Pressure : 250Psi
-
8/2/2019 Fire Fighting Note
38/125
Nozzles
Hose Guides
Fire Hose
Reel
Pressure
Reducing Valve
Fire Hose
Reel
Hose reel
-
8/2/2019 Fire Fighting Note
39/125
TYPICAL HOSE REEL
WET RISER
-
8/2/2019 Fire Fighting Note
40/125
WET RISERIs constantly filled with water and thesupply should be capable ofmaintaining a running pressure of410kPa at the highest landing valve
and give a flow rate of 23litres persecond. The maximum runningpressure permitted with one outletopen should be 510kPa.
To maintain the required water
pressure it is usually necessary toinstall pumping equipment. Directpumping from the main is notpermitted and a suction tank with aminimum actual volume of water of45.5 m2 must be installed.
-
8/2/2019 Fire Fighting Note
41/125
COMPONENTS
Hose reelPiping
Brasswork
Pump:
Duty pump
Standby pump
Water Tank
-
8/2/2019 Fire Fighting Note
42/125
WATER STORAGE TANK
Equipments and ancillaries
Clause Q.19.
Unless otherwise stated, equipment such as tankshall be enumerated (no).
-
8/2/2019 Fire Fighting Note
43/125
-
8/2/2019 Fire Fighting Note
44/125
HOSE REEL
Hose reel wall
mounted
-
8/2/2019 Fire Fighting Note
45/125
VALVE
BIBHorizontal
-
8/2/2019 Fire Fighting Note
46/125
HOSE
General purpose syntheticdelivery hose. Suitable forindustrial and rural firebrigades as well as staticbuilding protection.
General industrial, commercialand civil engineeringapplications including waterauthorities where a high burstperformance hose is not
necessary
Lightweight and flexibleHeat and cold resistantAnti rot and anti-twist
-
8/2/2019 Fire Fighting Note
47/125
BRANCH PIPE AND NOZZLE
Branch pipes provide an adjustablenozzle to allow the curtain of water tobe altered from a narrow spray to awide spray.
Nozzles provide a fixed jet of water.The basic branch pipe according toBS336 has an 21/2" inlet maleinstantaneous and outlet threaded11/3" BSP male for either a plain jetor a branchpipe adjustable nozzle.
The branch pipe is controlled fromSHUT-OFF through JET and SPRAYto wide angle CURTAIN by rotatingthe annular sleeve.
-
8/2/2019 Fire Fighting Note
48/125
HOSE REEL SYSTEM:
DRY PIPE
-
8/2/2019 Fire Fighting Note
49/125
System for dry riser
This range includes:
inlet breechings inlet and outlet
cabinets outlet valves
standpipes, bars andkeys.
-
8/2/2019 Fire Fighting Note
50/125
DRY RISER COMPONENT
DRY RISER
Designed to house inletbreechings and landing
valves Georgian wired glass panel
and spring cylinder lock withkey
Manufactured from zintec,
epoxy polyester powdercoated - Red
-
8/2/2019 Fire Fighting Note
51/125
FIRE EXTINGUSHER
-
8/2/2019 Fire Fighting Note
52/125
FIRE EXTINGUSHER
-
8/2/2019 Fire Fighting Note
53/125
Type of Fire
Extinguisher
Dry powderWater
Gas
Carbon
dioxide
(CO2)
Foam
Portable Fire Extinguisher
-
8/2/2019 Fire Fighting Note
54/125
PORTABLE FIRE EXTINGUISHER
1. Dry powder-No2. Testing-item.
CARBON DIOXIDE SYSTEM
1. CO2 cylinder-No
2. Testing-item.
Portable Fire Extinguisher
-
8/2/2019 Fire Fighting Note
55/125
POWDER EXTINGUISHERS
http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/ -
8/2/2019 Fire Fighting Note
56/125
WATER EXTINGUISHERS
http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/ -
8/2/2019 Fire Fighting Note
57/125
Foam extinguishers
http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/http://www.fire-protection-services.co.uk/products/ -
8/2/2019 Fire Fighting Note
58/125
Portable Fire Extinguisher.
Alat pemadammudahalih (Portable FireExtinguisher) digunakanmelindungi bangunan
dari bahaya kebakarankecil.
-
8/2/2019 Fire Fighting Note
59/125
Carbon
Dioxide fire
extinguisher
Portable foam &
water Extinguisher
Portable Dry
Chemical Powder
Fire Extinguisher
-
8/2/2019 Fire Fighting Note
60/125
ALARM SYSTEM
-
8/2/2019 Fire Fighting Note
61/125
-
8/2/2019 Fire Fighting Note
62/125
MANUAL ALARM
COMPONENTS
Fire alarm panel
Manual break glass
Alarm bell
-
8/2/2019 Fire Fighting Note
63/125
MANUAL BREAK GLASS
SMOKE DETECTOR
-
8/2/2019 Fire Fighting Note
64/125
SMOKE DETECTOR
-
8/2/2019 Fire Fighting Note
65/125
SMOKE DETECTOR
SMOKE DETECTOR
Fire alarm system isfunctioning as a
components which givewarning sign to occupants ina building if it is burning.
It normally, installed withdetector.
There is 2 type of detector,passive (Manual breakglass) and active (Smokedetector, heat detector, lightdetector).
-
8/2/2019 Fire Fighting Note
66/125
LIGHT FITINGSLIGHT FITTINGS
Keluar Sign
Flashing lights
Emergency light
SPRINKLER SYSTEM
-
8/2/2019 Fire Fighting Note
67/125
SPRINKLER SYSTEM
Sprinkler system adalah sebuah sistem gabungan antara paip-paipyang dipasang di dalam bangunan dan sprinkler (overhead piping) bagimembolehkan ianya digunakan sebagai alat pemadam api.
Alat-alat di dalam sistem :
Tangki Air (gravity Tank).Fire Pump.
Tangki Simpanan (Reservoir/Pressure Tank).
Penyambungan kepada Bekalan Utama (Connection to Main/CityService).
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
68/125
EQUIPMENT AND ANCILLLARIES
Q.20 Anti-vibration and sound insulation
Anti-vibration mountings for plant shall be enumeratedstating the type and the size. Anti-vibration materialand sound-insulating material in plant bases shall begiven in square metres stating the nature of thematerial and the thickness.
MEASUREMENT RULES
ANTI VIBRATION
-
8/2/2019 Fire Fighting Note
69/125
ANTI VIBRATION
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
70/125
EQUIPMENT AND ANCILLLARIES
Q.21 Equipment supports
1. Equipment supports shall be enumerated and
described.2. Particulars of the method of fixing shall be given in
the description in accordance with clauses Q.1.5-6.
MEASUREMENT RULES
FIRE HYDRANT
-
8/2/2019 Fire Fighting Note
71/125
FIRE HYDRANT
& HOSE REEL
PORTABLE FIRE
EXTINGUISHER
(DRY POWDER)
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
72/125
EQUIPMENT AND ANCILLLARIES
Q.22 Jointing
Particulars of the method of jointing shall be given inthe description of the equipment.
MEASUREMENT RULES
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
73/125
EQUIPMENT AND ANCILLLARIES
Q.24 Identification Plates
Identification plates shall be deemed to be included.
MEASUREMENT RULES
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
74/125
SUNDRIES
Q.30 Generally
1. Draining and refilling existing system shall be given
as a provisional or prime cost sum.
2. Disconnecting, setting aside and refixing equipmentfor the convenience of other trades shall be given
as an item stating the relevant particulars.
MEASUREMENT RULES
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
75/125
SUNDRIESQ.30 Generally
3. Temporarily operating each installation (except fortesting) shall be given as an item stating any
required qualifications of the attendant, the durationof the operating period in hours and the purposeand particulars of any special insurance coverrequired by the Employer. Provision of solid fuel,
liquid fuel, gas and electricity for power and lightingshall be deemed to be included with the item
MEASUREMENT RULES
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
76/125
SUNDRIESQ.30 Generally4. Testing each installation shall be given as an itemstating any
required qualifications of the attendant, the number of stagetests in addition to the final, the purpose of the tests, theinstruments and appliances required to be provided andparticulars of any special insurance cover required by theEmployer. Provision of solid fuel, liquid fuel, gas and electricityfor power and lighting shall be deemed to be included with theitem.
5. Preparing plans or diagrams of the installations as fitted shallbe given as an item stating the kind of information required tobe shown and the number of copies of each drawing requiredto be provided.
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
77/125
SCHEMATIC DRAWING
1.Heat Detector
2.Smoke Detector
3.Extinguishing Nozzles
4.Fire Curtain (for Louver Door /Opening)
5. CO2 Cylinder c/w Accessories
6. Alarm Bell
7. Key Switch
8. Double Inter-lock ControlPanel c/w Back
9. Normal / Discharge Light
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
78/125
BUILDERS WORKQ.31 GENERALLY
1. Unless otherwise stated, all items of builders shall
be given in accordance with the appropriatesection.
2. Builders works in connection with plumbing andmechanical engineering installations shall be
grouped together under an appropriate heading.
MEASUREMENT RULES
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
79/125
BUILDERS WORKQ.32 PARTICULARLY
1. Excavating trenches for pipes not exceeding 55mmnominal size shall be given in accordance with
clause D.12.9
2. For pipe over 55mm shall be given in accordancewith clause V.2
3. Cutting away for making good after M&E works
MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
80/125
SUMMARY OF SMM
SUMMARY OF MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
81/125
CLAUSE ELEMENT METHOD UNIT
Q.1.1 All element Shall be given in regulations, kind and qualityof material, gauge, thickness or substance ofmaterial with any tests.
Q.1.2 Assembling and
jointing
Connecting flanges and jointing shall include
with the items.
Q.1.3 Patterns, moulds,templets Shall be include with the items.
Q.1.4 Priming andpainting
Described the work whether applied before orafter fabrication or assembly.
Q.1.5 Nails, bolts, nuts,holes, screws,plugs, shot-firedpins
In the description of work, stated the method offixing.
SUMMARY OF MEASUREMENT RULES
SUMMARY OF MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
82/125
Q.1.6
(a-f)
a) building board
b) timberc) metal-faced or
composition-faced timber
d) brickwork,concrete orstonework
e) plain metalf) glass
Shall stated the method of fixing and includingthe necessary drilling of the backgrounds andbe given in the description.
Q.1.7 Temporary work Shall be include with the items ( removingtemporary work and making good )
Q.1.8 Connections Shall be given in the description the nature of
work, turning off supplies of any restrictionwhen breaking into existing pipes.
Q.2.1 d) fire fightinginstallation
Given under an appropriate heading with itsmetalwork and supports.
SUMMARY OF MEASUREMENT RULES
SUMMARY OF MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
83/125
Q.3.1 All element The location for the work that must be
identified :i) internallyii) externallyiii) in plant rooms
Q.8.1 Pipes Measured all over the pipe fittings, shortrunning lengths and branches stating the type
and nominal size. Separate it if it is purpose-made pipe. Curved pipe stating the radius.Joints shall be given in the description statingthe method of jointing.
M
Q.8.2 Joints of a specialcharacters and extrademountablecouplers
Shall be described as extra over Nos.
Q.8.3 Flexible pipes andextensible pipes
Measured as fully extended and shall each beso described.
Q.8.4 Pipes laid or fixed inducts, trenches andchases
Shall be described.
SUMMARY OF MEASUREMENT RULES
SUMMARY OF MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
84/125
Q.8.5 Flow and return
header pipe
All measurement stating the length, type and
nominal size of the main pipe and branch pipeand also method of construction and jointingthe ends.
Nos.
Q.8.6 Pipe fittings andpurpose made pipefittings
All details, cutting and jointing shall bedescribed.
Nos.
Q.8.7 Expansion loops All measurement stating the limiting dimensionsand the amount of expansions to beaccommodated.
Nos.
Q.8.8 Expansioncompensators
All measurement stating the type of joint andthe amount of expansions to beaccommodated.
Nos.
Q.8.9 Flanges and unions Necessary solely for erection purposes shallincluded.
Q.8.10 Jointing All jointing shall be deemed included with theitems.
Q.8.11 Fittings and jointing All measurements stating he size and kind ofpipe flanged concerned perforating
Nos.
SUMMARY OF MEASUREMENT RULES
SUMMARY OF MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
85/125
Q.9.1 Special connections
Special joints in pipesMeasured separately stating nominal size,
kind of pipe, method of jointing and must
be classifya) Connections between pipes of different
materials and difference grades and of thesame material.
b) Connections between pipes andappliances or equipment.
c) Connections to existing pipes.
Q.9.2 Isolated joints As extra over stating the type of jointing
Q.10 Made bends, madesprings, made offsets,beaded ends,ornamental ends, etc.
Shall included with the pipes on which theyoccur.
Q.12.1 Standard pipesupports
Shall described on the description of the pipesstating the type and spacing.
Q. 12.2 Non-standard pipesupports
Shall be described. Nos.
Q.12.3 Supports that arelined to insulate pipes
Shall described stating the type of liningmaterial.
SUMMARY OF MEASUREMENT RULES
SUMMARY OF MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
86/125
Q.12.4 Clips, saddles, pipe-
hooks, holderbats,brackets, rollers,chairs, hangers/blackplates,Gender-laps
Enumerated separately stating the type and size Nos.
Q.12.5 Pipe anchor Enumerated separately stating nominal size of
pipe, type and size of components, method offixing of the pipe and nature of work.
Nos.
Q.13 Connection Work which may only carried out by PublicUndertaking or Local Authority.
P.S
SUMMARY OF MEASUREMENT RULES
SUMMARY OF MEASUREMENT RULES
-
8/2/2019 Fire Fighting Note
87/125
Q.15.1 Special connections,special joints
Enumerated separately stating the size, kindof ducting and also method of jointing ,
classify ;a) Connections between ducting of differing
materials.b) Connections between ducting and
equipment stating the nature of theequipment.
c) Isolated joints which differ from those
given in the description of the ducting.d) Flexible connections between ducting and
plant.
Nos.
Q.15.2 Ducting turn andsplitters
Enumerated separately stating type andmaterial size of ducting
Nos.
Q.15.3 Nozzle outlets, testholes and coresaccess doors
Shall described stating size, method of jointingand material and thickness or gauge
Nos.
Q.15.4 Cowls, terminals,intake louvers
Stating size and type, size of ducting andmethod of jointing.
Nos.
SUMMARY OF MEASUREMENT RULES
Taking off list
-
8/2/2019 Fire Fighting Note
88/125
g_______________________________________________________________________________________________________________________
1.Hose Reel System
Swing hose reelWater tank
Electrical duty pump
Diesel standby pump
Alarm bell
3.Brass Work
Ball float valveStrainer valve
Stop valve
Flexible connection
Check valve
Gate valvePressure gauge
2.Pipe Work
Incoming pipe
Distribution pipe
Rising pipe
Painting to pipe
4.Connection To Public Main
5.Builders work
6.Testing
Taking off List
-
8/2/2019 Fire Fighting Note
89/125
Taking off List_______________________________________________________________________________________________________________________
No. ITEM CLAUSE UNIT
1. Hose Reel System
Swing hose reel
Water tank
Electrical duty pumpDiesel standby pump
Alarm bell
Q.19.1 Nos.
Taking off List
-
8/2/2019 Fire Fighting Note
90/125
Taking off List_______________________________________________________________________________________________________________________
No. ITEM CLAUSE UNIT
2. Pipe Work
Incoming pipe
Distribution pipe
Rising pipePainting to pipes
Pipe fittings
Q.7, Q.8.1
Q.8.6
M
Item
Nos.
Taking off List
-
8/2/2019 Fire Fighting Note
91/125
g_______________________________________________________________________________________________________________________
No. ITEM CLAUSE UNIT
3. Brass Work
Ball float valve
Strainer valve
Stop valve
Flexible connectionCheck valve
Gate valve
Pressure gauge
Q.19.1 Nos.
ki ff i
-
8/2/2019 Fire Fighting Note
92/125
Taking off List_______________________________________________________________________________________________________________________
No. ITEM CLAUSE UNIT
4.
5.
6.
Connection to public
main
Builders work
Testing
Q.13
Q.31, Q.32.1
Q.30.4
Provisional
Sum
Item
-
8/2/2019 Fire Fighting Note
93/125
TAKING OFF
LIST
1 Hose reel No
-
8/2/2019 Fire Fighting Note
94/125
1. Hose reel. -No2. Water storage tank. -No3. Electrical duty pump. -No4. Diesel standby pump -No5. Incoming pipe. -M6. Main distribution pipe .-M7. Rising main pipe. -M8. Distribution pipe. -M9. Suction pipe. -M
10.Drain pipe.- M11.Ball float valve. -No12.Strainer valve. -No13.Stop valve. -No14.Flexible connection. -No15.Check valve. -No
16.Pressure gauge. -No17.Pressure switch. -No18.Automatic air release valve. -No19.Cables. -M20.Testing -item
-
8/2/2019 Fire Fighting Note
95/125
1. Main fire alarm console panel. -No2. Manual break glass. -No3. Fire Alarm Bell. -No4. Heat detector. -No
5. Smoke detector. -No6. Cables. -No7. Testing -item.
TAKING-OFF LIST1 P bl
-
8/2/2019 Fire Fighting Note
96/125
1. Preambles
2. Builders work
i.Exc.trench to receive hydrant pipe M
ii.Exc.trench to receive incoming pipe M
3. Pipework
i.For pillar hydrant
- 150mm dia. MSCL pipe laid in trench M
ii.For incoming pipe
- 150mm dia. MSCL pipe laid in trench M
- 150mm dia. MSCL pipe laid on slab M
- 150mm dia. MSCL pipe fixed to wall M
iii.For pump house
- 200mm dia. MSCL pipe laid on slab M- 50mm dia. MSCL pipe laid on slab M
- 200mm dia. MSCL pipe fixed to wall M
- 50mm dia. MSCL pipe fixed to wall M
- 150mm dia. MSCL pipe fixed to wall M
TAKING-OFF LIST (Contd)
-
8/2/2019 Fire Fighting Note
97/125
3. Pipework (contd)
iv.For hosereel
- 50mm dia. G.I pipe fixed to wall M
- 25mm dia. G.I pipe fixed to wall M
v.For sprinkler
- 150mm dia. G.I pipe fixed to ceiling M
- 100mm dia. G.I pipe fixed to ceiling M
- 80mm dia. G.I pipe fixed to ceiling M- 65mm dia. G.I pipe fixed to ceiling M
- 50mm dia. G.I pipe fixed to ceiling M
- 45mm dia. G.I pipe fixed to ceiling M
- 32mm dia. G.I pipe fixed to ceiling M
- 25mm dia. G.I pipe fixed to ceiling M- 150mm dia. G.I pipe fixed to wall M
- 25mm dia G.I drain pipe fixed to wall M
vi.Brasswork
- Gate valve NO
- Alarm valve NO
TAKING-OFF LIST (Contd)
Pipework (contd)
-
8/2/2019 Fire Fighting Note
98/125
Pipework (cont d)
vii.Breeching inlet NO
4. Pillar Hydrant NO5. Hose Reel System
i.Swing hose reel NO
ii.Electrical duty pump NO
iii.Diesel standby pump NO
6. Sprinkler System
i.Sprinkler head NOii.Sprinkler tank NO
iii.Electrical duty pump NO
iv.Electrical jockey pump NO
v.Diesel standby pump NO
7. Conduitsi. 2 x 2.5mm2 PVC cable in metal conduit M
ii. 2 x 1.5mm2 PVC cable in metal conduit M
8. Cable
i. 2 x 2.5mm2 PVC cable in metal conduit M
ii. 2 x 1.5mm2 PVC cable in metal conduit M
TAKING-OFF LIST (Contd)
-
8/2/2019 Fire Fighting Note
99/125
9. Fire Alarm System
i.Control gear NOii.Junction box NO
iii.Manual break glass NO
iv.Fire alarm bell NO
v.Heat detector NO
vi.Smoke detector NO
10. Portable Fire Extinguisher
i.Dry powder extinguisher NO
ii.CO2 extinguisher NO
11. Testing ITEM
FIRE FIGHTING SYSTEMTAKING OFF LIST UNTUK HOSE REEL SYSTEM.
-
8/2/2019 Fire Fighting Note
100/125
1. Builders Work
a) Excavation M
2. Hose Reel System
a) Swing hose- reel No
b) Water storage tank No
c) Electrical duty pump No
d) Diesel duty pump No e) Piping: incoming pipe M
rising pipe M
distribution pipe M
3. Fire Alarm Panel
Manual Break Glass NO Fire Alarm Bell NO
Batteries NO
Batery Charger NO
FIRE FIGHTING SYSTEMTAKING OFF LIST UNTUK HOSE REEL SYSTEM.
-
8/2/2019 Fire Fighting Note
101/125
4. Brasswork Air release valve No Gate valve No Check valve No Strainer valve No Flexible joint No5. Equipment and Ancillaries Concrete plinth M26. Pipe Support Pipe hanger NO7. Sundries Testing Item
-
8/2/2019 Fire Fighting Note
102/125
Fire fightingInstallation system
Bill of Quantities
ITEM DESCRIPTION UNIT QTY RATE RM CENT
FIRE FIGHTING INSTALLATION, TESTING,
-
8/2/2019 Fire Fighting Note
103/125
COMMISSIONING AND MAINTENANCE OF
FIRE FIGHTING SYSTEM.
HOSE REEL SYSTEM
Swing hose-reel complete with 25mm diameter x
30mm long hose,12.5mm diameter nozzles, fixing,
bracket, reducer, gate valve and other accessories as
described.
Hot-dipped galvanized pressed steel water storage
tank of approved type, manufactured to BS 1564,
3.66m x 2.44m x 1.22m height with 2400 gallons
capacity, complete with float valve, level indicator,
ladder, overflow pipe and drain pipe, at approximately
1000mm high above ground level.
Electrical duty pump, 30 igpm, 150 ft. head.
Diesel standby pump, 32 igpm, 160 ft. head.
TESTINGAllow for testing the foregoing fire fighting system,
make good any defects and leave the whole of the
installation in perfect working order to the
satisfaction of the S.O and Local Authority.
No.
No.
No.
No.
Item
20
1
1
1
Preambles
-
8/2/2019 Fire Fighting Note
104/125
The drawing where the drawing no.
FNP/BL/0205/F01-04 shows the layout of the fire
fighting system.All quantities are all provisional
subject to remeasurement upon combination
construction of the said item.
The fire fighting system to be excuted by the
contractor in accordance to Jabatan Bomba
Malaysia requirement and approval.
All wiring to brickwall and soffit of ceiling shall
be concealed unless otherwise stated and all
wiring above ceiling space of roof level shall be in
galvanised iron conduit and coloured by red.
The item of this bill not fully described and the
rates shall be held to include for all short running,
bend,tees,joints,valve,reducer,backnuts and the
like.The contractor must allow for testing fire
fighting system and handling over the test
certificate to the architect.
The contractor shall be provide for obtaining all
necessary plan.
-
8/2/2019 Fire Fighting Note
105/125
ITEM DESCRIPTION UNI
T
QTY RATE RM CENT
FIRE FIGHTING INSTALLATION, TESTING,
COMMISSIONING AND MAINTENANCE OF
FIRE FIGHTING SYSTEM.
HOSE REEL SYSTEM
Swing hose-reel complete with 25mm diameter x
30mm long hose,12.5mm diameter nozzles, fixing,
bracket, reducer, gate valve and other accessories as
described.
Hot-dipped galvanized pressed steel water storagetank of approved type, manufactured to BS 1564,
3.66m x 2.44m x 1.22m height with 2400 gallons
capacity, complete with float valve, level indicator,
ladder, overflow pipe and drain pipe, at
approximately 1000mm high above ground level.
Electrical duty pump, 30 igpm, 150 ft. head.
Diesel standby pump, 32 igpm, 160 ft. head.
TESTING
Allow for testing the foregoing fire fighting system,
make good any defects and leave the whole of the
installation in perfect working order to the
satisfaction of the S.O and Local Authority.
No.
No.
No.
No.
Item
20
1
1
1
APARTMENT J.B
Description QTY Unit Rate RM SENELEMENT FIRE FIGHTING INSTALLATION
Fire-Fighting in connecting (internally)
Fire Alarm system
A Manual Break glass fire alarm with 24 volts 6 NO
D C supply mounted at wall as described
-
8/2/2019 Fire Fighting Note
106/125
D.C supply, mounted at wall as described
B 150 mm Diameter fire alarm bell with 24 6 NO
volts D.C supply, mounted as described
Fire Fighting Equipment
Lighting Installation (internally)
C KELUAR' Sign complete with nickel 8 NO
Cadmium batteries, tuber, etc and
accessories with approved 13 W
non-contained fluorescent
D Self contained Emergency Light fitting 8 NO
complete with nickel cadmium battery and
outomatic charger unit similar econ lite
Hose Reel system
E Hot Dipped Galvanised Pessed Steel Water 1 NO
Storage Tank of approved type,
manufactured to BS 1564, 3m x 2m x 2m
height with 2640 Gallons capacity,
complete with 50 diameter overflow
pipe,suction pipe, drain pipe incoming pipe
at approximately 100 mm above ground
level
F 1" Diameter Swing Type Hydraulic hose reel 6 NO
drums each c/w diameter x 100 ft. non.
Kink double braided tubing and 1" diameter
3 jet spray nozzle
G Electrical Duty Pump, 30 IGPM, 120 ft head 1 NO
H Diesel Standby Pump, ditto 1 NO
Galvanised Iron class 'B' Tubing to comply
with BS 1387, screw socket together
K 50 mm Diameter incoming pipe, at High 2.00 M
level free standing
L 50 mm Diameter overflow pipe,ditto 4 M
APARTMENT J.B
Description QTY Unit Rate RM SEN
Galvanised Iron class 'B' Tubing to comply
with BS 1387, screw socket together
A 50 mm Diameter suction pipe at low level 1 M
-
8/2/2019 Fire Fighting Note
107/125
A 50 mm Diameter suction pipe at low level, 1 M
free standing
B 25 mm Diameter riser pipe fixed to brickwall 3 M
C 50 mm Diameter drain pipe at low level and 2 M
jointing to Galvanised iron pipe
Brasswork To Comply With BS 1010 as described :-
D 50 mm Diameter flexible connection and 2 NO
jointing to galvanised iron pipe
E 50 mm Diameter Check valve, ditto 2 NO
F 50 mm Diameter stop valve, ditto 2 NO
G 50mm Diameter Ball float valve, ditto 2 NO
H 50mm Diameter gate valve, ditto 2 NO
J 50mm Diameter outomatic air release valve, 2 NO
ditto
K 50mm Diameter pressure gauge, ditto 1 NO
L 50mm Diameter stairer valve, ditto 2 NO
BUILDER'S WORK
M Wire brush and painting primer, undercoat Item
and two coat gloss oil to surface of
galvanised iron pipe
N Installation inclusive of hacking, punching of Item
holes in wall and floors, coring of holes
through reinforce concrete slab and making
good
Testing
O Allow for testing foregoing fire fighting Item
system, make good and any defects and
leave the whole of the installation in perfect
working order to the satisfaction of the S.O
and Local Authority
-
8/2/2019 Fire Fighting Note
108/125
PROJEK
Cadangan Merekabentuk, Membina &
Menyiapkan SMK Kenangan, Segamat, Johor,Di atas Lot 5848, 2259 Sebahagian Lot 5848
dan Sebahagian Lot 2258.
PEJABAT LLM WILAYAH TIMUR BERSERTA KEM DI INTERCHANGE KUANTAN.
ITEM UNIT QTY RATE RM
ELEMENT : FIRE FIGHTING INSTALLATION
(INTERNALLY)
DESCRIPTION
-
8/2/2019 Fire Fighting Note
109/125
(INTERNALLY)
PREAMBLE ( All Provisional )
A The fire fighting installation is to be executed by contrator
in accordance with Jabatan Bomba requirement and approval.
Where items in this bill are not fully describes the rates shall
be held to include for all piping, control gear and etc all as
described or as required by Jabatan Bomba as being
appropriate for installation. The rates be held to include for all
short running lengths, bends, tees and etc. The contractor
must allow for testing the fire fighting installation and handling
over the test certifiate to the Architect. (Q.1) Item
HOSE-REEL SYSTEM
B Hydraulic hose-reel complete with 36 mm x 25 mm diameter
long hose, 12.5 mm diameter nozzles, fixing, bracket,
reducer, gate valve and other accessories as described.
(Q.19) No 1
C Electrical duty pump with 30 IGPM at 135 feet head. (Q.19) No 1
D Diesel standby pump with 130 IGPM at 135 feet head (Q.19) No 1
Galvanised Iron Class 'B' Tubing to Comply With BS 1387
Screw Socketed Together Including All Necessary Short
Length, Fire Bends, Tees, Dimishing Pieces, Plugs and
The Like as Described.
E 50 mm Diameter incoming pipe laid in trench. (Q.8) M 13
F 50 mm Diameter distribution pipe laid in ground slab. (Q.8) M 17
G 50 mm Diameter distribution pipe fixed in ceiling space
horizontally with approved brackets. (Q.8) M 23
H 50 mm Diameter distribution pipe fixed to brickwall vertically
with approved brackets. (Q.8) M 17
J 25 mm Diameter distribution pipe fixed to hidraulic hose-reel.
(Q.8) M 1
K EXTRA OVER 50 mm Diameter elbow. (Q.8.1) No 11
FF / 01
TO COLLECTION
PEJABAT LLM WILAYAH TIMUR BERSERTA KEM DI INTERCHANGE KUANTAN. (CONT'D)
ITEM UNIT QTY RATE RM
ELEMENT : FIRE FIGHTING INSTALLATION
(INTERNALLY)
DESCRIPTION
-
8/2/2019 Fire Fighting Note
110/125
(INTERNALLY)
A EXTRA OVER 50 mm Diameter tee. (Q.8.1) No 1
B EXTRA OVER 25 mm Diameter elbow. (Q.8.1) No 2
C 12 mm Diameter mild steel brackets at 600 mm centres
to centres to support galvanised iron pipe. (Q.12.4) No 68
Brasswork to Comply with BS 1010 as Described.
D 50 mm diameter gate valve and jointing to galvanised iron
pipe. (Q.19) No 6
E Hot-dipped galvanised pressed steel water storage tank
opproved type, manufactured to BS 1564, 12' x 4' x 8' height
with 1000 gallons capacity, complete with float valve, level
indicator, ladder, overflow pipe and drain pipe at ground level.
(Q.19) No 1
Sundries
F Testing and commissioning the hose-reel system asdescribed in the specification. (Q.30.4) Item
PORTABLE FIRE EXTINGUISHER
G 9 kg ABC extinguisher dry powder bomba approved type
manufactured to BS 5306, complete with brackets and
accessories. (Q.19) No 7
Sundries
H Testing and commissioning the portable fire extinguisher
as described in the specification. (Q.30.4) Item
FIRE ALARM SYSTEM
J 150 mm Diameter fire alarm bell with 24 V (D.C) supply
mounted at wall as described. (Q.19) No 2
K Manual break glass fire alarm size 84 mm x 115 mm with
24 V (D.C) supply mounted at wall as described. (Q.19) No 2
PVC Insulated Cable Drawn into Concealed Galvanised
Iron Conduit. (measured separately)
L 2 x 2.5 mm2 cable. (Q.19.4) M 54
TO COLLECTION
FF / 02
PEJABAT LLM WILAYAH TIMUR BERSERTA KEM DI INTERCHANGE KUANTAN. (CONT'D)
ITEM UNIT QTY RATE RM
ELEMENT : FIRE FIGHTING INSTALLATION
(INTERNALLY)
DESCRIPTION
-
8/2/2019 Fire Fighting Note
111/125
(INTERNALLY)
Galvanised Iron Class 'B' Conduit with Screw Joints
Including All Short Running Length, Bends, Tees, Saddles
Crampets, Locknuts, Circular Boxes as Described.
A 50 mm Diameter conduit, chase into brickwall vertically
with approved bracket. (Q.19.4) M 17
B 50 mm Diameter conduit, fixed in ceiling space with
approved bracket. (Q.19.4) M 37
Sundries
C Testing and commissioning the fire alarm system as
described in the specification. (Q.30.4) Item
BUILDER'S WORK
D Excavate trench to receive 50 mm diameter incoming pipe,
maximum depth nearest to 0.25 m including filling in,
compaction and disposal of surplus soil as desribed. (Q.32.1) M 18
E 600 mm thick vibrated reinforced conrete grade 20 as
concrete plinth including all necessary formwork and
reinforcement. (F.3.19) m2
F Allow for testing the foregoing fire fighting installation,
make good any defect and leave the whole of the installation
in perfect working order to the satisfaction of the S.O and
Local Authority.
(Q.30.4) Item
TO SUMMARY
FF / 03
Taking Off list Builders Work
-
8/2/2019 Fire Fighting Note
112/125
u de s o
Excavate trench to receive pipe - M
Hose Reel System
Swing hose reel - NO Water storage tank - NO
Electrical duty pump - NO
Diesel standby pump - NO
Piping
50 mm Diameter incoming pipe - M
50 mm Diameter rising pipe M
50 mm Diameter distribution pipe - M
Brasswork
50 mm Diameter air release valve NO
50 mm Diameter gate valve NO
50 mm Diameter check valve NO
50 mm Diameter strainer valve NO
50 mm Diameter flexible joint NO
25 mm Diameter gate valve NO
Cable
2 x 1.5 mm2 cable
-
8/2/2019 Fire Fighting Note
113/125
2.5 mm2 cable
Fire Alarm System
Control gear NO Junction box NO
Manual break glass NO
2 x 2.5 mm cable M
50 mm Diameter conduit M
Portable Fire Extinguisher 9 kg Fire extinguisher - NO
Hydrant Hose Cabinet NO
Lighting Installation
Keluar sign - NO
5A Emergency light NO Testing
Allow for testing the foregoing fire fighting system - ITEM
-
8/2/2019 Fire Fighting Note
114/125
Taking Off List
-
8/2/2019 Fire Fighting Note
115/125
Taking Off List
1. Pumps. - No
2. Pipeworks. - M
3. Tee - No
4. Bend. - No
5. Valves and ancillaries. - No
6. Hydrant box. - No
7. Pillar. - No
8. Fire Extinguisher. - No
9. Electrical Works. - No
10. Testing. - Item
-
8/2/2019 Fire Fighting Note
116/125
1. Pumps - No
Equipment - Pumps
Electric Fire pump, end suction centrifugal
type with capacity of 750 GPM, 7 bar, 81 Kw/
108.7 Bhp. No 1
1 (PU 202)
-
8/2/2019 Fire Fighting Note
117/125
150mm dia. Black steel pipe, ERW. Sch 40,
embedded in in situ concrete m 130.00
130.00 (Pump Room) Length
75,000
55,000
130,000
2.Pipeworks
-
8/2/2019 Fire Fighting Note
118/125
3. Fitting and Accessories
EXTRA OVER 150x150x65mm Black steel tee. No 5
5 L.Basement
EXTRA OVER Bend 90, to 150mm dia Black No 1
steel pipe
1 L.Basement
Tees
Bend
-
8/2/2019 Fire Fighting Note
119/125
Hydrant
Indoor hydrant box size 800x1300x300mm,
complete with house rack, hydrant valve andfire
house type 40x25m. No 12
3 L.Basement
3
3 L. Dasar
3
3 L. 1
3
3 L. 2
3
12
4.Hydrant
5 Fi e E ting i he
-
8/2/2019 Fire Fighting Note
120/125
Fire extinguisher capacity 3 Kg complete with
box, and all necessary supporting fixing
accessories as specified. No. 52
4 13 L.B - L.2
52
5. Fire Extinguisher
-
8/2/2019 Fire Fighting Note
121/125
Allow for checking, testing, acceptance testing
and commisioning the Fire Protection Installation. Item
Allow for service and maintenance of the complete
installations during 12 months Defects Liability
Period, excluding any maintenance resulting from
defective workmanship or materials requiring repair
and/or replacement by contractor. Item
6. Testing
7. Maintenance
Item Description Unit Rate Qtty RM
Element Fire Fighting Installation
Builder's Work
A
17Excavate trench to receive 150mm diameter
-
8/2/2019 Fire Fighting Note
122/125
m 17
B m 7
Hose Reel System
A no 1
B no 1
C no 1
D no 1
E no 1
To collection
Diesel standy pump with the capacity of 30
igm againts 170 ft static head complete withwiring, pump plinth and other accessories.
One (1) nos of 2400 gallons of hose reel
water tank, 6mm thick press steel panel
complete with ball valve, fittings, level
indicator, float control, piping, external red
paint, internal asnd external ladder and other
accessories.
ca ate t e c to ece e 50 d a ete
incoming pipe, maximum depth not
exceeding 1.0m including filling in,
compaction and disposal of surplus soil as
required.
Swing type hose reel drum with corrugated
hose 30.5x25mm diameter complete with
valve, bracket, 12.5mm diameter nozzle and
other accessories as described.
Excavate trench to receive 50mm diameter
Galvanised Iron class 'B' incoming pipe,
maximum depth not exceeding 1.0m
including filling in, compaction and disposal
of surplus soil as described.
Electrical duty pump with the capacity of 30
igm againts 170 ft static head complete with
wiring, pump plinth and other accessories
Hose reel cabinet type SRI model HRS 045
or equivalent for all hose reel drum
Item Description Unit Rate Qtty Rm
Galvanised Iron Class 'B' Tubing Screw
S k t d T th I l di All N
-
8/2/2019 Fire Fighting Note
123/125
A m 17
B m 5
C m 2
A no 1
B no 2
C no 5
To collection
Socketed Together Including All Necessary
Short Length, Sockets, Connectors,
Backnuts, Elbows And The Likes As
Described
150mm Diameter incoming pipe laid in trench
(m/s)
50mm Diameter incoming pipe embedded
into ground floor slab
50mm Diameter incoming pipe fixed to
brickwall
65mm Diameter gate valve and jointing to
galvanised iron pipe
50mm Diameter check valve and jointing togalvanised iron pipe
50mm Diameter air release valve and jointing
to galvanised iron pipe
Brasswork To Comply To BS 1010 As
Described
Item Description Unit Rate Qtty Rm
Fire Alarm System Installation
A no 1Main fire alarm console panel (6 zones)
-
8/2/2019 Fire Fighting Note
124/125
A no 1
B no 1
C no 1
D no 1
Testing
A Item
To collection
150mm Diameter fire alarm bell with 24v
(d.c) suplly mounted at wall as described
Allow for testing the foregoing fire fightingsystem, make good any defect and leave the
whole installation in perfect working order to
the satisfaction of the superitandant officer.
Main fire alarm console panel (6 zones)
complete with LED mimic diagram, battery
compartment complete with 8 AHx24V and
charger as manufacturer's detail.
400x400x150mm fixed to wall junction box
approved type and quality, complete with
3mm thick galvanised steel covers, gasket
and all other necessary accessories.
Manual break glass fire alarm size
84mmx115mm with 24v(d.c) supply mounted
at wall as described
-
8/2/2019 Fire Fighting Note
125/125