Financing Energy Projects in Jordan
-
Upload
hayan-janakat -
Category
Documents
-
view
220 -
download
0
Transcript of Financing Energy Projects in Jordan
-
7/29/2019 Financing Energy Projects in Jordan
1/19
Project Finance Presentation forEDAMA
Eversheds LLP
Thursday 16th March 2013
-
7/29/2019 Financing Energy Projects in Jordan
2/19
Limited Recourse and Non RecourseFinancing Terms used interchangeably
What is it?
The financing of the development or exploitation ofa right, natural resource or other asset where the
bulk of the financing is to be provided by way ofdebt and is to be repaid principally out of the assetbeing financed and its revenues.
Key features
-
7/29/2019 Financing Energy Projects in Jordan
3/19
Financing Possible routes
Limited/Non recourse debt for greenfield projects What is limited recourse
The full scope project finance version, allowing significantly lower equity commitments
It is available, but requires to go through a specific discipline
Subject to rating agencies perception
Limited/Non recourse refinancing of operational projects
Available now that more projects are actually operational and have good track records Simpler than greenfield as all construction contractual & management issues have been
resolved
May take the form at some point of portfolio refinancings (and allow for sale of minoritystakes in these as well)
Sale of minority stakes in projects, pre- or post-completion
Allows to recycle capital invested in existing projects into new ones without loss ofoperational control
Recent transactions have shown there is appetite from many types of investors for theseassets
Most interested investors to date prefer to avoid construction risk, but that will change
Allows capture of value through long term O&M arrangements or PPAs
-
7/29/2019 Financing Energy Projects in Jordan
4/19
Project Finance Structure
Shareholders
SPV
Landlord
Offtaker
Subcontractors Subcontractors Subcontractors
Banks
Direct Agreementsand Assignments
Security (Debenture)
Limited Recourse Facility
Leases
-
7/29/2019 Financing Energy Projects in Jordan
5/19
Key elements of bankability of windprojects
-
7/29/2019 Financing Energy Projects in Jordan
6/19
Property and planning
Option for lease and lease
Term of lease
Certainty of rental and other costs - RPI Termination rights
Direct Agreement
Grid Connection - wayleaves
Site access roads Adjacent rights - restrictions
-
7/29/2019 Financing Energy Projects in Jordan
7/19
Energy Yield
Wind/Solar Data
Correlation
P50/P90 debt sizing
-
7/29/2019 Financing Energy Projects in Jordan
8/19
Debt to Equity
History of developer
Site
Funding shortfalls Contingent equity
Change of control
-
7/29/2019 Financing Energy Projects in Jordan
9/19
Grid Connection
Date of connection
Capacity
Land rights Remedies
-
7/29/2019 Financing Energy Projects in Jordan
10/19
Technology
Turbine supplier/Panel Supplier
Warranties
O&M Currency risk
-
7/29/2019 Financing Energy Projects in Jordan
11/19
PPA
Term
Contract Price
Price adjustments Change in law
Counterparty risk
Security arrangements
-
7/29/2019 Financing Energy Projects in Jordan
12/19
Construction
Longstop date
Assumed completion date
Liquidated damages Collateral warranties
Interface issues multi-contracting
Insurance and title transfer
-
7/29/2019 Financing Energy Projects in Jordan
13/19
Operational
O&M agreement
Project management agreement
Availability guarantees (95%-97%) Debt service reserve
Maintenance reserve
Monitoring
-
7/29/2019 Financing Energy Projects in Jordan
14/19
Bank Protections
Security structure
Intercreditor issues
Distributions and distribution conditions
Reporting requirements
Accounts and project revenue control
Insurance
Hedging agreements
-
7/29/2019 Financing Energy Projects in Jordan
15/19
Lender Sponsor Friction points
How intrusive is the due diligence? Review of interfaces, sub-contracts, logistics and project management irrespective of contractual
structure
Review of technology, supply chain, quality control processes, key personnel, sub-contractor
creditworthiness
How involved are the banks (or relevant advisors) in contract negotiation?
Requirement for a number of PF-standard clauses
More explicit warranty and interface language Decision on number of contracts
Responsibility for vessels
Parent company guarantees or performance bonds
How strict are the financial covenants?
Detailed information and at times, validation of decisions
Share retention clauses
Debt: Equity 70:30 Equity Upfront
Consecutive O&M assumptions
What are the terms and conditions for long term O&M?
Tenor, scope, liability, fixed price, counterparty
Options to exit after a few years
-
7/29/2019 Financing Energy Projects in Jordan
16/19
PF or not to PF (1)
It helps improve risk discipline for the project
More external eyes on contracts, interfaces and detailed project structure
Specific focus by banks and their advisors on potential downside scenarios
Project can work on a stand-alone basis (which makes it easier to sell)
It can help investors and contractors!
Blame the Bank
Less zero-sum negotiations
Its really limited/non-recourse
Banks take construction risk on the basis of the contracts and committed contingencymechanisms
While sponsor involvement is valued, banks evaluate deals with no expectation of additionalcash in
Pricing will come down
-
7/29/2019 Financing Energy Projects in Jordan
17/19
PF or not to PF (2)
It needs to be an early decision by investors A lot of the value from project finance discipline comes at an early stage, when choosing the
contractual structure and negotiating the relevant contracts
The good news is that a lot of that work can be done without involving large banking groups,by using a small number of specialised advisors
It requires experienced advisors
Bring in at your side entities which have credibility as lenders advisors and ask them to lookat the project from the perspective of lenders
Good, legal, financial and technical advisors are indispensable
Pre-packaging a deal that banks will accept
Investors and contractors need to be committed to it
Counterparties will accept to incorporate banks requirements in their commercial offers onlyif they really believe that the project will not happen without external financing
Take into account the feedback from specialised advisors
-
7/29/2019 Financing Energy Projects in Jordan
18/19
Any Questions....
...Thank you!
Indraj Mangat, Partner, Banking
Eversheds
T. +44 776 741 1508
mailto:[email protected]:[email protected] -
7/29/2019 Financing Energy Projects in Jordan
19/19
EVERSHEDS LLP 2013. Eversheds LLP is a limited liability partnership.