Financing Energy Projects in Jordan

download Financing Energy Projects in Jordan

of 19

Transcript of Financing Energy Projects in Jordan

  • 7/29/2019 Financing Energy Projects in Jordan

    1/19

    Project Finance Presentation forEDAMA

    Eversheds LLP

    Thursday 16th March 2013

  • 7/29/2019 Financing Energy Projects in Jordan

    2/19

    Limited Recourse and Non RecourseFinancing Terms used interchangeably

    What is it?

    The financing of the development or exploitation ofa right, natural resource or other asset where the

    bulk of the financing is to be provided by way ofdebt and is to be repaid principally out of the assetbeing financed and its revenues.

    Key features

  • 7/29/2019 Financing Energy Projects in Jordan

    3/19

    Financing Possible routes

    Limited/Non recourse debt for greenfield projects What is limited recourse

    The full scope project finance version, allowing significantly lower equity commitments

    It is available, but requires to go through a specific discipline

    Subject to rating agencies perception

    Limited/Non recourse refinancing of operational projects

    Available now that more projects are actually operational and have good track records Simpler than greenfield as all construction contractual & management issues have been

    resolved

    May take the form at some point of portfolio refinancings (and allow for sale of minoritystakes in these as well)

    Sale of minority stakes in projects, pre- or post-completion

    Allows to recycle capital invested in existing projects into new ones without loss ofoperational control

    Recent transactions have shown there is appetite from many types of investors for theseassets

    Most interested investors to date prefer to avoid construction risk, but that will change

    Allows capture of value through long term O&M arrangements or PPAs

  • 7/29/2019 Financing Energy Projects in Jordan

    4/19

    Project Finance Structure

    Shareholders

    SPV

    Landlord

    Offtaker

    Subcontractors Subcontractors Subcontractors

    Banks

    Direct Agreementsand Assignments

    Security (Debenture)

    Limited Recourse Facility

    Leases

  • 7/29/2019 Financing Energy Projects in Jordan

    5/19

    Key elements of bankability of windprojects

  • 7/29/2019 Financing Energy Projects in Jordan

    6/19

    Property and planning

    Option for lease and lease

    Term of lease

    Certainty of rental and other costs - RPI Termination rights

    Direct Agreement

    Grid Connection - wayleaves

    Site access roads Adjacent rights - restrictions

  • 7/29/2019 Financing Energy Projects in Jordan

    7/19

    Energy Yield

    Wind/Solar Data

    Correlation

    P50/P90 debt sizing

  • 7/29/2019 Financing Energy Projects in Jordan

    8/19

    Debt to Equity

    History of developer

    Site

    Funding shortfalls Contingent equity

    Change of control

  • 7/29/2019 Financing Energy Projects in Jordan

    9/19

    Grid Connection

    Date of connection

    Capacity

    Land rights Remedies

  • 7/29/2019 Financing Energy Projects in Jordan

    10/19

    Technology

    Turbine supplier/Panel Supplier

    Warranties

    O&M Currency risk

  • 7/29/2019 Financing Energy Projects in Jordan

    11/19

    PPA

    Term

    Contract Price

    Price adjustments Change in law

    Counterparty risk

    Security arrangements

  • 7/29/2019 Financing Energy Projects in Jordan

    12/19

    Construction

    Longstop date

    Assumed completion date

    Liquidated damages Collateral warranties

    Interface issues multi-contracting

    Insurance and title transfer

  • 7/29/2019 Financing Energy Projects in Jordan

    13/19

    Operational

    O&M agreement

    Project management agreement

    Availability guarantees (95%-97%) Debt service reserve

    Maintenance reserve

    Monitoring

  • 7/29/2019 Financing Energy Projects in Jordan

    14/19

    Bank Protections

    Security structure

    Intercreditor issues

    Distributions and distribution conditions

    Reporting requirements

    Accounts and project revenue control

    Insurance

    Hedging agreements

  • 7/29/2019 Financing Energy Projects in Jordan

    15/19

    Lender Sponsor Friction points

    How intrusive is the due diligence? Review of interfaces, sub-contracts, logistics and project management irrespective of contractual

    structure

    Review of technology, supply chain, quality control processes, key personnel, sub-contractor

    creditworthiness

    How involved are the banks (or relevant advisors) in contract negotiation?

    Requirement for a number of PF-standard clauses

    More explicit warranty and interface language Decision on number of contracts

    Responsibility for vessels

    Parent company guarantees or performance bonds

    How strict are the financial covenants?

    Detailed information and at times, validation of decisions

    Share retention clauses

    Debt: Equity 70:30 Equity Upfront

    Consecutive O&M assumptions

    What are the terms and conditions for long term O&M?

    Tenor, scope, liability, fixed price, counterparty

    Options to exit after a few years

  • 7/29/2019 Financing Energy Projects in Jordan

    16/19

    PF or not to PF (1)

    It helps improve risk discipline for the project

    More external eyes on contracts, interfaces and detailed project structure

    Specific focus by banks and their advisors on potential downside scenarios

    Project can work on a stand-alone basis (which makes it easier to sell)

    It can help investors and contractors!

    Blame the Bank

    Less zero-sum negotiations

    Its really limited/non-recourse

    Banks take construction risk on the basis of the contracts and committed contingencymechanisms

    While sponsor involvement is valued, banks evaluate deals with no expectation of additionalcash in

    Pricing will come down

  • 7/29/2019 Financing Energy Projects in Jordan

    17/19

    PF or not to PF (2)

    It needs to be an early decision by investors A lot of the value from project finance discipline comes at an early stage, when choosing the

    contractual structure and negotiating the relevant contracts

    The good news is that a lot of that work can be done without involving large banking groups,by using a small number of specialised advisors

    It requires experienced advisors

    Bring in at your side entities which have credibility as lenders advisors and ask them to lookat the project from the perspective of lenders

    Good, legal, financial and technical advisors are indispensable

    Pre-packaging a deal that banks will accept

    Investors and contractors need to be committed to it

    Counterparties will accept to incorporate banks requirements in their commercial offers onlyif they really believe that the project will not happen without external financing

    Take into account the feedback from specialised advisors

  • 7/29/2019 Financing Energy Projects in Jordan

    18/19

    Any Questions....

    ...Thank you!

    Indraj Mangat, Partner, Banking

    Eversheds

    T. +44 776 741 1508

    E. [email protected]

    mailto:[email protected]:[email protected]
  • 7/29/2019 Financing Energy Projects in Jordan

    19/19

    EVERSHEDS LLP 2013. Eversheds LLP is a limited liability partnership.