Finance: Net Present Value 8.1

20
1 Finance: Net Present Value 8.1 ECON 201 Summer 2009

description

ECON 201 Summer 2009. Finance: Net Present Value 8.1. Firm’s Financing Decision. Firm’s desire to expand and purchase new capital stock can be financed by: Loan (repay with interest) Borrow $X from a lending institution (bank) Issue bonds (debt) - PowerPoint PPT Presentation

Transcript of Finance: Net Present Value 8.1

Page 1: Finance: Net Present Value 8.1

1

Finance:Net Present Value

8.1

ECON 201

Summer 2009

Page 2: Finance: Net Present Value 8.1

2

Firm’s Financing Decision

• Firm’s desire to expand and purchase new capital stock can be financed by:– Loan (repay with interest)

• Borrow $X from a lending institution (bank)

– Issue bonds (debt)• Promise to pay back bond holders later for

obtaining $X today

– Sell stock (corporate holdings, stock splits)• Decrease stock price in the short-run

– Venture Capital

Page 3: Finance: Net Present Value 8.1

3

Benefit/Cost Analysis

• Basic Issue in Business or Personal Finance Decisions– How to evaluate projects/investment opportunities

that have a flow of benefits and costs over time

• Approach – Stream of benefits and costs are discounted over

time (Net Present Value)• Accounts for opportunity costs of money

– Time rate of preference

Page 4: Finance: Net Present Value 8.1

4

Why Firms Seek Funds

• The most common reason for firms to seek funds (financial capital) is to pay for plant and equipment (physical capital).

Page 5: Finance: Net Present Value 8.1

5

The Net Benefits from an Investment

• The net benefit of an investment project is the difference between the revenue generated by the project and the project’s cost, including opportunity cost.

Page 6: Finance: Net Present Value 8.1

6

Interest

• Interest is an important part of the investment decision for two reasons:

– First, interest must be paid to borrow funds.

– Second, interest is the opportunity cost of using money to pay for an investment project.

• Money used to purchase capital could have been deposited in a bank to earn interest.

Page 7: Finance: Net Present Value 8.1

7

Interest (cont’d)

• Lenders charge interest:– To compensate themselves for not being able

to use their own money to buy the things they want

– To compensate themselves for the risk they assume when they make a loan

– Because rising prices will reduce the purchasing power of the money when it is repaid

Page 8: Finance: Net Present Value 8.1

8

Time Value of Money

• Money today is more valuable than the same amount of money at some point in the future.– If you have money today, you could deposit it

in a bank and earn interest.

Page 9: Finance: Net Present Value 8.1

9

Present and Future Value

• The present value (PV) of money received in the future is equal to its value today.– In other words, it is the maximum amount that

someone would pay today to receive the money in the future.

Page 10: Finance: Net Present Value 8.1

10

Present and Future Value (cont’d)

• The future value (FV) of money is what an amount of money will be worth at some point in the future.

Page 11: Finance: Net Present Value 8.1

11

Present and Future Value (cont’d)

• The relationship between present and future value can be shown by the following equations:

FV PV (1 Interest Rate)PV FV (1 Interest Rate)

Page 12: Finance: Net Present Value 8.1

12

Present and Future Value (cont’d)

• Examples: Suppose the interest rate is 5%.

– What is the future value of $10,000 one year from now?

• FV = $10,000 x (1 +.05) = $10,500

– What is the present value of $10,000 received one year from now?

• PV = $10,000 / (1 +.05) = $9,524

Page 13: Finance: Net Present Value 8.1

13

Present and Future Value (cont’d)

• Discounting refers to the method used to calculate the present value of a stream of payments over time.

– Example: Suppose a firm expects to earn $10,000 of revenue in each of the next 2 years.

• • •

PV in Year 1 $10,000 (1 .05)$9,524

PV in Year 2 $10,000 (1 .05)2 $9,070Total Value $9,524 $9,070$18,594

Page 14: Finance: Net Present Value 8.1

14

Evaluating Projects

• Expansion project– Requires an initial investment, Io

– Yields a flow of benefits over time, Bt

10

0

...(1 ) (1 ) (1 )

nn t

o ot tt

B BBNPV I B I

r r r

Page 15: Finance: Net Present Value 8.1

15

Net Present Value

• Firms focus on the net present value (NPV) of an asset when making investment decisions. – NPV = PV of the asset minus the PV of the

expenditures on the asset.

• If NPV > 0 then the investment is profitable.– All else equal, the sooner the benefits are received

and the lower the interest rate, the higher the NPV.

Page 16: Finance: Net Present Value 8.1

16

Net Present Value (cont’d)

• Example: Suppose a firm is considering investing $8,000 in new equipment. As a result of the new equipment, the firm expects to earn revenues of $10,000 in each of the next 2 years.

• Since NPV is positive, the firm should undertake the investment.

NPV $8,000$10,000 / (1 .05)$10,000 / (1 .05)2

$8,000$9,524 $9,070$10,594

Page 17: Finance: Net Present Value 8.1

17

Interest and the Demand for Capital

• The interest rate represents the opportunity cost of purchasing capital. Therefore, as the interest rate increases, the quantity of capital demanded will fall.

Page 18: Finance: Net Present Value 8.1

18

Figure 14.1 The Demand Curve for Physical Capital

Page 19: Finance: Net Present Value 8.1

19

Washington State Lottery

• Jackpot Analysis For Washington MEGA MillionsDraw Date: Tuesday, March 11, 2008

• Jackpot is worth $47,000,000• Payment Options

– Annuity• 26 Annual Payments of  $1,807,692

– Lump Sum•   $29,200,000 

Page 20: Finance: Net Present Value 8.1

20

Lump Sum or Annuity?annual NPV @ 5% Lump sum

1,802,692 $25,914,031.54 29,200,0001,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,6921,802,692

46,869,992