FINAL REPORT RP1355 v4 Road Sector Development Team ...
Transcript of FINAL REPORT RP1355 v4 Road Sector Development Team ...
FINAL REPORT
RP1355 v4
Road Sector Development Team
Federal Ministry of Works
Abbreviated Resettlement Action Plan (ARAP)
For the Construction of alternate Bridge at (Km 7+350) along Enugu-
Abakiliki Road, Emene Enugu State
Prepared by
MULTIPLE DEVELOPMENT SERVICES LTD
October, 2012
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
1 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
TABLE OF CONTENTS
TABLE OF CONTENTS 1
LIST OF TABLES 3
ABBREVIATIONS AND ACRONYMS 4
DEFINITIONS 5
EXECUTIVE SUMMARY 7
1. INTRODUCTION 11
1.1 Background 11
1.2 Applicability of ARAP: Involuntary Resettlement 12
1.3 Aims and Objectives of the ARAP 13
1.4 Scope of Work 13
1.5 Methodology of Study 14
1.5.1 Field Surveys 15
1.5.2 Major Sub-activities of the ARAP 16
1.5.3 Identification of PAPS and Affected Assets 16
1.5.4 Work Program me 17
2. DESCRIPTION OF PROJECT 19
2.1 General Description of Study Area 19
2.2 Socio-Economic Survey of the Project Area 21
3. POLICY AND REGULATORY FRAMEWORK 24
3.1 World Bank Safeguard Policies 24
3.2 Nigeria Regulatory Framework 25
3.2.1 The Federal Ministry of Environment (FMEnv) 26
3.2.2 The National Environmental Standards and Regulations Enforcement
Agency (NESREA) Act No 25 of 2007 27
4.2.3 Environmental Impact Assessment (EIA) Act Cap 131 LFN 1992 28
4.2.3.1 Sect oral EIA Guidelines 29
3.3 Nigeria Urban & Regional Planning Law No 88 of 1992 29
3.4 Land Use Act Cap 202 LFN 1990 30
3.5 Comparison between Land Use Act and World Bank OP 4.12 31
4. IDENTIFICATION OF PROJECT IMPACTS AND PROJECT AFFECTED PERSONS 31
4.1 Approach to Impacts and PAPs Identification 31
4.2 Eligibility Criteria for Affected Persons 32
4.3 Proof of Eligibility 33
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
2 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
4.4 Entitlement Policy 33
4.4.1 PAPs Losing Structures 34
4.4.2 Vendors displaced from road corridors 34
4.4.3 PAPs with loss of economic trees 34
4.5 Notification 34
4.6 Duration for Civil works 35
4.7 Inventory and Census of Affected assets and PAPs 35
5. VALUATION AND COMPENSATION OF AFFECTED STRUCTURES AND PROPERTY 35
5.1 Introduction 36
5.2 Method of Valuation for compensation 36
5.3 Category of Payments of Compensation 37
5.4 Entitlement Matrix 37
5.5 Valuation of Resettlement/Compensation and Assistance Cost for PAPs 38
6. INSTITUTIONAL ARRANGEMENT AND RESPONSIBILITIES 39
6.1 Introduction 39
6.2 Institutional Arrangement 40
6.3 Grievances and Appeals Procedure 41
6.3.1 Grievance Redress Mechanisms 42
7. MONITORING AND EVALUATION 43
7.1 Internal Monitoring 43
7.1.1 Tasks of the Monitoring and Evaluation Officer 44
7.2 Independent Monitoring 45
7.2.1 Implementation Schedule 46
8. COMPENSATION FUNDING ARRANGEMENT AND TIMETABLE 48
8.1 Budget for Resettlement activities related with the Road Project 48
8.2 World Bank-RSDT 49
8.3 Training Needs 49
9. PUBLIC CONSULTATION 50
9.1 Introduction 50
9.2 Public Consultation Process 51
9.3 Overview of Public Consultations Programme 52
9.3.1 Otukwu Emene village 52
REFERENCES 53
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
3 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
LIST OF TABLES
Table E1: Indicative budget for ARAP implementation
Table 4.1: Comparison of Nigerian Land Use Act (1978) and World Bank’s OP 4.12
Table 5.1: Entitlement Matrix showing categories of project affected persons, type
of loss and compensation
Table 5.2: Valuation of Compensation and Assistance Cost for Project Affected
Persons
Table 6.1: Institutional Arrangement and Responsibilities for ARAP
Table 7.1: Summary of Responsibility for Implementation of Abbreviated
Resettlement Action Plan
Table 8.1: Timetable for Abbreviated Resettlement Action Plan
Table 8.2: Recommended Training and Awareness
Table 9.1: Attendance at a Focus Group Discussion with Otukwu village Emene
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
4 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
ABBREVIATIONS AND ACRONYMS
ADT - Average Daily Traffic
ARAP - Abbreviated Resettlement Action Plan
DP - Displaced Persons
ESIA - Environmental and Social Impact Assessment
ESMF - Environmental and Social Management Framework
ESMP - Environmental and Social Management Plan
FMW - Federal Ministry of Works
FGN - Federal Government of Nigeria
FGD - Focus Group Discussion
FERMA - Federal Roads Maintenance Agency
FRDP - Federal Roads Development Project
IDA - International Development Association
LGA - Local Government Authority
PAD - Project Appraisal Document
PAP - Project Affected Person
PRA - Participatory Rural Appraisal
PIU - Project Implementation Unit
PIM - Project Implementation Manual
PSP - Private Sector Partner or Private Sector Participation
RAP - Resettlement Action Plan
ROW - Right of Way
RPF - Resettlement Policy Framework
RSDT - Road Sector Development Team
SPIU - State Project Implementation Unit
SRMC - Sector Reform Management Committee
SSI - Semi Structured Interview
WB - World Bank.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
5 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
DEFINITIONS
Children: all persons under the age of 18 years according to international regulatory
standard (convention on the rights of Child 2002).
Community: a group of individuals broader than households, who identify themselves
as a common unit due to recognized social, religious, economic and traditional
government ties or shared locality.
Compensation: payment in cash or in kind for an asset or resource acquired or
affected by the project.
Cut-off-Date: the date of completion of inventory of losses and census of project
affected persons
Economic Displacement: a loss of productive assets or usage rights or livelihood
capacities because such assets / rights / capacities are located in the project area.
Entitlement: the compensation offered by RAP, including: financial compensation; the
right to participate in livelihood enhancement programs; housing sites and
infrastructure; transport and temporary housing allowance; and, other short term
provisions required to move from one site to another.
Head of the Household: the eldest member of the core family in the household, for the
purpose of the project.
Household: a group of persons living together who share the same cooking and
eating facilities, and form a basic socio-economic and decision making unit. One or
more households often occupy a homestead.
Involuntary Resettlement: resettlement without the informed consent of the displaced
persons or if they give their consent, it is without having the power to refuse
resettlement.
Lost Income Opportunities: lost income opportunities refers to compensation to
project affected persons for loss of business income, business hours/time due to project
Operational Policy 4.12: Describes the basic principles and procedures for resettling,
compensating or at least assisting involuntary displace persons to improve or atleast
restore their standards of living after alternatives for avoiding displacement is not
feasible
Physical Displacement: a loss of residential structures and related non-residential
structures and physical assets because such structures / assets are located in the
project area.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
6 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
Private property owners: persons who have legal title to structures, land or other assets
and are accordingly entitled to compensation under the Land Act.
Project-Affected Community: a community that is adversely affected by the project.
Project-Affected Person: any person who, as a result of the project, loses the right to
own, use or otherwise benefit from a built structure, land (residential, agricultural, or
pasture), annual or perennial crops and trees, or any other fixed or moveable asset,
either in full or in part, permanently or temporarily.
Rehabilitation: the restoration of the PAPs resource capacity to continue with
productive activities or lifestyles at a level higher or at least equal to that before the
project.
Relocation: a compensation process through which physically displaced households
are provided with a one-time lump-sum compensation payment for their existing
residential structures and move from the area.
Replacement Cost: the amount of cash compensation and/or assistance suffices to
replace lost assets and cover transaction costs, without taking into account
depreciation or salvage value.
Resettlement Action Plan (RAP): documented procedures and the actions a project
proponent will take to mitigate adverse effects, compensate losses, and provide
development benefits to persons and communities affected by a project.
Resettlement Assistance: support provided to people who are physically displaced by
a project. This may include transportation, food, shelter, and social services that are
provided to affected people during their resettlement. Assistance may also include
cash allowances that compensate affected people for the inconvenience associated
with resettlement and defray the expenses of a transition to a new locale, such as
moving expenses and lost work days.
Resettlement: a compensation process through which physically displaced
households are provided with replacement plots and residential structures at one of
two designated resettlement villages in the district. Resettlement includes initiatives to
restore and improve the living standards of those being resettled.
Squatters: squatters are landless household squatting within the public / private land
for residential and business purposes.
Vulnerable: people who by virtue of gender, ethnicity, age, physical or mental
disability, economic disadvantages, or social status may be more adversely affected
by resettlement than others and who may be limited in their ability to claim or take
advantage of resettlement assistance and related development benefits.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
7 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
EXECUTIVE SUMMARY
ES 1 Introduction
The Federal Government of Nigeria (FGN) through the Federal Ministry of
works, (FMW) requested the World Bank’s support towards the Federal Roads
Development Project (FRDP). The purpose is to meet the immediate and
short term funding needs for the federal road network and support
Government’s efforts with policy and institutional reforms promoting
improved service delivery, road management and financing.
As part of the ongoing efforts to ensure a sustainable rehabilitation works on
the Enugu Abakaliki Route length, the suggestion to construct an entirely
alternate bridge to replace the No 2 bridge counting from Enugu end at
7+300Km which has recently showed great structural failure becomes very
imperative.
An abbreviated resettlement Action Plan has been prepared for the
rehabilitation of the road, which did not capture the provision of the
alternate bridge at Km 7+350 hence, the need to prepare an abbreviated
resettlement action plan (ARAP) for the bridge which is consistent with the
RPF prepared for the project and in line with World Bank OP 4.12 to ensure
that the Project Affected Persons (PAPs) are adequately compensated or
provided assistance.
ES 2 Objectives of the Abbreviated Resettlement Action Plan of the Project
The specific objectives of the ARAP are:
To identify persons (individuals or groups) who are affected by
the project;
To identify, through consultation, appropriate options for the
resettlement and compensation of PAP, which are consistent
with Nigeria Laws, World Bank’s Operational Policy 4.12 and IFC
Performance Standards 5: Land Acquisition and Involuntary
Resettlement and
To determine a process for resettlement, compensation and
land acquisition, consistent with the project’s objective.
ES 3 Scope of Work
The scope of work underlying this ARAP is the identification of project impacts
and affected population through the following:
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
8 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
Thematic maps;
Census that enumerates project affected persons (PAPs) and registers
them according to location;
An inventory of lost and affected assets at the household, enterprise,
and community level;
Socio-economic surveys and studies of all affected populations as may
be deemed necessary;
Analysis of surveys and studies to establish compensation parameters,
to design appropriate income restoration and sustainable
development initiatives;
Identify baseline monitoring indicators
Consultation with affected populations regarding mitigation of impacts
and development opportunities
ES 4 Approaches and Methodology of Social Assessment
Resettlement planning is necessary whenever displacement or relocation
occurs as part of project activities. Prior to implementation of the
resettlement activities, baseline data is collected and potential impacts are
identified and analyzed. Mitigation measures are then put in place to
address negative impacts and compensatory plans are designed and
recommended.
The resettlement team visited the local authorities, the Bridge site, affected
facilities along the proposed transition road corridor, vendor unions and the
project affected persons in Otukwu village Emene Enugu, being the major
areas with possible significant impacts on socio-economic lives of
communities, especially PAPs.
Detailed field visits were carried out across the communities of project area
of influence. The field visits were used to identify and undertake detailed
inventory of PAPs as well as update baseline information of the project areas.
ES 5 Impacts of the Project
The impacts of the construction project as it concerns the social aspect are
categorized into positive and negative impacts. Whereas the positive
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
9 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
impacts are more, the negative impacts are minimal and subject to
mitigation.
Positive Impacts
o More guaranteed access to market and business
o Reduction in the rate of accidents due to dilapidating bridge
o Improve condition of living due to easy movement of input and
output by farmers and business people
o Inter-state transportation convenience and reduction in traveling
time
o Reduction in road congestions
Negative Impacts
o Disturbance of access to business and movement especially during
construction
o Displacement of vendors along the right of way of the high way
o Destruction of economic trees
Negative impacts are neutralized via involuntary resettlement budget plan.
ES 6 Indicative Budget for ARAP Implementation
The total indicative budget for the ARAP implementation is Eight Hundred
and Twenty Seven Thousand, Four Hundred and Fifty Naira only
(N827,450.00). This is comprised as shown in the table below:
Table E1: Indicative budget for ARAP implementation
Description PAP’s by group Total in
Naira
Otukwu
village
NNPC PHCN Block
industry
Sand
miners
1. Cost of
replacement
of structure
and /or cost
of shifting
affected
structure/kiosk
21000 105000 70000 73500 NA 269500
2. Loss of Income NA NA NA NA 42000 42000 3. Compensation
for Economic
Tree
157500 10500 NA NA NA 168000
Sub-Totals 178500 115500 70000 73500 42000 479,500
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
10 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
4. Capacity
Building and
enlightenment
for ARAP
Implementatio
n (Lump sum)
300,000
5. Monitoring
and
Supervision of
ARAP
Implementatio
n (10 % of
Total)
47,950
Total 827,450
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
11 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
1.0 INTRODUCTION
1.1 Background
In response to the enormous transport challenges in linking communities together,
reducing passenger travel times, transport cost for both freight and passengers,
vehicle operating costs, traffic related fatalities on targeted federal roads while
increasing access to markets, jobs, education, and health services as well as assisting
the Federal Government of Nigeria (FGN) to manage Nigeria's federal road assets in a
sustainable manner; The Federal Government of Nigeria (FGN), through the Federal
Ministry of Works (FMW), has requested World Bank’s support for the Federal Roads
Development Project (FRDP).
The FRDP is a major investment in improving the quality of life of Nigerians, especially
those in the rural areas.
The Federal Roads Development Project is organized into three components to
support both the implementation of the proposed reform and the financing of
critically needed investments. The three main components are:
Policy and Institutional Reforms
Institutional Capacity Building
Upgrading, Rehabilitation and Maintenance of Federal Roads
The activities under the investments for the Unity Roads will entail routine and periodic
maintenance, rehabilitation, and upgrading of Federal Highway of about 5700
kilometers identified by the Project Appraisal Document.
The Enugu-Abakaliki road which is under Phase I roads of FRDP is a segment of the
Trans-African Highway linking Lagos on the West African Atlantic coast with Kenya
town of Mombassa on the East African Indian ocean coast. The road is about 239 km
long, running approximately west - east axis starting from Enugu through Abakaliki,
Ogoja junction, Ikom and terminates at Mfum at the border of Nigeria and
Cemeroon Republics. The road when completed will link Enugu in Nigeria with
Bamenda in Cameroon.The project, which was co–financed by the African
Development Bank, the World Bank and the Japanese International Co-operation
Agency, are targeted at increasing trade and strengthening co-operation between
Cameroon and Nigeria.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
12 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
The sections under the AfDB funding are as follows:
Abakaliki-Ogoja Junction Road-86km Lot 1
Ikom- Mfum-22km Lot 2
While the sections under the IDA funding are as follows:
Enugu-Abakaliki-76km LotA
Mbok (Ogoja Junction)-Ikom-55km Lot B
As part of the ongoing efforts to ensure a sustainable rehabilitation works on the
Enugu -Abakaliki section of the road, it was observed that the bridge at km7+350 has
started showing sign of structural failures, hence the need to construct an entirely
alternate bridge to replace the existing bridge which was not initially in the scope of
work for the rehabilitation work.
Although there is land intake, but is within the ROW. However it was observed that
there are improvements on the land by some individual on the ROW. Those who have
made improvement on it will be compensated. Temporally shops, block industry,
NNPC water pipe lines and facilities, PHCN electric lines etc along the proposed
transition road corridor will be displaced. This will result to involuntary displacement
and disturbance of access to means of livelihoods, and therefore, triggering the World
Bank’s Operational Policy 4.12 (Involuntary Resettlement), hence, the need to
prepare an abbreviated resettlement action plan (ARAP) which is consistent with the
RPF prepared for the project and in line with World Bank OP 4.12 to ensure that the
Project Affected Persons (PAPs) are adequately compensated or provided with
assistance.
1.2 Applicability of ARAP: Involuntary Resettlement
This policy covers direct economic and social impacts that both result from the World
Bank-assisted investment projects, and are caused by:
The involuntary taking of land resulting in:
(i) Relocation or loss of shelter;
(ii) Loss of assets or access to assets, or
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
13 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
(iii) Loss of income sources or means of livelihood, whether or not the affected
persons must move to another location; or not.
The involuntary restriction of access to legally designated parks and
protected areas resulting in adverse impacts on the livelihoods of the
displaced persons. The Resettlement Policy Framework (RPF) report discusses
the applicability of this policy in detail.
The core requirements of OP 4.12 are as follows:
Avoid or minimize involuntary resettlement where feasible, exploring all viable
alternative project designs.
Assist project affected persons in improving their former living standards, income
earning capacity, and production levels, or at least in restoring them back to the
former status
Encourage community participation in planning and
implementing resettlement.
Provide assistance to affected people regardless of the legality
of land tenure.
Under the World Bank Safeguard Policy, on involuntary resettlement, a project is
classified as full Resettlement Action Plan (RAP) when the number of people to be
displaced involuntarily is from 200 and above and/or when the land take involves 10
percent of the total holding. On the contrary, if the number of people to be displaced
or affected is less than 200, and land take is less than 10 percent of the total holding, it
advocates for Abbreviated Resettlement Action Plan (ARAP).
1.3. Aims and Objectives of the ARAP
The objective of the consultation is to prepare an abbreviated Resettlement
Action Plan (ARAP) for the Enugu- Abakaliki Bridge No 2 of the FRDP.
To ensure that implementation of the bridge does no harm to the
environment and population.
Identification of project impacts and affected population(individuals or
groups) who are affected by the project
To identify, through consultation, appropriate options for the resettlement and
compensation of PAP, which are consistent with Nigeria Laws, World Bank’s
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
14 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
Operational Policy 4.12 and IFC Performance Standards 5: Land Acquisition and
Involuntary Resettlement and
To determine a process for resettlement, compensation and land acquisition,
consistent with the project’s objective.
1.4 Scope of Work of Consultant
The scope of work underlying this ARAP is the identification of project impacts
and affected population through the following:
Thematic maps;
Census that enumerates project affected persons (PAPs) and registers
them according to location;
An inventory of lost and affected assets at the household, enterprise, and
community level;
Socio-economic surveys and studies of all affected populations as may
be deemed necessary;
Analysis of surveys and studies to establish compensation parameters, to
design appropriate income restoration and sustainable development
initiatives;
Identify baseline monitoring indicators
Consultation with affected populations regarding mitigation of impacts
and development opportunities
1.5 Methodology of Study
Resettlement planning is necessary whenever displacement or relocation occurs as
part of project activities. Prior to implementation of the resettlement activities,
baseline data is collected and potential impacts are identified and analyzed.
Mitigation measures are then put in place to address negative impacts and
compensatory plans are designed and recommended.
Specifically for the project under review, the methodology is as follows:
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
15 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
Harmonization of project schedule and scope with Road Sector
Development Team;
Collection of relevant documents and literature materials
Reconnaissance survey of the project area to scope impacts along and out
of the right of way of the project site;
Documentation of existing land use activities within the Right-of-Way and the
status of PAPs along the proposed transition road corridor.
Staff organization and training of enumerators (Each of the enumerators
were given tag with numbers).
Review of various documents including:
o RAP document carried out for the proposed project area in 2010,
o the Nigerian regulatory framework on involuntary resettlement;
o World Bank safeguard policies on resettlement, and
o Baseline socio-economic survey of the project areas
Public Consultation and focus group discussions: This was continuous and a major
thrust throughout the project, for identifying PAPs, informing the communities about
the proposed project, eliciting their concerns and possible mitigation measures to
proposed impacts. The resettlement team visited the local authorities, vendor unions
and the project affected persons in Otukwu village Emene Enugu, being the major
owners of the areas with possible significant impacts on socio-economic lives of
communities, especially PAPs.
1.5.1. Field Surveys: Detailed field visits commenced in earnest on Saturday 13th,
October 2012 and were carried out at the 7+350km Enugu – Abakaliki bridge project
site and the village of project area of influence. The field visits were used to identify
and undertake detailed inventory of PAPs as well as update baseline information of
the project area.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
16 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
1.5.2. Major Sub-Activities of the ARAP
In the preparation of the ARAP, stakeholders were sensitized of the project. The
following were carried out in doing the project:
Census and socioeconomic survey of the Affected Vendors and
Households;
Consultations and discussions with the PAPs;
Categorization and valuation of assets to be affected;
Preparation of an entitlement matrix detailing the PAPs names,
affected assets and costs;
Preparation of a budget and time table for the ARAP implementation.
Establishing a mechanism for Grievance resolution.
1.5.3. Identification of PAPS and Affected Assets
Identification of project affected persons (PAPs) was based on the following
considerations:
Owners of assets/structures and facilities along the established transition
road and the new bridge which has gone beyond the right of way (ROW)of
the existing high way usually about 5m radius from the road corridor;
Owners /tenants of houses, structures or means of livelihood located within
this same path;
Those found during census and before cut-off date engaged in economic
activities within this corridor
PAPs whose land or farm will be taken or removed due to the planned
construction work
Owners of Economic trees that may be affected by the planned project.
The support staff and enumerators for this ARAP were trained and equipped with
instruments including questionnaire and tape rule which was used to identify
assets/PAPs and obtained required personal inventories of PAPs. To ensure that PAPs
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
17 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
cooperate with the team, the Consultants engaged in wide consultation with the
community leaders of the affected community, dialogued with them and also
through them, recruited temporal staff that is familiar with the local terrain and
culture. Consultation of PAPs also included meeting with the NNPC deports manager,
PHCN distribution manager and the owner of African tinkers block industry in
negotiation of the relocation of their affected facilities.
1.5.4 Work program me
In order to achieve the drawn up target objectives, a work programme was
developed. This is as presented below.
DAY ACTIVITY MEASURABLE INDICATOR
Day 1 ARRIVAL TO ENUGU
Reconnaissance survey of the
project area
Thematic description of communities and
areas requiring Census
Recruiting of Enumerators Trained and tested with questionnaire
template
Day 2 Identification of Communities,
Leaders and stakeholders
1st stakeholder consultation
Day 3 Census of PAPs /Public
Consultations
Inventory/verification of completed forms
and pictures
General stakeholder consultation
Day 4 Census of PAPs
Public Consultations
Inventory/verification of completed forms
and pictures
General stakeholder consultation
Day 5 Census of PAPs
Public Consultations
Inventory/verification of completed forms
and pictures
General stakeholder consultation
Day 6 Commencement of Post field activities
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
18 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
The existing threatened bank of Ekulu River with score protection by the embankment completely
failed
Proposed stretch for the new Bridge To be displaced African Tinkers block
industry
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
19 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
2.0 DESCRIPTION OF PROJECT AREA
2.1 General Description of Study Area
The project site is located at about 7+350km in Emene Enugu State South Eastern
Nigeria from the Enugu end of the Enugu – Abalaliki road. The proposed bridge to be
constructed is an alternative Bridge to the existing Bridge No 2 out of the 11 bridges
along the said road corridor as shown in table 2.1. It is geographically located
between N06o27.762’, E007o 35.096’ and N06o 27.775’, E007o 35.175’. It also has an
average elevation of 430ft above the sea level.
Table 2.1: List of Bridges along the Enugu – Abakaliki Road
CHAINAGE
SPAN
BRIDGE WIDTH
WALKWAY WIDTH
1+093
20m
(1 – Span)
11.40m
1.3m
7+350
40m
(2 – Span)
7.30m
1.3m
20+592
20m
(1 – Span)
7.30m
1.4m
20+916
30m
(1 – Span)
7.30m
1.3m
23+181
10m
(1 – Span)
7.30m
1.3m
27+254
9m
(1 – Span)
7.3om
1.3m
29+529
9m
(1 – Span)
7.35m
1.3m
37+104
75m
(3 – Span)
7.40m
1.3m
45+112
10m
(1 – Span)
7.40m
2.0mm
53+467
30m
7.30m
1.3m
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
20 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
(1 – Span)
63+247
9m
(1 – Span)
7.30m
1.4m
71+320
20m
(1 – Span)
7.30m
1.4m
74+824
20m
(1 – Span)
7.30m
1.2m
Figure 2.1 shows the Map of Nigeria showing the Eastern region with arrow pointing at
Enugu State, the project site location while an illustrative sketch of the immediate
project site is shown as figure 2.2.
Figure 2.1: Nigeria showing the Eastern Region with green arrow pointing at Enugu
the proposed project site location
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
21 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
Enugu Km 7+325 Abakaliki
---------------------------------------------------------------------
10m 3m 3m 10m
Transition road
Transition road
250m 10m 250m
---------------------------------------------------------------------------------------
EKULU RIVER flow KEY
1. A ---- NNPC facilities (Gate house, water pipe lines etc)
2. ----- Newly negotiated setback for NNPC access (8m from transition road)
3. Transition Road ---- A new proposed road connecting the existing Enugu –Abakaliki road (250m
from either side edge of the new bridge)
4. New bridge is 3m from the existing bridge
5. -------------- Existing PHCN high tension wire line to be relocated (10 poles in all, 5 on either side) –
Budget for relocation, yet to be given by PHCN but expected
6. -------------- Proposed line to relocate the PHCN line (10m from the new bridge)
Figure 2.2: Illustrative sketch of the immediate project site.
The prevailing condition of the existing Bridge is structurally bad and has technical
projections of not being there in the next two years. The bank of the river is seriously
threatened while the existing score protection by the embankment has failed
completely.
An ESIA has been carried out by the project developers in order to comply with the
statutory requirements and to identify, evaluate and mitigate the significant potential
40m Existing
Bridge No2
Proposed 60m New Bridge
A
B
B
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
22 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
impacts of the development project on the environment. Specifically in recognition
of the fact that environmental and social concerns may arise as a result of the
proposed project, the FMW commissioned an Environmental and Social Management
Framework (ESMF) study in fulfillment of the World Bank requirements for project
appraisal.
The ESMF was prepared to satisfy national and state regulatory requirements as well as
World Bank's mandate for Category B projects and it addresses the environmental
and socio-economic consequences of the project. As a category B project the
expected impacts from the projects are small scale and site specific thus easily
remedied.
The ESMF described the existing environment for those aspects of the physical,
biological, social and economic environment within the study area that are relevant
to the project. The framework also identifies the project-environment Interactions
during operational phase.
In addition, the ESMF defines standard procedures and methods for incorporating
environmental and social concerns into the selection, planning and implementation
of all sub-projects carried out under the project.
Furthermore a Resettlement Policy Framework (RPF) was conducted by RSDT. The
objective was to set out the resettlement and compensation principles, organizational
arrangements and design criteria to be applied to meet the needs of the people who
may be affected by the project, when project activities are identified. The
Abbreviated Resettlement Action Plan (ARAP) is prepared consistent with the
provisions of the RPF.
The bridge construction which is a sub-unit of the entire project will reduce the risk and
fright of collapse and thus ensure significant aid to the poor through greatly improved
transport infrastructure and access to marketplaces. The construction and operation
of the Project will bring a large number of direct and induced employment
opportunities to the local economy and further restore confidence on the users.
2.2. Socio-Economic Survey of the Project Area
A socio-economic survey was embarked upon within the project corridor. The socio-
economic survey was premised on PAPs with a view to determining their existing
socio-economic conditions, and how the project impact may affect them. Some of
the concerns along the corridor that are probably to be displaced are shown in plate
3.1.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
23 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
Some of the NNPC facilities that will be affected by the project; water pipe lines, manhole &
access gate
Consultation & enumeration of the items to be
affected by the 8m encroachment with the
Otukwu village exco & PAP’s
A petty trader (Mrs Patricia Anyanwu) along the
corridor of project
Specifically, this intended new development will during implementation affect the
following;
Local sand miners
African Tinkers block industry
NNPC facilities: water pipe line, manholes, perimeter fence, some economic
trees, gate house and access route
PHCN high tension line (10 no; 5 on each side of the bridge)
A woman’s (Patricia Anyanwu) local shop along the transition corridor
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
24 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
About 8m width by 100m length Otukwu village land with about 23 economic
trees (mainly palm trees and cashew).
3.0 POLICY AND REGULATORY FRAMEWORK
The following policy and regulatory frameworks guided the preparation of this ARAP:
3.1 World Bank Safeguard Policies
The World Bank Group is made up of two unique development institutions owned by
187 member countries: the International Bank for Reconstruction and Development
(IBRD) and the International Development Association (IDA).
Each institution plays a different but collaborative role in advancing the vision of
inclusive and sustainable globalization. The IBRD aims to reduce poverty in middle-
income and creditworthy poorer countries, while IDA focuses on the world's poorest
countries.
Their work is complemented by that of the International Finance Corporation (IFC),
Multilateral Investment Guarantee Agency (MIGA) and the International Centre for
the Settlement of Investment Disputes (ICSID).
Whereas:
The World Bank uses Safeguard Policies which apply to projects
owned by States and the Public sector;
The IFC uses performance standards, and are used for projects
owned or sponsored by the private sector;
The MIGA provides political risks guarantees that may accompany
an investment in an untested environment.
This project is a public good under the ownership of the Federal Ministry of Works
therefore; the World Bank Safeguard Policies are used. The World Bank has ten (10)
Safeguard Policies to reduce or eliminate the adverse negative effects of
development projects, and improve decision making.
With respect to this report (ARAP), the OP/BP 4.12 (Involuntary Resettlement) is
applied. The above-mentioned policy is reviewed in section 1.2 of the chapter 1 of
this report.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
25 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
3.2 Nigeria Regulatory Framework
With regards to management of the bio-physical environment throughout Nigeria, the
overall responsibility was held by the now defunct Federal Environmental Protection
Agency (FEPA), which was absorbed into the Federal Ministry of Environment (FMENV)
in 1999.
3.2.1 Federal Ministry of Environment (1999 Presidential Directive)
The Federal Environmental Protection Agency (FEPA) was established by Decree No.
58 of 1988 and subsequently amended by Decree 59 of 1992 with further amendment
by Decree 14 of 1999. FEPA was absorbed into the Federal Ministry of Environment
(FMENV) in 1999 by a presidential directive and its functions among others are now
the responsibility of the new Ministry. The FEPA Act has now been repealed in the
NESREA Act No 25 of 2007. Though the FEPA Act has now been repealed in the
NESREA Act No. 25 of 2007, the Regulations pursuant to it are still valid in Regulatory
terms.
3.2.2 The National Environmental Standards and Regulations Enforcement Agency
(NESREA) Act No 25 of 2007
The Agency, shall, subject to the provisions of this Act, have responsibility for the
protection and development of the environment, biodiversity conservation and
sustainable development of Nigeria’s natural resources in general and environmental
technology, including coordination and liaison with relevant stakeholders within and
outside Nigeria on matters of enforcement of environmental standards, regulations,
rules, laws, policies and guidelines.
NESREA mandate includes the establishment of federal Road air quality standards
and effluent limitations, protection of air and atmospheric quality; protection of the
ozone layer; control of the discharge of hazardous substances; inter alia and ensures
that all major development projects in Nigeria are subject to mandatory
Environmental Impact Assessment (EIA) pursuant to EIA Act. No. 86 (Decree No. 86) of
1992.
3.2.3 Environmental Impact Assessment (EIA) Act Cap 131 LFN 1992; This law makes it
mandatory to have an EIA study for any major development project likely to have
adverse effects on the environment and seeks to encourage the development of
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
26 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
procedures for information exchange, notification and consultation between organs
and persons when proposed activities are likely to have significant environmental
effects on boundary or trans-state or on the environment of bordering towns and
villages. The law prescribes the procedure for conducting and reporting EIAs.
3.2.3.1 Sectoral EIA Guidelines
In September 1995, FEPA (now Federal Ministry of Environment) published Sectoral EIA
Guidelines for Infrastructural Projects. The Guidelines are for any project that involves:
Coastal Development Project
Port and Harbour Development Project
Railways
Roads and Highways,
Airports
Urban development project
Domestic water supply and sanitation project
Electrification projects
3.3. Nigerian Urban and Regional Planning Law No 88 of 1992
Section 333 requires every developer of Land exceeding 4000 m2 or four floors to
submit a detailed EIA report to an appropriate Development Control Department in
the area of project location.
3.4. Land Use Act Cap 202 LFN 1990.
As contained in the Land Use Act of 1978, which was modified in 1990 all Land in
Nigeria is vested in the Governor of each state, and shall be held in trust for the use
and common benefit of all people. The administration of land area is divided into
urban land, which will be directly under the control and management of the
Governor of each state; and non urban land, which will be under the control and
management of the Local Government. The Governor of each state will have the
right to grant statutory rights of occupancy to any person for any purposes; and the
Local Government will have the right to grant customary right of occupancy to any
person or organization for agricultural, residential or any other purposes.
The rational for the Act was that dispute over land were resulting loss of lives and
properties; moreover, that the management and ownership of land needed to be
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
27 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
streamlined and simplified; and furthermore that citizens, irrespective of their social
status, need support to realize their aspirations owning a place where they and their
family can lead a secure and peaceful life. Therefore the twelve (12) sections found
to be relevant to the RAP purpose are hereunder stated.
i) Section 1: Subject to the provisions of this Act, all land comprise in the territory of
each state in the Federation are hereby vested in the Governor of each state
and such land shall be held in trust and administered for the use and common
benefit of all Nigerians in accordance with the provisions of this Act.
i) Section 2 (a): All land in urban areas shall be under the control and
management of the Governor of each state; and (b) all other land shall be
under the control and management of Local government within the area of
jurisdiction in which the land is situated.
ii) Section 5 (1): It shall be lawful for the governor in respect of land , whether or
not in an urban area (a) to grant statutory rights of occupancy to any person
for all purposes.
iii) Section 6 (1): It shall be lawful for a Local Government in respect of land not in
an urban area (a) to grant customary rights of occupancy to any person or
organization for the use of land in the Local Government area for Agriculture,
Residential and other purposes; (b) To grant customary rights of occupancy to
any person or organization for use of land for grazing purposes as may be
customary in the local government area concerned.
iv) Section 6 (3): It shall be lawful for a local Government to enter upon, use and
occupy for public purposes any Land within the area of its jurisdiction, and for
the purposes, to revoke any customary right of occupation on any such land.
v) Section 6 (5): The holder and occupier according to their respective interest of
any customary right of occupancy revoked under subsection (3) of this section
shall be entitled to compensation for the value at the date of revocation, of
their unexhausted improvement.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
28 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
vi) Section 6 (6): Where land in respect of which a customary right of occupancy is
revoked under this Act was used for Agricultural purposes by the holder, the
local Government shall allocate to such holder alternative land for use for the
same purpose.
vii) Section 28 (1): It shall be lawful for the government to revoke a right of
occupancy for overriding public interest.
viii) Section 29(1): If a right of occupancy is revoked, the holder and occupier shall
be entitled to compensation for the value at the date of revocation of their
unexhausted improvements.
ix) Section 29 (3): If the holder or occupier entitled to compensation under this
section is a community the Governor may direct that any compensation
payable to it shall be paid (a) to the community or (b) to the chief or leader of
the community to be disposed of by him for the benefit of the community in
accordance with the applicable customary law (c) into some fund specified by
the Governor for the purpose for being utilized or applied for the benefit of the
community.
x) Section 29 (4): Compensation under subsection (1) of this section shall be (a)
the land for the amount equal to the rent, if any paid by the occupier during
the year in which the right of occupancy was revoked, (b) Buildings, installation
or improvements thereon, for the amount of the replacement cost of the
building, installation or improvement, that is to say, such cost as may be
assessed on the basis of the prescribed method of assessment as determined
by the appropriate officer less any depreciation together with interest at the
bank rate for delayed payment of compensation and in respect of any
improvement in the nature of reclamation works, being such cost thereof as
may be sustained by documentary evidence and proof to the satisfaction of
the appropriate officer, (c) crops on land apart from any building, installation or
improvement thereon, for an amount equal to the value as prescribed and
determined by the appropriate officer.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
29 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
xi) Section 33(1): Where the right of occupancy of any developed land on which a
residential building had been erected is revoked under this Act, the Governor or
the Local Government, as the case may be may in his or its discretion offer in
lieu of compensation payable in accordance with the provision of this Act,
resettlement in any other place or area by way of a reasonable alternative
accommodation (if appropriate in the circumstance).
In the event of use of land for public interest, the Act specifies as follows:
That the government should resettle and/or compensate
occupants of land with Certificate of Occupancy (C of O); or
Issue notice to occupiers of land prior to displacement of land for
public project.
In practice, government does not compensate known rightful owners of
land/asset when the affected land/assets are located within the right of way of
utilities. Rather, the government enforces involuntary displacement by demolition
the structures and assets that are located within the land mapped for project.
3.5 Comparison between Land Law in the Federal Government of Nigeria and Bank
OP 4.12
The RPF also presented a comparison of the Land Laws in Nigeria with the World Bank
Policy. Whereas the law relating to land administration in Nigeria is wide and varied,
entitlements for payment of compensation are essentially based on right of
ownership. The Bank’s OP4.12 (Appendix 2) is fundamentally different from this and
states that affected persons are entitled to some form of compensation whether or
not they have legal title if they occupy the land by a cut-off date. However, as the
proposed Road Rehabilitation is to be funded by the World Bank, the principle of OP
4.12 is not negotiable and must be adhered to. As a result, the ARAP would adopt the
Land Use Act 1978 (modified in 1990) and where, there is conflict, the Bank OP 4.12
would take precedence. The comparison is presented in Table 4.1.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
30 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
Table 3.1: Comparison of Nigerian Land Use Act (1978) and World Bank’s OP 4.12
CATEGORIES OF
PAPS/TYPE OF LOST
ASSET
NIGERIAN LAND USE ACT WORLD BANK
Land Owners Cash compensation
based upon market value
Recommends land-for-land
compensation, or cash
compensation at replacement
cost.
Land Tenants Entitled to compensation
based on the amount of
rights they hold upon land.
Entitled to some form of
compensation subject to the
legal recognition of their
occupancy.
Land Users Not entitled to
compensation for land;
entitled for compensation
for crops
Entitled for compensation for
crops, for land replacement and
income loss compensation for
minimal of the pre-project level.
Owners of Non
permanent Buildings
Cash compensation
based on prevailing
market value
Entitled to in-kind compensation
or cash compensation at full
replacement cost including
labour and relocation expenses,
prior to displacement.
Owners of
permanent Buildings
Cash compensation
based on prevailing
market value
Entitled to in-kind compensation
or cash compensation at full
replacement cost including
labour and relocation expenses,
prior to displacement.
The ARAP for this bridge construction will be aligned with the World Bank Operational
Policy (OP 4.12) which indicates best practices to rehabilitation of livelihoods of
people affected by the implementation of the project. Hence, where there are gaps
between the Land Use Act (1978) and the World Bank Policy (OP 4.12), in regard to
compensation of PAPs, the World Bank’s Policy will apply since it is to fund the project.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
31 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
4.0 IDENTIFICATION OF PROJECT IMPACTS AND PROJECT AFFECTED PERSONS
4.1 Approach to Impacts and PAPs identification
Section two provided full details on impacts and PAPs identification which included
census/inventory survey and consultation with the PAPs. Consultation with the project
community and PAPs was continuous and started during the field survey on 12
October 2012 up to the extended cut-off date on 19th October 2012.
4.1.1 Road Corridor/Right of Way Re-consideration
Following the review of the initial submission by the ARAP Consultant in which the
starting and end points of the road were not clear, and in which the definition of ROW
was not well specified to reflect the Nigerian high way regulation the implementing
agency met with the design engineer and the ARAP consultant on the subject
matters. This was necessary to carry out the ARAP report based on the actual
scope/boundaries of the project. During the meeting, it was decided that in the new
design, the right of way (ROW) for the existing Enugu – Abakaliki Road which is 10m
from either side of the centre of the road has been exceeded in creating the
transition road and extensional 8m into the village land in order to grant NNPC a new
access to their water pumping facilities. The Consultant was asked to revisit the
inventory/census of PAPs based on this measurement.
4.2 Eligibility Criteria for Affected Persons
Any person who will suffer loss or damage to an asset, business, trade or loss of access
to productive resources, as a result of the project will be considered eligible for
compensation and/ or resettlement assistance.
The cut-off date for being eligible for compensation and/ or resettlement assistance
was the 15th October 2012, which is the last day during which the socio-economic
survey was completed.
The completion of the census represents a provisional cut-off date for eligibility for
resettlement assistance. Sufficient public awareness of the cut-off date was given to
the community through the Otukwu village chairman (Hilary Edeh) and his executives.
If there is a significant time lag between the completion of the census and
implementation of the RAP, resettlement planners should make provision for
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
32 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
population movements as well as natural population increase and expansion of land
use, which may include a repeat census.
Although concessions should be made for enumerator errors and omissions, as a rule
people moving into the project area after the cut-off date should not be entitled to
assistance.
Nevertheless individuals or groups who are not present at the time of registration but
who have a legitimate claim to membership in the affected community can be
accommodated. Such groups might include absent family members engaged in
migrant wage labor or nomadic pastoralists who use local resources on a seasonal
basis.
PAPs also include:
Those who have formal legal rights of land (including customary
and traditional rights recognized under the laws of the country);
Those who do not have formal rights to land at the at the time the
census begins but have a claim to such land or assets and become
recognized during the survey; as well as
Those who have no recognizable legal rights or claim to the land
they are occupying.
4.3 Proof of Eligibility
The PIU will consider various forms of evidence as proof of eligibility as stated in the
RPF, to cover the following:
PAP with formal legal rights, documented in the form of land title
registration certificates, leasehold indentures, tenancy agreements,
rent receipts, building and planning permits, business operating
licenses, and utility bills among others: unprocessed/unregistered
formal legal documents will be established in the ARAP.
PAP with no formal or recognized legal rights-criteria for establishing
non-formal, undocumented or unrecognized claims to eligibility
shall be established paying particular attention to each situation
and its peculiarities. Alternative means of proof of eligibility will
include
Affidavit signed by landlords and tenants;
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
33 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
Witnessing or evidence by recognized traditional authority,
customary heads, community elders, family heads and elders and
the general community.
However only PAPs enumerated during the baseline survey shall be eligible for either
the compensation or supplemental assistance. In other words the date of completion
of baseline survey (15th October 2010) is the cut-off date for receipt of compensation
or any assistance. Any new structures or additions to existing structures carried out
after the cut-off date and their occupants will not be eligible for compensation or
supplemental assistance.
4.4 Entitlement Policy
Since the project entails the construction of an alternate bridge beside an existing
one, we anticipate minor lands take; some relocation of facilities and displacement of
medium scale block industry.
On the above basis, project affected persons (PAPs) are mainly community people
whose economic trees in the portion of land to be used will be affected, NNPC whose
facilities will be relocated, PHCN whose electric lines will be relocated, sand miners
whose means of livelihood will be stopped, block molders who will be relocated,
economic trees and kiosks intercepts along the transition road. As a result, Project
Affected Persons (PAPs) would be entitled to the following types of compensation
and rehabilitation measures.
4.4.1 PAPs Losing Structures
Generally, all PAPs concerned in this project are without legal rights of
land use.
There will be no land compensation, but the structures and other
assets on land will be compensated as applicable to PAPs with legal
rights of land use.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
34 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
4.4.2 Facilities displaced from road corridors
These include all the PAPs whose kiosks, facility lines that intercepts the
transition route. PAPs will be paid their relocation/replacement value
for their assets to be removed.
PAPs will be compensated for livelihood restoration due to loss of
business days which will be determined by the expected number of
days of construction.
4.4.3 PAPs with loss of economic trees
Full compensation will be paid for the estimated market values of the
economic tree in at least two seasonal harvests.
4.5 Notification
All properties affected by the proposed civil works have been valued and assessed
according to laid down procedure.
Owners of affected properties have been notified in several ways. These included one
on one notification during the socio-economic survey, and also during public
consultation. A compensation valuation of all affected properties was carried out to
assess commensurable values.
4.6 Duration for Civil Works
Subsequently due to the proposed bridge construction, articulated vehicles and
trucks are to be diverted to an alternative road thus further reducing the load on the
deck, and hence settlement rate. The road is probably going to be closed to traffic
for the duration of construction works (estimated at 6 months minimum).
4.7 INVENTARY AND SENSUS OF AFFECTED ASSETS AND PAPs
A total of 20 persons/groups will be affected by the project including :
o 13 PAPs involving physical and/or economic displacement
o 7 PAPs involving temporal disturbance from location of business; in
which case a shift back from ROW will be required
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
35 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
The categorization and summation of affected assets and PAPs in the project areas is
presented as follows:
Category PAP’s by group Total
Otukwu
village
NNPC PHCN Block
industry
Sand
miners
PAPs for loss of
land
4 N/A N/A N/A N/A 4
PAPs for loss of
economic trees
6 1 NA NA N/A 7
PAPs for relocation N/A 1 1 1 1 4
PAPs for removal
of Kiosks
1 N/A N/A N/A 1 2
Security House,
gate & Fences
1
1 N/A N/A N/A 2
PAPs for removal
of Thatch house
N/A N/A N/A 1 N/A 1
Total 20
5.0 VALUATION AND COMPENSATION OF AFFECTED STRUCTURES AND PROPERTY
5.1 INTRODUCTION
Valuation of assets to be affected by the implementation of the project was
conducted using a general principle adopted in the formulation of the compensation
valuation which follows the World Bank’s Policy that lost income and asset will be
valued at their full replacement cost such that the PAPs should experience no net loss.
The asset valuation was conducted by a qualified multi-disciplinary team based on
the current market prices in the concerned state of project influence.
5.2 Method of Valuation for compensation
The method has been briefly described below:
Replacement Cost Method
The Replacement Cost Method, which is used in estimating the value of the
property/facility, is based on the assumption that the capital value of an existing
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
36 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
development can be equated to the cost of reinstating the development on the
same plot at the current labour, material and other incidental costs. The estimated
value represents the cost of the property as if new.
Land Resettlement
The World Bank OP 4.12 requires that displaced owners of land be provided with an
area of land equivalent to their displaced land. Land restoration should be in a
location that has similar value as the one displaced to the project.
Disturbance and Other Incidental Contingencies
Affected business premises which will have to close shop or be relocated will be given
compensation for loss of business time or assistance for transportation.
Affected Structures:
Immovable Structures/Property:
This consists of all structures/property that are not moveable (Immovable) such as
Fence and Economic Trees etc.
Moveable Structures/Property:
This includes Kiosks, Metal sign posts, electric poles and wires and Tables.
The PIU will arrange and make payment of estimated values to the beneficiaries. This is
to enable the PAP’s start arranging for alternative accommodation or resettle
elsewhere.
5.3 Category of Payments of Compensation
Compensation to Owners of Immovable Structures
Owners of Immovable Structures will be paid compensation that will be based on
assessed values of their properties. The compensation will be paid by the RSDT which is
the implementing agency.
Compensation to owners of structures will be based on the
cost of replacement of structure;
Income loss per day of the construction operation estimated
at 21 days. (This is subjectively the time it will take the Project
Affect Persons to move and adjust for business in an
alternative place.
cost of agricultural crops to be affected at full market price
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
37 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
5.4 Entitlement Matrix
Table 5.1: Entitlement Matrix showing categories of project affected persons, type of loss and compensation
CATEGORY OF PAP TYPE OF LOSS ELIGIBILITY CRITERIA ENTITLEMENTS
Property Owners
Loss of land
Holder of a title, leaseholder
Compensation at current market
price
Compensation at full replacement
cost value, mobility allowance and
disturbance
Loss of structure
Building permit, structure drawings,
three neighbor witnesses and
photographs (of informal properties)
Compensation for missed profit
Farmers
Loss of farm land
Evidence of ownership
Compensation at full replacement
cost value
Loss of agricultural crops
Lease contract, rental receipts, MOU
Compensation at current market
price of produce
Business tenant No loss of land
Lease contract, rental receipt, MOU Compensation for advanced lease
Loss of rental
accommodation
Loss of goodwill
Lease contract, rental receipts, MOU
Compensation for equivalent lease
and lost goodwill fee, mobility
allowance and disturbance
Residence owners Loss of land
Holder of a title, leaseholder Compensation for equivalent lease
Loss of structure Building permit, structure drawings,
three neighbor witnesses and
photographs (of informal properties)
Compensation at full replacement
cost value
Residence tenant Loss of rental
accommodation
Lease contract, rental receipts, MOU Compensation for advance rent
Lease contract, rental receipts, MOU Compensation for equivalent
accommodation or three months
lease, mobility allowance and
disturbance
Vulnerable Groups Comfort and Security Elderly, physically challenged, long
term sick, Female Household Head
Supplementary compensation to be
settled case by case
Squatters/encroachers Loss of use of land Three neighbor witnesses Supplementary assistance, mobility
allowance and disturbance
Public amenities Relocation of amenities Amenities in the Right of Way
(ROW)
Relocation cost
Religious sites (church) Loss of structure Holder of a title, leaseholder
Building permit, structure drawings
Compensation for equivalent lease
Compensation at full replacement
cost value.
5.5 VALUATION OF RESETTLEMENT/COMPENSATION AND ASSISTANCE COST FOR PAPs
Based on the Entitlement Matrix and Valuation procedures the total cost of
compensation and assistance is given in table 5.2 below.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
38 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
Table 5.2: Valuation of Compensation and Assistance Cost for Project Affected Persons
ALTERNATE BRIDGE NO 2 EMENE ENUGU PROJECT AREA
LOCATION NAME OF PAP IDENTITY
SIZE (m
2)
RATE REPLACEMENT COST AT BASE
YEAR
EXPECTED REPLACEMENT
COST
INCOME PER DAY
DAYS INCOME* DAY
COMPENSATION SUM(N)
SUB-TOTAL
EMENE HILARY UDEH ECONOMIC TREES
0 0 1,500 21 31500 31500
EMENE CHRISTOPHER UGWUEGU
LAND, ECONOMIC TREES
0 0 1,000 21 21000 21000
EMENE OGBONNA OKOLO
LAND, ECONOMIC TREES
0 0 1,500 21 31500 31500
EMENE JUDE OKWOR
LAND, ECONOMIC TREES
0 0 1,500 21 31500 31500
EMENE CHIKA UGWU
LAND, ECONOMIC TREES
0 0 1,500 21 31500 31500
EMENE PATRICIA ANYANWU
RELOCATION OF KIOSK
0 0 1,000 21 21000 21000
EMENE
PETER ONUCHUKW NOMEH
ECONOMIC TREES
0 0 500 21 10500 10500
EMENE NWAOGU NDUBUISI
ECONOMIC TRESS
0 0 500 21 10500 10500
EMENE NNPC RELOCATION 0 0 5000 21 105000 105000
EMENE PHCN RELOCATION 0 0 7000 10 70000 70000
EMENE AFRICAN TINKERS RELOCATION
0 0 3,500 21 73500 73500
EMENE FABIAN EDEH SAND MINER
0 0 2,000 21 42000 42000
Total 479,500
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
39 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
6. INSTITUTIONAL ARRANGEMENT AND RESPONSIBILITIES
6.1 Introduction
The major institutions that are involved in the Resettlement process are
the Road Sector Development Team- Federal Ministry of Works, the World
Bank, and the District Resettlement Committee (DRC) in each project
designated area.
6.2 Institutional Arrangement
The roles and responsibilities of the institutions regarding Resettlement
Implementation and Grievance redress is as per table 5.1.
Table 6.1: Institutional Arrangement and Responsibilities for ARAP
S/N
o
Stakehold
ers/
Institutions
Responsibilities
1 RSDT Establishment of District Resettlement Committee (DRC).
Ensuring that the project conforms to World Bank
safeguard policies, including implementation of the
Abbreviated Resettlement Action Plan (ARAP), as
required.
Engaging the services of contractors and consultants to
carryout preparation and implementation of ARAP and
subsequent engaging the service of external monitors for
the ARAP implementation.
Approval of payments to consultants for ARAP activities
carried out under the project.
Internal monitoring and evaluation of ARAP activities.
Preparation of quarterly and annual progress reports on
ARAP implementation.
Submission of Reports to RSDT, and World Bank for
review.
2 World
Bank
Overall responsibility of ensuring that the OP 4.12 is
complied with in the ARAP.
Responsible for the final review, clearance and approval
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
40 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
of the ARAP.
3 Monitorin
g and
Evaluation
Officer
from the
RSDT
Ensure that there are sufficient resources (time, money and
people) to supervise the implementation of compensation
Ensure that any changes during implementation process
that have significant environmental or social impact are
communicated to the RSDT in time and advice on actions
to be taken and costs involved.
Ensure that the PIU is sufficiently informed on monitoring
results.
4 Social
Safeguard
Specialist
from RSDT
Has a critical role to play especially in the implementation
of the action plan of the social mitigation measures.
Responsible for the implementation of Resettlement Plan
and social development. Will coordinate with the District
Resettlement Committee (DRCs)
5 District
Resettlem
ent
Committe
es (DRCs)
Being responsible for guiding compensation and
resettlement activities in district areas.
Form a survey team to carry out Detailed Measurement
Survey (DMS) for affected PAPs and assets; finalize DMS and
Entitlement forms for each PAP.
Checking the unit prices of compensation as used in RP,
suggestions for adjusting the unit prices in conformation with
market prices/replacement costs (if required) to Project
Implementation Unit for approval.
In co-ordination with RSDT, organize meetings with PAPs,
communal authorities disseminate copies of Resettlement
Information Booklet (RIB) and entitlement forms.
Based on the policy and proposed process/mechanism in
ARAP, the DRCs prepare the detailed implementation plan
(quarterly) and together with RSDT pay entitlements to PAPs
and implement for other activities in a timely manner.
Settling the complaints and grievances raised by
complainants and suggest solutions for the outstanding
issues to responsible institutions for improving of the ARAP
implementation.
Organise seminars to disseminate the ARAP report to
relevant stakeholders, communities, etc.
Assisting local people in overcoming the difficulties during
the implementation period.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
41 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
6 Selected
independ
ent
NGO
Will be a grass root level worker, actually dealing with the
PAPs. Develop rapport with the PAPs, help in skill upgrading
where required, and help obtaining benefits of entitlement
framework and appropriate Government programmes.
Facilitate in negotiation, if required.
7 Project
Affected
Persons
(PAPs)
Giving their own opinions and, or support on alternative
project designs during Focused Group Discussion,
Support Community- based developmental project.
6.3. Grievances and Appeals Procedure
The objective of a proposed mechanism for complaint is to respond to
the complaints of the PAPs in a timely and transparent manner. The
mechanism is designed to be easy, transparent and fair. The procedures
are proposed as follows;
At the first stage, PAPs will register their complaints and grievances to
the grievance redress committee which will have to provide a written
response to the PAPs, within fifteen calendar days of receiving the
complaint.
If the PAPs are not satisfied with the decision of the DRC, the PAPs
should present the case to the PIU of RSDT within fifteen calendar days
of receiving the written response from the DRC authorities. The
decision of the DRC should be sent to PAPs by no later than fifteen
calendar days of receipt of the PAPs appeal.
If the PAPs are not satisfied with the decision at the second level, the
case can be submitted for consideration to the district court or to
Provincial Peoples Committee.
PAPs will be exempted from all administrative and legal fees.
6.3.1 Grievance Redress Mechanisms
A Grievance Redress Committee will be set up by RSDT to address
complaints from ARAP implementation. This committee will be directly under
the RSDT-PIU and its members will include legal and accounts
representatives of RSDT, and the legal expert from the ministry shall be the
secretary. The functions of the Grievance Redress Committee are:
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
42 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS.
Provide support to PAPs on problems arising from loss of private properties
and business area.
Record the grievance of the PAPs, categorize and prioritize the
grievances that need to be resolved by the committee; and
Report to the aggrieved parties about the developments regarding their
grievances and the decision of the project authorities.
The main objective of this procedure will be to provide a mechanism to
mediate conflict and cut down on lengthy litigation, which often delays
such infrastructural projects. It will also provide people who might have
objections or concerns about their assistance, a public forum to raise their
objections and through conflict resolution, address these issues adequately.
The committee will provide ample opportunity to redress complaints
informally, in addition to the existing formal administrative and legal
procedures. However, the major grievances that might require mitigation
include:
PAPs not listed;
Losses not identified correctly;
Inadequate assistance;
Dispute about ownership;
Delay in disbursement of assistance and improper distribution of
assistance.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
43 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
7. MONITORING AND EVALUATION
7.1. Internal Monitoring
Implementation of the Abbreviated Resettlement Action Plan (ARAP) will
be regularly supervised and monitored by the Environmental Officer /
Social Officer in coordination with staff of the RSDT - PIU. The Social Officer
in RSDT will be directly responsible for the implementation of ARAP.
The findings will be recorded in quarterly reports to be furnished to the
RSDT - PIU, and the World Bank
7.1.1 Tasks of the Monitoring and Evaluation Officer (Social Officer)
Verify that the baseline information of all PAPs have been carried out
and that the valuation of assets lost or damaged, and the provision of
compensation, resettlement and other rehabilitation entitlements has
been carried out in accordance with the provisions of this policy
framework and the respective inventory and ARAP.
Oversee that the ARAPs are implemented as designed and approved.
Verify that funds for implementing the ARAPs are provided to the
respective local level (district) in a timely manner in amounts sufficient
for their purposes and that such funds are used by the local authorities
in accordance with the provisions of the ARAP.
Ensure the identification and signature/thumb print of PAPs before and
during receipt of compensation entitlements.
Record all grievances and their resolution and ensure that complaints
are dealt with in a timely manner.
7.2. Independent Monitoring
An independent agency will be retained by the RSDT to periodically carry
out external monitoring and evaluation of the implementation of the
ARAP. The independent agency will be either an academic or research
institutions, non-governmental organizations (NGO) or an independent
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
44 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
consulting firm. They should have qualified and experienced staff and
their terms of reference acceptable to World Bank
In addition to verifying the information furnished in the internal supervision
and monitoring reports, the independent monitoring agency will visit a
sample of 10% of the Project affected Population in each relevant district,
six months after the ARAP has been implemented to:
Determine whether the procedures for PAPs participation and delivery
of compensation and other rehabilitation entitlements have been
done in accordance with the Policy Framework and the respective
ARAP.
Assess if the ARAP objective or enhancement or at least restoration of
living standards and income levels of PAPs have been met.
Gather qualitative indications of the social and economic impact of
project implementation on the PAPs.
Suggest modification in the implementation procedures of the ARAP,
as the case may be, to achieve the principles and objectives of its
policy framework.
The terms of reference for this task and selection of qualified agency will
be prepared by the RSDT-PIU in collaboration with the World Bank at the
beginning of project implementation stage.
7.2.1. NGO Participation in ARAP
An NGO/consulting firm will be contracted by the RSDT to support the detailed design
and implementation of the various proposed schemes and measures mentioned
above or any additional acceptable schemes that would ensure proper treatment of
the PAPs. The NGO /consulting firm will also be responsible for periodical reporting on
progress and challenges facing implementation
The NGO will be recruited for the implementation of ARAP. The selected NGO will be
trained and have skills in resettlement policy and practices and will be based locally
with sufficient manpower and leadership. The ARAP Consultants will play a key role in
this venture. The following criteria can guide in assessing the NGOs suitability and
capabilities for assisting in the resettlement work. The NGO should:
Be from the project-affected area or have prior work’s experience in
the area;
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
45 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
Have a good track record in terms of program planning and
implementation in areas like rural development, poverty, gender and
environmental issues;
Have appropriate staff with technical and social skills in resettlement,
community development and participation, including familiarity with
the local language(s) and customs;
Be registered with the government as an NGO with good standing
and sound financial condition for project implementation purpose;
and
Not be involved with any political party or religious groups directly or
indirectly.
Involvement of NGOs in resettlement projects will be particularly useful in the
following areas:
• Gathering and sharing information and avoiding potential problems;
• Mobilization and motivation to PAPs to form community based organizations;
• Planning and implementing income-generating schemes;
• Developing information campaigns and community participation;
• Strengthening local institutions and community self-reliance; and
• Delivering services to hard-to-reach communities in a more efficient and cost-
effective manner.
RSDT will engage the services of the NGOs to partner in the ARAP implementation and
to work closely with the DRCs.
Key tasks that are to be carried out by the partnering NGOs will include:
Establishing rapport with PAPs, between the PAPs, the DRCs and RSDT for
improving cooperation and coordination;
Formation of CBOs to organize the PAPs and promote their participation;
Assessing the level of PAP skills and efficiency in pursuing economic activities,
identifying the scope and necessity for training, and conducting such programs
to improve the efficiency and/or to impart new skills to PAPs;
Assisting PAPs in receiving resettlement and rehabilitation entitlements due to
them, particularly compensation and/or assistance for land and property losses;
Providing proper guidance to PAPs for making the maximum use of benefits
under the Resettlement policy provisions, and motivating them for the same;
Helping the PAPs to derive benefits from development programmes;
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
46 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
7.2.1. Implementation Schedule
Table 7.1 below summarizes the implementation schedule of the Abbreviated
Resettlement Action Plan by phase, responsibilities and completion time for the
alternate bridge construction in Emene.
Table 7.1: Summary of Responsibility for Implementation of Abbreviated
Resettlement Action Plan
ROAD
PROJECT
CYCLE
PHASE ACTIVITIES RESPONSIBILITIES
PLANNING
Scoping
and
Screening
Initial site visit &
consultations.
Identification of
Resettlement and
Social issues
Application of
safeguard policies
Categorization
Action plan
Screening Report
WB No-Objection
Consultant;
Supervision by
RSDT- PIU
DESIGN Preparation
of ARAP
and
consultatio
ns
Draft ARAP
Consultations
WB No-Objection
Consultant;
Supervision by
RSDT -PIU
Disclosure Disclosure of ARAP
locally & to WB Info
Shop
RSDT –PIU
World Bank
Finalization
and
Incorporati
on
Final version of ARAP
Incorporation of
ARAP into contract
documents
WB No-Objection
Consultant;
Supervision by
RSDT –PIU
EXECUTION Implement Implementation Contractors
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
47 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
ation and
monitoring
Monitoring &
reporting on
environmental and
social mitigation
measures
Monitoring and
reporting of
Resettlement and
livelihood issues
Supervision by
RSDT/ and the
community
OPERATION
S (POST-
IMPLEMENT
ATION)
Operations
and
maintenan
ce
Maintenance
Monitoring and
reporting of
Resettlement and
social livelihood
issues
Contractors
Supervision by
RSDT-PIU/ and the
community
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
48 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
8. COMPENSATION FUNDING ARRANGEMENT AND TIMETABLE
8.1. Budget for Resettlement activities related with the Proposed Project
Based on the preliminary valuation of affected assets and affected
people presented in Table 4.3, the budget for resettlement activities
associated with the implementation plan of the ARAP is as follows:
8.2. World Bank-RSDT
The timetable and schedules for the completion of the Abbreviated
Resettlement Action Plan can be seen in Table 8.1 below. The ARAP has
to be completed and PAPs adequately compensated before operation
in the designated project area.
Table 8.1: Timetable for Abbreviated Resettlement Action Plan
No. Activities Completion time
CUT OFF DATE 15th October 2012
1. Completion of ARAP- draft document October 2012
2. Submit to RSDT –PIU, and the World Bank October 2012
3. Disseminate ARAP to zones and districts for
comments
November 2012
4. Return of Comments from Zones and World
Bank
December 2012
4. Update of Comment into Final ARAP
Document
December 2012
5. Submission of Final ARAP Document December 2012
6. Advertisement in Two Local Newspapers in
Country
January
2013
7. Posted in the World Bank Info Shop January
2013
8 Commencement of ARAP February 2013
6 Completion of ARAP February 2013
7 Commencement of civil work February 2013
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
49 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
8.3 Training Needs
Based on the assessment of the institutional capacities of the RSDT for the ,
implementation of the ARAP, it is recommended that RSDT Contract Consultant
to provide training and operational support to the project implementation unit
(PIU) and other agencies involved in the ARAP implementation. The training
needs for the responsible institutions are identified in Table 8.2.
Table 8.2: Recommended Training and Awareness
Item Description Course Content Target Estimated
Amount(N)
Training &
Awareness
Involuntary
Resettlement
and
Rehabilitation
1. Principles of
Resettlement
Action Plan
2. Monitoring &
Evaluation of
RAP/ARAP
Implementat
ion
3. Conflict
Manageme
nt and
Resolution in
RAP/ARAP
1. PIU-RSDT
2. FMW
Conflict redress/management committee members
200,000
Sensitization
and
Awareness on
ARAP process
3. Community
representative
officers
4. PIU-RSDT Officer
100,000
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
50 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
9. PUBLIC CONSULTATION
9.1 Introduction
Public consultation is considered as a best practices measure for project
sustainability by World Bank and other international development partners. It is
pertinent as a process of informing the community of the need for sitting a
project in their domain, the scope and the need for the community to own and
safeguard the project as beneficiaries and stakeholders. It also affords an
opportunity for input and feedback information, aimed at strengthening the
development project and avoiding negative impacts or mitigating where they
cannot be avoided.
9.2 Public Consultation Process
Consultation was done at two levels, viz community level and project affected
persons level. The following process guided the public consultations:
The Social safeguard team first identified the built up areas, particularly, the
areas with potentials for involuntary resettlement.
Name of village, the administrative organization and leadership structure
were sought, and subsequently, a visit was made to the leaders and/or
representatives of the Otukwu village Emene particularly to the groups that
PAPs belong.
Public forum with stakeholders on the project matter
Identification of PAPs and their social-economic baseline
Inventory of PAPs and affected assets
9.3 Overview of Public Consultations Programme
9.3.1 Otukwu Village- Emene Public Consultation.
Day and Time: The public consultation with the Otukwu village Emene held at the
site in order to be exact on the affected properties with the executives and PAP’s in
attendance. The meeting was held on the 12th October, 2012 by 10.30am.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
51 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
Consultation & enumeration of the items to be
affected by the 8m encroachment with the
Otukwu village exco & PAP’s
ARAP Consultant with the Aim Engineering
Design Consultants & RSDT – ESE Engr.
Fidelis Anokwu monitoring the consultation
Fig 9.2: Public Consultation with Otukwu village-Emene
Participation: 16 people participated in the forum (see list in Table 9.2).
In participation were the leaders of the Otukwu village, farmers association, and
mineral miner’s representative.
Concerns: The people were happy for the alternate bridge project. They informed
that the affected piece of land is very strategic because of its high fertility for
agriculture. They also lamented on what is going to be the fate of sand miner’s from
the Ekulu River which has been their source of livelihood for a long time now. They
raised the following concerns:
That the government should be quick with the bridge construction to
save lost of life from the dilapidated existing bridge,
Government should engage their youths in employment even as
casual labourers in the proposed bridge and road construction.
That practical alternative in the form of by-pass be constructed where
feasible to enable the community’s movement during project
operation phase. This request for alternative bypass was made clear to
PAPs as being outside the project competence and should be
channeled to the State government through the local council.
It was also found that the PAPs along the transition road corridor have
some of them as widows who have got that land as the only
inheritance.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
52 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
The consultant asked the community leaders never again to rent the
road to any vendor for trading activity; and this was happily received.
Recommended Action: It is recommended as follows:
That a workable time line be given to PAPs for early evacuation of
belongings by December 2012,
That a notification board indicating the period of work on corridor
and bridge be provided by the contractor by December 2012,
That the resettlement committee should ensure transparency in
dispensing compensation benefits, and
That contractor should show professional standards and social
responsibility during bridge construction by providing temporary
access way so that communities and commuters are not hindered
from going about their normal businesses.
That contractor should put in place appropriate safeguard measures
and signal words to prevent pubic intrusion into construction work
areas.
That site specific Environmental Management Plan is prepared by the
contractor to mitigate environmental impacts by January 2011.
Table 9.2: Public Consultation Meeting at Otukwu village- Emene on 12/10/2012
S/N Name Gender Contact
1 Hon. Hilary Edeh C M 08060375581 President
2 Mr. Christopher Ugwuegu M 07067196319 PRO
3 Mr. Ogbonna Okolo M 08077581217
4 Mr Jude Okwor M 08032155666
5 Mrs. Pamela Edeh F 08064094376
6 Mrs. Oby Okwor F 08067631552
7 Mrs. Chika Ugwu F 08157012568
8 Mrs. Peace Okolo F 08038312920
9 Mrs. Patricia Anyanwu F 07036430474
10 Mrs. Patricia Okeke F 07067199103
11 Miss Elizebeth Afer F 08165463829
12 Chief Richard Okwor M 08033372118
13 Mr Fabian Edeh M 08064082572
14 Mr Francis Edeh Ogbu M 08165057637
15 Mr Peter Onuchukwu Nomeh M 07065397701
16 Mr Ndubuisi D. Nwaogu M 08069110402
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
53 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
REFERENCE
International Finance Cooperation (IFC), Handbook for preparing a
Resettlement Action Plan.
Land Use Act (1978), Federal Republic of Nigeria.
Resettlement Action Plan (2007) for the Dualization of Enugu-Abakiliki-Ogoja-
Ikom Road, African Development Bank
Road Sector Development Team (2010), Engineering Design of Rehabilitation of
Enugu-Abakiliki, Ogoja Junction-Ikom Road
World Bank (2001), Operational Policies: Involuntary Resettlement OP.4.12 and
Annex.
World Bank (2000), Resettlement and Rehabilitation Guidebook, Washington DC
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
54 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
Appendix 1: Minute of the meeting for the construction of the Bridge at km 7+350 with the Stake
Holder
MINUTES OF THE FOURTH MEETING WITH THE FEDERAL CONTROLLER OF
WORKS, HOUSING & URBAN DEVELOPMENT HELD AT FEDERAL SECRETARIAT,
INDEPENDENT LAYOUT, ENUGU ON TUESDAY 31ST
JULY, 2012,
1.0 ATTENDANCE:
1.1 Engr. Joe Onyejekwe …………. Fed. Controller of Works
1.2 Engr. Leonilo Q. Tavera …………. CRE (Aim Consultants Ltd)
1.3 Engr. Fidelis Anokwu …………. ESE, RSDT
1.4 Engr. Michael Feyisola ………… Snr. Structural/Bridge Engineer (AIM Consultants Ltd)
1.5 Surv. Isaac Eluma …………..Snr. Surveyor (AIM Consultants Ltd)
1.6 Engr. Steve Emefu ------------- Engr. Steve Emefu (Multiphase consultant Ltd)
1.7 Engr. Fouad Sarraf ………….. AM/PM (Setraco Nig. Ltd)
ITEM DESCRIPTION ACTION
2.0
2.1
2.2
OPENING PRAYER / ADDRESS BY CONTROLLER
The meeting commenced by 10:45am with an opening prayer by Engr.
Michael Feyisola followed by an apology by the Federal Controller of
Works for starting the meeting late. Aim consultants ltd’sER inevitable
absence was also presented, before the review of the minute of the
previous meeting.
The agenda for the meeting were:
1. Review of the minutes of the previous meeting.
2. Surveyor’s update on bridge settlement at km 7+350
3. Deliberations
4. AOB
3.0
3.1
3.2
REVIEW OF MINUTS OF PREVIOUS MEETING
The minutes of the last meeting was read by the minuter, Engr. Michael
Feyisola and thereafter reviewed.
Observations:
The following observations were made and correction effected.
a. Item 2.2, first line, “was instead of were”
b. Item 6.2, last line, “refusal depth instead of refusal stage”
c. Item 8.12, last line, “sub-soil test instead of soil test”
d. Item 8.12, third line, “hydraulic studies instead of hydraulic test”
e. Item 8.14, first line, “Nunkai instead of Dunken”
f. Item 8.15, second line, “Refusal Depth instead of refusal point”
g. Item 8.21, last line, “refusal state instead of refusal load”
h. Item 8.29, the omission of ‘was’ in the second line.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
55 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
i. Rehabilitation portion instead of rehabilitated portion in the third
line of the addendum to item 8.27.
4.0
4.1
4.2
4.3
4.4
4.5
4.6
4.7
SURVEYOR’S UPDATE ON BRIDGE SETTLEMENT AT KM
7+350
The Controller requested the Surveyor to give an update report on the
monitoring of the bridge settlement at km 7+350.
The Surveyor stated that up till July 24th
, 2012, they have been recording
an average of 2mm settlement per day which sounded very alarming.
The CRE suggested that, because of this alarmic rate of settlement, the
jacking of the deck should be carried out immediately, otherwise the
leveling of the depressed portion be filled with asphaltic materials to
reduce the force of impact by vehicles.
It was also suggested that the surveyor should by himself cross-check the
information (levels) on the settlement submitted by the Setraco contractor.
The Controller also emphasized that the Surveyor should confirm the
correctness of the levels forwarded by the field men of the contractor and
inquired if their survey equipment is in good condition.
The Surveyor confirmed the efficiency of the survey equipment used to
monitor the settlement of the bridge at km 7 + 350
The Controller stated that, with the latest information at hand as regards
the settlement of the bridge at km7+350, at the rate of 2mm per day which
is very alarmic, he will have to travel to Abuja by Friday 2nd
August,
earlier than schedule to inform the FMW H/Q.
5.0
5.1
5.2
DELIBERATIONS
The Controller reminded the meeting that, it was agreed in the last
meeting that the estimation and costing of the repairs and jacking up of
the deck should be brought forward by the nominated consultant to fast
rack the solution.
RSDT stated that, information reaching him from their head office stated
that Setraco should come forward with their own proposal as regards the
repairs to be carried out on the bridge.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
56 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
Setraco Nig. Ltd, agreed that, they have received the BOQ submitted by
the Nominated Consultant,Etteh Aro & partners for both repairs and
jacking up of the 2x20m span bridge deck at ch.7+350 from Aim
Consultants Ltd and promised to forward it to their Head Office with
explanation on the need for the document to be treated urgently.
The Controller asked the RSDT, if the on-going Enugu-Abakaliki Road
project accommodates the cost of executing, the nominated consultant
submissions, even if it is only the Jacking up of the deck.
RSDT stated that, though the project contains contingency, it is left for
their management to decide in view of the fact that there is no savings in
the project and if there is any as gathered from abakaliki end, it would be
used to augment the sections earmarked for asphaltic overlay,
rehabilitation or reconstruction after the rescoping of the works and in
particular the high traffic areas(where trailer parks). Noting also that there
was no intervention for the first 10km by the first consultant which had
also been taking care of by Aim consultant’s ltd. Nevertheless RSDT
wants Setraco to submit their quotation.
Aim Consultants Ltd stated that the project, is encouraging Setraco Nig
Ltd to submit their quotation and that the RSDT could as well wanted
other Contractor like Arab Contractor on the Dualization to also bid for
the bridge works if warranted.
The controller asked RSDT, if their Head Quarters is aware of the
deliberated situations to which the ESE answered in affirmative and.
The Controller inquired from the Contractor that with the urgency
attached to the situation at hand, how soon they could submit their pricing
of the BOQ.
Setraco Nig Ltd stated that, due to their company’s policy, they cannot
say exactly when but will as a matter of urgency forward the informations
to their management and explain the urgency attached to them, since it is
their tender department that handles such proposals.
The CRE was of the opinion that, the contractor could ask to speed up the
pricing for the jacking up aspect of the bill because of the urgency to
avoid any disaster.
The Controller wanted Setraco Nig Ltd to confirm the jacking up
technology relative to the nominated Consultant’s submission based on
their experience.
Setraco Nig Ltd stated that, their firm have in the time past done similar
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
57 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
5.13
5.14
5.15
5.16
5.17
5.18
5.19
5.20
5.21
projects and in fact they did the jacking of the Okoso bridge that is being
referred to in the deliberations and elaborated on what they did at okoso in
relation to the present situation. As regards the submission of the
nominated consultants, it will be looked into and if there is any short
coming, their head office will look into it.
Aim Consultants Ltd suggested that as a matter of urgency, traffic road
signs should be positioned accordingly at the approaches of the bridge
along with the provisions of the speed breakers and also speed up the
jacking up process.
Setraco agreed to talk to his supervisor to install the speed breakers 5m
away from the bridge approaches and increasingly in height progressively
from the first climb at 20 meters interval as agreed at the meeting, before
the end of the week .
RSDT & CRE, agreed that there is provision for traffic signs in the on
going contract.
The Controller reminded Aim Consultants to furnish his office with the
up-dated progress report of the on-going Enugu-Abakaliki Rehabilitation
project.
The Controller also inquired whether there are challenges mitigating
against the smooth execution of the project to which the consultant replied
there’s none that is beyond the control of the project.
The Controller wanted to know, to which extent has the issue of the
reconciliation of the levels at the transition between the dualization and
the on-going rehabilitation reached.
Aim Consultant Ltd stated that, they have met with the state consultant,
Multiphase consultants. Ltd alongside with the Arab Contractor’s
Surveyor and Setraco Nig. Ltd Surveyor on previous day of the meeting,
to exchange information regarding the reconciliation of levels via bench
marks and that the co-coordinating of the levels is on-going since gps was
used for the enugu-abakaliki project while they used automatic level.
The Controller wanted to know whether the issue of the new bridge
location/alignment was discussed but the Enugu state consultant
responded that, such is not in their brief otherwise they needed to be
instructed by the appropriate authority before embarking on that.
The state consultant however promised on the request of the controller to
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
58 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
5.22
5.23
5.24
5.25
5.26
5.27
5.28
5.29
5.30
5.31
5.32
discuss the issue of the new bridge location and alignment with the Hon.
Commissioner through his director.
And it was agreed that, discussion regarding the above is necessary in
view of the situation of the on-going development along the road even if it
is just for the state team to fly their levels and extend their alignment to
the bridge point at km 7+ 350 .
The issue of sensitization of the public as regards the traffic diversion and
the stoppage of the dredging and quarrying around the bridge was raised.
The Controller stated that, it is unfortunate that the EMW representative
has not been totally committed in the deliberations and of course was not
present in the day’s deliberations to brief the meeting.
The state consultant stated that, he will inform his principal regarding the
sensitization and quarrying around the bridge who may in turn influence
the talking when meeting with the Hon. Commissioner for works.
A rigorous deliberation on the workability of the submission of the
nominated consultant was embarked upon at the instance of the controller
based on the (assumption) that the submission of the nominated consultant
cold not be worked on by the contractor .
There were posers on whether the angle of barter of the existing piles and
the distance in between them will allow for the installation of new piles as
regards the nominated consultant‘s submission.
The question is how the contractor sinks new piles, if the existing ones are
not removed.
The contractor is to come up with their own proposal and the pricing of
the BOQ given to them.
After a long session of brainstorming regarding the practical execution of
the submission of the nominated consultant, the controller suggested that
the contractor should go back to site and work out the barter influence of
the piles and possibly come up with bigger sizes of piles to avoid the
influence.
Inclusion of additional piers at 10m-20m-10m distance was considered.
Setraco observed that, if the length of span changes, it would affect the
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
59 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
5.33
5.34
5.35
5.36
5.37
5.38
5.39
5.40
5.41
load on abutment.
The Contractor stated that, once there is a change in the position of any of
the piles, definitely others would change and also by affecting the length
of the beams, the abutment will also be affected.
A phone call was made to Etteh Aro & partners by ESE-RSDT, that
deliberation was going on regarding their submissions. And what could be
their opinion on how to construct the bridge if new piers and piles are to
be in place. Etteh Aro & partners promised to call back.
Multiphase consultant believed, that ette aro & partners could not be
blamed for any shortcoming in their submission because the time given to
them was too short and more or less a fire brigade approach.
RSDT stated that etteh aro & partners had earlier in the previous meeting
claimed that they have prepared the costing and promised to forward such
to the controller, which was corroborated by Aim consultants Ltd.
A phone call was also made to Setraco bridge department by the Area
Manager in Lebanese language and he reported to the meeting that,
Setraco confirmed that it is possible to execute the submission of the
nominated consultants if there is space not less than 1.0m between the
existing piles which of course is inevitable according to their contact on
phone.
It was discovered that the beme submitted by Etteh Aro & partners was in
adequate by not accommodating an item for the removal of existing pier,
piles and superstructure as portrayed in the summary and was relayed to
them on phone.
Etteh Aro & partners promised through the phone, to forward the missing
items in their BOQ to ESE-RSDT for onward delivery to the contractor.
Setraco Nig. Ltd should peruse the documents from the nominated
consultant and note their observations vis-à-vis any omissions and return
with their own pricing bearing in mind the sufficiency of the tender.
`The meeting agreed that, the contractor should concentrate firstly on
jacking up of the deck and the addendum to be sent by Etteh Aro &
partners to them as soon as collected by the RSDT for pricing on the
repairs.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
60 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
6.0
6.1
6.2
6.3
AOB
The controller wanted the secretary (minuter) to be forwading text
messages to all involved as a reminder before the meetings but the
minuter confirmed that this is always done by the ER, through e-mail.
Though the controller still prefer phone messages as some people don’t
asses their e-mail regularly.
The adjournment of the meeting, was moved by surveyor Isaac Eluma and
supported by Engr steve
The meeting came to an end by 12.50pm with a closing prayer by engr
steve and the date for the next meeting will be Tuesday 14th
August, 2012
PREPARED BY : Engr Michael Feyisola
CHECKED BY : Engr Dele Betiku
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
61 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
MINUTES OF THE 5th MEETING WITH THE FEDERAL CONTROLLER OF WORKS,
HOUSING & URBAN DEVELOPMENT AT THE FEDERAL SECRETARIAT,
INDEPENDENCE LAYOUT, ENUGU ON MONDAY 28TH
AUGUST, 2012.
1.0 ATTENDANCE: Engr. Joe Onyejekwe ………… .Fed. Controller of works
Engr. Dele Betiku ………….Team Leader (AIM Consultants Ltd)
Engr. Leonillo Tavera ……………CRE (Aim Consultants Ltd)
Engr. Fidelis Anokwu …………RSDT Site Engineer
Engr. Archibong Nkposong …………..Partner (Etteh Aro & Partners)
Engr. Paul Amula …………..ACRE (FMW, Enugu)
Ewe him Chuka (Mrs) …………..Sec. (FMW, Enugu)
Engr. Michael Feyisola ………… Snr. Structural/ Bridge Engineer (AIM Consultants Ltd)
Engr. Isaac Eluma ………… …Snr. Surveyor (Aim Consultants Ltd)
Dr. R. Chaudhuri …………. ...Technical Director (Setraco)
Engr. Ali Hachew …………… .Technical Manager (Setraco)
Engr. Girma Feleke ………………QA/QC Engineer (Setraco)
Engr. Branco Koncarevic ……………..Project Manager (Setraco)
ITEM DESCRIPTION ACTION
2.0
2.1
OPENING PRAYER/OPENING REMARKS BY THE
CONTROLLER
The meeting commenced at 10:50 am with an opening prayer by Engr.
Michael Feyisola, followed by a welcome remarks and call for
introduction by the Federal Controller of Works, Engr. Joe Onyejekwe.
The introduction of the attendees was done.
2.2 The agenda for the meeting were:
Opening Prayer.
Remarks by the Controller/Introduction of the attendees.
Review of previous Minutes of Meeting.
The Engineer’s Representative brief.
Setraco Preliminary Report.
Nominated Bridge Consultant Report.
Aim Consultants comments.
Deliberation.
Resolution.
AOB
Closing Prayer.
3.0
3.1
REVIEW OF MINUTES OF PREVIOUS MEETING
The minutes of the last meeting was reviewed and the motion for
adoption was moved by Engr. Leonilo Tavera and seconded by Engr.
Fidelis Anokwu after the observation by the Controller to add the
surname of Engr. Steve to read Engr. Steve Emefu.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
62 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
4.0
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
THE ENGINEER’S REPRESENTATIVE BRIEF.
The Controller refered to the E-mail earlier sent to him by the ER
regarding the reports of the visits of the bridge experts that visited the
bridge location at ch. 7+325 from Setraco head office and requested the
ER to brief on the outcome of their visit because he was worried on the
tone of the mail which was alarmic.
The ER who formally welcome Dr. Chaudhuri and thanked him for his
presence, stated that it was noticed during the visit of Setraco experts to
the bridge at Km 7+325, that settlement continues but at reduced rate
but the beams are opening up at the expansion joint more pronouncely
which may lead to eventual collapse of the bridge.
The continuous settlement means that even if the jacking up of the
beam is embarked upon, the weak foundation may trigger off a
collapse, which is dangerous even for the bridge and people that would
work there because no guarantee that the foundation will carry the load.
According to the expert, the success of the jacking up of the bridge
then is 50/50 chance until he made more detail assessment with his
office experts.
The expert, after meeting with his head office assembled experts, later
considered that they could not embark on the jacking, due to the high
risk of embarking on it. They could not guarantee the safety of the
people that would work there and the bridge itself.
One of the immediate recommendations of the expert from Setraco
was that, the road should be closed for heavy and multi-axle vehicles
traffic, immediately in view of the numbers couple with the volume
and weight of multi-axle trailers passing the road regularly. No
problems with light vehicles like cars and light passenger’s vehicles
The expert emphasized that light vehicles, passengers’ car do not pose
threat but other petroleum product tankers and heavy trucks should be
discouraged from the bridge.
Jacking up is no longer considered feasible and there is need to embark
on the new design and construct a new bridge preferably at a new
location.
ER, stated that his team immediately started, thinking of diversion for
this heavy trucks and tankers, while the bridge should be limited to
light vehicles.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
63 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
5.0
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
SETRACO NIGERIA LTD’S PRELIMINARY REPORTS
Dr. Chaudhuri, stated that he had to come in view of the pictures and
information given to him by their experts who visited the bridge at Km
7+325.
He stated that, they had handled similar situation on the East-West
road, and in that case, they didn’t have any choice than to take the risk
of jacking since there was no possibility of diversion and luckily up till
now, the bridge is still standing.
Dr. Chaudhuri stated that, he is skeptical when a bridge is in danger,
that in the case of Okoso bridge in East-West project, they had a base
to their jacking while in this case they may have to erect a platform on
the pile cap with a base that is still settling which may portends danger
to the process, and invariably risky to embark on the jacking.
Dr. Chaudhuri stated that they have been to the site and observed that
the expansion joint is now pronouncedly wide meaning that the bridge
is in great danger, therefore the jacking is not possible unless they are
instructed to go ahead by the stakeholders.
According to the director, It is not advisable to take a risk in this kind
of situation in view of the safety of life and the bridge itself.
He stated that the best solution is to consider a new bridge and this will
be easier if Etteh Aro & Partners have done the soil assessment
otherwise, they will bring their own experts to do that.
He stated that, since the bridge way constructed in 1971, they could
not confirm the Etteh Aro & Partners submission yet, but as soon as all
investigation is ready Mr. Ali, the bridge expert from Setraco could
design or they will liaise with Etteh Aro and that won’t be a problem
and construction will also be no problem if the design is acceptable and
the weather is clement by 2-5 months it’s ready.
The Technical Director cited the example of a bridge in Taraba State
which poses danger like this situation and when there was a flash of
flood it resulted in loss of over 200 lives and properties.
Dr. Chaudhuri also stated that because Setraco is the visible contractor
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
64 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
5.10
5.11
5.12
5.13
along the road now, they don’t want to take responsibility for any
catastrophe which may arise as regards the emergency situation.
He therefore, added that only light vehicle should be allowed to move
across the bridge and very conspicuous danger signs and warnings
should be erected along the road from vantage points to sensitize the
road users.
Setraco Director volunteered to discuss with the RSDT, Engr. Tope
Oyibuyaku and Engr. Ishaq Mohammed when he returns back to
Abuja, on the way forward as regards the financing of the new bridge.
He also expects the Federal Controller and RSDT to meet with the
Honorable Minister of Works and discuss the issue.
The Controller, who stated that it’s obvious that, there is problem and
challenges as regards this situation also said that nobody want to be
blamed for any fault, nonetheless, would see the Excellency, the
Governor of the State who is outside the State with the Commissioner
as soon as they return, even though we cannot afford to wait for them
in view of the dangerous situation at hand.
6.0
6.1
6.2
6.3
NOMINATED BRIDGE CONSULTANT’S REPORTS
Etteh Aro agreed with the Setraco position on the prevailing situation
and stated that all that has been in offing by them has been palliative
but they have done the survey and preliminary soil investigations.
Etteh Aro & partners added that the depth of the existing pile is around
10.0m deep of soft rock material, while they observed that the hard
strata is actually about 30m deep from their preliminary studies and
hope to discuss along with setraco nig. Ltd.
The nominated consultant, stated that the problem is the softrock
underneath and that the impact upon it over time have caused more
damage, they will also recommend a new bridge.
7.0
7.1
DELIBERATIONS
ESE-RSDT stated that they want a solution whereby the state
government would fund the bridge projects if it is possible.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
65 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12
The Controller stated that, from the look of things, the State of finance
of the State goverment is so tight and that payment of a few federal
projects embarked upon by the State government are still awaiting to
be refunded, but nevertheless all avenues will be exhausted to avoid
any disaster.
Setraco wanted to know under which parastal the bridge project falls,
which the Controller stated that it is the FMW.
The ER stated that the challenge facing the bridge project is funding
and that all along RSDT was considering accommodating the jacking
of the beam but as it is, constructing a new bridge may be beyond
them.
The ER suggested, writing SOS to the Ebonyi and Enugu State
Government and FMW, since the situation at hand needs urgent
disposal.
As regards the issue of funding, the Setraco director promised to see
the RSDT unit Manager and Project Manager as soon as he gets to
Abuja for their onward brief to the Honorable Minster, who will in turn
solicit for fund for the project.
The ER stated that the proposed road for the diversion has been
inspected by him and his team, and it was dicovered that the road has
some snags which should be attended to before any diversion is done.
The ER stated that the road is much more of pedestrian, cyclists and
has about
four culverts under construction which needs tidying up and suggested
that even residents along the road would prefer the heavy and long
trucks diversion to be done at night.
RSDT suggested that, Ecological Fund, could be approached for
emergency assistance and the Controller added that even the Taraba
State project referred to earlier was funded outside the ministry’s
budget (fund), and promised to harness the State Government avenue
and also the FMW.
Dr. Chaudhuri reminded the meeting that, he observed 2 distinguished
Senators were present during the commissioning of the project and
suggested they could also be approached to influence the quick
attention needed by the project.
The Controller submitted that with the latest update, it is imperative for
him to quickly talk to Abuja as regards a new bridge since he was
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
66 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
7.13
7.14
7.15
7.16
7.17
7.18
7.19
8.0
8.1
8.2
8.3
formally discussing the jacking up of the beam of the existing bridge
and moreso that Setraco have profered that they have a design which
could be adopted to the situation at hand.
The surveyor reported that the bridge is still going down at about 0.5
mm per day compared to the former rate of 2.0 mm/day before the
introduction of the speed breakers, aftermath the resolution in the last
meeting.
The Controller referred to the minute of the last meeting, item 5.13 as
regards the introduction of road signs, to which the report on the
introduction of the road signs was affirmative.
The ER suggested that, if need be, the Consultancy Firm that designed
the bridge could be contacted but the meeting was of the opinion that
this may not be necessary any longer, at this point.
The ER stated that, diverting long trucks to the inspected road without
proper preparation and sensitizing of the people could prove dangerous
because of the pedestrians and congested traffic nature of the road, the
trailer population on the road is always congested, the nature of the
traffic is pedestrian.
The usage of existing Airport road interchange may not be feasible
because of the turnings and also the construction of four culverts along
the other road to Abakpa junction needed to be speeded up for
completion.
The Setraco Director suggested that under 7days, broad danger signs
should be erected and the Controller must discuss with the
Governments of both State at Federal level while he will take the
matter up with the Engr. Tope and Engr. Isaq both of RSDT in Abuja.
Setraco summarized that the bridge is in danger and they will not take
charge of any disaster.
The issue of discouraging the dredging around the bridge will be
discussed by the controller with the State Government as is has been
recurring suggestions in the previous meetings
RESOLUTIONS
It was resolved that, there must be a diversion of all heavy and long
trucks from the bridge.
That, broad and conspicuous danger and warning signs should be
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
67 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
8.4
8.5
8.6
8.7
8.8
8.9
conspicuously displayed in 2 to 3 places before the first 1Km to the
bridge and that the ER’s team should proceed to observe the road well
and work on that.
The publicity and sensitizing of the public to be embark upon by the
Contractor-Setraco and the RSDT to request them to fund the publicity
before they go ahead.
Portal frames has to be erected to limit the passage of the diverted
categories of vehicle from using the bridge as soon as the publicity is
on and the road for diversion is ready.
Setraco also suggested a strong letter to emanate from the Controller to
the State Government and the Honorable Minister stating the
emergency situation of the bridge.
Setraco agreed to take over the improvement of the alternative routes
and make it motorable in 2-4 weeks if concluded and so instructed.
The improvement and traffic management of the alternative road is
imperative.
It was also resolved that a new 3-span of 20m bridge will be provided
by Setraco.
Setraco agreed to work with the nominated consultant, Etteh Aro &
Partners and moreso that Setraco is doing same type of project at Oji
bridge.
10.0
10.1
CLOSING PRAYER
The meeting came to an end by 2:45pm with a closing prayer by
Surveyor Isaac Eluma and the date of next meeting will be determined
and sent across.
PREPARED BY: Engr. Michael Feyisola CHECKED BY: Engr. Dele
Betiku ER/TL
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
68 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
MINUTES OF THE 6th MEETING WITH THE FEDERAL CONTROLLER OF WORKS,
HOUSING & URBAN DEVELOPMENT AT KM 7+350 BRIDGE SITE MONDAY 4TH
SEPTEMBER, 2012.
DAY 1
1.0 ATTENDANCE: Engr. Joe Onyejekwe ………… .Fed. Controller of works
Engr. Tope Oribuyaku …………….PM (RSDT)
Engr. Dele Betiku ………….Team Leader (AIM Consultants Ltd)
Engr. Leonillo Tavera ……………CRE (Aim Consultants Ltd)
Engr. Fidelis Anokwu …………RSDT Site Engineer
Engr. Archibong Nkposong …………..Partner (Etteh Aro & Partners)
Engr. Paul Amula …………..ACRE (FMW, Enugu)
Engr. Michael Feyisola ………… Snr. Structural/ Bridge Engineer (AIM Consultants Ltd)
Engr. Isaac Eluma ………… …Snr. Surveyor (Aim Consultants Ltd)
Engr. Rufai Abdul-Azeez …………..Environmental (RSDT)
Mr. Samuel Mene …………………Social/Safeguard Officer (RSDT)
Mr. Lanre Adigun ………………… Land Officer (Fed. Ministry of Lands Housing) HQ Abuja
Engr. Charles Ononuju ………………Contract Mgt. Specialist (Aim Consultants Ltd)
Surv. Kayode Adaramoye…………….. Compensation Expert (AIM Consultants Ltd)
Engr. Branco Koncarevic ……………..Project Manager (Setraco)
ITEM DESCRIPTION ACTION
2.0
2.1
HIGHLIGHTS
OPENING
The meeting commenced by 2:25Pm with the introduction of the new
bridge alignment to the RSDT project manager by the ER.
3.0
3.1
3.2
3.3
3.4
AIM CONSULTANTS LTD STATEMENT
The ER pointed out the setting out of the alignment of the new bridge
to the PM, RSDT.
The ER stated that, it was resolved during the fifth meeting held at the
Federal Controller’s Office that the new bridge will be 3-span, 20m
bridge of total height 60m span to avoid any future threat to the
abutment of the new bridge.
Engr. Dele Betiku stated that, an alternative route has been located for
the diversion of heavy (multi-axle) load traffic and it was also resolved
at the fifth meeting as volunteered by Setraco that, Setraco Nig. Ltd.
Will improve on the condition of the alternative route, (if) when
instructed by RSDT.
AIM Consultants Ltd. stated that, they had inspected the alternative
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
69 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
3.5
3.6
road and spined that proper preparation and sensitizing of the people
are important because of the human traffic and reported traffic
congestion on the road at certain times. Other signs are the culvert
construction works going on along the road with pot holes filled
surface.
The ER mentioned that, it was also agreed at the previous meeting that
portal frames has to be erected to limit the passage of the diverted
categories of vehicle from the bridge as soon as the publicity is on and
the road for diversion is ready.
The ER called the attendant of the PM to the fact that tests carried out
on the settlement rate which has reduced to 0.5mm/day and showed
that the increasing gap between the bidge g…. at the expansion joint
had increased considerably and may eventually signal the sudden
collapse of the bridge.
4.0
4.1
4.2
4.3
4.4
4.5
RSDT STATEMENT.
The Project Manager suggested and preferred a 40m- span new bridge
instead of the resolved 60m-span during the fifth meeting session.
Engr. Tope Oribuyaku stated that, if it would reduced the cost and
reduced the stress of the diversion exercise especially to the public,
then he suggested that new piles could be sunk at determine equidlll on
parallel to both sides of the bridge and beains seat across to lift the
existing bridge being palliative before the completion work on the new
bridge.
The PM, stated that the RSDT agrees to the constructing of a new
bridge and a meeting, must be schedule for agreement with the State
Ministry of Works.
Engr. Tope maintains that RSDT will not fund the jungle and publicity
of the road diversion and usurp the responsibility of who has the
upparatus to do that conveniently.
The PM stated the portal frame alongside other traffic signs will be
supported by RSDT but it has to be agreement with the state
government.
5.0
5.1
5.2
NOMINATED CONSULTANT STATEMENT
Etteh Aro & Partners supported the 2span-40m bridge suggested by
the Project Manager, RSDT.
The nominated consultant agreed with the PM that piles could be sunk
with beams across the underneath the deck of the old bridge as
palliative while the construction of a new one is being concluded.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
70 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
5.3
Engr. Archibong explains the nature of the subsoil around the bridge to
the PM, RSDT.
6.0
6.1
6.2
6.3
FEDERAL CONTROLLER’S STATEMENT
Engr. Joe Onyejekwe stated that, he had reported the situation of the
bridge to the authority based on the minute of the previous meetings
and that diversion of heavy traffic is inevitable to avoid disaster and
that a new bridge had been resolved, and the diversion is already being
worked out.
The FC, pointed out that, the Setraco has volunteered to conduct and
sponsor the juples… and media, if the RSDT instruct them to take
charge.
The Controller also noted that, his report to Abuja was specific on the
previous celermic reports from the site that jacking of the existing
bridge is not safe and a new bridge should be provided.
7.0
7.1
7.2
7.3
7.4
7.5
7.6
RESOLUTIONS
Decision was concluded about stating action on the new bridge in the
next 2 weeks
The construction of New Bridge is has been jult in notion.
The RSDT approved the new bridge in principle and it has to be
conveyed to the governor.
The state governor to fast-track the diversion matters.
The state government should handle the jungle and publicity.
Improvement and Traffic Management needed on the diversion road.
8.0
10.1
CLOSING
The meeting came to an end by 3:20pm and the date of next meeting
will be determined.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
71 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
DAY 2
2.0 ATTENDANCE:
Engr. Tope Oribuyaku …………….PM (RSDT)
Engr. Dele Betiku ………….Team Leader (AIM Consultants Ltd)
Engr. Leonillo Tavera ……………CRE (Aim Consultants Ltd)
Engr. Fidelis Anokwu …………RSDT Site Engineer
Engr. Michael Feyisola ………… Snr. Structural/ Bridge Engineer (AIM Consultants Ltd)
Engr. Isaac Eluma ………… …Snr. Surveyor (Aim Consultants Ltd)
Engr. Rufai Abdul-Azeez …………..Environmental (RSDT)
Mr. Samuel Mene …………………Social/Safeguard Officer (RSDT)
Mr. Lanre Adigun ………………… Land Officer (Fed. Ministry of Lands Housing) HQ Abuja
Engr. Charles Ononuju ………………Contract Mgt. Specialist (Aim Consultants Ltd)
Surv. Kayode Adaramoye…………….. Compensation Expert (AIM Consultants Ltd)
Engr. Branco Koncarevic ……………..Project Manager (Setraco)
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
HIGHLIGHTS
The meeting commenced by 8:30 am
The ER briefed the PM, RSDT on the new ideas of how to mitigate the
challenges confronting the team as regards the new bridge and the
diversion.
The PM, RSDT stated that he had such an idea too and thinks, it should
be given consideration.
It was observed that, similar analogy of the idea is going on along
Azikwe Avenue in Enugu town and the PM suggested a visit to the site.
At the visited site, it was decided that the new bridge could be 1.0m
(paraphet to paraphet) fromthe existing.
And the Abutment could also be 10.0m back to back from the existing
and new bridge would be 60m span.
And that as the new bridge issue is in motion, action have started.
It was later in the evening decided as earlier proffered by the ER that
the new bridge should be 3.0m (paraphet to paraphet) from the existing.
The meeting came to an end by 9:30am.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
72 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
MINUTES OF THE 9th MEETING WITH THE FEDERAL CONTROLLER OF WORKS,
HOUSING & URBAN DEVELOPMENT AT THE FEDERAL SECRETARIAT,
INDEPENDENCE LAYOUT, ENUGU ON TUESDAY 18TH
SEPTEMBER, 2012.
1.0 IN ATTENDANCE:
1.1 Engr. Joe Onyejekwe ………… Fed. Controller of works
1.2 Engr. Onodugo Uche ……...…. Director (Highways) M.O.W, Enugu
1.3 Engr. Okereke Anyaora ………... SEC (M.O.W Enugu)
1.4 Engr. Dele Betiku ………... ER/TL (Aim Consultants Ltd)
1.5 Engr. Leonilo Q. Tavera ..……… CRE (Aim Consultants Ltd)
1.6 Engr. Fidelis Anokwu …………. RSDT Site Engineer
1.7 Mrs. Ewelum Chika …..……. Sec. (Fed. Min. Works)
1.8 Engr. Michael Feyisola ………… Snr. Structural/Bridge Engineer (AIM Consultants Ltd)
1.9 Isaac Eluma ………… Snr. Surveyor (Aim Consultants Ltd)
1.10 Engr. Fouad Sarraf …………. Area Manager (Setraco)
1.11 Engr. Branko Koncarevic ………… Project Manager (Setraco)
1.12 Engr Samuel Ibitoye ………… Project Engineer (Greyline)
ITEM DESCRIPTION ACTION
2.0
2.1
OPENING PRAYER / OPENING REMARKS BY THE
CONTROLLER
The meeting commenced at 12:00noon with an opening prayer by Engr.
Michael Feyisola, followed by opening remarks by the Federal Controller
of Works, Engr. Joe Onyejekwe.
3.0
3.1
3.2
REVIEW OF MINUTES OF PREVIOUS MEETING
The minute of the last meeting was reviewed and the names, Mrs. Chika
Ewehim and Engr. Ani Ifechukwunanaemen were corrected to be Mrs.
Chika Ewelum and Engr. Ani Ifechukwunaeme.
Also Engr. Onodugo Uchet was corrected to read Engr. Onodugo Uche.
T.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
73 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
4.0
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
DELIBERATIONS
The Federal Controller after welcoming and reminding the meeting of the
situation at hand, implored the Director to respond to the meeting in view
of item 4.0 in the previous meeting.
The Director beckoned on the Grey Line, representative to report on how
far they have gone with the mandate given to them to prepare the
diversion road.
Engr. Kayode Ibitoye stated that they had plan A&B to tackle the work on
site. In their plan A which involves earthworks, they are limited by the
rains and in their plan B, they are concentrating on the completion of the
concrete culvert works. He mentioned that the M.O.W, Engineer
inspected the site and encouraged them to clear the road of any
obstructing materials.
The Director (Highways) M.O.W, did not hide his unhappiness with the
report of the Grey Line and stated that he believed the contractor should
have completed the necessary preparation on the diversion road as agreed
and promised by them during the previous meeting.
The Director stated that the completion of the road preparation for
diversion is achievable and wondered why Grey Line is not living up to
expectation because they have no tenable excuse for the delay.
The F.C, was also disappointed on the level of report forwarded by Grey
Line against the promise they made in the previous meeting and wondered
if the Grey Line representation is the right person to speak to as regards
the delay.
Grey Line Engineer explains further that they are almost completing the
necessary aspect of the work but they met some challenges like the
underground water which they are trying to overcome.
The Director (Highways) stated that Grey Line was not doing what was
agreed in the previous meeting rather they are beating about the bush,
while, what they have to do on the road is precise and direct.
The Controller, while emphasizing on the crisis situation at hand stated
that now that, we are at cross road with the Grey Line approach to
completion of the surface preparation of the diversion road, what shall we
do?
Grey line repeated their believe, that the diversion road is motorable but,
FC preferred to inform or relate with their principals directly.
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
74 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
4.20
The ER, stated that the ridability of the road is important. The usage of
TSM (Traffic System Management) requirement is important. He also
emphasized that there is need to look into the diversion and the dual
carriageway critically and observe that basic thing in traffic is segregation
of pedestrian from the trailers and recommended that the controller and
the Director Hihgways,M.O.W should be decisive on this.
While the FC, is of the opinion that Grey Line has failed to deliver based
on their promise, the Director Highways, MOW stated that it was against
their expectation that Grey Line could have changed in their disposition
but he believes Grey Line has the capability and he would take it up with
their Directors later in the day.
On the question that should there be an alarm as regards the failing bridge
before the next 10days which may be extension for Grey Line, the
director stated that he would talk to the Grey Line principals and he would
respond but if there is an alarm, they would close the bridge and as
regards motorable, it could mean vehicles can pass.
Grey Line stated that they would finish before the extension of the 10
days.
FC, wanted the meeting to re-visit the ER’S earlier suggestion of Night
management of traffic for heavy trucks to alleviate the challenges.
The FC, stated that other principal stakeholders will be briefed after this
meeting in case if Grey Line failed. And assuming they fail, there could
be alternative B of Night traffic.
SSE, MOW, Enugu suggested that the closing of traffic for heavy trucks
during the day could start, from the abrupt of the Naira triangle at Enugu
axis and other convenient point before the Eke market.
The FC, enlightened the meeting on his experience during the
construction of Nunkai Bridge in 2001 in Taraba State and stated that the
military came to their rescue by providing a ‘float force bridge’ to pave
alternative access for road users and believes if the military is approached
by the proper authority, they should be willing to also assist since the
situation is emergency.
The ER and the meeting agreed to the FC’s suggestion if it would serve
the purpose to defeat the challenges of diversion, which is at hand.
The FC, who stated that though the military may not want to do it free of
charge promised to write to the Excellency, the Executive Governor of the
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
75 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
4.21
4.22
4.23
State, regarding the float force bridge and encouraged the Director
Highways (MOW) to follow up.
The FC inquired about the feedback as regards the Director (Highways)
liaising with his counterpart in the Transport Ministry.
The Director Highways stated that, he had briefed his principal who has
also discussed with the Commissioner for Transport and earlier in the
morning told him that the ministry of Transport will send a representative.
They have trashed the issue at hand to the extent of possibility of
providing a standby towing vehicle, but the only distraction for the
Commissioner for Works is the additional involvement of the
Commissioner for inter Ministerial Affairs on the matter.
The FC, stated that he has discussed with the Commissioner not to be
distracted or discouraged since the matter concerned fell under his
Ministry and that the ER should discourage further involvement of the
Commissioner for inter Ministerial Affairs to reduce any political
maneuvering.
5.0
5.1
5.2
5.3
5.4
RESOLUTIONS
The Director Highways, MOW to continue meeting with the Ministry of
Transport.
The FC, to write to the Governor as regards the float force bridge and the
Director, Highways to follow it up.
The Director Highways will meet with hi s principals and briefed them on
the resolution of the meeting that, they should not be distracted and that
the success of overcoming these challenges lies in their hand.
The Director promised to get back to the FC in 2 to 3 days.
6.0
6.1
CLOSING PRAYER
The meeting came to an end by 2:00pm with a closing prayer by Engr.
Okereke A.I, after the motion for the adjournment was moved by Engr.
Michael Feyisola and seconded by Engr. Okereke A.I. The date of the
next meeting will be communicated later.
Prepared by:Engr. Michael Feyisola Checked by: Engr. Dele Betiku ER
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
76 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
MINUTES OF THE MEETING WITH ALL THE STAKEHOLDERS IN RESPECT OF
RELOCATION OF THE NNPC PIPE LINE, HELD AT THE BRIDGE LOCATION ON
WENESDAY 10TH
OCTOBER, 2012.
1.0 ATTENDANCE: Mr. Lambert U.C 08033386474 NNPC - PPMC
Mr Odofin A.A 08023717070 NNPC - PPMC
Mr. Alawode A.A 08056225391 NNPC - PPMC
Mr. Ojo A.B 08033118886 NNPC – PPMC
Engr. DR. Anthony C. Nobo 08037164483 Consultants to ENSWC
Engr. Raphel 08065139757 Consultants to ENSWC
Mr Obriene Ofodu 08033240670 MD ENSWC
Engr. Eze Charles 08037112076 Project Engr. ENSWC
Engr. Leonillo Tavera 08099928673 CRE (Aim Consultants Ltd)
Engr. Kolawole Kusimo 08099928662 Snr. Q.Materials Engr. (Aim Consultants Ltd)
Engr Fidelis Anokwu 08035923222 RSDT Site Engineer
Engr. Branco Koncarevic 08177234730 Project Manager (Setraco)
ITEM DESCRIPTION ACTION BY
Highlights:
The meeting commenced at 10:00 am at the bridge location at
km7+125 with all the stakeholders basically to look into the
possibility of protecting or relocating of existing pipe line, manholes,
perimeter fence, gate house and access road to the NNPC.
Hence the under listed was agreed after the meeting:-
1. It was jointly agreed that a survey should be conducted the next
day, October 11 , 2012 to establish the extent of relocation and to
enable the Enugu State Water cooperation come up with the cost
of the relocation of the pipes which is to be submitted to the
NNPC and thereafter to Aim Consultants Ltd.
2. Aim Consultants Ltd requested the NNPC officials to forward to
them any detailed drawings that may be of help.
3. It was also agreed that during construction that the staff of the
Abbreviated Resettlement Action Plan for the alternate Bridge at km7+350 along Enugu – Abakaliki Road
77 | ARAP OF ALTERNATE BRIDGE NO 2 CONSTRUCTION ENUGU – ABAKALIKI ROAD BY MDS
Water Corporation should be present to supervise the relocation of
the pipes.
4. It was jointly agreed that the Water Corporation and NNPC
personnel to jointly come up with the cost estimate for the
relocation for the pipes.
The meeting came to an end by 11:05am.
Prepared By: Engr. Kolawole Kusimo Checked By: Engr. Leonillo Tavera