Final Report for ENGR4950 Daniel Bondarenko
-
Upload
daniel-bondarenko -
Category
Documents
-
view
55 -
download
2
Transcript of Final Report for ENGR4950 Daniel Bondarenko
Design and Construction
of a Humidity System for
a Climatic Wind
Chamber
ENGR4950U
Capstone Systems Design
Dr. Remon Pop-Iliev
Dr. Martin Agelin-Chaab
Dr. Sharman Perera
Design Report 1
Team G03-02
December 02 2013
Daniel Bondarenko (ID:100363648)
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
1
Table of Contents 1. Design Challenge and Objectives .......................................................................................................... 2
1.1. Project-related Background .......................................................................................................... 2
1.2. Project-related Review of the Current State of the Art ................................................................ 4
2. Detailed Design Documentation ........................................................................................................... 7
2.1. Phase 0: Product Planning ............................................................................................................ 7
2.1.1. Project Identification............................................................................................................. 7
2.1.2. Project Scope ........................................................................................................................ 8
2.1.3. Evaluation and Priorotization of Projects ............................................................................. 9
2.1.4. Allocate Resources and Plan timing .................................................................................... 12
2.2. Phase 1: Concept Development .................................................................................................. 18
2.2.1. Sub-Phase A: Identifying Customer Needs ......................................................................... 18
2.2.2. Sub-Phase B: Establishing Target Engineering Specifications ............................................. 18
2.2.3. Sub-Phase C: Setting the Final Specifications ..................................................................... 20
2.2.4. Sub-Phase D: Concept Generation ...................................................................................... 28
2.2.5. Sub-Phase E: Concept Screening and Scoring ..................................................................... 32
2.3. Phase 2: System-Level Design ..................................................................................................... 36
2.4. Phase 3: Detail Design ................................................................................................................. 42
2.5. Phase 4: Design Fundamental Simulations and Analysis ............................................................ 46
3. Conclusions ......................................................................................................................................... 57
4. Acknowledgements ............................................................................................................................. 57
References .................................................................................................................................................. 58
Appendix: .................................................................................................................................................... 60
A. Project Gantt Charts ........................................................................................................................... 60
B. The project planning schedule of the sequential tasks for the Humidity Regulation System ............. 64
C. Organized hierarchy of customer needs ............................................................................................. 71
D. Competitive Products ......................................................................................................................... 79
E. Complete QFD for the HRS ................................................................................................................ 107
F. Concept Generation vie Concept Combination Table ....................................................................... 110
G. Calculations for the Staggered Tube Bank Configration .................................................................. 143
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
2
1. Design Challenge and Objectives There exists a Modular Open Wind Climatic Chamber (MOWCC) on the grounds of University of
Ontario Institute of Technology, however, it is not completed and cannot work according to its purpose.
The challenge is to make this existing open channel climatic wind chamber fully functional and in
accordance to the requirements of the project supervisor, Professor Perera. One of the requirements, set
by Professor Perera, is a functional humidity control unit that will provide operating conditions similar to
the conditions in Canada. This objective has been nominated to Daniel Bondarenko (Team G03-02),
specifically to design and construct a humidity control system for MOWCC, because it does not have the
this required system.
For a reason that the MOWCC will be capable of separating into independent climatic modules the
humidity control system will be expected to operate in several modes:
An obligatory humidification and de-humidification of air for a stand-alone climatic
chamber, without the operation of the primary wind generating air fan.
An obligatory humidification and de-humidification of air for a system under test, such as
a model building, that will be positioned onto the test area within the climatic wind
chamber.
An optional humidification and de-humidification of air for a climatic wind chamber with
the operation of the primary wind generating air fan
1.1. Project-related Background
Firstly, a climatic chamber is a volume confined to boundaries and subjected to changes in temperature,
pressure, humidity, and lighting, in order to simulate weather under controlled conditions and on a small
scale. By building small scale models of either existing engineering structures, or engineering prototypes,
and testing them within a climatic chamber it is possible to model real world applications and predict their
actual scale counterparts’ behaviour with respect to varying environmental stresses. A climatic wind
chamber is similar to a climatic chamber, though an additional feature is the controlled wind speed within
the chamber and boundary conditions allowing for the passage of air. The climatic wind chamber project
in the FESNS is of modular type, and, hereby, can be arranged to be a stand alone climatic chamber as
well as a wind climatic chamber.
Though the climatic wind chamber is project that requires team effort for completion, the humidity
control portion is of primary interest for successful completion of ENGR 4950. Hence, the primary
highlights of the background information presented in this section will be in regard to the humidity
control system.
Humidity is the amount of water vapor in a volume of air [1]. The specific/absolute humidity is the mass
of water vapor present in a unit mass of dry air, specifically denoted by ω:
(kg water vapor/kg dry air) {1}
Dry air on its own contains no water vapor and it humidity is zero. When water vapor is added to the dry
air, the humidity of air rises up until the point of saturation. The saturated air has so much moisture that
any additional moisture added will immediately precipitate out of the air-vapor mixture as condensate.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
3
The saturated air, however, holds only a specific amount of moisture at a particular temperature; so even
though the temperature changes the specific humidity remains the same. To take into account the change
in moisture levels corresponding to the changes in the temperature it is convenient to think in terms of
relative humidity. The relative humidity is the ratio of the moisture suspended in air (mv) at a specific
temperature, relative to the maximum amount of moisture the air can hold at that temperature (mg)
{2}, where Pg=Psat@T
The relative humidity ranges between 0, for dry air, and 1, for vapor saturated air.
Accounting for the temperature effect on the level of moisture in the air it is only logical to deduce that at
a specific temperature it is possible to extract the vapor from the air, specifically for water vapor, at
standard atmospheric conditions, this temperature is about 0oC. In principle, the methodology of
controlling the humidity is a matter of diffusing water mist through the air and allowing it to mix in order
to humidify air at a specific temperature, or cooling the air to a temperature of water condensation in
order to extract the vapor from the air. In order to change the temperature of the air, however, the energy
either needs to be added or extracted from the air volume. The challenge presented in this project is that
the humidity has to be controlled precisely according to the conditions set by the operator of climatic
wind chamber. This challenge can be overcome by applying the principles of thermodynamics, heat
transfer, control systems, and, likely, machine design.
Now, in order to lower the temperature of the air or raise its temperature it has to be either cooled or
heated by the means of heat exchange from a surface to the mass of air. The heat exchange process for
this matter will then primarily occur my means of conduction, that is direct contact of air with the heat
exchanging surface, and convection, which is the mixing of the volumes of air as it leaves the surface [2].
The radiation plays a minor role in control of humidity, so right now it is negligible to discuss it, although
it will play role in the overall operation of the climatic wind chamber (any special scenarios of radiation
heat transfer and humidity control will be discussed if ever such event occurs during the project).
Therefore, simply by focusing on the two modes of heat transfer, conduction and convection, it is
understandable that the matter of surface temperature, flow speed, as well as the shapes of the surfaces
will affect the humidity within the climatic chamber. Going into further discussion about the shape and
form of the humidity control system will only make sense after confirming the requirements for the
overall system. Hence, as far as the basic principles of humidity control go, it is simply a matter of
changing the temperature of the air in order for it to either absorb water vapor or condensate it on the
surface of heat exchanger.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
4
1.2. Project-related Review of the Current State of the Art As a transition from the previous section it is worthwhile to consider several wonderful ideas pertaining
the humidity control. The current state-of-the-art devices for humidity extraction and humidification are
primarily based on the principles discussed in the background section; though the methods of humidity
control can be quite extravagant the foundations remain solid. Hence, consider the following figure that
illustrates the humidification and dehumidification system found widely in the field of heating,
ventilation, and air-conditioning.
Figure 2. Humidity Control System used in HVAC industry
Most of the existing and state-of-the-art systems for humidity control employ the system shown in figure
1, due to its simplicity and flexibility of application to different scenarios [1].
However, knowing that the system presented in the figure 1 is the base foundation for most of the other
humidity control systems is not an indicator that it cannot be improved. In fact it is worth pointing out the
outstanding ideas that show most promise for the humidity control, even though these ideas are merely
additions to the system that has long been established as the primary method for humidity control.
One of the ways to improve the performance of the humidity control system is to find a cycle that will be
best suited as a refrigerator for the humidity extraction. Depending on the size of the system, the
refrigeration cycle may either employ something as involved as an open air-vapor compression
refrigeration system, like the one shown in fig. 4 [3], or as simple as a Peltier thermoelectric cooler, which
only requires and input of electricity to create a temperature gradient between surfaces [4].
An interesting method to cool down air is by the use of a vortex tube [1]. However, it requires the gas to
be input under a significant pressure, in order to operate properly, and the efficiencies of these devices are
not as high as the conventional refrigeration cycles.
Figure 3. Vortex tube lets the pressurized gas in, the cool gas exits to the left, and hot to the right
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
5
Figure 4. Circuit diagram of an open air-compression refrigeration system for air-conditioning
and desalination
One of the areas in humidity control that is steadily gaining attention is the desiccant wheel. One
particular aspect that makes desiccant wheel an attractive option for many de-humidification systems is
that it is a low thermal energy driven device. A rotary honey-comb desiccant wheel can continually
remove moisture from the system [5]. A schematic of the desiccant wheel humidity control system is
shown in fig. 3.
Figure 5. A schematic of experimental desiccant wheel. (1) Electric heater. (2) Electrothermal humidifier.
(3) Console. (4) Desiccant wheel. (5) Motor pulley. (6) Process air fan. (7) Damper. (8) Re-generation
heater. (9) Console. (10) Regeneration air fan. (11) Process air filter.
(12) Regeneration air filter.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
6
Some systems utilize porous glasses to control the humidity levels [6]. Though interesting, their use is
limited to the field of humidity sensors. The porous glasses improve the performance of the humidity
sensors by setting the new limits for humidity level detection, which could be potentially used to observe
the performance of the climatic chamber project. However, this decision will primarily rely on the
feasibility study of such sensors as well as the actual requirements set by the supervisors.
It would not be a complete description of the state-of-the-art technologies, available for humidity control
system, if the novel developments in materials are not mentioned. The composite materials used in honey-
combed desiccant wheels can improve the humidity extraction up to 50% compared to the conventional
materials [5]. Certain coatings like acrylate-based copolymer emulsion [6], when deposited on a surface
can regulate the humidity by either absorbing or releasing water vapor depending on the temperature of
the wall, which could be beneficial if applied to the desiccant wheels.
Lastly, some of the control options currently utilized in the state of the art humidity control systems may
involve genetic algorithms, or artificial neural network controllers [7].
There are, perhaps, a multitude of other technologies available for the humidity control, but given the
limited time for this project the ideas listed above are the most prominent.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
7
2. Detailed Design Documentation
2.1. Phase 0: Product Planning
2.1.1. Project Identification
The identity of the MOWCC project is a demand oriented platform design (configuration design), with
low level of customization (parametric design). The project of the team G03-02 is to design and construct
a fully functional humidity control system for MOWCC. The humidity control system allows for the
addition and the extraction of moisture from the air by means of water evaporation and air cooling. This
system is also a demand oriented platform design, and it also has low level cuctomization aspect; this
project will include finding the values for the features that characterize the humidity control system that
will fit the existing MOWCC shell. The product of the design process will be a new platform product
because it will involve a major development effort to create a new device, based on a common platform
of MOWCC. The design for this project will follow a successive development and application of
constraints until only one unique project design remains. Development and application of the constraints
will be done incrementally and in accordance to the decision making, which will be based on the
knowledge, drawings, models, analyses, and notes generated throughout the project. However, the design
requirements will effectively constrain the possible solutions to a subset of possible designs, since the
MOWCC shell already exists.
As per the requirements of ENGR 4950, and in accordance to the lecture notes [10], the design practice
for this project will be focused on following, as close as possible, the best practices:
1. Focusing on the entire product life
2. Using and supporting the design teams
3. Realizing that the processes are as important as the product
4. Attention to planning for information centred tasks
5. Careful product requirements development
6. Encouragement of multiple concept generation and evaluation
7. Awareness of the decision making processes
8. Attention to designing in quality during every phase of the design process
9. Concurrent development of product and manufacturing process
10. Emphasis on communication of the right information to the right people and at the right time.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
8
2.1.2. Project Scope
Currently the MOWCC lacks the following components that will provide desired performance:
- Instrumentation (primarily sensors) and control
- Insolation system
- Temperature regulation system
- Humidity regulation system
- Geothermal regulation system
The MOWCC already has existing components for the shell of the chamber as shown in figure 1. The
wind chamber also has the control system unit in form of NIcrio data acquisition cradle and data
acquisition modules.
Figure 1. Shell of the climatic wind chamber
The reason for existence of MOWCC is that there is an academic and educational need for a controlled
environmental wind chamber at Faculty of Energy Systems and Nuclear Science (FESNS) at UOIT. The
collective team of students from FESNS and FEAS will be working together to complete the required
components of this project. A portion of this large project includes a controlled humidity system, this
system will be designed and built by a FEAS student member of the team, Daniel Bondarenko. The
purpose of the humidity control system is to humidify air and/or extract humidity at the will of the
operator. The humidity control system has to preferably be modular, compact, and compatible with the
integrated control system for the whole climatic wind chamber. It is expected that by April the humidity
control system will be a fully functioning and integrated with the climatic wind chamber.
Since, the primary concern of team G03-20 is the completion of the humidity regulation system it has
been pointed out that this system should be safe, modular, easily maintainable, inexpensive, robust during
operation, capable of integrating with other components of the wind chamber, use as few toxic materials
as possible, and follow the control set points directed by the operator of the wind chamber.
The cost of the humidity regulation system is limited to $200. Although this may seem as a financial
constraint it is also a constraint that sets the limit to the designs possible for the humidity control. The
control of the humidity regulation system will be done through the LabView and NIcrio. The system
should be modular and fit in a box of about 1 cubic meter for the two obligatory options (stand-alone
climatic chamber without the operation of the primary fan, and the system under test, such as a model
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
9
building). The system should also be relatively simple and have few operational parts for the ease of
maintenance.
In the best case scenario the obligatory and the optional humidity regulation systems would be able to
regulate the relative humidity levels from 5 to 95%. The temperature levels for the system are expected to
be between -20oC to +40
oC. During the open channel operation the airspeeds may reach as high as 11m/s.
2.1.3. Evaluation and Priorotization of Projects
2.1.3.1. Competetive Strategy
Firstly, it is fully understood that the design process for this project, and the creation of the end product
itself, will involve an error uncertainty. The competetive strategy outlined in this section shows an
approach to the design, which will ,hopefully, help to reduce the error uncertainty.
During the course of the project it is planned that the design will be rooted from the technology
leadership, cost leadership, and imitation of existing products. The technological leadership will be based
on the basic research and development of the technology, and the consequtive deployment of this
technology through the product development. The cost leadership is based on the existing budget
constraints ($200) and the fact that the technology will have to be efficient in its operting condition, as
well as through the manufacturing, assembly, and the management of the production; the cost-leadership
is largely emphasized during the DFX phase. Lastly, there will be an aspect of imitation of existing
products, because the creation of the state of the art humidity control system relies on closely following
the trends in the humidity control industry. The imitation will allow to explore the best options that
currently exist, it will follow the fast development process to effectively find a solution for the project,
and it is a good approach in general, due to the limited time and resources.
There will be an element of means-ends approach in the analysis of the project, because this project will
advance incrementally towards the end-goal of a fully functioning humidity control system. Both the
algorithm procedures and the heuristic procedures will be used during the design analysis, though it is
expected that the most realistic procedure will be used over a more theoretical one; this is due to the fact
that end product has to function in the “real-world”, not the simulation. Also, since some imitation of the
existing products will be performed during the execution of the design process, some backward dis-
assembly will be made as well; the ultimate goal of the project is to create a humidity control system,
which has been created before and has solid theoretical foundation, and, based on this goal, it will be
decided what constitutes a reasonable direction prior to reaching this goal.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
10
2.1.3.2. Technology Roadmap
The technology roadmap for the humidity regulation system is shown in figure 6, this roadmap will guide
the project development for the period between the beginning of the project and its completion.
Figure 6. Technological Roadmap for the Humidity Regulation System
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
11
Also, figure 7 gives an outline of the product life cycle management system, which is relevant to each
humidity regulation sub-system of MOWCC. The product life-cycle management system will be followed
throughout the project development and in accordanc to the technological roadmap.
Product Life-Cycle Management
(PLM)
System Engineering
Design Automation
Bill of Materials
Manufacturing Engineering
Service, Diagnosis, Warranty
Portfolio Planning
Needs
Feautures
Functions
Architecture
Signals and Connections
Simulation
Customer
Environment
Regulations
ECAD
MCAD
Sofware
Drawings
Solid Models
Detail
Layout
Assembly
DFA
DFM
Figure 7. Product Life-Cycle Management for the Humidity Regulation System
The two obligatory and one optional design projects will be followed through simultaneously throughout
the term of the ENGR 4950, as it is preferable that all of them get completed by April 2014. Hence,
prioritywise, the projects will be approached simultaneously, but the design choices will be streamlined
towards the options that can be transferable in theory, modular, and cost effective. It is likely that the
finalized design choice for the house and the individual chamber will share similarities, albeit having
different dimensions.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
12
2.1.4. Allocate Resources and Plan timing
2.1.4.1. Resource Allocation The resources necessary to complete the MOWCC project in time and on budget primarily include the
team’s human resources, such as skills and support, and the facilities available to complete the project.
The team works together in a designated lab specifically meant for the climatic wind chamber. In this lab,
the project plan and approach is discussed and implemented. It is also the place where the FESNS team
for MOWCC, Dakota Watson, Jonathan Allcock, Nandine Kanesalingam, Jason Runge, and the FEAS
student, Daniel Bondarenko, meet and work on project.
Currently, the available hardware includes the National Instruments Control Cradle with Data Acquisition
Modules, the lab computer for data acquisition, visualization, and control. The available software for the
project includes NX Nastran, Fluent, EES, RefPROP, Labview, and Matlab.
The specific equipment available in the lab for the humidity regulation system includes the MOWCC
shell, the model house, the humidity sensors form ``Omega``, misting equipment (MistKing: pump,
control unit, connectors, and hoses), thermocouples, fog machine, and machine shop facilities on UOIT
Energy Research Center (ERC) grounds.
The engineering tools that will be used, but are not limited to, are the following:
Functional Breakdown by the use of the Fishbone Diagram
SWOT analysis
Pros-&-Cons analysis
Quality Function Deployment (QFD) using the House of Quality (HoQ)
Concept Drawings (Assembly, Detail, Layout)
Decision Matrix
Gantt Chart
It is expected that the some of the help in approaching the project will come from the following primary
experts:
Dr. Agelin-Chaab (Assistant Professor, Faculty of Engineering and Applied Science)
Professor. Perera (Lab Specialist, Faculty of Energy Systems and Nuclear Science)
Dr. Pop-Iliev(Professor, Faculty of Engineering and Applied Science)
Robert Ulrich (Lab Technician, Faculty of Energy Systems and Nuclear Science)
Dr. Waller (Professor, Faculty of Energy Systems and Nuclear Science)
Dr. Gabbar (Core Faculty, Faculty of Engineering and Applied Science)
Dr. Dincer (Professor, Faculty of Engineering and Applied Science)
Dr. Rosen (Professor, Faculty of Engineering and Applied Science)
Qi Shi(Engineering Specialist, Faculty of Engineering and Applied Science)
Cliff Chan(Engineering Specialist, Faculty of Engineering and Applied Science)
Hidayat Shahid (Manager of Technical Services, Faculty of Engineering and Applied
Science)
Leon Wu (Engineering Specialist, Faculty of Engineering and Applied Science)
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
13
Michael MacLeod (Lab Specialist, Faculty of Engineering and Applied Science)
Dr. Arulliah (Associate Professor, Faculty of Science).
The primarily accountable person for the completion of the humidity regulation system is Daniel
Bondarenko. Hence, he is responsible for communicating the progress on the design project and following
through with the completion of the project. He will have to stay within the $200 financial limit, and he
needs to find the design option that will provide the quality and the performance. Daniel Bondarenko is
the main human resource devoted to completing the humidity regulation project, but he needs to work in
unison with the FESNS team, who are also responsible for providing the deliverables for the MOWCC
project.
2.1.4.2. Project Timing The Microsoft Project mangement document describing the planned project activities for the whole team
working on the MOWCC project is provided in Appendix A. Figure A4, in Appendix A, shows the
planned project activities for the humidity regulation system by Daniel Bondarenko.
The rationale for design and construction of the humidity regulation system, is that one designer, Daniel
Bondarenko, will complete the design of this system within the time period of Cap-Stone course. He will
work on a design that is primarily demand oriented platform design, and has a low level cuctomization.
2.1.4.3. The Product Plan/ Project Methodology
In order to complete the design and construction of the humidity system for a climatic wind
chamber the first task that needs to be done is to figure out where and how the CapStone class
notes, progress reports, and resources fit in with respect to the design process outline provided in
“Product Design and Development, 3rd
ed.” by Karl T. Ulrich and Steven D. Eppinger. What needs to be
done is to see the available pieces for the design process provided by Dr. Pop-Iliev, Dr. Martin, and Dr.
Perera, and assemble them into a framework that will show a design path. It is understandable that not all
the parts are going to fit together perfectly, but the design path created this way will be based on solid
foundation formed by the generations of designers. This may appear as a linear process, however, the
project is admitedly straight forward: the objective is clear, the means to achieve the results exist, and
there is a budget to work with in order to create the final product. A plan defined right now does not
imply that tehere is no room for creativity or innovative thinking, it simlpy allows to make the fuzzy
perception of the project approach to crystalize into a labyrinth, that may not neccesarily lead to
successful completion of the project, but it has a structured layout and the option to complete the project
successfully.
Near the start of this “design labyrith” there is a “sand-box”, or the portion that allows to release creative
ideas and create a plan. This portion is the concept generation and it will lead to choices in the design
labyrinth. Hence, part of the design plan is to make the intelligent choices in order to progress with the
design.
The rest of the design closely corresponds to the outline provided in “Product Design and Development,
3rd
ed.” and the lecture notes. The path of the project aims at completing the report, figure 8,
simultaneously with the project phases, figure 9.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
14
Figure 8. Design Report Structure and Design Layout
By completing each chapter of the report for the specific aspect of the design a milestone is met, and,
since the design process is an iterative process, the project is built from the foundation and upwards. This
can be seen from the “Table of Contents” of the current report, where each chapter has respective phases.
Figure 9. Flow-Diagram of the Design Process for Design and Consruction of HSCWC.
It has been identified that the design challenge of the the humidity system for climatic wind chamber is a
generic design challenge. The reason why this project is a generic design challenge is that there is a an
opportunity to make the climatic wind chamber for UOIT, and the approach process for this project
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
15
includes distinct planning, concept development, system-level design, detail design, testing and
refinement, and a production phase.
The following points are additional key steps that will be completed during the design process:
Identify the requirements and find solutions currently existing for similar
challenges/problems.
Generate a range of alternate solutions for variety and conceptualization of possible
solutions
Follow the heuristic outlined in “Product Design and Development, 3rd
ed.”, in order not to
stray away from the intended design process.
The system needs to be specified according to internal and external interfaces (the system
architecture will be provided in a form of a flow diagram)
The system is modularized so the interfaces and boundaries between the components
must be considered.
Be as compliant to the requirements as possible.
Emphasize on continuous improvement of both the product and the process for
developing the product.
Aim for design for sustainability by following the Hannover Principles (Table 1)
Make a functional breakdown of a system into the funcional blocks, not the physical blocks.
Table 1. The Hannover principles
1. Be Persistent to Support Sustainability Insist on rights of humanity and nature to co-exist in a healthy,
supportive, diverse and sustainable condition
2. Recognize Interdependence The elements of human design interact with and depend upon the natural world, with broad and diverse implications at every side.
Expand design considerations to recognizing even distant effects.
3. Respecct relationships between spirit and matter Consider all aspects of human settlement including community, dwelling, industry and trade in terms of existing and evolving
connections between spiritual and material conciousness
4. Accept responsibility for the consequences of design Make decisions upon human well-being, the viaility of natural systems anf their rights to co-exist.
5. Create safe objects of long-term value Do not burden future generations with requirements for maintanence or
vigilant administration of potential danger due to the careless creation
of products, processes, or standards
6. Eliminate the concept of waste Evaluate and optimize the full life-cycle of products and processes to
approach the state of natural systems, in which there is no waste
7. Rely on natural energy flows Human designs should, like the living world, derive their creative
forces from perpetual solar income. Incorporate this energy efficiently and safely for responsible use
8. Understand the limitations of design No human creation lasts forever and design does not solve all
problems. Those who create and plan should practice humility in the
face of nature. Treat nature as a model and mentor, not as an
inconvenience to be evaded or controlled
9. Seek constant improvement by sharing he knowledge Encourage direct and open communication between colleagues,
patrons, manufacturers, and users to link long term sustainable considerations with ethical responsibility, and re-establish the integral
relationshipbetween natural processes and human activity.
Prior to proceeding with the project, Table B1 in Appendix B, “The project planning schedule of the
sequential tasks for the Humidity Regulation System”, will be considered for project planing schedule
with a detailed task analysis. However, for some tasks the “Decision Needed” portions will be updated
when the particular phase of the project is reached.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
16
2.1.4.4. Pre-Project Planning The foundational analyses for the humidity regulation system may include the following subjects:
Control Systems
Fluid Dynamics
Thermodynamics
Heat Transfer
Machine Design
Electric Circuits
2.1.4.5. Mission Statement
Table 2: Mission Statement for the MOWCC Humidity Regulation System
Mission Statement: High Efficiency Humidity Regulation Unit
Product Description Robust, reliable, safe and highly responsive humidity regulation unit capable of adding
and extracting jumidity between 5% to 95% relative humidity levels in the temperature
range between -20 oC to +40
oC
Key Goals
Can be used as a teaching tool
Operates as per the product description
Can serve as a foundation for future developments of the MOWCC project in
the area of humidity control
Stay within the set $200 budget
Complete the project milestones as per the set deadlines
Provide exceptional quality throughout the project
Primary Target
Market for the
Product
Educational staff of FEAS and FESNS
Students of FEAS and FESNS
Environmentally benign
Pride instilling for the faculties and the MOWCC team
Secondarey Target
Markets UOIT investors
Visiting emplyers
Funding comitee
Assumptions and
Constraints New Product Platform
Compatible for control with LabView
Has to have a limited footprint, about 1m3, from the entire MOWCC
Portable and modular
Control efficiencies has to be taken into account when defining efficiency
Manufacturing:
- The ERC machine shop may be used to make some of the components for
the humidity regulation system
- The primary suppliers for sensor systems should be “Omega”, during an
event that any sensors are required
- The existing production systems are capable of producing the design in
accordance to the specifications
Service:
-Off-the-shelf components are usable in maintenace
-The number of components is only limited to the best functionality of the
product
Environment:
-The project can be completed and operated with a fair correspondence to
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
17
Hannover principles
Stake Holders MOWCC team: , Dakota Watson, Jonathan Allcock, Nandine Kanesalingam,
Jason Runge
Professor Perera
Dr. Agelin-Chaab
MOWCC operators
ERC technicians
Teaching and Lab Assistants
Faculty and Staff
Safety Comitee
Students of UOIT
2.1.4.6. Reflection on the Results and the Process
As per the lecture notes: “The goal of the design process is not to eliminate changes, but to manage the
evolution of the design, so that most changes come through iterations early in the process.”[10]. Given the
opportunity to work on the humidity regulation system for MOWCC, there is an exciting and fairly
diverse set of product opportunities. In order to pursue these opportunities it was deemed that the product
plan, as it has been provided above, supports the strategies for educational goals of UOIT, as well as
addresses the most important current opportunities available for completing the MOWCC humidity
regulation unit. At present moment, it is known that there is a budget to complete the design project, and
the resources allocated to product development are sufficient to pursue the competetive strategy.
Furthermore, the product platform design approach is considered beneficial for the humidity regulation
system project due to its ability to creatively leverege the finite resources available.
At present stage of phase 0, it is accepted that there will be challenges in the course of the project
resulting from the mission statement. However, the elements of the mission statement are consistent with
the requirements for the project, hence, the challenges are expected to be manageble. In addition, there are
sufficient constraints and assumptions, put in place within the mission statement, that allow the freedom
for the design team to develop the best possible product. If any changes in the plan for the product
development are encountered, they will be analysed and affirmed through the discussions with the project
supervisors.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
18
2.2. Phase 1: Concept Development
2.2.1. Sub-Phase A: Identifying Customer Needs
2.2.1.1. The organized hierarchy of customer needs
The primary customer for the MOWCC project is the engineering education faculty of UOIT, since the
MOWCC project is intended for the teaching purposes. However, the customer requirements for this
project were primarily set by the project supervisors: Professor Perera and Doctor Agelin-Chaab. The
requirements for the humidity regulation system have been gathered through a series of interviews and
meetings with the supervisors. Table C1, in Appedix C, provides a hiearchical list of primary and
secondary customer needs for the humidity regulation system (HRS), with the *** denoting critically
important needs, ** denoting medium needs, * denoting low needs and ! denoting latent needs. In this
table the team implies to convey its understanding of customer needs to be met, which will lead to solid
engineering specifications, as well as infusing the quality into the product during the product design.
Some of the customer needs are based upon the technological roadmap from section 2.1.3.2, figure 6.
Please note, for the project to be absolutely successful all the categories of customer needs have to be
implemented to the degree of realism financially and physically.
2.2.1.2. Reflect on the Results and the Process
During the analysis of Table C1, the few things that came to attention were the implementation of the
humidity regulation schedules in the control, as well as the real-time CFD and HRS operation for
dynamic analysis of data. These requirements, although expected, were not very explicit during the
meetings and interviews with the supervisors. Hence, they will be approached with caution. In the future,
if any creeping specifications occur, they will be mentioned in the addendums of the task schedule and
taken care of if the opportunity to do so occurs.
2.2.2. Sub-Phase B: Establishing Target Engineering Specifications
2.2.2.1. A List of Needs Metrics Matrix
Table C2, in appendix C, gives an insight into HRS metrics list.
2.2.2.2. Competitive Benchmarking Information
An internet search of possible market alternatives available for humidity regulation systems yielded
several companies. The company that manufactures the humidity regulation systems for educational
purposes is GUNT Hamburg [11], which follows the ISO 9001 for verification of its quality standards.
The other companies that manufacture the humidification and de-humidification products for comercial
purposes include: DRI-EAZ [12], Novel Air [13], DEZ-AIR [14], FANTECH [15], DAYTON [16], and
Air O Swiss [17]. Table C3, gives a competetive benchmarking chart based on metrics for the selected
companies. The information gathered from the websites are present in the appendix D; it contains the
specifications about the products available from these companies. In case of GUNT Hamburg, some of
the brochures of the products are presented in cut-out fotm. .
*Note: The humidification process is set by the existing misting pump and the fog generation unit, they
are most likely to be employed for generating humidity in the systems. Hence, the primary objective of
the team working on the current project will be to focus on the de-humidification aspects of humidity
regulation system.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
19
2.2.2.3. Ideal and Marginally Acceptable Target Values
Based on the competetive benchmarking information the ideal and marginally acceptable target values are
presented in table 3.
Table 3. Ideal and Marginal target values
Metrics
#
Needs
#s
Metric
Engineering Spec.
Importace Units Ideal
Value
Marginal
Value
1 1, 2, 3 Humidity extraction and addition rate 4 kg/hr 10 4
2 4 Coefficient of performance on the HRS
cooling units
5 ratio 4 1
3 5 Negative feedback loop for set humidity levels 5 DL Yes Yes
4 6 Auxiliary ventilation and air conditioning 3 subj. Yes No
5 7 Humidity setting is input via the terminal and
displayeld alongside with the actual humidity
reading
5 subj. Yes Yes
6 8 Manual for the HRS providing step by step
procedures
5 pages ~100 ~50
7 9, 12 Maximum temperature ranges from -50 to
+100 oC
4 oC -50 to
100
-30 to +50
8 10 Mechanism for flow regulation 3 subj. Yes Yes
9 11, 13 HRS is error-tolerant, and if a fault occurs
over a specific time period the HRS will take
preventive actions and return the system to the
set conditions or shut-down to prevent error
accumulation
5 seconds 0.0001 0.01
10 12, 13 Low thermal expansion materials 4 mm/ oC 0.1 0.5
11 13 Statistical analysis of HRS normal
performance
3 DL Yes Yes
12 14 Temperature variation is not affected by the
HRS operation and vice versa
4 oC/φ 1/10% 5/10%
13 15 TES performance is not affected by the HRS
operation and vice versa
4 oC/φ 1/10% 5/10%
14 16 Air-flow variation is not affected by the HRS
operation and vice versa
3 (m/s)/φ none 0.1/10%
15 17 Solar regulaion is not affected by the HRS
operation and vice versa
2 lum/ φ none 0.001/10%
16 18, 19 The whole HRS fits into a box of dimensions
less than 0.5m3 for the two obligatory options
(stand-alone climatic chamber without the
operation of the primary wind generating air
fan and the system under test, such as a model
building)
5 m3 0.2 0.5
17 18, 19 The space factor of HRS is less than 1/12th
of
MOWCC
5 m3 0.2 0.5
18 20 Total mass 5 kg 5~10 40
19 14, 15,
16, 17,
21, 22
Variable adjustments of ports 3 m Pass Fail
20 22 Ports are sealable 5 Binary Pass Pass
21 23 HRS is thoroughly sealed and insulated 5 Binary Pass Pass
22 24 HRS can regulate the humidity levels in the
range between 5% to 95% relative humidity,
with the expected temperature levels for the
5 φ(%) 0-100 5-95
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
20
system between -20 degC to +40 degC, and
possible wind speeds reaching up to 11m/s
23 25 HRS follows the control setpoints accurately
and steadily
5 Subj. &
DL
True True
24 26 The scenarios and schedules for humidity
control system can be configured in a straight-
forward manner
4 DL &
subj.
True True
25 27 The user can see the humidity level side by
side with the actual humidity in the system
5 φ &
subj.
True True
26 28 The HRS can be error-resistant and is capable
of keeping the operator from making errors
whenever possible
5 DL &
subj.
True True
27 29 CFD models of the MOWCC 3 DL &
subj.
True Maybe
28 30 HRS is easy to turn on, and prevents
inadvertent switching off
5 DL &
subj.
True True
29 31 HRS can be dropped from height of 1 m and
still excel in operation
4 m 1 0.5
30 32 Filtering and separtion of
0.01 micrometer particles
4 µm 0.01 0.03
31 33 Cycles in operation without visible corrosion 4 cycles 106 10
4
32 34, 35 Time to dis-assembe /assemble for
mainteneance
4 seconds 600 1200
33 35 Special tools required for maintenance 5 subj. No Maybe
34 36 Focus group rating- appearance 5 subj. Great Good
35 37 Instills pride 5 subj. Yes Maybe
36 38 Focus group rating- professionalism 5 subj. Yes Yes
37 39 Emergency shutdown procedures/ sequences 5 Binary Pass Pass
38 40 Budget limit of maximum $200 5 $ 150 200
39 41 Air conditioning equimpment catalogue 3 List Yes Maybe
40 42 Noise measurement 4 dB 30 55
41 43, 44 Protection equimpment and labels are in place 5 subj. Yes Yes
42 44 Life cycle analysis and Hannover principles 4 subj. Yes Maybe
2.2.2.4. Reflection on the Results and the Process
In the course of establishing the tafget engineering specifications the customer needs have been
crystalized and the associative engineering targerts have been set. The competetive market analysis has
been performed, and as a result the ideal and the marginally acceptable target values for the engineering
specifications have been set.
2.2.3. Sub-Phase C: Setting the Final Specifications
2.2.3.1. A Technical Model of the Product
In writing, the project of interest is a humidity regulation system capable of adding and extracting the
humidity without affecting other components in the Modular Open Wind Climatic Chamber. However,
consider the following functional flow chart of MOWCC with the primary element of interest as the
humidity regulation system, figure 10. This figure demonstrates the components required for the
MOWCC completion, and the physical resources associated with it. The figure also demonstrates that for
some humidity change mechanisms the external mechanisms of temperature change may have to be
involved.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
21
Figure 10. Functional Charecteristics of the MOWCC’s Humidity Regulation System
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
22
2.2.3.2. Cost Model of the Humidity Regulation System
Table 7 provides approximate costing of materials for early estimates of the realistic tradeoffs in the
product specifications.
Table 4. Approximate Cost Model of HRS
Component Quantity
High ($ ea.) Low ($ ea.) High Total
($)
Low Total
($)
Insulation 6 22 7 132 42
Temperature
Sensors
Available Void Void Void Void
Humidity Sensors Available Void Void Void Void
Flow Sensor 2 100 20 200 40
Particles per
Volume Sensor
2 30 10 60 20
Controller 2 100 14 200 28
Control Program Available Void Void Void Void
Adsorptive
Material
2 500 20 1’000 40
Absorbtive
Material
2 200 15 400 30
Cooling Unit for
Model
1 100 30 100 30
Cooling Unit for
Stand-Alone
Chamber
1 300 40 300 40
Venting Unit ~2 60 10 120 20
Fan for model unit 1 40 10 40 10
Fan for Stand-
Alone Chamber
1
100 30 100 30
Misting
Equipment
Available Void Void Void Void
Fogging
Equipment
Available Void Void Void Void
Ducts ~4 40 20 160 80
Actuators ~6 30 10 180 60
Heat Exchangers 2 300
(36000BTU)
150
(3425 BTU)
600 300
Total - - - 3’592 770
It is apparent from table 7 that some serious tradeoffs have to be considered for a functioning humidity
regulation system or some extremely clever engineering has to be implemented in order to satisfy the
customer needs and meet all of the engineering specifications. Since, the budget limit for the whole
project is $200, then it is likely that some of the components may have to be sourced from second-hand
sites; as long as these components have replacement parts and are maintainable with the commonly
available tools and provide a satsfying performance it is likely that this strategy will be implemented. The
issue with picking the second hand components is that they may not provide a very professional look.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
23
2.2.3.3. The Specifications Refinement and Flow Down
By going over the approximate cost model of the HRS, and keeping in mind the customer requirements
and the engineering specifications, some tradeoffs have to be made as appropriate to maintaining the
original purpose of the HRS. Table 5 returns to the ideal and marginal metrics and re-iterates the Ideal
and marginal values according to latest evaluations and highlights the metrics most relevant to the
successful project completion.
Table 5. Ideal and Marginal target values refinement and highlights
Metrics
#
Needs
#s
Metric/
Engineering Spec.
Importace Units Ideal
Value
Marginal
Value
1 1, 2, 3 Humidity extraction and addition rate 4 kg/hr 8 4
2 4 Coefficient of performance on the
HRS cooling units
5 ratio 3 0.5
3 5 Negative feedback loop for set
humidity levels
5 DL Yes Yes
4 6 Auxiliary ventilation and air
conditioning
2 subj. Maybe No
5 7 Humidity setting is input via the
terminal and displayeld alongside with
the actual humidity reading
5 subj. Yes Yes
6 8 Manual for the HRS providing step by
step procedures
5 pages ~100 ~50
7 9, 12 Maximum temperature ranges from -
50 to +100 oC
4 oC -50 to
100
-20 to +40
8 10 Mechanism for flow regulation 3 subj. Yes Maybe
9 11, 13 HRS is error-tolerant, and if a fault
occurs over a specific time period the
HRS will take preventive actions and
return the system to the set conditions
or shut-down to prevent error
accumulation
5 seconds 0.0001 0.01
10 12, 13 Low thermal expansion materials 4 mm/ oC 0.1 0.5
11 13 Statistical analysis of HRS normal
performance
3 DL Yes Yes
12 14 Temperature variation is not affected
by the HRS operation and vice versa
4 oC/φ 1/10% 5/10%
13 15 TES performance is not affected by
the HRS operation and vice versa
4 oC/φ 1/10% 5/10%
14 16 Air-flow variation is not affected by
the HRS operation and vice versa
3 (m/s)/φ none 0.1/10%
15 17 Solar regulaion is not affected by the
HRS operation and vice versa
2 lum/ φ none 0.001/10%
16 18, 19 The whole HRS fits into a box of
dimensions less than 0.5m3 for the
two obligatory options (stand-alone
climatic chamber without the
operation of the primary wind
generating air fan and the system
5 m3 0.2 0.5
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
24
under test, such as a model building)
17 18, 19 The space factor of HRS is less than
1/12th of MOWCC
5 m3 0.2 0.5
18 20 Total mass 5 kg 5~10 30
19 14, 15,
16, 17,
21, 22
Variable adjustments of ports 3 m Pass Fail
20 22 Ports are sealable 4 Binary Pass Pass
21 23 HRS is thoroughly sealed and
insulated
5 Binary Pass Pass
22 24 HRS can regulate the humidity levels
in the range between 5% to 95%
relative humidity, with the expected
temperature levels for the system
between -20 degC to +40 degC, and
possible wind speeds reaching up to
11m/s
5 φ(%) 5-95 20-60
23 25 HRS follows the control setpoints
accurately and steadily
5 Subj. &
DL
True True
24 26 The scenarios and schedules for
humidity control system can be
configured in a straight-forward
manner
4 DL &
subj.
True True
25 27 The user can see the humidity level
side by side with the actual humidity
in the system
5 φ &
subj.
True True
26 28 The HRS can be error-resistant and is
capable of keeping the operator from
making errors whenever possible
5 DL &
subj.
True Maybe
True
27 29 CFD models of the MOWCC 3 DL &
subj.
True Maybe
28 30 HRS is easy to turn on, and prevents
inadvertent switching off
5 DL &
subj.
True Maybe
True
29 31 HRS can be dropped from height of 1
m and still excel in operation
4 m 1 0.5
30 32 Filtering and separtion of
0.01 micrometer particles
4 µm 0.01 0.03
31 33 Cycles in operation without visible
corrosion
3 cycles 106 10
4
32 34, 35 Time to dis-assembe /assemble for
mainteneance
4 seconds 600 1200
33 35 Special tools required for maintenance 3 subj. No Maybe
34 36 Focus group rating- appearance 3 subj. Great Good
35 37 Instills pride 3 subj. Yes Maybe
36 38 Focus group rating- professionalism 4 subj. Yes Yes
37 39 Emergency shutdown procedures/
sequences
5 Binary Pass Pass
38 40 Budget limit of maximum $200 5 $ 150 200
39 41 Air conditioning equimpment
catalogue
3 List Yes Maybe
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
25
40 42 Noise measurement 4 dB 30 55
41 43, 44 Protection equimpment and labels are
in place
5 subj. Yes Yes
42 44 Life cycle analysis and Hannover
principles
3 subj. Yes Maybe
A quality function deployment chart is available in the appendix that contains all the information relevant
to the design of the humidity regulation system. A portion of QFD summary is presented in table 6. The
complete QFD for the humidity regulation system is available in Appendix E.
Table 6. HRS QFD summary
Row Number
Quality Characteristics (a.k.a. "Functional Requirements" or
"Hows")
Minimize (▼),
Maximize (▲), or Target
(x)
Target or Limit Value
Max Relationship
Value Requirement
Weight
Relative Weight
(Relative Importance)
1 Humidity extraction and addition rate ▲ 8 9 246.11 2.76%
2 Coefficient of performance on the HRS cooling units
▲ 4 9 312.78 3.51%
3 Negative feedback loop for set humidity levels
x Yes 9 261.11 2.93%
4 Auxiliary ventilation and air conditioning ▼ Yes 9 45.56 0.51%
5 Humidity setting is input via the terminal and displayed alongside with the actual humidity reading
x Yes 9 308.33 3.46%
6 Manual for the HRS providing step by step procedures
x 100 9 253.89 2.85%
7 Maximum temperature ranges from -50 to +100 oC
x (-50 to 100) 9 237.78 2.66%
8 Mechanism for flow regulation x Yes 9 215.00 2.41%
9
HRS is error-tolerant, and if a fault occurs over a specific time period the HRS will take preventive actions and return the system to the set conditions or shut-down to prevent error accumulation
▲ 0.0001 9 238.33 2.67%
10 Low thermal expansion materials ▼ 0.1 9 178.33 2.00%
11 Statistical analysis of HRS normal performance
x Yes 9 201.67 2.26%
12 Temperature variation is not affected by the HRS operation and vice versa
x 1/0.1 9 197.22 2.21%
13 TES performance is not affected by the HRS operation and vice versa
x 1/0.1 9 197.22 2.21%
14 Air-flow variation is not affected by the HRS operation and vice versa
x none 9 190.56 2.14%
15 Solar regulation is not affected by the HRS operation and vice versa
x none 9 190.56 2.14%
16
The whole HRS fits into a box of dimensions less than 0.5m3 for the two obligatory options (stand-alone climatic chamber without the operation of the primary wind generating air fan and the
▼ 0.2 9 136.67 1.53%
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
26
system under test, such as a model building)
17 The space factor of HRS is less than 1/12th of MOWCC
▼ 0.2 9 195.56 2.19%
18 Total mass ▼ 5 to 10 9 220.00 2.47%
19 Variable adjustments of ports ▲ Pass 9 210.56 2.36%
20 Ports are sealable x Pass 9 241.67 2.71%
21 HRS is thoroughly sealed and insulated ▲ Pass 9 263.33 2.95%
22
HRS can regulate the humidity levels in the range between 5% to 95% relative humidity, with the expected temperature levels for the system between -20 degC to +40 degC, and possible wind speeds reaching up to 11m/s
x 0 to 100 9 508.89 5.70%
23 HRS follows the control setpoints accurately and steadily
x TRUE 9 308.33 3.46%
24 The scenarios and schedules for humidity control system can be configured in a straight-forward manner
▲ TRUE 9 217.22 2.43%
25 The user can see the humidity level side by side with the actual humidity in the system
x TRUE 9 296.11 3.32%
26 The HRS can be error-resistant and is capable of keeping the operator from making errors whenever possible
▲ TRUE 9 284.44 3.19%
27 CFD models of the MOWCC x TRUE 9 216.67 2.43%
28 HRS is easy to turn on, and prevents inadvertent switching off
x TRUE 9 141.11 1.58%
29 HRS can be dropped from height of 1 m and still excel in operation
▲ 1 9 92.22 1.03%
30 Filtering and separation of 0.01 micrometer particles
▲ 0.01 9 141.11 1.58%
31 Cycles in operation without visible corrosion
▲ 10^6 9 126.67 1.42%
32 Time to dis-assemble /assemble for maintenance
▼ 600 9 84.44 0.95%
33 Special tools required for maintenance ▼ No 9 92.78 1.04%
34 Focus group rating- appearance ▲ Great 9 144.44 1.62%
35 Instills pride ▲ Yes 9 426.67 4.78%
36 Focus group rating- professionalism ▲ Yes 9 259.44 2.91%
37 Emergency shutdown procedures/ sequences
x Pass 9 201.11 2.25%
38 Budget limit of maximum $200 x 150 9 103.33 1.16%
39 Air conditioning equipment catalogue ▲ Yes 9 252.78 2.83%
40 Noise measurement ▼ 30 9 82.22 0.92%
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
27
41 Protection equimpment and labels are in place
▲ Yes 9 161.11 1.81%
42 Life cycle analysis and Hannover principles x Maybe 9 239.44 2.68%
2.2.3.4. Reflection on the Results and the Process
Based on the iterative design methods of this chapter, the primary aspects of the humidity regulation
system were categorized and rated according to their importance. It has been conceived from the QFD
that among all the other things, the primary interest involving this project are the control parameters
asscociated with the humidity regulation system as well making the system very efficient during the
operation with the specific settings of the humidity. The cost models are really rough but they are in the
ball park of expected expedentures for the HRS, and hence they are used to motivate the innovative ideas
of elegant and cost effective engineering.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
28
2.2.4. Sub-Phase D: Concept Generation
2.2.4.1. Problem Clarification
The Humidity Regulation System (HRS) is decomposed into simpler sub-components via function
diagram show in figure 11.
Figure 11. Function diagram of humidity regulation system
The use of this diagram will benefit to guiding the concept creation process and choosing the alternatives
best suited for the MOWCC HRS. By following the requirements set by the MOWCC supervisor and the
engineering specifications, and by using the functional diagram as a guideline, the next step is to perform
a search of possible technologies that meet the criteria of HRS performance.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
29
2.2.4.2. Internal and External Idea Search
As per the lecture notes of ENGR 4950, the mechanical system, such as HRS, has form that is determined
by a function, and that form enables the predetermined function. If the function closely corresponds to the
desired output and matches with the behaviour of the designed system, then the design can be considered
successful. Systems like HRS have been previously designed an employed in a variety of situations, as
was observed in the competitors’ over-view. However, due to the high expenses of the competitor
products, and their in-compatibility with MOWCC, it has been deemed to make an HRS system that is
inexpensive, and is able to operate within the set limits of the customer requirements. The search for a
possible HRS solutions is done internally and externally throughout the concept creation process, and the
record of such search is presented along with the concepts generated. Hence, if any of the concepts
include some ideas obtained from any-person involved with the project, patents, published literature or
related products, these sources will be mentioned and noted for providing the concept ideas.
On the side note, the use of TRIZ may be possible for the HRS because there are several notable
contradictions involved with HRS:
1. The HRS has to be energy efficient at any rate of the humidity addition and removal, although the
power loss may be great.
2. The control system has to respond fast, although the system of humidity regulation depends on
the properties of air-water-mixture and its interaction with the environmental surfaces.
3. The HRS has to be durable and accurate, but the budget is limited and the professional quality
may be compromised.
By using the TRIZ website [18] the suggested principles of solving the above contradistions were:
1. Principles to solve this contradiction: Improving 22: Loss of Energy without damaging 21: Power
3. Local quality
Change an object's structure from uniform to non-uniform, change an external environment (or
external influence) from uniform to non-uniform. (Use a temperature, density, or pressure gradient
instead of constant temperature, density or pressure)
Make each part of an object function in conditions most suitable for its operation.
Make each part of an object fulfill a different and useful function.
38. Strong Oxidants (Redacted)
2. Principles to solve this contradiction:
Improving 9: Speed without damaging 27: Reliability
11. Beforehand cushioning
Prepare emergency means beforehand to compensate for the relatively low reliability of an object.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
30
35. Parameter changes
Change an object's physical state (e.g. to a gas, liquid, or solid.)
Change the concentration or consistency.
Change the degree of flexibility.
Change the temperature.
27. Cheap short-living objects
Replace an inexpensive object with a multiple of inexpensive objects, comprising certain qualities
(such as service life, for instance).
28. Mechanics substitution
Replace a mechanical means with a sensory (optical, acoustic, taste or smell) means.
Use electric, magnetic and electromagnetic fields to interact with the object.
Change from static to movable fields, from unstructured fields to those having structure.
Use fields in conjunction with field-activated (e.g. ferromagnetic) particles.
3. Principles to solve this contradiction:
Improving 16: Durability of non moving obj. without damaging 28: Measurement accuracy
10. Preliminary action
Perform, before it is needed, the required change of an object (either fully or partially).
Pre-arrange objects such that they can come into action from the most convenient place and without
losing time for their delivery.
26. Copying
Instead of an unavailable, expensive, fragile object, use simpler and inexpensive copies.
Replace an object, or process with optical copies.
If visible optical copies are already used, move to infrared or ultraviolet copies.
24. 'Intermediary'
Use an intermediary carrier article or intermediary process.
Merge one object temporarily with another (which can be easily removed).
These principles will also be used to draw ideas and if further contradictions occur during the concept
generation, the TRIZ method will be consulted to provide further ideas.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
31
2.2.4.3. Systematic Approach
The approach to the finding a set of possible concepts suitable for a feasible HRS is by means of
implementing the concept combination table for the three levels (Electrical Energy, Air, and Water). The
computer setting and sensor signal are not included because most of the sensor components are already
pre-determined by the project supervisor, and the control of the system will be done through LabView
program. The concepts that will be provided will elaborate on the features of the components that can
provide with function as per the customer requirements and the functional requirements.
Table 7. Concept Combinmation Table for Electrical Energy Conversion
Store or accept external
energy
Convert energy to thermal
form
(Extact or Add)
Condensate water on
surface
Add thermal energy to
water to mix water and
air
Pneumatic storage Vortex tube configuration Vertical staggered tube
arrangement
Misting system
Configuration
Electric field storage High convection
evaporative cooling
Vertical in-line tube
arangement
Ultrasonic mister
Use electric energy Thermo-electric peltier pile Mesh bafles Steam generation/
Water boiling
Standard refrigeration cycle Porous media
Strirling refrigeration cycle Absobant/adsobtive
circulation unit
(Dessicant Wheel)
Finned surface
Table 8. Concept Combinmation Table for Air Systems/ Humidity Extraction
Ventilate the air Move air over water
affinitive surface
Condensate water on
surface
Remove condensed
water from the surface
Single duct Fan Vertical staggered tube
arrangement
Fan
Double duct Vortex Tube Configuration Vertical in-line tube
arangement
Natural Convection
Natural convection Mesh bafles Electrostatic Repulsion
Porous media Shock “Hammering”
Absobant/adsobtive
circulation unit
Gravity Drain
Finned surface
Table 9. Concept Combinmation Table for Water Systems/ Humidity Addition
Store water Isolate some water for
humidification
Add thermal energy to
water to mix water and
air
Ventilate Air over the
mix to move humidified
Air
Basin Open surface Boiling Fan
Syringe Misting Air Preheat Natural Convection
Porous media Desiccant wheel Electrostatic Repulsion
The generated options for the HRS are presented in sketches withinin appendix F.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
32
2.2.4.4. Reflection on the Results and the Process
After generating a multitude of the potential sketches it was decided that the available sketches are
sufficient for further work and decision making. It appears that some clear candidates for implementation
are present, and in some cases the concepts may be altered or combined in a specific way that will yield
the best possible solution.
2.2.5. Sub-Phase E: Concept Screening and Scoring
In the previous section some concepts have been generated and outlined for making a Humidity
Regulation System (HRS). In this section, it will be outlined what are the rationale for choosing a specific
concept. The concepts will be ranked and rated, and then they may be further altered and combined to
produce an improved concept. After the alternations are employed it will be decided whether the new
design is good for further implementation.
2.2.5.1. Rationale Matrix
The rationale matrix is largely based on the previous experience with the customer and engineering
requirements. This rationale is primarily a set of questions which are outlined as follows:
A. Does the HRS have high rates of humidity extraction and/or addition?
B. Is the coefficient of performance of the HRS cooling unit above 1?
C. Is it easy to implement the negative feed-back loop in this system?
D. Is it possible to have the temperature ranges between -50 to +100?
E. Is HRS error-tolerant via the virtue of its design?
F. Does the variation of the humidity affect the temperature, and vice versa, very little?
G. Can the whole assembly be fit into a space of less than 0.2m3?
H. Can this design be light-weight?
I. Is it possible to thoroughly seal and insulate the design?
J. Does the design appear that it could regulate the humidity between 5% and 95% relative humidity ?
K. Does the design appear to have few control variables and still meet the criteria of its performance?
L. Does the design appear to have fewest possible components that need to be activated?
M. Does the design look like it is easy to assemble/dis-assemble and maintain?
N. Is the design affinitive to the emergency shutdown procedures?
O. Could this design be made under $100?
P. Does the design look like it could be quiet?
Q. Does the design look safe?
R. Does the design look environmentally benign?
These questions are used to evaluate the concepts generated during the sub-phase D. If a concept design
receives most “+” answers to the above questions, this design is a potential contender for the final design.
If the design has received most “-”s or “0”s then it is not very likely to be chosen, but it may be altered
and combined with other concepts to produce a legitimate and an over-all good design. The choice of
assigning “Yes” and “No” to specific concepts is based a litle bit on intuition, evaluation of pros and cons
and generally a good amount of common sense. As mentioned in Mr. Ulrich’s book [9], the choice made
during the concept selection will seriously constrain the upcoming manufacturing costs of the product,
and the project success. Hence, the importance of this stage is deeply acknowledged.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
33
2.2.5.2. Concept Ranking and Rating
Table 10 is a concept screening matrix used for ranking the concepts from sub-section D and appendix F.
Table 10. Concept Screening Matrix
Concepts
Rationale 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A 0 - + + + 0 0 0 + + 0 + + + 0
B - - - + + - - 0 0 0 - - - - -
C - - + 0 + + - 0 - - + - - + -
D 0 + 0 + + 0 0 0 0 0 + 0 0 + +
E - - 0 0 0 - - + + + - 0 - 0 0
F 0 + + + + 0 0 + + + 0 - - + +
G - + + 0 + + - + - - + + + + +
H - + + 0 + + - 0 0 0 + + + + +
I - + + 0 0 0 - + 0 0 0 0 0 - 0
J + - + + + 0 + 0 + + + 0 0 0 0
K - + + 0 + 0 - 0 0 - + 0 - + +
L 0 + 0 - + + 0 0 - - + - - + +
M - 0 0 - + + - + - - + - - 0 +
N - 0 + 0 + 0 - + + + + - - 0 +
O - + + 0 0 + - 0 0 0 + 0 - + 0
P - + + - 0 + - 0 0 0 + + + + +
Q + - + + + + + 0 + + 0 + - + +
R - 0 + - + + - 0 0 0 + + + + +
Sum +’s 2 9 13 6 14 9 2 6 6 6 12 6 5 12 11
Sum 0’s 4 3 4 8 4 7 4 12 8 7 4 6 10 4 5
Sum –‘s 12 6 1 4 0 2 12 0 4 5 2 6 3 2 2
Net
Score
-10 3 12 2 14 7 -10 6 2 1 10 0 2 10 9
Rank 15 8 2 9 1 6 14 7 11 12 3 13 10 5 4
Continue?
Y(es)
/
N(o)
/
C(ombine)
N N Y N Y C N C N N C N N C N
2.2.5.3. Concept Combinations and Improvements
According to the concept screening matrix, it appears that the potential candidate concepts, for the most
prominent design, are crystalizing further. However, at this stage it would make sense to consider whether
some of the concepts can be combined or improved in order to finalize the best suitable design. Also, as
per the customer requirements, the humidity regulation system has to be made for the model under test as
well as the stand-alone climatic chamber. Hence, one concept idea may work better for the model under
test system, while it may not necessary work for the independent climatic chamber. In fact, concept #3
appears well suited for the model HRS, and concept #5 may be better suited for a large space humidity
regulation, such is the climatic chamber. These concepts are improved and presented in the next section.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
34
2.2.5.4. Finalized Concepts Selection
The concepts below are the imroved versions of the top-most ranked concepts, with several modifications
as per the concept screening matrix. In the new sketches there is no dessicant wheels due to the additional
components required for wheel rotation, it is generally preferred that as many as reasonably possible
moving parts are avoided in the designs.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
35
2.2.5.5. Reflection on the Results and the Process
Based on the analysis of customer requirements, the engineering specifications, the concept generation
work and the concept selection the two sketches above are the most relevant for completing this project
with intention for success. Hence, the two chosen sketches are the foundation upon which the rest of the
project will be build.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
36
2.3. Phase 2: System-Level Design The functional break-down of the Humidity Regulation System for the model unit is shown in figure 12
Figure 12. Functional break-down of the model unit HRS.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
37
The functional break-down of the HRS for the test chamber is shown in figure 13.
Figure 13. Functional break-down of the test chamber HRS.
The fundamental and incidental interactions with the boundary components are identified in figure 14.
Figure 14. Fundamental and incidental interactions with the boundary components of HRS.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
38
The safety parameters for the HRS units are provided in table 11.
Table 11. Safety parameters of the HRS units
Model Unit HRS Test Chamber HRS
Component Safety Parameter Component Safety Parameter Solenoid Valves High impedance
devices, beware of
electric shock
Misting Assembly Distribution of mist may
cause chocking and eye
damage, wear protective
equipment Air Fan Rotating machinery, do
not touch the blades
while it is operating
Air Fan Rotating machinery, do
not touch the blades
while it is operating Air Filter May have contaminants
such as mildew and
pores, handle with care
Air Filter May have contaminants
such as mildew and
pores, handle with care Peltier Thermo-Electric
Cooler (TEC) Temperature difference
between two sides is up
to 70oC, beware of frost
bites and burns
Heat Dumping HX Temperature difference,
beware of burns.
Heat Exchanger(HX) for
TEC’s hot side Temperature difference,
beware of burns.
Humidity Extraction HX Temperature difference,
beware of frost bites. Humidity Extraction HX Temperature difference,
beware of frost bites.
High Torque Electrical
Actuators for Stirling
Refrigeration Cycle
High impedance
devices, beware of
electric shock Water Heating Element Temperature difference,
beware of burns.
Stirling Engine Chambers Moving equipment, do
not touch the
components while it is
operating Water Holding Chamber Temperature difference
and hot fluid, beware of
serious burns and steam.
Stirling Solenoid Valve High impedance
devices, beware of
electric shock
The environmental parameters that may affect the performance of the HRS units include:temperature
variations outside of the testing units, mishandling by the operators, flooding, explosions, and electronic
malfunction due to solar storms.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
39
The specific standards that may be relevant to the components of the HRS units may include the
following:
CSA Standards
C.S.A Standard B51-2009; Boiler, pressure vessel and pressure piping code
C.S.A. Standard B52-05; Mechanical Refrigeration Code
CSA C22.1-12; Canadian electrical code, safety standards for electrical
CSA C83-96; Communication and Power Line Hardware installations
ASME Standards
A.S.M.E Boiler and Pressure Vessel Code 2010
B31.1-2010 Power Piping
ASME-BPVC-SEC 10-2013; Fiber-reinforced plastics pressure vessel
ASME-BPVC-SEC 8 DIV 2-2013; Rules for construction of pressure vessels
ASME-BPVC-SEC 4-2013; Rules for construction of heating boilers
ASME-BPVC-SEC 6-2013; Recommended rules for the case and operation of heating boilers
The set points for the HRS units have to fit within the humidity levels in the range between 5% to 95%
relative humidity, with the expected temperature levels for the system between -20 degC to +40 degC,
and possible wind speeds reaching up to 11m/s.
The possible changes in component cohesiveness may include:
Structural design
Component orientation
Electric and electronic systems design
Control systems design within LabView
Size and dimensions
Sensor positions
The possible trade-offs of the individual components for the model unit HRS may include: not fitting
together due to different sizes and manufacturing practices, fan speed control only for segmented settings,
variety of voltage ranges required for proper operation of different components, and different sensetivity
to the control signals.
Due to the limited budget and extensive demands, the following selection of materials is made in the form
of bill of materials, with the corresponding descriptions. The materials with “*” beside their names
indicate that a data sheet is within the data-sheet folder of the enclosed DVD.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
40
Table 12. Bill of materials for the Model HRS
Name of the component Description of the Component Number of
Components
Price
$
Temperature Sensor* A K-type thermocouple linked to the
humidity extracting heat exchanger (HX),
the TEC’s hot side HX and inside the model
for taking the temperature readings in these
key points
3 Available on
site, no
purchase
necessary
Humidity Sensor* Sensor that detects relative humidity content
in the air within the model
1 Available on
site, no
purchase
necessary
Solenoid Valve* Regulates the steam addition in the HRS by
opening and closing at the demand of the
operator
1 ~13
Air Fan* One fan circulates the air in the HRS loop
and the other fan forces air over the TEC’s
HX. The air flow rate of the duct fan is
27CFM at 2050 RPM, and the TEC’s HX
fan has a flow rate of 4600 RPM
2 Available on
site, no
purchase
necessary
Air Filter Filter for dust and contaminants, meant to
keep bacterium and fungi out of the test
chamber and the working components of
HRS
1 ~20
Peltier Thermo-Electric Cooler
(TEC)*
The TEC units are the primary components
for extracting the humidity via the cooling
of the air, they also allow for a quick and
robust control directly via the electric
current. The available TECs have thermal
energy extraction rate of ~5.5W
2 ~11
Heat Exchanger(HX) for TEC’s
hot side
The HX is meant to remove excess heat
from the TECs and ventilate it away from
them in order to keep their performance in
the best condition
1 Scrap
Salvage
Linking conductor A copper plate linking the top and bottom
TECs to the same HX
1 5
Humidity Extraction HX A custom made HX from two aluminum
sheets and the films extending from one
sheet to the other
(figures are provided in the CAD section)
1 ~10
Water Heating Element A standard water heating element. 1 10
Water Confinement Chamber A stainless steel chamber, leak proof 1 5
Duct Works (Acrylic) A custom made ducts from acrylic sheets.,
which are just the right size and available.
Assembly out of
acrylic
Scrap
Salvage
Insulation An inch thick insulation to prevent energy
losses
1 sheet ~16
Total Price 90
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
41
Table 13. Bill of Materials for the Chamber HRS
Name of the component Description of the Component Number of
Components
Price
$
Temperature Sensor* A K-type thermocouple linked to the
humidity extracting heat exchanger (HX),
the TEC’s hot side HX and inside the model
for taking the temperature readings in these
key points
3 Available on
site, no
purchase
necessary
Humidity Sensor* Sensor that detects relative humidity content
in the air within the model
1 Available on
site, no
purchase
necessary
Misting Assembly* Regulates the mist addition in the HRS by
opening and closing at the demand of the
operator
1 Available on
site, no
purchase
necessary
Air Fan This fan circulates the air in the HRS loop. 1 ~30
Air Filter Filter for dust and contaminants, meant to
keep bacterium and fungi out of the test
chamber and the working components of
HRS
1 ~20
Heat Dumping HX A large heat exchanger meant for dumping
large amount of thermal energy outside of
the testing chamber
1 Available on
site, no
purchase
necessary
Humidity Extraction HX A custom made HX from the copper tubing
and the aluminum films extending from the
tubing system
1 ~10
High Torque Electrical
Actuators for Stirling
Refrigeration Cycle
The actuators are motors connected to a
worm-gear and a torque gear. They are
meant for driving the cooling and the
heating chambers of the Stirling
Refrigeration cycle
2 ~30
Stirling Engine Chambers Standard lawn mower engines with majority
of components removed and configured to
the Alpha-Stirling cycle configuration
2 Available on
site, no
purchase
necessary
Tubing and heat extracting
assembly
The tubing is connected to the Stirling
engines and it allows for the working fluid
(gas) circulation to the zones of heat
removal
2 !Additional
Funding
Request from
ERC! ~40
Stirling Solenoid Valve A valve that increases the overall
performance of the Stirling refrigeration
cycle
1 !Additional
Funding
Request from
ERC! ~15
Duct Works A custom made ducts from acrylic sheets.,
which are just the right size and available.
Assembly !Additional
Funding
Request from
ERC! ~30
Insulation An inch thick insulation to prevent energy
losses
1 sheet ~20
Total Price !191!
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
42
2.4. Phase 3: Detail Design The CAD drawings documenting the model unit HRS in the figures 15 through 23 show the model unit
HRS devices that were thought to be initially implemented in the creation of this system. Due to
unfortunate positioning of the metal film humidity extracting heat exchanger, however, these CAD
drawings will be altered to follow the original sketches and updated for accuracy for the the system that is
intended to be built.
Figure 15. HRS box contents isometric view, with tags for components
Figure 16. HRS box contents side view
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
43
Figure 17. HRS box contents Top View
Figure 18. HRS box contents Cross-Section Side View
*Note: Water container has a heating element for generating steam
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
44
Figure 19. Ducting System within the model house Side View
Figure 20. Ducting System within the model house Top View Floor 1
Figure 21. Ducting System within the model house Top View Floor 2
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
45
Figure 22. Ducting System within the model house Isometric View
Figure 23. The picture on the left depicts the heat exchanger in the staggered tube bank configuration. The
picture on the right depicts the film heat exchanger configuration. The explanation of why the staggered
tube bank was rejected can be found in appendix G.
Need to include dimensions and bill of materials
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
46
2.5. Phase 4: Design Fundamental Simulations and Analysis The humidity regulation system analysis is a multi-discipline process, it includes:
Thermodynamics
Heat transfer
Fluid Mechanics
Electric Circuits
Control System
In this section only the key analysis procedures will be highlighted,Thermodynamics and Heat Transfer,
because these procedures are most relevant to the design of the humidity addition and extraction units.
1. Thermodynamics
Humidity Addition
Air with temperature of Tin [oC] and a wet bulb temperature of Twbin [
oC] enters a steam-spray
humidifier. The mass flow rate of air is m’air [kg/min]. Saturated water vapor (steam) at Tst [oC] is
injected into the mixture at a rate of m’st [kg/min]. Assuming that the heat transfer with the
surroundings is negligible, and the pressure is assumed to be constant throughout at 1.013 [bar]. The
following needs to be determined at the exit of the humidification system:
a) The humidity ratio
b) The temperature in [oC]
Assumptions:
-Heat transfer with surroundings is negligible
-Pressure is constant throughout the system at 1.013 [bar]
-The system is assumed to be a control volume operating at a steady state
Properties:
-The psychrometric properties apply
-The fluid in this scenario is an air-water mixture or moist air
Analysis:
a) The humidity ratio at the exit ω2 can be found from the mass rate balances on the dry air and water
individually. Hence:
=> , &
.:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
47
Using the dry-bulb temperature, Tin [oC], and the inlet wet bulb temperature, Twbin [
oC], the value of
the humidity ratio ω1 can be found by inspection of the psychrometric chart from EES. The result is
ω1= [kg(vapor)/ kg(dry air)], which can be verified by the above equation:
b) The temperature at the exit can be determined using an energy rate balance, as long as the
assumptions apply. The specific enthalpies of water vapor at inlet(1) and outlet (2) are evaluated at
the respective saturated vapor values, and hg3 denotes the enthalpy of the saturated vapor injected into
the air
The first term on the right can be obtained from the psychrometric chart at the state defined by the
intersection of the inlet dry-bulb temperature, Tin [oC], and the inlet wet-bulb temperature, Twbin [
oC]:
[kJ/kg(dry air)]. The second term on the right can be evaluated with the known humidity ratios ω1 and
ω2 and the value hg3 from the table of properties for the saturated water (liquid-vapor).: [kJ/kg(dry
air)]. The state of at the exit is fixed by ω2 and (ha2+ω2*hg2)= [kJ/kg(dry air)]. The temperature at the
exit can be either read from the psychrometric chart or obtained from the EES software.
Humidity Addition
Water exiting the humidification nozzle at Tnozzle [oC] enters the humidification unit with a mass flow
rate of m’mist [kg/h]. A stream of cooled water is returned to replenishment chamber from the
humidification unit with a temperature of Twout [oC] and the same flow rate. The air from the test
chamber enters the humidification unit at Tain [oC] and φain % relative humidity. The moist air exits
the humidification unit at Taout [oC] and φaout % relative humidity. Assuming that the heat transfer with
the surroundings is negligible, and the pressure is assumed to be constant throughout at 1.013 [bar].
The following needs to be found out:
The process is reminiscent to the analysis presented in engineering thermodynamics by Michael J.
Moran.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
48
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
49
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
50
Humidity Extraction
Moist air at Tin [oC] and φ% relative humidity enters a dehumidifier operating at a steady state with a
volumetric flow rate of V’ [m3/min]. The moist air passes over a cooling sheets and water vapor
condenses. Condensate exits the dehumidifier saturated at Tw [oC]. Saturated moist air exits in a
separate stream at the same temperature. Assuming that the heat transfer with the surroundings is
negligible, and the pressure is assumed to be constant throughout at 1.013 [bar]. The following needs
to be found out:
a) The mass flow rate of the dry air, in kg/min
b) The rate at which water is condensed, in kg of dry air flowing through the control volume
c) The required regenerating capacity in kW
Assumptions:
-Heat transfer with surroundings is negligible
-Pressure is constant throughout the system at 1.013 [bar]
-The system is assumed to be a control volume operating at a steady state
-Changes in kinetic and potential energy can be neglected, Wcv=0
-The air exiting the de-humidification unit is assumed to be saturated
-The condensate exits through a condensation port as a saturated liquid at temperature Tout
Properties:
-The psychrometric properties apply
-The fluid in this scenario is an air-water mixture or moist air
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
51
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
52
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
53
The CFD model for the vertical plate HX is provided
Figure 24. Temperature distribution of the film HX
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
54
2. Heat transfer
Humidity Extraction
The moist air at atmospheric pressure condenses on a h[m] high and l[m] long vertical plate
maintained at Ts [oC] by activation of a Peltier Thermo-Electric Cooler (TEC). What needs to be
found out is the following:
a) The rate of heat transfer by condensation to the plate
b) The rate at which the condensate drips off the plate at the bottom
This process is take out from Professor Yunus Cengel’s book “Heat and Mass Transfer”
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
55
Refrigerating Stirling Cycle Mechanism:
For the chamber unit, a Stirling refrigeration cycle will be used. The operation of this cycle is
described by the use of figures 5 and 6.
Figure 25. Components of the Alpha-Type Stirling Engine.
Figure 26. Stirling Cycle sequence
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
56
1. Most of the working gas is in contact with the cylinder walls, the volume expansion has lead
to the bottom of its travel in the cylinder, and the corresponding decrease in the temperature has
followed. The expansion continues in the hot cylinder, which is 45° ahead of the cold piston in
its cycle.
2. The gas is now at its maximum volume. The cold cylinder piston begins to move most of the
gas into the hot cylinder, where the heat is dumped into the environment, and the pressure drops.
3. Almost all the gas is now in the hot cylinder and cooling continues. The hot piston, powered
by outside motor, compresses the remaining part of the gas.
4. The gas reaches its minimum volume, and it will now expand in the cold cylinder where it will
extract thermal energy once more, and continue on the cycle.
Since, the theory of operation of the Stirling Cycle is fairly complex due to the regenerator, the
theory of its operation is not present in this report.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
57
3. Conclusions After an extensive research and involvement with the project the following milestones are verified to have
been met: the planning stages are complete, the concept process and selection process is complete and the
analysis of the final concept has formed a stream towards successful completion. Based on the above
analyses it can be concluded that the chosen designs are in step with the customer requirements and the
engineering specifications set prior to the concept generation. The future steps will involve finalising
analysis for the designs, creating control systems in LabView, and creating appropriate circuits for
components in the system.
4. Acknowledgements I would like to personally thank the FESNS team, Dakota Watson, Jonathan Allcock, Nandine
Kanesalingam, and Jason Runge with whom I’ve been collaborating on the Modular Wind Climatic
Chamber and generally enjoying the conversations and discussion in regard to the project and the
miscalleneous. Also, I would like to thank the lab supervisors Robert Ulrich and Bradley MacInnis, who
share their knowledge and experience with our team and help us out in making this project. Many thanks
to Professor Nokleby and group G06-01 for making the presentation possible on a short notice.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
58
References [1] Yunus A. Cengel, Michael A. Boles, “THERMODYNAMICS, An Engineering Approach, 5
th
edition”, McGraw-Hill, pp. 1-881, New York, 2006
[2] Yunus A. Cengel, “HEAT AND MASS TRANSFER, A Practical Approach, 3rd
edition”, McGraw-
Hill, pp. 1-901, New York, 2007.
[3] Hou, S., et al., “An open air-vapor compression refrigeration system for air conditioning and
desalination on a ship”, Desalination, Vol. 222, pp. 646-655, 2008.
[4] Description of thermoelectric plate: “Thermoelectric Cooler - 40x40mm”. Author : Sparkfun
Online Resource: https://www.sparkfun.com/products/10080
[5] Jia, C.X., et al., “Experimental comparison of two honeycombed desiccant wheels fabricated
with silica gel and composite desiccant material”,Energy Conversion & Management, Vol. 47,
pp. 2523-2534, 2006.
[6] Safronsky, E.D., et al., “Application of porous glasses for humidity control”, Optical
Materials, Vol 5, pp. 217-220, 1996.
[7] Wang, R.M., et al., “Preparation of acrylate-based copolymer emulsion and its humidity
controlling mechanism in interior wall coatings”, Progress in Organic Coatings, Vol 71, pp. 369-
375, 2011.
[8] Mohanraj, M., et al., “Applications of artificial neural networks for refrigeration, air-conditioning and
heat pump systems- A review”, Renewable and Sustainable Energy Reviews, Vol. 16, pp. 1341-1358,
2012.
[9] “Product Design and Development, 3rd
ed.”, Karl T. Ulrich, Steven D. Eppinger, McGraw Hill,
pp.366, New York, 2004.
[10] Dr. Pop-Iliev’s Lectures for ENGR 4950U [make a proper refernce]
[11] GUNT Hamburg website: http://www.gunt.de/static/s1_1.php
[12] DRI-EAZ:
http://www.grainger.com/product/6UFY3?cm_sp=HIO-_-HIDP-_-
RR_VTV70300505&cm_vc=IDPRRZ13
http://www.grainger.com/product/DRI-EAZ-Dehumidifier-Filter-6UFY4?opr=OAPD&pbi=6UFY3
http://www.grainger.com/product/4AYF4?cm_sp=HIO-_-HIDP-_-
RR_VTV70300505&cm_vc=IDPRRZ13
[13] Novel Air:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
59
http://www.allergybuyersclub.com/novelaire-comfort-plus-300-desiccant-electric-
dehumidifiers.html?itemId=1907
[14] DEZ-AIR:
http://www.allergybuyersclub.com/dezair-dez1100-dehumidifiers.html?itemId=3154
[15] FANTECH:
http://www.grainger.com/product/3H356?cm_sp=HIO-_-HIDP-_-
RR_VTV70300505&cm_vc=IDPRRZ13
[16] DAYTON:
http://www.grainger.com/product/DAYTON-Dehumidifier-5EAJ3?opr=APPD&pbi=3H356
[17] Air O Swiss:
http://www.allergybuyersclub.com/air-o-swiss-s450-steam-humidifier.html?itemId=3354
http://www.allergybuyersclub.com/airoswiss-7142-humidifiers.html?itemId=1369
[18] TRIZ website: http://www.triz40.com/
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
60
Appendix:
A. Project Gantt Charts
Figure A1. The expected first 24 tasks of the group
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
61
Figure A2. Group’s expected tasks 25 to 55
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
62
Figure A3. Group’s expected tasks 25 to 55
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
63
Figure A4. Humidity regulation system Gantt chart.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
64
B. The project planning schedule of the sequential tasks for the Humidity
Regulation System Table B1. The project planning schedule of the sequential tasks for the Humidity Regulation System
Project Planning
Design Organization: UOIT MOWCC Team Date: October 28 2013
Product: Humidity Regulation System
Task 1 Name of the Task: Re-Iterate 1st Chapter
Objective: Make sure that the content of the 1st chapter is concise
Deliverables: Edited 1st chapter leads to clarifying the scope and fixing any grammatical
error, it is meant to primarily have a clear objective over the course of the whole project
Decisions Needed: (simulation, testing, prototype manufacture)
Decision: If there is no grammatical error, if the scope and objectives are clear then
proceed
Personnel Needed: Daniel Bondarenko
Time Estimate:
2 day (25/10/13 to 26/10/13)
Costs: 0
Task 2 Name of the Task: Clear the Report and Organize the Design Layout
Objective: Organize the project report in accordance with the respective phases and
with respect to the cap-stone requirements (Defined as information to be refined and
developed , specific)
Deliverables: A clear project report layout
Decisions Needed: Decide how the lecture notes match to the reference book for
approaching the design
Personnel Needed: Daniel Bondarenko
Time Estimate:
1 day (25/10/13 to 25/10/13)
Costs: 0
Task 3 Name of the Task: Phase 0 Product Planning
Objective: Make a plan that will provide an approach to make a great humidity
regulation system
Deliverables: A clear project strategy of how to approach the project and successfully
complete it within the limited time
Decisions Needed: Decide on what plan will lead towards successful completion of the
project.
Personnel Needed: Daniel Bondarenko, Jason Runge, Dakota Watson, Nancy
Kanesalignam , Dr. Agelin-Chaab, Professor Perera
Time Estimate:
6 days (20/10/13 to 25/10/13)
Costs: 0
Task 4 Name of the Task: Phase 1 Concept Development
Objective: Create about 10 concepts for possible humidity regulation systems
Deliverables: The concept designs for the humidity regulation system
Decisions Needed: Decide what are the best possible options for regulating humidity in
MOWCC single chamber and the model house
Personnel Needed: Daniel Bondarenko
Time Estimate:
35 days (23/09/13 to 08/11/13)
Costs: approximately 5% of budget or $10
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
65
Task 5 Name of the Task: Sub-Phase A Identify Customer Needs
Objective: Get to know and understand the customer requirements and record them
accordingly
Deliverables: Clear record of customer requirements
Decisions Needed:
Decide when to draw the line for customer specifications to gather all the
necessary information for the project and to avoid any creeping specifications
in the future
Decide what needs have the greatest importance to successful completion of he
project and decide what needs may not be expressed directly, or latent
Personnel Needed: Daniel Bondarenko, Jason Runge, Dakota Watson, Nancy
Kanesalignam , Dr. Agelin-Chaab, Professor Perera
Time Estimate:
5 days (25/10/13 to 31/10/13)
Costs: approximately 1% of budget or $2
Task 6 Name of the Task: Sub-Phase B Establish Target Specifications
Objectives:
Prepare a List of Needs Metrics Matrix
Prepare a List of Physical Metrics Matrix
Collect Competitive Benchmarking Information
Set Ideal and Marginally Acceptable Target Values
Reflect on the Results and the Process
Deliverables:
A clear matrix of needs metrics
A clear matrix of physical metrics
Any additional information on state of the art technologies in humidity
regulation
Decisions Needed: Decide when the collected information is within limits of the project
so that further collection of information does not create a lag for the rest of the project
milestones and deadlines
Personnel Needed: Daniel Bondarenko
Time Estimate:
5 days (28/10/13 to 01/11/13)
Costs: approximately 1% of budget or $2
Task 7 Name of the Task: Sub-Phase C Setting the Final Specifications
Objectives:
Develop technical models of the product Develop a cost model of the product
Refine the Specifications (making trade-offs where necessary)
Flow down the specifications as appropriate
Reflect on the results and the process
Deliverables:
The four different representations of the conceptual designs (Semantic,
Graphical, Analytical, and Physical)
Cost model of the product
Clarification of all the specifications and requirements
Decisions Needed: Decide on how to make the representations effective to convey the
message about the advantage of a specific technology.
Personnel Needed: Daniel Bondarenko, Jason Runge, Dakota Watson, Nancy
Kanesalignam , Dr. Agelin-Chaab, Professor Perera, Robert Ulrich
Time Estimate:
4 days (29/10/13 to 01/11/13)
Costs: approximately 1% of budget or $2
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
66
Task 8 Name of the Task: Sub-Phase D Concept Generation
Objectives:
Clarify the by decomposing a comlex problem into simpler subproblems
Search Externally for Ideas
Search Internally for Ideas
Explore Ideas Systematically
Deliverables:
Interviews with lead users
Expert consultations
Patents Search
Research of published literature
Benchmarks of related products
Concept Classification Tree
Concpet Combinmation Table
Management of the Exploration Process
Decisions Needed: Decide on what is the most relevant information that is crucial for
making the project competitive and successful
Personnel Needed: Daniel Bondarenko
Time Estimate:
6 days (02/11/13 to 08/11/13)
Costs: approximately 1% of budget or $2
Task 9 Name of the Task: Sub-Phase E Concept Screening and Scoring
Objectives:
Prepare the Selection Matrix
Rate the Concepts
Rank the Concepts
Combine and Improve the Concepts
Select one or more Concepts
Reflect on the Results and the Process Deliverables: A specific concept that meets all the criteria required by the project
Decisions Needed: Decide on what methods of selection provide the benefits for the
customer and follow in compliance with the physical limitations of the product
Personnel Needed: Daniel Bondarenko
Time Estimate:
6 days (01/11/13 to 08/11/13)
Costs: approximately 1% of budget or $2
Task 10 Name of the Task: Phase 2 System Level Design
Objectives:
Create a Schematic of the Product (Functional Break Down)
Cluster the Elements of the Schematic
Identify the Fundamental and Incidental Interactions
Identify Safety Parameters
Identify Environmental Parameters
Identify Specific Standards Relevant to the Components
Create a Rough Geometric Layout of the Product Boundaries of the Interacting
Elements
Identify the Set Points for Components` Performance
Identfy any Possible Changes for the Component Cohesiveness
Identify the Variety of the Components Used in the Project and Corresponding
Costs
Identify Standard Components to be Used in the the System and
Corresponding Costs
Consider the Options for the Manufacturability and Corresponding Costs
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
67
Identify the Tradeoffs of Individual Components
Identify the Tradeoffs of the System as a Whole
Deliverables:
A Schematic of the Product (Functional Break Down)
The Schematic Elements Cluster
Identify the fundamental and incidental interactions
Identified safety parameters
Identified environmental parameters
Identified specific standards relevant to the components
Rough geometric layout of the product boundaries of the interacting elements
Identified the set points for components` performance
Identfied any possible changes for the component cohesiveness
Identified the variety of the components used in the project and their
corresponding costs
Identified standard components to be used in the the system and their
corresponding costs
The options for the manufacturability and corresponding costs
Identified tradeoffs of individual components
Identified tradeoffs of the system as a whole
Decisions Needed: Decide on the level of detail for all the deliverables of this task
Personnel Needed: Daniel Bondarenko, Jason Runge, Dakota Watson, Nancy
Kanesalignam , Dr. Agelin-Chaab, Professor Perera
Time Estimate:
2 days (25/10/13 to 27/10/13)
Costs: approximately 2.5% of budget or $5
Task 11 Name of the Task: Phase 3 Detail Design
Objectives:
Identfy the functional needs
Identify safety parameters
Identify environmental parameters
Identify the form of the project (Ergonomics and Aesthetics) Identify specific standards relevant to the components
Preliminary refinement of selected concepts
Further refinement and final concept selection
Creation of control drawings and schematics
Identify the material options for use in design
Deliverables:
Functional needs
Safety parameters
Environmental parameters
Form of the project (Ergonomics and Aesthetics)
Specific standards relevant to the components
Refined of selected concepts
Refined and final concept selection
Control drawings and schematics
Identify the material options for use in design
Decisions Needed: Decide on the level of detail for all the deliverables of this task
Personnel Needed: Daniel Bondarenko
Time Estimate:
7 days (10/11/13 to 16/11/13)
Costs: approximately 2.5% of budget or $5
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
68
Task 12 Name of the Task: Phase 4 Design Analysis
Objective: Complete the fundamental simulation and analysis, and the Design for X
procedures
Deliverables: Simulation foundations for the models to work
Decisions Needed: Decide how to manage the time between the simulation work and
the design work for X.
Personnel Needed: Daniel Bondarenko, Jason Runge, Dakota Watson, Nancy
Kanesalignam , Dr. Agelin-Chaab, Professor Perera
Time Estimate:
7 days (10/11/13 to 16/11/13)
Costs: approximately 5% of budget or $10
Task 13 Name of the Task: Sub-Phase A Fundamental Simulations and Analysis
Objectives:
Evaluate the design components for physical compatibility
-Make simulation of electronic components
-Make Simulation of thermal effects for the relevant components
-Make the finite element analysis for stress and displacement for the relevant
Components
-Make the Computational Fluid Dynamics analysis for the relevant
components
-Make the System Analysis Simulation for component coherence and
integration
Identify all Safety parameters and concerns
Create the safety procedure for safe operation
Identify environmental issues related to the project as a whole
Identify procedures to prevent and avoid environmental issues for the project
Identify the maintenance and repair procedures for the components
Coordinate with engineering, manufacturing, and external vendors
Deliverables:
Simulations of electronic components
Simulations of thermal effects for the relevant components
Finite element analysis for stress and displacement for the relevant
Components
Computational Fluid Dynamics analysis for the relevant components
System Analysis Simulation for component coherence and integration
Safety parameters and concerns
Safety procedure for safe operation
Environmental issues related to the project as a whole
Procedures to prevent and avoid environmental issues for the project
Maintenance and repair procedures for the components
Decisions Needed: Decide how to comply with objectives and provide the deliverables
within the limited time
Personnel Needed: Daniel Bondarenko, Hidayat Shahid, Dr. Aruliah, Jason Runge,
Dakota Watson, Nancy Kanesalignam , Dr. Agelin-Chaab, Professor Perera.
Time Estimate:
4 days (10/11/13 to 13/11/13)
Costs: approximately 2.5% of budget or $5
Task 14 Name of the Task: Sub-Phase B Design for X
Objective: Meet as many DFX deliverables as possible for this project
Deliverables:
Design for
-Safety
-Quality
-Cost
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
69
-Standards
-Electronic Components
-Manufacturing
-Assembly
Decisions Needed: Decide how to keep costs to the very minimum and meet all of the
requirements for the project completion
Personnel Needed: Daniel Bondarenko, Jason Runge, Dakota Watson, Nancy
Kanesalignam , Dr. Agelin-Chaab, Professor Perera, Robert Ulrich.
Time Estimate:
4 days (13/11/13 to 16/11/13)
Costs: approximately 2.5% of budget or $5
Task 15 Name of the Task: Test Plans and Results
Objective: To write a narrative description of test plan(s), and to use tables, graphs, and
wherever possible show the results. It is intended that this section forms the written
record of the design performance against specifications. Deliverables:
A description of how to test the final system and any additional features that will be
included in the design to facilitate the testing.
Decisions Needed: Decide what makes a description of the testing procedure consistent
and understandable.
Personnel Needed: Daniel Bondarenko
Time Estimate:
12 days (01/12/13 to 16/12/13)
Costs: approximately 5% of budget or $10
Task 16 Name of the Task: Phase 5 Testing and Refinement
Objective:
Look back on all the steps that have been done over the course of the design
project and decide how to make a the test procedure for the project
Make sure that all the data from analysis makes sense
Scrutinize own work
Make sure that the project has not deviated from its original scope
Apply Common Sense to the Project in its Current State and confirm that it
makes Sense
Make any iterations if needed
Once testing is verified proceed to next phase Deliverables: A clear layout to test the product prototype
Decisions Needed: Decide on a strategy to extract the desired behaviour from the
product based on the product functions and find the testing procedure that will not
damage the product and yield the performance outputs as per the functional inputs
Personnel Needed: Daniel Bondarenko
Time Estimate:
12 days (02/01/14 to 17/01/14)
Costs: approximately 5% of budget or $10
Task 17 Name of the Task: Phase 6 Proof of Concept/ Functional Prototype
Objective: Construct the the prototype to to detect un-anticipated phenomena and
observe the behaviour
Deliverables:
Define the purpose of the of the prototype
Establish the level of approximation of the prototype
Outline of experimental plan
A Schedule for procurement, construction, and testing
A Plan for milestone prototypes Decisions Needed: Decide how to make the prototype most demonstrative of the
humidity regulation system.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
70
Personnel Needed: Daniel Bondarenko, Robert Ulrich
Time Estimate:
17 days (25/10/13 to 16/12/13)
Costs: approximately 5% of budget or $10
Task 18 Name of the Task: Bill of Materials
Objective: Create a detailed bill of materials with included (if possible) manufacturer,
part number, part description, supplier, quantity, and cost. Deliverables: A full bill of materials providing the detailed descriptions of the parts and
components involved in the project.
Decisions Needed: Decide how to describe the materials involved in the project so that
they would be understandable and visually appealing
Personnel Needed: Daniel Bondarenko
Time Estimate:
37 days (25/10/13 to 16/12/13)
Costs: approximately 60% of budget or $120
Task 19 Name of the Task: Ethical Considerations
Objective: Act in accordance to ethics and law throughout the project
Deliverables: Respectable and civil organization and execution of the project
Decisions Needed: Only ethical decisions honoring the opinions of members of the
project and its stakeholders
Personnel Needed: All team members involved with MOWCC
Time Estimate:
174 days (01/09/13 to 30/04/14)
Costs: If fail to follow ethics the cost is the moral values
Task 20 Name of the Task: Safety Considerations
Objective: During the entire project has to always follow safety procedures and never
cut corners on personal and member safety
Deliverables: A safe product and a safe process for achieving such product.
Decisions Needed: Only decisions that lead to the safe performance and safe execution
of the project.
Personnel Needed: All team members involved with MOWCC
Time Estimate:
174 days (01/09/13 to 30/04/14)
Costs: If fail to follow safety the cost can be life!
Member: Daniel
Bondarenko
Prepared by: Daniel Bondarenko
Approved by:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
71
C. Organized hierarchy of customer needs Table C1. Organized hierarchy of customer needs
Category Primary Need Secondary Need
1. Modes of operation and
automation
***HRS can regulate
humidity levels in a
model under test (such
as a house)
***HRS can regulate
humidity levels in a
stand-alone climatic
chamber
*HRS can regulate humidity levels in
the complete MOWCC with a through
air-flow
2. Predictable:
the operator must be able to
anticipate and rely upon
automation’s actions
**The HRS efficiently
utilizes the energy to
extract humidity
(Heat exchanging
process for humidity)
**Capable of maintaining the space
humidity at a constant level over a long
period of time without additional
energy input
**Can extract humidity from very
damp (almost soaking) environments
***The HRS is simple to operate,
maintain, and keep
3. Accountable:
must inform user of its
actions
must be able to explain
actions upon user request
***The HRS can
easily to start
humidity extraction
and infusion
(Heat exchanging
process for humidity)
**The HRS has an available guide
menu that can show the process of
using the terminal
4. Adaptable:
must be configurable within a
wide range of user
preferences and needs
**The HRS can easily
tolerate a range of
environments without
affect on its
performance
(HRS layout)
*The HRS can prevent the air
counterflow events
**The HRS is robust during operation
**The HRS can withstand high
fluctuations in temperature
***The HRS operates normally after
repeated use
5. Comprehensible:
must be intelligible to the
user, must match user mental
model
***The HRS is
capable of integrating
with other components
of MOWCC
(HRS layout)
***The HRS is easily integratable with
the temperature regulation and
monitoring unit
**The HRS is easily integratable with
the thermal energy storage unit
(geothermal storage)
**The HRS is easily integratable with
the wind flow regulation and
monitoring system
*The HRS is easily integratable with
the solar radiation regulation and
monitoring unit
6. Flexible:
must have a range of control
and management options
**The HRS is small
and light
(HRS layout)
*The HRS can be positioned anywhere
in the MOWCC without affecting
performance of other components
***The HRS can be easily removed
from MOWCC to be maintained and
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
72
cleaned
***The HRS is
modular
(HRS layout)
*The HRS can be transferred to a
Hydrogen genetaion unit or the natural
gas cleansing unit and operate without
a hinge
***The HRS doe not have any leaks
that would prevent from proper
operation during the re-installation
7. Subordinate
must never assume control,
except in pre-defined
situations, must be
countermandedin those
situations
***The HRS is easy to
control
(Diagnostics)
***The user can easily alter the
settings without damaging the
performance of the HRS
**!The settings can be “locked on” a
specific humidity regulation scenario
or schedule
***The HRS is informative by its
capability to display the actions
performed by the user as well as the
system status
***The humidification and de-
humidification processes are non-
conflicting and can alternate without
hindering performance of HRS
*!The HRS performance can be
followed visually via the realtime CFD
display of the existing system
8. Dependable
must do what it is ordered to
do, must never do what it is
not ordered to do, must never
make the situation worse
***The HRS is easy to
set up and use
(HRS layout)
***The HRS lasts a
long time and survives
heavy use
(HRS layout)
**The HRS self-cleans from air
contaminants like dust, bacteria, and
fungi
***The HRS does not corrode during
operation
***The HRS is easy to maintain
** HRS can be maintained with readily
available tools
***The HRS is
visually appealing
(User interface)
**Instills pride to the people operating
and the people observing the sysem
***The HRS looks like a professional
quality unit
**The HRS prevents
any damage to the
system under test
(HRS layout)
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
73
***Inexpensive
(HRS layout)
**The HRS
implements existing
components for
operation
**The HRS has a
pleasant sound when
in use
(User interface)
***The HRS is safe
(Use of intermediary
heat exchanging fluid
& HRS layout)
**!The HRS components are protected
from accidental floods, shortings,
temperature variations, and explosions
**!The HRS employs environmentally
safe technologies and components
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
74
For table C2, dimensionless units are represented by “DL” and subjective atributes are represented by
“subj.” .
Table C2. HRS metrics list
Metrics
#
Needs #s Metric Importace Units
1 1, 2, 3 Humidity extraction and addition rate 4 kg/hr
2 4 Coefficient of performance on the HRS cooling units 5 ratio
3 5 Negative feedback loop for set humidity levels 5 DL
4 6 Auxiliary ventilation and air conditioning 3 subj.
5 7 Humidity setting is input via the terminal and displayeld
alongside with the actual humidity reading
5 subj.
6 8 Manual for the HRS providing step by step procedures 5 pages
7 9, 12 Maximum temperature ranges from -50 to +100 oC 4
oC
8 10 Mechanism for flow regulation 3 subj.
9 11, 13 HRS is error-tolerant, and if a fault occurs over a specific
time period the HRS will take preventive actions and return
the system to the set conditions or shut-down to prevent
error accumulation
5 seconds
10 12, 13 Low thermal expansion materials 4 mm/ oC
11 13 Statistical analysis of HRS normal performance 3 DL
12 14 Temperature variation is not affected by the HRS operation
and vice versa
4 oC/φ
13 15 TES performance is not affected by the HRS operation and
vice versa
4 oC/φ
14 16 Air-flow variation is not affected by the HRS operation and
vice versa
3 (m/s)/φ
15 17 Solar regulaion is not affected by the HRS operation and
vice versa
2 lum/ φ
16 18, 19 The whole HRS fits into a box of dimensions less than
0.5m3 for the two obligatory options (stand-alone climatic
chamber without the operation of the primary wind
generating air fan and the system under test, such as a
model building)
5 m3
17 18, 19 The space factor of HRS is less than 1/12th of MOWCC 5 m
3
18 20 Total mass 5 kg
19 14, 15,
16, 17,
21, 22
Variable adjustments of ports 3 m
20 22 Ports are sealable 5 Binary
21 23 HRS is thoroughly sealad and insulated 5 Binary
22 24 HRS can regulate the humidity levels in the range between
5% to 95% relative humidity, with the expected temperature
levels for the system between -20 degC to +40 degC, and
possible wind speeds reaching up to 11m/s
5 φ(%)
23 25 HRS follows the control setpoints accurately and steadily 5 Subj. &
DL
24 26 The scenarios and schedules for humidity control system
can be configured in a straight-forward manner
4 DL &
subj.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
75
25 27 The user can see the humidity level side by side with the
actual humidity in the system
5 φ &
subj.
26 28 The HRS can be error-resistant and is capable of keeping
the operator from making errors whenever possible
5 DL &
subj.
27 29 CFD models of the MOWCC 3 DL &
subj.
28 30 HRS is easy to turn on, and prevents inadvertent switching
off
5 DL &
subj.
29 31 HRS can be dropped from height of 1 m and still excel in
operation
4 m
30 32 Filtering and separtion of
0.01 micrometer particles
4 µm
31 33 Cycles in operation without visible corrosion 4 cycles
32 34, 35 Time to dis-assembe /assemble for mainteneance 4 seconds
33 35 Special tools required for maintenance 5 subj.
34 36 Focus group rating- appearance 5 subj.
35 37 Instills pride 5 subj.
36 38 Focus group rating- professionalism 5 subj.
37 39 Emergency shutdown procedures/ sequences 5 Binary
38 40 Budget limit of maximum $200 5 $
39 41 Air conditioning equimpment catalogue 3 List
40 42 Noise measurement 4 dB
41 43, 44 Protection equimpment and labels are in place 5 subj.
42 44 Life cycle analysis and Hannover principles 4 subj.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
76
Table C3. Competetive Bench Marking Chart Based on Metrics
Metric
#
Needs
#s
Metric
Engineering Spec.
Imp. Units GUNT
Gmbh.
DRI
EAZ
Nov.
Air
DEZ
AIR
Air O
Swiss
1 1, 2, 3 Humidity extraction
and addition rate
4 kg/hr ~8
add&sub
~4.74
sub
~3.85
sub
~2
sub
0.55
add
2 4 Coefficient of
performance on the
HRS cooling units
5 ratio ~3 0.9 ~0.9 ~0.9 ~0.9
3 5 Negative feedback
loop for set humidity
levels
5 DL Yes Yes Yes Yes Yes
4 6 Auxiliary ventilation
and air conditioning
3 subj. Yes No No No No
5 7 Humidity setting is
input via the terminal
and displayeld
alongside with the
actual humidity
reading
5 subj. Yes Yes Yes Yes No
6 8 Manual for the HRS
providing step by step
procedures
5 pages 100
~
300
20
~
30
20
~
30
20
~
30
20
~
30
7 9, 12 Maximum temperature
ranges from -50 to
+100 oC
4 oC -10 to
+60
-30 to
+50
-30 to
+50
-30 to
+50
-20 to
+40
8 10 Mechanism for flow
regulation
3 subj. Yes Yes Yes Yes No
9 11, 13 HRS is error-tolerant,
and if a fault occurs
over a specific time
period the HRS will
take preventive actions
and return the system
to the set conditions or
shut-down to prevent
error accumulation
5 seconds 0.001 ~1 ~1 ~1 ~1
10 12, 13 Low thermal
expansion materials
4 mm/ oC ~0.1 ~1 ~0.5 ~0.5 ~0.5
11 13 Statistical analysis of
HRS normal
performance
3 DL Yes Yes Yes Yes Yes
12 14 Temperature variation
is not affected by the
HRS operation and
vice versa
4 oC/φ ~6/
10%
~10/
10%
~8/
10%
~8/
10%
~8/
10%
13 15 TES performance is
not affected by the
HRS operation and
vice versa
4 oC/φ - - - - -
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
77
14 16 Air-flow variation is
not affected by the
HRS operation and
vice versa
3 (m/s)/φ - - - - -
15 17 Solar regulaion is not
affected by the HRS
operation and vice
versa
2 lum/ φ - - - - -
16 18, 19 The whole HRS fits
into a box of
dimensions less than
0.5m3 for the two
obligatory options
(stand-alone climatic
chamber without the
operation of the
primary wind
generating air fan and
the system under test,
such as a model
building)
5 m3 1 0.5-
0.7
~0.5 0.188 0.029
17 18, 19 The space factor of
HRS is less than 1/12th
of MOWCC
5 m3 1 0.5-
0.7
~0.5 0.188 0.029
18 20 Total mass 5 kg ~200 30~50 ~100 39 4.5
19 14,
15,
16,
17,
21, 22
Variable adjustments
of ports
3 Binary Pass Fail Pass Pass Fail
20 22 Ports are sealable 5 Binary Pass Fail Pass Pass Fail
21 23 HRS is thoroughly
sealed and insulated
5 Binary Pass Pass Fail Pass Fail
22 24 HRS can regulate the
humidity levels in the
range between 5% to
95% relative humidity,
with the expected
temperature levels for
the system between -
20 degC to +40 degC,
and possible wind
speeds reaching up to
11m/s
5 φ (%) 0-100 20-99 30-70 35-65 30-70
23 25 HRS follows the
control setpoints
accurately and steadily
5 Subj. &
DL
True True True True Undef
24 26 The scenarios and
schedules for humidity
control system can be
4 DL &
subj.
True False True True Undef
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
78
configured in a
straight-forward
manner
25 27 The user can see the
humidity level side by
side with the actual
humidity in the system
5 φ &
subj.
True False False False False
26 28 The HRS can be error-
resistant and is
capable of keeping the
operator from making
errors whenever
possible
5 DL &
subj.
True False True True True
27 29 CFD models of the
MOWCC
3 DL &
subj.
No No No No No
28 30 HRS is easy to turn
on, and prevents
inadvertent switching
off
5 DL &
subj.
Yes Yes Yes Yes Yes
29 31 HRS can be dropped
from height of 1 m
and still excel in
operation
4 m 0.2 1 0.5 0.5 0.5
30 32 Filtering and separtion
of
0.01 micrometer
particles
4 µm Undef 0.04 0.02 0.02 Undef
31 33 Cycles in operation
without visible
corrosion
4 cycles 103 10
5 10
6 10
6 10
4
32 34, 35 Time to dis-assembe
/assemble for
mainteneance
4 seconds 3600 3600 1200 1200 1200
33 35 Special tools required
for maintenance
5 subj. Maybe No No No No
34 36 Focus group rating-
appearance
5 subj. Great Good Med. Med. Good
35 37 Instills pride 5 subj. Yes ~ ~ ~ ~
36 38 Focus group rating-
professionalism
5 subj. Yes Yes Yes Yes Med.
37 39 Emergency shutdown
procedures/ sequences
5 Binary Pass Fail Pass Pass Fail
38 40 Budget limit of
maximum $200
5 $ ~104
1’868-
4’065
5’499 1’500 ~300
39 41 Air conditioning
equimpment catalogue
3 List Yes Yes Yes Yes Yes
40 42 Noise measurement 4 dB 30-60 80-85 20-30 55-60 30-35
41 43, 44 Protection
equimpment and
labels are in place
5 subj. Yes Yes Yes Yes Yes
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
79
42 44 Life cycle analysis and
Hannover principles
4 subj. Undef Undef Undef Undef Undef
D. Competitive Products CE 130 “Convection Drying”:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
80
CE 540 “Adsorptive Air Drying”:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
81
600 “Conditioning of Room Air”:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
82
ET 605 “Air Conditioning System Model”:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
83
ET 611 “Air Conditioning System with Chamber”:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
84
ET 620 “Air Conditioning and Ventilation System”:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
85
DRI-EAZ:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
86
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
87
Novel Air:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
88
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
89
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
90
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
91
DEZ-AIR:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
92
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
93
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
94
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
95
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
96
FANTECH:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
97
DAYTON:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
98
Air O Swiss:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
99
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
100
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
101
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
102
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
103
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
104
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
105
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
106
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
107
E. Complete QFD for the HRS
Competitive Analysis (0=Worst, 5=Best)
Row #
Demanded Quality (a.k.a. "Customer Requirements" or "Whats")
Weight / Importance
Relative Weight
Ou
r C
urr
en
t P
rod
uc
t
GU
NT
Ham
bu
rg
DR
I-E
AZ
No
vel
Air
DE
Z-A
IR
Air
O S
wis
s
1 HRS can regulate humidity in a model under test 5 2.78 5 5 2 5 4 4
2 HRS can regulate humidity in a stand-alone climatic chamber
5 2.78 5 5 3 5 4 4
3 HRS can regulate humidity levels in the complete MOWCC
1 0.56 2 0 2 0 0 0
4 HRS efficiently utilizes energy to extract humidity 5 2.78 5 4 3 5 5 4
5 HRS is capable of maintaining a constant humidity level 5 2.78 5 5 4 5 5 4
6 HRS can extract humidity from very damp environments
1 0.56 4 3 5 2 4 0
7 HRS can easily start humidity extraction and infusion 5 2.78 5 5 2 2 2 2
8 HRS has an available guide menu that can show the process of using the terminal
3 1.67 4 4 2 2 2 2
9 HRS can easily tolerate a range of environments without effect on its performance
3 1.67 4 2 5 4 3 3
10 HRS can prevent the air counter-flow events 3 1.67 4 4 4 2 3 0
11 HRS is robust during operation 3 1.67 4 4 5 4 4 2
12 HRS can withstand high fluctuations in temperature 3 1.67 4 3 5 3 3 2
13 HRS operates normally after repeated use 5 2.78 4 4 5 4 4 4
14 HRS is easily integratable with the temperature regulation and monitoring unit
5 2.78 5 5 1 3 3 2
15 HRS is easily integratable with the thermal energy storage unit
5 2.78 5 0 1 3 3 2
16 HRS is easily integratable with the wind flow regulation and monitoring system
3 1.67 3 3 1 1 1 1
17 HRS is easily integratable with the solar radiation regulation and monitoring unit
3 1.67 3 2 1 1 1 1
18 HRS is small and light 5 2.78 4 1 3 5 3 5
19 HRS can be positioned anywhere in MOWCC without affecting performance of other components
3 1.67 4 0 0 3 2 1
20 HRS can be easily removed from MOWCC to be maintained and cleaned
5 2.78 5 0 0 3 2 2
21 HRS is modular 3 1.67 5 3 2 4 3 2
22 HRS can be transferred to a hydrogen generation unit or natural gas cleansing unit and operate without a hinge
1 0.56 4 0 0 4 2 0
23 HRS does not have any leaks that would prevent it from proper operation during re-installation
5 2.78 5 5 4 4 4 4
24 HRS is easy to control 5 2.78 5 5 5 4 4 4
25 The operator can easily alter the settings without damaging the performance of the HRS
5 2.78 5 5 4 2 4 4
26 The setting can be "locked on" a specific humidity regulation scenario
5 2.78 5 4 2 2 3 3
27 HRS is informative by its capability to display the actions performed by the user as well as the system status
5 2.78 5 3 1 1 1 1
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
108
28 The humidification and de-humidification processes are non-conflicting and can alternate without hindering performance of HRS
5 2.78 5 3 0 0 2 0
29 HRS performance can be followed visually via the real-time CFD display of the existing system
3 1.67 4 0 0 0 0 0
30 HRS is easy to set up and use 5 2.78 4 3 5 5 4 5
31 HRS lasts a long time and survives heavy use 3 1.67 4 3 5 3 4 4
32 HRS self-cleans from air contaminants like dust bacteria and fungi
3 1.67 4 3 4 4 4 4
33 HRS does not corrode during operation 3 1.67 5 5 4 4 4 4
34 HRS is easy to maintain 5 2.78 5 4 4 5 4 4
35 HRS can be maintained with readily available tools 5 2.78 5 3 4 4 4 4
36 HRS is visually appealing 5 2.78 4 5 4 3 3 5
37 Instills pride to the people operating and the people observing the system
5 2.78 5 5 3 2 2 3
38 HRS looks like a professional quality unit 5 2.78 4 5 4 3 3 4
39 HRS prevents any damage to system under test 3 1.67 4 3 1 3 3 1
40 HRS is inexpensive 5 2.78 5 0 0 0 0 0
41 HRS implements existing components for operation 5 2.78 4 3 3 4 4 4
42 HRS has a pleasant sound when in use, preferably very quiet
5 2.78 4 4 1 5 5 4
43 HRS is safe 5 2.78 5 5 4 5 4 4
44 HRS employs environmentally safe technologies and components
5 2.78 5 2 1 1 1 1
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
109
*Note: The full QFD version is available digitally on the DVD
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
110
F. Concept Generation vie Concept Combination Table Table F1. Concept Combinmation Table for Vortex Cooler System
Store or accept external
energy
Convert energy to thermal
form
(Extact or Add)
Condensate water on
surface
Add thermal energy to
water to mix water and
air
Pneumatic storage Vortex tube configuration Vertical staggered tube
arrangement
Misting system
Configuration
Electric field storage High convection
evaporative cooling
Vertical in-line tube
arangement
Ultrasonic mister
Use electric energy Thermo-electric peltier pile Mesh bafles Steam generation/
Water boiling
Standard refrigeration cycle Porous media
Strirling refrigeration cycle Absobant/adsobtive
circulation unit
(Dessicant Wheel)
Finned surface
Concept # 1.
Brief: The stored pneumatic energy reaches a specific level of pressure, which is then released into the
vortex tubes for the purpose of spot cooling a small porous block where the moisture accumulation takes
place. The now dry air passes over an ultrasonic mister where humidity can be added upon activation of
the mister. This concept takes some ideas from the benchmarked products and the ideas of the vortex
tubes that have a potential to split the hot and cool air streams [3] [17].
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
111
List of Components Involved:
Ducts
Insulation
Air Filter
Ultrasonic Misting Assembly
Air Comppressor
Pneumatic Lines
Solenoid Actuator
Vortex Tubes
Porous block for humidity accumulation
Water storage for the ultrasonic mister
Funnel or pan for excess moisture collection
Pros Cons
Instead of relying on the electric energy the
pneumatic energy provides a constant an
uniform flow of air and provides the
cooling
The porous media allows for the air to pass
through it and the water to accumulate and
drain away by the gravity
The ultrasonic mister allows for the precise
control of how much humidity needs to be
added to the system
Energy intensive
Multiple parameters requiring control
(compressor, solenoid valve, ultrasound
mister)
May get fairly expensive (besides some
componens such as a misting pump already
exist, hence there is little reason to
purchase more materials)
Interference from/to ultrasonic sensors
(would require a more complicated
algorithm for using sensors and
humidification)
Requires a lot of inputs/outputs
The response time may be very slow due to
the humidity translation throughout the
block
The porous block may be very fragile and
as a result it crack and crumble
The flow of air may be significantly
reduced due to the presence of the porous
block and baffles, which may affect the
overall performance of the system
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
112
Table F2. Concept Combinmation Table for Electric Field Moisture Confinement and Evaporative
Cooling
Store or accept external
energy
Convert energy to thermal
form
(Extact or Add)
Condensate water on
surface
Add thermal energy to
water to mix water and
air
Pneumatic storage Vortex tube configuration Vertical staggered tube
arrangement
Misting system
Configuration
Electric field storage High convection
evaporative cooling
Vertical in-line tube
arangement
Ultrasonic mister
Use electric energy Thermo-electric peltier pile Mesh bafles Steam generation/
Water boiling
Standard refrigeration cycle Porous media
Strirling refrigeration cycle Absobant/adsobtive
circulation unit
(Dessicant Wheel)
Finned surface
Concept # 2.
Brief: The electric energy is converted to a static electricity, which is confined to the isolated metalic
meshes within the duct. When the air passes over the meshes the moisture particles within the air get
charged by the positive meshes and accumulate on the negative mesh. The accumulated moisture then
drips away into the condensate containtainment via gravity. The water in the basin is heated up to a
boiling point and the baffle is opened by the actuator to release the low quality steam into the air and
hereby induce a flow and mixing with the air. This action will raise the humidity of the air and the now
moist warm air will rise into the testing unit of its destination.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
113
List of Components Involved:
Ducts
Insulation
Air Filter
Water storage and containment
Resistive heating element
Walton-Cockroft Multipliers for the electric field moisture mixing
Electrical insulators
Metal mesh
Funnel or pan for excess moisture collection
Actuator with the moving baffle assembly (the baffle has to be preferably insulative to the heat)
Pros Cons
A unique method for humidity
accumulation and removal via the the
electric field confinement
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The response time for activating humidity
addition is quick
The flow of air is not constricted
significantly to cause the back-flows.
The high voltage involved in this concept
can present a significant danger to
operating personnel, as well as cause some
problems for the electronic components
within the system.
The energy consumption may be
significant
There is no mechanism to prevent
significant backflows from the system.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
114
Table F3. Concept Combinmation Table for Thermo-electric Peltier Pile
Store or accept external
energy
Convert energy to thermal
form
(Extact or Add)
Condensate water on
surface
Add thermal energy to
water to mix water and
air
Pneumatic storage Vortex tube configuration Vertical staggered tube
arrangement
Misting system
Configuration
Electric field storage High convection
evaporative cooling
Vertical in-line tube
arangement
Ultrasonic mister
Use electric energy Thermo-electric peltier pile Mesh bafles Steam generation/
Water boiling
Standard refrigeration cycle Porous media
Strirling refrigeration cycle Absobant/adsobtive
circulation unit
(Dessicant Wheel)
Finned surface
Concept # 3.
Brief: The peltier thermo-couple is connected to a metal mesh that allows the passage of air through it.
The accumulation of moisture on the mesh is then removed by means of gravity. If any remaining
moisture remains in the air it can be removed by the dessicant wheel that adsorbs the remaoining moisture
in the cool air and releases it to the warmer air of the environment. The water in the basin is heated up to
a boiling point and the baffle is opened by the actuator to release the low quality steam into the air and
hereby induce a flow and mixing with the air. This action will raise the humidity of the air and the now
moist warm air will rise into the testing unit of its destination.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
115
List of Components Involved:
Ducts
Insulation
Air Filter
Peltier thermo-electric piles
Dessicant Wheel
Motor for the wheel
Driving Belt
Desiccant Wheel Rotational Axis
Water storage and containment
Resistive heating element
Metal mesh
Actuator with the moving baffle assembly (the baffle has to be preferably insulative to the heat)
Drain Valve
Pros Cons
Energy consumtion is relatively low
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The response time for activating humidity
addition is fairly quick
The flow of air is not too constricted
because the dessicant wheel has holes for
air passage over the liquid.
Regulation happens by activating only
afew variables (ie. Heating, activting
motor, and turning on the peltier pile)
The response time for activating humidity
addition is quick
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The peltier thermo-electric element doesn’t
have any moving parts and is easily
reversible. It needs to be controlled only by
changing the current.
Somewhat constricted assembly
May be expensive due to multiple parts
The peltier pile is fairly in-efficient
The dessicant wheel may be very fragile
and as a result it crack and crumble
The temperature of the air may drop as it
passes through the wheel, which may
negatively affect the performance of
climatic wind chamber components
Can become infested with mold and
bacteria if either the air filter is breached or
water has contaminants
Involves moving parts which may require
significant maintenance and periodic
checking.
Regulation happens by activating multiple
variables
There is no mechanism to prevent
significant backflows from the system.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
116
Table F4. Concept Combinmation Table for Standard Refrigeration Cycle
Store or accept external
energy
Convert energy to thermal
form
(Extact or Add)
Condensate water on
surface
Add thermal energy to
water to mix water and
air
Pneumatic storage Vortex tube configuration Vertical staggered tube
arrangement
Misting system
Configuration
Electric field storage High convection
evaporative cooling
Vertical in-line tube
arangement
Ultrasonic mister
Use electric energy Thermo-electric peltier pile Mesh bafles Steam generation/
Water boiling
Standard refrigeration cycle Porous media
Strirling refrigeration cycle Absobant/adsobtive
circulation unit
(Dessicant Wheel)
Finned surface
Concept # 4.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
117
Brief: The humidity extraction occurs as a result of cooling perfromed by the standard refrigeration cycle.
The condensation occurs on the finned humidity exchanger and removed by gravity from the system. The
water in the basin is heated up to a boiling point and the baffle is opened by the actuator to release the low
quality steam into the air and hereby induce a flow and mixing with the air. This action will raise the
humidity of the air and the now moist warm air will rise into the testing unit of its destination.
List of Components Involved:
Ducts
Insulation
Air Filter
Fan
Water Basin
Tubing for the re-fill appendix
Heating element
Drain Valve
Heat Exchanger
Refrigeration Cycle Assembly
Actuator with the moving baffle assembly (the baffle has to be preferably insulative to the heat)
Pros Cons
Energy consumtion may be relatively low
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The flow of air is not constricted
significantly to cause the back-flows.
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The response time for activating humidity
addition is quick
The flow of air is not constricted
significantly to cause the back-flows.
Somewhat constricted assembly
The refrigerant fluid is potentially toxic
and may be environmentally unfriendly
The response time for activating humidity
aextraction may be fairly slow due to the
activation of the refrigerator assembly
The control of humidity involves heating
the air to some degee
The temperature of the air may drop as it
passes through the heat exchanger
Involves moving parts which may require
significant maintenance and periodic
checking.
Regulation happens by activating multiple
variables which may complicate the
controls
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
118
Table F5. Concept Combinmation Table for Stirling Refrigeration
Store or accept external
energy
Convert energy to thermal
form
(Extact or Add)
Condensate water on
surface
Add thermal energy to
water to mix water and
air
Pneumatic storage Vortex tube configuration Vertical staggered tube
arrangement
Misting system
Configuration
Electric field storage High convection
evaporative cooling
Vertical in-line tube
arangement
Ultrasonic mister
Use electric energy Thermo-electric peltier pile Mesh bafles Steam generation/
Water boiling
Standard refrigiration cycle Porous media
Strirling refrigeration cycle Absobant/adsobtive
circulation unit
(Dessicant Wheel)
Finned surface
Concept # 5.
Brief: The humidity extraction occurs as a result of cooling perfromed by the stirling refrigeration cycle.
The condensation occurs on the finned humidity exchanger and removed by gravity from the system. The
humidity addition, on other hand, involves the misting of the air with water and allowing for the water to
mix with air.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
119
List of Components Involved:
Ducts
Insulation
Air Filter
Fan
Water holding Chamber
Motor
Driving Chain
Stirling Cycle Engine (2 Refubrished Mowing Engines)
Drain Assembly
Misting Pump
Misting pipes assembly
Flow Regulation Valve
Water storage
The staggered configuration heat exchanger
Pros Cons
Energy consumtion is relatively low and
the stirling cycle is significantly efficient
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The response time for activating humidity
addition and extraction is fairly quick (a
matter of activating the misting assembly
or the strirling cycle)
The flow of air is not too constricted
because the dessicant wheel has holes for
air passage over the liquid.
Relatively easy assembly
Cost is small as most of the parts are easily
sourced
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
Despite the use of the misting equipment
the costs can be significantly low
The Stirling cycle does not use toxic
working fluids and is relatively low
maintnenace This cycle may also be used
for heating, as it is reversible.
Involves moving parts which require some
attention and safety precautions
The temperature of the air may drop as it
passes through the misting assembly
There is no mechanism to prevent
significant backflows from the system.
The misting assembly of the design and the
condensation equipment of the stirling
cycle may cause the temperature of the air
to drop (hence strict control over how
much humidity is added or removed needs
to be maintained)
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
120
Some Alternative Sketches and Photos of currently available material
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
121
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
122
Table F6. Concept Combinmation Table for Single Duct Humidity Extraction Version 1
Ventilate the air Move air over water
affinitive surface
Condensate water on
surface
Remove condensed
water from the surface
Single duct Fan Vertical staggered tube
arrangement
Fan
Double duct Vortex Tube Configuration Vertical in-line tube
arangement
Natural Convection
Mesh bafles Electrostatic Repulsion
Porous media Shock “Hammering”
Absobant/adsobtive
circulation unit
Gravity Drain
Finned surface
Concept # 6.
Brief: The air is ventilated by the fan through a dessicant wheel that absorbs the humidity and rotates
within the duct. As the dessicant wheel rotates the moisture from the vented side is exposed to the outside
air where it could be removed by an additional fan into the environment. This solution is relatively low
energy and low cost, but the dessicant wheel may be somewhat fragile.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
123
List of Components Involved:
Ducts
Insulation
Air Filter
Fan
Desiccant Wheel
Motor
Driving Belt
Desiccant Wheel Rotational Axis
Pros Cons
Energy consumtion is significantly low
The control over how much humidity is to
be exctracted can be controlled fairly well
and with significant precission
The response time for activating humidity
extraction is fairly quick (a matter of
activating the motor and the fan)
The flow of air is not too constricted
because the dessicant wheel has holes for
air passage over the liquid.
Relatively easy assembly
Cost is rlatively small
The back-flows are preventable due to the
presence of the fan
The low number of parts makes this an
attractive option for increasing humidity
Involves moving parts which require
maintenance
Can become infested with mold and
bacteria if either the air filter is breached or
water has contaminants
The dessicant wheel may be very fragile
and as a result it crack and crumble
The temperature of the air may drop as it
passes through the wheel, which may
negatively affect the performance of
climatic wind chamber components
An additional fan may be required on the
other side of the assembly
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
124
Table F7 . Concept Combinmation Table for Single Duct Humidity Extraction Version 2
Ventilate the air Move air over water
affinitive surface
Condensate water on
surface
Remove condensed
water from the surface
Single duct Fan Vertical staggered tube
arrangement
Fan
Double duct Vortex Tube Configuration Vertical in-line tube
arangement
Natural Convection
Mesh bafles Electrostatic Repulsion
Porous media Shock “Hammering”
Absobant/adsobtive
circulation unit
Gravity Drain
Finned surface
Concept # 7.
Brief: The stored pneumatic energy reaches a specific level of pressure, which is then released into the
vortex tubes for the purpose of spot cooling a small porous block where the moisture accumulation takes
place. The air passess over some baffles and the porous block to dry further.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
125
List of Components Involved:
Ducts
Insulation
Air Filter
Air Comppressor
Pneumatic Lines
Solenoid Actuator
Vortex Tubes
Porous block for humidity accumulation
Funnel or pan for excess moisture collection
Pros Cons
Instead of relying on the electric energy the
pneumatic energy provides a constant an
uniform flow of air and provides the
cooling
The porous media allows for the air to pass
through it and the water to accumulate and
drain away by the gravity
Energy intensive
Multiple parameters requiring control
(compressor, solenoid valve)
May get fairly expensive
The response time may be very slow due to
the humidity translation throughout the
block
The porous block may be very fragile and
as a result it crack and crumble
The flow of air may be significantly
reduced due to the presence of the porous
block and baffles, which may affect the
overall performance of the system
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
126
Table F8. Concept Combinmation Table for Single Duct Humidity Extraction Version 3
Ventilate the air Move air over water
affinitive surface
Condensate water on
surface
Remove condensed
water from the surface
Single duct Fan Vertical staggered tube
arrangement
Fan
Double duct Vortex Tube Configuration Vertical in-line tube
arangement
Natural Convection
Mesh bafles Electrostatic Repulsion
Porous media Shock “Hammering”
Absobant/adsobtive
circulation unit
Gravity Drain
Finned surface
Concept # 8.
Brief: The air passes over the cooled staggered tube bank, there the moisture condensates and leaves
through a gravity drain. The advantage of this design is that the flow over this particular bank is
relatively smooth and the humidity condensation distributes evenly among the banks.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
127
List of Components Involved:
Ducts
Insulation
Air Filter
Fan
Staggeed Tube Bank Heat Exchnger
Device for removing the thermal energy from air and condensing the humidity
Pros Cons
Energy consumtions are significantly low
due to the smooth flow over the staggered
tube bank
Relatively easy assembly
The back-flows are preventable due to the
presence of the fan
The low number of parts makes this an
attractive option for controlling humidity
The energy efficiency largely depends on
the choice of the cooling mechanism
The temperature of the air may drop as it
passes through the bank, which may
negatively affect the performance of
climatic wind chamber components
Some Other Concepts:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
128
Table F9. Concept Combinmation Table for Double Duct Humidity Extraction Version 1
Ventilate the air Move air over water
affinitive surface
Condensate water on
surface
Remove condensed
water from the surface
Single duct Fan Vertical staggered tube
arrangement
Fan
Double duct Vortex Tube Configuration Vertical in-line tube
arangement
Natural Convection
Mesh bafles Electrostatic Repulsion
Porous media Shock “Hammering”
Absobant/adsobtive
circulation unit
Gravity drain
Finned surface
Concept # 9.
Brief: The double duct systems offers the sepaation of the air flow to either humidification system or to
the de-humidification system. In the de-humidification zone the air passes over a set of in-line tube bank
heat exchanger that is continually cooled to have any moisture condese on the surface.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
129
List of Components Involved:
Ducts
Insulation
Air Filter
In-line tube bank heat exchger
Actuator for re-directing the air flows
A device for removing the thermal-energy
Funnel or pan for excess ice collection
Pros Cons
The humidification and de-humidification
processes are separated and the control
over the humidity is increased
The positioning of the servo in this
scenario makes for a good performance of
the device
The air turbulence created in the tube-blank
makes for an in-convenience of leaving out
some condensation at the wrong places
The cooled down air may have to be
reheated and this makes for more energy
expenses
Some Other Concepts
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
130
Table F10. Concept Combinmation Table for Double Duct Humidity Extraction Version 3
Ventilate the air Move air over water
affinitive surface
Condensate water on
surface
Remove condensed
water from the surface
Single duct Fan Vertical staggered tube
arrangement
Fan
Double duct Vortex Tube Configuration Vertical in-line tube
arangement
Natural Convection
Mesh bafles Electrostatic Repulsion
Porous media Shock “Hammering”
Absobant/adsobtive
circulation unit
Gravity drain
Finned surface
Concept # 10.
Brief: The double duct systems offers the sepaation of the air flow to either humidification system or to
the de-humidification system. In the de-humidification zone the air passes over a set of fins that are
continually cooled to have any moisture precipitate as ice on the surface of the fins. Since ice may block
the air flow, a proposed solution to prevent the ice accumulation is by an electrostatic shcok (similar in
construction to the air purifiers in the coal plants). The shaken off ice will then be disposed to the funnel
for extraction of the ice from the system.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
131
List of Components Involved:
Ducts
Insulation
Air Filter
Finned Heat Exchanger
Circuitry for the electro-static hammering
Ice removal valve
Actuator for re-directing the air flows
Electrical insulators to prevent electric shocks
Funnel or pan for excess ice collection
Pros Cons
The moisture is removed in a solid form
and any hazard of leaving a trip hazard is
avoided
The humidification and de-humidification
processes are separated and the control
over the humidity is increased
A definite way of extracting the hmidity
The process may be very energy intensive
to turn all the moisture into ice
The electro-static hammering process can
be hazardous to high voltages and it may
damage sensitive circuitry
The positioning of the servo in the sketch is
not well thought out, a better positioning
may be possible
Too many control variables may be
involved in order to make this happen
The cooled down air may have to be
reheated and this makes for more energy
expenses
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
132
Table F11. Concept Combinmation Table for Humidity Addition via Basin
Store water Isolate some water for
humidification
Add thermal energy to
water to mix water and
air
Ventilate Air over the
mix to move humidified
Air
Basin Open surface Boiling Fan
Syringe Misting Air Preheat Natural Convection
Porous media Desiccant wheel Electrostatic Repulsion
Concept # 11.
Brief: The water in the basin is heated up to a boiling point and the baffle is opened by the actuator to
release the low quality steam into the air and hereby induce a flow and mixing with the air. This action
will raise the humidity of the air and the now moist warm air will rise into the testing unit of its
destination.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
133
List of Components Involved:
Ducts
Insulation
Air Filter
Water Basin
Tubing for the re-fill appendix
Heating element
Actuator with the moving baffle assembly (the baffle has to be preferably insulative to the heat)
Pros Cons
Only the control over a baffle and the
resistive element has to be implemented
The control can be achieved fairly fast
precisely with the desired results
The low number of parts makes this an
attractive option for increasing humidity
Low level of flow restriction, practically
non-existent
Back-flows may take place and hinder the
performance of he humidity addition
The basin might have to have a cover that
opens and closes when the humidity need
to be added
Some moving components are used in this
design
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
134
Table F12. Concept Combinmation Table for Humidity Addition via Syringe Version 1
Store water Isolate some water for
humidification
Add thermal energy to
water to mix water and
air
Ventilate Air over the
mix to move humidified
Air
Basin Open surface Boiling Fan
Syringe Misting Air Preheat Natural Convection
Porous media Desiccant wheel Electrostatic Repulsion
Concept # 12.
Brief: The air passes through a filter to remove any contaminants and then is pulled through the fan and
into the heat exchanger unit. The heat exchanger unit may warm up the air before it comes in contact with
the misting nozzle assembly. When the warm air and water mist mix, the temperature of the air drops
slightly but humidity content of air increases. The now humid air passes over some wood baffles to
prevent the mist from entering into the testing space.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
135
List of Components Involved:
Ducts
Insulation
Air Filter
Misting Pump
Misting pipes assembly
Flow Regulation Valve
Water storage
Heat Exchanger
Fan
Wooden Baffles
Funnel or pan for excess moisture collection
Pros Cons
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The response time for activating humidity
addition is quick
The flow of air is not constricted
significantly to cause the back-flows.
Despite the use of the misting equipment
the costs can be significantly low
The back-flows are preventable due to the
presence of the fan
The assembly requires multiple variables to
be activated in order for the system to work
(activating the fan, turning on the heater,
engaging the misting assembly into action)
The wood baffles may become suspect to
humidity accumulation and buffering the
humidity regulation
The obstrictions in the path of the air flow
may hinder the performance of humidity
addition
The energy consumption rates may be
significant due to a multitude of
components
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
136
Table F13. Concept Combinmation Table for Humidity Addition via Syringe Version 2
Store water Isolate some water for
humidification
Add thermal energy to
water to mix water and
air
Ventilate Air over the
mix to move humidified
Air
Open Basin Open surface Boiling Fan
Syringe Misting Air Preheat Natural Convection
Porous media Desiccant wheel Electrostatic Repulsion
Concept # 13.
Brief: The concept presented here is a unique version of humidity addition. The misting nozzle has a
metal tip that is connected to a heating element and a charge pump, or Walton-Cockroft multiplier. The
misting nozzle can be activated to produce hot, charged, mist that is accelerated to the negatively chaged
mesh. The induced flow of mist will mix the hot water with air and the hot air will be able to travel
through the duct after some excess moisture is accumulated on the negatively charged mesh. The excess
moisture will drip from the mesh into a moisture collecting pan or funnel and will be gravitationally
siphoned out of the system.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
137
List of Components Involved:
Ducts
Insulation
Air Filter
Misting Pump
Misting pipes assembly
Flow Regulation Valve
Water storage
Resistive heating element that can be attached to the misting nozzle
Metal misting nozzles
Walton-Cockroft Multipliers for the electric field moisture mixing
Electrical insulators
Metal mesh
Funnel or pan for excess moisture collection
Pros Cons
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The response time for activating humidity
addition is quick
The flow of air is not constricted
significantly to cause the back-flows.
Despite the use of the misting equipment
the costs can be significantly low
Involves moving parts which may require
significant maintenance and periodic
checking.
The high voltage involved in this concept
can present a significant danger to
operating personnel, as well as cause some
problems for the electronic components
within the system.
Regulation happens by activating multiple
variables (heating nozzles, activating
electric field, turning on misting pump, and
opening or closing the flow regulation
valve).
The energy consumption may be
significant due to the many components
such as the misting pump, the heating
elements, and the electric field units.
There is no mechanism to prevent
significant backflows from the system.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
138
Table F14. Concept Combinmation Table for Humidity Addition via Porous Media Version 1
Store water Isolate some water for
humidification
Add thermal energy to
water to mix water and
air
Ventilate Air over the
mix to move humidified
Air
Open Basin Open surface Boiling Fan
Syringe Misting Air Preheat Natural Convection
Porous media Desiccant wheel Electrostatic Repulsion
Concept # 14.
Brief: The dessicant wheel has one half submerged in a chamber of of water and the other half exposed to
air flow. The wheel rotates around its central axis, and, as it rotates, the water fills the gaps within the
wheel and then these damp gaps interact with the air as air flows through them. Since the water basin and
the air flow are isolated from each other, as long as the dessicant wheel remains stationary, the humidity
levels can be controlled failry precisely by simply rotating the wheel, and exposing the damp gaps to the
air. The air temperature will regulate how much moisture is mixed, and hence there is a need for a heating
element. The Fan may be avoided in the structure by utilizing the natural convection properties of air, as
shown in the top right corner of the sketch. The assembly without the fan would certainly cut the costs
and maintenance, but the natural convection allows for relatively slower control than forced convection.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
139
List of Components Involved:
Ducts
Insulation
Desiccant Wheel
Water holding Chamber
Air Heater
Air Filter
Piping for the water re-fill system
Drain
Motor
Driving Belt
Desiccant Wheel Rotational Axis
Fan
Pros Cons
Energy consumtion is relatively low
The control over how much humidity is to
be exposed can be controlled fairly well
and with significant precission
The response time for activating humidity
addition is fairly quick (a matter of
activating the motor)
The flow of air is not too constricted
because the dessicant wheel has holes for
air passage over the liquid.
Involves moving parts which require
maintenance
The control of humidity involves heating
the air to some degee and activating the fan
to induce the forced convection within the
dessicant wheel
Can become infested with mold and
bacteria if either the air filter is breached or
water has contaminants
The dessicant wheel may be very fragile
and as a result it crack and crumble
The temperature of the air may drop as it
passes through the wheel, which may
negatively affect the performance of
climatic wind chamber components
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
140
Table F15. Concept Combinmation Table for Humidity Addition via Porous Media Version 2
Store water Isolate some water for
humidification
Add thermal energy to
water to mix water and
air
Ventilate Air over the
mix to move humidified
Air
Open Basin Open surface Boiling Fan
Syringe Misting Air Preheat Natural Convection
Porous media Desiccant wheel Electrostatic Repulsion
Concept # 15.
Brief: When air is within the duct and comes in contact with the porous block, the air begins to pass
through the block and absorbs moisture. The moisture is absobed because the porous block allows water
to distribute uniformly throughout its body as a result of boiling happening in the water holding chamber.
Please note, the sketch does not show it but the outlet duct should be much wider in order to enforce the
natural convection of the moist air.
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
141
List of Components Involved:
Ducts
Insulation
Porous Block
Water holding Chamber
Heating Element
Air Filter
Piping for the water re-fill system
Drain Valve
Pros Cons
Does not involve any rotating or transalting
mechanisms
Regulation happens by activating a single
variable (ie. heating)
Relatively low levels of energy
consumption
Relatively easy assembly
Cost is small
Can become infested with mold and
bacteria if either the air filter is breached or
water has contaminants
The response time may be very slow due to
the humidity translation throughout the
block
The porous block may be very fragile and
as a result it crack and crumble
The flow of air may be significantly
reduced due to the presence of the porous
block, which may affect the overall
performance of the system
Some Other Prelimenary Concepts:
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
142
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
143
G. Calculations for the Staggered Tube Bank Configration
Figure G1. Staggered Tube Bank configuration heat exchanger.
Initially it was expected that a staggered tube bank configuration heat exchanger (Figure G1)
would be utilized in this project to extract the humidity. However, after performing the
calculations below it was found that this configuration would be far too energy demanding to
meet the demands for humidity extraction. Calculations for the staggered tube bank are as
follows:
Known:
Volumetric flow rate provided by the fan = 27 CFM=0.01274[m3/s]
Dimension of the inlet: 0.081[m]X0.082[m]
Fluid diameter of the inlet: D=(2*0.081*0.082)/( 0.081+0.082)[m]=0.0805[m]
Reinlet=(1.918*D)/(1.5/105)=10’293.66>2300 .: The flow is turbulent
Figure G2. The dimensions of the staggered tube bank in the model HRS
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
144
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
145
Daniel Bondarenko(100363648) ENGR 4950U December XX 2013
Design and Construction of a Humidity System for a Climatic Wind Chamber
146
Due to such large energy requirements, it was deemed that this configuration is un-suitable for
meeting the needs, and a more elegant solution was found in the form of vertical metal films
connected to the Peltier TEC. The metal films are made out of aluminum sheet, as it is the least
expensive material, and it has good thermal conductivity properties.