Final presentation Rev3
Transcript of Final presentation Rev3
Critical First Well Process: High Temperature Wells in Gulf of Thailand
Block I – December 2013
Kody Chandler Halliburton Baroid
Gulf of Mexico
Ekkadit Siriwachirawat Halliburton Baroid
Thailand
2
At Halliburton, solving customer challenges is second only to keeping everyone
safe and healthy. You can find more safety tips at www.halliburton.com/HSE.
• Plan the Trip• Prepare Vehicle• Prepare Yourself
Winter Driving
3
Objectives
• Analyze the Critical First Well (CFW) Process.
• Interpret information provided in CFW Checklists.
• Explain the role of the GTFA. • Describe the CFW process.
- Technical Mainstay- Role in DDSQ
4
Customer: Chevron Thailand Exploration
Platform: SBWA (South Baanphot Alpha)
1st Batch: 5 Wells
Rig name: Key Gibraltar
Project Overview
5
Overview of Technical and Black Book Processes
6
Estimated BHT 425o F.
Issues getting logs to bottom.
No previous logging data.
Barite sag, especially in static conditions.
Identify the Challenge
7
Solution Creation
“This was probably the most-tested fluid Baroid has ever launched,”
JJ Miller, Global Technical Services Manager for Baroid
HalNews 9/30/2013
8
Solution Creation “Doing Our Homework”
System PerformanceReview
Evaluate POP
System Customization
System Rationalization ValidationData Analysis
9
Solution Creation “Doing Our Homework”
System PerformanceReview
Evaluate POP
System Customization
System Rationalization ValidationData Analysis
Offset well data from SBWA-10,19, 14 and 02 Lessons Learned Log from SBWA project in 2011
10
Solution Creation “Doing Our Homework”
System PerformanceReview
Evaluate POP
System Customization
System Rationalization ValidationData Analysis
Fluid Risk Assessment– Mud Engineers unfamiliar with Chevron GoT operation– Consumption of chemicals more than expected– Contamination with CO2
– Lost Circulation
11
Solution Creation “Doing Our Homework”
System PerformanceReview
Evaluate POP
System Customization
System Rationalization ValidationData Analysis
Opportunity to introduce “new products” to the customer– PERFORMUL– BENTONE 38
12
Solution Creation “Doing Our Homework”
System PerformanceReview
Evaluate POP
System Customization
System Rationalization ValidationData Analysis
Lab work flow: Bangkok Kuala Lumpur Jarkata Pune Houston
Lab Testing new HT ENVIROMUL formulation– PERFORMUL 7.5 ppb– BENTONE 38 2.0 ppb
13
Solution Creation “Doing Our Homework”
System PerformanceReview
Evaluate POP
System Customization
System Rationalization ValidationData Analysis
14
Solution Creation “Doing Our Homework”
System PerformanceReview
Evaluate POP
System Customization
System Rationalization ValidationData Analysis
Ops Leader & Country Manager confirm all potential solutions can be effectively delivered to customer.
15
Overview of Technical and Black Book Processes
16
CFW Process Map
Criteria for determining a CFW
Process-driven
Sets us apart from our competitors
17
Baroid was relegated to servicing a few rigs
working on low-temperature wells.
Unsuccessful HT Well project in 2011.
August
September
October
November
December
Baroid was called upon to enhance this fluid for HT wells,.
Radioactive Source got stuck in the well bore and was irretrievable.
Baroid’s service was reduced from 8 rigs to 2 rigs.
The wellbores were not log-able because of the fluid’s gelation.
18
Encompassing design
Consistency
GTFA
CFW Checklist
19
GTFA Support
20
Overview of Technical and Black Book Processes
21
Present the Value
Avg. Cost $750K USD / Well, approx.
$3.8M
“Zero” NPT and
Recordable Incidents
5 Wells Completed - 72,767 ft in 77
days
22
Success in getting logs to bottom
Consistent mud weight, especially during periods without circulation – No barite sag
Key Performance Indicators
23
Customer focused Excellence in delivery
– Quality– Consistency
Delivering on our word
CFW Process and DDSQ
24
HalNews 9/30/2013 “Lab testing brings HT success in the Gulf of Thailand”. SBWA Pre-Spud Meeting May 5th, 2013 SBWA Risk management planning. Asia Pacific Share point : Technical and Black Book Process Page Baroid Critical First Well Support : Chevron SWBA 2nd Pass Debrief and
Lessons Learned Report on18 June 2013 report by Robert Bertrand (GTFA)
Shell Safety Alert : September 2013. Critical Well Process PM-GL-HAL-HMS-702 Critical Well Execution Process Criteria ST-GL-HAL-HMS-702 Personal Interview: Chip Miller, Vice President Personal Interview: Toby Dixon, Global Ops Manager Personal Interview: Dennis Lynch, PASQ and HSE Manager High Temperature OBM fluids for Chevron Lab Test Report in Pune, India
23rd March 2012
Reference
25
Thank you. Questions?