Final Ennore SEZ - Site Grading - Specification - Dt.280213

101
ENNORE SEZ THERMAL POWER PROJECT 2X660MW Site Grading the area of the proposed site for establishment of 2X 660 MW Ennore SEZ coal based Super critical Thermal Power Plant in the Ash Dyke area of North Chennai Thermal Power Station (NC TPS ) SPECN.NO.SE/C/P&E - 05 / 2012 -13 COST OF SPECIFICATION (INCLUDING ALL TAXES) WITHIN TAMIL NADU : Rs. 10,000 /- OUTSIDE TAMIL NADU : Rs. 10,000 /- (EXTRA RS.300/- IF SENT BY POS T) DUE DATE AND TIME FOR : Up to 2.00 pm SUBMISSION OF TENDER on 03.04.2013  The specification can be downloaded free of cost in the follow ing website www.tnebnet.org and www.tenders.tn.gov.in OFFICE OF THE SUPERINTENDING ENGINEER / CIVIL, PROJECTS & ENVIRONMENT 3 rd FLOOR / E ASTER N WING, NPKRR MAALIGAI, 144, ANNA S ALAI, CHENNA I-600 002, TAMIL NADU. (Not Transferable)

Transcript of Final Ennore SEZ - Site Grading - Specification - Dt.280213

Page 1: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 1/101

ENNORE SEZ THERMAL POWER PROJECT – 2X660MW

Site Grading the area of the proposed site for establishmentof 2X 660 MW Ennore SEZ coal based Super critical ThermalPower Plant in the Ash Dyke area of North Chennai Thermal

Power Station (NCTPS)

SPECN.NO.SE/C/P&E - 05 / 2012-13

COST OF SPECIFICATION (INCLUDING ALL TAXES)

WITHIN TAMIL NADU : Rs. 10,000 /-OUTSIDE TAMIL NADU : Rs. 10,000 /-

(EXTRA RS.300/- IF SENT BY POST)

DUE DATE AND TIME FOR : Up to 2.00 pmSUBMISSION OF TENDER on 03.04.2013

 

The specification can be downloaded free of cost in the following websitewww.tnebnet.org and www.tenders.tn.gov.in

OFFICE OF THE SUPERINTENDING ENGINEER / CIVIL,PROJECTS & ENVIRONMENT

3rd FLOOR / EASTERN WING, NPKRR MAALIGAI,144, ANNA SALAI, CHENNAI-600 002, TAMIL NADU.

(Not Transferable)

Page 2: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 2/101

:TAMILNADU GENERATION AND DISTRIBUTION CORPORATION LIMITED :

SPECIFICATION NO. SE/C/P&E - 05/ 2012-13

1. NAME OF WORK :  ENNORE SEZ THERMAL POWER PROJECT –2X660MW - Site Grading the area of the proposedsite for establishment of 2X 660 MW Ennore SEZcoal based Super critical Thermal Power Plant inthe Ash Dyke area of North Chennai ThermalPower Station (NCTPS)

 2. E.M.D. : Rs. 15,00,000 /-

3. DUE DATE AND TIME FORSUBMISSION OF TENDER : Up to 2.00 p.m. on 03.04.2013

4. DUE DATE AND TIME OFOPENING OF TENDER : At 2.30 p.m. on 03.04.2013

***

Page 3: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 3/101

FOR ATTENTION OF TENDERERS

A. BID QUALIFICATION REQUIREMENT.

i) Bidders should have got proven experience in the similar nature of worki.e. site grading by cutting and filling.

ii) The bidders should have executed similar site grading / Excavation /filling works to a value not less than Rs.10 crores in a single contract inany one of the last three years. Necessary end user certificate is to beenclosed along with the bid.

iii) Bidders should have executed similar site grading / Excavation / filling

works to a quantity of not less than 8 lakh m³ in a year in a singlecontract with in last three years. The bidder should produce necessaryend user certificate for the same.

iv) Annual turnover of the bidders shall not be less than Rs.10 crores

during any one of the last three financial years. Necessary auditedannual statement of accounts for the previous three years shall befurnished along with the offer.

v) Experience of the main contractor shall only be considered for satisfyingthe experience criteria specified in Bid Qualification Requirement.

vi) Joint Ventures/Consortiums are not eligible to participate in the tender.

vii) The Bidders may also enclose the following documents as a proof of Turn Over.

a. Attested copy of IT return filed by the Bidder.

b. Attested copy of STCC

c. Attested copy of Enlistment Certificate issued by NSIC containing turn

over details of Bidder for respective periods.

viii) BQR evidences submitted by the Bidder after opening of Techno

Commercial Bid, but before opening of Price Bid will also be considered

for evaluation.

ix) Bidders not satisfying the Bid Qualifying Requirement will be summarily

rejected.

Page 4: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 4/101

B. EARNEST MONEY DEPOSIT PARTICULARS.

1) Earnest Money Deposit for an amount of Rs.15,00,000/- in theform of Demand Draft / Banker's Cheque drawn in favour of TANGEDCO Collection Account payable at Chennai is to be

placed in the outer cover or along with sealed inner cover containing technical bid (Envelope-‘A’).

2) If the TENDERER is exempted from payment of E.M.D, the proof for such exemption and undertaking as prescribed in thespecification are to be placed in the outer cover or along with thesealed inner cover containing technical bid (Envelope-‘A’).

 3) If the TENDERER is having Permanent Earnest Money Deposit

of Rs.20 lakhs and above at TANGEDCO Headquarters alone andnot forfeited, the proof of same, is to be placed in the outer cover or along with the sealed inner cover containing technical

bid (Envelope-’A’) .

4) When the outer cover is opened, it should have the following twoitems.i) One of the above three items (1 or 2 or 3 either in the outer 

cover or Envelope-’A’)

ii) Envelope-‘A’ - Technical Specification, commercial terms andexperience. This envelope should not contain any price bid.

iii) Envelope-‘B’ - Should contain filled in price bid in duplicateonly.

 5) At the time of opening of the tenders any offer which does not

satisfy the Earnest Money Deposit conditions, shall not be readoutand will be rejected. Then it will be returned by the concernedofficer to the TENDERER stating the reasons for rejection.

C) Tender documents can be downloaded from TANGEDCO website(www.tnebnet.org) or GOTN website (www.tenders.tn.gov.in) atfree of cost and the same shall be enclosed along with the offer asstated in Clause 4.0 of Section-‘A’ of this Specification.

Page 5: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 5/101

INDEX

SECTION CONTENTS PAGE No.

From To

 A Scope of work, Definition of Terms and

Specification documents, Instructions tobidders 1 20

B Project Information21 21

C General and Commercial conditions of contract 22 59

D Technical specification60 69

E Schedule of quantities (Separate book isenclosed in duplicate) - -

F Annexures 70 81

G Bid drawings- -

Page 6: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 6/101

CONTENTS

SECTION - A

Cl.No. DescriptionPageNo.

1.0 Scope of Work 1

2.0 Definition of Terms & SpecificationDocuments

2

2.1 Definition of terms 2

2.2 Specification Documents 5

3.0 Instruction to Bidders 6

3.1 Information Furnished 6

3.2 Time of completion and work schedule 7

3.3 Night Work 8

3.4 Inspection of site by bidders 9

3.5 Work Execution and Supervision 10

3.6 Services & Facilities by the Owner 10

3.7 Prices & Rates 11

3.8 Validity of Bid 11

3.9 Demobilisation 11

3.10 Security & Safety Rules of Owner 11

3.11 Payment 12

3.12 List of Works 12

3.13 Drawings 12

3.14 Discrepancies between Drawing &Specification

12

3.15 Bid Documents 12

4.0 Submission of Bid (Two Part tender System)

13

5.0 Return of Bid Document 16

6.0 Owner Reserves right 16

7.0 Materials Supplied By Contractor 17

8.0 Surveying and Lay out 17

9.0 Quantities 17

10.0 Splitting of Work 1711.0 Equipment 17

12.0 Delivery & Prices 18

Page 7: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 7/101

Cl.No. DescriptionPageNo.

13.0 Other Works 18

14.0 Contract Documents 18

15.0 Sub-Contractor 19

16.0 Bid Evaluation 19

17.0 Registration in TANGEDCO 20

18.0 General Note 20

SECTION - B

Cl.No. Description PageNo.

1.0 Project Information 21

Page 8: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 8/101

SECTION – C

Cl. No. DescriptionPage

No.1.0 Submission of Tender 22

2.0 Certificate of Income Tax 24

3.0 Earnest Money Deposit 25

4.0 Validity of Tender 27

5.0 Security Deposit 27

6.0 Instructions to Tenderers 28

7.0 Employment of technically qualifiedPersonnel by the contractors in theexecution of works.

30

8.0 Insurance 31

9.0 Schedule of Quantities 31

10.0 Completion of works 32

11.0 Sub-letting 33

12.0 Further information 33

13.0 Evidence of Previous experience 33

14.0 Supply of compressed air 33

15.0 Power Supply for works 34

16.0 Water Supply for works 34

17.0 Erection of Sheds 34

18.0 Rates of Contract 35

19.0 Completeness of scope 35

20.0 Liquidated Damages 35

21.0 Force Majeure 36

22.0 Terms of payment 36

Page 9: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 9/101

Cl. No. Description PageNo.

23.0 Contractor not to dispose off soil, etc. 37

24.1 Liability for accidents to persons 38

24.2 Liability for Damage to Works or Plants 39

25.0 Power for Engineer to decide order of works

40

26.0 Contractor to inform Engineer for arrangements for execution of work

40

27.0 Sunday Work 40

28.0 Suspension of work 40

29.0 Inspection of works 41

30.0 Patent Rights 42

31.0 Access to site and work on site 42

32.0 Materials brought to the site of works 43

33.0 Contractor to keep inventory of plant, etc. 43

34.0 Tools and Plants for the execution of thecontract

43

35.0 Maintenance 43

36.0 Completion Certificate 44

37.0 Final Certificate 44

38.0 Certificate to be Provisional and Subjectto correction

44

39.0 Negligence 45

40.0 Death, Bankruptcy etc. 46

41.0 Measuring, valuing and certifying byEngineer 

46

42.0 Arbitration 46

43.0 Cleaning up 46

Page 10: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 10/101

Cl. No. Description PageNo.

44.0 Jurisdiction 47

45.0 Submission of PERT Chart 47

46.0 Quality of Materials 47

47.0 Waste Materials 47

48.0 Recovery of money from Contractor 48

49.0 Weekly Progress Reports 48

50.0 Gold, Silver, Minerals, Oil, Relics etc.found on the site.

48

51.0 Interest on money due to the contractor 48

52.0 Deviation, alterations etc. in the materials 48

53.0 Deviations, alterations and additions to

the works

49

54.0 Claims for extra work or for deductions 49

55.0 Measurement of Extra works 49

56.0 Rates for Supplemental Items 50

57.0 Work executed by day labour 50

58.0 Application for retention sum 51

59.0 Breach on part of Purchaser not to annulcontract

51

60.0 Regulations of local authorities 51

61.0 Notices : How to be given 51

62.0 Construction of contract 52

63.0 Contractor's Representatives andworkmen

52

64.0 Right of Engineer to order withdrawal of labour 

52

65.0 Works materials, works and workmanshipto be executed to the satisfaction of theEngineer 

53

Page 11: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 11/101

Cl. No. Description PageNo.

66.0 Execution of works in conformity with thecontract documents

53

67.0 Contract includes all necessary operation 54

68.0 Contractor to supply and be responsiblefor the sufficiency of the means employed

54

69.0 Fencing and Lighting 54

70.0 Discrepancies between drawing andspecification

54

71.0 Quantities, Prices and Payment 55

72.0 Documents Confidential 55

73.0 Tender Document not returnable 55

74.0 Filling up of Tender Proforma 55

75.0 Illumination 55

76.0 Communication facilities 56

77.0 Health and Sanitary Rules for workers 56

77.1 First Aid 56

77.2 Drinking Water 56

77.3 Washing and Bathing places 56

77.4 Latrine and Urinals 57

77.5 Shelters during rest 57

77.6 Crèches 5777.7 Canteen 58

78.0 Shed for Workers 58

79.0 Provisional Laws 58

80.0 Taxes and Duties 58

80.1 Excise Duty 59

80.2 Service Tax 59

81.0 Precaution during working 59

82.0 Deduction for Labour Welfare Fund 59

Page 12: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 12/101

SECTION – D

Cl.No.Description

PageNo.

1.0 Scope60

2.0 Drawing 60

3.0 General 60

4.0 Reference Pillars and Bench Marks 61

5.0 Excavation 61

6.0 Measurement and Payment 61

7.0 Timber Shoring 62

8.0 Dewatering 63

9.0 Rain Water drainage 6310.0 General site grading 64

11.0 Fill Density 64

12.0 Filling with pond ash 64

13.0 Extent of work 65

14.0 Placement 66

15.0 Procedure 66

16.0 Compaction 66

17.0 Moisture control 6718.0 Prevention of Pollution 67

19.0 Stability of Excavation 67

20.0 Protection of filling 68

21.0 Measurement and Payment 68

22.0 Finishing of surfaces 68

23.0 Sampling and testing 68

24.0 Acceptance Criteria 69

25.0 IS CODES 69

Page 13: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 13/101

SECTION - E

SCHEDULE OF QUANITIES - SEPARATE BOOK

SECTION – F

ANNEXURE- I to VIII

Annexure Description Page No.

I Proforma for submission of tender 70

II Particulars of employment of ex-servicepersonnel

73

III Undertaking in-lieu of payment of EMD 74

IV Schedule of equipment 76V Schedule of rates for labour 77

VI Bidders experience 78

VII Details of technical personal of thetenderers organization

79

VIIII Undertaking towards Jurisdiction for  Legal Proceedings

80

Page 14: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 14/101

SECTION - A

Page 15: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 15/101

1 SECTION - A

Name of Work : ENNORE SEZ THERMAL POWER PROJECT – 2X660MW -Site Grading the area of the proposed site for establishmentof 2X 660 MW Ennore SEZ coal based Super critical ThermalPower Plant in the Ash Dyke area of North Chennai Thermal Power Station (NCTPS)

****1.0. SCOPE OF WORK

The scope of work covered under this specification pertains to the SiteGrading the area of the proposed site for establishment of 2X 660 MWEnnore SEZ coal based Super critical Thermal Power Plant in the AshDyke area of North Chennai Thermal  Power Station (NCTPS). The Earthwork excavation/cutting will be in the wet ash under water in Ash pondarea and peripheral canal, transporting and filling in low lying areaincluding cutting, transporting loading, spreading and consolidation in

layers using power roller etc., The Earth work excavation will also be inthe existing Ash Dyke bund to required level, including earth work,transporting, loading, spreading and compaction using power roller etc.,and all operations covered within intent and purpose of this specification.

.1.1 The scope of work may also include such related works as indicated in the

“Schedule of Quantities” although they may not be specifically mentionedin the above paragraphs, and all such incidental items not specified butreasonably implied and necessary for the completion of the job as awhole, all as desired and as directed by Owner. All works shall be done ina manner acceptable to the owner who shall have power to reject any

work or material which, in his judgement, is not in full accordance with thespecification.

1.2 Owner reserves the right to split up the work included in the scope of thiswork among more than one contractor at the stage of initial award or during the progress of work in case of unsatisfactory work or slowprogress of the contractor.

1.4 All the costs and expenses incidental for preparation of bids, discussionsand conferences, technical and other presentation in the Purchaser’s officeetc. shall be to the account of the bidders and purchaser shall be no liability

whatsoever on such costs and expenses.

1.5 Time is the essence of the contract. With this in view, the Purchaser /Engineer shall have the right to add, alter, modify the scope of work,defined above during the execution of the work. In the event of any disputeregarding the scope of work, the decision of the Purchaser / Engineer shallbe final and binding.

Page 16: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 16/101

SECTION – A2

2.0 DEFINITION OF TERMS AND SPECIFICATION DOCUMENTS2.1 DEFINITION OF TERMS

a) ‘OWNER'/`PURCHASER' shall mean the TANGEDCO on whosebehalf the work is issued and shall include TANGEDCO’sauthorised officers.

b) ‘ENGINEER’ shall mean duly authorised representatives, appointedby the OWNER/PURCHASER for the ‘Project'.

  c ) `BIDDER' shall mean the firm/party who quotes against the work.

  d) ‘VENDOR / CONTRACTOR / FABRICATOR’ shall be theSuccessful Bidder whose Bid has been accepted by the OWNER/PURCHASER and on whom the Contract or Purchase Order isplaced by the OWNER / PURCHASER and shall include hisheirs, Legal representatives, and successors and permittedassigns.

 e) ‘SUB-VENDOR / SUB-CONTRACTOR / SUB-FABRICATOR' shall

mean the person named in the `Contract' undertaking a part of thework or any person to whom a part of the `Contract’ has beensublet with the consent in writing of the OWNER/ PURCHASERand shall include his heirs, legal representatives, successors andpermitted assigns.

f) ‘MANUFACTURER' refers to a person or firm who is the producer and furnisher of material or designer and fabricator of equipment toeither the OWNER/PURCHASER of the VENDOR/CONTRACTOR

or both under the ‘Contract'.

g) ‘OTHERS’ shall mean other successful BIDDERS whose Bids havebeen accepted by the OWNER/PURCHASER and to whom theorders have been placed by the OWNER/PURCHASER and shallinclude their heirs, legal representatives, successors and permittedassigns.

h) ‘INSPECTOR’ shall mean authorised representatives appointed bythe OWNER/PURCHASER or the ENGINEER for purpose of inspection of materials /equipments / works.

  i) ‘PROJECT’ shall mean the actual place of the proposed ‘Project’ asdetailed in specification or other places where work has to beexecuted under the contract.

j) ‘SITE’ shall mean the actual place of the proposed work spot asdetailed in the Specification or other place where work has to beexecuted under the contract.

k) `MONTH' shall mean calendar month.

Page 17: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 17/101

SECTION – A3

l) ‘SPECIFICATION' shall mean collectively all the terms andstipulations contained in those portions of the `Contract’ known asGeneral Conditions, the Specifications and such Amendments,Revisions, Deletions or Additions, as may be found in the

 Agreement and all written Agreements made or to be made

pertaining to the method and manner of performing the work or tothe quantities and qualities of the materials to be furnished under this `Contract'.

m) ‘BID’ shall mean the proposal/ document that the BIDDER submitsin the requisite and specified form in the `Specification'.

n) `PLANT’ or `EQUIPMENT and `WORK' or `WORKS’ shall meanrespectively the goods to be supplied and services to be providedby the VENDOR / CONTRACTOR / FABRICATOR under the`Purchase Order' or Contract'.

o) `CONTRACT’ or `PURCHASE ORDER' shall mean the order andassociated specifications executed by the OWNER/ PURCHASERand the VENDOR/ CONTRACTOR including other documentsagreed between the parties or implied to form a part of the`Contract'.

  p) ‘CONTRACT PRICE’ shall mean, if there is a formal agreement, theprices referred to in the agreement or if there is no formalagreement, the price agreed to be the value of the `Contract'.

q) ‘DATE OF CONTRACT' shall mean the calendar date on which theOWNER/PURCHASER and VENDOR/ CONTRACTOR havesigned the `Contract'.

r) ‘CONTRACT PERIOD' shall mean the period during which the`Contract' shall be executed as agreed between VENDOR /CONTRACTOR and OWNER/ PURCHASER in the `Contract'.

s) ‘MAINTENANCE PERIOD’ shall mean the period during which thework shall give the same performance as guaranteed by theVENDOR in the Schedule of Guarantee as in the `Specification'.

t) ‘ APPROVED’ and `APPROVAL', where used in the `Specification'shall mean, respectively, approved by and approval of theOWNER/PURCHASER or the ENGINEER. When the words,`Approved', `Approval', `Subject to Approval’, ‘Satisfactory', `Equalto’, `Proper', `Requested', `As Directed', `Where directed', `Whendirected’, `Determined By', `Accepted', `Permitted’ or words andphrases of like import are used, the approval, judgement, directionetc. is understood to be a function of the OWNER/PURCHASER or the ENGINEER.

Page 18: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 18/101

SECTION – A4

u) "ENGINEER’s INSTRUCTIONS" shall mean any drawings and/or instructions oral and/or in writing, details, direction and explanationsissued by the ENGINEER or the OWNER/PURCHASER from timeto time during the `Contract Period'.

v) ‘WRITING' shall include any manuscript, typewritten or printedstatement under or over signature and/or seal as the case may be.

w) ‘NOTICE IN WRITING' or `WRITTEN NOTICE' shall mean a noticein written, type or printed characters sent (unless deliveredpersonally or otherwise proved to have been received) byregistered post to the last known private or business address or registered office of the addressee and shall be deemed to havebeen received when in the ordinary course of post it would havebeen delivered.

x) ‘CONTRACTOR WORKS’ or ‘ MANUFACTURER’S WORKS’ shallmean and include the land and other places which are used by theVENDOR/CONTRACTOR /FABRICATOR or SUB-VENDOR/ SUB -CONTRACTOR / SUB-FABRICATOR for the manufacture of ‘Equipment or performing the ‘Works’.

y) ‘VIRTUAL COMPLETION’ shall mean that all works are completedas directed and the ‘Site' is cleared to the satisfaction of theOWNER/PURCHASER or the ENGINEER.

z) ‘MINOR MODIFICATION' shall mean the modification work

required to be done on the ‘Equipment’ and `Works’, which need amaximum of 48 man-hours per item of work. In case of civilcontracts, it shall be `works’ which need a maximum of 8 man-hours per item of work.

aa) ‘MAJOR MODIFICATION’, as applied to equipment erectioncontracts only, shall mean the modification work required to bedone on the ‘Equipment’ and ‘Works’, needing more than 48 man-hours per item of work, where such work is required to be done for no fault of the VENDOR/CONRACTOR. In the case of Civilcontracts, it shall be works needing more than 8 man-hours per 

item of work.

ab) ‘COMMERCIAL USE’ shall mean use of equipment / work whichthe contract contemplates or that which equipment/ work iscommercially capable.

ac) Words implying the singular only shall also include the plural, andvice versa, where the context requires.

ad) `DRAWINGS' shall mean all:

Page 19: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 19/101

SECTION – A5

i) Drawings furnished by the OWNER/ PURCHASER or theENGINEER as a basis for proposals;

ii) Supplementary drawings furnished by the OWNER/ PURCHASERor the ENGINEER to clarify and to define in greater detail the intentof the `Contract'.

iii) Drawings submitted by the VENDOR with his proposal providedsuch drawings are acceptable to the OWNER/PURCHASER or theENGINEER.

iv) Engineering data/design and drawings submitted by the VENDORon award of work/ progress of the work provided such drawings areacceptable to the ENGINEER.

v) Drawings furnished by the OWNER/ PURCHASER or theENGINEER to the VENDOR during the progress of the work.

2.2. SPECIFICATION DOCUMENTS

a) This `Specification’ consists of six sections as listed below and allof these are to be considered together for correct understandingand interpretation of the Specification.

b) SECTION-A: The scope of work and description of the`Specification' document and the list of contents. It also includesinstructions to the BIDDERS and specific non-technicalrequirements.

c) SECTION-B: Relevant `Project’ information for the reference anduse of the BIDDER.

d) SECTION-C: General Conditions of Contract.

e) SECTION-D: Technical specifications of Contract.

f) SECTION-E: Schedule of Quantities (in separate book)

g) SECTION-F: Proforma for submission of tender, particulars of employment of Ex-service personnel, undertaking in lieu of 

payment of EMD, Schedule of equipments, Schedule of rates for labour, Bidder's experience, Schedules of deviations from technicalspecification, details of technical personnel of the tenderer'sorganisation and Statement showing the quantities for each type of quarters.

h) The BIDDER shall be deemed to have carefully examined the`Specification' in its complete form and to have fully informed andsatisfied himself as to the details, nature, character and quantities

Page 20: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 20/101

SECTION – A6

of the work to be carried out, site conditions and other pertinentmatters and details.

i) In case of conflict between different sections of the `Specification’requirements of Section-C shall govern.

 j) It is the intent of the OWNER/PURCHASER to incorporate thesespecification documents in the final `Contract’ or `Purchase Order’for the supply of material, equipment and services. The BIDDERSare required to review these documents and clearly state in their proposals their acceptance of the same. Exceptions, if any, shall beclearly stipulated in the appropriate bidding schedule. The final‘Contract’ between the OWNER/ PURCHASER and theVENDOR/CONTRACTOR shall be subjected to such changes, if any, mutually agreed upon between the OWNER / PURCHASERand the VENDOR/CONTRACTOR and included in the main text of the `Contract' or `PURCHASE ORDER'.

k) The bidder shall specify all the deviations with respect to thisspecification in the appropriate schedule.

INSTRUCTIONS TO BIDDERS

3.0. The provision of Tamil Nadu Transparency in Tender Act1998 and Tamil Nadu Transparency in Tender Rules 2000will be followed in the Tender.

3.1. INFORMATION FURNISHED

a) This Specification is intended as a general description of qualityenvisaged for material, workmanship and of the finished work. It isnot intended to cover minute details. The work shall be executed inaccordance with the best modern practice and to the completesatisfaction of the OWNER. Special techniques approved byENGINEER shall be used if and where found necessary.

 b) The information given in this Specification is in good faith and

meant to serve as a guide to the Tenderer. It is, therefore,imperative that Tenderer shall obtain and examine for himself allthe data, information and particulars required for the satisfactory

execution of the work under this enquiry. The submission of atender by Tenderer, implies that he has fully read theSpecifications, tender drawings, Contract Document and General /Technical Conditions of Contract and has made himself aware of the scope and the specifications for the work to be performed andlocal conditions and other features which have a bearing on thecost and execution of the work. The owner shall not, therefore, after acceptance of the tender, pay any extra charges for any reasonwhatsoever. If any tenderer requires clarifications on tender 

Page 21: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 21/101

SECTION – A7

documents it should be asked for before 48 hours of the opening of tender.

c) Tenderer should note that standard specification under Section-Dshould be read in conjunction with AMENDMENTS thereof, if any,general notes (given in the Section-C) should also be noted before

quoting rate against various items in Section-E.

d) In case of any conflict among the clauses and different technicalspecifications given under Section-D, the decision of the OWNERshall be final and binding on the CONTRACTOR.

3.2. TIME OF COMPLETION AND WORK SCHEDULE

a) Time is the essence of the Contract. The work covered under thiscontract as a whole shall be completed within 9 (Nine) months

from the date of handing over of site. To suit this completion period

the contractor has to bring necessary labour, plant, machinery andequipments. The interim period of completion for the mainplant area consisting turbine generator area transformer yardand GIS switchyard as given in the sketch is 5 (Five) months

from the date of handing over of site

b) The Contractor shall, within 10 days from date of handing over of site, submit to the Owner for his approval detailed work scheduleshowing how he proposes to carry out the work, specificallymentioning the periods as well as date of commencement andcompletion of each activity and such approved schedules must be

strictly adhered to, by Contractor. The Schedules are to bereviewed periodically with the Owner to ensure that the completiondate will be met or to institute corrective steps (at no extra cost tothe owner) to adhere to the completion dates.

The Owner reserves the right to revise the schedule at hisdiscretion in order to keep up the completion date and to suit theproject requirement and such alterations shall not entitle theContractor to any extra payment.

  c) The contractor should take over the site within 7days on receipt of 

award letter and commence the work.

d) The whole work must be proceeded with, within such sections andat such times and in such order and manner as described in thesespecifications and as directed by the ENGINEER. No extrapayment or escalation in the rates will be permitted on account of this.

Page 22: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 22/101

SECTION – A8

e) The contractor should furnish the ENGINEER with weekly progressreports in triplicate on the Saturday of every week in the followingformat.

Item of Work

ScheduleFor the

Week

 ActualProgress

Reasons for shortfall

Steps taken tomeet shortfall

(1) (2) (3) (4) (5)

f) The contractor shall make all necessary arrangements at site tomobilise machinery, equipment, labour and materials and tomaintain necessary number of machinery and equipment andoperators to guarantee such minimum rate of progress of thework as is required by the agreed schedule for the timely

completion of the work as per relevant clauses in GeneralConditions of contract.

g) Extension of contract period, only for completion of work shall begranted by the OWNER equal to the period of Force Majeureconditions if were in existence as applicable to this contract.Monsoon, inclement weather shall not be considered as a reasonfor extension of time.

h) Idle time charges for any reason whatsoever shall not beentertained by the OWNER.

  i) If the contractor fails to maintain the stipulated time of completionspecified herein above, he shall be liable to pay liquidated damages

as set out in `General Conditions of Contract' under Section-C. Itshall be clearly understood that failure to meet the completion datesand or slow progress of work shall also attract penalty as per General Conditions of Contract in Tamil Nadu Building Practice(TNBP).

 j)  A PERT chart for executing the work should be furnished by thecontractor within TEN days from the date of handing over of site.Failure to submit the pert chart in time will attract a penalty of Rs.10,000/-

k) The contract period shall commence from the date of taking over of site.

3.3. NIGHT WORK

The time of completion as defined in clause 3.2 herein above, shallbe deemed to exclude working during night hours. However,ENGINEER may consider granting permission for working duringnight hours, if he considers it essential in order to complete thework in the stipulated time, on a specific request by theCONTRACTOR. Night work shall not entitle the contractor to anyextra payment. The contractor at his cost, to safeguard the

Page 23: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 23/101

SECTION – A9

workmen and the public, shall provide where night work is inprogress sufficient lights and he shall take suitable precautions toprevent accidents. Excavated areas shall be barricaded andprovided with red lights as a precaution to prevent accidental falls.

3.4. INSPECTION OF SITE BY BIDDERS

a) Bidder shall inspect the site, examine and obtain all informationrequired and satisfy himself regarding matters and things such asaccess to site, communication, transport, right of way, the type andnumber of equipment and facilities required for the satisfactorycompletion of work, the quantity of various sections of the work, theavailability of local labour, availability and rates of material, localworking conditions, uncertainties of weather obstructions andhindrances that may arise, etc. which may affect the work or costthereof, before submission of his bid. Ignorance of site conditionsshall not be accepted as basis for any claim for compensation of any nature during or after completion of work. The submission of a

bid by the bidder will be construed as evidence that such anexamination was made and any later claims/ disputes in regard torates quoted shall not be entertained or considered by the Owner.

b) The access road to the work site is available. If any temporaryfeeder road is considered essential for the proper execution of thework, this shall have to be formed by the contractor at his cost withthe prior approval of the ENGINEER and restored to originalcondition as and when required. The CONTRACTOR shall organisehis own arrangement to transport his equipment, men and materialsin such a manner that the completion period will not be exceeded

on any account.

  c) Power supply will be made available for construction purposes for specified construction equipments only as stipulated in Section-C.Water supply for construction purposes will be arranged bypurchaser as stipulated in Section-C.

d) The rates quoted by BIDDER shall be based on his own knowledgeand judgement of the conditions and hazards involved and shall notbe based on any interpretations of the ENGINEER.

e) It shall be ensured by the contractor that the work should proceeduninterrupted. As such adequate number of equipments shall beprovided by the contractor as an alternate arrangement in caseelectrically operated equipments are proposed to be brought tosite.

Page 24: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 24/101

SECTION – A10

3.5 WORK EXECUTION AND SUPERVISION a) Tenderer shall furnish along with the tender a list of machinery and

other equipment he proposes to employ in the work.CONTRACTOR shall provide and maintain all equipment andplants necessary in good working condition to perform the work atsite. All arrangements for transporting machinery, equipment, men

and materials to and from the site shall be done by CONTRACTORat his own expense.

b) The CONTRACTOR shall make his own arrangements for providing accommodation for all necessary staff, and storage spacefor equipment, consumables, but not limited to petrol andlubricants, explosives, oxygen, acetylene, welding rods, formingmaterials, etc., together with sufficient quantity of spare parts for efficient and uninterrupted execution.

c) During inclement weather, CONTRACTOR shall suspend

concreting for time as ENGINEER may direct and shall protect fromdamage all works in progress and works which are just thencomplete. All such temporary protective measures shall be atCONTRACTOR’s cost.

d) CONTRACTOR shall have at the site accredited and qualifiedENGINEERS and foremen/ supervisors with adequate number of years of experience in execution of similar works and alsooperators of machinery and equipment, for satisfactory progressand timely completion of the works.

e) CONTRACTOR’s ENGINEER-in-charge of the work at site shall becapable of interpreting the specification and drawings and makeadequate site decisions as and when required. He shall also takeinstructions from the ENGINEER and be responsible for carryingout the instructions. In the event of occurrence of any accidentat/near the site of work or in connection with execution of the worka report shall be made immediately to the ENGINEER, giving fulldetails of the accident. He shall also report such accidents to all thecompetent authorities wherever such reports are required by them.

3.6 SERVICES AND FACILITIES BY THE OWNER

a) The following facilities and services will be provided by the Owner to the CONTRACTOR:

i) One permanent benchmark and a reference base line for lay out.

ii) Some area of land as available at site (free of ground rent) toenable the CONTRACTOR arrange for site office/store at his owncost.

Page 25: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 25/101

SECTION – A11

3.7 PRICES AND RATES

a) Prices and rates quoted shall include cost of all materialsincluding labour, supervision, setting out, machinery andequipment, transport charges, all consumables such as but notlimited to petrol, oil, diesel, lubricants, pipes, ropes etc.,construction facilities such as arrangements for water 

diversion and dewatering, scaffolding, formwork, centring,shoring, tarpaulins, etc. taxes, duties, royalties, octroi and anyother levies payable on all transactions, overheads / profits of contractor, for due performance of the work under this contractincluding the taxes and duties mentioned in clause – 80 of Section C. Clauses 5.0 and 82.0 of Section C of the specificationshould also be taken into account while quoting the rates.

b) Prices and rates quoted shall be deemed to include everythingnecessary to satisfactorily complete work as determined by theEngineer. The quoted rates shall hold good for all shapes and sizes

of members whether or not shown in the tender drawings issuedalong with the Specification. The rates quoted shall hold good for works below or above GL irrespective of deviations unless separaterates are called for, for different elevations.

c) The prices and rates quoted shall be firm for the entire duration of contract and any agreed extensions thereto.

3.8 VALIDITY OF BID

 All the bids shall be valid for acceptance without any change inprices and rates for a period of 180 days from date of opening of 

tender. In case of TENDERERS who quote a lower validity thanthat called for in the Specification, their offer will be rejected.

3.9 DEMOBILISATION

Demobilisation of any materials, equipments, arrangements donefor execution of work but not limited to mixer machines, batchingplants, concreting pumps, dewatering pumps, welding transformers,cranes, crabs etc., should be carried out only with theconcurrence/approval of the ENGINEER in charge. If any of suchmaterial / equipments are required even after the demobilisationunder certain contingency the same have to be re-established by

the CONTRACTOR without any extra cost.

3.10 SECURITY AND SAFETY RULES OF OWNER

a) CONTRACTOR shall strictly abide by the rules and regulations of security and safety enforced by the OWNER. CONTRACTOR shallprovide proper identity cards, badges, etc. to his employeeswhenever directed by the OWNER.

b) CONTRACTOR shall be solely responsible for the security / safetyof his personnel and equipments.

Page 26: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 26/101

SECTION – A12

c) CONTRACTOR, his employees and agents shall not disclose anyinformation or drawing furnished to them by the Owner / Engineer.

 All drawings, reports or any other information prepared by theOwner/ Engineer/ Contractor, either individually or jointly for theexecution of the contract shall not be disclosed without prior written

approval of the owner. No photographs of the work or plant withinthe work site shall be taken without prior written approval of theOwner.

3.11 PAYMENT

The mode of submission of bills and payment shall be as indicatedin the General Conditions of Contract under Section-C.

3.12 LIST OF WORKS

Bidders shall submit along with their bids complete particulars of similar jobs executed by them as called for in "Bidder's Experience"

under Section-F.

3.13 DRAWINGS

Drawing showing the site location map of the proposed project inthe existing NCTPS ash dyke area of Primary Pond I, is enclosed.The drawings which are enclosed are intended to give thetenderers a general idea of the type and extent of the workinvolved. The drawings are as such indicative and for tender purposes only. Work shall proceed only based on technicalspecification and as directed the Engineer at site.

3.14 DISCREPANCIES BETWEEN DRAWING AND SPECIFICATIONShould there be any discrepancy between the specification and/or 

schedule of prices and/or drawings or any inconsistency error or omission in either of them, reference must be made to the Engineer for an explanation and the contractor will be held responsible for any errors that may occur in the work through neglect of thisprecaution.

3.15 BID DOCUMENTS

a) Under Section 3.13 of this Section, particulars of the bid drawing isindicated. The drawing is intended to give the bidder general idea

of the type and extent of work involved and as such, they areindicative and for bid purposes only. Work shall proceed only basedon the drawing furnished by the purchaser. No claim from thecontractor will be entertained by the owner, for the approvedconstruction drawings being at variance if any to any extent fromthose issued for bid purposes.

b) No alteration or mutilation, other than filling in particulars wherever called for, shall be made in the bid documents. Any changes /

Page 27: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 27/101

SECTION – A13

modification made by the bidder on the bid document itself shall notbe taken into consideration.

4.0  SUBMISSION OF BID (TWO PART TENDER SYSTEM)4.1 a) Bid shall be submitted in sealed envelope after duly filling in all

particulars called for, in the manner, set forth in the 'Notice

Inviting Tenders'.

b) Bid will be received up to the time and date mentioned in the ‘NoticeInviting Tenders'. Bids received after the due date and time will beimmediately returned to the bidder without opening the bid. If thelast day for submission of bid happens to be a holiday, the nextworking day will be the last day for submission of bid.

c) Each page of the bid document including the bid drawings shall besigned in Ink by the Bidder as a token of having examined thesame. Any corrections in the rates entered in the schedule of 

quantities shall also be signed by the Bidder in ink, beforesubmitting the bid. Non-compliance with this condition will make thebid liable for rejection.

d) The bid prices and rates must be filled in the Schedule of Quantitiesunder Section-E which are in duplicate and those received in anyother form will not be accepted. All the copies of the completedschedule of Quantities shall be submitted along with the other documents.

e) Bid shall be accompanied by a covering letter, in duplicate, in which

bidder may furnish any information which he wishes to beconsidered along with his bid.

f) All accompaniments to the bid shall be in duplicate.

4.2 Submission of Bids shall be under two part Tender System in twoseparate sealed envelope superscribed as “Envelope-A” and“Envelope-B”. Both the envelopes should be presented in anoverall sealed envelope as superscribed tender in respect of Specification No.SE/C/P&E - 05 / 2012-13 and submit the same onor before the notified due date and time fixed for the submission of 

the tender.

The first envelope – A shall contain the following :-i) Technical Specifications, Qualifying data for the works, layout

drawings, deviations from specifications and other technical details.

ii) Acceptance of commercial terms including payment terms,liquidated damages, guarantees and other commercial matters.

Page 28: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 28/101

SECTION – A14

iii) Relevant details about skilled personnel and experience inexecution of similar work to TANGEDCO/Other Electricity Board /Other organisations, along with copies of complete certificate for the same, and

iv) Any other information called for in the specification other than

price.

ENVELOPE – A SHOULD NOT CONTAIN ANY PRICE BID

The second envelope called Envelope ‘B’ shall contain all the pricebids.

 BIDDERS SHOULD QUOTE ONLY FOR THE STIPULATEDTECHNICAL SPECIFICATIONS. NO ALTERNATIVE DESIGNWILL BE ACCEPTED.

v) Envelope – A, Envelope – B and the cash receipt for the paymentof Earnest Money Deposit or any other form of Earnest MoneyDeposit as mentioned in clause 3.0 of Section C of the specificationshall be enclosed in an overall envelope and this shall be sent toreach the prescribed officer in the TANGEDCO on or before thenotified time and date for the receipt of tender. Envelope-A,Envelope-B and the overall envelope shall be individually sealed,superscribed and addressed as instructed in the specification.

The cash receipt for the payment of EMD / PEMD or any other formof EMD as mentioned in clause.3.0 of Section-C of Specification or 

proof of exemption from payment of EMD or undertakingalternatively shall also be placed in the inner sealed cover containing technical bid (Envelope-A).

4.3.  At the time and date notified for opening of the tenders, the overallenvelope will be opened and bids which do not contain E.M.D. inany one of the forms as specified in Clause 3.0. of Section-C of thespecification or proof of exemption from payment of E.M.D. will berejected straightway and Envelope A and B of these bids will not beopened and the same will be returned to the BIDDER byRegistered Post with Acknowledgement Due, stating the reason

thereof.

Envelope A of those bidders who satisfy the requirements of EMDwill only be opened at the time notified for opening. If any of theBidders indicate the price in Envelope A, the bid will not be read outand be rejected.

Envelope B shall not be opened at the time of opening Envelope-A,but will be authenticated on the covers by the Officers authorised toopen the bids.

Page 29: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 29/101

SECTION – A15

4.4. The bidder should furnish the evidences as called for under Section- ‘F’.

4.5. Bidders shall submit with bid certified copies of Auditor certificate / Annual Accounts and IT PAN Number along with IT returns filed by

the bidder and certified copies of Sales Tax Clearance Certificate.

4.6. Bidders shall submit along with his bid complete particulars of similar jobs executed by him as called for in ‘Biddersexperience’ under Section - ‘F’ and certificates from thecustomers for the timely completion of respective workswithin the contract period.

4.7. Bidders shall submit attested copies for the proof of having thenecessary tools and plants, RC Book of Vehicles or Bills for thepurchase of tools and plants or the auditors report certified by

Chartered Accountant and shall contain information regarding themachinery for which RC books are not available.

4.8. Bidders shall submit copies of work orders issued in respect of works not commenced and certificates from the customersregarding stage of work in progress.

4.9. Bidders shall submit attested copies of letter with the details of balance work and balance amount given by the Chief Executive of the Department or from the authority who executed the agreement.

4.10 Bidders shall produce an affidavit signed by him on a stamp papersRs. 20/- indicatinga) The balance works on hand as on date is Rs. ………..lakhs only.b) No. of staff in the firm ………c) For debarring one year from tendering when facts are

suppressed.

4.11 The above Bid-qualification details submitted by the bidders will beanalysed based on the above details.

4.12. The following shall also be furnished by the Bidder along with his

bid in Envelope A. Failure to furnish these information will make thebid liable for rejection.

a) A detailed note on excavation methods, machineries to beemployed for excavation & transport, method of placing &transporting concrete, formwork arrangements proposed andshuttering capacity.

b) Details of stand-by provision for plant equipments.c) Skilled manpower that will be deployed for operation and

supervision.d) Memorandum of understanding with a specialised Agency if any.

Page 30: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 30/101

SECTION – A16

e) A detailed write-up on the testing laboratory and procedure for testing, which the TENDERER will employ at site.

f) Bio-data of supervising engineers. The CONTRACTOR shall havequalified and experienced technical staff stationed full time at site.This technical staff shall be fully conversant with all aspects of thework and shall have previously supervised such kind of work.

5.0 RETURN OF BID DOCUMENT

BID document complete with all enclosures shall be returned to theaddressee indicated in “Notice Inviting Tenders” by every bidder towhom it is issued.

The tender documents and the connected documents, drawings,pamphlets, sketches, designs etc., submitted by the TENDERER(whether the TENDERER happens to be the lowest or not) shallbecome the property of the PURCHASER and are not returnable.

However in the case of rejected TENDERERS, clause 6.0 of Section-A of the specification shall govern.

6.0 OWNER RESERVES RIGHT

a) The OWNER reserves the right to accept any bidirrespective of whether it is the lowest or otherwise or reject any or all bids without assigning any reasons whatsoever.

b) The bid is also liable for rejection if it is:i) not in the prescribed form.

ii) not properly signed by the Bidder.

iii) not conforming to OWNER’s Specification.iv) not accompanied by Demand Draft / Bankers Cheque

from any Nationalised / scheduled bank or proof of exemption with the required undertaking / agreementwhere E.M.D is exempted.

v) with EMD in the form of cheque or Bank Guarantee.vi) received after the expiry of the due date and time.

vii) received by telex / telegram /fax /E.-Mail.viii) stipulating terms related to payment, which does not

conform to TANGEDCO's commercial terms.ix) received from any black- listed firm or contractor.

x) found that Bidder’s PAST PERFORMANCE or VENDORRATING is not satisfactory.

xi) received without superscription as prescribed in thespecification.

xii) from a TENDERER who is directly or indirectly connectedwith Government Service or TANGEDCO's service or Service of Local Authority.

xiii) from a TENDERER who quotes a lower validityperiod than that called for in the Specification.

xiv) The offer with deviation in Commercial and Technical terms

Page 31: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 31/101

SECTION – A17

of the specification.xv) from an approved tenderer whose permanent EMD is not

adequate for the particular tender.

7.0 MATERIALS SUPPLIED BY CONTRACTOR

 All materials including explosives required for the work will be

supplied by the CONTRACTOR and the owner will not supply anymaterials.

 8.0  SURVEYING AND LAYOUT

Only a base line and one permanent Bench mark would befurnished to the CONTRACTOR on the site and surveying andlaying out of all works shall be done by the CONTRACTOR at hisown cost. The CONTRACTOR shall maintain the reference line andthe Bench mark without disturbance during the course of executionof the work,

9.0  QUANTITIESThe quantities against various items of work furnished in theschedule of quantities under Section - E are approximate and arelikely to vary. They are meant only for the purpose of having acommon base of comparison of various tenders.

The Contractor should execute the work as per TANGEDCO’sSpecification without any deviation.

Deviation in quantities is likely during the execution of the contract.If any materials / works are necessarily required over and above

the estimate quantity, the contractor has to execute the work ataccepted rates without any extra cost.

10.0 SPLITTING OF WORK

OWNER reserves the right to split up the work covered in the scopeof this contract among more than one CONTRACTOR at the stageof initial contract award (or) during the operation of the contract dueto the unsatisfactory progress or quality of work or both, of theCONTRACTOR as considered by the OWNER. OWNER will notentertain any claim from the CONTRACTOR on account of suchsplitting up.

11.0 EQUIPMENTa) The BIDDER along with his bid shall furnish a list of the equipment

he proposes to deploy at the site to achieve the time of completionspecified.

b) The Contractor shall provide and maintain at the site necessarynumber and type of machinery, vehicles, equipments and surveyinstruments like Total station in good working condition for proper setting out and timely completion of the various works covered

Page 32: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 32/101

SECTION – A18

under this Specification. All arrangements for transporting theequipment to and from the site shall be done by the Contractor athis own expense. No claim shall be entertained for mobilisingadditional equipment and/or personnel to complete the work withinthe stipulated time. All equipment required for handling, transportand erection shall be arranged by the contractor at his cost.

c) Contractor shall provide all fuels and lubricants required for theoperation and maintenance of the construction machinery andequipment as well as his transport vehicles.

d) It shall be ensured by the Contractor that work shall proceeduninterrupted. Sufficient men / machine equipment shall bemobilised in this regard.

12.0 DELIVERY AND PRICES:

The prices should be for the finished work strictly in accordancewith the specification. The price should be in Indian currencyrupees. The price quoted should be on the basis of the unitrate as specified in the schedule-E and it should be inclusiveof Manual Labour Welfare Fund. The rate quoted shall notinclude Service Tax and Service Tax should be indicatedseparately. Service tax applicable to this contract shall bereimbursed upon production of documentary evidence.

13.0 OTHER WORKS

During the course of contractor’s work, other works either by the

owner or by other contractors or by both simultaneously will be inprogress within the project area. Contractor is to make his besteffort to work in harmony with others in the best overall interest of the project and its speedy completion and comply with Engineersinstructions in making alternative arrangements at any time for maintaining the work schedule at no extra cost to Owner.

14.0 CONTRACT DOCUMENT

A draft copy of the contract document has to be prepared by thesuccessful tenderer within 20 days from the date of receipt of detailed acceptance letter and sent to the Chief Engineer/ Projects

for acceptance. A copy of the specification for the preparation of draft contract document can be had from the Chief Engineer/Projects free of cost if required. After approval, the draft copy willbe returned to the Contractor. Based on the approved copy, theContractor will have to prepare one "Original Copy" along with the‘Articles of Agreement’ on a stamp paper of value of Rs.20/- andanother `Duplicate Copy' of the contract document duly signing allthe pages of both the copies and submit them within 15 days fromthe date of receipt of draft copy to the Chief Engineer / Projects for executing the contract document after the execution of agreement,

Page 33: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 33/101

SECTION – A19

the original copy will be retained in this office and the duplicatecopy will be returned to the Contractor. Six (6) true copies of thiscontract document shall be prepared by the Contractor andsubmitted to this office within 15 days of receipt of the approvedduplicate copy of the Contract document. The charges for thepreparation of the contract document shall be at contractor’s cost.

15.0 SUB-CONTRACTOR

Tenderers are requested to furnish a panel of sub-Contractors,proposed to be engaged by them, if desired, along with their bio-data, previous experience and financial status. Only those sub-Contractors listed in their tender and approved by the TANGEDCOwill be considered as sub-Contractor. No other sub-Contractor willbe acceptable to the TANGEDCO.

16.0 BID EVALUATION

16.1. GENERALThe bids will be evaluated strictly as per Tamil Nadu Transparencyin Tenders Act 1998 in Tenders Rules 2000 and as detailed below.The bids received and accepted will be evaluated by the Purchaser to ascertain the technically and commercially responsive bid for thecomplete scope of the proposal covered under these specificationsand Documents. Out of the tenders found to be substantiallyresponsive after initial examination, the tenderer who has quotedthe lowest evaluated price in accordance with evaluation criteria or the tenderer scoring the highest on the evaluation criteria specified,as the case may be, shall be determined.

16.2. In determining the lowest evaluated price, the following factors shallbe considered, namely.

a) The quoted price shall be corrected for arithmetical errors.b) In case of discrepancy between the price quoted in words and in

figures, lower of the two shall be considered.c) If there is a discrepancy between Rate and Amount, the rate

shall prevail.d) In case of discrepancy between the rate quoted in the schedule of 

original and duplicate, lower of two shall be considered.e) After evaluation and comparison of tenders, the tender 

accepting authority shall accept the lowest tender ascertainedon the basis of objective and quantifiable factors specified in theSpecification and giving relative weights among them.

f) No revised price bid will be entertained.

16.3 In order to secure the best possible procurement price, negotiationwith the tenderer determined as per Cl.16.1 and 16.2 above arepermissible subject to the provisions detailed below.

Page 34: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 34/101

SECTION – A20

a. If at any time before acceptance of tender, thetender accepting authority receives information that a tenderer who has submitted the tender, has been banned by anyprocuring entity, the tender submitted by the tenderer shall berejected even if it may be the lowest tender.

b. In case where two or more tenderers quoted the same price,Tender accepting authority shall split the work among suchtenderers taking into consideration, the experience and credentialsof such tenderers.

17.0 Registration in TANGEDCO

The successful tenderer, on intimation from TANGEDCO has toregister his name in TANGEDCO.

18.0 GENERAL NOTE

There is no departmental supply of items in this work, unless it isspecifically stated in the schedule of the work. Therefore, thetenderer, in this tender shall state the source of supply of variousmaterials, such as cement, steel reinforcements, etc. which are tobe supplied by the tenderer for the various items of work if applicable.

Page 35: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 35/101

SECTION - B

Page 36: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 36/101

SECTION - B21

SECTION – B : PROJECT INFORMATION

1. Owner/ Purchaser : TAMIL NADU GENERATION ANDDISTRIBUTION CORPORATION LIMITED

2. Name of work : ENNORE SEZ THERMAL POWERPROJECT – 2X660MW - Site Grading the

area of the proposed site for establishmentof 2X 660 MW Ennore SEZ coal basedSuper critical Thermal Power Plant in the

 Ash Dyke area of North Chennai ThermalPower Station (NCTPS)

3. Location : Ash dyke of North Chennai Thermal Power Station – Primary Pond I , Thiruvallur District, Tamil Nadu35 km from Chennai Central.

4. (i) Nearest Railway Station : Athipattu Pudunagar, Chennai -120.(ii) Nearest Town : Athipattu, Chennai

5. Nearest Airport : Chennai Airport (60 km).

6. Access Road : All weather road from Pattamandiri on theThiruvottiyur – Ponneri District Highway

7. Elevation above MSL : Approximately +10.0 m above MSL

8. Ambient air Temperature

i) Annual Mean Maximum : 450Cii) Annual Mean Minimum : 15.60C

9. Relative HumidityMaximum : 100%

Minimum : 36%Design : 75%

10. Annual Rainfalli) Maximum : 2540 mmii) Average : 1600 mm

iii) Minimum : 1175 mmiv) Monsoon showers : October to December 

11. Design wind pressure : As per I.S. 875 Part 3.

12. Seismic Data : Zone III as per I.S. 1893.

***

Page 37: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 37/101

SECTION - C

Page 38: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 38/101

SECTION - C22

SECTION – C: GENERAL AND COMMERCIAL CONDITIONS

1.0 SUBMISSION OF TENDER1.1. For and on behalf of TANGEDCO sealed tenders in duplicate

superscribed as “ENNORE SEZ THERMAL POWER PROJECT –2X660MW - Site Grading the area of the proposed site for 

establishment of 2X 660 MW Ennore SEZ coal based Super critical Thermal Power Plant in the Ash Dyke area of NorthChennai Thermal  Power Station (NCTPS)” conforming to theSpecification No. SE/C/P&E - 05/ 2012 - 13 will be received byChief Engineer/ Projects in the prescribed form obtainable fromSuperintending Engineer/Civil, Projects & Environment, 3rd Floor/Eastern Wing, NPKRR Maaligai, 144, Anna Salai, Chennai-600002.

 The Tamil Nadu Transparency in Tenders Act 1998 and the TamilNadu Transparency in Tender Rules 2000 are applicable for thistender.

TANGEDCO hereinafter called "TANGEDCO/ PURCHASER" willreceive bids for the contract as set forth in the accompanyingTechnical Documents. All bids shall be prepared and submitted inaccordance with these instructions.

The scope of work, the bidding procedures and the terms andconditions of contract are brought out in the Tender Documentswhich include:

a) GENERAL & COMMERCIAL CONDITIONS.b) TECHNICAL SPECIFICATIONS.

c) SCHEDULE OF QUANTITIES.d) BID-DRAWING.

These are to be considered together for correct understanding andinterpretation of the specification.

All the costs and expenses incidental to preparation of their proposal, discussions and conferences if any, including pre-awarddiscussions, technical and other presentation in the Purchaser'soffice, etc., shall be to the account of the Bidders and Purchaser shall bear no liability whatsoever on such costs and expenses.

The sale of Tender Documents to a prospective Bidder shall not

mean that he is considered qualified.

 Any attempt by any bidder to bring to bar extraneous pressureson the Tender Accepting Authority shall be sufficient reason todisqualify the tender.

The Rule 17 of Tamil Nadu Transparency in Tender Rules2000 provides that the Tender Inviting Authority may make

Page 39: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 39/101

SECTION - C23

changes, modifications or amendments in the tender documents at any time before opening of the tender.

  1.2 Information regarding the Project, Location, Approach to the site,Meteorological and Geological conditions as prevailing at the siteare provided in Section B. However, no undertaking is given to the

accuracy of this information and it shall no way invalidate thecontractors obligations under various clauses and conditions of thecontract in case any variation is encountered during executionstage .The bidder shall visit the site before quoting to ascertain for himself of all site, road and local conditions, existing ground levels,location of supply points for construction, power and water,location of stores, construction yard, other uncertainties etc,

Tenders received after the specified time shall be immediatelyreturned to the bidder without opening the tenders.

1.3 The tenderers should submit their tenders under two cover tender 

system on or before 2.00 P.M. on 03.04.2013 addressed to theChief Engineer/ Projects, 5th Floor/ Western Wing, NPKRRMaaligai, 144, Anna Salai, Chennai-600 002 and submitting the bidin the office of Superintending Engineer / Civil, Projects &Environment, 3rd Floor/ Eastern Wing, NPKRR Maaligai, 144, Anna Salai, Chennai-600002. Please refer clause 4.0 of Section Aof the specification for details.

1.4. SUBMISSION OF TENDERS IN PROPER FORMThe tenders not submitted in proper form and in due time are liableto be rejected.

1.5 The TENDERER should submit his rates only in the Departmentschedule of quantities, Section-E in duplicate enclosed. Thetenderers should work out their own workable rates. Theapproximate value of work is about Rs. 1902 lakhs.

1.6 The tenders received within the time schedule fixed for submissionof tenders alone will be opened in the presence of Tenderers or theauthorised agents as may be present, by the Chief Engineer/Projects or his authorised representative at 2.30P.M. on03.04. 2013.

1.7 The Tenderers or their authorised agents are expected to bepresent at the time of opening of tenders. The tender receivingofficer will, on opening each tender, indicate attested andunattested corrections therein. The absentee Tenderer shall acceptthe corrections indicated without any question whatsoever.

1.8 If the tender is made by an individual, it shall be signed with his fullname and address. If it is made by a firm, it shall be signed by anauthorised person who shall furnish his own name and designation

Page 40: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 40/101

SECTION - C24

and the name and address of each member of the firm. If thetender is made by a corporation, it shall be signed by a dulyauthorised officer who shall produce with his tender satisfactoryevidence of such authorisation. Such tendering corporation may berequired, before the contract is executed, to furnish evidence of itscorporate existence.

1.9 TENDER AND AGREEMENTThe fact of the submission of tender to TANGEDCO shall bedeemed to constitute an agreement between the TENDERER andTANGEDCO whereby such tender shall remain open for acceptance by TANGEDCO. If the TENDERER be notified that histender is accepted by TANGEDCO, he shall be bound by the termsof the agreement constituted by tender and such acceptancethereof by TANGEDCO, until a formal contract of the same tender has been executed between him and the department inreplacement of such agreement. The stamp duty payable in thisagreement shall be borne by the successful TENDERER.

2.0 CERTIFICATE OF INCOME TAXThe tenderer should furnish evidence of Permanent AccountNumber (PAN) in the tender.

2.1 Income Tax payable on the contract amount at the appropriate rate

levied from time to time will be deducted from and out of thepayments to be made to the CONTRACTORS in accordance withthe provision of Income Tax Act 1961 as amended from time totime.

 2.2 One copy each of the annual report, balance sheet, Trading

 Account and Profit and loss Account for the last three years dulyaudited by a chartered Accountant should be submitted bycontractors / suppliers.

The attested copy of I.T. return filed by the bidders, attested copyof Sales Tax Clearance Certificate and attested copy of enlistmentcertificate issued by NSIC containing turnover details of the bidder for the respective period to be enclosed.

Note :-

(i) Government and Public Sector Undertakings need not submitannual report / balance sheet.

(ii) A separate statement showing the results of operations andfinancial position of the firm during the preceding three yearsshould also be furnished in the form given below:-

Last Year Ending1. Sales

Page 41: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 41/101

SECTION - C25

2. Gross profit3. Depreciation4. Pre-tax profit5. Taxation6. Net profit after tax7. Percentage of net profit on sale

8. Net Block9. Dividend declared10.Capital employed11.Reserves12.Percentage profit on capital employed.

2.3. BLACK LISTINGThe firm or the bidder will be blacklisted if the particulars producedby the bidders such as Auditor Certificate/ Annual Account, SalesTax Clearance Certificate & Experience etc., are found to be false.

3.0 EARNEST MONEY DEPOSIT

3.1. Each tenderer must pay as Earnest Money Deposit (EMD)a sum of Rs. 15,00,000 (Rupees Fifteen lakhs only). The aboveamount is payable in the form of Demand Draft / Bankers Chequefrom any Nationalised/ Scheduled Bank.

The Demand Draft / Bankers Cheque should be drawn in favour of TANGEDCO Collection Account, Chennai - 600002 payable atChennai.

3.2. The PEMD holders of Rs. 10,00,000/ and above at Headquartersonly can participate without remitting separate EMD specified for this tender.

The proof of PEMD shall be enclosed forthwith. 

3.3 If the Demand Draft / Banker’s Cheque from any Nationalised /Scheduled Bank towards Earnest Money Deposit or proof of exemption or proof of PEMD, is not placed in the cover as detailedin Cl.4.0 of Section A of the specification, the tender will berejected.

a) Purchase of Tender documents:i) The tender forms and connected documents shall be purchased by

the intending tenderers after remitting the rate prescribed towardsthe cost of the specification either by cash (payable before 1.30pm)or Demand Draft /Banker’s cheque drawn from any Nationalised/Scheduled Bank in favour of TANGEDCO Collection Account/Chennai –2 payable at Chennai.

ii) The tender specification are posted in websites (www.tnebnet.org)& www.tenders.tn.gov.in also. The Specification can bedownloaded from these websites at free of cost.

Page 42: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 42/101

SECTION - C26

b)  Exemption from payment of EMD :A firm is exempted from payment of EMD by virtue of the following:

i) Departments of Govt. of Tamil Nadu and Undertakings andCorporation owned by Govt of Tamil Nadu.

ii) The SSI units within Tamil Nadu and outside the Stateregistered with NSIC, if the SSI units have SSI registration in

respective Civil works as per the Bid Qualification Requirementcondition on written request.

iii) Labour contract co-operative societies.iii) Tiny Industries classified under SSI registered within the state of 

Tamil Nadu and registration certificate issued by Department of Industries and Commerce, Government of Tamil Nadu.

NOTE

1) A Copy of the registration certificate/exemption order shall beattached to the covering letter instead of Demand Draft/BankersCheque.

2) TENDERERS may note that their registration with the DGS &D does not entitle them to exemption from payment of EMDcalled for.

3) The SSI Units registered with District Industries Centres of Directorate of Industries and Commerce should hold PermanentRegistration Certificate. Further, they are exempted from paymentof EMD only for the materials specified in the SSI Certificate.

4) Temporary Registration Certificate is not entertained.5) Undertakings / Corporations and Departments of Central and

other State Government Departments shall have to pay cost of tender documents and E.M.D.

6) In respect of labour contract co-operative societies who areexempted from payment of EMD, only 90% of the bills are to beadmitted initially and the 10% is to be paid after satisfactorycompletion of the contract.

7) Firm exempted from payment of EMD shall furnish an undertakingas in Annexure IV of Section F.

3.4 REFUND OF E.M.D.The Earnest Money Deposit will be refunded by means of a chequeto the unsuccessful tenderer after the tender is finalised. Theamount shall not carry any interest.

3.5. FORFEITURE OF EMDThe EMD made by the TENDERER will be forfeited:

i) If he withdraws his tender after acceptance.ii) If he withdraws his tender before the date mentioned in the

clause 4 (Section C) `Validity of Tender’.iii) If the successful tenderer fails to remit the Security Deposit

amount within the stipulated period.iv) If he violates any of the provisions of these regulations or 

the conditions of tender, issued by the competent authority.

Page 43: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 43/101

SECTION - C27

v) If the particulars produced by the bidders such as Auditor Certificate / Annual Account, Sales Tax Clearance Certificate& Experience etc., are found to be false.

3.5.1 For the Tenderer participated with the production of proof for permanent EMD, the amount equivalent to Earnest Money

Deposit stipulated for this tender will be forfeited in the event of all cases specified for forfeiture of Earnest Money Deposit and

fact will be intimated to the concerned tenderer.

3.6 The Earnest Money will be retained in the case of successfultenderer and will not carry any interest. The E.M.D. will be adjustedagainst the Security Deposit.

In the event of the documents furnished with the offer is found tobe bogus or the documents contain false particulars, the EMD paidby the tenderers will be forfeited in addition to blacklisting them for future tenders/ contracts in TANGEDCO.

4.0 VALIDITY OF TENDERThis clause has already been discussed in clause 3.8 of Section Aof this specification.

5.0 SECURITY DEPOSIT5.1. When a tender is to be accepted, the TENDERER whose tender is

under consideration shall attend the office on the date fixed bywritten intimation to him. If the TENDERER fails to attend the officebefore the end of the period specified, his tender will not beconsidered. He shall forthwith upon intimation being given to him of acceptance of his tender by the PURCHASER must furnish aSecurity Deposit for AN AMOUNT which together with the EMDalready paid by him will amount to 5% of the contract value byD.D/Banker’s Cheque/Irrevocable Bank Guarantee from anyNationalised/ Scheduled Bank and then sign an agreement in theproper departmental form for the due fulfilment of the contract. TheSecurity Deposit if paid in the form of irrevocable Bank Guaranteeshould be valid for the entire duration of the contract and for themaintenance period of first twelve months. The Security Depositshall be paid within 15 days from the date of receipt of acceptanceletter. The payment of Security Deposit is a pre-requisite for signing the agreement. If the TENDERER fails to pay the Security

Deposit within the stipulated period, the acceptance letter is liableto be cancelled together with forfeiture of EMD. National SavingsCertificates and National Plan Certificates will not be accepted. If the Security Deposit in DD/ Banker’s Cheque/ Irrevocable BankGuarantee from any Nationalised/ Scheduled Bank is not paidwithin the time stipulated in the contract, 22 % penal interest will belevied from the date of receipt of actual payment for the delayedpayment of S.D.

Page 44: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 44/101

SECTION - C28

5.2. This Security Deposit and the amount withheld (as per Cl.22 of Section C) shall be retained as Security for the due fulfilment of thecontract. The Security deposit will be released as per Clause 22 of 

Section C. (Failure to enter into the required agreement or tomake the security deposits as defined in this clause shall entailforfeiture of the E.M.D). If the TENDERER withdraws his tender 

after its acceptance, the EMD deposited by him will be forfeited.The written agreement to be entered into between theCONTRACTOR and the PURCHASER in a non-judicial stamppaper of Rs.20.00 in the standard form (the cost of the stamppaper shall be borne by the successful TENDERER) shall be thefoundation of the rights of both the parties and the contract shallnot be deemed to be complete until the agreement has first beensigned by the CONTRACTOR and then by the proper Officer authorised to enter into contract on behalf of the PURCHASER.

5.3 Refund of Security Deposit and Retention Amount:If the Security Deposit is either in the form of D.D./Banker Cheque,

it will be refunded or Security Deposit in the form of BankGuarantee, it shall be returned to the successful TENDERER after expiry of 12 months reckoned from the date of completion of worksor as soon after the expiration of such period of 12 months as alldefects shall have been made good according to the true intent.

5.4. The amount withheld from the bills (as per Cl.22 of Section C) willbe retained under ‘Deposits’. The withheld amount will be refundedto the successful TENDERER after expiry of 12 months from thedate of completion of works. The payment of S.D., including Additional Security Deposit/ Retention amount will not bear anyinterest.

6.0 INSTRUCTIONS TO TENDERERS

The TENDERER shall examine closely the following: -6.1. Joint ventures/consortiums are not eligible to participate in this

tender.

6.2. Tamil Nadu Building Practice and also the General conditions of contract contained therein and Indian Standard Specification areapplicable for this contract. Unit rates shall be for finished work atsite. He shall also carefully study the drawings, additional

specifications, and all the documents, which form part of theagreement to be entered into by the accepted TENDERER. TheTamil Nadu Building Practice and other documents connected withthe contract such as specification, plans etc. can be seen on anyworking day in the office of Superintending Engineer/Civil/ Project& Environment, 3rd floor, Eastern Wing, NPKRR Maaligai, 144, Anna Salai, Chennai - 600002.

 

Page 45: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 45/101

SECTION - C29

The TENDERER’s attention is directed to the requirements, for materials under the clause `Materials and workmanship’ in the‘General Conditions of Contract’. Materials conforming to the IndianStandard Specification shall be used on the work and theTENDERER shall quote his rates accordingly.

6.3 Every TENDERER is expected before quoting his rates to inspectthe site of the proposed work. He should also inspect the quarriesand satisfy himself about the quantity and availability of thematerial and check the distance from various quarries to work site.The list of quarries where from certain materials can be obtained isgiven in the lead statement enclosed as Annexure-I, Section-F.The best class of materials to be obtained from the quarries or other sources defined shall be used on the work. In every case, thematerials must comply with the relevant standard specification.Samples of materials as called for in the specification as requiredby the ENGINEER in any case shall be submitted for theENGINEER’s approval before the supply to site of work is

commenced.

6.4 The PURCHASER will not, however, after acceptance of thecontract rate, pay any extra charge for the lead or for any other reason in case the CONTRACTOR has found later on to havemisjudged the materials available. Attention of the CONTRACTORis directed to ‘General conditions of Contract’ regarding payment of tolls, etc.

6.5 The Tamil Nadu Building Practice (TNBP) of the Tamil Nadu PublicWorks Department and I.S. codes will be followed for theperformance of the contract, wherever applicable and for allparticulars not specifically covered by this specification. Wherever there is difference between T.N.B.P. and I.S. codes, the relevantI.S. Codes will apply. The TENDERER’s attention is invited to theSections and clauses in the Standard `Preliminary specification of Tamil Nadu Building Practice' dealing with the following items

a) Test inspection and rejection of defective materials at work site.b) Carriage.c) Construction plant.d) Water and lighting.e) Cleaning up during progress and for delivery.

f) Accidents.g) Delays, andh) Particulars of payment.

6.6. a) Payment will be made by cheques on any of the commercialbanks or their branches in the Tamil Nadu as may bedecided by the PURCHASER from time to time. Exchangecommission, if any, in the issue of demand drafts / chequeswill be to the account of the successful TENDERER.

Page 46: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 46/101

SECTION - C30

b) No advance payments will be made for any item of work.c) The contractor should closely peruse all the specification clauses

which govern the rates of items for which he is tendering.

6.7 APPEAL

 Any TENDERER aggrieved by the order of tender acceptingauthority (Competent Authority) may prefer an appeal toPURCHASER within 10 days from the date of order and suchan appeal shall be disposed off within fifteen days.

6.8. MOBILISATION ADVANCENo mobilisation advance will be considered for this contract.

6.9. EMPLOYMENT OF EX-SERVICEMEN Attention of the TENDERER is invited to the Public WorksDepartment G.O.Ms.No.2385 dated 13.9.1945 according to whichthe CONTRACTORS must offer employment to ex-servicemen as

far as possible at local rates and a report shall be sent to theENGINEER for his reference.The number of ex-servicemen to whom he can so offer employment should be mentioned in the tender and he should alsoundertake in the agreement to offer such employment to suchnumber. Suitable clauses in the final agreement will be inserted tothis effect.

7.0. EMPLOYMENT OF TECHNICALLY QUALIFIED PERSONNELBY THE CONTRACTORS IN THE EXECUTION OF WORKSThe TENDERER should state in clear terms whether they areprofessionally qualified or whether they undertake to employtechnical men required by the department as specified in schedulebelow for the work, at their cost to look after the work.

Sl.No

Value of Contract

Minimum qualification prescribed for the Technical Staff to be employed.

Rate of penalty.

1. AboveRs.50lakhs One B.E./ Civil or equivalent degree

holder plus 3 Diploma Holder in CivilEngineering with 3 years experience

 Asindicatedbelow

 NOTEi) An amount of Rs.7000/- per month per person for Graduate

ENGINEERS and Rs.6000/- per month per person for diplomaholders will be recovered as penalty for non-employment of technical personnel.

ii) The CONTRACTOR should see that one of the senior mentechnically qualified is always at the site of work during workinghours personally checking all items of work and paying extraattention to such works as may demand special attention. If thetenderer fails to employ the technical staff as indicated above for 

Page 47: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 47/101

SECTION - C31

the works, penalty shall be levied as per the rate of penaltyindicated above for the period of such employment of technicalstaff.

  8.0 INSURANCEIt is incumbent on the part of the CONTRACTOR to see that it shall

be his sole responsibility to protect the public and his employees,against any accident from any cause and he shall indemnify thePURCHASER against any claim for damages for injury to personor property resulting from any such accident and shall also wherethe provisions of workmen’s compensation Act apply take steps toproperly insure against any claim there under by way of accidentrisk insurance demand for all purposes of relief, failing the sameor otherwise, CONTRACTOR alone will be responsible tomeet the compensation awarded under the said act.

The CONTRACTOR should satisfy the field SuperintendingEngineer that an `Accident Risk Insurance Policy’ is taken before

taking over the site for taking up the work and also to satisfy thefield Superintending Engineer, that the policy/policies is/are kept inforce till the contract is completed and the works are taken over bythe PURCHASER, on the issue of completion certificate.

  Recoveries will be made from CONTRACTOR's bill for any liabilityfor the accidents and refund of the same considered later after theclaim is fully settled by the Insurance Authorities.

  The CONTRACTOR shall insure all his plants and materialsagainst all possible risks including Transit Insurance or loss (or)damage from whatsoever causes. The rates quoted shall beinclusive of this.

9.0 SCHEDULE OF QUANTITIES9.1 Schedule of Quantities in duplicate indicating the items of work

generally involved in the scope of this specification is enclosed. Itshall be definitely understood that the PURCHASER does notaccept any responsibility for the correctness or completeness of this schedule and that this schedule is liable to alteration byomissions, deductions or additions at the discretion of theSuperintending Engineer (or as set forth in the conditions of contract). The TENDERER however may base his tender on this

Schedule of Quantities. He should quote specific rate for eachitem in the schedule and the rates should be written both in wordsand figures, and the units in words. The TENDERER should alsoshow the total of each item and grand total of the whole contract.Where there is discrepancy between the rates quoted in figuresand words, the lower of the two shall be considered. Where there isany discrepancy between rates and amounts, rates shall govern.When there is any discrepancy between rates in schedule of original and duplicate, the lower of two shall be considered.

Page 48: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 48/101

SECTION - C32

This schedule accompanying the tender shall be written legibly andbe free from erasures, over-writings or corrections of figures.Corrections where unavoidable should be crossed out with initialsand re-written.

The TANGEDCO or any officer authorised by it reserves right toreject any or all the tenders without assigning any reason there for and also reserve the right to award the entire work to ONECONTRACTOR or split the work suitably and award the same toone or more CONTRACTORS, without assigning any reasonsthereof.

9.2 RIGHT TO DECIDE THE TENDER RESERVEDIt shall be expressly understood by the TENDERER that thePURCHASER or the competent authority to decide the tender shallhave the right to relax or waive any of the conditions stipulated inthis specification wherever deemed necessary in the best interests

of the PURCHASER for good and sufficient reasons. ThePURCHASER or the competent authority to decide the tender reserves this right.

9.3 The TANGEDCO does not bind to accept the lowest and reservesthe right to reject any or all the tenders without assigning anyreasons therefor and also to award the entire work to oneCONTRACTOR or split the work suitably and award the same toone or more CONTRACTORS, without assigning any reasonsthereof.

10.0 COMPLETION OF WORKS

The time of completion shall be as per the clause on `Instructionsto bidders’ under Section - A of the specification provided alwaysthat if in the opinion of the Engineer, the completion of work shallbe delayed by the order of the ENGINEER or by any altered,modified, substituted or additional works or materials or by theorder of the works or materials to be omitted by any strike or lockout of any workmen employed by the CONTRACTOR or by causesdirectly due to him or by the CONTRACTOR not being given thepossession of the site or any part thereof, whether under thepower herein contained or otherwise or by any non-performance

of work or non-supply of materials to be performed or suppliedby the PURCHASER or by the CONTRACTOR not receivingany orders, drawings, instructions or directions in time or bythe suspension of the works, or by fire, flood, exceptionally badweather, tempest storm or by or from unforeseen circumstances(and whether the same shall be due to any act or omission of thePURCHASER or his agents or those in their respective serviceor not), the ENGINEER shall, if in his uncontrolled discretion shallthink whether forthwith or at any later time and from time to time

Page 49: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 49/101

SECTION - C33

notwithstanding that the prescribed or extended time for completion has expired or that the works have been completed,by writing under his hand extend the time for the completion of works to such date as he shall appoint. Provided always, thatunless the CONTRACTOR makes a written application to theENGINEER on or before the time when the cause of delay is

occurring or about to occur and unless the time is extended by theENGINEER, the prescribed time shall not be extendednotwithstanding delays from the foregoing or any other causes of whatsoever kind.

11.0 SUB-LETTINGNo part of the contract shall be sublet without prior writtenpermission of the Superintending Engineer nor shall transfer bemade by Power of Attorney authorising others, to receive paymenton CONTRACTOR's behalf.

In case of the CONTRACTOR engaging contract labourers with the

prior approval mentioned above in writing, the following should bestrictly adhered to.

a) The CONTRACTOR should fulfil strictly all the conditionsas stipulated in the contract labour (Regulation and Abolition) Act,1970 and the rules made there under.

b) The CONTRACTOR should take out a licence at his cost,under section 11 of the above said act within the specifiedperiod as mentioned by the Management / Principal employer at the time of awarding the contract.

12.0 FURTHER INFORMATIONIf further necessary information is required, the Chief Engineer/Projects, Tamil Nadu Generation and Distribution CorporationLimited, 5th Floor, Western Wing, NPKRR Maaligai, 144, AnnaSalai, Chennai-600 002 will furnish such, but it must clearly beunderstood that tenders must be received in order and according toinstructions.

13.0 EVIDENCE OF PREVIOUS EXPERIENCEAll TENDERERS shall furnish evidence of their good record andcapacity to do works. Previous works executed by them must beclearly indicated in the tender giving full particulars of value of workdone and the department / agency to whom the work was

executed.

14.0 SUPPLY OF COMPRESSED AIR  The successful tenderer has to make his own arrangement for the

compressed air required for the work at his cost.

Page 50: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 50/101

SECTION - C34

15.0 POWER SUPPLY FOR WORKSThe power supply will be effected at two convenient points to thecontractor, one near the work site and one near the Ash Pond B,by the Engineer at site. The contractor will have to put up andmaintain their distribution system at their own cost. Three phaseL.T. supply to the CONTRACTOR’s plants, tools and for works and

for lighting for works will be metered and charged as per theprevailing tariff under the category of LT tariff V commercial. Theenergy charges consumed by the contractor will be recovered fromhis bill at the rates prevailing from time to time.The CONTRACTOR may procure and supply to the PURCHASERnecessary energy meter for metering the supply and all charges for testing and maintenance of meters to the satisfaction of ENGINEER will have to be borne by the CONTRACTOR. Additional Tax on consumption of energy at the rate of 5% on theprice of energy consumed above will be levied. All equipments, materials and works in connection withCONTRACTOR's electrical installation shall conform to I.E. Rules

and specification and acceptable to the ENGINEER. TheCONTRACTOR’s electrical installation shall be maintained in safeand satisfactory operating condition.

ALTERNATE SUPPLYCONTRACTOR should not have any excuse if TANGEDCO’spower supply fails. Alternate arrangement for power supply bymeans of D.G.set shall be made by the CONTRACTOR at his owncost.

16.0  WATER SUPPLY FOR WORKThe contractor has to make his own arrangement for procurement /supply of water for construction and domestic purposes, if required,and the water so supplied shall conform to the requirements either for construction or domestic purposes as laid down in ISspecifications and WHO standards.

17.0 ERECTION OF SHEDSThe CONTRACTOR will be permitted to erect their own shed atavailable space for office/ stores at the place approved by thePurchaser free of ground rent.

The CONTRACTOR will also be permitted for putting up labour 

shed and living quarters for the construction staff, canteen etc. atthe land available, to the extent possible, at the place approved bythe Purchaser on rent basis at the rate of 9% on 50% of guide linevalue of the land. The CONTRACTOR has to make his ownarrangement to level the site and construct the labour shed, livingquarters, canteen and other facilities at his own cost.

Page 51: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 51/101

SECTION - C35

On completion of work, the contractor shall demolish his office,stores and labour sheds and living quarters and make the groundopen and plain at his own cost.

18.0 RATES OF CONTRACTThe prices and rates quoted by the contractor shall be firm for the

entire duration of the contract and any agreed extension theretoand more detailed in clause 3.7 of Section A of the specification.

.19.0 COMPLETENESS OF SCOPE

It will be deemed that the rates quoted by the TENDERER areinclusive of all incidental items of work not necessarily mentionedin the schedule but are nevertheless essential for the correct andcomplete execution of the work.

20.0 LIQUIDATED DAMAGESIf the CONTRACTOR fails in the due performance of his contractwithin the time fixed by the contract or any extension thereof, and

the PURCHASER shall have suffered any loss from the delayoccasioned by such failure, the CONTRACTOR is liable, at thediscretion of the ENGINEER and the Liquidated Damages for delayin execution which shall be at half percent (0.5%) of the contractprice of delayed portion for each completed week of delayreckoned on the contract value of such portion only of the works ascannot in consequence of the delay be used commercially andefficiently during each month between the appointed or extendedtime as the case may be and the actual time of acceptance or taking over of the work and such penalty shall be in full satisfactionof the CONTRACTOR’s liability for delay but shall not in any caseexceed 10% of the contract value of such portion of the work.

If the works executed in part could not be beneficially used by theTANGEDCO, the L.D shall be worked out on the basis of entirecontract value only and not on the value of delayed portion. Inaddition to this, the provision regarding levy of penalty for slowprogress of work and delay for not keeping up the interim and finalcompletion period specified for various mile stone activities asstipulated in the General Conditions of Contract in Tamil NaduBuilding practice for civil works would apply. The L.D. amount,penalty for slow progress and any other penalties put together shallnot exceed 10% of the value of the contract. The L.D. clause so

defined above is applicable for delays in supply as well as for Erection also wherever the clause is applicable, when such delaysare attributable to the contractor by way of non-adherence of completion schedule furnished by the tenderer as per clause 3.2 of Section A of this specification.

In case of default in executing the work, the CONTRACTOR isliable to pay to the TANGEDCO in addition to liquidated damagesfor delay the actual difference in price whenever the TANGEDCO

Page 52: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 52/101

SECTION - C36

orders the delayed works to be executed by other agencies athigher rate. The ENGINEER shall be at liberty to terminate thiscontract in case the CONTRACTOR slows down the works,abandons or does not use quality materials. A seven days noticesin writing shall be served to CONTRACTOR in this regard whichwill lead to even the termination of the contract without prejudice to

recover amount due either from money available through thiscontract or other contracts. The date of actual handing over to thePURCHASER after satisfactory completion alone shall bereckoned as date of completion.

21.0 FORCE MAJEUREIf at any time during the continuance of this contract, theperformance in whole or in part in any delegation under thiscontract shall be prevented or delayed by reasons of any war,hostilities, acts of public enemy, acts of Civil Commotion, strikes,lock outs, sabotages, fire, floods, explosions, epidemics,warranting restrictions or other acts of Nature (hereinafter referred

to as eventualities), then provided notice of the happenings of anysuch eventuality is given by the TENDERER to the PURCHASERwithin 15 days from the date of occurrence thereof, neither partyshall, by reasons of such eventuality, be entitled to terminatethis contract nor shall have any claims for damages against theother in respect of such non-performance and deliveries under this contract shall be refunded as soon as practicable after sucheventuality has come to an end or ceased to exist.

Provided that if the performance in whole or part by theTENDERER or any obligation under this contract is prevented or delayed by reasons of any eventuality for a period exceeding 60days, the PURCHASER may at his option, terminate this contractby notice in writing.

22.0 TERMS OF PAYMENTPayments will be made to the CONTRACTOR based on thecertificate to be issued at reasonably frequent intervals by theENGINEER from the date of issue of each certificate. For delay inmaking payment, the contractor shall have no claim and ensure theprogress of work shall not be affected.

Payments will be made for two bills on the basis of certificate and

every third bill will be paid on detailed measurements includingprevious payments. Detailed measurements will be recorded for allthe items of work done. 

22.1  An intermediate payment will be made by the ENGINEER of a sumequal to 95% of the value of work, as so certified and the balance5% will be withheld and retained as security for the due fulfilment of the contract. Under the certificate to be issued by the ENGINEERon completion of the entire works, the CONTRACTOR will receive

Page 53: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 53/101

SECTION - C37

the final payment of all the money due or payable to him under or any by virtue of the contract except security deposit and thewithheld amount equal to 5% of the total value of the work doneprovided there is no recovery from or forfeiture by theCONTRACTOR to be made under clause 57.0 of the GeneralConditions of Tamil Nadu Building Practice. The amount withheld

from the final bill will be retained under `Deposits' and paid to theCONTRACTOR together with the Security Deposit after twelvemonths reckoned from the date of completion of work or as soonas the expiration of such period of twelve months after all defectsshall have been made good according to the true intent andmeaning hereof whichever shall last happen. No certificate of theENGINEER shall be considered conclusive evidence as to thesufficiency of any work or materials or correctness of measurementto which it relates, nor shall it relieve the CONTRACTOR from hisliability to make good defects as provided by the Contract. TheCONTRACTOR when applying for a certificate shall prepare asufficiently detailed bill based on the original figures of quantities

and rates in the contract schedule to the satisfaction of theENGINEER, to enable the ENGINEER, to check the claims andissue the certificate. The certificate as to such of the claimsmentioned in the application as are allowed by the ENGINEERshall be issued within fourteen days of the application.

No application for a certificate shall be made within thirty days of aprevious application.

 Not more than two consecutive bills can be paid without detailedmeasurements or in a method as agreed by both the parties.

When there are complaints from the Labour Department aboutnon-payment of wages to the labourers employed by theCONTRACTORS for the execution of work under agreement, theENGINEER shall have full powers to withhold the bills claimed bythe CONTRACTOR pending clearance certificate from the labour department and to act as per the direction given by the Labour Department.

23.0 CONTRACTOR NOT TO DISPOSE OFF SOIL, ETC.The CONTRACTOR shall not sell or otherwise dispose off or remove, except for the purpose of this contract, the sand, stone,

clay ballast, earth, rock or other substances or materials which maybe obtained from any excavation made for the purpose of thiscontract or produce upon site at the time of delivery of thepossession of the land, but all such substances, materials andproduce shall be the property of the TANGEDCO provided that theCONTRACTOR may with the permission in writing of theENGINEER, use any of the same for the purposes of the works onthe terms that may be approved by the ENGINEER.

Page 54: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 54/101

SECTION - C38

24.0 LIABILITY FOR ACCIDENTS AND DAMAGES:24.1 LIABILITY FOR ACCIDENTS TO PERSONS

The CONTRACTOR shall indemnify and save harm to thePURCHASER against all actions, suits, claims, demands, cost of expenses arising in connection with injuries suffered, prior to thedate when the works or plant shall have been taken over, by the

PURCHASER by person employed by the CONTRACTOR or hisSUB-CONTRACTOR on the works whether under the general lawor under the Workmen’s Compensation Act, 1923, or any other statute in force on the date of the contract, dealing with question of liability of employer for injuries suffered by employees and to havetaken steps properly to insure against any claims thereunder.

On the occurrence of an accident which results in the death of theworkmen employed by the CONTRACTOR or which is due to thecontract work and of so serious nature as to likely to result in thedeath of any such workmen, the CONTRACTOR within 24 hours of happening of such accident intimate in writing to the concerned

ENGINEER and such officers required by the provision of theworkmen’s compensation Act the fact of such accident. TheCONTRACTOR shall indemnify the PURCHASER against all lossor damage sustained by the PURCHASER resulting directly or indirectly from his failure to give intimation the manner aforesaidincluding the penalties or fines, if any payable by the PURCHASERas a consequence, of the PURCHASER’s failure to give noticeunder the Workmen's Compensation Act or otherwise to conform tothe provisions of the said Act in regard to such accident.

In the event of any claim being made, or action brought against thePURCHASER involving the CONTRACTOR and arising out of thematters referred to and in respect of which the CONTRACTOR isliable under clause, the CONTRACTOR shall be immediatelynotified thereof, and he shall with the assistance, if he so requires,of the PURCHASER but at the sole expense of theCONTRACTOR, conducts all negotiations for the settlement of thesame or any litigation that may arise therefrom. In such cases, thePURCHASER shall, at the expense of the CONTRACTOR, affordall available assistance for any such purpose.

In the event of an accident in respect of which compensation maybecome payable under Workmen’s Compensation Act VII of 1923

and any subsequent amendment thereof whether by theCONTRACTOR, or by the PURCHASER, as principle it shall belawful for the ENGINEER to retain out of money due and payableto the CONTRACTOR such sum or sums of money as may be inthe opinion of the said ENGINEER be sufficient to meet suchliability. The opinion of the ENGINEER shall be final in regard to allmatters arising under this clause and will not be subject to anyarbitration.

Page 55: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 55/101

SECTION - C39

Liability for damage or loss to third party including inspectionofficers due to act of the CONTRACTOR or his SUB-CONTRACTOR connected with the execution of the contract shallbe fully borne by the CONTRACTOR. The CONTRACTOR shallmaintain such detailed records to furnish information regardingentertainment and discharge of all workmen employed under this

contract as to be adequate for the timely and full settlement of claims under the Workmen's Compensation Act. All cases of accidents or injuries shall be reported to the ENGINEER with allthe full details required for the settlement under the Workmen’sCompensation Act.

The CONTRACTOR should report about all accidents within 24hours to the Assistant Engineer of the PURCHASER in thepreliminary accident form. He should furnish other particulars suchas medical certificates, wage particulars, fitness, etc., in duecourse without delay.

24.2 LIABILITY FOR DAMAGE TO WORKS OR PLANTSThe CONTRACTOR shall during the progress of the work properlycover up and protect the work and plant from injury by exposure tothe weather, and shall take every reasonable, proper, timely anduseful precaution against accident or injury to the same from anycause and shall be and remain answerable and liable for allaccidents or injuries there to which until the same, be or beoccasioned by the acts or omissions of the CONTRACTOR or hisworkmen or his sub-contractors, and all losses and damages tothe works or plant arising from such accidents or injuries asaforesaid shall be made good in the most complete andsubstantial manner by and at the sole cost of the CONTRACTORand to the reasonable satisfaction of the ENGINEER. Shouldsuch loss or damage happen to units of works or plant or materialsfailing outside the scope of this contract and due to the contract,those shall be replaced or compensated for by the CONTRACTORto the satisfaction of ENGINEER.

In the case of loss or damage to any portion of the workoccasioned by other causes, the same shall, if required by thePURCHASER, be made good by the CONTRACTOR in likemanner but at the cost of the PURCHASER at a price to be agreedbetween the contractor and the PURCHASER and the

PURCHASER shall pay to the CONTRACTOR the contract valueof the portion of the work so lost or damaged or any balance of such contract value remaining unpaid as the case may be.

Until the work shall be deemed to be taken over as aforesaid, theCONTRACTOR shall also be liable for and shall indemnify thePURCHASER in respect of all damage or injury to any person or toany property of the PURCHASER or of others occasioned by Act of the CONTRACTOR or his workmen or his sub-contractors or by

Page 56: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 56/101

SECTION - C40

defective design, work or material but not due to cause beyond hisreasonable control. Provided that the CONTRACTOR shall not beeligible under the contract for any loss of profit or loss of contractsor any claims made against the PURCHASER not already providedfor in the contract, nor for any damage or injury caused by or arising from acts of the PURCHASER or of others (save as to

damage by fire, as hereinafter provided) due to the circumstancesover which the CONTRACTOR has no control nor shall his totalliability for loss, damage or injury exceed the total value of thecontract.

25.0 POWER FOR ENGINEER TO DECIDE ORDER OF WORKS

The CONTRACTOR shall commence execution at such parts of the site and in such order, as the ENGINEER shall decide inwriting. The Engineer may from time to time by direction in writingwithout in any way vitiating this contract, alter the order of theworks of any part thereof at such time, or times as the ENGINEER

may deem desirable and the CONTRACTOR shall after receivingsuch direction proceed in the order as directed.

26.0 CONTRACTOR TO INFORM ENGINEER FOR ARRANGEMENTSFOR EXECUTION OF WORK

The CONTRACTOR shall from time to time, as and when requiredby the ENGINEER, furnish the Engineer with a statement in writingof the arrangements he proposes to adopt for the execution of thiscontract, and in case the ENGINEER shall at any time or timesconsider any alteration as desirable, the CONTRACTOR shall onnotice thereof adopt such alteration. A detailed programme on theproject for execution of the different items of work shall beprepared by the CONTRACTOR immediately after commencingthe work. These when accepted by the PURCHASER, shall bekept up till the completion.

27.0 SUNDAY WORKNo work of any description shall be carried out on Sundays andother important National Holidays without the knowledge andformal sanction in writing from the ENGINEER.

28.0 SUSPENSION OF WORK

The ENGINEER may from time to time by direction in writing for any valid reason, without in any way vitiating this contract, directthe CONTRACTOR to suspend the work or any part thereof atsuch time or times and for so long as the ENGINEER may deemdesirable, and the CONTRACTOR shall not, after receiving suchwritten notice proceed with the works therein ordered to besuspended until he shall have received written notice or authority tothe effect from the ENGINEER. The CONTRACTOR shall not beentitled to claim from the PURCHASER compensation for any loss

Page 57: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 57/101

SECTION - C41

or damage sustained by him by reason of the suspension of worksas aforesaid.

No compensation shall be payable for idle labour, staff andmachinery (hired or otherwise) due to occasional power failure or any causes beyond the control of the PURCHASER and for pre-

arranged shutdowns in electricity supply for which prior notice maybe given.

29.0 INSPECTION OF WORKS29.1 The ENGINEER or his duly authorised agent shall have at all times

full power to inspect the work wherever in progress either on site or the CONTRACTOR'S premises or at the premises wherever situated or any firm or company where work in connection with thiscontract may be in hand. All records, registers or documentsrelating to the works including materials used on works shall bekept open to the inspection of the PURCHASER or his authorisedrepresentative when so called for in writing.

29.2 All requisite scaffolding, shoring, timbering and pathways shallhave perfect supports. Care must be taken to ensure the safety of work people and the CONTRACTOR shall comply with suchinstructions as the ENGINEER may issue to ensure such safety.THE CONTRACTOR will be responsible for any damage or injuriesto persons and properties resulting from ill erected scaffolding,defective pathways and ladders or during under water explorationand erection or otherwise arising out of his default in this respect.

29.3 OPENING OUT OF DEFECTIVE WORKSShould the ENGINEER consider it necessary in order to satisfyhimself as to the quality of the work, the CONTRACTOR shall atany time during the continuance of the contract pull down or cutinto any part of the work and made such openings into and to suchan extent through the same, as the ENGINEER may direct and theCONTRACTOR shall make good the whole, to the satisfaction of the ENGINEER, should the work prove to be faulty or in anyrespect not in accordance with the terms of the contractdocuments, the ENGINEER shall be at liberty to order suchfurther removal as he may consider necessary and the wholeof the expenses incurred shall be defrayed by the contractor. If however, the work proves to be sound and in accordance with the

contract documents, the actual expenses incurred in suchexamination will be borne by the PURCHASER.

29.4 REMOVAL OF IMPERFECT WORKIf, it shall appear that work has been executed with unsound,imperfect or unskilled workmanship, or with materials of anyimperfect or any inferior quality or otherwise not in accordance withthe contract documents, the CONTRACTOR shall at his own costrectify, reform, remove or reconstruct the same, either in the

Page 58: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 58/101

SECTION - C42

whole or in part, as may be directed by the ENGINEER, whether or not the value of any such work or materials shall have beenincluded in any payment made to the CONTRACTOR.

30.0 PATENT RIGHTS

In the event of any claim or demand, being made or action beingbrought against the PURCHASER for infringement or allegedinfringement of letters, patent, in respect of any machine, plantwork, materials or things used or supplied by the CONTRACTORunder this contract in respect of any method of using or working bythe PURCHASER of such machine, plant, work, materials or thing,the CONTRACTOR will indemnify the PURCHASER against allcosts and expenses arising from or incurred by reason of any suchclaim provided that the PURCHASER shall notify theCONTRACTOR immediately any claim is made and that theCONTRACTOR shall be at liberty if he so desires with theassistance of the PURCHASER, if required but at the

CONTRACTOR's expense, to conduct all negotiations for thesettlement of the same or any litigation that may arise there fromand providing that no such machine, plant, work materials or thing shall be used by the PURCHASER for any purpose or inany manner other than that for which they have been supplied bythe CONTRACTOR and SPECIFIED under this contract.

31.0 ACCESS TO SITE AND WORK ON SITEThe PURCHASER may, if he shall think fit from time to time, enter upon any lands which may be in the possession of theCONTRACTOR under this contract, for the purpose of executingany works not included in this contract and may execute suchworks respectively by himself or his agents, or by other CONTRACTOR, shall in accordance with the requirements of theENGINEER offer all reasonable facilities for execution of the worksincluding occupation of lands by structure or otherwise for anyother CONTRACTORs employed by the PURCHASER and hisworkmen or for the workmen of the PURCHASER, who may beemployed in the execution on or near the site of the work notincluded in the contract or of any contract in connection with or ancillary to the work and in default the CONTRACTOR shall beliable to the PURCHASER, for any delay or expense incurred byreason of such default, provided always that if the exercise of 

these powers shall cause any damage to the CONTRACTOR hemay and when such damage arises make a statement of the sameto the ENGINEER who shall from time to time certify to thePURCHASER shall from time to time pay to the CONTRACTORthe amounts (if any) so certified by the ENGINEER. TheCONTRACTOR shall not, however, on account of any suchmodified new or extra work executed by or for the sake of thePURCHASER, be entitled to claim relief from the obligation toexecute other works.

Page 59: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 59/101

SECTION - C43

32.0 MATERIALS BROUGHT TO THE SITE OF WORKS All materials, tools and tackles brought to and delivered upon thesite for the purpose of the work shall from the time of their being sobrought vest in and be the property of PURCHASER but may beused for the purpose of the work but for the purpose only and shall

not on any account be removed or taken away by theCONTRACTOR or any other person without the prior permission inWriting of the ENGINEER but the CONTRACTOR shallnevertheless be solely liable and responsible for any loss or destruction thereof or damage thereto unless resulting from causesbeyond the CONTRACTOR's control.

The PURCHASER shall have a lien on such materials, tools andtackles for any sum or/sums which may at any time prior to thecompletion of the works be due or owing to him by theCONTRACTOR under in respect of or by reason of the contractand PURCHASER shall be at liberty to sell and dispose off any

such materials, tools and tackles and in such manner as he sothinks fit and to apply the proceeds in or towards the satisfaction of such sum or sums so due or owing as aforesaid.

33.0 CONTRACTOR TO KEEP INVENTORY OF PLANT, ETCThe CONTRACTOR shall prepare and maintain an inventory of allmaterials, temporary rolling stock, plant purchased or hired for employment or for any of the purposes of this Contract and suchinventory or a copy thereof shall at all times be available for inspection by the ENGINEER, on the completion of the contract, allsuch materials, rolling stock and plant as shall have been hiredshall be removed forthwith by the CONTRACTOR and returned tothe parties from whom the same have been hired.

34.0 TOOLS AND PLANTS FOR THE EXECUTION OF THECONTRACT

 All tools and plants, equipment and tackle required for the completeexecution of the contract shall be arranged for by theCONTRACTOR only at his own cost. The CONTRACTOR, mayhowever, specify in his tender the terms under which or concessions, if any, that would require for procuring and using thetools and plant and equipment on the work except those that are tobe supplied on hire or free of charge.

35.0 MAINTENANCE35.1 For a period from the date of issue of completion certificate till the

expiry of 1 year commencing from the date of issue of thecompletion certificate the CONTRACTOR shall be liable for thereplacement of any part of the works found to be defective fromcauses arising from faulty design, materials, or workmanship andfor making good any damage arising therefrom.

Page 60: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 60/101

SECTION - C44

35.2 Issue of the `Final Certificate’ and the payment thereby of thebalance of the contract sum as provided in clause 22 above under `Terms of payment’ before the expiry of the maintenance periodshall in no way absolve the CONTRACTOR from his obligationsunder the contract in respect of the un-expired portion of the periodand to this extent the Bank Guarantee entered into for the due

performance of this contract shall remain in full force and effectuntil the end of the maintenance period.

36.0 COMPLETION CERTIFICATE As and when the whole of the work shall have been completed tothe satisfaction of the ENGINEER and in accordance with thiscontract, he shall give to the CONTRACTOR the `CompletionCertificate' and thereupon the PURCHASER shall take over thework. Provided always that the ENGINEERS shall in his discretionbe at liberty from time to time certify, that a part of the work hasbeen completed to his satisfaction and in accordance with thiscontract and there upon the PURCHASER shall take over that part

of the works included in such certificates.

37.0 FINAL CERTIFICATEThe contract shall not be considered as completed until acertificate (herein referred to as the final certificate) shall havebeen signed by the ENGINEER to the effect that theCONTRACTOR has carried out all his obligations under `MAINTENANCE' and in the manner provided by this contractnotwithstanding any previous entry upon the works or takingpossession, working or using any part thereof by thePURCHASER, but the issue of the final certificate as aforesaidshall be without prejudice to the rights, duties, obligations

of the parties, during any part of the maintenance period whichhas not expired at the time of the issue of the final certificate.

38.0  CERTIFICATE TO BE PROVISIONAL AND SUBJECT TOCORRECTIONEvery certificate for payment on account of work, materials or things shall be regarded as only provisional and approximate andall payments made on such certificates shall be regarded as beingopen payments and shall respectively be subject to revision andsettlement by the ENGINEER and in the event of his deciding thatfrom any circumstances the measurements of work executed,

returns of materials provided and used for the estimates of valuepreviously made, did not truly represent the portion of worksexecuted and materials provided and used having reference tothe amount of the contract sum and the work remaining to beexecuted by the CONTRACTOR, the ENGINEER shall havepower from time to time to correct the total results by addingthereto or deducting therefrom such sum as, after communication with the CONTRACTOR or his duly authorisedagent, the ENGINEER may deem to be just and such addition or 

Page 61: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 61/101

SECTION - C45

deduction shall be credited to or (as the case may be) debitedagainst the CONTRACTOR at such time as the ENGINEER maythink fit.

39.0 NEGLIGENCEIf the CONTRACTOR shall neglect to execute the work with due

diligence and expedition, or shall refuse or neglect to comply withany reasonable orders given to him in writing by the ENGINEER inconnection with the work, or shall contravene the provision of thiscontract, the PURCHASER may give seven days notice in writing,to the CONTRACTOR to make good the failure, neglect or contravention complained of any should the CONTRACTOR fail tocomply with the notice within the reasonable time from date of service thereof in the case of failure, neglect or contraventioncapable of being made good within that time or otherwise withinsuch time as may be reasonably necessary for making it good,then and in such case, the PURCHASER shall be at liberty toemploy other workmen and forthwith perform such work as the

CONTRACTOR may have neglected to do, or if the PURCHASERshall think fit, it shall be lawful for him to take the work, wholly or in part off the CONTRACTOR's hands and re-contract at areasonable price with any other person or persons or provide anyother materials, tools and tackles or labour for the purpose of completing the work or any part thereof and in that event thePURCHASER shall, without being responsible to theCONTRACTOR for the fair wear and tear of the same, have thefree use of all the materials, tools, tackles, construction plant, or other things which may be on the site for use at any time inconnection with the work to the exclusion of any right of theCONTRACTOR over the same and the PURCHASER shall beentitled to retain and apply and balance which may be otherwiseuse to the contract by him to the CONTRACTOR or such partthereof as may be necessary to the payment of the cost of executing such work as aforesaid.

If the cost of executing the work as aforesaid shall exceed thebalance due to the CONTRACTOR and the CONTRACTOR fails tomake good the deficit, the said materials, tools, tackles,construction plant, or other things which are the property of theCONTRACTOR may be seized and sold by the PURCHASER andthe proceeds applied towards the payment of such differences and

the cost of and incidental to such sale. Any outstanding balanceexisting after crediting the proceeds of such sale, shall be paid bythe CONTRACTOR on the certificate of the ENGINEER, but whenall expenses, costs, and charges incurred in the completion of thework are paid by the CONTRACTOR, all such materials, toolstackle, construction plant of other things remaining unsold beremoved by the CONTRACTOR. The actual difference in pricewhere ever the PURCHASER gets executed through other 

Page 62: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 62/101

SECTION - C46

agencies at a higher rate is payable by the contractor toPURCHASER.

40.0 DEATH, BANKRUPTCY ETCIf the CONTRACTOR, shall die or commit any act of bankruptcy or being a Corporation commence to be wound for reconstruction

purposes or carry on its business under a receiver, the executors,successors or other representatives in law of the Estate of theCONTRACTOR or any such receiver, liquidator or any person inwhom the contract may become vested, shall forthwith give noticethereof in writing to the PURCHASER and shall for one month,during which he shall take all reasonable steps to prevent astoppage of the works, have the option of carrying out thiscontract subject to his or their providing such guarantee as maybe required by the PURCHASER but not exceeding the value of the work for the time being remaining un-executed. In the event of stoppage of the works, the period of the option under this clauseshall be fourteen days only. Provided that, should the above option

be not exercised, the contract may be determined by thePURCHASER by notice in writing to the CONTRACTOR, and thesame power and provisions reserved to the PURCHASER in theproceeding clause on the taking of the work out of theCONTRACTOR’s hands shall immediately become operative.

41.0 MEASURING, VALUING AND CERTIFYING BY ENGINEERIn measuring, valuing, deciding or certifying, the ENGINEER isintended to act by his skill and from his knowledge of the facts andincidents connected with the works and in so far as any facts arenot within his own knowledge, the ENGINEER shall be at liberty toascertain for himself by enquiry of such person or persons as hemay consider necessary. The ENGINEER shall at all times beconsidered seized of all the facts necessary for him to form his ownopinion, make his measurements or valuations give his decisionand order, make his requisition, or give or refuse his certificate andhe shall be at the liberty to certify at such time and in such manner as in his discretion he may think proper and he shall not be boundto give any reason for or any particulars of his certificate or anyreasons for his not certifying.

42.0 ARBITRATION Arbitration shall not be applicable for this contract.

43.0 CLEANING UPUpon completion of the work, the CONTRACTOR SHALL removefrom the vicinity of the work all plant, buildings, rubbish, unusedmaterials, concrete forms and other materials, belonging to him or used under his discretion, during construction and in the event of his failure to do so, the same will be removed by thePURCHASER, and the relevant expenditure recovered from theCONTRACTOR.

Page 63: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 63/101

SECTION - C47

44.0 JURISDICTIONNo suit or any proceedings in regard to any matter arising in anyaspect under this contract shall be instituted in any court save inthe City Court at Chennai or the Court of Small Causes at Chennai.It is agreed to that no other Court shall have jurisdiction to entertain

any suit proceedings, even though part of the cause of action mightarise within their jurisdiction. In case of any part of the cause of action arises within the jurisdiction of any Court of Tamil NaduState and not in the Courts of Chennai city then it is agreed tobetween the parties that such suits or proceedings shall beinstituted in Court within the State of Tamil Nadu and no other courtoutside the State of Tamil Nadu shall have jurisdiction even thoughany part of the cause of the action might arise within the jurisdictionof such Courts. The Contractor shall furnish an undertaking to thiseffect in non-judicial stamp paper for Rs. 80/- as per the formatenclosed in annexure - VIII of Section ‘F’

45.0 SUBMISSION OF PERT CHARTWithin ten days from the date of handing over of site theCONTRACTOR/ SUPPLIER should furnish to the ENGINEER aPERT Chart which, in addition to indicating the overall completion+time of the contract, should also indicate the time for completionof each individual activity of the contract. The CONTRACTORshould also mention in his schedule the required dates for anysignificant point of communication or transfer of responsibilitybetween the CONTRACTOR and other participants in the projecti.e., the required date for supply of design and loading data withreference to plant and equipment from the manufacturers, theassistance required from the PURCHASER with reference topurchase/hire of construction equipment, date of supply of designand drawings, approval to the contractor's drawings etc. Failureto furnish PERT chart in time will attract penalty as stipulated in 3.2(j) of Section A of specification. The CONTRACTOR shall alsofurnish on the first of every month status review report on his worktogether with the above PERT network updated to the ENGINEER.Whenever there is any likelihood of a change in his constructionschedule, the CONTRACTOR should inform the same to theENGINEER forthwith.

46.0 QUALITY OF MATERIALS

For quality of materials and general workmanship, the Tamil NaduBuilding Practice or the relevant ISS will apply. If there is anydiscrepancy between the Tamil Nadu Building Practice and the I.S.Codes, the latter shall govern.

47.0 WASTE MATERIALS All waste materials as decided by the site ENGINEER should be letout of the compound at CONTRACTOR’s cost and the

Page 64: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 64/101

SECTION - C48

CONTRACTOR should keep the site always clean during progressof work.

48.0 RECOVERY OF MONEY FROM CONTRACTORIn every case in which provision is made for recovery of moneyfrom the CONTRACTOR, PURCHASER shall be entitled to retain

or deduct the amount thereof from any money that may be due or become due to the CONTRACTOR under these presents and/or under other contract or contracts or any other account whatsoever.

49.0 WEEKLY PROGRESS REPORTSThe CONTRACTOR shall furnish to the PURCHASER weeklyprogress report in triplicate on Saturday of every week indicatingthe following:

Item of work

Schedule of progress for the week

 Actualprogress

Reasons for shortfall if any.

Steps taken tomeet theshortfall.

(SIGNATURE OF THE CONTRACTOR)

50.0 GOLD, SILVER, MINERALS, OIL, RELICS ETC. FOUND ON THESITEAll gold, silver, oil or other minerals of any description and allprecious stones, coins, treasures, relics, antiques and other similar things which shall be found in or upon the site shall be the property

of the PURCHASER and the CONTRACTOR shall duly preservethe same to the satisfaction of the ENGINEER and shall from timeto time deliver the same to such person or persons as theENGINEER may from time to time appoint to receive the same.

51.0 INTEREST ON MONEY DUE TO THE CONTRACTORThe amount due to the contract shall not attract any interest.

52.0 DEVIATION, ALTERATIONS ETC. IN THE MATERIALSThe CONTRACTOR shall not in any way alter any of the materialsto be used on the works without the previous consent of theENGINEER but the ENGINEER may from time to time and at anytime direct in writing any deviations, alterations, additions or omissions to be made from in or to the materials or any part thereof shall not vitiate this contract and any deviation so directed to bemade shall be made to the satisfaction of the ENGINEER in thesame manner as if such materials have been originally included inor omitted from the specification and schedule of prices, exceptthat the value of the same whether by way of addition or deduction shall be estimated by the ENGINEER according to the

Page 65: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 65/101

SECTION - C49

schedule of prices and the amount so intimated shall be added toor deducted from the contract sum, as the case may be.

53.0 DEVIATIONS, ALTERATIONS AND ADDITIONS TO THEWORKSThe CONTRACTOR shall not in any way alter any of the works

without the previous written consent of the ENGINEER but theENGINEER may from time to time and at any time during theprogress of the works, in writing under his hand direct anydeviations, alterations or additions to be made from, in or to theworks or any part thereof or may direct the CONTRACTOR tocurtail or to omit any of the works to execute any new or substituted work or to commence and execute the works or anypart thereof, in such order and manner as shall any deviations,alterations, additions and admissions made in pursuance thereof shall not vitiate this contract or be made the ground for any claimfor compensation for alleged loss or profit in respect of omittedworks or (except as hereinafter provided) for extra payment for 

additional works and any works so directed to be executed shallbe executed and any work so directed to be omitted shall be andany deviations so directed to be made shall be made to thesatisfaction of the ENGINEER in the same manner (as nearly ascircumstances shall admit) and if such works had been originallyincluded in or omitted from the specification except that the valueof the same whether by any of addition or deduction shall beestimated by the ENGINEER according to the schedule of pricesand amount so estimated shall be added to or deducted from thecontract sum as the case may be. The CONTRACTOR shall not,however, on account of any such modified new or extra worksexecuted by or for the PURCHASER be entitled to claim relief fromthe obligations to execute other works.

54.0 CLAIMS FOR EXTRA WORK OR FOR DEDUCTIONSThe PURCHASER shall not be responsible for the payment of anyclaim for extras not included in nor shall be entitled to claim anydeduction from the contract sum in respect of any charges or alterations in the materials employed unless the same shall havebeen ordered or sanctioned as the case may be in writing by theENGINEER. And in the event of any dispute arising either as to thevalidity of the claim or as to the amount to be paid or allowed inrespect thereof, the decision of ENGINEER shall be final and

binding on all parties, and in the meantime, the CONTRACTORshall either proceed with the work in question or suspend thesame, as may be determined by the ENGINEER and no paymentsdue or payable by the PURCHASER or his agent as the case maybe, shall be withheld on account of such dispute.

55.0 MEASUREMENT OF EXTRA WORKS All extra works of every description which shall be executed inpursuance of any of the provision of this contract shall be

Page 66: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 66/101

SECTION - C50

measured up and shall be paid according to actual quantitiesascertained by such measurements and the prices inserted in theschedule of prices so that such prices shall include all suchoperations and accessories as appear in the said schedule of prices or specification to be or shall in the opinion of theENGINEER the contingencies upon the works mentioned in such

schedule of prices or be required to make such works perfect andfit for use. Provided also that if any work shall be ordered by theENGINEER and executed by the CONTRACTOR for the paymentof which no provision shall in the opinion of the ENGINEER bemade in the schedule of prices or the specification, the ENGINEERshall fix and determine such prices for the same as may in his judgement appear to accord generally with the prices in theschedule of prices, such allowance being made as may seem tothe ENGINEER sufficient for any difference in the character or conditions of the work.

56.0 RATES FOR SUPPLEMENTAL ITEMS

In the case of authorised supplemental items of works if anyexecuted by the contractor, the rate will be decided generally asper the guidelines contained in G.O.Ms.No..1241 dated.13.10.78which are outlined below:

(i) The derivation of a suitable rate for supplemental item if technicallyfeasible will be done from the relevant accepted rate in thecontract.

(ii) If such derivation is not technically feasible, a rate based on theschedule of rates relevant to the tender date will be worked out andthe tender premium plus or minus as the case may be, if any shallbe added to this rate and this rate shall be offered for acceptanceby the Contractor.

iii) If during the period of execution of this supplemental item of work,the schedule of rates have changed, then a rate based on theschedule of rates prevailing at the time of execution of thesupplemental item of work shall be worked out and offered for acceptance and in such a case no tender premium shall be addedto this rate.

57.0 WORK EXECUTED BY DAY LABOUR Any extra work such as complicated, miscellaneous or disjointedcharacter that it cannot be valued by measurement, may beexecuted by day labour or a specific lumpsum may be agreed for 

any special piece of work to be carried out. Before any work is puton hand under day work, rates and order in writing must beobtained by the CONTRACTOR from the ENGINEER and aschedule of day work rates agreed upon.

The CONTRACTOR shall deliver to the ENGINEER’s office,weekly, full detailed account (in triplicate) of all labour andmaterials employed or used respectively on any portion of the workfor which an order has been issued that, it must be carried out at

Page 67: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 67/101

SECTION - C51

day work rates. This return shall cover the work done during theprevious `CONTRACTOR's week. One of the accounts, if foundcorrect will be certified by the ENGINEER and returned to theCONTRACTOR and must be produced by him, if required, beforepayment can be made. The CONTRACTOR shall afford everyfacility for checking by the ENGINEER on the ground, all times and

materials so charged for.

58.0 APPLICATION FOR RETENTION SUMThe retention sum and any other portion of the contract sum for thetime being unpaid or any part or parts thereof respectively may beapplied by the PURCHASER at his discretion in all or any of thefollowing ways (and either during the construction of the work or attime before the issue of final certificates hereinafter referred to) thatis to say, in or towards making good any defect or unsoundnesswhich shall be certified by the ENGINEER, to existing works or anypart thereof or in the materials used in the formation andconstruction thereof and provided by the CONTRACTOR or which

being provided, by the PURCHASER shall while in the custody of the CONTRACTOR, be damaged or tendered imperfect of in or towards the satisfaction of any damages or other money payableby the CONTRACTOR to the PURCHASER under this contract.Provided that nothing contained on this clause shall prejudice anyof the other rights or remedies of the PURCHASER or his agents inrespect of any breach of this contract.

59.0 BREACH ON PART OF PURCHASER NOT TO ANNULCONTRACTNo breach or non-observance on the part of the PURCHASER of any of the agreements herein contained shall annul this contract or discharge the CONTRACTOR from the observance andperformance thereof or of any part thereof but compensation of damage (if any) shall be made to the CONTRACTOR or at theoption of the ENGINEER an extension of the time given to theCONTRACTOR in respect of such breach or non-observance bythe PURCHASER, such compensation or extension of time to befixed by the ENGINEER.

60.0 REGULATIONS OF LOCAL AUTHORITIESThe PURCHASER shall throughout the continuance of the contractand in respect of all matters arising in the performances thereof;

serve all notices and obtain consents, way-leaves, approvals andpermissions required in connection with the regulations and bye-laws of the local or other authority which shall be applicable to theworks.

61.0 NOTICES: HOW TO BE GIVENWhere any legal or other notice or any other documents is to begiven to or served to the CONTRACTOR it shall be deemed to beduly given or served, if it shall have been either delivered to him

Page 68: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 68/101

SECTION - C52

personally or to his recognised agent (including in the case of thecompany the Secretary of such company) or delivered at or sentthrough the post addressed to the CONTRACTOR at theCONTRACTOR's office in the site or sent through the postaddressed to the last known place of business or abode of theCONTRACTOR or in the case of a Company to its Registered

Office and in the case of a firm of CONTRACTOR notice or other documents, which shall be so given to or so served on any one of the partners in such firm, shall be deemed to have been given toor served on all of them.

62.0 CONSTRUCTION OF CONTRACTThe Contract shall in all respect be constructed and operated as acontract as defined in the Indian Contract Act, 1872, and allpayments made there under shall be made in rupee unlessotherwise specified.

63.0 CONTRACTOR'S REPRESENTATIVES AND WORKMENThe CONTRACTOR shall employ atleast one competentrepresentative, whose name or names shall have previously beencommunicated in writing to the ENGINEER by the CONTRACTORto carry out and supervise the works. The said representative or if more than one shall be employed, then one of suchrepresentatives, shall be present on the site during working hours,and any written order or instructions which the ENGINEER or hisduly authorised representative whose name have been previouslycommunicated in writing to the CONTRACTOR may give to thesaid representative of the CONTRACTOR, shall be deemed tohave been given to the CONTRACTOR.

The CONTRACTOR shall at all times employ as much labour of every description as required for the proper progress of the work asplanned and shall on demand furnish from time to time, suchreturns as may be required by the ENGINEER of the number anddescription of skilled and unskilled labourers and supervisory staff employed upon the work.

  The quantum of such labour force/workmen deployed by theCONTRACTOR in the interest of progress of work will not attractany claim/ compensation by way of wages or any other form etc.

from the PURCHASER.

64.0 RIGHT OF ENGINEER TO ORDER WITHDRAWAL OF LABOURThe ENGINEER shall be at liberty to object to any representativeor other persons or labourers employed by the CONTRACTOR inthe execution or otherwise about the works, who shall misconducthimself or be incompetent or negligent and the CONTRACTORshall remove the person so objected to upon the receipt from theENGINEER of notice in writing requiring him to do so, and shall

Page 69: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 69/101

SECTION - C53

provide in place, a competent substitute at the CONTRACTOR'sexpenses.

65.0 WORKS MATERIALS, WORKS AND WORKMANSHIPTO BE EXECUTED TO THE SATISFACTION OF THEENGINEER

a) The CONTRACTOR shall proceed with the works with diligenceand expedition and the whole of the works therein specified, aswell as the mode of execution, shall be under the supervision anddirection and shall be carried on to the entire satisfaction of theENGINEER, who shall have full power to order the CONTRACTORto alter, enlarge or diminish the forms, dimensions, position, or quantities of any works, or to make use of materials andworkmanship of different descriptions and qualities from thoseherein specified and works should be properly carried out to thesatisfaction of the ENGINEER.

b) The whole of the works, together with any temporary works

associated therewith, shall be carried out in the most substantial,proper and workman like manner with the best materials andworkmanship and to the entire satisfaction of the ENGINEER andin such order of time as he may direct, the CONTRACTOR shallattend to and execute without delay, all orders and instructionswhich may from time to time be issued by the ENGINEER. Whenthe works or their appurtenance foul with the arrangements of other units of works not covered by this specification, working methodsshall be discussed with the ENGINEER and his prior concurrenceobtained.

c) The work shall be executed in a thoroughly substantial manner withmaterials and workmanship of the best quality and strictly inaccordance with the specification, and with the drawings or withsuch other drawings or written instructions as may from time totime be furnished to the CONTRACTOR in accordance with theterms of this contract, and shall be completed in every respect withall materials and workmanship implied and necessary according tothe fair interpretation and meaning of the same, and should therebe any discrepancy between the drawings and specifications or any difference or dispute as to the dimensions to be worked toor the quality of the materials to be used or the mode of doing or periodical quantity of the work to be executed or with respect to

any subject arising out of this contract, the decision of theENGINEER shall be final and binding on all parties.

66.0 EXECUTION OF WORKS IN CONFORMITY WITH THECONTRACT DOCUMENTSThe whole of the works shall be executed in perfect conformity withthe contract documents, and such explanatory and detail drawingsand directions as may be furnished from time to time by theENGINEER for the guidance of the CONTRACTOR.

Page 70: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 70/101

SECTION - C54

67.0 CONTRACT INCLUDES ALL NECESSARY OPERATIONThe contract is to include the whole of the works whether permanent or temporary which are described in, or implied by thecontract documents or which may be inferred to be obviouslynecessary for the efficiency, stability and completion of the

permanent works and also the performance of all other operationsand the supplying of all the materials which may be deemeddesirable or required for the completion in all respects of theabove works to the entire satisfaction of the ENGINEER, and allsuch matters shall be deemed as included in the contract sum.Work shown upon in the drawings and not mentioned in thespecification or described in the specification without being shownon the drawings shall nevertheless be held to be included in thiscontract and their execution have been especially shown upon inthe drawings and described in the Specification also.

LOCATION OF CONTRACTOR’S PLANTS

The whole work including location of construction plant, disposal of excavated materials etc. shall be carried out so as not to cause anyhindrance to or interference with other works in or near the localityof the work covered by the contract.

68.0 CONTRACTOR TO SUPPLY AND BE RESPONSIBLE FOR THESUFFICIENCY OF THE MEANS EMPLOYEDCONTRACTOR must supply and take upon himself the entireresponsibility of the sufficiency of the scaffolding, timbering,machinery, tools and implements and generally of all the meansused for the fulfilment of this contract, whether such means may or may not be approved, offered or recommended by the ENGINEERand the CONTRACTOR must accept all risks of accident or damages from whatever cause they may arise, until the completionof this contract.

69.0 FENCING AND LIGHTINGExcept as hereinafter provided, the CONTRACTOR shall unlessotherwise specified be responsible for the proper fencing, guarding,lighting around the works area to avoid accidents. Similarly proper watching arrangement shall be made by the CONTRACTOR duringexcavation, water diversion and during flooding to avoid loss of property and life. Necessary temporary roadways, footways and

guards for the above shall be provided by the CONTRACTOR.

70.0 DISCREPANCIES BETWEEN DRAWING AND SPECIFICATIONShould there be any discrepancy between the specification and/or schedule of prices and/or drawings or any inconsistency, error or omission in either of them, reference must be made to theENGINEER for an explanation and the CONTRACTOR will be heldresponsible for any errors that may occur in the work through

Page 71: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 71/101

SECTION - C55

neglect of this precaution. The explanation of the ENGINEER shallbe final and binding on the CONTRACTOR.

71.0 QUANTITIES, PRICES AND PAYMENT71.1 The quantities against various items of work furnished in the

Schedule of quantities under Section - E are approximate and are

likely to vary. They are meant only for the purpose of having acommon base of comparison of various tenders and total prices.The payment shall be made in accordance with the net quantitiesmeasured as described in the relevant clauses at the rates statedin the schedule of prices, whether such actual quantities be greater or less than the quantities given in the schedule of prices. If anymaterials/ works are necessarily required to be executed over and above the schedule of quantities, the Contractor has toexecute the work at accepted rates.

71.2 Prices quoted by the CONTRACTOR shall include the cost of loading, unloading, handling charges, storage and other alliedcosts/charges involved.

72.0 DOCUMENTS CONFIDENTIALThe TENDERER (whether his tender is considered or not) shalltreat the details of the tender specification and other documentsattached thereto as private and confidential.

73.0 TENDER DOCUMENTS NOT RETURNABLEThe tender documents and the relevant connected documents,pamphlets, sketches, designs etc. submitted by the TENDERER(Whether his tender is considered or not) shall become theproperty of the PURCHASER and are not returnable.

74.0 FILLING UP OF TENDER PROFORMAThe TENDERER should fill up all the proforma given in section - Fof the specification document.

75.0 ILLUMINATION Adequate illumination using electric or acetylene lamps is to beprovided by the CONTRACTOR at his cost. Where any works iscarried out at night, the site of such works is to be illuminatedadequately by flood lights. At the drilling faces at the heading, thevoltage of lamps, if of AC current is to be reduced to 55 volts, andsuitable transformers have to be installed at the CONTRACTOR’s

expenses. For electric current for work sites, workshops,CONTRACTOR’s offices and stores the Contractor has to put in hisown distribution system at his own cost from the points of take off from the nearest mains provided by the PURCHASER.

The electric supply to the residence of the CONTRACTOR’s staff,the wiring and other electric installation within the CONTRACTOR’sstaff residences should be provided at the CONTRACTOR’sexpense. The contractor shall construct and maintain at his own

Page 72: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 72/101

SECTION - C56

business the necessary circuit for distributing the power in order toprovide voltage regulations.

76.0 COMMUNICATION FACILITIESThe CONTRACTOR shall install, maintain and operate such other communication and signal facilities as are necessary for the safe

and efficient execution of the work. All such communication andsignal facilities shall be subject to the approval of the ENGINEER. Authorised employees of the PURCHASER shall have free use of such facilities installed by the CONTRACTOR for the transmissionof official messages.

77.0 HEALTH AND SANITARY RULES FOR WORKERSThe CONTRACTOR’s special attention is invited to 'Model Rulesfor the provision of Health and Sanitary arrangements for workersemployed' of the General Conditions of Tamil Nadu BuildingPractice and he is required to provide at his own expenses thefollowing amenities to the satisfaction of the ENGINEER at site.

77.1 FIRST AIDAt the work site there shall be maintained in a readily accessibleplace, first aid appliances and medicines including adequate supplyof sterilised dressing and sterilised cotton wool. The applianceshould be kept in good order. They shall be placed under thecharge of a responsible person who shall be readily availableduring working hours.

77.2 DRINKING WATER(a) Water of good quality fit for drinking purposes shall be provided for 

the workers .

(b) Where drinking water is obtained from an intermittent public water supply, each work site shall be provided with a storage tank wheredrinking water shall be stored.

(c) Every water supply storage shall be a distance of not less than15 metres from any latrine, drain or other source of pollutions,where water has to be drawn from an existing well which is withinsuch proximity of any latrine, drain or other source of pollution, thewell shall be properly chlorinated before water is drawn from it for drinking. All such wells shall be entirely closed in and be provided

with a trap door which shall be dust and water proof.

(d) A reliable pump shall be fitted to each well, the trap door shall bekept locked and opened only for inspection or cleaning which shallbe done atleast once a month.

77.3 WASHING AND BATHING PLACESAdequate washing and bathing places shall be provided separatelyfor men and women. Such places shall be kept clean and well

Page 73: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 73/101

SECTION - C57

drained. Bathing or washing should not be allowed in or near anydrinking water well.

77.4 LATRINES AND URINALSThese shall be provided within the premises of every work site inan accessible place and the accommodation, separately for each

of them shall be on the following scale or on the scale so directedby the ENGINEER, in any particular case.

Seats1. Where the number of persons employed

does not exceed 50. 22. Where the number of persons employed

are 50 and above but does not exceed 100. 33. For every additional 100 3

If women are employed separate latrine and urinals screened fromthose for men, shall be provided on the same scale.

Except in work sites provided with water flushing latrinesconnected with water borne sewage system, all latrines shall becleaned atleast four times, daily and atleast twice during workinghours and kept in a strictly sanitary conditions. The receptaclesshall be tarred inside and outside atleast once a year.

The excreta from the latrines shall be disposed off at theCONTRACTOR's expenses, in outway pits approved by the localpublic health authority. The CONTRACTOR shall also employadequate number of scavengers and conservancy staff to keep thelatrines and urinals in a clean condition.

77.5 SHELTERS DURING RESTTwo shelters shall be provided free of cost one for men and theother for women workers.

77.6 CRECHESAt every work site at which 50 or more women are ordinarilyemployed, there shall be provided two huts of suitable size for theuse of children under the age of 6 years belonging to such women.One hut shall be used for infants, games, and play, and the other as their bed room. The huts shall not be constructed on a standard

lower than the following.  a) Thatched roofs.b) Mud floors and walls.

  c) Planks spread over the mud floor and covered with matting. Theuse of the huts shall be restricted to children, their attendants andmothers of the children.

Page 74: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 74/101

SECTION - C58

77.7 CANTEEN A cooked food canteen on a moderate scale shall be provided for the benefit of workers if it is considered necessary.

78.0 SHED FOR WORKERSThe CONTRACTOR should provide at his own expense sheds for 

housing the workers. The sheds shall be of standard not less thanthe cheap shelter type to live in which the workers in a locality areaccustomed. The sheds are to be in rows with 1.52m clear spacebetween sheds and 6 metres clear space between rows, if conditions permit. The workers camp shall be laid out in units of 400 persons, and each unit shall have clear space of 12.2m oneach side.NOTE : In case alternative facilities exist in regard to the amenitiesin rule 1 of the above relevant rules, the corresponding itemsshould be scored out with due attestation at the time of taking theagreement.

79.0 PROVISIONAL LAWSIn any case where the contract price includes a provisional sum tobe provided by the CONTRACTOR for meeting the expenses of extra work to be done or materials to be supplied by a subCONTRACTOR such a sum shall be expended or used either wholly or partly, or be not used at the discretion of the ENGINEERentirely as he may decide and direct. If no part or only part thereof, be used then the whole or the part,as the case may be not used, shall be deducted from the contractprice. None of the works or articles to which sum of money refersshall be done or purchased without the written order of theENGINEER. The CONTRACTOR shall allow such SUB-CONTRACTOR every facility for the execution of their severalworks simultaneously with his own and shall within fourteen daysafter ENGINEER has requested him in writing to do so pay theamounts of the accounts of such persons for such articles andworks. To the net amounts so paid shall be added 10% sum of theCONTRACTOR’s profit and the sum provided shall be added to or deducted from the contract price as the case may be. Providedalways that the CONTRACTOR shall have no responsibility withregard to such works or articles unless he shall have previouslyapproved the SUB-CONTRACTOR and or the material or plant to

be supplied.

80.0 TAXES AND DUTIESThe rates quoted by the CONTRACTOR should be inclusive of alltaxes and duties if any for the materials to be brought to the site.

Page 75: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 75/101

SECTION - C59

80.1 EXCISE DUTYIf CENVAT credit has been taken into account while quoting theprice, a certificate to such effect shall be furnished along with theoffer. Any increase in ED consequent to the Tenderers coming intodifferent duty slab during the execution of contract shall have to betaken into account and all inclusive firm price shall be quoted

accordingly by the Tenderers.

80.2 SERVICE TAX:Quoted rate shall not include service tax and service tax shall beindicated separately. Service tax as applicable to this contract shallbe reimbursed upon production of documentary evidence.

81.0 PRECAUTION DURING WORKING a. The CONTRACTOR should take all precautions necessary and as

specified by the ENGINEER for works. He should at his expenses

provide helmets for all the workmen working. Any specialprecautions that may be required by the Acts of Rules of theTamil Nadu Government from time to time shall also be taken bythe CONTRACTOR at his own cost.

b. Inclement Weather During inclement weather, the contractor shall protect from injuryall works already in progress, just then completed.

Should the work be suspended by reason of rain, strikes, lockoutsor any other cause, the CONTRACTOR shall take all precautionsnecessary for protection of works and make good, at his ownexpense, any damage arising from any of these causes.

82.0 DEDUCTION FOR LABOUR WELFARE FUNDTowards contribution to Manual Labour Welfare Fund, an amountof  0.3% of the gross value of the bill will be deducted from eachrunning bill and the recovery will be remitted to Tamil NaduConstruction Workers Welfare Board, Chennai - 600 018. TheCONTRACTOR should take this into account while quoting rates.

**********

Page 76: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 76/101

SECTION - D

Page 77: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 77/101

SECTION - D60

SECTION – D : TECHNICAL SPECIFICATION

1.0 SCOPE:This specification covers the general requirements of leveling thesite to the desired level of +8.5m by cutting the mounts /uphill andfilling the pits for the low lying area as directed by Engineer at a

uniform layer 300mm thick by consolidating first by moving thevehicle and finally with the power roller of suitable capacity in eachlayer so as to achieve a proctor compaction density of 95% bytransporting the cut material to the required distance. (Requireddistance will be from the source of cutting area to the requiredfilling area of the site)

The scope also includes ash excavation with in the ash pond orfrom adjourning the ponds if necessary

2.0 DRAWINGS:Engineer/Owner shall furnish site plan showing the primary ash

pond 1 and adjoining peripheral canal area where the work has tobe executed involving the cutting and filling. Based on the siteplan, the Contractor has to do a detailed survey of the PrimaryPond 1 and peripheral canal area and furnish the contour plan.

3.0 GENERAL

3.1 CONTRACTOR shall furnish all tools, plants, instruments, qualifiedsupervisory personnel, labour, materials, any temporary works,consumables, any and everything necessary, whether or not suchitems are specifically stated herein for completion of the job in

accordance with specification requirements.

3.2. CONTRACTOR shall carry out the survey of the site beforeexcavation and set properly all lines and establish levels for variousworks such as earthwork in excavation for grading. Such surveyshall be carried out by taking accurate cross sections of the areaperpendicular to establish reference/grid lines at 5m intervals or nearer as determined by ENGINEER based on ground profile.These shall be checked by ENGINEER and thereafter properlyrecorded.

3.3 The excavation shall be done to correct lines and levels. This

shall also include, where required, proper shoring to maintainexcavation and also the furnishing, erecting and maintaining of substantial barricades around excavated areas and warning lampsat night for ensuring safety.

3.4 Contractor shall furnish 10 hard copies and 2 soft copies of finalcompleted drawings with grade levels and grid.

Page 78: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 78/101

SECTION - D61

4.0 REFERENCE PILLARS AND BENCH MARK

Under no circumstances shall the CONTRACTOR remove or disturb any permanent bench marks / reference pillars installed bythe Board. The Tenderer shall carefully maintain and protect allbenchmarks and reference pillars and shall carry out all his works

by accurate reference thereto.

5.0 EXCAVATION5.1. Excavation work shall be carried out on mechanical equipments

unless, in the opinion of Engineer, the work involved and timeschedule permit manual work.

5.2 All excavation shall be done to the minimum dimensions asrequired for safety and working facility. Prior approval of Engineer shall be obtained by CONTRACTOR in each individual case, for the method he proposes to adopt for the excavation, including

dimensions, side slopes, dewatering, disposal etc. This approval,however, shall not in any way relieve CONTRACTOR of hisresponsibility for any consequent LOSS or DAMAGE. Theexcavation must be carried out in the mostexpeditious and efficient manner. Side slopes shall be as steep aswill stand safely for the actual soil conditions encountered. Everyprecaution shall be taken to prevent slips. Should slips occur, theslipped material shall be removed and the slope dressed to amodified stable slope. Removal of the slipped earth will not bepaid for.

5.3 Excavation shall be carried out with such tools, tackles and asDescribed herein before.

6.0 MEASUREMENT & PAYMENT:6.1 All excavation shall be measured net. Dimensions for purpose of 

payment shall be reckoned on the horizontal area of the excavation atthe base for foundations of the walls, columns, footings, tanks, rafts or other foundations/structures to be built, multiplied by the mean depthfrom the surface of the ground in accordance with the drawings.Excavation in side slopes will not be paid for. Contractor may makesuch allowance in his rates to provide for excavation in side slopeskeeping in mind the nature of the soil and safety of excavation.

Reasonable working space beyond concrete dimensions and shutteringwhere considered necessary, in the opinion of Engineer have to bedone without any extra payment for additional excavation.

6.2 Payment for fill inside trenches, plinth or similar filling with selectedexcavated material will be made for only compaction asspecified/directed. Cost of all other operations shall be deemed tohave been covered in the rate quoted for excavation. Payment for thiswork will be made based on measurement of plinth/trench dimensions

Page 79: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 79/101

SECTION - D62

filled. The plinth ground levels shall be surveyed before hand for thispurpose. If no compaction is specified /desired such filling will not beseparately paid for. In such a event the fill shall be leveled/finished tothe profile as directed at no extra cost.

7.0 TIMBER SHORING

7.1. ScopeThis specification covers the general requirements of timber shoringfor excavation of trenches, pits, and open excavations.

 7.2 Close timbering shall be done by completely covering the sides of the

trenches and pits generally with short upright members called pollingboards. These shall be of minimum 25cm x 4cm sections or asdirected by ENGINEER. The boards shall generally be placed inposition vertically side by side without any gap on each side of theexcavation and shall be secured by horizontal welding of strong wood

at maximum 1.2metres spacing, strutted with ballies or as directed byENGINEER. The length of the ballies struts shall depend on the widthof the trench or pit. If the soil is very soft and loose, the boards shall beplaced horizontally against each side of the excavation and supportedby vertical, welding, which in turn shall be suitably strutted. The lowestboards supporting the sides shall be taken into the ground and noportion of the vertical side of the trench or pit shall remain exposed, soas to render the earth liable to slip out.

7.3 Timber shoring shall be CLOSE or OPEN type depending on thenature of soil and the depth of pit or trench. The type of timbering shall

be as approved by ENGINEER. It shall be the responsibility of CONTRACTOR to take all necessary steps to prevent the sides of excavations, trenches, pits, etc. from collapsing.

7.4 Timber shoring may be required to keep the sides of excavationvertical to ensure safety of adjoining structures or to limit the slope of excavations, or due to space restrictions or for other reasons. Suchshoring shall be carried out, except in an emergency, only under instructions from Engineer.

7.5 The withdrawal of the timber shall be done very carefully to preventthe collapse of the pit or trench. It shall be started at one end and

proceeded with systematically to the other end. No claim shall beentertained for any timber which cannot be withdrawn and is lost or buried.

7.6 In the case of open timbering, the entire surface of the side of trenchor pit is not required to be covered. The vertical boards of minimum25cms x 4cms sections shall be spaced sufficiently apart to leaveunsupported strips of maximum 50cms average width. The detailedarrangement, sizes of the timber and the spacing shall be subject to

Page 80: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 80/101

SECTION - D63

the approval of ENGINEER. In all other respects, specification for close timbering shall apply to open timbering.

7.7 In case of large pits and open excavations, where shoring is requiredfor securing safety of adjoining structures or for any other reasons andwhere the planking across sides of excavations /pits cannot be strutted

against suitable inclined struts, supported on the excavated bed shallbe provided. Load from such struts shall be suitably distributed on thebed to ensure no yielding of the strut.

8.0 DEWATERING

8.1 Generally, all excavation shall be kept free of water. Grading in thevicinity of excavations shall be controlled to prevent surface water running into excavated areas. Contractor shall remove by pumping or other means approved by Engineer any water inclusive of rain water and subsoil water accumulated in excavation and kept all excavationsdewatered until the foundation work is completed and back filled.

Sumps made for dewatering must be kept clear of theexcavations/trenches, required for further work. Method of pumpingshall be approved by Engineer, but in any case, the pumpingarrangement shall be such that there shall be no movement of subsoilor blowing in due to different head of water during pumping. Pumpingarrangements shall be adequate to ensure no delays in construction.

8.2 When there is a continuous in flow of water and quantum of water to behandled is considered in the opinion of Engineer, as large, well pointsystem- Single stage or multistage, shall be adopted. Contractor shallsubmit to Engineer his scheme of well point system including thestages, the spacing, number and diameter of well points, headers, etc.and the number, capacity and location of pumps of approval. The costof dewatering shall be included in the items rate itself.

8.3 Unless separately provided for in the schedule of quantities,dewatering is deemed to have been included in the unit rates quoted.Wherever the Schedule is described with specific dewatering for itemsof works involved below Ground level, the rate quoted for the specificitem should be inclusive of all dewatering charges of any type as maybe required from the time of excavation, till the back filling iscompleted for the entire period of all operations for the structureconcerned including excavation, mat concreting RCC including tying

reinforcements, curing etc. NO SEPARATE PAYMENT WILL BEPAYABLE on whatsoever grounds including misjudgment of the natureof dewatering and idle periods.

9.0 RAIN WATER DRAINAGE

9.1 Grading in the vicinity of excavation shall be such as to excluderain/surface water draining into excavated areas. Excavation shall be

Page 81: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 81/101

SECTION - D64

kept clear of rain and such water as the CONTRACTOR may be usingfor his work by suitably pumping out the same at no extra cost to theOWNER. The Scheme for pumping and discharge of such water shallbe approved by the ENGINEER.

 10.0 GENERAL SITE GRADING

10.1. Site grading shall be carried out as indicated in the drawings and asdirected by the Engineer. Excavation shall be carried out as specifiedin the specification. Filling and compaction shall be carried out asspecified else where unless otherwise indicated below.

10.2. To ensure that the fill has been compacted as specified, field andlaboratory tests shall be carried out by the contractor at his cost.

10.3. Field compaction test shall be carried out at different stages of filling andalso after the fill to the entire height has been completed. This shallhold good for embankments as well.

10.4. Contractor shall protect the ash fill from being wash away by rain of damaged in any other way. Should any slip occur, Contractor shallremove the affected material and make good the slip at his cost.

10.5. The fill shall be carried out to such dimensions and levels as indicatedon the drawings after the stipulated compaction. The fill will beconsidered as incomplete if the desired compaction has not beenobtained.

11.0 FILL DENSITYThe compaction shall comply with the specified proctor density or moisture content differing not more than 4 percent from the optimummoisture content. Contractor shall demonstrate adequately at his costby field and laboratory tests that the specified density (95%) has beenobtained.

12.0 FILLING WITH POND ASH

Filling with ash from ash Pond ash of North Chennai Thermal Power Station for site leveling work involve the following operations.

(1) Excavation / cutting the mount/uphill of (+)8.50 MSL. and above

within the proposed project area and also Dewatering, excavation,Loading, transportation the wet ash with in the NCTPS stagePrimary pond I and also from periphery canal and if required fromthe Primary pond II, to proposed project area (Inside the Primary Ash Pond I) and unloading of excavated material in the low lyingareas for filling the pits to the required level of (+) 8.50 m asdirected by Engineer at site.

Page 82: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 82/101

SECTION - D65

(2) Spreading of pond ash and filling at a uniform layer 300mm thickby consolidating, first by moving the vehicle and finally with thepower/vibrating roller of suitable capacity in each layer so as toachieve a proctor compaction density of 95% includingremoval/bailing out of rain/surface/sub-soil water from theexcavation and filling site.

(3) Finishing of surface

(4) Sampling and testing, compacting trials

(5) Setting out and making profiles

(6) Recording of measurements etc. as directed by Engineer 

13.0 EXTENT OF WORK

13.1 Initial level shall be taken and produced to TANGEDO for 

concurrence and after that only, site grading works is to be takenup

13.2 Initially, the low lying areas are to be filled up with wet ashavailable excess above the specified level in the primary pond 1and the ash deposited in peripheral canal, if further quantity isrequired for the specified level may be taken from the PrimaryPond No-2. The existing earthern bund around PPI (From+13.00m to +8.50m) is to be cut and have to be used as a cover over the fly ash filled leveled area.

13.3 Wet ash is to be spread in layers and compacted by to & fro

movement using dozors to the satisfaction of the Engineer at siteand final compaction by vibratory rollers as described in Clause 16of this section.

13.4 Top cover of 23cm is to be provided using the earth, cut down fromthe Bund & Extended Bund portion, on completion of the sitegrading work, with a finished (level) top level of +8.5m in plant area& corridor area, the site may be handed over to TANGEDCO.

13.5 The salient features for this work is furnished here below:

The existing bund top level of Primary Pond I - (+) 13.00 m

The bottom Bed level of Ash pond - (+) 7.00 m

The maximum level of Ash surface in P.P.I - (+)10.30m

(partly)

The proposed FFL (i.e.) finished floor level on

completion of all works (PROJECT) - (+) 10.00 m

Page 83: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 83/101

SECTION - D66

The average top level proposed for which site

grading is to be done. - (+) 8.50 m

The average top level proposed in corridor area- (+) 8.50 m

13.6 The site grading work inside PPI is to be carried out from westernside towards North Eastern side, enabling to drain excess water from the pond, through the Toe drains & cross Drains (in NorthEastern side of PPI)

13.7 Special care & precautionary measures may be taken during theexecution of site grading work considering the physical charactersof wet ash. If the access is slushy & unapproachable it is theresponsibility of the contractor to make safe and sturdy approachfor this area.

14.0 PLACEMENT

14.1 Ash excavated having required moisture content shall be placed inlayers not exceeding 300mm in compacted thickness. Thiscombined excavation and placing operations shall be such that thematerials when compacted in the fill will be blended sufficiently toproduce specified degree of compaction and stability.

14.2 No stones, cobbles or not fragments, having maximum dimensionsmore than 200mm shall be placed in the fill. Such stones andcobbles shall be removed either at the borrow pit or after beingtransported to the fill but before the ash in the fill is rolled andcompacted.

15.0 PROCEDUREThe excavated materials shall be placed in the fill in continuoushorizontal layers stretching right across the whole section, notmore than 300mm in compacted thickness and rolled as hereinspecified. The length of one layer shall not exceed 150 metre atone stretch. The layers shall be compacted in strips overlappingnot less than 600mm. If the rolled surface of any fill is found to betoo wet for proper compaction, it shall be raked up, allowed to dry,or shall be worked with in harrow or any other approved equipmentto reduce the moisture content to the required amount and then itshall be re-compacted before the next layer of ash is placed. Ash

surfaces are likely to become dry in short intervals especiallyduring hot and dry weather and hence enough moisture shall beadded between passes to ensure proper compaction.

16.0 COMPACTIONThe compaction of each layer shall be carried out so as to achievein-situ dry density not less than 95% of Standard Proctor’smaximum dry density of the material as per IS : 2720 (Part-VII).To achieve the 95% compaction level, use of vibratory rollers shall

Page 84: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 84/101

SECTION - D67

be made. Required number of passes shall be made so as toachieve desired compaction. Number of passes required shall beverified through trial tests before actual of work.

17.0 MOISTURE CONTROLPrior to and during compacting operations, the materials in each

layer of ash / earth shall have a moisture content about 2% less for earth fill (for earth cover) and about 5% less for ash, than theoptimum moisture content. This shall however to adjusted,according to the weather conditions. So far as practicable thematerials shall be brought to the proper moisture content in the ashpond area before excavation. If additional moisture content isrequired, it shall be added at the fill site by sprinkling water beforerolling the layer. The contractor shall make his own arrangementsfor supply of water in ash pond areas (excavated area) as well as infill area. If the moisture content is greater than required, thematerial shall be spread and allowed to dry before starting rolling.The moisture content shall be uniform throughout the layer of 

material and ploughing, horrowing, or other methods of mixing maybe required to obtain uniform distribution. If the moisture content ismore or less than the range of the required moisture content, or if itis not uniformly distributed throughout the layer, rolling shall bestopped, and shall be started again only when the above conditionsare satisfied.

If the area happens to be water logged, ground water table of siteshall be lowered by dewatering the same so that proper compaction of fill material at around optimum moisture content canbe ensured.

18.0 PREVENTION OF POLLUTIONIt shall be the responsibility of contractor that no air borne andwater borne pollution should occur during all stages of hisoperations such as in Ash pond excavated areas, duringtransportation of ash / wet ash during placement of fill materials,etc., shall be mandatory for the contractor to undertake allmeasures such as water sprinkling, covering moist ash / earth withtarpaulins in open trucks, etc. to take care of above.

19.0 STABILITY OF EXCAVATIONThe methods of excavation shall be in every case being subject to

the approval of the Engineer and the Contractor shall ensure thestability and safely of the excavations, adjacent structures, servicesand the works as per the provisions of the safety codes for excavation.

Whenever the Engineer directs, the sides of the excavation shall betimbered and shored by a proper method approved by the Engineer.

Page 85: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 85/101

SECTION - D68

The contractor shall have full responsibility for the stability of theexcavation and safely of workmen. If any slip occurs, the contractor shall remove all the slipped material from the excavated pit withoutpayment. Also if any damage to the built up structure occursbecause of the slips, the contractor shall make good the samewithout any payment, at his own cost.

20.0 PROTECTION OF FILLINGThe contractor shall protected all fill and in the event of its beingwashed away by rainwater or damaged in any other way he shallrestore and make it good. Should any slips occur, the affectedmaterial shall be removed and made good with sound material.

21.0 MEASUREMENT AND PAYMENTThe items of filling for site leveling work shall be measured and paidfor the volume of actual earthwork in filling measurement in cu.mcorrect to two decimal places. The volume shall be calculated basedon the spot levels of the area(s) filled in, taken jointly by the Engineer 

and the Contractor before commencement of filling and after thefilling has been completed (i.e. after the area has been finished to therequired levels and slopes after compaction).

The ground level shall be taken at 5 m intervals in level or uniformlysloping grounds and at closer intervals where local mounds, pits or undulations are met with as directed by the Engineer. The groundlevels so taken shall be recorded in field books and plotted on a planwhich shall be signed by the contractor and the owner before earthwork is started. Men & materials required for taking levels shall besupplied by contractor at his own cost. Levels shall be taken after thecompletion of the work at suitable intervals and the quantity of excavation in cutting will be computed from this level.

22.0 FINISHING OF SURFACESThe surface of the filled up areas, slopes etc. after reaching final levelsshall be dressed to the request levels slopes. The difference in levelsand dimensions shall not be more than +/- 5 cm(locally) with respect tothose specified in Released for Construction drawings.

23.0 SAMPLING AND TESTINGThe contractor shall submit and finalise a detailed Field Quality Assurance programme within 30 day from the date of award of the

contract according to the requirements of the specification. This shallinclude setting up of a testing laboratory arrangement of testingapparatus /equipment deployment of qualified experienced manpower,preparation of format for record, Field Quality Plan etc. On finalizedField Quality Plan, the owner shall identify Customer hold Pointsbeyond which the work shall not proceed without written approval of theEngineer.

Page 86: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 86/101

SECTION - D69

The fill material shall be tested for determining optimum moisturecontent and maximum dry density by Standard Proctor Test as per IS2720 (Part-II) and (Part-VII). The fill material shall also be tested for determining moisture content before compaction as per IS:2720 (Part-II) For each of the above tests, one sample for every 10000 cu.m. of fillmaterial shall be tested. Additional samples shall be tested, where ever 

there is a change in the source or type of fill material.

24.0 ACCEPTANCE CRITERIA A sample shall be deemed to have passed the test when the relativedensity equal to or more than the specified quality.

If a sample taken from a compacted layer of 10,000 Sqm area, fails topass the test, the layer shall be further compacted and two moresamples taken and tested. Both of these samples should pass withoutany negative deviation. This procedure will be repeated till the samplespass the test. Only after this, spreading of further layers shall be takenup.

25.0 IS CODES:The following are some of the important IS codes relevant to thissection.

IS: 2720 Methods of testing for soils.IS: 3764 Safety Code for Excavation work.IS: 9758 Guidelines for dewatering during excavation.IS: 10379 Code of Practice for field control of moisture

and compaction of soils for embankment andsub-grade.

Page 87: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 87/101

SECTION - E(Separate book is enclosed for schedules)

Page 88: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 88/101

SECTION - F

Page 89: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 89/101

SECTION – F :ANNEXURE - I

PROFORMA FOR SUBMISSION OF TENDER(LUMPSUM)

ToThe Chief Engineer/ Projects,

Tamil Nadu Generation and Distribution Corporation Limited,5th Floor/ Western Wing, N.P.K.R.R. Maaligai,144, Anna Salai,Chennai-600 002.

Sir,1. I/We do hereby tender, and if this tender be accepted undertake to

execute the following work, viz. Site Grading the area of theproposed site for the establishment of 2X 660 MW Ennore SEZcoal based Super critical Thermal Power Plant in the Ash Dykearea of North Chennai Thermal  Power Station (NCTPS), shown inthe drawings and described in the specification prepared in the

office of the Chief Engineer/ Projects, 5th Floor, NPKRR Maaligai,Electricity Avenue, 144, Anna Salai, Chennai-600 002 with suchvariations by way of alterations and additions to, and omissionsfrom the said works and method of payment as are provided for in the conditions of contract for the sum as quoted in price bid or such other sum as may be arrived at under the clause of thestandard preliminary specification relating to payment onlumpsum basis or by final measurement at unit prices.

2. I /We, have also completed the price list of items of scheduleannexed (in words and figures) for which I/We agree to execute thework when the lumpsum payment under the terms of theagreement is varied by payment on measured quantities.

3. I/We, hereby distinctly and expressly declare and acknowledgethat, before the submission of my/our tender, I/We have carefullyread the Tamil Nadu Building Practice and the General Conditionsof Contract therein, and that I/We have made such examination of the contract documents and of the plans, specifications andquantities and of the location where the said work is to be doneand such investigation of the work is to be done and suchinvestigation of the work required to be done and in regard to thematerials required to be furnished as to enable me/us to

thoroughly understand the intention of same and therequirements, covenants, agreements, stipulations and restrictionscontained in the contract, and in the said plans and specificationsand distinctly agree that I/We will not hereafter make any claimor demand on the TANGEDCO based upon or arising out of any alleged misunderstanding or misconception or mistakeon my/our part of the said requirements, convenants,agreements stipulations, restrictions and conditions.

Page 90: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 90/101

4. I/We enclose Certified copies of Auditor Certificate/ Annual Accounts. I/We enclose the necessary Demand Draft/ Banker’scheque (tick the mode of payment and strike out the other) for thepayment of the sum of Rs………… (Rupees……………………………………………… only) as the EarnestMoney not to bear interest. If my/ our tender is not accepted, this

sum shall be returned to me/us on my / our application, whenintimation is sent to me/us of rejection or on the expiration of 180days from the date of opening of this tender whichever isearlier. If my/our tender is accepted, the earnest money shall beretained by the TANGEDCO as Security for the fulfillment of theContract if upon written intimation to me/us by the Chief Engineer/Projects/ NPKRR Maaligai, Electricity Avenue, 144, Anna Salai,Chennai-600 002. I/We fail to attend the said office before the endof the period specified on such intimation, the tender will not beconsidered and upon intimation being given to me/us by the Chief Engineer/ Projects, NPKRR Maaligai, Electricity Avenue, 144, Anna Salai, Chennai-600 002 of acceptance of my/our tender, I/We

fail to make the additional Security Deposit or to enter into therequired agreement as defined in the tender notice, then I/Weagree to the forfeiture of the earnest money. Any notice required tobe served on me/us hereunder shall be sufficiently served onme/us by post to me/us (registered or left at my/our address given)such notices shall if sent by post in due course of post, it would bedelivered at the address to which it is sent.

5. I/We fully understand the written agreement to be entered intobetween me/us and the TANGEDCO shall be the foundation of rights of both the parties and the contract shall not be deemed tobe complete until the agreement is first signed by me/us and thenby the proper officer authorised to enter into contracts onbehalf of TANGEDCO, I am/We are professionally qualified andam/are agreeable to Clause C.7.0 of Section-C of thisSpecification and my/our qualification(s) are given below:

--------------------------------------------------------------------------------------------

Sl.No. Name Qualification-------------------------------------------------------------------------------------------

-------------------------------------------------------------------------------------------- 

6. I/We will employ the following technical staff for supervising thework as per clause 7.0 of Section-C of this specification including

Page 91: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 91/101

the penalty in the clause and will see that one of them is alwaysat site during working hours personally checking all items of worksand paying extra attention, (eg.) reinforced concrete work.

-----------------------------------------------------------------------------------------Sl. Name of members of technical

No. Staff proposed to be employed Qualification----------------------------------------------------------------------------------------

----------------------------------------------------------------------------------------

  NOTE: 

The TENDERER should score out the last clause or the

penultimate, accordingly as they are themselvesprofessionally qualified or undertaken to employ technical staff under them.

  CONTRACTOR 

Page 92: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 92/101

ANNEXURE - IIPARTICULARS OF EMPLOYMENT OF EX-SERVICE PERSONNEL

I/We undertake to employ at any time during the execution of thiscontract, the following ex-service personnel, if available.

-----------------------------------------------------------------------------------------Sl.No. NAME----------------------------------------------------------------------------------------

1.

2.

3.

4.

5.

6.

7. 

-----------------------------------------------------------------------------------------

SIGNATURE OF THE TENDERER 

Page 93: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 93/101

ANNEXURE – III

UNDERTAKING IN - LIEU OF PAYMENT OF EMD(in Stamp Paper for a value of Rs.80/-)

THIS UNDERTAKING Executed at _____________ on this the ______ day of ___________ Two thousand and four by M/s. ______________________ a company registered under Companies Act, 1956, having its registered office at _______________ hereinafter called the "Tenderer" TO AND IN FAVOUR OFTHE TANGEDCO, a Body Corporate incorporated under Companies Act, 1956having its office at NPKRR Maaligai, Electricity Avenue, 144, Anna Salai,Chennai-600 002 represented by ______________ (hereinafter called the`TANGEDCO')

WHEREAS the contract is for the supply and erection/constructionetc._____________ in terms of the Tender SpecificationNo.______________ dated ______________.

AND WHEREAS in accordance with clause of the above said tender specification the tenderer has to furnish E.M.D. of Rs………. (Rupees……………………… only).

AND WHEREAS the tenderer has requested the TANGEDCO toaccept an undertaking in lieu of payment in cash of the E.M.D.

AND WHEREAS the TANGEDCO has accepted the request of thetenderer subject to his executing an undertaking to pay to the TANGEDCO notexceeding Rs…………. (Rupees ……………………………… only) representingthe Earnest Money Deposit together with costs in cash for non-fulfillment of theconditions stipulated in the Tender Specification or the conditions stipulated inthe contract by the tender.

IN CONSIDERATION of the TANGEDCO having agreed to accept anundertaking from the tenderer in lieu of payment of Earnest Money Deposit incash, the tenderer undertakes to pay the sum of Rs……………. (Rupees…………………………………………………only) immediately when a demandis raised by the TANGEDCO against the tenderer without any demur in theevent of the following:

i) if he withdraws his tender or backs out after acceptance of thetender or fails to remit the Security Deposit.

ii) if he revises any of the terms quoted during the validity period.iii) if he violates any of the conditions of the tender Specification.

NOW THE CONDITION OF THE ABOVE WRITTENUNDERTAKING is such that if the tenderer shall duly and faithfully observeand perform the terms and conditions specified in terms of the above, then theabove written undertaking shall be void, otherwise the same shall remain in fullforce.

Page 94: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 94/101

The tenderer undertakes not to revoke this guarantee till the contract iscompleted under the terms of contract.

The expressions, `Tenderer' and `the TANGEDCO' herein beforeused shall include their respective successors and assigns in office.

IN WITNESS WHEREOF THIRU.......................... for and behalf of thetenderer has signed this undertaking on the day, the month and year firstabove written.

SIGNATURE

In the presence of witnesses:

1.

2.

Page 95: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 95/101

 ANNEXURE - IV

SCHEDULE OF EQUIPMENT

The BIDDER shall indicate herein below the equipment, he has inpossession and the equipment he proposes to bring to the site, in case

the work is awarded to him.

-------------------------------------------------------------------------------------------------Sl. Type and Description Numbers the bidder Number he proposes

No. of the equipment has in possession to bring on to site1. 2. 3. 4.--------------------------------------------------------------------------------------------------

---------------------------------------------------------------------------------------------------

Bidder hereby confirms that the quantity and type of tools he will employfor construction will not be less than those listed above, and agree tobring more equipment, if so warranted, in the opinion of the Engineer.

SIGNATURE :

DESIGNATION :

COMPANY :

DATE :

COMPANY SEAL :

Page 96: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 96/101

ANNEXURE - V

SCHEDULE OF RATES FOR LABOUR

BIDDER shall quote hereunder the all inclusive price of labour assumed

for the purposes of this contract per day of 8 hrs each.

------------------------------------------------------------------------------------------Supplying labour Rs./Each

-------------------------------------------------------------------------------------------i) Unskilled labour maleii) Unskilled labour femaleiii) Skilled labour maleiv) Masonv) Carpenter vi)vii)

viii)ix)x)xi)xii)

----------------------------------------------------------------------------------------------Engineer/Owner shall have the right to ask contractor to supply labour for any work at the rates quoted above.

SIGNATURE :

DESIGNATION :

COMPANY :

DATE :

COMPANY SEAL :

 

Page 97: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 97/101

 ANNEXURE - VI

BIDDER'S EXPERIENCE

The BIDDER shall furnish here a list of similar jobs executed by him towhom a reference may be made by the OWNER in case the OWNER

considers such a reference necessary.

Sl. Name and Value of Period of Client PersonsNo. Designation work construction to whom

& date referencemay bemade

1. 2. 3. 4. 5. 6.-----------------------------------------------------------------------------------------------

 

-----------------------------------------------------------------------------------------------

SIGNATURE :

DESIGNATION :

COMPANY :

DATE :

COMPANY SEAL :

 

Page 98: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 98/101

ANNEXURE - VII

DETAILS OF TECHNICAL PERSONNEL OF THE TENDERER'SORGANISATION

------------------------------------------------------------------------------------------------------Sl. Designation Name Length of Qualifi- Professional experience &No service in cations details of work carried out

the firm--------------------------------------------------------------------------------------------------------

1. Project Manager 

2. Works Manager or Senior Engineer 

3. Engineers (Civil)

4. Engineers (Mech..)and Electrical)

5. Assistant ProjectEngineer 

6.

7.

8.

9.

--------------------------------------------------------------------------------------------------------

SIGNATURE OF TENDERER

Page 99: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 99/101

 ANNEXURE - VIII

UNDERTAKING TOWARDS JUSRISDICTION FOR 

LEGAL PROCEEDINGS

( NON JUDICIAL STAMP PAPER VALUE RS.80/=)

This undertaking executed at…………………………………………………

on this…………….. (Date)………................. (Month) Two thousand and ……

by M/s ……………………………………………………Registered under Companies

 Act, 1956 having its registered office at ……………………………………………

hereinafter called the contractor (which expression shall where the

context so admits mean and include its successors in office and in favour

of Tamil Nadu Generation and Distribution corporation Limited, a

company incorporated under the company Act 1956, having its

registered office at No. 144, (Old NO. 800), Anna Salai, NPKRR Maaligai,

Chenai-600 002 herein after called the purchaser (which expression shall

where the context so admits means and includes its successors if Office

and assigns).

WHEREAS a contract for the supply of ………………………….has been

awarded in favour of the contractor under the Purchase order

No……………..dated…………….

 AND WHEREAS in accordance with the terms of the above

Purchase order, the contractor has to furnish un undertaking to the effect

that no suit or any proceedings in regard to any matter arising in any

respect under this contract shall be instituted in any matter in any respect

under this contract shall be instituted in any court other than in the High

court, Madras of District court at …………….. or Sub-court at

…………………….or at the District Munsiff court at …………………….. as the

case may be.

IN CONSIDERATION of the Board having agreed to accept the

undertaking the contractor hereby undertakes that no suit or any

proceedings in regard to any matter arising in respect of this contractshall be instituted in any court, save in the High court , Madras or District

court at…………….or sub court at ……………………. Or at the District

Munsiff court at ………………….as the case may be it is agreed that no

other court shall have jurisdiction to entertain any suit or proceedings,

even though , part of the cause of action might arise within their

urisdiction. In case any part of the cause of action might arise within the

Page 100: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 100/101

 jurisdiction of any other Courts in Tamil Nadu and rest within the

 jurisdiction of Courts outside the State of Tamil Nadu , then it is agreed to

between the parties that such suits on proceedings shall be instituted in a

court within the State of Tamil Nadu and no other Court outside the State

of Tamil Nadu shall have jurisdiction.

IN WITNESS WHEREOF Thiru……………………………………..……… of 

M/s …………………………. hereby put his hand and seal for due observance

of the undertaking in the presence of the following witnesses

COMPANY SEAL SIGNATURE :

DESIGNATION :

COMPANY :DATE :

WITNESSES:

1)

2)

Page 101: Final Ennore SEZ - Site Grading - Specification - Dt.280213

7/29/2019 Final Ennore SEZ - Site Grading - Specification - Dt.280213

http://slidepdf.com/reader/full/final-ennore-sez-site-grading-specification-dt280213 101/101

SECTION – G(Drawings)