FINAL Capstone Project Gantt - proj354.com · Title: FINAL Capstone Project Gantt Author: James...
Transcript of FINAL Capstone Project Gantt - proj354.com · Title: FINAL Capstone Project Gantt Author: James...
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
1 99% 1 Capstone Project: CMS 65 days Mon 1/6/20 Fri 4/3/20
2 100% 1.1 Hardware Configuration 2 days Thu 1/9/20 Fri 1/10/20
3 100% 1.1.1 Hardware Collection 2 days Thu 1/9/20 Fri 1/10/20
4 100% 1.1.1.1 Compile Hardware List 8 hrs Thu 1/9/20 Thu 1/9/20
5 100% 1.1.1.2 Submit Hardware List 8 hrs Thu 1/9/20 Thu 1/9/20
6 100% 1.1.1.3 Collect Hardware 16 hrs Thu 1/9/20 Fri 1/10/20
7 100% 1.1.1.4 M: Hardware Collected 0 days Thu 1/9/20 Thu 1/9/20
8 100% 1.1.2 Corporate Side Hardware Set-Up 0.75 days Thu 1/9/20 Thu 1/9/20
9 100% 1.1.2.1 Connect Peripheral Devices (Monitor, Keyboard, Mouse)
1 hr Thu 1/9/20 Thu 1/9/20
10 100% 1.1.2.2 Run diagnostic tests to determine device functionality, perform device cleanup
2 hrs Thu 1/9/20 Thu 1/9/20
11 100% 1.1.2.3 Install WS 2016 Datacenter OS image 1 hr Thu 1/9/20 Thu 1/9/20
12 100% 1.1.2.4 Perform housekeeping configurations (hostname, static IPs, etc.)
1 hr Thu 1/9/20 Thu 1/9/20
13 100% 1.1.2.5 Test hardware configuration 1 hr Thu 1/9/20 Thu 1/9/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
14 100% 1.1.2.6 M: Hardware successfully configured 0 days Thu 1/9/20 Thu 1/9/20
15 100% 1.1.3 Client Side Hardware Set-Up 0.75 days Fri 1/10/20 Fri 1/10/20
16 100% 1.1.3.1 Connect Peripheral Devices (Monitor, Keyboard, Mouse)
1 hr Fri 1/10/20 Fri 1/10/20
17 100% 1.1.3.2 Run diagnostic tests to determine device functionality, perform device cleanup
2 hrs Fri 1/10/20 Fri 1/10/20
18 100% 1.1.3.3 Install WS 2016 Datacenter OS image 1 hr Fri 1/10/20 Fri 1/10/20
19 100% 1.1.3.4 Perform housekeeping configurations (hostname, static IPs, etc.)
1 hr Fri 1/10/20 Fri 1/10/20
20 100% 1.1.3.5 Test hardware configuration 1 hr Fri 1/10/20 Fri 1/10/20
21 100% 1.1.3.6 M: Hardware successfully configured 0 days Fri 1/10/20 Fri 1/10/20
22 100% 1.1.4 M: Hardware set up completed 0 days Fri 1/10/20 Fri 1/10/20
23 100% 1.2 Network Configuration 10.25 days Fri 1/10/20 Fri 1/24/20
24 100% 1.2.1 Construct Network Topology 3.5 days Fri 1/10/20 Thu 1/16/20
25 100% 1.2.1.1 Draft network diagram 1 day Fri 1/10/20 Mon 1/13/20
26 100% 1.2.1.2 Decide subnets 2 hrs Mon 1/13/20Mon 1/13/20
27 100% 1.2.1.3 Determine IP addresses 2 hrs Tue 1/14/20 Tue 1/14/20
28 100% 1.2.1.4 Implement Network Configuration 2 days Tue 1/14/20 Thu 1/16/20
29 100% 1.2.1.5 M: Network Topology created 0 days Thu 1/16/20 Thu 1/16/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
30 100% 1.2.2 Configure Network Hardware 6.75 days Thu 1/16/20 Fri 1/24/20
31 100% 1.2.2.1 Set up Switch & Router 6.75 days Thu 1/16/20 Fri 1/24/20
32 100% 1.2.2.1.1 Configure network connection 2 hrs Thu 1/16/20 Thu 1/16/20
33 100% 1.2.2.1.2 Implement network security 4 hrs Thu 1/16/20 Thu 1/16/20
34 100% 1.2.2.1.3 Configure additional Router and Switch Settings
48 hrs Fri 1/17/20 Fri 1/24/20
35 100% 1.2.2.1.4 Verify network configurations 0 hrs Fri 1/24/20 Fri 1/24/20
36 100% 1.2.2.1.5 Test network connectivity 0 hrs Fri 1/24/20 Fri 1/24/20
37 100% 1.2.2.1.6 Test network security 0 days Fri 1/24/20 Fri 1/24/20
38 100% 1.2.2.1.7 M: Network Hardware configuration completed0 days Fri 1/24/20 Fri 1/24/20
39 100% 1.2.3 Create VLAN 7 days Thu 1/16/20 Fri 1/24/20
40 100% 1.2.3.1 Design subnets 2 hrs Thu 1/16/20 Thu 1/16/20
41 100% 1.2.3.2 Generate VLANs 16 hrs Thu 1/16/20 Fri 1/17/20
42 100% 1.2.3.3 Manage trunking configuration 56 hrs Thu 1/16/20 Fri 1/24/20
43 100% 1.2.3.4 Implement VLAN configuration to Router &Switch
7 days Thu 1/16/20 Fri 1/24/20
44 100% 1.2.3.5 Test network connectivity 6 days Fri 1/17/20 Fri 1/24/20
45 100% 1.2.3.6 M: Successfully created VLANs 0 days Fri 1/24/20 Fri 1/24/20
46 100% 1.2.4 M: Network configuration successfully completed
0 days Mon 1/20/20
Mon 1/20/20
47 100% 1.3 Client Side Server Services 11.88 days Thu 1/16/20 Fri 1/31/20
48 100% 1.3.1 Hyper-V Set Up 2 days Thu 1/16/20 Fri 1/17/20
49 100% 1.3.1.1 Install Hyper-V Role on Windows Server 2016
2 hrs Thu 1/16/20 Thu 1/16/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
50 100% 1.3.1.2 Configure Hyper-V services 2 days Thu 1/16/20 Fri 1/17/20
51 100% 1.3.1.3 Test Hyper-V configuration 0 hrs Fri 1/17/20 Fri 1/17/20
52 100% 1.3.1.4 M: Hyper-V successfully configured 0 days Fri 1/17/20 Fri 1/17/20
53 100% 1.3.2 Client A: Active Directory Set Up 3 days Fri 1/17/20 Tue 1/21/20
54 100% 1.3.2.1 Create virtual machine for Active Directory 2 hrs Fri 1/17/20 Fri 1/17/20
55 100% 1.3.2.2 Install Active Directory Domain Services Role on Windows Server 2016
1 hr Fri 1/17/20 Mon 1/20/20
56 100% 1.3.2.3 Configure domain/forest for client A 2 hrs Fri 1/17/20 Tue 1/21/20
57 100% 1.3.2.4 Configure AD structure: Users, OUs, Groups, etc.
1 hr Fri 1/17/20 Tue 1/21/20
58 100% 1.3.2.5 Test Active Directory configurations 1 hr Fri 1/17/20 Tue 1/21/20
59 100% 1.3.2.6 M: Active Directory and Client A domain successfully configured
0 days Tue 1/21/20 Tue 1/21/20
60 100% 1.3.3 Client A: Remote Desktop Services Set Up 2 days Thu 1/23/20 Fri 1/24/20
61 100% 1.3.3.1 Create virtual machines for RDS 2 hrs Thu 1/23/20 Thu 1/23/20
62 100% 1.3.3.2 Install RDS Roles on Windows Server 2016 16 hrs Thu 1/23/20 Fri 1/24/20
63 100% 1.3.3.3 Configure RDS infrastructure 3 hrs Fri 1/24/20 Fri 1/24/20
64 100% 1.3.3.4 Test RDS Configurations 1 hr Fri 1/24/20 Fri 1/24/20
65 100% 1.3.3.5 M: Remote Desktop Services successfully configured
0 days Fri 1/24/20 Fri 1/24/20
66 100% 1.3.4 Client B: Active Directory Set Up 0.25 days Fri 1/24/20 Fri 1/24/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
67 100% 1.3.4.1 Create virtual machine for Active Directory 2 hrs Fri 1/24/20 Fri 1/24/20
68 100% 1.3.4.2 Install Active Directory Domain Services Role on Windows Server 2016
1 hr Fri 1/24/20 Fri 1/24/20
69 100% 1.3.4.3 Configure domain/forest for client B 1 hr Fri 1/24/20 Fri 1/24/20
70 100% 1.3.4.4 Configure AD structure: Users, OUs, Groups, etc.
2 hrs Fri 1/24/20 Fri 1/24/20
71 100% 1.3.4.5 Test Active Directory configurations 1 hr Fri 1/24/20 Fri 1/24/20
72 100% 1.3.4.6 M: Active Directory and Client B domain successfully configured
0 days Fri 1/24/20 Fri 1/24/20
73 100% 1.3.5 Client B: Remote Desktop Services Set Up 4.13 days Fri 1/24/20 Thu 1/30/20
74 100% 1.3.5.1 Create virtual machines for RDS 3 hrs Fri 1/24/20 Fri 1/24/20
75 100% 1.3.5.2 Install RDS Roles on Windows Server 2016 5 hrs Fri 1/24/20 Fri 1/24/20
76 100% 1.3.5.3 Configure RDS infrastructure 1 day Fri 1/24/20 Mon 1/27/20
77 100% 1.3.5.4 Test RDS Configurations 1 hr Thu 1/30/20 Thu 1/30/20
78 100% 1.3.5.5 M: Remote Desktop Services successfully configured
0 days Thu 1/30/20 Thu 1/30/20
79 100% 1.3.6 Client C: Active Directory Set Up 0.88 days Thu 1/30/20 Thu 1/30/20
80 100% 1.3.6.1 Create virtual machine for Active Directory 2 hrs Thu 1/30/20 Thu 1/30/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
81 100% 1.3.6.2 Install Active Directory Domain Services Role on Windows Server 2016
1 hr Thu 1/30/20 Thu 1/30/20
82 100% 1.3.6.3 Configure domain/forest for client C 1 hr Thu 1/30/20 Thu 1/30/20
83 100% 1.3.6.4 Configure AD structure: Users, OUs, Groups, etc.
2 hrs Thu 1/30/20 Thu 1/30/20
84 100% 1.3.6.5 Test Active Directory configurations 1 hr Thu 1/30/20 Thu 1/30/20
85 100% 1.3.6.6 M: Active Directory and Client C domain successfully configured
0 days Thu 1/30/20 Thu 1/30/20
86 100% 1.3.7 Client C: Remote Desktop Services Set Up 0.88 days Fri 1/31/20 Fri 1/31/20
87 100% 1.3.7.1 Create virtual machines for RDS 2 hrs Fri 1/31/20 Fri 1/31/20
88 100% 1.3.7.2 Install RDS Roles on Windows Server 2016 2 hrs Fri 1/31/20 Fri 1/31/20
89 100% 1.3.7.3 Configure RDS infrastructure 2 hrs Fri 1/31/20 Fri 1/31/20
90 100% 1.3.7.4 Test RDS Configurations 1 hr Fri 1/31/20 Fri 1/31/20
91 100% 1.3.7.5 M: Remote Desktop Services successfully configured
0 days Fri 1/31/20 Fri 1/31/20
92 100% 1.3.8 M: Client(s) Server Services set up completed 0 days Fri 1/31/20 Fri 1/31/20
93 100% 1.4 Corporate Side Server Services 5 days Fri 1/31/20 Fri 2/7/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
94 100% 1.4.1 Hyper-V Set Up 0.38 days Fri 1/31/20 Fri 1/31/20
95 100% 1.4.1.1 Install Hyper-V Role on Windows Server 2016
2 hrs Fri 1/31/20 Fri 1/31/20
96 100% 1.4.1.2 Configure Hyper-V services 1 hr Fri 1/31/20 Fri 1/31/20
97 100% 1.4.1.3 Test Hyper-V configuration 1 hr Fri 1/31/20 Fri 1/31/20
98 100% 1.4.1.4 M: Hyper-V successfully configured 0 days Fri 1/31/20 Fri 1/31/20
99 100% 1.4.2 Corporate: Active Directory Set Up 0.38 days Thu 2/6/20 Thu 2/6/20
100 100% 1.4.2.1 Create virtual machine for Active Directory 2 hrs Thu 2/6/20 Thu 2/6/20
101 100% 1.4.2.2 Install Active Directory Domain Services Role on Windows Server 2016
1 hr Thu 2/6/20 Thu 2/6/20
102 100% 1.4.2.3 Configure domain/forest for organization 1 hr Thu 2/6/20 Thu 2/6/20
103 100% 1.4.2.4 Configure AD structure: Users, OUs, Groups, etc.
1 hr Thu 2/6/20 Thu 2/6/20
104 100% 1.4.2.5 Test Active Directory configurations 1 hr Thu 2/6/20 Thu 2/6/20
105 100% 1.4.2.6 M: Active Directory and organization domain successfully configured
0 days Thu 2/6/20 Thu 2/6/20
106 100% 1.4.3 Corporate: Apache Web Server Set Up 0.88 days Thu 2/6/20 Thu 2/6/20
107 100% 1.4.3.1 Create virtual machine for web server 2 hrs Thu 2/6/20 Thu 2/6/20
108 100% 1.4.3.2 Install WAMPServer on Windows Server 2016
1 hr Thu 2/6/20 Thu 2/6/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
109 100% 1.4.3.3 Configure WAMPServer Apache settings: virtual hosts, access, SSL set up, etc.
3 hrs Thu 2/6/20 Thu 2/6/20
110 100% 1.4.3.4 Test WAMPServer configurations 1 hr Thu 2/6/20 Thu 2/6/20
111 100% 1.4.3.5 M: Apache Web Server successfully configured
0 days Thu 2/6/20 Thu 2/6/20
112 100% 1.4.4 Corporate: mySQL Database Set Up 1 day Thu 2/6/20 Thu 2/6/20
113 100% 1.4.4.1 Create virtual machine for web server 2 hrs Thu 2/6/20 Thu 2/6/20
114 100% 1.4.4.2 Install WAMPServer on Windows Server 2016
1 hr Thu 2/6/20 Thu 2/6/20
115 100% 1.4.4.3 Configure WAMPServer mySQL settings: access, SSL set up, etc.
2 hrs Thu 2/6/20 Thu 2/6/20
116 100% 1.4.4.4 Create database structure 2 hrs Thu 2/6/20 Thu 2/6/20
117 100% 1.4.4.5 Test WAMPServer configurations 1 hr Thu 2/6/20 Thu 2/6/20
118 100% 1.4.4.6 M: mySQL Database successfully configured
0 days Thu 2/6/20 Thu 2/6/20
119 100% 1.4.5 M: Corporate Server Services set up completed
0 days Fri 2/7/20 Fri 2/7/20
120 100% 1.5 Web Application Set Up 29.13 days Mon 2/3/20 Fri 3/13/20
121 100% 1.5.1 PowerShell Scripting 20.13 days Mon 2/3/20 Mon 3/2/20
122 100% 1.5.1.1 Develop PowerShell script to batch create user accounts for each client
3 days Mon 2/3/20 Wed 2/5/20
123 100% 1.5.1.2 Test account creation PowerShell script 1 hr Thu 2/6/20 Thu 2/6/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
124 100% 1.5.1.3 Develop PowerShell script to retrieve user account info from client's Active Directory for password notification
2 days Fri 2/14/20 Mon 2/17/20
125 100% 1.5.1.4 Test account info retrieval PowerShell script
1 hr Fri 2/14/20 Fri 2/14/20
126 100% 1.5.1.5 Develop PowerShell script to configure Auto Login to Remote Desktop Services forclients
2 days Thu 2/27/20 Fri 2/28/20
127 100% 1.5.1.6 Test Auto Login PowerShell script 1 hr Mon 3/2/20 Mon 3/2/20
128 100% 1.5.1.7 M: PowerShell scripts completed 0 days Mon 3/2/20 Mon 3/2/20
129 100% 1.5.2 mySQL Database Set Up 8.25 days Fri 2/7/20 Wed 2/19/20
130 100% 1.5.2.1 Design database structure 2 hrs Fri 2/7/20 Fri 2/7/20
131 100% 1.5.2.2 Configure database structure 3 days Fri 2/7/20 Wed 2/12/20
132 100% 1.5.2.3 Test and verify database structure 1 hr Fri 2/14/20 Fri 2/14/20
133 100% 1.5.2.4 Integrate database with PowerShell scripts 3 days Fri 2/14/20 Wed 2/19/20
134 100% 1.5.2.5 Test PowerShell integration 1 hr Wed 2/19/20Wed 2/19/20
135 100% 1.5.2.6 M: mySQL Database successfully configured
0 days Wed 2/19/20
Wed 2/19/20
136 100% 1.5.3 Web Application Pages 19.13 days Mon 2/17/20Fri 3/13/20
137 100% 1.5.3.1 Application Login Page 6.13 days Mon 2/17/20Tue 2/25/20
138 100% 1.5.3.1.1 Design web page structure 2 days Mon 2/17/20Tue 2/18/20
139 100% 1.5.3.1.2 Develop and code HTML structure for web page
2 days Wed 2/19/20
Thu 2/20/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
140 100% 1.5.3.1.3 Develop and code PHP elements for webpage
2 days Fri 2/21/20 Mon 2/24/20
141 100% 1.5.3.1.4 Test login page functionality 1 hr Tue 2/25/20 Tue 2/25/20
142 100% 1.5.3.1.5 M: Login Page completed 0 days Tue 2/25/20 Tue 2/25/20
143 100% 1.5.3.2 Request Credentials Page 6.13 days Fri 2/21/20 Mon 3/2/20
144 100% 1.5.3.2.1 Design web page structure 2 days Fri 2/21/20 Mon 2/24/20
145 100% 1.5.3.2.2 Develop and code HTML structure for web page
2 days Tue 2/25/20 Wed 2/26/20
146 100% 1.5.3.2.3 Develop and code PHP elements for webpage
2 days Thu 2/27/20 Fri 2/28/20
147 100% 1.5.3.2.4 Test request page functionality 1 hr Mon 3/2/20 Mon 3/2/20
148 100% 1.5.3.2.5 M: Request Page completed 0 days Mon 3/2/20 Mon 3/2/20
149 100% 1.5.3.3 Account and Password Status Page 6.13 days Mon 3/2/20 Tue 3/10/20
150 100% 1.5.3.3.1 Design web page structure 2 days Mon 3/2/20 Tue 3/3/20
151 100% 1.5.3.3.2 Develop and code HTML structure for web page
2 days Wed 3/4/20 Thu 3/5/20
152 100% 1.5.3.3.3 Develop and code PHP elements for webpage
2 days Fri 3/6/20 Mon 3/9/20
153 100% 1.5.3.3.4 Test status page functionality 1 hr Tue 3/10/20 Tue 3/10/20
154 100% 1.5.3.3.5 M: Status Page completed 0 days Tue 3/10/20 Tue 3/10/20
155 100% 1.5.3.4 User Credentials Page 5 days Thu 3/5/20 Wed 3/11/20
156 100% 1.5.3.4.1 Design web page structure 1 day Thu 3/5/20 Thu 3/5/20
157 100% 1.5.3.4.2 Develop and code HTML structure for web page
2 days Thu 3/5/20 Fri 3/6/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
158 100% 1.5.3.4.3 Develop and code PHP elements for webpage
3 days Mon 3/9/20 Wed 3/11/20
159 100% 1.5.3.4.4 Test credentials page functionality 1 hr Wed 3/11/20Wed 3/11/20
160 100% 1.5.3.4.5 M: Credentials Page completed 0 days Wed 3/11/20Wed 3/11/20
161 100% 1.5.3.5 Account Reset Page 5 days Thu 3/5/20 Wed 3/11/20
162 100% 1.5.3.5.1 Design web page structure 1 day Thu 3/5/20 Thu 3/5/20
163 100% 1.5.3.5.2 Develop and code HTML structure for web page
2 days Fri 3/6/20 Mon 3/9/20
164 100% 1.5.3.5.3 Develop and code PHP elements for webpage
3 days Tue 3/10/20 Thu 3/12/20
165 100% 1.5.3.5.4 Test credentials page functionality 1 hr Fri 3/13/20 Fri 3/13/20
166 100% 1.5.3.5.5 M: Credentials Page completed 0 days Fri 3/13/20 Fri 3/13/20
167 100% 1.5.3.6 M: Web Application Pages completed 0 days Fri 3/13/20 Fri 3/13/20
168 100% 1.5.4 M: Web Application Set Up successfully completed0 days Fri 3/13/20 Fri 3/13/20
169 100% 1.6 Client Side Security Set Up 30.25 days Fri 2/7/20 Fri 3/20/20
170 100% 1.6.1 Create virtual machine for pfSense 2 hrs Fri 2/7/20 Fri 2/7/20
171 100% 1.6.2 Install pfSense 1 hr Fri 2/7/20 Fri 2/7/20
172 100% 1.6.3 Open essential services ports 1 hr Fri 2/7/20 Thu 3/19/20
173 100% 1.6.4 Configure firewall and NAT rules 1 hr Fri 2/7/20 Thu 3/19/20
174 100% 1.6.5 Configure site-to-site VPN using IPSec 1 hr Thu 2/13/20 Thu 2/13/20
175 100% 1.6.6 Test site-to-site VPN connections 1 hr Thu 2/13/20 Thu 2/13/20
176 100% 1.6.7 Perform penetration and functionality tests 2 hrs Fri 3/20/20 Fri 3/20/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
177 100% 1.6.8 M: Security settings successfully configured 0 days Fri 3/20/20 Fri 3/20/20
178 100% 1.7 Corporate Side Security Set Up 35.25 days Fri 2/7/20 Fri 3/27/20
179 100% 1.7.1 Create virtual machine for pfSense 2 hrs Fri 2/7/20 Fri 2/7/20
180 100% 1.7.2 Install pfSense 1 hr Fri 2/7/20 Fri 2/7/20
181 100% 1.7.3 Open essential services ports 1 hr Fri 2/7/20 Fri 2/7/20
182 100% 1.7.4 Configure firewall and NAT rules 1 hr Fri 2/7/20 Fri 2/7/20
183 100% 1.7.5 Configure site-to-site VPN using IPSec 1 hr Fri 2/7/20 Fri 2/7/20
184 100% 1.7.6 Test site-to-site VPN connections 1 hr Fri 2/7/20 Fri 2/7/20
185 100% 1.7.7 Configure client-to-site VPN using OpenVPN 4 hrs Thu 2/27/20 Thu 2/27/20
186 100% 1.7.8 Test client-to-site VPN connection 1 hr Fri 3/6/20 Fri 3/6/20
187 100% 1.7.9 Perform penetration and functionality tests 2 hrs Fri 3/27/20 Fri 3/27/20
188 100% 1.7.10 M: Security settings successfully configured 0 days Fri 3/27/20 Fri 3/27/20
189 100% 1.8 Documentation 6 days Thu 3/26/20 Thu 4/2/20
190 100% 1.8.1 Develop User Manual 6 days Thu 3/26/20 Thu 4/2/20
191 100% 1.8.2 Develop Administrator Manual 6 days Thu 3/26/20 Thu 4/2/20
192 100% 1.8.3 Develop Final Project Report 6 days Thu 3/26/20 Thu 4/2/20
193 100% 1.8.4 Develop Final Project Presentation PowerPoint
6 days Thu 3/26/20 Thu 4/2/20
194 100% 1.8.5 M: Documentation completed 0 days Tue 3/31/20 Tue 3/31/20
195 75% 1.9 Wrap-Up Meeting 6 days Fri 3/27/20 Fri 4/3/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: FINAL Capstone Projec
Date: Fri 4/3/20
ID % Complete Task
Mode
WBS Task Name Duration Start Finish
196 100% 1.9.1 Plan Wrap-Up Meeting 1 hr Fri 3/27/20 Fri 3/27/20
197 0% 1.9.2 Attend Meeting 0.02 days Fri 4/3/20 Fri 4/3/20
198 0% 1.9.2.1 Agenda Adoption 1 min Fri 4/3/20 Fri 4/3/20
199 0% 1.9.2.2 Meeting Minutes Adoption 1 min Fri 4/3/20 Fri 4/3/20
200 0% 1.9.2.3 Deliver Final Product 11 mins Fri 4/3/20 Fri 4/3/20
201 0% 1.9.2.4 Project Debrief 7 mins Fri 4/3/20 Fri 4/3/20
202 0% 1.9.2.5 M: Wrap-Up Meeting Completed 0 days Fri 4/3/20 Fri 4/3/20
203 0% 1.9.3 M: Meetings completed 0 days Fri 4/3/20 Fri 4/3/20
204 0% 1.10 M: Capstone Project Completed 0 days Fri 4/3/20 Fri 4/3/20
18 23 28
November 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 13
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
Nino Angelo Cubero
1/9
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 14
Project: FINAL Capstone Projec
Date: Fri 4/3/20
1/9
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/10
1/10
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
1/16
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 15
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Al George Regaspi
Al George Regaspi
Al George Regaspi
1/24
1/24
1/24
1/24
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
1/24
1/20
James Mathew Nefulda
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 16
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
1/17
1/17
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/21
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/24
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 17
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/24
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/30
James Mathew Nefulda
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 18
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/30
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/31
1/31
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 19
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/31
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
2/6
James Mathew Nefulda
James Mathew Nefulda
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 20
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
2/6
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
2/6
2/7
Nino Angelo Cubero
Nino Angelo Cubero
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 21
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
3/2
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
2/19
Nino Angelo Cubero
Nino Angelo Cubero
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 22
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Nino Angelo Cubero
Nino Angelo Cubero
2/25
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
3/2
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
3/10
Nino Angelo Cubero
Nino Angelo Cubero
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 23
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Nino Angelo Cubero
Nino Angelo Cubero
3/11
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
3/13
3/13
3/13
James Mathew Nefulda
James Mathew Nefulda
Al George Regaspi
Al George Regaspi
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 24
Project: FINAL Capstone Projec
Date: Fri 4/3/20
3/20
James Mathew Nefulda
James Mathew Nefulda
Al George Regaspi
Al George Regaspi
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
3/27
Nino Angelo Cubero
James Mathew Nefulda
James Mathew Nefulda
Al George Regaspi
3/31
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 25
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
4/3
4/3
4/3
28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2
November 2019 December 2019 January 2020 February 2020 March 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 26
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
Nino Angelo Cubero
1/9
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 27
Project: FINAL Capstone Projec
Date: Fri 4/3/20
1/9
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/10
1/10
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
1/16
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 28
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Al George Regaspi
Al George Regaspi
Al George Regaspi
1/24
1/24
1/24
1/24
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
Al George Regaspi
1/24
1/20
James Mathew Nefulda
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 29
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
1/17
1/17
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/21
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/24
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 30
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/24
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/30
James Mathew Nefulda
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 31
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/30
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/31
1/31
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 32
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
1/31
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
2/6
James Mathew Nefulda
James Mathew Nefulda
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 33
Project: FINAL Capstone Projec
Date: Fri 4/3/20
James Mathew Nefulda
James Mathew Nefulda
2/6
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
2/6
2/7
Nino Angelo Cubero
Nino Angelo Cubero
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 34
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
3/2
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
2/19
Nino Angelo Cubero
Nino Angelo Cubero
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 35
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Nino Angelo Cubero
Nino Angelo Cubero
2/25
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
3/2
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
Nino Angelo Cubero
3/10
Nino Angelo Cubero
Nino Angelo Cubero
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 36
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Nino Angelo Cubero
Nino Angelo Cubero
3/11
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
3/13
3/13
3/13
James Mathew Nefulda
James Mathew Nefulda
Al George Regaspi
Al George Regaspi
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 37
Project: FINAL Capstone Projec
Date: Fri 4/3/20
3/20
James Mathew Nefulda
James Mathew Nefulda
Al George Regaspi
Al George Regaspi
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
James Mathew Nefulda
3/27
Nino Angelo Cubero
James Mathew Nefulda
James Mathew Nefulda
Al George Regaspi
3/31
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 38
Project: FINAL Capstone Projec
Date: Fri 4/3/20
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
Al George Regaspi,James Mathew Nefulda,Nino Angelo Cubero
4/3
4/3
4/3
2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5
March 2020 April 2020 May 2020 June 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 39
Project: FINAL Capstone Projec
Date: Fri 4/3/20