fidic
-
Upload
viorel-nitu -
Category
Documents
-
view
100 -
download
12
Transcript of fidic
12/11/2009
CLAIMS &
DISPUTES RESOLUTION
UNDER FIDIC 99REDBOOK
Suranga Jayasena
Senior Lecturer
Department of Building Economic
University of Moratuwa
CLAUSE 20
12/11/2009
CLAUSE 20
... is all about Claims and Disputes Resolution
pages 58 to 62
CLAIM FLOWCHART
Claim Event,
Circumstance
arisen
Clause 20.1
Contractor gives notice
to the Engineer
describing the event or
circumstance giving
rise to the Claim,
within 28 days
Contractor becomes
aware or should have
become aware of the
Claim
Yes
No Claim
No
12/11/2009
Clause 20.1
Contractor gives notice
to the Engineer
describing the event or
circumstance giving
rise to the Claim,
within 28 days
Contractor becomes
aware or should have
become aware of the
Claim
Clause 20.1
Claim Fails
The Employer is
discharged from all
liability in connection
with the Claim
No
Clause 20.1
Contractor provides
Engineer with detailed
particulars and within
42 days and final claim
within 28 days after
end of effect if
continuing event and
complies with other
contractual
requirements
Yes
Clause 20.1
Claim approved may be
limited, if failure has
prevented or prejudice
the proper
investigation of Claim
No
Clause 20.1
Contractor provides
Engineer with detailed
particulars and within
42 days and final claim
within 28 days after
end of effect if
continuing event and
complies with other
contractual
requirements
Clause 20.1
Claim approved is
limited, if failure has
prevented or prejudice
the proper
investigation of Claim
No
Dispute
No
Clause 20.4
Contractor is satisfied
with Engineer’s
decision
Yes
12/11/2009
Clause 20.1
Contractor provides
Engineer with detailed
particulars and within
42 days and final claim
within 28 days after
end of effect if
continuing event and
complies with other
contractual
requirements
Clause 20.1
The Engineer
(dis)approves, or gives
opinion on the Claim
within 42 days
Yes
Clause 20.1
The Engineer
(dis)approves, or gives
opinion on the Claim
within 42 days
Clause 20.4
Contractor is satisfied
with Engineer’s
decision
Yes
Dispute
No
YesContractor does not
tolerate Engineer’s
delay in decision
No
Clause 20.4
Contractor is satisfied
with Engineer’s
decision
Yes
Clause 20.1
The Engineer
(dis)approves, or gives
opinion on the Claim
No NoNo
12/11/2009
Certification
Valuations
Instructions Dispute
Determination
Opinion
20.4
CLAUSE 20
... is all about Claims and Disputes Resolution
However ... Typical sequence shown in
beginning of the document is useful
Recall...
12/11/2009
TYPICAL SEQUENCE OF DISPUTE EVENTSENVISAGED IN CLAUSE 20
8.1Commencement Date
20.4A Party refers a dispute to the DAB
20.6A Party initiate arbitration
20.4A Party issues a “notice of dissatisfaction”
Parties present submissions to the
DAB
20.2Parties appoint the DAB
Amicable settlement
<28d <28d<84d >56d
Arbitrators appointed
DAB gives its decision
20.2
PARTIES APPOINT THE DAB
� Within 28 days of Date of Commencement?
� ... by the date stated in Appendix to Tender.
(28 days in example in sample forms)
� Guidance for Particular Conditions – “It is preferable,
but not essential, to agree before the Letter of
Acceptance”
� A list of potential members may be included in tender
12/11/2009
20.2
PARTIES APPOINT THE DAB ... CONTINUED ...
� Parties jointly appoint a DAB
� DAB comprises one or three member stated in Appendix
� If not stated nor agreed, it shall be three
� If three, each party nominate one member for
approval of other party, two members appoint
chairman
� Each part pay one-half of DAB remuniration
20.2
PARTIES APPOINT THE DAB ... CONTINUED ...
� What if parties fail to agree DAB?
� An appointing entity is named in Appendix to Tender 20.3
� What if date of appointment not stated in Appendix?
� Might go for “ad-hoc” DAB > i.e. only appointed if and
when a particular dispute arises.
� What if appointing entity not stated in Appendix?
� ?
12/11/2009
20.2
PARTIES APPOINT THE DAB ... CONTINUED ...
� Parties may appoint members to be available to
replace members resign or be terminated
� Otherwise, replacement be similar to new
appointment
� Termination shall only be by mutual agreement of
Parties
� usually DAB expires when discharge become effective
20.2
PARTIES APPOINT THE DAB ... CONTINUED ...
� DAB members must be selected carefully, because
� Parties empowers the DAB to reach decisions with which
they undertake to comply, and
� A DAB member cannot normally be removed except with
the agreement of both parties (20.2 last para)
12/11/2009
A “FULL-TERM” DAB
� Appointed before Contractor commence Works
� Visit the Site on a regular basis
� Also available to assist in avoiding disputes during
these visits
� 20.2 Para 7 – “if at any time the Parties so agree, they may
jointly refer a matter to DAB for it to give its opinion. Neither
party shall consult DAB on any matter without the
agreement of the other party
DAB: “FULL-TERM” OR “AD-HOC”
� Red Book General Conditions are for “full-term” – see 20.2
� Parties may decide on appropriate model by
considering (among other things):
� Extent of Contractor’s Activities off-site – paying DAB may not
economical
� Extent of uncertainties in scope of works – underground
tunnelling – a full-term DAB most appropriate
� Extent of Variations expected – full-term
� Magnitude of the Contract – No. of DAB members 1 or 3
12/11/2009
20.4
OBTAINING ADB’S DECISION
� 20.4 Reads “if a dispute (of any kind whatsoever)
arises between the Parties ....
� in connection with or arising out of the Contract
or the execution of the Works
� including any dispute as to any certificate,
determination, instruction, opinion or valuation
of the Engineer ...
� may refer the dispute in writing
� to the DAB for decision”
20.4
OBTAINING ADB’S DECISION ... CONTINUED ...
� No matter can be referred to DAB unless it is in
dispute
� but, no formal notice of dispute required
� If matter is still in discussion or only interim
determination given
other party may assert that “no dispute”
� DAB to find if dispute has arisen – see if
agreement achieved under sc 3.5
12/11/2009
THE MATTER HAS DEVELOPED INTO A
DISPUTE
When ...
� Final determination rejected
� Discussions discontinued without agreement
� Party decline to participate in discussion
� Party decline to reach agreement as per sc3.5
� So little progress being achieved that it is clear
that agreement is unlikely
20.4
WRITTEN REFERENCE TO DAB
The Written Submission by Claimant
� For the decision of DAB
� Describes the situation
� Sets out the principles of the matter in dispute
� What Claimant wishes the DAB’s decision to be
� A copy must be passed to the other party
(Respondent) and Engineer
12/11/2009
20.4
DAB’S DECISION
� within 84 days after receiving the original
reference, or
� within such other period as may be proposed by
the DAB and approved by both parties
� approvals must not be unreasonably withheld or
delayed
� for complex matters DAB may propose to give
decisions in stages
� shall be reasoned and stated that it given under
sub-clause 20.4
20.4
DAB’S DECISION ... CONTINUED ...
� Note that DAB decision shall be admissible in
evidence in arbitration. sc 20.6
� Therefore well reasoned decision preferred
� The Contractor shall execute the Works while
DAB proceeding.
� The decision shall be binding on both parties
12/11/2009
20.4
DISSATISFACTION ON DAB’S DECISION
� The Party must give a formal “notice of
dissatisfaction” within 28 days.
� It establishes the claimant the right to commence
arbitration.
� Unless the notice given within 28 days, decision
become final and binding.
20.5
AMICABLE SETTLEMENT
� During first 56 days after notice
� Parties should attempt amicable settlement
� DAB should not get involve in amicable
settlement procedure.
� If no amicable settlement (or attempt thereto),
.....
the dispute shall be finally settled by
international arbitration sc 20.6
12/11/2009
20.7
WHAT IF...
� Formal notice of dissatisfaction NOT given,
� DAB decision became final and binding
� a Party FAILS to comply with decision
� Other Party may refer THIS FAILURE directly
to arbitration,
without having to refer again to DAB or try
amicable settlement
20.8
WHAT IF...
� a dispute occurs, but
no DAB is in place, either by
� expiry or otherwise
� the dispute may be referred directly to
arbitration under sc 20.6
� However, there is still room for amicable
settlement
the word ‘otherwise’ shall be used to
cover failure of appointing DAB due to
defect in document. E.g. “the
appointing entity is non-existent”
12/11/2009
20.6
ARBITRATION
� Unless otherwise agreed by both parties
� Rules of International Chamber of Commerce
� Three arbitrators
� Language be language defined in 1.4
� Shall commence before or after completion
� Shall not prevent executing obligation of contract
during the proceedings
::: BREAK :::
1101001011010110101010101010100100010111010011001100110
0101010010100101010011110101011101010110110101000101001
0110010101001111010010011011010111010111100010110011101
1001010010101001010100101111101001101010100100101001111
1001110101001001011111100010101111111001101001010100101
011110100101010100101010110100 0 1 0 0 0 0
We’ll try something practical now
12/11/2009
CASEPROPOSED SCHOOL BUILDING FOR SEEVALI COLLEGE
Variation Instructions were issued changing the Ground Floor
walls to block work from brick work which was in original
contract. No block work was found in ground floor level in the
original contract but upper floor partition walls in the original
contract was similar type.
Contractor asked for the same rate from the upper floor block
work but the Engineer rejected it and approved rate of his own
schedule of prices (used for Engineer’s Estimate) which is less
than claimed rate.
TASK 01
Write the cover letter for referring the matter to DAB
You may make necessary assumptions
12/11/2009
<< Date >>
<< Adjudicator1 >> - chairman (member)
<< Adjudicator2 >> - member
<< Adjudicator3 >> - member
Dispute Adjudication Board
Proposed School Building for Seevali College
<< Address >>
Dear Sirs,
REFERENCE TO ADJUDICATION
...............
.....
We are not in agreement with the rates determined by the Engineer for
Block work (varied item) at Ground Floor Level we carried out under the
above contract. Therefore a dispute has arisen between the parties to the
above Contract and pursuant to Sub-clause 20.4 we refer the dispute to
DAB for its decision. The detail claim is attached herewith.
Thank you.
Yours faithfully,
<< Contractor >>
cc: << Employer >>
<< Engineer >>
12/11/2009
TASK 02
Write the Adjudication Submission
You may make necessary assumptions
TASK 02 - TIPS
How much to write - Keep it short but clear
Format – Not strict, but you may use something similar to
arbitration submissions
Order –
Introduce parties and contract
DAB appointed
Contractual provision 1,
Contractual provision 2,
Occurance, your statement
........
Dispute
Your claim for decision by DAB
12/11/2009
In the matter of Adjudication
Dispute Between
ABC Construction,
No 9, Road Lane
Colombo 20
Contractor/Claimant
and
Seevali College,
111/1, Lane Road
Colombo 19.
Employer/Respondent
STATEMENT OF CLAIM
........
1. The Contractor is a civil engineering contractor registered under
ICTAD as a Grade C-5. The Employer is a public school in Colombo.
2. By a contract dated 09th October 2009 (‘the Contract’), The Contractor
undertook to construct and complete certain building works, namely
“the Construction of Proposed School Building for Seevali College”
(‘the Works’) in consideration for payment by the Employer on
measure and pay basis without price fluctuation adjustment for the
priced bills of quantities bid by the contractor, at the time and in the
manner prescribed by the contract.
12/11/2009
3. The Contract Incorporates the FIDIC Conditions of Contract for
Construction, First Edition 1999 (‘the FIDIC Conditions’).
4. The Dispute Adjudication Board (‘the DAB’) was appointed by a
tripartite agreement signed on 15th October 2009.
5. Sub-clause 13.1 of the FIDIC Conditions provides that Variations may
be initiated by the Engineer and the Contractor shall execute and be
bound by each Variation.
6. On 28th October during a site visit, the Engineer instructed a
Variation changing all ground floor walls to block work from brick
work specified in the Contract.
12/11/2009
7. Sub-clause 3.3 of the FIDIC Conditions provides that in the event
Engineer gives oral instructions the Contractor shall confirm the said
instruction by writing.
8. Sub-clause 13.3 of the FIDIC Conditions provides that each Variation
shall be evaluated in accordance with Clause 12 [Measurement and
Evaluation].
9. Sub-clause 12.3 of the FIDIC Conditions provides that the appropriate
rate for an item shall be the rate specified for similar work.
10.The Contractor confirmed the Variation instructions and notified the
applicable rate to be the rate of similar work in the Contract – BOQ
Item 2.34: Block Work Walls at Second Floor level, by his letter to the
Engineer dated 01st November 2009.
12/11/2009
11.The Contractor included the block work quantity with applicable rate
to its Interim Statement dated 31st December 2009.
12.Sub-clause 14.6 of the FIDIC Conditions provides that the Engineer
shall issue an Interim Payment Certificate which shall state the
amount which the Engineer fairly determines to be due.
13.The Engineer, in the Interim Payment Certificate, had not certified
the rate applied for Variation and had determined a lower rate.
14.The Engineer failed to certify payment to the Contractor of sums to
which it is entitled pursuant to the said Sub-clause 12.3; which sums
amount to Rs. 115,000.00.
PARTICULARS
<<< Include a brief calculation here, annex if there are detailed calculations>>
15.Accordingly, the Contractor claims Rs. 115,000.00 under Sub-clause
12.3 of the Contract, plus interest thereon at the rate of three
percentage points above the discount rate of the Central Bank of Sri
Lanka, compounded monthly, pursuant to Sub-clause 14.8 of the
Contract.
12/11/2009
16.I certify on behalf of the Contractor that the facts stated in this
Statement of Claim are true to the best of my knowledge and belief.
..........................................................
Muralitharan, M.
Project Coordinator
ABC Construction
No 9, Road Lane
Colombo 20
WELLWELL--DONEDONE