Gas Electric Partnership Lessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein – Project Director (Compression)

Transcript of FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold...

Page 1: FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein –Project Director (Compression) CS Number ADDL STA HP PL SUCT LOOP

Gas Electric PartnershipLessons Learned PresentationFGT Phase 8 Project     2011

Arnold Eisenstein – Project Director (Compression)

Page 2: FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein –Project Director (Compression) CS Number ADDL STA HP PL SUCT LOOP
Page 3: FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein –Project Director (Compression) CS Number ADDL STA HP PL SUCT LOOP

CS Number

ADDL STA HP PL SUCT LOOP MCCUNIT HP PL DISC LOOP AUX GEN SIZE

UNIT TYPE SUCT HDR FT - OD FG SYSTEMUNIT COST $MM DISCH HDR FT - OD Air SYSTEMPRESENT FLOW SUCTION SCRUBBER FIRE & GAS DETECTION

ADD'L FLOW FIN-FAN 3 BAYS ESD SYSTEMSTA DESIGN PRESSURE UNIT LL OD ELEC. BSD SYSTEM

ADDIT'L SITE , AC NO. LL VALVES ESD PANELADD SITE FT X FT SURGE VALVE " GROUNDING

COMP BUILDING FT X FT UNIT RECYC LINE FT GROUND BEDPCR BUILDING FT X FT UNIT RECY OD TRANSFORMEREOPS BUILDING FT X FT RECYCLE VALVE " POWER FEED FT

STA ROADS FT STA RECYC LINE FT UPS SYSTEMFENCE & GATE STA RECYC VALVE " AREA LIGHTS

FENCE FT UNIT SILENCER LIGHTNING PROTECTIONPILING STA SILENCER

GRADING PIPE PIERS Station BLOWDOWNSITE FILL NOISE WALL FT TOOLS

GRAVELEnvironmental EMISSIONS

MITIGATION OPS TRAININGFOUNDATIONS

Facility Check List

Page 4: FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein –Project Director (Compression) CS Number ADDL STA HP PL SUCT LOOP

ESTIMATE ASSUMPTIONS• Sta. 15A• Install a Solar Titan 130 gas fired turbine with a Solar C65 compressor (20.5k hp) in a separate 

50’ x 80’ compressor building. Building will be equipped with fire/gas detection equipment for ESD/BSD system. Due to poor soil conditions, piling will likely be required.

• Purchase additional 15 acre site to accommodate the added unit at the existing compressor station. Civil improvements such as grading, fencing and roads for the additional property are included in the estimate.

• Install a 14’ x 50’ Process Control Room (PCR) enclosure. PCR enclosure to have MCC, UPS, and ESD/BSD control systems.

• Install new additional station gas coolers for additional capacity• Install new gas fired standby generator for incremental station loads.• Install area lighting and station grounding systems.• Install unit and expand station control and instrumentation system.• Install approximately 500’ of 36” station suction and discharge piping from the unit headers 

to the 1,333 psig mainline piping.• Install suction scrubber with block valves and gas aftercoolers on discharge piping.• Install unit suction and discharge valves and piping, unit surge valves, and station recycle 

valves and piping.• Install unit and station vent silencers.• Install fuel gas conditioning system for the gas fired turbines.• Purchase spare parts needed to operate the station.• Install 250’ soundwall• Retrofit two existing reciprocating engines for emissions mitigation. Work to include re‐

aeroing existing turbochargers, installation of jet cells, and upgrading of engine intercoolers.

Page 5: FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein –Project Director (Compression) CS Number ADDL STA HP PL SUCT LOOP

Florida Gas Transportation Company – Phase VIIIProject Execution Plan

Table of ContentsSection Description Page NumberExecutive Summary 11. Project Description 52. Corporate and Business Goals of the Project 63. Project Objectives  74. Scope of Work 85. Organization Plan 96. Contractual Plan 117. Cost Management Plan and Project Budget 148. Schedule Management Plan 239. Overall Milestone Schedule 2610. Risk Management Plan 2711. Engineering Management Plan 2712. Value Engineering Plan 4613. Right‐of‐Way Management Plan 4714. Material Management Plan 4815. Construction Feasibility Plan 5316. Construction Management Plan 5417. Environmental Management Plan 5918. Mechanical Completion Plan 6119. Quality Management Plan 6720. Information Management Plan 7021. Safety and Security Plan 7222. Contingency Management Plan 73

I.  Appendix I ‐ Detail Description and Location of FacilitiesII. Appendix II – Project Plot Plans and P&ID’s

Page 6: FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein –Project Director (Compression) CS Number ADDL STA HP PL SUCT LOOP
Page 7: FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein –Project Director (Compression) CS Number ADDL STA HP PL SUCT LOOP
Page 8: FGT Phase 8 Lessons Learned PresentationLessons Learned Presentation FGT Phase 8 Project 2011 Arnold Eisenstein –Project Director (Compression) CS Number ADDL STA HP PL SUCT LOOP