FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING...

61
FERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board Silos Project Background Accelerated Schedule Waste Retrieval Silos 1 and2 Silo 3 Question and Answer Session 8:30 p.m. Adjourn Gary Stegner Jim Bierer Nina Akgunduz Ray Corradi Bruce Schweitzer John North Doris Edwards Panel I - Graphics # 7507.0A 4102

Transcript of FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING...

Page 1: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

FERNALD SILOS PROJECT PROGRESS BRIEFING

April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board Silos Project Background Accelerated Schedule Waste Retrieval Silos 1 and2 Silo 3 Question and Answer Session

8:30 p.m. Adjourn

Gary Stegner Jim Bierer Nina Akgunduz Ray Corradi Bruce Schweitzer John North Doris Edwards Panel

I - Graphics # 7507.0A 4102

Page 2: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILOS PROJECT Background H 2000

May H Rocky Mountain Remedial Services began site preparation construction for Silo 3 project

June H Foster Wheeler Environmental Corporation began site preparation and construction on the Waste Retrieval Transfer Tank Area and Radon Control System Building

July

December 0 DOE awarded site closure contract to Fluor Fernald and teaming partners Jacobs Engineering Group and

Record of Decision (ROD) Amendment signed

Duratek Graphics # 75W.SA 4/02

Page 3: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

. .,.. . - > .

SILOS PROJECT Background e 2001

January Rocky Mountain Remedial Services subcontract terminated

April e Jacobs Engineering Group begins Silos 1 and 2 conceptual design

June 0 Foster Wheeler Environmental Corporation subcontract terminated. Fluor Fernald assumed AWR work with Jacobs Engineering Group as design authority

June e Began Silo 3 Preeconceptual design d)oooq)3 8,s , ‘5 d . $ ’ ’c’

- \ * c Graphics # 75WSB 4/02 ..

Page 4: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILOS PROJECT Background H 2001 (Cont.)

July/August H DOE completed the Site Closure Contract (2009) Baseline Review

September H Jacobs Engineering Group completed Silos 1 and 2 conceptual design

Fluor Fernald and DOE agreed to 2006 closure and rebaseline

December

Graphics # 7507.5C 4/02

I '

Page 5: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SIL,OS PROJECT Background H 2002

January H Fluor Fernald completed Transfer Tank Area concrete work

January Jacobs Engineering Group completed Silo 3 conceptual design

March 0 Fluor Fernald completed two transfer tanks and the concrete building that will house the Radon Control System

March/April H DOE in process of reviewing the 2006 Closure Baseline

~ O O O d ) ~ S , LL q . - .. < . 6 . . Graphics # 7507.5D 4/02

Page 6: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

Graphics # 7507.3A 4/02

ACCELERATED SCHEDULE

Why Accelerate to 2006?

Reduce public risk

Reduce occupational exposure

Improve project efficiency

Reduce total cost to taxpayers

. ...

Page 7: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

ACCELERATED SCHEDULE

Ground Rules for Acceleration

. Maintain safety

Maintain planning

Do not compromise scope

Accommodate minor changes by making some design components adaptable

Build as parts of design become ready

Graphics # 7507.3B 4/02

Page 8: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

ACCELERATED SCHEDULE

What Changed in Silos?

Fluor changed project delivery methods to achieve closure

in 2006

New baseline removed funding constraints

Implemented a rigorous constructability process with an experienced staff

Planned to carefully coordinate start of construction with completion of design for each phase

Graphics # 7507.3C 4/02

Page 9: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

ACCELERATED SCHEDULE Project Delivery Change

I

Previous Bid I I I I Approach I

I I

m " " " I " I " ~ " I I D " ~ . I

I Design I Current I I Approach

I

I Build Bid

L I I " ' I ' I I I ' I ' I . I ' I ' I - ' I D - ' - -

I d - I I I I I

II

Graphics # 75073D 4/02

Page 10: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

e

e

e

e

e

e

e

" * L r . 9 2 0 9

ACCELERATED SCHEDULE

Benefits of Fast TrackDesigncBuild

Focuses engineering efforts on construction priorities

Allows for early identification of issues without cascade effects

Takes advantage of interactive design and construction involvement

Decreases material staging space needs

Offers resource leveling opportunities to meet project priorities

Allows better quality control for discrete tasks

Allows for wellcplanned project acceleration

I

Graphics # 7507.3E 4/02

Page 11: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

ACCELERATED SCHEDULE Risks of Work Package Execution

To avoid late equipment changes: must get approved information and vendor installation support

To avoid lack of interface definition: must perform crossediscipline checks and use experienced constructability planners and package owners

Graphics # 7507.3F 4/02

Page 12: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

WASTE RETRIEVAL Major Components

Radon Control System (RCS) Bridges over Silos 1 and 2

Silos 1 and 2 sluicing and slurry pump modules

Silos Waste Retrieval System pipe rack

Transfer Tank Area (TTA)

Page 13: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

WASTE RETRIEVAL Radon Control System Components

Fans

Desiccant dryers

Carbon be.ds

Exhaust stack

Electrical, mechanical, instrument and control support systems

Graphics # 7507.6B 4/02

Page 14: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

RADON CONTROL SYSTEM DESICCANT DRYER

Graphics # 7507.6C 4/02 Photo # 7385-Dl232 OQ0.0%4 ,

.'I _ - - . .*y

Page 15: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

; - & . 'ri 1 F

4 2 0 9

RADON CONTROL SYSTEM CARBON BEDS

~

Graphics # 7507.6D 4/02 Photo # 7385-Dl222

Page 16: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

RADON CONTROL SYSTEM CONSTRUCTION

., .

+ . Graphics # 7507.6E 4/02, Photo # 7385D988

Page 17: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

RADON CONTROL SYSTEM TANK PLACEMENT

.

-1 .. Graphics # 7507.6F 4/02 Photo # 7385D903

Page 18: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

FOUNDATIONS FOR CABLE TRAY SUPPORTS

Graphics # 7507.66 4/02 Photo # 7385-Dl235 . 800018

Page 19: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

WASTE RETRIEVAL How the 'Radon Control System Works

Filters air in the silos headspace to remove radon c

Air circulates through two desiccant dryers

Air then circulates through four carbon beds which adsorb radon

Air returns to the silos or is vented through the

exhaust stack

Graphics # 7507.6H 4/02

Page 20: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

WASTE RETRIEVAL Radon Control System Operation

Phase 1 during bridge construction and material removal components installation

Phase 2 during material transfer from Silos 1 and 2 to the transfer tanks

Phase 3 during material treatment

, I Graphics # 7507.61 4/02

I

. -. 42 .09 ' , ' ! , , ,.

Page 21: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

WASTE RETRIEVAL Radon Control System Statistics

Operates at up to 2,000 cubic feet per minute

Will condition air to 40 degrees Fahrenheit

Will condition air which contains up to 15 percent relative humidity

Each 1,500Hcubic~foot carbon bed contains 45,000 pounds of carbon

Graphics # 7507.6K 4/02

Page 22: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

Graphics # 7507.6L 4/02

WASTE RETRIEVAL ’ r;?,.. 4 2 0 8 . : . . . . . . . .

How Waste Retrieval Works

Bridges over Silos 1 and 2 support sluicing and pump modules

Sluice jets inside silos mix waste material with water

Slurry pumps draw material through double containment piping into transfer tanks

008022 ,. . . ... t.’ . .

. , .7 -,

Page 23: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

WASTE RETRIEVAL

Waste Retrieval Statistics

Silos 1 and 2 contain a total of 1.8 million

gallons of waste

Each of the four transfer tanks holds 750,000 gallons; total of 3 million gallons

Each of the two bridge spans is 175 feet long

Graphics # 7507.6M 4/02

Page 24: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

c 4 2 0 9 TRANSFER TANK AREA

. I I----

Page 25: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

I

- . I * TRANSFER TANK CONSTRUCTION + . ‘ ” - -

.t-17 - *. - Graphics # 7507.6P 4/02 Photo # 7385D1095 . ..

Page 26: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

t . *' ' 4 2 0 s TRANSFER TANK AREA e4- , ,

ROOF ASSEMBLY CONSTRUCTION

Graphics # 7507.6Q 4/02 Photo # 7385-Dl271 '1

Page 27: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

I .. 0 e . 1

TRANSFER TANK ROOF ASSEMBLY LIFT

- Graphics # 7507.61 4/02 Photo # 7385-Dl306

Page 28: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

TRANSFER TANK ROOF ASSEMBLY WELDING

142..c L 4 -. 4 -

Graphics # 7507.6 4/02 Photo # 7385D1332

Page 29: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

WASTE RETRIEVAL Waste Retrieval Construction Schedule

I

August 2002

November 2002

December 2002

August 2003

Crews to complete construction on Radon Control System

I

1

Radon Control System startzup. Crews complete Silos Waste Retrieval System pipe rack construction

Start Silo 1 and 2 bridge construction

Sluice and slurry system construction

Graphics # 7507.6T 4/02

to

Page 30: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILOS 1 AND 2

Agenda

2006 baseline approach

Facilities/process design overview

Engineering/Procurement/Construction approach

Issues/risks

Look ahead

Page 31: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

, . i: ..

' r - 'a2Q I

SILOS 1 AND 2 2006 Baseline Approach I I

I

Dewatering and chemical stabilization/solidification I

(unchanged) I

I Treated grout product placed in sealed steel containers (unchanged)

Gondola cars ship waste containers by rail to licensed 1

commercial disposal facility 1

Treatment operations overlap Waste Retrieval operatioas I

by 3 4 months I

0 - Treatment operations begin February 2005 and end

February 2006 Graphics # 7507.18 4/02

Page 32: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation
Page 33: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

1 ~

I

I

I I I

I

I

i i

3". '7 ~ ;-;:a . . -

Graphics # 7507.11) 4/02

Page 34: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILOS 1 AND 2 WASTE 2

I'. I

0 9

Page 35: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILOS 1 AND 2 WASTE ... i ' 4.2,0..9 . z .

TREATMENT FACILITY

Graphics # 7507.1F 4/02

Page 36: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

GRAPPLER AND GRAPPLER LIFT ' F * - 42.09

Graphics # 7507.16 4/02 Photos # 7774-Dl & 7774D2 Video Grabs 0 o.o\fI3ci:~ '1 c* :_> L.

Page 37: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILOS 1 AND 2 a ' .

. . I _ -

Engineering/Procurement/Construction Approach

In April 2002, DOE and CAT will review and comment upon the Preliminary Design Package

Procurement of major process equipment and systems will begin in April 2002

Final Design issued as discrete packages to support logical sequencing of construction

Final Design packages will be complete by February 2003

Crews will complete construction in June 2004 000037 - I I

Graphics # 7507.18 4/02

Page 38: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILOS 1 AND 2

Early Procurement Packages

3 2 0 Q L -

' . . .

Award Equipmends ys tern

May 2002 Clarifier system

June 2002 Tank agitators

July 2002 Product mixers J

July 2002 Container handling, filling and lidding systems

Page 39: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

Begin

42 :. 0 g.,.,,

SILOS 1 AND 2

Early Construction Packages

Package

July 2002 Warehouse

September 2002 Rail facilities

October 2002 Treatment facility mat foundation

Graphics # 7507.1K 4/02

Page 40: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILOS 1 AND 2

Issues and Risks

4 2 0 9 -is-

ROD amendment and licensing of commercial disposal facilities

Availability of rail cars and owsite rail facilities

Procurement and construction prior to total design completion and Remedial Design (RD) package approval

Graphics # 7507.1L 4/02

Page 41: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

e

.e

e

e

e

SILOS 1 AND 2

Look Ahead

April 2002 Preliminary Design Package review

May 2002 Begin equipment/system procurement

July 2002 Begin early construction packages

August 2002 .Submit draft RD Package to EPA (milestone date: December 20, 2002)

February 2003 Complete final design

Graphics # 7507.1M 4/02

Page 42: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Agenda

Material properties

Remediation design approach

Shipping and packaging

Engineering/procurement/construction (EPC) approach

Look ahead

4 2 0 9 . L

Page 43: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Material

5 100 cubic yards metal oxide

DOE classification 1 l (e)2 byproduct material

Stored in 8O-foot diameter silo which is a little

over 26 feet high Calcined, incinerated, noncexplosive material containing no organics

Brown powder, rustclike because of metals, behaves like flyash or salts

Graphics # 7507.2B 4/02

Page 44: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3 WASTE MATERIAL -. 4 2 0 9

Graphics # 7507.2C 4/02 Photo # 7325-D763

Page 45: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Material Radiological Concerns

Radium 226: gives off radon

Thorium 230: ranges from 26,000 pCi/g (picocuries per gram) to 76,000 pCi/g

Alpha emitter: particles can be stopped by paper and Personal Protective Equipment

Inhalation hazard

Graphics # 7507.2D 4/02

Page 46: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Remediation Design

I

No treatment

Removal, packaging and shipping

Two retrieval strategies: pneumatic (vacuuming) and mechanical (excavation)

. 4 2 o g . .

Page 47: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Retrieval Strategies: Pneumatic (Vacuuming)

In the 1950s, workers pneumatically conveyed material into Silo 3

Dome access evaluation

Containment over Silo 3

Access platforms over manways

4

Graphics # 7507.2F 4/02

Page 48: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3 DUST COLLECTOR REMOVAL G , .: 42i9 ....... ._ .... ,-..~,--...-_-. ...... . . . . . . . . . . . .

. I

. . : I ,

" . . %

. .

. . . . . . ' . . . . .

. . . . ., . * .~

Graphics # 7507.2G 4/02 Photo # 4849-28

Page 49: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3 REMEDIATION FACILITIES

6 Graphics # 7507.28 4/02 * (Q

Page 50: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Retrieval Strategies: Mechanical (Excavation)

Engineers recently completed analysis on cutting opening

Crews will install reinforcing material around the silo

Plans include a separate excavator room for retrieval

,

Graphics # 7507.25 4/02

Page 51: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3 REMEDIATION FACILITIES

0 . €3 8' Q: tn'

Graphics # 7507.2K 4/02 ' . _. ! .'

Page 52: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3 EXCAVATOR ROOM

Graphics # 7SW.2L 4/02

2-

Page 53: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Packaging

Packaging area will have closed system

I F 2 package

Package meets requirements of Department of Transportation (DOT) standard, 49 CFR 173.4 1 1

Inner liner for worker protection and contamination control

Outer shipping container

I .

I 4'

.;u C'

. . : Graphics # 7507.2M 4/02 000053

Page 54: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3 PACKAGING AREA

. I Graphics # 7507.2N 4/02

.. ., I . , . .

Page 55: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

- p t c [.42 Q g

SOFTcSIDED PACKAGE TESTING

- . - .

i'

f-S.5

, -. c Graphics # 7507.2P 4/02 Photo # 777fD1 from vendor 000055

Page 56: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

b- 4 2 0 9

SILO 3 REMEDIATION

Page 57: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

' , . : I -

IPH2 packaging requirement

SILO 3 Shipping

Ship material offsite without treatment

Graphics # 7507.21 4/02

Page 58: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Design Packages

April 2002 Silo reinforcing

April 2002 Site preparation

May 2002 Civil/concre te

June 2002 Mechanical

July 2002 Electrical and instrumentation

Graphics # 7507.28 4/02

Page 59: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Early Construction Activities

May 2002 Start field work

December 2002 Complete field work

Graphics # 7507.2T 4/02

Page 60: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

SILO 3

Look Ahead

Submit Remedial Design package to EPA ROD amendment: no treatment

Disposal contract '! .

Packaging and Shipping Request for Proposal (RFP)

I Graphics # 7507.2U 4/02

Page 61: FERNALD SILOS PROJECT - Office of Legacy · PDF fileFERNALD SILOS PROJECT PROGRESS BRIEFING April 2002 6:30 p.m. Opening Remarks Fernald Citizens Advisory Board ... SILO 3 Remediation

42 0,g SILO 3 SILOS 1 & 2

HAZARDS Radon gas, radium, gamma does Thorium 230 dust

RETRIEVAL Sluice material to AWR Transfer Tanks

Vacuum loose dry material and excavate compacted material

~~ ~

Directly to packaging TRANSFER T o treatment facility

TREAT Chemically treat RCRA metals No on-site treatment

~~

STABILIZE Free moisture and material mixture No moisture requiring stabilization

DURATION OF OPERATIONS

February 2005 - February 2006 March 2003 - September 2003

~~ ~

Sealed cylindrical metal canisters PACKAGE Sealed plastic liner inside IP2 certified lift liner bag inside cargo container

Four cargo containers to one flatbed railcar-; three cars attached to each Waste Pit unit train: total of 38 cars

Explanation of Significant Differences (ESD) calls for chemical stabilization or encapsulation to meet RCRA limits and disposal facility Waste Acceptance Criteria (WAC). Disposal at either NTS or permitted offsite facilitv

SHIP Seven canisters to each shielded gondola car; dispatch as unit trains

Record of Decision (ROD) calls for chemical stabilization and disposal at Nevada Test Site (NTS)

CURRENT MANDATES

Proposed amendment would allow disposal as required by permitted offsite facility's WAC

ROD AMENDMENTS Proposed amendment would allow alternate disposal and treatment as required by permitted offsite facility's WAC

Graphics # 7507.0B 4/02