Fermilab
Cavity Refurbishment Status
J. ReidM. Slabaugh
November 19, 2014
November 19, 2014J. Reid 1
Fermilab
Cavity 1008
Cavity # 1008 – Removed from Station 5 – Cavity downstream end cut open - Class 3 cavity
•October 21 - Mechanical refurbishment complete
•October 22 – Installed in test cave at MI-60.
•November 12 – Repairs completed - LCW leak on center casting cooling tube.
•November 24 – Finish testing and ready to ship to Booster
•December 1 – Ship to Booster
•December 2 – Ready for installation in Booster Station 9
November 19, 2014J. Reid 2
Fermilab
Cavity 1008
November 19, 2014J. Reid 3
Fermilab
Cavity 1008 Repairs
November 19, 2014J. Reid 4
Fermilab
Cavity 1008
November 19, 2014J. Reid 5
Fermilab
Cavity 1008
November 19, 2014J. Reid 6
LCW Leak on braze joint
Fermilab
November 19, 2014J. Reid 7
Cavity 1002
Cavity 1002
•November 20 - Cavity fully machined and will be mounted on a girder with bottom tuner
•November 24 – Mount back tuner
•November 26 - Mount front tuner
•December 1-4 – Complete plumbing and vacuum leak test
•December 8 – Install in test cave at MI-60
•December 22 – Testing complete
•January 6, 2015 - Ready to install in Booster
Fermilab
Cavity 1001
• Removed from Station 9
• Needs center casting cooling tube replaced
• Presently on Bridgeport mill – refurbishment not started yet
November 19, 2014J. Reid 8