FEED THE FUTURE TANZANIA LAND TENURE ASSISTANCE (LTA ...
Transcript of FEED THE FUTURE TANZANIA LAND TENURE ASSISTANCE (LTA ...
This publication was produced by the Tanzania Land Tenure Assistance Activity (LTA) under Contract No. IQC: AID-OAA-I-12-00031/AID-621-T0-16-00005 at the request of the United States Agency for International Development. This document is made possible by the support of the American people through the United States Agency for International Development. Its contents are the
sole responsibility of the author or authors and do not necessarily reflect the views of USAID or the U.S. Government.
FEED THE FUTURE TANZANIA LAND
TENURE ASSISTANCE (LTA)
MONTHLY REPORT NO 60
NOVEMBER 1 - 30, 2020
This publication was produced by the Tanzania Land Tenure Assistance Activity (LTA) under Contract No. IQC: AID-OAA-I-12-00031/AID-621-T0-16-00005 at the request of the United States Agency for International Development. This document is made possible by the support of the American people through the United States Agency for International Development. Its contents are the sole
responsibility of the author or authors and do not necessarily reflect the views of USAID or the U.S. Government.
FEED THE FUTURE TANZANIA LAND TENURE
ASSISTANCE (LTA) MONTHLY REPORT NO. 60
Program Title: Feed the Future Tanzania Land Tenure Assistance (LTA)
Sponsoring USAID Office: Economic Growth Office USAID/Tanzania
Contract Number: IQC: AID-OAA-I-12-00031/AID-621-T0-16-00005
Contractor: DAI Global, LLC
Date of Publication: December 15, 2020
Author: LTA Staff
Cover Photo: Photo by LTA
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
I
TABLE OF CONTENTS
ACRONYMS AND ABBREVIATIONS 2
EXECUTIVE SUMMARY 3
1.0 INTRODUCTION 5
2.0 FY 21 MONTH OF NOVEMBER 20 ACTIVITIES 6
2.1 ASSISTING IN LAND USE PLANNING PROCESS AND
DELIVERING OF CCROS 6
2.1.1 BOUNDARY VERIFICATION/RECTIFICATION 6
2.1.2 LAND USE PLANNING 7
2.1.3 DEMARCATION AND ADJUDICATION 8
2.1.4 PUBLIC DISPLAY 8
2.1.5 DISPUTE RESOLUTION 8
2.1.6 DELIVERY OF CCROS 9
2.1.7 VILLAGE LAND REGISTRY REHABILITATION 9
2.2 EDUCATE AND BUILD CAPACITY OF VILLAGE LAND
GOVERNANCE INSTITUTIONS AND INDIVIDUAL VILLAGERS 12
2.2.1 VILLAGE LAND GOVERNANCE INSTITUTIONS 12
2.2.2 VILLAGE RESIDENTS 12
2.3 DEVELOPING AND FIELD TESTING OF THE BENEFEICIARY
CONTRIBUTION MODEL 13
2.3.1 THE STATUS OF BENEFICIARY CONTRIBUTION 14
2.4 FORMALIZING AND BUILDING LTA AS LOCAL NON-
GOVERNMENTAL ORGANIZATIONS 14
3.0 ANNEXES 16
ANNEX A: THE STATUS OF IMPLEMENTATION OF VLR IN IRINGA AND
MBEYA TO DATE – PHASE 2 16
ANNEX B: STATUS OF IMPLEMENTATION FOR PHASE 1 17
ANNEX C: BENEFICIARY CONTRIBUTION TRACKER 19
ANNEX D: MAIN ACTIVITIES PLANNED FOR DECEMBER 2020 21
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
2
ACRONYMS AND ABBREVIATIONS
CCRO Certificates of Customary Right of Occupancy
COP Chief of Party
CSO Civic Society Organization
DC District Council
DCOP Deputy Chief of Party
DED District Executive Director
DLO District Land Office
FTF Feed the Future
GoT Government of Tanzania
ILMIS Integrated Land Management Information System
IP Implementing Partner
JGI Jane Goodall Institute
LCWT Landscape Conservation in Western Tanzania
LTA Feed the Future Land Tenure Assistance Activity
MAST Mobile Application to Secure Tenure
MLHHSD Ministry of Lands, Housing, and Human Settlements Development (referred to the
Ministry of Lands)
MOHCDEC Ministry of Health, Community Development, Gender, Elderly and Children
MOU Memorandum of Understanding
NGO Non-Government Organization
NLUPC National Land Use Planning Commission
PLUM Participatory Land Use Management
PRA Participatory Rural Appraisal
TRUST Technical Register Under Secure Tenure
SAGCOT Southern Agricultural Growth Corridor of Tanzania
USAID United States Agency for International Development
VA Village Assembly
VAC Village Adjudication Committee
VC Village Council
VEO Village Executive Officers
VLC Village Land Council
VLR Village Land Registration
VLUMC Village Land Use Management Committee
WEO Ward Executive Officer
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
3
EXECUTIVE SUMMARY
During the reporting period, LTA made an objective assessment of the status of its progress with
respect to land use planning and delivering of CCROs and adopted a practical strategy to expedite its
activities. The assessment and adoption of a broad strategy was conducted in the context of the
slowdown that the project experienced as a result of the limitations posed by the COVID-19
pandemic. In accordance with this new strategy, LTA took concrete measures to speed up its activities
with respect to the processes for developing land use planning and delivering CCROs. Among the
concrete measures that LTA undertook were to deploy five field staff teams to simultanously start
implementing the processes for land use planning and delivery of CCROs in five villages.
LTA also showed significant progress in relation to pending cases of denied claims of land ownership,
boundary verification, VLUP, demarcation and adjudication, and public display of the result of
adjudication and demarcation in project villages. Specifically, among others, assisted the Mbeya DLO,
the Mbeya District Land Surveyor, and Town Planner to resolve pending cases involving denied claims
of land ownership in Isangala and Haporoto Villages. LTA also assisted the District PLUM team to start
preparation for conducting the VLUP process for Nyabula village in Iringa District. As part of the
preparation for developing the VLUP, the PLUM team provided trainings for the VC and VA. After the
conduct of the training, the VC nominated nine members to establish the Village Land Use
Management Committee (VLUMC). The nominated villagers were later approved by the VA. The
VLUMC is composed of five females and four male members.
In November, LTA was able to show considerable progress with respect to demarcation and
adjudication. Demarcation and adjudication represent important aspects of the process for delivering
CCROs as any claim of land is ascertained through adjudication and demarcation, entailing mapping of
land parcels. In collaboration with the DLO, LTA completed working on demarcation and adjudication
activities in Lumuli and Kipera villages. During the reporting period, LTA assisted in demarcating 408
land parcels in Kipera village. Additionally, in November 2020, LTA assisted in demarcating 327 parcels
in Lumuli village.
In the reporting period, LTA continued facilitating the resolution of disputes that arose in the course
of public display of the results of demarcation and adjudication. In the reporting period, three
conflicting claims and 13 land use-related disputes were reported to the village land council for their
resolution. The later cases included 13 parcels demarcated in grazing areas. LTA will continue to
follow up and facilitate the resolution of these disputes. Moreover, LTA assisted in printing and
registering of a total of 1,769 CCROs for Mangalali village, Iringa District.
During the reporting period, LTA organized CCRO issuance ceremonies in Kibena, Iringa District and
Isangala and Haporoto Villages in Mbeya District. The three ceremonies were attended by District
Land Office staff, village leaders, village residents, and LTA staff. A total of 480, 574, and 783 CCROs
were delivered to Isangala Village Land Registry, Kibena Village Land Registry and Haporoto Village
Land Registry, respectively. In the three CCRO issuance ceremonies, a total of 1,237 CCROs were
collected by village residents and vividly exhibited their excitement to receive their CCROs. The
successful beneficiaries who did not make their contributions were encouraged to witness those who
made their contributions receive their CCROs and many promised to make their contributions
shortly.
During the reporting period, LTA completed the rehabilitation of the village land registry in Kipera
village. LTA also commenced working on the rehabilitation of Village Land Registries in five villages
including Sadani, Kaning’ombe, Mfyome, Mibikimitali, and Ng’enza.
LTA conducted considerable activities with respect to educating village land governance institutions
and village residents. Several training sessions were provided on topics covering the basic principles
of the Village Land Act and the Land Use Planning Act, establishment of village land use planning
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
4
structures, the roles and responsibilities of village residents in the preparation and implementation of
VLUP, and the beneficiary contribution model.
In the reporting month, LTA continued taking practical measures to encourage beneficiaries to make
their contributions in accordance with the MOU that LTA signed with VCs. In collaboration with the
DLO, LTA organized sensitization meetings aimed at boosting beneficiary contributions in ten villages
in Iringa District, i.e. Ng’enza, Sadani, Kaning’ombe, Mibikimitali, Mfyome, Wangama, Nyabula, Kibena,
Iguluba, and Nyamahana villages. In the meetings, in accordance with an agreement reached with the
DLO, LTA introduced an incentive system for influential village leaders who have agreed to collaborate
with LTA on collecting beneficiary contribution. LTA also conducted awareness raising activities with
respect to beneficiary contributions. These measures were preceded by a technical meeting held by
the LTA team, District Land Office, District Community Development Office, and Ward Level
Community Development Officers to discuss strategies to boost beneficiary contribution.
Additionally, LTA held fruitful meetings with the land offices of Iringa and Mbeya districts.
LTA also started introducing the LTA-NGO to government counterparts to build support for its
establishment and planned activities. In November, LTA’s COP, DCOP, and Land Administration
Specialist traveled to Dodoma and held a series of meetings with several officials and technical staff of
the Ministry of Lands including the Deputy Permanent Secretary, Coordinator for Land Formalization
Program, and Senior Legal Officer. One of the main purposes of the meetings was to introduce the
LTA-NGO to the Ministry of Lands officials and to build support for its establishment and planned
activities. LTA also held similar meeting with Iringa District Council officials. The reaction of the
government counterparts including the Ministry of Lands and the Iringa District Council has been
encouraging.
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
5
1.0 INTRODUCTION
As part of the Feed the Future (FTF) initiative, the United States Agency for International Development
(USAID) invested in several agricultural projects in the Southern Agricultural Growth Corridor of
Tanzania (SAGCOT) and sought to develop focused land tenure programming to support USAID's
existing and planned investments in the region.
The Feed the Future Land Tenure Assistance (LTA) activity sought to clarify and document village land
ownership, support land use planning efforts, and increase local understanding of land use and land
rights in the Iringa District, as well as test the transferability of the model from one district to another
with subsequent implementation in the Mbeya District. The project began operations in FY 2016 in 36
villages in the Iringa District and completed the first period of performance in FY 2020 with five villages
in the Mbeya District of Tanzania. As a result of the LTA activity's success, USAID extended the
activity for a further two years to ensure local sustainability. The interventions are intended to reduce
land tenure-related risks, lay the groundwork for sustainable agricultural investment, and provide a
systematic village land registration model. LTA assists local level authorities in the delivery of land
tenure services under the Village Land Act, 1999; Village Land Regulations, 2001; the Registration of
Documents Act, 1924; Registration of Documents Regulations, 1963; the Land Use Planning Act, 2007;
and The Courts (Land Disputes Settlements) Act, 2002.
In carrying out its activities, LTA collaborates and coordinates with the Government of Tanzania (GoT)
and other donor-funded programs to produce complementary programming that was timely, cost-
effective, and sustainable. LTA adopted and adapted digital technology developed by the USAID Mobile
Application to Secure Tenure (MAST) pilot project and created an additional application for the digital
registration of post-registration transactions in the form of the Technical Register Under Secure
Tenure (TRUST). LTA developed and refined the process for systematic adjudication and demarcation
of village land using MAST and the preparation and systematic registration of Certificates of Customary
Right of Occupancy (CCROs). This process is referred to as the Village Land Registration (VLR)
process.
The Ministry of Lands, Housing, and Human Settlements Development (referred to hereafter as the
Ministry of Lands) accepted the LTA developed VLR process and adopted the Mobile Application to
Secure Tenure (MAST) and the Technical Register Under Secure Tenure (TRUST) as the preferred
digital data capture system and digital land administration system respectively for first village land
registration and post-registration transactions in Tanzania. LTA developed the VLR process following
the legislation and regulations governing village land registration in Tanzania with modifications made
to improve cost and time efficiencies. The Government of Tanzania (GOT) has formulated regulations
to give effect to these modifications.
Landholders and village leaders have embraced the system because of LTA's concerted effort to supply
training and emphasize community sensitization and public participation in its model. The uptake of
CCROs issued by LTA is around 90 percent. LTA has in the past and continues to respond to requests
from land stakeholders from other districts for training in MAST and TRUST.
The two-year extension's focus is to apply the beneficiary contribution model for village land
registration in villages in the Iringa District, which were not previously targeted by LTA, and are not
designated as future urban planning areas. In this model, beneficiaries contribute to the registration of
Certificates of Customary Rights of Occupancy (CCROs). The extension also envisages that LTA will
transition its activities to an NGO to be established during the extension and that LTA will build
capacity to use the MAST and TRUST applications throughout the SAGCOT and nationally.
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
6
2.0 FY 21 MONTH OF NOVEMBER 20 ACTIVITIES
2.1 ASSISTING IN LAND USE PLANNING PROCESS AND
DELIVERING OF CCROS
During the reporting period, LTA made an objective assessment of the status of its progress with
respect to land use planning and delivering of CCROs and adopted a practical strategy to expedite its
activities. The assessment and adoption of a broad strategy was conducted in the context of the
slowdown that the project experienced as a result of the limitations posed by the COVID-19
pandemic.
In accordance with the new strategy that LTA adopted in the reporting month, LTA took concrete
measures to speed up its activities with respect to the processes for developing land use planning and
delivering CCROs. Among the concrete measures that LTA decided to take was to deploy five field
staff teams to simultanously start implementing the processes for land use planning and delivery of
CCROs in five villages. Subsequently, LTA and DLO held technical meetings to plan the execution of
field activities including village boundary rectification, VLUP preparation, awareness and sensitization,
demarcation and adjudication, and CCRO issuance. The representatives from the DLO supported
LTA’s plan to deploy five field teams at the same time. The DLO representatives also proposed a
refresher training to be provided for newly appointed DLO field staff and Community Development
Officers. The list of five priority villages was reviewed and field implementation in five villages was
jointly approved by LTA and the DLO.
2.1.1 BOUNDARY VERIFICATION/RECTIFICATION
During the reporting period, LTA held a meeting with the Mbeya DLO and discussed the issue of
denied land parcels for Isangala and Haporoto Villages. During the meeting, the Mbeya DLO and LTA
agreed that the District Land Surveyor and Town Planner should conduct VC meetings to resolve the
pending issues of denied land parcels and to conduct a field visit to the areas where the contested
parcels of land are located. Accordingly, LTA worked with the the Mbeya District Land Surveyor,
Town Planner, and VC to bring finality to the
issue of denied claims of land ownership.
Consequently, LTA staff, the District Land
Surveyor, District Town Planner, and VC
members held a meeting and conducted site
visits to the contested land parcels to verify the
village land boundaries against the backdrop of
the village land use plan. Subsequently, the VC
members confirmed that land parcels
designated for industrial and grazing purposes
should be managed under the custodianship of
the VC and not individual villagers. Accordingly,
the VC decided that all villagers whose land
parcels were mapped within those areas will
not be granted formal recognition of their holdings.
LTA and DLO meeting in Mbeya on November 24
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
7
Table 1: Status of Village Land Certificates, Iringa, as of November 30, 2020
No Village VLC Reg.
No. Boundary
Verification VLC status
1 Lumuli 121 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
2 Itengulinyi TBD Boundary rectified Preparation of revised Deed Plan and VLC is underway
3 Isupilo 124 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
4 Kikombwe 45 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
5 Kibena 120 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
6 Muwimbi 72 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
7 Magunga 109 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
8 Kiponzelo 92 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
9 Igunda 115 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
10 Ibumila 66 IRA Boundary verified Existing VLC matches with boundary on the ground. VLC to submitted and uploaded into TAMIS in May
11 Mibikimitali TBD Boundary rectified Preparation of revised Deed Plan and VLC is underway
12 Ifunda 69 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
13 Mfukulembe 134 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
14 Ilandutwa 44 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
15 Lwato 10 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
16 Ng’enza TBD Boundary rectified Preparation of revised Deed Plan and VLC is underway
17 Msuluti 103 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
18 Ikuvilo 90 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
19 Udumka 91 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
20 Kipera 58 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
21 Ukwega TBD Boundary rectified Preparation of revised Deed Plan and VLC is underway
22 Luganga 27 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
23 Ilolo mpya 47 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
24 Mkombilenga 29 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
25 Mafuluto 31 IRA Boundary verified Existing boundary matches with approved VLC
26 Mfyome 7 IRA Boundary verified Existing boundary matches with approved VLC
27 Isele 19 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
28 Magombwe 25 IRA Boundary rectified Preparation of revised Deed Plan and VLC is underway
2.1.2 LAND USE PLANNING
In the reporting month, LTA assisted the District PLUM team to start preparation for conducting the
VLUP process for Nyabula village in Iringa District. As part of the preparation for developing the VLUP,
the PLUM team provided trainings for the VC and VA. After the conduct of the training, the VC
nominated nine members to establish the Village Land Use Management Committee (VLUMC). The
nominated villagers were later approved by the VA. The VLUMC is composed of five female and four
male members.
Table 2: Status of Village Land Use Plans, Iringa Phase 2 Villages, as of November 30, 2020
No Village Start Date End Date VLUP Status
1 Mangalali 2/25/2020 3/5/2020 Completed
2 Ibangamoyo 2/25/2020 3/6/2020 Completed
3 Kibena 3/13/2020 4/7/2020 Completed
4 Lumuli 3/27/2020 4/7/2020 Completed
5 Lyamgungwe 4/16/2020 4/28/2020 Completed
6 Kikombwe 4/21/2020 4/28/2020 Completed
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
8
7 Ng’enza 5/7/2020 5/19/2020 Completed
8 Msuluti 5/7/2020 5/15/2020 Completed
9 Mibikimitali 5/22/2020 5/29/2020 Completed
10 Ibumila 5/22//2020 6/2/2020 Completed
11 Sadani 6/8/2020 6/17/2020 Completed
12 Kipera 6/19/2020 6/26/2020 Completed
13 Kaning’ombe 6/8/2020 6/17/2020 Completed
14 Makongati 6/19/2020 6/30/2020 Completed
15 Luganga 8/7/2020 8/15/2020 Completed
16 Ukwega 8/7/2020 8/18/2020 Completed
17 Mkombilenga 8/22/2020 8/29/2020 Completed
18 Ilolo mpya 8/22/2020 8/28/2020 Completed
19 Magombwe 9/03/2020 9/14/2020 Completed
20 Mafuluto 9/03/2020 9/14/2020 Completed
21 Mfyome 9/17/2020 9/27/2020 Completed
22 Kihanga 9/21/2020 10/23/2020 Completed
23 Nyabula 11/24/2020 Ongoing
2.1.3 DEMARCATION AND ADJUDICATION
In November, LTA was able to show considerable progress
with respect to demarcation and adjudication. Demarcation
and adjudication represent important aspects of the process
for delivering CCROs as any claim of land is ascertained
through adjudication and demarcation, entailing mapping of
land parcels. In collaboration with the DLO, LTA completed
working on demarcation and adjudication activities in
Lumuli and Kipera villages. During the reporting period,
LTA assisted in demarcating 408 land parcels in Kipera
village. Additionally, in November 2020, LTA assisted in
demarcating 327 parcels in Lumuli village.
Additionally, from November 24 to November 30, 2020,
LTA and the DLO conducted a five-day demarcation and
adjudication training to parasurveyors and adjudicators in five villages (Ng’enza, Sadani, Mibikimitali,
Mfyome, and Kaning’ombe) in preparation for land parcel demarcation and adjudication process. The
content of the training covers the procedures and basics for land parcel adjudication and the
demarcation of the land parcels using the mobile application technology (MAST) as a step towards
CCRO registration.
2.1.4 PUBLIC DISPLAY
In the month of November, LTA worked on final editing of parcels and data attributes for Kipera and
Lumuli villages, Iringa district for preparation of public display of the the results from adjudication and
demarcation activities. The public display is planned to take place next month.
2.1.5 DISPUTE RESOLUTION
In the reporting period, LTA continued facilitating the resolution of disputes that arose in the course
of public display of the results of demarcation and adjudication. In the reporting period, three
conflicting claims and 13 land use-related disputes were reported to the village land council for their
resolution. The later cases included 13 parcels demarcated in grazing areas. LTA will continue to
follow up and facilitate the resolution of these disputes.
Adjudication and demarcation training in
Mfyome village on November 24
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
9
2.1.6 DELIVERY OF CCROS
In November, LTA completed editing of parcel maps
and data attributes for Mangalali village, Iringa
district and uploaded them to MAST. The list of
claims was submitted to the District Authorized
Land Officer for review and approval. Subsequently,
the list was approved for printing and registration of
CCROs. Accordingly, LTA assisted in printing and
registering a total of 1,769 CCROs for Mangalali
village.
Additionally, during the reporting period, LTA
organized CCRO issuance ceremonies in Kibena,
Iringa district and Haporoto, and Isangala villages in
Mbeya district. The three ceremonies were
attended by District Land Office staff, village leaders,
village residents, and LTA staff. A total of 480, 574, and 783 CCROs were delivered to the Isangala
village land registry, Kibena village land registry and Haporoto village land registry, respectively. In the
three CCRO issuance ceremonies, a total of 1,237 CCROs were collected by villagers and vividly
exhibited their excitement to receive their CCROs. The successful beneficiaries who did not make
their contribution were encouraged to witness those who made their contributions receive their
CCROs and many promised to make their contributions shortly. In addition, prior to the issuance
ceremony, the Regional Commissioner for Land held a meeting with VC members and VLRC to
discussed strategies to increase contributions. She emphasized the importance of CCROs and
encouraged VC and VLRC to sensitize residents to contribute for CCROs. She commented that
Haporoto village will be used as an example to encourage and train other villages to use the beneficiary
contribution model in rural land registration in the Mbeya region. VC members and the VLRC agreed
to set a time frame for contributions to January 5, 2021.
2.1.7 VILLAGE LAND REGISTRY REHABILITATION
During the reporting period, LTA completed the rehabilitation of the village land registry in Kipera
village. LTA also commenced working on the rehabilitation of village land registries in five villages
namely: Sadani, Kaning’ombe, Mfyome, Mibikimitali, and Ng’enza. LTA has been assisting in the
rehabilitation of village land registries by refurbishing one room in a village registry, and by providing
basic furniture including metal cabinets for CCRO storage with a chair and table.
Printing and Registration of CCROs for Mangalali
Village on November 9
CCROs Issuance Ceremony Held at Kibena Village on November 13, 2020
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
10
Table 3: Village Registry Upgrades for Phase 2 villages as of November 30, 2020
No Village Name Village Office Status
Office Upgrade Status Completion
Date Comments
1 Mangalali Village office Office upgrade: requires repair of the cement sand floor screed, walls developed several cracks to be repaired, wall plastering and painting. Installation of a windows, grills and
door, no ceiling and there is a need for anti-termite treatment, chair, desk, and cabinet.
9/22/2020 Completed
2 Isangala Village office Office upgrade: requires repair of the cement sand floor screed, walls developed several
cracks to be repaired, wall plastering and painting. Installation of a windows, grills and door, no ceiling and there is a need for anti-
termite treatment, chair, desk, and cabinet.
6/26/2020 Completed
3 Haporoto Political Office
Construction of the new Village Office is underway
4 Ibangamoyo Village office Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and
door, no ceiling and there is a need for anti-termite treatment, chair, desk, and cabinet.
9/25/2020 Completed
5 Lumuli Village office Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and
door, no ceiling and there is a need for anti-termite treatment, chair, desk, and cabinet.
10/30/2020 Completed
6 Isupilo Village office Office upgrade: requires repair of the cement sand floor screed, walls developed several cracks to be repaired, wall plastering and
painting. Installation of a windows, grills and
door, no ceiling and there is a need for anti-termite treatment, chair, desk, and cabinet.
TBD NTR
7 Kibena Political Office
Office upgrade: requires provision of a chair, desk, and cabinet
6/27/2020 Completed
8 Ibumila Political Office
Office upgrade: requires provision of a chair, desk, and cabinet
TBD NTR
9 Mibikimitali Political Office
Office upgrade: requires provision of a chair, desk, and cabinet
TBD NTR
10 Lyamgungwe Village office that is still
under construction
Office upgrade: requires repair of the cement sand floor screed, wall plastering and
painting. Installation of a windows, grills and door, no ceiling and there is a need for anti-termite treatment, chair, desk, and cabinet.
TBD NTR
11 Kikombwe Village office Office upgrade: requires repair of the cement sand floor screed, walls developed several
cracks to be repaired, wall plastering and
painting. Installation of a windows, grills and door, no ceiling and there is a need for anti-
termites treatment, chair, desk, and cabinet.
TBD NTR
12 Msuluti Village office that is still under construction
Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and door, no ceiling and there is a need for anti-
termite treatment, chair, desk, and cabinet.
TBD NTR
13 Kipera Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and door, no ceiling, chair, desk, and cabinet.
11/30/2020 Completed
14 Kidilo Temporary Village Office
Construction of the new Village Office is underway
TBD NTR
15 Sadani Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and
painting. Installation of a windows, grills and door, no ceiling, chair, desk, and cabinet
TBD NTR
16 Makombe Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and
TBD NTR
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
11
painting. Installation of a windows, grills and door, no ceiling, chair, desk, and cabinet.
17 Kaning’ombe Village Office Construction of the new Village Office is underway
TBD NTR
18 Makongati Political Office
Office upgrade: requires provision of a chair, desk, and cabinet
TBD NTR
19 Mahanzi Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and
door, no ceiling, chair, desk, and cabinet.
TBD NTR
20 Wasa Political Office
Office upgrade: requires provision of a chair, desk, and cabinet
TBD NTR
21 Ufyambe Political
Office
Office upgrade: requires provision of a chair,
desk, and cabinet
TBD NTR
22 Mangawe Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and
painting. Installation of a windows, grills and door, no ceiling, chair, desk, and cabinet
TBD NTR
23 Kinyika Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and
door, no ceiling, chair, desk, and cabinet
TBD NTR
24 Magombwe Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and door, no ceiling, chair, desk, and cabinet
TBD NTR
25 Nyang’oro Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and
painting. Installation of a windows, grills and door, no ceiling, chair, desk, and cabinet
TBD NTR
26 Mikong’wi Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and
painting. Installation of a windows, grills and door, no ceiling, chair, desk and cabinet
TBD NTR
27 Ivangwa Neither Political nor Village Office
Discussion for construction of the village office is underway among VC members and VA members
TBD NTR
28 Uhominyi Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and
painting. Installation of a windows, grills and door, no ceiling, chair, desk and cabinet
TBD NTR
29 Mkombilenga Village Office Construction of the village office is underway TBD NTR
30 Wangama Village Office Construction of the village office is underway TBD NTR
31 Mfyome Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and
door, no ceiling, chair, desk and cabinet
TBD NTR
32 Nyabula Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and painting. Installation of a windows, grills and door, no ceiling, chair, desk and cabinet
TBD NTR
33 Ng’enza Village Office Office upgrade: requires repair of the cement sand floor screed, wall plastering and
painting. Installation of a windows, grills and door, no ceiling, chair, desk and cabinet
TBD NTR
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
12
2.2 EDUCATE AND BUILD CAPACITY OF VILLAGE
LAND GOVERNANCE INSTITUTIONS AND INDIVIDUAL
VILLAGERS
2.2.1 VILLAGE LAND GOVERNANCE INSTITUTIONS
In the reporting month, LTA assisted in organizing and facilitating a meeting in Nyabula village, Iringa
district, where the District PLUM team conducted trainings to the Village Land Use Management
Committee, Village Council, and Village Assembly on VLUP preparation and enforcement. The
trainings covered the following topics: the basic principles of the Village Land Act and the Land Use
Planning Act, establishment of village land use planning structures, and the roles and responsibilities of
village residents in the preparation and implementation of VLUPs.
LTA also conducted five training sessions to educate village land authorities in Ng’enza, Mibikimitali,
Mfyome, Sadani, and Kaning’ombe villages with
respect to land rights and management of village
land. Specifically, the training sessions aimed at
building the capacity of village land authorities
including VC members regarding land rights and
their roles and responsibilities during
implementation of land registration activities and
the beneficiary contribution model.
The trainings were attended by a total of 137
members (61 female and 76 male), including 47
youth.
2.2.2 VILLAGE RESIDENTS
In November 2020, LTA continued undertaking
activities aimed at educating village residents with
respect to land rights and tenure ownership. LTA, in
collaboration with the DLO, conducted five village
assembly trainings in Ng’enza, Mibikimitali, Mfyome,
Sadani, and Kaning’ombe villages. The trainings
focused on creating awareness of village residents on
principles of land rights, beneficiary contribution for
land registration activities, and the role of villagers
during adjudication and demarcation of individual
land parcels. The trainings were attended by a total
of 962 villagers (537 female and 425 male), including
298 youth.
Also, in collaboration with Ward Level Community
Development Officers, LTA conducted training for residents of Matembo hamlet in Mfyome village.
The training pertained to land rights and focused on enforcement of village land use planning, land
rights to women, youth and pastoralists, introduction of village land registration process using MAST,
beneficiary contribution model, the dispute resolution process, the importance of post registration
transactions using TRUST, and advice on types of tenancy. LTA staff also seized the opportunity to
Village council training and awareness raising meeting
on land administration at Mfyome on November 25
Village assembly training and awareness raising meeting
on land administration at Sadani village
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
13
convey messages to motivate villagers to contribute for their land registration and to sensitize villagers
on appropriate precautions that should be taken to prevent the spread of COVID-19. The training
was attended by a total of 52 residents (25 female and 27 male), including 26 youth.
LTA and the DLO facilitated women’s sensitization and
awareness raising training on land rights in Sadani, Mfyome,
Ng’enza, Mibikimitali and Kaning’ombe villages. The
trainings were attended by 537 women, including 123 youth.
The participants were provided with training on women’s
land and property rights in accordance to Tanzania’s laws,
women’s roles in decision-making on land matters at the
village-level, rights to access land and advised them to
participate in the demarcation and adjudication activities.
Moreover, in the reporting month, LTA and the DLO
conducted training on land acquisition for pastoralist and
their rights to certificates of customary for pastoralist
community at Mlambalasi hamlet in Kipera village. The
trainings were attended by a total of 55 residents (32 female
and 23 male), including 31 youth.
2.3 DEVELOPING AND FIELD TESTING OF THE
BENEFEICIARY CONTRIBUTION MODEL
In the reporting month, LTA continued taking practical measures to encourage beneficiaries to make
their contributions in accordance with the MOU that LTA signed with VCs. In collaboration with the
DLO, LTA organized sensitization meetings aimed at boosting beneficiary contributions in ten villages
in Iringa District, i.e. Ng’enza, Sadani, Kaning’ombe, Mibikimitali, Mfyome, Wangama, Nyabula, Kibena,
Iguluba, and Nyamahana villages. In the meetings, in accordance with an agreement reached with the
DLO, LTA introduced an incentive system for influential village leaders who have agreed to collaborate
with LTA on collecting beneficiary contributions. LTA also used posters to build awareness on
beneficiary contributions among villagers.
These measures were preceded by a technical meeting held by the LTA team, District Land Office,
District Community Development Office, and Ward Level Community Development Officers to
discuss strategies to boost beneficiary contributions. Additionally, LTA held meetings with the land
offices in Iringa and Mbeya districts. On November 16, LTA held a discussion with the Iringa District
Council Management Team (CMT) and discussed
the status of project implementation and the
challenges encountered concerning beneficiary
contributions. The DED expressed his appreciation
for the project efforts helping the government with
respect to land registration. He also appreciated
the project’s focus on sustainability of LTA’s
progress through the use of the beneficiary
contribution model. In the meeting, he instructed
the district officials to provide necessary support
to LTA to ensure that the beneficiary contribution
model becomes a success. In addition, the DED
instructed the head of departments of Community
Women sensitization training and awareness raising
in Ng’enza village
Awareness raising meeting on beneficiary contributions for
the Village Assembly at Magozi village on November 6
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
14
Development and Land and Natural Resources to have a technical discussion with LTA and come up
with strategies for speeding up the collection of the beneficiary contribution payments.
In November, the LTA team and DLO conducted an introductory Village Assembly meeting at Magozi
village attended by 191 residents (112 female, 79 male), including 96 youth and introduced a village
beneficiary contribution model to the villagers and facilitate the formation of VLRC, responsible for
village bank account opening and mobilization of contribution. The account has already been opened
and villagers are expected to start contribution.
Furthermore, LTA in collaboration with the DLO worked with Village Land Registration Committees
for six villages in Iringa district (Ilolo Mpya, Magozi, Kibebe, Mkombilenga, Kinyika, and Wasa villages)
to review the agreement made by the Village Assembly on opening bank accounts and completing
various forms as required by the bank. LTA worked to obtain the consent of beneficiaries at Ward
and District levels and consequently the agreement was fully executed by the Ward Executive Officer.
And subsequently the District Executive Director issued an official letter to support the opening of
bank accounts for the six villages. In November, six bank accounts were opened and village residents
commenced to make their contribution for their land certificates.
2.3.1 THE STATUS OF BENEFICIARY CONTRIBUTION
As of November 30, the percentage of contributions made - by number of parcels for the villages who
had started contribution - is presented as follows: 1381 (59%) in Kibena village, 257 (13%) in Mangalali
village, 259 (15%) in Ibangamoyo village, 254 (15%) in Ibumila village 7 (0%), in Ng’enza village, 88(8%)
in Msuluti village, 1 (0%) in Kikombwe village, 60 (6%) in Lyamgungwe village, 106 (9%) in Lumuli village,
114 (7%) in Isupilo village, 87 (16%) in Mibikimitali village, 14 (1%) in Makongati village, 162 (15%) in
Kipera village, 56 (3%) in Kaning’ombe, 324 (22%) in Nyabula village, 4 (0%). Mkungugu, 16 (1%), in
Makombe village, 82 (6%) in Mfyome village, 90 (3%) in Kihanga village, 69 (13%) Wangama village, and
89 (16%) Iguluba village. Iringa District. In Mbeya region, as of November 30 residents had paid
contributions of TSH 30,000 per CCROs as follows: 58 (4%) in Njelenje village, 678 (38%) in Isangala
village and 1,027 (56%) in Haporoto village.
2.4 FORMALIZING AND BUILDING LTA AS LOCAL NON-
GOVERNMENTAL ORGANIZATIONS
In the previous reporting period, the Tanzania Land Tenure Assistance (LTA) NGO was successfully
registered as a local NGO in Tanzania by the Ministry of Health, Community Development, Gender,
Elderly and Children (MOHCDEC). In November 2020, LTA received Certificate of Registration of
the LTA- NGO.
LTA also started introducing the LTA-NGO to government counterparts to build support for its
establishment and planned activities. In November, LTA’s COP, DCOP and Land Administration
Specialist travelled to Dodoma and held a series of meetings with several officials and technical staff of
the Ministry of Lands including the Deputy Permanent Secretary, Coordinator for Land Formalization
Program, and Senior Legal Officer. One of the main purposes of the meetings was to introduce the
LTA-NGO to Ministry of Lands officials and to build support for its establishment and planned
activities. The LTA team was also able to identify potential areas for collaboration between the
Ministry and the LTA-NGO. LTA also held similar meetings with Iringa District Council officials. The
reaction of government counterparts, including the Ministry of Lands and the Iringa District Council
has been encouraging.
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
15
2.5 RAISE AWARENESS OF THE MAST TECHNOLOGY
WITHIN THE GOT, CIVIL SOCIETY, ACADEMIA AND
PRIVATE SECTOR, WITH THE GOAL OF INCREASING
UPTAKE During the reporting month, LTA’s GIS and
Database Manager travelled to Kigoma and Katavi
regions to provide a six-day training in MAST
processes and technology to 16 district land staff
and 3 LCWT technical staff. The training covered
the following specific topics: publishing of vector
and raster layers on geoserver, projects set up in
MAST system, application of MAST for
demarcation and adjudication of land parcels,
editing of data on DMI, preparation of data and
maps for public display, and printing and
registration of CCROs. At the same time, LTA’s
GIS and Database Manager assisted in installing
MAST and TRUST on local servers of four districts
including Kigoma and Uvinza districts in Kigoma
region and Mpanda and Nsimbo districts in Katavi
region.
Additionally, LTA conducted a refresher training of trainers to 8 staff from the Iringa District Council.
The training focused on adjudication and demarcation principles and the use of MAST for mapping of
land parcels.
Training on MAST application using mobile phones
practical at LCWT Kigoma office for Kigoma nad Uvinza
Districts’ DLO officials
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
16
3.0 ANNEXES
ANNEX A: THE STATUS OF IMPLEMENTATION OF VLR IN IRINGA AND MBEYA TO DATE – PHASE 2
No
VIL
LA
GE
NA
ME
CU
RR
EN
T S
TA
TU
S
ES
TIM
AT
ED
PA
RC
EL
S
AC
TU
AL
PA
RC
EL
S
% D
IFF
ER
EN
CE
AD
JUD
ICA
TIO
N
AN
D
DE
MA
RC
AT
ION
OB
JEC
TIO
NS
AN
D
CO
RR
EC
TIO
NS
PR
INT
ING
AN
D
RE
GIS
TR
AT
ION
NU
MB
ER
OF
CC
RO
s
RE
GIS
TE
RE
D
% R
EG
IST
ER
ED
NO
. O
F C
CR
Os
DE
LIV
ER
ED
TO
VIL
LA
GE
CC
RO
DE
LIV
ER
ED
TO
DA
TE
NO
. O
F C
CR
Os
CO
LL
EC
TE
D B
Y
CL
AIM
AN
T
% C
CR
Os
CO
LL
EC
TE
D
NO
. O
F U
NIQ
UE
CL
AIM
AN
TS
START
DATE
END
DATE
START
DATE
END
DATE
START
DATE
END
DATE
1 Haporoto CCROs
Issuance 1,353 1,842 36% 2/21/2020 3/24/2020 6/2/2020 6/15/2020 6/26/2020 6/29/2020 1,765 96% 783 11/25/2020
- - -
2 Isangala CCROs
Issuance 1,926 1,775 -8% 2/28/2020 4/1/2020 6/3/2020 6/16/2020 6/29/2020 7/3/2020 1,535 86% 480 11/24/2020
- - -
3 Ibangamoyo
Awaiting
CCROs
issuance
1,100 1,707 55% 7/8/2020 8/25/2020 9/2/2020 9/17/2020 9/27/2020 9/30/2020 1,641 96% - - - - -
4 Mangalali
Awaiting
CCROs
Issuance
1,298 1,948 50% 7/7/2020 8/30/2020 9/24/2020 10/7/2020 11/9/2020 11/18/2020 1,769 91% - - - - -
5 Kibena CCROs
Issuance 2,336 2,287 -2% 5/3/2020 6/19/2020 7/24/2020 8/8/2020 9/23/2020 9/26/2020 2,009 88% 574 11/13/2020 - - -
6 Lumuli
Awaiting
objections and
corrections
1,184 1,683 42% 9/29/2020 11/13/2020 - - - - - - - - - - -
7 Kipera
Awaiting for
printing and
registration
1,108 1,582 43% 10/4/2020 11/11/2020 - - - - - - - - - - -
8 Ng'enza
Adjudication &
demarcation
commenced
1,168 - - - - - - - - - - - - - - -
9 Mibikimitali
Adjudication &
demarcation
commenced
540 - - - - - - - - - - - - - - -
10 Sadani
Adjudication &
demarcation
commenced 812 - - - - - - - - - - - - - - -
11 Kaning'ombe
Adjudication &
demarcation
commenced 2,012 - - - - - - - - - - - - - - -
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
17
12 Ibumila
Adjudication &
demarcation
commenced 2,076 - - - - - - - - - - - - - - -
TOTAL 16,913 12,824 8,719 68% 1,837 - - - -
ANNEX B: STATUS OF IMPLEMENTATION FOR PHASE 1
No
Villa
ge N
am
e
Parc
els
Dem
arc
ate
d
Nu
mb
er
of
CC
RO
s R
egis
tere
d
Parc
els
ou
tsid
e o
f V
LC
s -
reso
lved
thro
ugh
in
ter
villa
ge
nego
tiati
on
Parc
els
ou
tsid
e o
f V
LC
s -
reso
lved
thro
ugh
in
ter
villa
ge
nego
tiati
on
-
pri
nte
d t
o C
CR
Os
Parc
els
ou
tsid
e o
f V
LC
s -
reso
lved
thro
ugh
in
ter
villa
ge
nego
tiati
on
-
pen
din
g p
rin
tin
g
Parc
els
ou
tsid
e V
LC
s -
to b
e d
en
ied
Dis
pu
ted
parc
el re
solv
ed
Dis
pu
ted
parc
el
- p
en
din
g r
eso
luti
on
Dis
pu
ted
parc
el
- d
en
ial le
tters
issu
ed
alr
ead
y
Parc
els
wit
h m
issi
ng in
form
ati
on
Parc
els
wit
h n
o in
form
ati
on
, u
sed
for
train
ing a
nd
dem
on
stra
tio
n
pu
rpo
ses.
(D
ele
ted
fro
m t
he
syst
em
) P
arc
els
wit
hin
ro
ad
rese
rves
Parc
els
wit
hin
so
cia
l se
rvic
es
Parc
els
wit
hin
fo
rest
rese
rves
Parc
els
wit
hin
sw
am
p a
reas
Parc
els
wit
hin
gra
zin
g a
reas
Parc
els
wit
h o
verl
ap
s
Exis
tin
g P
arc
els
(w
ith
old
CC
RO
nu
mb
ers
)
Parc
els
dem
arc
ate
d in
exis
tin
g
farm
s (C
Os)
Parc
els
wit
hin
WM
A
Parc
els
in
DV
SP
are
a
Parc
els
read
y f
or r
egis
trati
on
follo
win
g r
eso
luti
on
Bala
nce o
f p
arc
els
dem
arc
ate
d
1 Kinywang'anga 855 794 19 0 19 0 0 0 0 0 0 0 0 25 0 0 0 0 0 0 0 17 855
2 Kilambo 2,004 2,002 0 0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2,004
3 Kiponzelo 2,263 2,092 0 0 0 0 28 3 0 8 3 4 0 0 123 0 0 0 2 0 0 0 2,263
4 Usengelindete 1,594 1,576 0 0 0 0 0 4 0 0 1 5 0 0 0 0 8 0 0 0 0 0 1,594
5 Magunga 1,904 1,732 0 0 0 0 0 20 0 2 8 0 0 0 40 0 4 0 98 0 0 0 1,904
6 Lwato 550 534 2 0 2 0 2 0 0 0 0 8 0 0 0 0 0 0 4 0 0 0 550
7 Malagosi 1,070 1,047 0 0 0 1 4 0 0 0 0 12 0 0 0 0 5 0 0 0 0 1 1,070
8 Mgama 2,302 2,151 30 0 30 19 1 0 11 1 0 70 0 0 0 0 0 9 10 0 0 0 2,302
9 Mfukulembe 1,828 1,775 0 0 0 0 0 0 0 30 0 13 0 0 0 0 0 0 0 0 0 10 1,828
10 Udumka 1,167 1,070 73 0 73 0 1 0 12 9 0 2 0 0 0 0 0 0 0 0 0 0 1,167
11 Ilandutwa 993 925 0 0 0 7 11 0 0 1 0 0 0 0 0 0 0 0 49 0 0 0 993
12 Muwimbi 1,569 1,472 16 0 16 4 7 7 0 0 0 15 0 0 30 5 0 0 0 0 13 0 1,569
13 Mwambao 663 659 1 0 1 0 2 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 663
14 Nyamihuu 1,824 1,766 0 0 0 32 0 0 0 0 0 0 0 0 0 0 1 0 24 0 0 1 1,824
15 Ngano 1,114 1,055 19 0 19 0 0 1 0 22 0 15 0 0 2 0 0 0 0 0 0 0 1,114
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
18
16 Makota 1,543 1,524 0 0 0 2 3 0 0 3 0 6 0 0 0 0 0 0 1 0 0 4 1,543
17 Ikungwe 816 808 0 0 0 3 3 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 816
18 Isele 1,711 1,551 0 0 0 116 8 0 0 7 0 6 0 0 0 0 0 23 0 0 0 0 1,711
19 Holo 729 609 0 0 0 0 0 0 0 0 4 29 0 86 0 0 0 1 0 0 0 0 729
20 Mapogoro 3,635 3,443 48 0 48 0 23 57 0 0 13 9 0 0 0 33 0 0 6 1 2 0 3,635
21 Kimande 2,106 1,896 11 0 11 93 29 8 0 0 19 6 0 0 0 0 9 1 15 0 4 15 2,106
22 Chamndindi 1,663 1,505 0 0 0 53 11 0 0 3 0 4 0 26 0 61 0 0 0 0 0 0 1,663
23 Matembo 1,135 1,101 0 0 0 0 3 0 0 1 0 7 0 0 0 23 0 0 0 0 0 0 1,135
24 Kisanga 2,063 1,879 9 0 9 109 34 27 0 4 0 0 0 0 0 0 0 1 0 0 0 0 2,063
25 Weru 1,284 1,216 113 109 4 2 2 3 0 2 3 1 0 5 0 46 0 0 0 0 0 0 1,284
26 Mlanda 1,946 1,861 44 44 0 0 1 0 0 2 0 74 0 8 0 0 0 0 0 0 0 0 1,946
27 Igunda 1,237 1,192 0 0 0 0 2 2 0 0 0 14 0 14 0 9 0 3 1 0 0 0 1,237
28 Kitapilimwa 1,529 1,480 0 0 0 0 0 15 0 0 0 1 7 11 0 15 0 0 0 0 0 0 1,529
29 Ihomasa 1,939 1,853 45 0 45 4 11 6 0 1 0 2 9 7 0 1 0 0 0 0 0 0 1,939
30 Lupembelwasenga 2,720 2,607 43 0 43 23 0 9 0 0 0 1 1 24 0 8 0 4 0 0 0 0 2,720
31 Kiwere 3,156 3,117 0 0 0 10 0 3 0 0 0 14 2 0 5 3 0 0 0 0 2 0 3,156
32 Kitisi 1,241 966 172 146 26 47 6 11 0 0 0 0 0 0 0 0 0 7 0 178 0 0 1,241
33 Ikuvilo 2,402 2,343 29 4 23 14 0 6 0 3 0 2 4 0 2 5 0 0 0 0 0 0 2,402
34 Magubike 3,142 2,868 0 0 0 1 0 40 0 1 0 26 0 44 0 150 0 2 10 0 0 0 3,142
35 Igangidung'u 3,882 3,804 99 99 0 4 0 1 0 1 1 19 0 3 0 47 0 2 0 0 0 0 3,882
36 Kising'a 1,493 1,465 0 0 0 0 0 19 0 0 2 2 0 0 0 2 0 0 3 0 0 0 1,493
37 Hatwelo 908 875 0 0 0 16 0 4 0 0 0 0 0 0 6 0 0 0 3 0 0 4 908
38 Shibolya 2,436 2,180 0 0 0 64 0 0 0 2 0 56 0 0 109 0 8 0 0 0 0 17 2,436
39 Muvwa 2,206 2,036 0 0 0 77 0 0 0 0 0 35 0 0 35 0 7 0 0 0 0 16 2,206
40 Mapogoro Mbeya 854 839 0 0 0 13 0 0 0 1 0 1 0 0 0 0 0 0 0 0 0 0 854
41 Ilota 893 881 0 0 0 0 0 0 0 0 0 0 0 0 10 0 2 0 0 0 0 0 893
TOTAL 70,369 66,549 773 402 369 714 192 248 23 106 54 459 23 253 362 408 44 54 226 179 21 85 70,369
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
19
ANNEX C: BENEFICIARY CONTRIBUTION TRACKER N
O
VIL
LA
GE
NA
ME
VL
R B
AN
K
AC
CO
UN
T
OP
EN
ING
ST
AT
US
ES
TIM
AT
ED
NU
MB
ER
OF
PA
RC
EL
S
NU
MB
ER
PA
RC
EL
S P
AID
ES
TIM
AT
ED
AV
ER
AG
E
CO
NT
RIB
UT
ION
(TZ
S)
AM
OU
NT
CO
NT
RIB
UT
ED
TO
DA
TE
(TZ
S)
%
CO
NT
RIB
UT
ION
RE
CE
IVE
D
1 Haporoto Completed 1,842 1,027 55,260,000 30,815,000.00 56%
2 Isangala Completed 1,775 678 53,250,000 20,340,000.00 38%
3 Kibena Completed 2,287 1,381 68,610,000 41,432,031.58 60%
4 Ibangamoyo Completed 1,707 259 51,210,000 7,755,000.00 15%
5 Mangalali Completed 1,948 257 58,440,000 7,710,000.00 13%
6 Lumuli Completed 1683 106 50,490,000 3,170,000.00 6%
7 Kipera Completed 1582 162 47,460,000 4,860,000.00 10%
8 Sadani Completed 812 89 24,360,000 2,670,000.00 11%
9 Mibikimitali Completed 540 87 16,200,000 2,610,000.00 16%
10 Kaning'ombe Completed 2012 56 60,360,000 1,685,000.00 3%
11 Mfyome Completed 1288 82 38,640,000 2,470,000.00 6%
12 Ng'eza Completed 1168 88 35,040,000 2,640,000.00 8%
13 Nyabula Completed 1476 324 44,280,000 9,720,000.00 22%
14 Luganga Completed 1160 1 34,800,000 30,000.00 0%
15 Kikombwe Completed 966 60 28,980,000 1,810,000.00 6%
16 Kihanga Completed 2804 90 84,120,000 2,700,000.00 3%
17 Ilolo Mpya Completed 502 - 15,060,000 - 0%
18 Ukwega Completed 500 - 15,000,000 - 0%
19 Msuluti Completed 852 1 25,560,000 30,000.00 0%
20 Ibumila Completed 2076 7 62,280,000 210,000.00 0%
21 Makongati Completed 1264 14 37,920,000 420,000.00 1%
22 Wangama Completed 548 69 16,440,000 2,070,000.00 13%
23 Wasa Completed 1684 - 50,520,000 - 0%
24 Magozi Completed 822 - 24,660,000 - 0%
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
20
25 Isupilo Completed 1696 114 50,880,000 3,420,000.00 7%
26 Nyamahana Completed 956 69 28,680,000 2,070,000.00 7%
27 Malinzanga Completed 2286 - 68,580,000 - 0%
28 Nyang’oro Completed 1028 1 30,840,000 30,000.00 0%
29 Kibebe Completed 738 1 22,140,000 30,000.00 0%
30 Mikong'wi Completed 502 1 15,060,000 30,000.00 0%
31 Ivangwa Completed 400 1 12,000,000 30,000.00 0%
32 Iguluba Completed 552 89 16,560,000 2,670,000.00 16%
33 Kidilo Completed 1200 1 36,000,000 30,000.00 0%
34 Itwaga Pending 1496 - 44,880,000 - 0%
35 Mafuluto Completed 1020 - 30,600,000 - 0%
36 Magombwe Completed 904 - 27,120,000 - 0%
37 Kinyika Completed 1258 - 37,740,000 - 0%
38 Ufyambe Completed 1432 - 42,960,000 - 0%
39 Mahanzi Underway 600 - 18,000,000 - 0%
40 Ulata Completed 1140 - 34,200,000 - 0%
41 Lupalama Completed 450 - 13,500,000 - 0%
42 Mangawe Completed 672 1 20,160,000 30,000.00 0%
43 Mawindi Completed 374 1 11,220,000 30,000.00 0%
44 Chamgogo Completed 950 1 28,500,000 30,000.00 0%
45 Ikengeza Completed 940 - 28,200,000 - 0%
46 Igula Underway 672 - 20,160,000 - 0%
47 Lyamgungwe Completed 882 0 26,460,000 3,000.00 0%
48 Ndolela Completed 306 1 9,180,000 30,000.00 0%
49 Uhominyi Completed 372 - 11,160,000 - 0%
50 Mkombilenga Completed 554 - 16,620,000 - 0%
51 Makadupa Underway 402 - 12,060,000
0%
52 Makombe Completed 1300 16 39,000,000 480,000.00 1%
53 Njelenje Completed 1506 58 45,180,000 1,740,000.00 4%
54 Mkungugu Completed 1600 4 48,000,000 120,000.00 0%
Total
1,844,580,000 155,920,031.58 8%
USAID.GOV LTA MONTHLY REPORT NO 60 - NOVEMBER 2020
21
ANNEX D: MAIN ACTIVITIES PLANNED FOR DECEMBER 2020
ACTIVITY I: Assist villages and district administrations in completing land use planning
process and delivering CCROs
Conduct boundary verification for four villages;
VLUP to be prepared for two villages;
Conduct adjudication and demarcation of land parcels in five villages;
Public display process will start in Lumuli village; and
CCROs will be delivered to Mangalali and Ibangamoyo villages.
ACTIVITY 2: Educate and build capacity of village land governance institutions and
individual villagers to complete the land use planning and CCRO process, effectively
manage land resources, respect women’s, youth and pastoralist’s land rights and build
agriculture-related business skills
LTA will provide trainings to village residents including women groups in five villages in
relation to land rights and beneficiary contribution.
ACTIVITY 3: Develop and refine the beneficiary contribution model that will allow
scaling up of rural land tenure registration in areas not directly reached by LTA
LTA will follow up with WEO and DED to obtain their approval to open bank accounts for
9 villages.
LTA will establish procedures for recovering cost from beneficiary contribution accounts.
ACTIVITY 4: Formalize LTA as a local non-governmental organization and build its
capacity to sustain operations as an independent organization to provide support to
district-level land governance institutions and other stakeholders to complete the land
use planning and CCRO process, effectively manage land resources, respect women’s,
youth and pastoralist’s land rights and build agriculture related business skills
LTA will start working the operationalization plan of LTA NGO
Activity 5: Raise awareness of the MAST technology within the GOT, civil society,
academia, and private sector, with the goal of increasing uptake of the MAST and
TRUST technology on a national level and enabling its use and replication on a self-
sustaining basis.
LTA will continue to provide technical support to District Land Authorities on MAST and
TRUST