FEASIBILITY STUDY OF PRESSURE=FED ENGINE A ER SPA'CE ... · ~9a-r~ 7 498 se-019-008-2 h-c part ii...
Transcript of FEASIBILITY STUDY OF PRESSURE=FED ENGINE A ER SPA'CE ... · ~9a-r~ 7 498 se-019-008-2 h-c part ii...
~ 9 a - r ~ 7 498
SE-019-008-2 H-C PART II
FEASIBILITY S T U D Y OF A PRESSURE=FED E N G I N E F O R A W ER REC SPA'CE SHUTTLE BO
VOLUME 111
PROGRAM ACQUISITION PLANNING PROGRAM COSTS
IS MARCH 1972
PREPARED FOR OEQRGE C. MARSHALL SPACE FLIGHT CENTER
NATIONAL AERONAUTICS A N D SPACE ADMlNlSTRATlON HUNTSVILLE, ALABAMA
SVSIEMS. 7iiW ORW?
O N e S P A C E P A R K * R E O O N D O B e A C H C A L I F O R N I A
https://ntrs.nasa.gov/search.jsp?R=19720018058 2020-06-19T06:36:44+00:00Z
SE-019-008 -2 H- C PART II
FEASIBILITY STUDY OF A PRESSURE-FED ENGIN F O R A W A T E R R E C O V E R A B SPACE SHUTTLE B O O S T E R
VOLUME 111
PROGRAM ACQUISITION PLANNING PROGRAM COSTS
15 MARCH 1972
DRD M A - 0 5 PREPARED FOR
GEORGE C. MARSHALL SPACE FLIGHT CENTER N A T I O N A L AERONAUTICS A N D SPACE A D M I N I S T R A T I O N
HUNTSVILLE, A L A B A M A
E LE
SYSTEMS GROUP
O N E S P A C E P A R K 0 R E O O N O O B E A C H * C A L I F O R N I A
SE - 0 I 9 - 00 8 - 2H -, B
PHASE A/B FINAL COST ESTIMATES DOCUMENT FOR
FEASIBILITY STUDY OF A PRESSURE-FED ENGINE FOR A WATER RECOVERABLE SPACE SHUTTLE BOOSTER
DPD 303 DR MA 05
15 March 1972
P repa red for
National Aeronautics and Space Administration
George C , Marshal l Space Flight Center
Huntsville, Alabama 35812
Under Contract
NAS 8-28218
P repa red by c(I-C.=&&& A. C. Ellings
Appro ve d by 8
Dr . Harland L. Burge P rogram Manager P r e s s u r e Fed Engine Study
SYSTEMS GROUP Q N E S P A C E P A R K * R E O O N O O B E A C H C A L l F O P N l A
This document contains inf?rmation PROPRIETARY TO TRW SYSTEMS GROUP. TRW XNC., and shall not be reproduced or transfermed to other documents. or disclosed to others. or used for any purpose other than that for which it i s furnished without the prior written permrssion of TRW Systems Group, TRW Inc.
ii
CONTENTS
Section Page
1 . 0 COSTING APPROACH, METHODOLOGY AND 1 RATIONALE
I. I Costing Approach
1.2 Ground Rules
1.3 Work Breakdown Structure
1 .4 Quantities of Hardware
I. 5 Vendor Survey
1 . 6 Refurbishment
1 . 7 F e e
2 . 0 COST SUMMARY 9
2. 1 Baseline Schedule 9 2 . 2 Maximum Success and Most Probable Schedule 10
2 . 3 Effect of Varying the Number of Flights 10
3 . 0 COST ESTIMATE BY WBS ELEMENT 11
3.1 P rogram Cost Summary
3.2 Engine Costs
11
11
4.0 TECHNICAL CHARACTERISTICS DATA 16
5 . 0 . TOTAL PROGRAM FUNDING SCHEDULES 17
5 .1 Baseline Schedule
5.2 Alternate Schedules
5 a 3
5.4 Manpower Requirements
Alternate Flight Mission Models
17
17
17
17
6.0 WORK BREAKDOWN STRUCTURE DICTIONARY 26
APPENDIX A ADDITIONAL STUDIES A-1
iii
This report has been prepared in partial fulfillment of NASA
Contract NAS 8-28218 entitled “Feasibility Study of a P r e s s u r e Fed
Engine for a W a t e r Recoverable Space Shuttle Booster. I r
This volume presents the Final Cost Estimates for the engine
configurations and schedules studied.
the TRW 4 February 1972 briefings at the Marshal l Space Center.
It updates the data presented in
This volume is prepared in accordance with Data Requirements
Description MF-030A. Work i s covered in Appendix A plus a summary of other cost studies
conducted and additional background data related to the basic study.
The data requested in the Additional Statement of
The complete final report for the study is covered in six volumes:
Executive Summary NASA NO. SE-019-008-2H-A
Technical Report S E - 0 1 9 - 0 0 8 - 2H - B
Program Acquisitional Planning Part 1 and P g r t 2
Design Data Book
SE- 0 19-008 - 2H-C
SE-0 19-0 11 -2H
Prel iminary De sign Package SE-019-013-2H
Mass Proper t ies Report SE - 0 1 9 - 0 1 5 - 2H
iv
I. 0 COSTING APPROACH, METHODOLOGY AND RATIONALE
I. 1 COSTING APPROACH
A detailed engineering approach was used in generating the cost
data and was based on consideration of the engine configuration, program
plan, specified engine deliveries and estimated spares and support
requirements for the fl ight program.
1. 2 GROUND RULES
I. 2. I Configurations Costed
The configurations of the P r e s s u r e Feed Space Shuttle Booster
Engine which were costed in detail included the following pr imary
characterist ics:
Thrust Level: I, 200 K lbs. and 600 K lbs .
Chamber Cooling : Regenerative and Duct
Thrust Control: Fixed and Throttlable
Thrust Vector Control: LITVC (LOX a s injectant)
Head End 2 axis Gimbal
c. g. I axis Gimbal (Hinge)
Hot gas injection for thrust vector control (GITVC) was considered,
however, technical considerations led to the conclusion that GITVC was
too high a r i sk program to mee t program objectives and costs were,
therefore, not prepared.
The detailed cost of the two axis and single axis gimballed configura-
tions were within a few percent of each other and, therefore only one s e t
of costs a r e presented in the summar ies .
The 1, 200 K lb. thrust regenerative chamber, gimballed engine was
used as a baseline for costing purposes.
1 .2 .2 Schedules Costed
I. 2 .2 .1 Alternate FMOF Schedules
Three schedules were costed. The baseline with the First Manned
Orbital Flight (FMOF) on March 1, 1978, a maximum success schedule
1
with the FMOF on August 1, 1977 and a mos t probable schedule with the
FMOF on January 1, 1979. Only the baseline configuration was used in
costing the maximum success and most probable schedules.
1.2.2.2 Flight Models
The baseline flight schedule, 445 flights, used in the costing is
shown in Table 1-1 also shown are the alternate f l i gh t schedules r ang ing
f rom 10 flights to 60 flights maximum pe r year whose operational costs
were estimated.
C Y Year 1978
Baseline 6
Option 1 6
2 6
3 6
4 6
Table 1-1
Baseline and Alternate Flight Schedules
79 80 8 1 82 83 8 4 85 86 87
15 2 4 32 41 50 59 60 60 60
10 10 10 10 10 10 10 10 10
15 20 20 20 20 20 20 20 20
15 2 4 32 40 40 40 40 40 40
15 2 4 32 41 50 59 60 60 60
Total
445
96
18 1
3 17
40 7
2
1.2.2.3 Engine Deliveries
The costs for delivered hardware were based on the following delivery
of vehicle se t s ( 7 engines per s e t for the 1, 200 K lb. thrust program and
10 engines for the 600 K thrust program).
Sys. Dev. Veh., PTA::
Flight Dev. Veh.
Dynamic Test Veh. w
Flight Veh. No. 1
2
3
7
8
Schedule
Baseline Max. Success
1- 1-75
3 - 1 - 7 6
6- 1 -76
7 - 1 -78
1 - 1 - 77:::::::::
7 - 1 -77
1- 1-78
1- 1-79
7- 1-79
1- 1-80
7 - 1-80
1- 1-75
3 - 1 - 7 6
-
10- 1-76::::::::
4- 1 -77
10- 1-77
4- 1 -78
10- 1-78
4- 1-79
10- 1 -79
4 -1 -80
Most Probable
4- 1-75
11- 1 -76
5 - 1 - 7 7
4 - 1 - 7 9
1 0 - 1 - 7 7 ::: :::::
4- 1 -78
I O - 1-78
10- 1-79
4 -1 -80
10- 1-80
4 - 1 - 8 1
9 1 - 1 - 8 1 10- 1 -80 1 0 - 1 - 8 1
10 7 - 1 - 8 1 4 - 1 - 8 1 4- 1 -82
Spare 1 - - -
Spare 2 - - - ::: 5 engines f o r 600 K lb. th rus t program
::: ::: Dummy Engine s
Engine for FMOF .*_ .,, .,, ,,. ,,. ?,.
3
The cost for the System Development, Flight Development, and
Dynamic Tes t and No. 1 flight vehicles were included in the non-recurring
costs, the balance in the Investment Phase.
I. 3 WORK i3REAKDOWN STRUCTURE
The work breakdown s t ruc ture is shown pictorially in F ig . 1- Y and
the cost methodology for each level 5 cell in Table 1- 2 .
1.4 QUANTITIES OF HARDWARE
The number of engines included in the costs were as follows:
P r o g r a m 1, 200 K lb. Thrus t 600 lb Thrust
Non-recurring
Development
Engine Development
PFC
F F C Deliverable
PTA F F C Flight No. I
Re cur ring
Deliverable
5
11
8
7 7 7
7 7
5
11
8
5 10 10
110
1.5 VENDOR SURVEY
The vendors f rom whom quotes were received a r e l isted in Table
The quotes were evaluated by increasing apparently low quotes, 1- 3. reducing those that appeared excessive, and averaging others .
1 . 6 REFURBISHMENT
In considering the cost of refurbishment, it was assumed that
engines would not be removed f rom the vehicle.
that only those components which were active would wear out and need
replacement.
Table 1- 4 which also shows the hardware breakdown used in costing.
It was assumed that f rom the standpoint of cost ,each active component
would be replaced once in 50 missions.
conservative.) As the ra te of wear out would decrease as the number
It was also assumed
The components considered as active a r e starred 0.7
(This assumption is considered
4
--I--
I -
5
a, k 5 c, V 5 k
;; $ 0
W 24 cd a, k M
2
d I d
a, k 5 M
iz
Table 1-2. Cost Methodology
Identification Number
WRS Comments Identification How E s t imated
xx 100 10 10
xx 100 40 10 Development Seconds of fir ing t ime $300/second at I , 200 K lb thrus t
xx 100 i o 20
Includes other fluids and gases anc losses .
N- at i . 8 c / e a l .
xx 100 10 30
xx 100 10 40 xx 100 10 50
xx 100 10 60 xx 100 10 70
xx 100 10 80
xx 100 20 10
xx 100 20 20
xx 100 20 20
xx 100 20 30
P r o g r a m Management and Engineering
Component Development
Development Hardware Procurement
Engine Tes t
Site Activation
GSE Procuremen t
Tooling
F ie ld Support
Di rec t Manhours
Vendor and TRW es t imates
Vendor es t imates fo r par t s . TRW Direc t Manhours assembly and checkout.
Direct Manhours
Architect and Engineering F i r m fo r s t ruc tua l modifications. TRW Manhours fo r installation of wiring, e tc .
TRW es t imate
Vendor es t imate and TRW manufacturing es t imate .
Direct Manhours.
DELIVERABLE HARDWARE
Covers Development through bench qualification.
Hardware through F F C . (See Section I . 4 fo r quantities. )
Covers activation and modification of EAFR Tes t Facil i ty.
Design engineering in xx 100 10 10
Components and Purchased P a r t s
Assembly
Product Assurance
Acceptance T e s t
Vendor and TRW es t imates
Direct Manhours pe r engine.
5 percent of Vendor and assembly cost .
Direct Manhours
TRW assembly
OVERHAUL AND REFURBISHMENT PARTS
xx 100 30 10 Overhaul and Refurbished Pe rcen t of Deliverable hardware I Parts I
xx 100 40 20
xx 100 40 30
P F C
F F C
Seconds of fir ing t ime $300/second a t I, 200 K lb thrus t
Second of fir ing t ime $300/second a t I , 200 K lb thrus t
xx 200 i o 10
xx 200 10 20
xx 200 10 30
xx 200 10 40
xx 200 20 10
xx 200 20 20
xx 200 20 30
xx 200 20 40
Deliverable Engines
GSE
Initial Spares
Acceptance Tes t Propellants
INVESTMENT
Vendor and TRW es t imates
TRW manufacturing es t imate
Pe rcen t of Deliverable engines
15 seconds of fir ing t ime p e r engine at $300/second a t 1, 200 K lb thrus t engine.
OPERATIONS
Flight Support
Operations
Overhaul and Refurbish- ment Parts
Propellants and Ancillary Fluids
Covers GSE delivered to Launch Si te
Di rec t Manhours
Direct Manhours
Pe rcen t of initial engine cos t based on wear out rate es t imate
Es t imated lo s ses f r o m flushing sys tem.
P r imar i ly fluids for flushing engines.
6
Table 1-3. Vendor Survey
SHUT OFF VALVES WHITTAKER PARKER
POSI -SEAL
SURGE SUPPRESSION (SCALED SHUT OFF)
L I T V C SHUTOFF VALVE
(SCALED SHUT OFF)
CONTROL , ELECTRONICS TRW
ENGINE PARTS FORGINGS
LAD I S H ARCTURU S
SHELL L A D I S H
GRANO
CENTRAL WESTERN
ACTUATORS (GIMBAL AND THROTTLING) TUBES MOOG ( E L E C T R I C HYDRAULIC) L A F E I L
HYDRAULIC RESEARCH ( E L E C T R I C HYDRAULIC)
6 END I X ( ELECTR I C-MECHAN I CAL ) BRAZED ASSEMBLY RYAN AERO
L I T V C SERVO INJECTOR SOLAR
MOOG ROHR L T V
APU A I RESEARCH
A B L A T I V E S HITCO
Table 1-4. Hardware I tems Costing Breakout
* CONTROL, ELECTRONIC AND WIRING
* INSTRUMENTATION * LOX SHUTOFF VALVE * LOX T R I M VALVE * LOX DUCT * RP SHUTOFF VALVE
* RP T R I M VALVE
* RP DUCT * I G N I T E R
INJECTOR
* ACTUATOR
* ACTUATOR ARM
* ACTUATOR MOUNT TOROID, FUEL
* PARTS AND ASSEMBLY
CHAMBER THRUST R I N G
* GIMBAL, R ING/HINGE
SHELL (AND RINGS) MANIFOLD (REGEN I N L E T ) TUBES COLLECTOR R I N G ( INJECTOR INTERFACE)
ASSEMBLY, BRAZE AND ND7
L I T V C (LOX)
* SHUTOFF VALVES
DUCT
MANIFOLD (VALVE I N L E T )
* VALVES CHAMBER MANIFOLD
* ACTIVE ITEMS FOR SPARES COSTING 7
of missions p e r engine is decreased, in o rde r to calculate the refurbish-
ment par t s for the various mission models (paragraph 1 . 2 . 2 . 2 ) the
logarithmic wear out curve shown in Fig. 1- 2 was constructed.
this curve it can be seen that for the 96 flight mission model, the r e -
placement par ts drop to 2 .69 f rom the 100% used for the 445 flight model.
Parts required for damage in recovery are covered by the Investment
Phase init ial spares .
From
AVE. ENGINE LIFE IOVEHICLES
Figure 1-2 . Cost Wear Curve for Replacement
1 . 7 FEE
All costs in this volume include fee (a t 8770) unless otherwise noted.
8
2 . 0 COST SUMMARY
2 . 1 BASELINE SCHEDULE
The total program and non-recurring costs are summarized below
for the baseline schedule.
Configuration Total P rogram Non- Recur ring 1200 K $M $M
A - Regenerative, Fixed Thrust, Gimbal TVC
B - Regenerative, Throttable, LITVC
C - Regenerative, Throttable, Gimbal TVC
D - Duct,Fixed Thrust., Gimbal TVC
600 K
25 2 114
29 6 133
27 5 127
230 104
E - Regenerative Fixed Thrust Gimbal TVC
230 9 1
F r o m the above it i s seen that the duct chamber configuration
results in the lowest cost program although not significantly lower than
the comparable regenerative engine in non-recurring costs.
A comparison of configuration B and C shows that LITVC results
in approximately a 9 percent increase in total funding costs. This results
f rom the high total cost of the 32 LITVC values used in that configuration.
In ear l ie r studies, it was shown that if the APU and actuator were
included, the gimballed configurative would be the m o r e expensive.
In comparing configuration A and C, it is seen that throttling
resul ts in a 9 percent increase in total program costs over the f ixed
thrust configuration.
F o r equivalent configuration (A and E), the 600 K lb thrust program
has lower total costs than the 1200 K lb thrust program, pr imari ly the
resul t of lower hardware and propellant costs in development.
9
2.2 MAXIMUM SUCCESS AND MOST PROBABLE SCHEDULE
F o r the baseline configuration (Regenerative,Fixed Thrust, Gimbal
TVC), the effect of schedule changes to the 445 f l i gh t program was a s follows:
Schedule
Baseline
Total P rogram Non- Recur ring SCM $M
252 114
Maximum Success 27 1 129
Most Probable 263 127
Both schedule modifications resul t in higher costs than the baseline.
The maximum success has higher costs to provide for m o r e redundancy
in development.
the baseline on the assumption that the level of development effort would
be maintained for the added 9 months.
The most probable schedule program cost increase over
2.3 EFFECT O F VARYING THE NUMBER OF FLIGHTS
The effect of varying the number of flights in the program (see
Section 1.2.2.2) on the recurr ing operational costs, assuming the baseline
configuration, is shown below.
i s covered in the non-recurring costs.
The operational cost of the first 5 flights
Recurring Phase
Total No. Flight Rate Flights (max.)
96 10
18 1 20
3 17 40
40 7 60
445 60
Average Cost No. cost Per Flight
Flights __c (SCM) (SCM )
9 1 22.28 0 .24
176 33.20 0.19
3 12 53 .24 0.17
402 75.60 0.19
440 81.56 0.19
The average cost per f l i gh t is essentially the same fo r each schedule.
Although the overhaul and refurbishment par ts cost decrease as per the
percentage shown in Section 1.6 with the decreasing number of flights, the
reduced labor efficiency compensates resulting in the essentially equal costs. The costs of the 96 flight model reflect the costs of minimum staffing.
10
3.0 COST ESTIMATE B Y WBS ELEMENT
3.1 PROGRAM COST SUMMARY
The program total funding requirements for the key configurations
and schedules costed a r e presented in Table 3-1 to level 5 except f o r
non-recurring costs which are summarized at level 4.
tions represent f o r the baseline schedule: (I) the 1200 K lb thrust base-
line configuration, fixed thrust, regenerative, gimballed; ( 2 ) the lowest
cost program, the fixed thrust, duct, gimballed engine; ( 3 ) the highest
cost program, the throttable, regenerative, LITVC configuration; and
(4 ) the throttable, regenerative, gimballed engine. Also shown to the
baseline schedule is the 600 K lb thrust baseline configuration, The
costs for the three schedules; baseline, maximum success and most
probable, are shown for the baseline configuration.
down of the level 4 cell DEVELOPMENT is given in table 3- 2 .
The configura-
The level 5 break-
3 . 2 ENGINE COSTS
3 . 2 . 1 No. of Engines
The number of all up engines costed in the program were a s follows:
WBS
Level - No. Identification No. of Engines
5 xx 100 10 30 Development Hardware 24 Procurement
4 xx 100 20 Delive rable Hardware 21
5 xx 200 10 20 Deliverable Engines 77
3.2.2 Sequence Number
The production sequence number of the first unit used in the r ecu r r -
ing phase is 37 for the 1200 K lb thrust program and 50 for the 600 K lb
thrust program.
curve for 1200 K lb thrust engine and 40th unit for the 600 K 1b thrust
engine .)
(34th unit f rom the standpoint of application of learning
3 .2 .3 Reference Unit Costs
The unit costs of the reference units for the configurations costed
a r e given in Table 3-3 along with the first unit costs.
11
e
12
S A U F
m 0 0 - - 0 1 0 1 N \ O m W t - N V O 0 OD 1 N * - + N 0 0 - $ N N N W W - < $ l $ I . . . . . N
m 0 0 - . - 0 1 0 N S 0 . W P - N P ' O m 1 O + - N 0 0
1 N N C O W M 1 W N N
. . . . . . .
Q N O * * 0 1 0 1 m 0 . O m P - N r r O Q 0 P - + . + - N 0 0 1
N N
$ N m C Q W - 1 1 I i I . . . . . . .
0 0 0 - - o m 0 m P - \ O m P - m 1 0 m Q m ~ - o P - o N N N C - W - i m W N N
. . . . . . .
0 o o . + - o - r o N N 1 W P - N P O \O P - P - * + N W O
0 0 0 - . + 0 1 0 Q N N C O W P - N 1 O 00 a r m * - ~ m o I P- . . . . . . m ~ m m m - m N N P-
1 0 0 - " 0 1 0 Q N P - C O P - a ) t - O .+ 1 W Q + O O O
1 N N P - W M m 1 N N
. . . . . . .
N 0 0 - + + 0 1 0 W P- W m m F W 1 0 N m ~ m Q + o o o I a
13
rn c, m 0 u c, .?I
s"
iz
s
c, m k
W 54 cd U .rl
a, U c; a, k a, ..u
2 c'c, I
rr, a, 9 cd
d
F
C O F O F c o r n
0 o * 0 4 ..t-
d
I n m m m C O Q
In t- o a ..P d
N rr)
d
t- rr)
d
d * d
m NI
d
m rr, d
- In rr)
.rl
0 * d
14
Also shown is the ratio of the first unit cost of the 1200 K lb thrust tcj
the 600 K lb thrus t engines which var ies between 1.32 and 1.41. It is
noted that the ratio of engines per vehicle se t 10/7 is 1.43, therefore,
there is not a large differential in the cost of delivered engines for the
two configurations.
f o r the two thrus t levels is 1.41, the engine cost for a given configuration
therefore, sca le approximately with the chamber diameter .
The ratio of the thrus t chamber cylindrical sections
3 .2 .4 Learning: Curve
A 95 percent s t ra ight line cumulative average learning curve was
used in calculating the engipe cost .
3 .2 .5 Confidence Level
A confidence rating of 3, medium high, has been applied to the
es t imates ,
type engine of the thrus t levels specified,have not been fabricated.
All c r i te r ia for this level of rating a r e met, except a proto-
3 .2 .6 First Unit Cost
The first unit costs a r e shown in Table 3-3. This cost was applied
to the first unit for PFF program and the learning curve applied to sub-
sequent units.
unit cost .
figuration is given in Table 3-4.
Development and PTA engines were costed at the f irst
A fur ther breakdown of the first unit cost of the baseline con-
Table 3 - 4 . F i r s t Unit Cost TRW PFE (Baseline Schedule and 1200 K l b Thrus t Coafiguration)
- --. _- - - . - Cos t (K$)
~- - - _ _ E l e c t r i c a l Cont ro ls In s t rumen ta t ion 72 .0
Part
and Wiring
LOX shu t off and t r i m va lves
R P shut off and t r i m va lves
P rope l l an t l i nes and bellows
Ignition s y s t e m
39.3
19.7
110.5
8 . 0
In j ec to r A s s e m b l y
C h a m b e r A s s e m b l y
T h r u s t mount and g i m b a l r ing
Sub-Tota l Components
QC, engine a s s e m b l y and t e s t
G and A and f ee
Tota l f i r s t unit - _
40.0
254.7
83 .8
628.0
161. 0
106.0
895 .0
15
4 . 0 TECHNICAL CHARACTERISTICS DATA
The p r imary parameters of the technical character is t ics which may
have a significant effect on cost a r e l isted below for the baseline
configuration
Sizing Weight
P e r f o rmanc e
Complexity
Isp delivered (90% of theoretical)
Combustion Stability
Number of missions (50 missions required - 100 mission goal)
No par t icular problem is anticipated with the above parameters .
The basic design philosophy was that of low cost.
in the study a r e therefore considered conservative.
90 percent of theoretical has not been a problem in scaling the basic
injector design up to 250 K lbs thrus t f rom 50 K lbs thrust and none is
anticipated in scaling fur ther to the thrus t levels required. Although the
single axial injector studied has been proven stable in a large number of
tes ts and is considered stable f r o m a theoretical point of view, it is l isted
a s a TCD parameter only because it has not been demonstrated at
the 600 K and 1200 K lb thrus t levels .
chamber will impact costs pr imar i ly because of the extent of the test pro-
g ram required to demonstrate its life.
The weights derived
Arriving at an Isp
The number of missions of the
In the LITVC configuration the maximum thrust vector angle will
impact costs as it determines the valve s ize which tends to increase
exponentially with the la rger s izes up to the maximum thrus t vector
angle obtainable. If the thrust vector angle specified is close to the
maximum obtainable, it may also require a significant number of tes ts to
determine the maximum position and angle.
16
5.0 TOTAL PROGRAMMING FUNDING SCHEDULES
5 . 1 BASELINE SCHEDULE
The t ime phased costs for the key configurations and the baseline
schedule (FMOF 3-1-78) a r e shown in Tables 5-1 through 5-4.
5 . 2 ALTERNATE SCHEDULES
The t ime phased costs for the maximum success schedule (FMOF
8-1-77) is shown in Table 5-5 and for the most probable schedule (FMOF
1-1-79), see Table 5-6.
5 . 3 ALTERNATE FLIGHT MISSION MODELS
The t ime phased costs for the alternate flight mission models a r e
shown in Table 5-7. (See Table 1-1 for Mission Models,)
5 . 4 MANPOWER REQUIREMENTS
The t ime phased TRW direct manpower requirements f o r the
program a r e given in Table 5-8.
directly associated with development of some engine components which
were estimated as TRW make decisions, i . e . , the e lectr ical controls
and injector assembly.
per s onnel .
These requirements exclude manpower
Also excluded a r e c ler ical and other supporting
1 7
18
I
21
T I
22
23
TABLE 5-7
SPACE SHUTTLE 1200 K PF ENGINE FUND ESTIMATE RECURRING OPERATIONS COST FOR ALTERNATE
MISSIONS MODELS
Baseline Schedule and Configuration
F M O F 3-1-78
I1977 I1978 11979 119801 19811 19821 19831 19841 19851 1'
91 FLIGHT MISSION MODEL
Opera t ions
F l i g h t Suppor t
Opera t ions
Overhau l and Refu rb i sh P a r t s
P r o p e l l a n t s
176 FLIGHT MISSION MODEL
Opera t ions
F l i g h t Suppor t
Ope ra t ions
Overhau l and Refu rb i sh Parts
P r o p e l l a n t s
312 FLIGHT MISSION MODEL
Opera t ions
F l i g h t Suppor t
Opera t ions
Overhau l and Refu rb i sh Parts
P r o p e l l a n t s
402 FLIGHT MISSION MODEL
Ope ra t ions
F l i g h t Suppor t
Ope ra t ions
Overhau l and Refu rb i sh Parts
P r o p e l l a n t s
F Y 78
+
2.13
0.98 0.90 0.18
0.07
-
- 2.77
1.35 1.05 0.27
0.10 _I
4.16
1.65 1.26 1.18
D. 07
-
_I
5.47
1.65 1.26 2.42
3 . 14
79
-
2.79
1.30 1.20 0.22
0.07
-
- 3.94
2.00 1.40 0.44
0. 10
-
- 6.43
2.40 2.08 1.81
0. 14
~
-..c-
9.14
2.50 2.08 4.42
0.14
80
-
I
2.79
1.30 1. 20 0.22
0.07
I
i=j.__
3.84
1.90 1.40 0.44
0.10
.-
- 6.62
2.40 2.32 1.81
0.09 - 9.17
2.41 2.32 4.42
0.02
-
81
-L
2.49
1.20 1.00 0.22
0.07
-
IILIIPP.
3.75
1.90 1.40 0.44
0.01
-
- 6.62
2.40 2.40 1.81
0.01
-
- 9.42
2.41 2.58 4.42
D.01
82
-
2.23 - 1.20 0.95 0.08
- 3.46
1.90 1.40 0.15
0.01
7
__c
5.02
2.00 2.40 0.61
0.01
-
- 7.07
2.14 3.42 1.50
0.01
-
85
I
2.12
1.10 0.95 0.07
-
=_i..
3.24
1.70 1.40 0.13
0.01
.__
--
4.87
1.95 2.40 0.51
0.01 ==.pp
6.79
2.05 3.48 1.25
0.01
7
86
161 1
2.00
1.00 0.95 0.05
-
- 3 . 11
1.60 1.40 0.10
0.01
-
II---
4.67
1.85 2.40 0.41
0.01
-
- 6.54
2.05 3.48 1.00
0.01
87
7
88 I 89 I
24
Table 5 - 8
.F ' Y
1973
7 4
75
76
77
78
79
80
8 1
82
83
8 4
85
86
87
88
89
Totals
Direct Manpower Requirements
Man Years
Non-Recurring Recur ring
106
148
172
172
1 48
8 2
25
853
13
19
8 4
123
127
131
126
136
140
140
140
140
75
1394
Total
106
i48
172
172
161
101
109
123
127 131
126
136
140
140
140
140
75
2247
25
I u cd
V
(d
.r( c,
c, m F:
.r( I
E 0 U
M G
cd S
.r( c, U cd
.ri c,
R M .r(
m w 0
ci 8 w 0
a G rd
w z z w * 5
a F: cd c,
5
c, m a, E
c,
5 0
Q w * m u 0 Q
0 0 In d
0 0 d 0
0 0 0
4
d M
X X X X
0 0 d tu 0
cy 0 * 0 d
0
0 0
d
d
0 0 d d
0
0 0
d
d
k a, P E
X x z x
2
X 4 a, S N rr)
0 0 0 0 d d
0 0
X x X X X X
X X
X X
m m In In m In
26
w 0 h s E
5 a, m
a G cd a,
2 c, u
9 G cd E k 0 w a a, k 5 e a,
M m d Q
.rl
k .
Z G 0 *& O d Ea,
M G 0 0
.I+ d
E
0 F
0
0 0
0
d
d
d
X X
Ln
x 3 E a, m m Id a, G M .I+
2 k 0 w a a, k 5 e a, k m c1 k cd a a G rd
.rl
m c,
2
2
4
0 u a a, m
k
i a d cd m c,
2
8: : E
G 0
0
0 N
0 0
0
d
d
d
X X
Ln
a, FI M .I+
G a a, c, a, I4
2 0 u w 0 h
z1 E a, m
d
h 3 E a, v) < 0 N 0 N 0 0
0
4
d
X X
Ln
27
a, : 2 5 m m
c, z a 0 k PI 0 rr)
0 N
0 0
0
d
d
X x LD
v) c, m a, E a, 0 d cd c, a a, 0
2 0 w 0 N 0 0 d
0 d
X X
Ln
0 rr)
0 0 4
X X m fd
i!i fd v)
G a,
A
c,
E m 2 2 3 w
a G cd
3 cd
kc, a , k bcd
d
A m
OPI 0
0 cr, 0 0
0
d
d
4
X X
Ln
rl
d d a d cd
x" 0 4
I3 z 4 4 4 W PI 0 d PI
0 w 0 0
0
d
d
X X
*
Ei cd k M 0 k PI w s E F4 0 a, 3 a,
d
n a, G M .rl
i
d
k 0 U 4
d a G cd
X 0 4
2
E' rd k bJl 0 k F4 V bl 61 k 0
W
d
d d a G rd
x 0 J
2?
i 2 M 0 k PI
u bl PI k 0 U U
d d a E: rd
X 0 J ..
zN
G 0
F:
.rl w
.rl
G
u
w d '-s E-c u 5
i3
m
2 fi M
a, d P cd k e, > 'ti 4 a, n 0
0
4
4
d E-c VI
F a, F a rn
a, k rd a VI d
d m w > z H
u 61 P i
u 6-I bl d
0 0 0 0 4 N r n d . l 0 0 0 0 0 W W + W 4
0 0 0 0 0 0 k O O O O 0 0
3 0 0 N
0 0 0 0 N N
0 0 (\y
0 4
X X
0
9 a ) . r ( 4 4 4 N N
0 0 3 0 0 0 0 4 4 U d 4 4
z x x x x X X x x x x x X
0 4
X X
0 0 d 4
x X x x Ln In
28
h I
d m 01 a,
2 k 3 w a, k
M G k a, a,
.rl rd F: rd rl 5 rd
a, 3 0
-f: a r: rd
d M .?I
2 M c c .ti
4 3 rd
a, + 0
E k 0 w
a, U 4
4 3
a c 6 c,
5! E a, M rd F: rd E
a a, c, rd .rl U 0 rn 2 c, k 0
W w w
E rd k M 0
ti u 5 d F tn
0 Q ?cl 4 w d w
c, k 0 a a 5 tn
2 .rl
I+
Fr 0
0 N
d
m
0 N
0 N
0 0 N
0 d
0 e 0 N
0 N
0 0 hl
0 N 0
0 N
0 0 N
0 0 N
k a, a 0
0 d
0 0 d
X X
E 2
0 4
X X
0 d
X x X X
X X
e In In In
2 9
Appendix A
ADDITIONAL STUDIES
1 .0 EFFECT ON COSTS AND SCHEDULE OF ENGINE LIFE
The effect on Development Costs (W.B.S. 10 100 10) of engine
life over the range of 20 to 100 mission duty cycles a r e shown in F i g .
A - I . duty cycles.
not for equal levels demonstrated reliability.
mission duty cycle development,
duty cycles; in the 50 mission duty cycle, 10 engines would be used to
demonstrate 50 + cycles; in the 100 mission duty cycle program, 6 engines
would be run f o r the 100 missions.
The baseline program was established to demonstrate 50 mission
Because of practical t e s t limitations, the costs shown are
F o r example in the 20
13 engines would be run for 20 plus
Also shown in Fig. A-1 is the difference in cost of propellant
(WBS 10 100 40) which has a relatively large change as the number of
demonstrated mission duty cycles i s changed.
A 20 mission duty cycle program could reduce the development
program time (through FFC) by 12 months and the 100 mission d.uty cycle
program would increase the engine testing phase by 8 months.
The baseline configuration, regener9tive thrust chqmber, fixed
thrust injector, and gimballed engine were assumed for these est imates .
2 . 0 REFURBISHMENT COSTS
The cost of refurbishment consists of labor, etc. (Operations
W.B.S. 10 200 20 20) and overhaul and refurbishment par ts
( W . B.S. 10 200 20 30).
costs is given in Section. 1 .6 of this report .
operations costs for alternate mission models all based on 9 flight
vehicles including and subsequent to the FMOF.
in Table 5-7 and plotting against the number of mission duty cycles per
engine as a percentage of the engine unit cost resul ts in Fig. A-2.
The philosophy for determination of the par ts Section 5.3 presents the
Propagating the data
A- 1
70
I- m 0 60 U
t W
n z 0
n
A
Y w
50
/
80 1 00
NUMBER OF MISSION DUTY CYCLES PER ENGINE
0
'0
0
F i g u r e A - I . E f f e c t on C o s t of D e m o n s t r a t e d E n g i n e Life
A -2
2 00
I-
;3 v
100 90
80
70
60
50
40
30
20
10 10 20 30 40
NUMBER OF MISSION DUTY CYCLES PER ENGINE
50
: I '
1 ; : I . .
I
I
i t
t i
1 I
i t I
b I
i I
r
t
i
f
I
F i g u r e A-2 . C o s t of R e f u r b i s h m e n t as P e r c e n t of E n g i n e Cos t V e r s u s E n g i n e Life
A - 3
3 . 0 ABLATIVE ENGINES
As an alternate to the regenerative thrus t chamber configuration,
the costs of programs based on a n ablative thrust chamber engine were
also estimated. Two types of engines were considered, 1) a reusable
engine in which the chamber would be relined af ter each flight and 2)
a ''throw away" engine which included additional simplifications, i. e . ,
single use valves.
The first unit and program costs for these configurations a r e tabulated
below and compared with the Baseline regenerative thrust chamber
configuration and Baseline 445 flight schedule .
Both also a s s u n e d a fixed thrust and gimballed TVC.
First Unit Program Costs
c o s t Total Non- recurring '
Baseline 895 25 2 114
Ablative Chamber 694 378 92
Throw Away Ablative 592 714 Chamber
86
Although the first unit costs and non-recurring costs are reduced,
the total program costs a r e considerably higher for the ablative engine.
A-4
4.0 FACILITIES
Review of the Edwards Rocket Test Fac i l i ty , Edwards Air Force Bgse, California and the f a c i l i t i e s modifications required has confirmed tha t the original plan f o r operation of tes t stands 2A and 1B i s the most ef- fec t ive from a f a c i l i t y cost standpoint. development program on the schedule shown by the Prel iminary Development Plan dated 10 February 1972, t e s t stand 2A and i t s a$sociated control center will have t o be activated immediately upon i n i t i a t i o n of the program. The costs associated w i t h the control center a r e primarily fo r act ivat ing the recording f a c i l i t y . The additional increment f o r activating the 1B control panel and checkout of land lines was shown i n the TRW labor cos t f o r the activation of s tand 1 B . The costs f o r act ivat ing the 2A position and i t s control center would therefore be a s follows:
I p order to perform the in jec tor
TRW Labor $145,000 Purchased Parts 21 6,000 Purchased Services
C1 eani ng 65,000 Metro1 ogy 107,000
Total $553,000
The additional cos t fo r act ivat ing Stand 1B would be as follows:
TRW Labor $ 450,000 Modification t o 1B 1,600,000 Water Flow Fac i l i ty 150,000
Total $2,200,000
On 1 March 1972 a v i s i t t o the Edwards Rocket Test Faci l i ty fo r the purpose of reviewing engine test stands 1C and 1D as possible sites f o r tes t ing of pressure fed boosters disclosed the following:
1 . The tes t stands a re i n excellent condition. 1D i s currently i n operation while 1C is i n an excellent s t a t e of preservation. control center cmmon t o the two stands is currently i n an oper- ational s t a tus .
The
A-5
2 . The physical separation between the two t e s t s tands will make maintenance of the t e s t schedule eas ie r than on stand 1B.
3 . The separation distance between the stands precludes the use of a common set of run t a n k s .
4. The use of a common control center introduces the same schedul- i n g problems t h a t a re presented on s t and 1B.
The costs fo r converting stands 1C and 1 D t o pressure fed booster re- quirements a re estimated t o be as follows:
TRW Labor $ 100,000 Purchased Parts 1 00 , 900 Modification of stand 1 C 1 , 600 , 000 Propel 1 an t Sys tern ModificatiQn of stand 1 D 1 , 600 , 000 Propel 1 an t System Ins ta l la t ion of Water 15O,OOO F1 ow Faci 1 i ty
$3 , 550 , 000
Total cos t for lC, 1 D and 2A is therefore $4,083,000 as compared t o $2,733,000 for 1 B and 2A. The costs presented above are less G&A and f ee which a re included i n the main body of t h i s report.
In planning the modifications of the Edwards Rocket Test Fac i l i ty , TRW has been working i n c lose association w i t h Norman Engineering Company o f Culver City, California. The costs and schedules for the modification of the 1 B t e s t s t and have been prepared by them i n accordance w i t h engineering direct ion from TRW. The schedule i s based upon the release o f a purchase order f o r procurement of the longest lead time item, namely the propellant run tanks by the second week a f t e r go-ahead; as soon as the tank spec i f i - cation can be released. .On 29 February the realism of the proposed schedule was discussed w i t h Mr. E . F . S l a t t e ry , Vice President of Norman Engineering Company. Pittsburg-DesMoines Steel Company who confirmed a 9 m o n t h schedule f o r desigt,, fabr icat ion, erect ion, and t e s t of the run t anks . A detai l breakdown o f the a c t i v i t i e s required t o ac t iva te the 1B test stands i s given i n Part I o f t h i s
report . activated on the same schedule as shown for stand 1 B ; the second can be activated 3 months l a t e r .
As a r e s u l t of t h i s conversation Mr. Sla t te ry contacted the
If t e s t stands 1 C and 1 D a r e used, the f i r s t t e s t stand can be
A- 6