Farmington Public Schools · The auditorium project started on December 22; the seating has been...
Transcript of Farmington Public Schools · The auditorium project started on December 22; the seating has been...
![Page 1: Farmington Public Schools · The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed](https://reader033.fdocuments.net/reader033/viewer/2022060708/6074cb9c555edd5b27105d02/html5/thumbnails/1.jpg)
Farmington Public Schools
Farmington High School
December 30, 2016
![Page 2: Farmington Public Schools · The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed](https://reader033.fdocuments.net/reader033/viewer/2022060708/6074cb9c555edd5b27105d02/html5/thumbnails/2.jpg)
Project Overview
The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed and electrical demolition is underway.
![Page 3: Farmington Public Schools · The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed](https://reader033.fdocuments.net/reader033/viewer/2022060708/6074cb9c555edd5b27105d02/html5/thumbnails/3.jpg)
Project Overview
The new auditorium entrance and ticket booth have been constructed and will act as the construction separation for the project.
![Page 4: Farmington Public Schools · The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed](https://reader033.fdocuments.net/reader033/viewer/2022060708/6074cb9c555edd5b27105d02/html5/thumbnails/4.jpg)
Project Overview
The painting of the auxiliary gym is underway and will be complete when students return.
![Page 5: Farmington Public Schools · The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed](https://reader033.fdocuments.net/reader033/viewer/2022060708/6074cb9c555edd5b27105d02/html5/thumbnails/5.jpg)
Project Overview
The new dehumidification unit for the pool has been set. Duct work on the roof to the pool area can now proceed.
![Page 6: Farmington Public Schools · The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed](https://reader033.fdocuments.net/reader033/viewer/2022060708/6074cb9c555edd5b27105d02/html5/thumbnails/6.jpg)
Project Overview
The first set of bathrooms has been completed and reopened to the students.
![Page 7: Farmington Public Schools · The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed](https://reader033.fdocuments.net/reader033/viewer/2022060708/6074cb9c555edd5b27105d02/html5/thumbnails/7.jpg)
Project Overview
18 classrooms have been renovated with fresh paint new flooring and new furniture. 10 new unit ventilators were installed in the second floor classrooms over break; existing unit ventilators in other areas are being updated with new control valves.
![Page 8: Farmington Public Schools · The auditorium project started on December 22; the seating has been removed, the folding partitions have been demolished, the fire curtain has been removed](https://reader033.fdocuments.net/reader033/viewer/2022060708/6074cb9c555edd5b27105d02/html5/thumbnails/8.jpg)
Two Week Look Ahead
Week of January 2 • Continue with the renovation of the second bathroom set • Demolition of the plaster ceiling in the auditorium • Demolition of the control rooms in auditorium • Continue with corridor water line replacement • Continue with renovation of classrooms
Week of January 9
• Continue with demolition of plaster ceiling in auditorium • Start demolition of existing catwalk • Start erection of scaffolding in auditorium