Farmington Public Schools Bid Package #1 & #2
Forest Elementary and East Middle School Construction Progress Report
Monday May 16, 2016
Jon Riebe- Farmington Public Schools Brian Smilnak – Wakely Associates/A/E
Paul Wills- Plante Moran CRESA Scott Smith- Plante Moran CRESA
Rich Griffin – McCarthy & Smith Project Superintendent Leo Cartier- McCarthy & Smith Project Superintendent
Ryan Black – McCarthy & Smith Project Engineer Aaron Phillips – McCarthy & Smith Project Manager
![Page 2: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools](https://reader033.fdocuments.net/reader033/viewer/2022050411/5f87e70082d91b42b1537d18/html5/thumbnails/2.jpg)
Current Status
Shoreview Electric installing temporary hanger wires on lights and mobilizing in gymnasium for over head piping.
East Middle School
![Page 3: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools](https://reader033.fdocuments.net/reader033/viewer/2022050411/5f87e70082d91b42b1537d18/html5/thumbnails/3.jpg)
Current Status
East Middle School gymnasium
Overhead piping
![Page 4: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools](https://reader033.fdocuments.net/reader033/viewer/2022050411/5f87e70082d91b42b1537d18/html5/thumbnails/4.jpg)
Current Status
Forest Elementary
Set up and layout for new footings.
![Page 5: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools](https://reader033.fdocuments.net/reader033/viewer/2022050411/5f87e70082d91b42b1537d18/html5/thumbnails/5.jpg)
Current Status
Forest Elementary
Rebar installation
![Page 6: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools](https://reader033.fdocuments.net/reader033/viewer/2022050411/5f87e70082d91b42b1537d18/html5/thumbnails/6.jpg)
Packing up books at Forest Elementary.
![Page 7: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools](https://reader033.fdocuments.net/reader033/viewer/2022050411/5f87e70082d91b42b1537d18/html5/thumbnails/7.jpg)
Plan Ahead
CEI Electric mobilized at Lanigan Elementary to start overhead piping and data piping. Shoreview Electric mobilized at Farmington High on 5/12/16 and will start overhead piping this week. McCarthy & Smith plans on setting up the job site trailers at each school by the end of May.