Farley Initial Exam 2012-301 General Correspondence. · exam simulator scenarios and JPMs and the...
Transcript of Farley Initial Exam 2012-301 General Correspondence. · exam simulator scenarios and JPMs and the...
Southern NuclearOperating Company, Inc.
FNP-20 11-0075 -TRNAshford, Aabama 36312
) Tel 334899.5156Fax 334.814.4661
November 11,2011SOUTHERNi
COMPANYMr. Bruno Caballero Energy to Serve Your Wor1€I’U.S. Nuclear Regulatory Commission, Region II245 Peachtree Center Ave., NE, Suite 1200Atlanta, Georgia 30303-1257
Dear Mr. Caballero:
You will find enclosed the exam material as required by NUREG 1021, “Operator Licensing ExaminationStandards for Power Reactors”, Revision 9, supplement 1. All exam materials MUST be withheld frompublic disclosure until after the examinations are complete.
Enclosed you will find the printed paperwork listed below for the upcoming examination scheduled forthe week of June 18, 2012 at Parley Nuclear Plant.
• ES-20 1-2, Examination Outline Quality Checklist• ES-201-3, Exam Security Agreement• ES-301-1, Administrative Topics Outline• ES-301-l, Administrative Topics Outline with explanation• ES-301-2, Control Room/In-Plant Systems Outline• ES-301-2, Control Room/In-Plant Systems Outline with explanation• ES-301-3, Operating Test Quality Checklist• ES-30l-4, Simulator Scenario Quality Checklist• ES-301-5, Transient and Event Checklist• ES-301-6, Competencies Checklist• ES-D-1, Outline Submittal, forms for Six (6) Simulator exams• Excel spreadsheets for the NRC exam simulator scenarios and JPMs and the Simulator Audit
exam• Audit Exam Operating test — (4 simulator scenarios, 301-1 form and 301-2 form)• ES-301-1 and ES-301-2 for the past two NRC exams
In addition to the above printed material, there is one CD-R provided that includes an electronic versionof the above listed materials and the reference disk for 10-10-2011. All of this is provided to ensurecomplete and proper documentation for the upcoming examination.
If you have any questions, please contact Gary Ohmstede, Billy Thorton or Howard Fitzwater at 334-8 14-4758.
Sincerely,
Gary OhmstedeLead Instructor- Exam Development
Enclosure: GTOcc: File
Southern NuclearOperating Company, Inc.Post Office Drawer 470Ashford, Alabama 36312
Tel 334899.5156Fax 334.814.4661
March 1, 2012
Mr. Bruno CaballeroU.S. Nuclear Regulatory Commission, Region II245 Peachtree Center Ave., NE, Suite 1200Atlanta, Georgia 30303-1257
Dear Mr. Caballero:
FNP-2012-001l -TRN
SOUTHERNAgSCOMPANY
Energy to Serve Your World
You will find enclosed the exam material as required by NUREG 1021, “Operator Licensing ExaminationStandards for Power Reactors”, Revision 9, supplement 1. All exam materials MUST be withheld frompublic disclosure until after the examinations are complete.
Enclosed you will find the printed paperwork listed below for the upcoming examination scheduled forthe week of June 18, 2012 at Farley Nuclear Plant.
• 25 SRO written exam questions with feedback and analysis• 1 simulator JPM• 1 Admin JPM
In addition to the above printed material, there are two CD-Rs provided that include an electronic versionof the above listed materials and a reference disk for 2-27-2012. The 25 SRO questions and the 2 JPMsare our early submittal as requested. The remaining 75 RO questions and the entire operating exam withthe proper forms will be sent on March 9, 2012.
If you have any questions, please contact Gary Ohmstede, Billy Thornton or Howard Fitzwater at 334-8 14-4758.
Enclosure: GTOcc: File
Exam Development
Southern NuclearOperating Company, Inc.
Post Office Drawer 470Ashford, Alabama 36312
Tel 3348995156Fax 334814.4661 SOUTHERN
COMPANY
March 8, 2012
Mr. Bruno CaballeroU.S. Nuclear Regulatory Commission, Region II245 Peachtree Center Ave., NE, Suite 1200Atlanta, Georgia 30303-1257
Dear lVIr. Caballero:
You will find enclosed the exam material as required by NUREG 1021, “Operator LicensingExamination Standards for Power Reactors”, Revision 9, supplement 1. All exam materials MUST bewithheld from public disclosure until after the examinations are complete.
Enclosed you will find the printed paperwork listed below for the upcoming examination scheduled forthe week of June 18, 2012 at Farley Nuclear Plant.
• ES-20 1-2, Examination Outline Quality Checklist• ES-20 1-3, Exam Security Agreement• ES-301-l, Administrative Topics Outline for RO and SRO exams• ES-30 1-2, Control Room/In-Plant Systems Outline• ES-30 1-3, Operating Test Quality Checklist• ES-301-4, Simulator Scenario Quality Checklist• ES-3 01-5, Transient and Event Checklist• ES-301-6, Competencies Checklist• ES-401-2 and -3, PWR Examination Outline• ES-401-4, Record of Rejected K/As• ES-401 -6, Written Examination Quality Checklist• ES-D- 1, Outline Submittal, forms for Six (6) Simulator exams• Two (2) separate bindings containing the 75 question RO Written Exam, and includes the
references for the RO exam and the SRO exam• One (1) binding containing the Administrative Topics JPMs and Simulator JPMs and In-
plant JPMs• One (1) binding containing the six (6) simulator scenarios and Excel spreadsheets for the
NRC exam simulator scenarios and JPMs and the Simulator Audit exam
In addition to the above printed material, there is one CD-R provided that includes an electronicversion of the above listed materials plus the following:
• A copy of the written examination (25 SRO questions and 75 RO questions), references for theRO exam and SRO exam, and the cover sheet for the SRO exam
• A copy of all simulator scenarios, JPMs and Admin JPMs• A copy of the Audit exam with the ES-D-l outlines for 4 scenarios, ES-301-1 and -2 forms for
the operating exam• The past 2 operating exams ES-301-1 and -2 forms
(‘
In addition, we provided the 25 question SRO exam one week early. This is not included in thissubmittal on paper but is in the folder titled “1 1LT35 Written” on the CD-R and has not changed sinceour early submittal. Also included in the early submittal was two (2) JPMs. These have been includedin printed paperwork for your ease of review.
All of this is provided to ensure complete and proper documentation for the upcoming examination.If you have any questions, please contact Gary Ohmstede, Billy Thornton or Howard Fitzwater at 334-814-4758.
Sincerely,
4ry OhmstedeLead Instructor- Exam Development
Enclosure: GTOcc: File
Southern NuclearFNP20120020 -TRN
Operating Company, Inc.Post Office Drawer 470Ashford, Alabama 36312
Tel 334.899. 56SOUTHERN
COMPANY
May 31, 2012
Mr. Bruno CaballeroU.S. Nuclear Regulatory Commission, Region II245 Peachtree Center Ave., NE, Suite 1200Atlanta, Georgia 30303-1257
Dear Mr. Caballero:
You will find enclosed the exam material as required by NUREG 1021, “Operator Licensing
Examination Standards for Power Reactors”, Revision 9, supplement 1. All exam materials MUST be
withheld from public disclosure until after the examinations are complete.
Enclosed you will find the printed paperwork listed below for the upcoming examination scheduled for
the week of June 18, 2012 at Farley Nuclear Plant.
• ES-201-2, Examination Outline Quality Checklist
• One copy of the current ES-201-3, Exam Security Agreement
• ES-301-l, Administrative Topics Outline for RO exam
• ES-301-1, Administrative Topics Outline for SRO exam
• ES-301-2, Control Room!In-Plant Systems Outline
• ES-301 -3, Operating Test Quality Checklist
• ES-401-2 and -3, PWR Examination Outline
• ES-401-4, Record of Rejected K/As
• ES-401-6, Written Examination Quality Checklist
• One (1) 75 question RO written exam with a cover sheet
• One (1) 100 question SRO written exam with a cover sheet
• References for the SRO and RO exam
• The answer key for the Written Exam consisting of the header information,
Feedback and Notes section of the exam V
• An answer key bubble type sheet for each exam printed from LxR
• An answer key by number and KA value
• Eight (8) Administrative JPMs
• Eleven (11) Control Room/In-Plant JPMs
In addition to the above printed material, there is one CD-R provided that includes an electronic
version of the above listed materials.
4’ ,,Y
As discussed the following will be sent on Monday June 4, 2012 when the scenarios have beendetermined and candidate schedule for the simulator exam is developed.
• ES-301-4, Simulator Scenario Quality Checklist• ES-301-5, Transient and Event Checklist• ES-301-6, Competencies Checklist• ES-D-l, Outline Submittal, forms for the Simulator exams• The simulator scenarios for scenarios 2, 3, 4 5 and 6
All of this is provided to ensure complete and proper documentation for the upcoming examination.If you have any questions, please contact Gary Ohmstede, Billy Thornton or Howard Fitzwater at 334-8 14-4758.
Sincerel
ary OhmstedeLead Instr ctor- Exam Development
Enclosure: GTOcc: File
Thomas A. Lynch Southern Nuc’earVice President - Farley Operating Company, nc.
Farley Nuclear PlantPost Office Drawer 470Ashford, Alabama 36312
Tel 334.814.4511Fax 334.8144728
SOUTHERN2COMPANY
June 1,2012FNP-2012-0019-TRN
Mr. Victor McCreeRegional Administrator, Region IIU.S. Nuclear Regulatory Commission245 Peachtree Center Ave., NE, Suite 1200Atlanta, GA 30303-1257
Attention: Mr. Bruno Caballero
Dear Mr. Caballero
Fancy Nuclear Plant formally request the NRC administer an operating test and a written examinationbeginning June 18, 2012 to candidates whose final Personal Qualification Statement-Licensee andCertification of Medical Examination by Facility licensee forms are included with this submittal.
If you should you have any questions regarding this matter, please contact Mrs. Donna Christiansen at334-814-4513 or Mr. Brian Reed at 334-814-4981.
Sincerely,
T.A.LynchVice President - Fancy
TAS/BWR
FNP-2012-0023 -TRNSouthern NuclearOperating Company, Inc.Post Office Drawer 470Ashford, Alabama 36312
Tel 3348995156Fax 334814.4661 SOUTH ERN
COMPANY
June 4,2012
Mr. Bruno CaballeroU.S. Nuclear Regulatory Commission, Region II245 Peachtree Center Ave., NE, Suite 1200Atlanta, Georgia 30303-1257
Dear Mr. Caballero:
You will find enclosed the exam material as required by NUREG 1021, “OperatorLicensing Examination Standards for Power Reactors”, Revision 9, supplement 1. Allexam materials MUST be withheld from public disclosure until after the examinationsare complete.
Enclosed you will find the printed paperwork listed below for the upcomingexamination scheduled for the week of June 18, 2012 at Farley Nuclear Plant.
• ES-301-3, Operating Test Quality Checklist• ES-301-4, Simulator Scenario Quality Checklist• ES-301-5, Transient and Event Checklist• ES-301-6, Competencies Checklist• The simulator scenario schedule as discussed with candidates names• The Simulator Exam Scenario outlines for Five (5) Simulator exams, in
which each include:o The current ES-D-1o Scenario Outlines and Booth Operator Guideo ES-D-2, Required Operator Actionso The crew briefing sheet and Turnover sheet
In addition to the above printed material, there is one CD-R provided that includes anelectronic version of the above listed materials.
All of this is provided to ensure complete and proper documentation for the upcomingexamination.If you have any questions, please contact Gary Ohmstede, Billy Thornton or HowardFitzwater at 334-814-4758.
Enclosure: GTOcc: File
Sincerely,
Lead Exam Development
Southern NuclearOperating Company, Inc.Post Office Drawer 470Ashford, Alabama 36312
Tel 334.8995156Fax 334.814.4661
SOUTHERNCOMPANY
May 04, 2012
Mr. Bruno CaballeroU.S. Nuclear Regulatory Commission, Region II245 Peachtree Center Ave., NE, Suite 1200Atlanta, Georgia 30303-1257
Mr. Caballero:
As discussed in our phone conversation this morning, we have enclosed a CD-R disc whichcontains the password protected files (2) of the 2012 Written Examination. These files representthe written exam as modified from the original submission based upon our discussions, reviewsand Operations Management review of those changes.
Also, included is a password protected electronic copy of the ES-401-4.
Sincerely
Howard Fitzwater
Facility Author
Enclosure: HBFcc: File
Southern Nuclear FNP-2012-0026 -TRNOperating Company, Inc.Post Office Drawer 470Ashford. Alabama 36312
Tel 334899.5156Fax 334.814.4661 SOUTHERN
COMPANY
July 3, 2012
Mr. Bruno CaballeroU.S. Nuclear Regulatory Commission, Region II245 Peachtree Center Ave., NE, Suite 1200Atlanta, Georgia 30303-1257
Dear Mr. Caballero:
You will find enclosed the exam material as required by NUREG 1021, “Operator LicensingExamination Standards for Power Reactors”, Revision 9, supplement 1.
Enclosed you will find the printed paperwork required upon completing the site administeredInitial Written Examination by NUREG 1021, “Operator Licensing Examination Standards forPower Reactors”, Revision 9, supplement 1.comjnt.tpclngeor delete any question on the exam.
The Form ES-201-3, Examination Security Agreement, has not been completed but aworking copy of the original is included. The final signed original will be sent at a later datewhen all signatures have been acquired.
Enclosed are the following:• A copy of the ES-201-3, Examination Security Agreement.• A SCANTRON form Marked as KEY and an LXR TEST KEY report.• Statistics for each question for the RO and SRO exams.• Preliminary grades (RO, SRO-only, SRO-OVERALL scores).• Ten (10) original exam answer SCANTRON sheets: 6 SRO & 4 RO for use in grading
the exam and copies of the same.• Ten (10) original signed exam cover sheets and copies of the same: 6 SRO & 4 RO.• A copy of each applicant’s LXR generated individual scores report attached to his
answer sheet.• NMP-TR-423-F15 which list the questions asked by the applicants during the exam
with the responses given.• Individual question sheets that the students filled out and the proctor returned to the
student with the answer.• List of Applicants and docket numbers.• Seating chart utilized during the written exam.• Exams as administered (one 75 question RO exam and one 100 question SRO exam).• One entire 100 question exam key with feedback.• Compilation of Comments collected from the applicants from the post-exam review
with facility response/action stated. This document also identifies the facility reviewedHIGH-Miss questions.
FNP-2012-0026 -TRNSouthern Nuc’earOperating Company, Inc.Post Office Drawer 470Ashford, Alabama 36312
Tel 334.8995156Fax 334.814.4661 SOUTHERN
COMPANY
If you have any questions, please contact Gary Ohmstede, Billy Thornton or HowardFitzwater at 334-814-4758.
Enclosure: GTOcc: File
Lead In ictor- Exam Development
Southern Nuclear FNP-2012-0027 -TRNOperating Company, Inc.Post Office Drawer 470Ashford, Alabama 36312
Tel 334.899.5156Fax 334.814.4661 SOUTHERN
COMPANY
July 12, 2012
Mr. Bruno CaballeroU.S. Nuclear Regulatory Commission, Region II245 Peachtree Center Ave., NE, Suite 1200Atlanta, Georgia 30303-1257
Dear Mr. Caballero:
You will find enclosed the exam material as required by NUREG 1021, “Operator LicensingExamination Standards for Power Reactors”, Revision 9, supplement 1.
Enclosed you will find the completed ES-201-3, Exam Security Agreement, paperworkrequired upon completing the site administered Initial Written Examination by NUREG 1021,“Operator Licensing Examination Standards for Power Reactors”, Revision 9, supplement 1.
If you have any questions, please contact Gary Ohmstede 334-814-4758.
Sincerely,
Gary OhmstedeLead Instructor- Exam Development
Enclosure: GTOcc: File