Far Experimental Hutches
description
Transcript of Far Experimental Hutches
David Saenz
FAC Review [email protected]
November 11, 20081
SLAC National Accelerator Laboratory
Far Experimental Hutches
David Saenz
Project Manager
David Saenz
FAC Review [email protected]
November 11, 20082
SLAC National Accelerator Laboratory
Far Experimental Hall Hutches
Scope
Design Status/Deliverables
Schedule
Estimated Construction Cost
Present Status
Summary
David Saenz
FAC Review [email protected]
November 11, 20083
SLAC National Accelerator Laboratory
ScopeApproximately 7,800sf of new facilities for three Hutches, Control Rooms and Common Rooms
Current approved specifications are well defined and present no major challenges
David Saenz
FAC Review [email protected]
November 11, 20084
SLAC National Accelerator Laboratory
Scope – Cont’dUtilities (MEP)
Process chilled water
Chilled water
Compressed air @ 100psi
HVAC 72° ± 1 °F
RH 45% ± 10%
24” cable trays
Standard lighting
Surface mounted conduits
Standard 110V and 208V outlets
1 ton capacity cranes
Radiation protection
Standard door sizes
Existing common floor
Standard wall/ceiling finishes
No acoustic requirements
David Saenz
FAC Review [email protected]
November 11, 20085
SLAC National Accelerator Laboratory
Engineering Specification DocumentsLCLS ESD’s approved by key stake-holders.
ESD 1.9-112
Hutch 4
ESD 1.9-113
Hutch 5
ESD 1.9-114
CXI Room
ESD 1.9-115
XCS Room
ESD 1.9-116
Common Room
ESD 1.9-117
David Saenz
FAC Review [email protected]
November 11, 20086
SLAC National Accelerator Laboratory
Access Tunnel (looking south)
David Saenz
FAC Review [email protected]
November 11, 20087
SLAC National Accelerator Laboratory
FEH (looking west)
Existing utility systems in place
David Saenz
FAC Review [email protected]
November 11, 20088
SLAC National Accelerator Laboratory
FEH Floor Plan/Section by DGA
Building Section
Floor Plan
David Saenz
FAC Review [email protected]
November 11, 20089
SLAC National Accelerator Laboratory
HVAC Floor Plan by DGA
David Saenz
FAC Review [email protected]
November 11, 200810
SLAC National Accelerator Laboratory
Design StatusDesign was awarded Oct 10, 08
Title I completed on Nov 6, 08
Internal design review currently in process and will be completed on 11/13/2008
Title II 60% scheduled for Jan 15, 09
Title II 90% scheduled for Feb 25, 09
Title II 100% scheduled for Mar 4, 09
David Saenz
FAC Review [email protected]
November 11, 200811
SLAC National Accelerator Laboratory
Design Deliverables
√ Existing Conditions Report
√ 30% Design Review
√ Structural Design Review
√ Preliminary Cost Estimate
60% Design Review
Detailed Cost Estimate
90% Design Review
Engineering Coordination Presentation
Updated Cost Estimate
100% Design Review
Final Cost Estimate
Issue of Issue For Construction (IFC) documents
Value Engineering
•All deliverables are expected to be provided on time!
•Sufficient quantity of deliverables are established to manage progress and complete development
David Saenz
FAC Review [email protected]
November 11, 200812
SLAC National Accelerator Laboratory
Construction Schedule9 months including pre-construction activities to commence Mar 09 and complete Dec 09Need to revise schedule to reflect construction award Mar 09 for major packages
David Saenz
FAC Review [email protected]
November 11, 200813
SLAC National Accelerator Laboratory
Estimated Construction CostInitial estimate provided by AE valued at $3.6M
Includes direct and in-direct cost and escalation
Strategy for construction delivery method is consistent with expectations
Design → Bid → Build
Current WBS (1.9.3.14.2) budget is $4.1M (including contingency)
David Saenz
FAC Review [email protected]
November 11, 200814
SLAC National Accelerator Laboratory
SummaryDesign parameters are clearly defined
Sufficient quantity of deliverables are in process
Title I complete
Title II in process
AE firm has provided alternatives solutions for higher priced items i.e. structural steel
David Saenz
FAC Review [email protected]
November 11, 200815
SLAC National Accelerator Laboratory
end of presentation