Failures - Sleipner a - North Sea Oil Platform Collapse

8
Actions Wiki Home Recent Changes Pages and Files Members Search Navigation Home M Kevin Parfitt - Moderator Peer Reviewers Building Failures Forum (Blog) Wiki Installments Building Enclosure Bridge & Infrastructure Building Failure Cases Failures in the News Fire Case Studies Industrial Disasters Natural Disasters Stadiums & Arenas Systems & Failure Categories Weird Failures Wiki Contributions Contribute a New Case Comment on a Case Editing Instructions Wikispaces Help Resources Journal of Performance TCFE of ASCE MatDL Failures Case Studies Links - See Building Failures Forum In Planning Stages: Illustrated Glossary Failures Photo Library Penn State AE About AE 537 Sleipner A - North Sea Oil Platform Collapse Edit 8 147 Figure 2: Partially completed buoyancy cells to be floated to a fjord Table of Contents Background Typical Condeep Platform The Sleipner A-1 The Accident Summary of Conditions Timeline Likely Causes Verification Reactions and Outcome Revised Design Philosophy The New Sleipner A Platform References Works Cited Works Read Additional Reading Figure 1: Simplified rendition of a typical Condeep platform built for natural gas drilling in the North Sea Sleipner A-1 Gravity Base Structure 23 August 1991 in the Gandsfjord outside of Stavanger, Norway Ksenia Tretiakova -Integrated BAE/MS Candidate (Dec 2012) in the Department of Architectural Engineering, Pennsylvania State University Please note: All images in this article are generated by the author; In-text figure references include credit for any resources referenced during the illustration. Background The original Sleipner A (SLA-1) platform was to be used for oil and natural gas drilling in the Sleipner gas field in the North Sea. It was built in the fashion of typical Condeep platforms (as seen in Figure 1 [1 ][7 ] ), but sank during a controlled ballast test, unlike other platforms with similar designs. It was found that a combination of poor geometry andinadequate design were the causes of the platform failure. The failure mechanism was concluded to be a shear failure that split open several walls in one of the platform shafts, which led to rapid intake of water. Typical Condeep Platform Condeep platforms are reinforced concrete structures meant to float in water up to 300 meters (~1000 feet) deep. These platforms consist of of a number of buoyancy cells that serve as the floating mechanism. Water ballast is pumped in and out of the buoyancy cells to control the depth of the lower portion of the structure (the Gravity Base Structure or GBS) in the water. Several of the buoyancy cells extend upward ("shafts") to provide structural support to the deck, which contains all of the buildings, machinery and amenities needed for several hundred people to live on the platform and drill for natural gas. This deck typically weighs around 55,000 tons [3 ] . The construction process for a Condeep platform starts on a dry dock, where all of the buoyancy cells and shafts are cast without enclosing the cell tops. The dock is then flooded, and the conglomeration of buoyancy cells is floated out to a sheltered location with deep water ("fjord"), where the buoyancy cells that will not be support shafts are capped off, and the GBS is slipformed upward (see Figure 2 [1 ][8 ] ). As more of the structure is cast, water ballast is pumped into the buoyancy cells to sink the structure and keep the construction close to the water. Once the GBS is completed, the platform structure must undergo a controlled ballast test to test the mechanical equipment under service loads and check for minor leaks. A controlled ballast test requires the platform to be sunk until the GBS is submerged, as it would be during deck-mating, which would follow at the end of the test and any necessary repairs. During deck-mating, the GBS is sunk until submerged once more, and the 55,000 ton deck is floated above the GBS; ballast is released from the buoyancy cells, and the GBS lifts the deck into the air. The completed platform can then be floated to its final location. For deck-mating, the GBS typically has to be about 20 meters (66 feet) deeper than it would be at service load. Welcome. Learn more about what Wikispaces has to offer. o=http%3A%2F%2Ffailures.wikispaces.com%2FSleipner%2BA%2B-%2BNorth%2BSea%2BOil%2BPlatform%2BCollapse)

description

offshore-accident

Transcript of Failures - Sleipner a - North Sea Oil Platform Collapse

Page 1: Failures - Sleipner a - North Sea Oil Platform Collapse

Actions

Wiki Home

Recent Changes

Pages and Files

Members

Search

Navigation

Home

M Kevin Parfitt - Moderator

Peer Reviewers

Building Failures Forum (Blog)

Wiki Installments

Building Enclosure

Bridge & Infrastructure

Building Failure Cases

Failures in the News

Fire Case Studies

Industrial Disasters

Natural Disasters

Stadiums & Arenas

Systems & Failure Categories

Weird Failures

Wiki Contributions

Contribute a New Case

Comment on a Case

Editing Instructions

Wikispaces Help

Resources

Journal of Performance

TCFE of ASCE

MatDL Failures Case Studies

Links - See Building Failures Forum

In Planning Stages:

Illustrated Glossary

Failures Photo Library

Penn State AE

About AE 537

Sleipner A - North Sea Oil Platform Collapse Edit 8 147 …

Figure 2: Partially completed buoyancy

cells to be floated to a fjord

Table of ContentsBackground

Typical Condeep

Platform

The Sleipner A-1

The Accident

Summary of

Conditions

Timeline

Likely Causes

Verification

Reactions and Outcome

Revised Design

Philosophy

The New Sleipner A

Platform

References

Works Cited

Works Read

Additional Reading

Figure 1: Simplified rendition of a

typical Condeep platform built for

natural gas drilling in the North Sea

Sleipner A-1 Gravity Base Structure23 August 1991 in the Gandsfjord outside of Stavanger, NorwayKsenia Tretiakova -Integrated BAE/MS Candidate (Dec 2012) in the Department of Architectural Engineering, Pennsylvania State

University

Please note: All images in this article are generated by the author; In-text figure references include credit

for any resources referenced during the illustration.

BackgroundThe original Sleipner A (SLA-1)

platform was to be used for oil and

natural gas drilling in the Sleipner

gas field in the North Sea. It was

built in the fashion of typical

Condeep platforms (as seen in

Figure 1[1][7]), but sank during a

controlled ballast test, unlike other

platforms with similar designs. It

was found that a combination of poor

geometry andinadequate design

were the causes of the platform

failure. The failure mechanism was

concluded to be a shear failure that

split open several walls in one of the

platform shafts, which led to rapid

intake of water.

Typical Condeep Platform

Condeep platforms are reinforced

concrete structures meant to float in water up to 300 meters (~1000 feet)

deep. These platforms consist of of a number of buoyancy cells that serve

as the floating mechanism. Water ballast is pumped in and out of the

buoyancy cells to control the depth of the lower portion of the structure (the Gravity Base Structure or

GBS) in the water. Several of the buoyancy cells extend upward ("shafts") to provide structural support to

the deck, which contains all of the buildings, machinery and amenities needed for several hundred people

to live on the platform and drill for natural gas. This deck typically weighs around 55,000 tons[3].

The construction process for a Condeep platform starts on a dry

dock, where all of the buoyancy cells and shafts are cast without

enclosing the cell tops. The dock is then flooded, and the

conglomeration of buoyancy cells is floated out to a sheltered

location with deep water ("fjord"), where the buoyancy cells that

will not be support shafts are capped off, and the GBS is

slipformed upward (see Figure 2[1][8]). As more of the structure is

cast, water ballast is pumped into the buoyancy cells to sink the

structure and keep the construction close to the water. Once the

GBS is completed, the platform structure must undergo a

controlled ballast test to test the mechanical equipment under

service loads and check for minor leaks. A controlled ballast test

requires the platform to be sunk until the GBS is submerged, as

it would be during deck-mating, which would follow at the end of

the test and any necessary repairs. During deck-mating, the GBS

is sunk until submerged once more, and the 55,000 ton deck is

floated above the GBS; ballast is released from the buoyancy

cells, and the GBS lifts the deck into the air. The completed

platform can then be floated to its final location. For deck-mating,

the GBS typically has to be about 20 meters (66 feet) deeper

than it would be at service load.

Welcome. Learn more about what Wikispaces has to offer. (http://www.wikispaces.com/site/signin?goto=http%3A%2F%2Ffailures.wikispaces.com%2FSleipner%2BA%2B-%2BNorth%2BSea%2BOil%2BPlatform%2BCollapse)

Page 2: Failures - Sleipner a - North Sea Oil Platform Collapse

Figure 3: Plan view of SLA-1 buoyancy cells, with shafts and tri-cells highlighted

As a result of the need to float a very heavy structure using concrete, extreme care has to be taken in

design. One of the critical design factors for a deep sea platform GBS is the buoyancy cell wall thickness:

if the walls are too thin, they will rupture during deck mating; if the walls are too thick, the structure will

simply not float, or will prove difficult to move to its final destination. To deal with the fine line between "too

thick" and "too thin", low factors of safety are used during the design, requiring both precise load

estimation and precise analysis of buoyancy cell geometry[1].

The Sleipner A-1

The Sleipner A-1 platform was an example of a typical Condeep platform that "did not deviate significantly

from earlier platforms"[2]. It was the 12th platform built by Norwegian Contractors (now Aker Oil & Gas

Technology, Inc.)[5]. SLA-1 was designed using the same software that Norwegian Contractors (NC)

applied to the other 11 deep sea platforms.

Construction for

SLA-1 started in

July of 1989, just

under 2 years

before the failure

of the GBS[6]. As

can be seen in

Figure 3[2][3][4][7]

[8], the SLA-1

platform had 24

buoyancy cells,

four of which

extended into the

shafts that

supported the

deck. Two of the

shafts served as

"drill shafts"

while the

remaining two

served as riser and utility shafts. The GBS was 110 meters (361 feet) tall[1][7], and designed to operate in

82 meters (269 feet) of water[2][7][9]. The deck that would be mated to the SLA-1 GBS weighed

approximately 57,000 tons[9].

The critical design detail in the SLA-1 platform was the connection of the buoyancy cells to one another,

called a "tri-cell" (as shown in Figure 3[2][3][4][7][8]). In Figure 4[2][3][4], the geometry of a "representative"

platform tri-cell (Gullfaks B[2][3][4]) can be observed and compared to the SLA-1 tri-cell geometry. The

reduced thickness of the walls in SLA-1 tri-cells as compared to Gullfaks B is attributed to an effort by the

NC designers to optimize the concrete volume and tricell geometry[3]. Figure 5.1[2][3][4][7][8] magnifies one

of the joints in the tri-cells used for SLA-1 so that the reinforcement details can be observed[2][3][4].

Additional reinforcement detailing is shown in Figure 5.2[1][7]: a section of an elevation of one of the SLA-1

shaft walls[1]. The key items to note in Figure 5[1][2][3][4][7][8] are highlighted in red: the T-headed bar in the

joint (5.1[2][3][4][7][8]) and the location of the last stirrup in the shaft (5.2[1][7]).

The initial cost to build the SLA-1 GBS was approximately $180 million (US).

Page 3: Failures - Sleipner a - North Sea Oil Platform Collapse

Figure 4: Tri-cell geometry of a typical platform (4.1)

compared to the geometry of SLA-1 (4.2)

Figure 5: Tri-cell joint reinforcement detailing (5.1) and shaft wall reinforcement detailing (5.2) with key

features highlighted

The AccidentSleipner A-1 was scheduled to undergo deck-mating on 1 September 1991. A second controlled ballast

test was administered on the morning of Friday, 23 August 1991 in the Gjandsfjord near Stavanger

(southwest coastal Norway, in the North Sea) after the platform underwent repairs for minor leaks

discovered during the first test. The platform began taking on water uncontrollably at a depth of 97.5

meters[2][8][9] (320 feet)-- about 5 meters (16 feet) from the anticipated deck-mating depth[1]. The platform

took between 17[3] and 18.5[2] minutes to become fully submerged. The 14 people on board at the time of

the accident were successfully rescued with no injuries[2][4].

Summary of Conditions

The initial intake of water was denoted with a very "deep bang-like sound"[2] from one of the drill shafts, D3

(pointed out in Figure 3[2][3][4][7][8]). An eyewitness account indicated that water ingress could be seen in

the lower portion of the shaft, at an elevation of 49 meters (160 feet) or less. The estimated size of the

opening required to sink the SLA-1 platform in the the observed time was approximately 0.4 square meters

(4.31 square feet)[2][9], which translates to a calculated crack length of about 7 to 8 meters (23 to 26 feet).

At the time of failure, the D3 shaft wall was experiencing a differential water pressure of about 67 meters

Page 4: Failures - Sleipner a - North Sea Oil Platform Collapse

Figure 6: Probable failure location at tri-cell joint (6.1) and probable failure location on shaft wall (6.2)

(220 feet) waterhead.

Undersea probes were released after the failure to explore the sea floor and observe the wreckage. The

debris of the SLA-1 platform was scattered over an area of roughly 90,000 square meters (approximately

97,000 square feet). The top of one of the shafts could be identified in the debris. 192 pieces of SLA-1 were

mapped across the sea bed, indicating a total collapse of the concrete GBS. As a result of the complete

demolition of SLA-1, no physical evidence could be used to indicate the cause of the failure.

The timeline below outlines key events and actions that took place.

Timeline

Morning of 23 August 1991

05:48:30 - Platform is at a depth of 97.5 meters; a "deep bang-like sound" is heard, followed by

strong vibrations and the sound of rushing water.

05:49:00 (30 seconds later) - another, slightly weaker, bang is heard. Preliminary investigations

follow; Drill shaft D3 is identified as the location of the failure, and emergency deballasting is

initiated.

05:56:30 (8 minutes after the first bang) - The call is given for the 14 personnel on board to abandon

the platform.

05:59:30 (13 minutes after the first bang) - The platform is fully evacuated.

06:07:00 (20 minutes and 30 seconds after the first bang) - The platform completely disappears

underwater.

06:07:45 (21 minutes and 15 seconds after the first bang) - A magnitude 3 (Richter) event is

registered at several local seismological stations.

It was observed that D3 sank first, corroborating the assumption that D3 was the only shaft to experience

rapid intake of water.

Note: Summary of Conditions and Timeline summarized from Jakobsen (1992) [2]

Likely CausesIt was concluded that the tri-cell walls and supports at the cell joints were the weakest points in the

platform; Calculations based on final design geometry showed that the load on these parts was at or very

close to their maximum capacity. The investigators from NC concluded that "final failure was believed to

take place as crushing of the concrete, presumably at the intersection between the tri-cell wall and the cell

joint."[2] The investigators working for Statoil agreed and elaborated on this conclusion, reasoning that

"shear failure occurred due to lack of transverse reinforcement."[3]

Ultimately, the most probable failure mechanism for the SLA-1 GBS was found to be concrete crushing

and shear failure that occurred in the portion of a tri-cell wall located above the transverse reinforcement,

close the the joint. Figure 6[1][2][3][4][7][8] illustrates the probable location of the failure mechanism.

This failure mechanism manifested because of several inconsistencies in the initial conditions defined in

the design software[1][2][8][9][10]. The sinking was partially caused by the inappropriate use of finite element

Page 5: Failures - Sleipner a - North Sea Oil Platform Collapse

the design software[1][2][8][9][10]. The sinking was partially caused by the inappropriate use of finite element

(FE) -code NASTRAN[10] with regards to the global analysis of the finalized design[2][9]: the finite element

mesh used to analyze the tri-cells was too coarse to predict the shear stress accurately. The flawed

analysis and post-processing of the tri-cell design led to shear forces being underestimated by some 45%[1][2][9].

Another flaw with the use of the software was the human error involved: the design software involved

considerable complexity, which led to a a very high perception of precision by those who used it. One of

the features of this software was the way it ran calculations: it would only flag certain sections that were

deemed critical by the software presets, and indicate those as sections that the engineers on the design

team needed to check. The probable failure point of the SLA-1 GBS was not flagged.

Additionally, the supports for the tri-cell walls in SLA-1 were designed to only resist lateral forces

indirectly, which meant that the detailing for the tri-cell joints had to be very carefully designed and

analyzed[2]. It was found that the T-headed reinforcing (highlighted in previous figures) in the tri-cell joints

was not long enough to resist the forces on the tri-cell walls. It was also found that the transverse

reinforcing (also highlighted in previous figures) did not extend far enough up to resist the forces on the tri-

cell walls[2][3][9].

Verification

NC began an investigation into the failure the same day that the SLA-1 GBS sank, as did Statoil (the

company that would have operated the finished platform). The groups that carried out the investigation

attempted to fit potential physical causes for the GBS failure to eyewitness accounts using a "Sequential

Times Events Plot" system that diagrammed in-depth witness descriptions along a time axis to pinpoint

significant events and their locations[6]. The investigative teams then followed up with analytical

calculations to verify their conclusions.

Additionally, the company SINTEF carried out testing of small and full scale models to support the

findings of the investigation team. These models included versions of the existing (collapsed) structure, as

well as modified versions to correspond to investigative theories regarding the initial inadequate reinforcing

at the joint details and in the shaft[2][4][8][9]. The models tested with the "improved" design provided

evidence to suggest that, had the reinforcing been appropriately designed, the load capacity of the tri-cells

would have been about 70% higher[2][3], and the SLA-1 GBS would not have been a total loss.

The findings among the NC investigation team, the Statoil investigation team, and the SINTEF investigation

team coincided very well. As a result of the consistency of the findings in each independent investigation,

Statoil chose to rebuild the Sleipner A platform[9], with some modifications to assure safety and structural

stability.

Reactions and Outcome

The fact that two simples changes to the

reinforcement detailing would have prevented an

extremely expensive structural failure has

resounded widely among structural designers. The

total loss of the Sleipner A-1 platform is an

unfortunate, but excellent, example of the need for

extreme care and detail in design. The SLA-1

accident demonstrates the importance of having

experienced engineers verify computer-generated

design work to ensure the proper use of analysis

and design techniques[9][11].

The initial cost for the SLA-1 GBS was about

$180 million. Statoil estimated their losses

without the SLA-1 platform came in at about $1

million per day. It took over two years to redesign

the Sleipner platform and bring it to fully

operational status[4].

Revised Design Philosophy

The design philosophy after the SLA-1 GBS

collapse was focused on establishing additional,

extensive risk analysis criteria that includes

analysis for impact damage, and design for

platform stability in the case that one of the

Page 6: Failures - Sleipner a - North Sea Oil Platform Collapse

Figure 7: Tri-cell geometry of SLA-2 (7.1) compared to

the geometry of SLA-1 (7.2)

platform stability in the case that one of the

buoyancy cells or other compartments is

damaged[3].

Additionally, the revised design philosophy called for greater forgiveness in the initial design in order to

account for any potential future changes that might occur later in the design process. Additional load

factors were applied to all new platform designs. Once the design was completed, the new philosophy

required qualified engineers to check every pre-identified critical section-- not as flagged by any software in

use, but as identified to be a potential weak section in any design by those who investigated the SLA-1

GBS collapse[3].

The New Sleipner A Platform

The new Sleipner platform (SLA-2) was designed entirely using hand calculations. This was the result of a

decision by Statoil to continue through with the design while investigators continued troubleshooting the

software used to design all of the NC platforms in the North Sea. The stipulation behind the SLA-2 design

was that, in addition to hand calculation and design, all of the buoyancy cells in the platform were modeled

and analyzed before they left the dry dock for further construction[3].

The designers of SLA-2 changed the cell wall geometry to minimize stress concentrations (see Figure 7[2]

[3][4] for the differences in geometry). The criteria for the new design included a 10% higher load factor

when accounting for water pressure. The formula for shear capacity was revised as well[3].

Overall, the total time spent on verification of the design was quadrupled in comparison to the design of the

SLA-1 GBS. The SLA-2 platform was up and operation in October of 1993, more than 2 years after the

initial SLA-1 GBS collapse. The overall estimated cost of the SLA-1 GBS collapse totals to $700 million,

after taking into account the downtime losses and cost to redesign the platform[1][3].

References

Works Cited[1] Collins, M., Vecchio, F., Selby, R., Gupta P (2000) "Failure of an Offshore Platform," Canadian

Consulting Engineer - Structures, pp 43-48, March/April

Journal Article. Provides a wealth of information on the typical construction and design of a

Condeep platform; Also describes the Sleipner A-1 design, failure mechanism, failure causes, and

the failure aftermath (including information on the construction of Sleipner A-2). Discusses

estimated costs and lessons learned as well.

[2] Jakobsen, B. (1992) “Loss of the Sleipner A platform,” The proceedings of the International Offshore and

Polar Engineering Conference, pp. 1-9

Conference Proceedings. Written by members of the Norwegian Contractors' investigation team.

Describes investigations into the platform collapse; Discusses eyewitness accounts that helped

locate the probable point of failure, as well as the most likely causes for failure and collapse (and

why); Also describes some model tests that have been performed to verify the conclusions in the

paper.

[3] Rettedal, W. (1993) “Design of concrete platforms after Sleipner A-1 sinking,” Proceedings of the

International Conference on Offshore Mechanics and Arctic Engineering – OMAE, pp. 309-316

Conference Proceedings. Discusses new design methods for offshore concrete platforms;

Describes full-scale testing of certain joints to identify failure modes, as well as the revised design

philosophy (including discussion of loads, design criteria, etc.). Also covers the design of the

platform that replaced Sleipner A-1, and the verification of that design. Additionally, discusses risk

analysis and some forethought on future designs.

[4] Jakobsen, B. (1994) “The Sleipner Accident and its Causes,” Engineering Failure Analysis, Vol. 1, No.

3, pp. 193-199

Journal Article. Written by members of the Norwegian Contractors' investigation team. Describes

the initial collapse as well as the factors that determined the probable cause of the failure. Also

discusses the additional model tests to verify failure modes on the joints. Compares results from

model tests to eyewitness accounts to verify the actual failure mode.

[5] Norway.org (1996) "Norwegian Companies in USA - - Aker ," norway.org, n.d., Web

Periodical. News article from the official site of Norway in the United States. Regarding the

Page 7: Failures - Sleipner a - North Sea Oil Platform Collapse

acquisition of Norwegian Contractors (NC) by Aker Oil & Gas Technology, Inc. Discusses company

holdings and history, and includes contact information for Aker.

[6] Ynnesdal, H., Berger, F. (1994) "The Sleipner Accident," Proceedings of the Second International

Conference on Health, Safety & Environment in Oil & Gas Exploration & Production, pp. 715-716, 25-27

January

Conference Proceedings. Provides a general summary of the entire story on behalf of the Society

of Petroleum Engineers, emphasizing the usefulness of a "Sequential Times Events Plot" (STEP)

in pinpointing the probable cause and location of the failure based on witness interviews. Briefly

covers the base facts of the accident, then reviews the methodology of the investigations, involving

the "STEP" system to track the course of events of the accident.

[7] Schlaich, J., Raineck, K-H. (1993) "Die Ursache fur den Totalverlust der Betonplattform Sleipner A,"

Beton- und Stahlbetnbau, Vol. 88, pp. 1-4

Journal Article. Article is in German. Title translates to "Causes for the total loss of the Sleipner A

concrete platform." Primary usefulness of this article for this wik i page is the availability of clear

illustrations for portions of offshore platform geometries to reference in figure generation. The article

recounts the accident, describes the conditions during the accident (with great diagrams), includes

diagrams for the finite element meshing of various portions of the GBS, also shows the loading

conditions for the tri-cells.

[8] Arnold, D. (2009) "The sinking of the Sleipner A offshore platform ," Institute for Mathematics and its

Applications (IMA) at University of Minnesota, 7 September 2009, Web.

Website. Produced by the director for mathematics at the University of Minnesota. Provides an

excerpt of one of the elusive SINTEF reports and provides a general summary of the platform, the

failure, the circumstances of failure, and where to look for additional information.

[9] Jakobsen, B., Rosendahl, F. (1994) "The Sleipner Platform Accident," Structural Engineering

International, IABSE, Vol. 3, pp. 190-193

Journal Article. Produced by members of the NC investigation team. Summarizes the accident

and discusses lessons learned. Mentions several important dates for the rebuilding of the structure,

and reasons for choosing to build SLA again. Published in the "Lessons from Structural Failures"

section of the journal.

[10] Huckle, T. (2011) "Collection of Software Bugs ," Institut fur Informatik, TU Munchen, 7 November

2011, Web

Website. Produced by a professor at the university. A large and relatively comprehensive list of

accidents and disasters that occurred as a result of an error in the design software. Provides

names, dates, summaries of the failures, and reasons for failure. Also includes additional resources

to find more information on each accident. SLA-1 is #15 in the list.

[11] Holand, I. (1996) "Structural analysis of offshore concrete structures ," IABSE Congress Report,

IABSE, Vol. 15, pp. 879

Technical Report. A report made available to the public on the web by the International

Association for Bridge and Structural Engineering. Discusses how the Sleipner accident is a good

example of the necessity for verification, risk analysis, and quality assurance.

Works Read

Stead, B. (1992) “Importance of fabrication engineering in the early phases of the Sleipner a development,”

Proceedings of the International Offshore Mechanics and Arctic Engineering Symposium, Vol. 1, pp. 543-

548

Conference Proceedings. Describes the conclusions drawn that led to the initial design choice for

the offshore platform (discussions include topographical factors that led to the choice of a gravity-

only system, costs for construction as well as the various hookups required for the typical offshore

platform, and considerations leading to the choice of concrete)

Vecchio, F. (2002) “Contribution of Nonlinear Finite-Element Analysis to Evaluation of Two Structural

Concrete Failures,” Journal of Performance of Constructed Facilities, pp. 11-115, August

Journal Article. Describes 2 failures, one of which is Sleipner A; Recounts the event itself,

summarizes what happened, includes some discussion of loads and dimensions in the summary.

Discusses the nonlinear finite-element modeling analysis the author performed, and how it

accurately portrays load capacity and failure modes: justifies use of computer modeling as a way to

analyze a structure.

Wackers, G.(2004) “Resonating Cultures: Engineering Optimization in the Design and (1991) Loss of the

Page 8: Failures - Sleipner a - North Sea Oil Platform Collapse

Help · About · Blog · Pricing · Privacy · Terms · Support

Contributions to http://failures.wikispaces.com/ are licensed under a Creative Commons Attribution Share-Alike 3.0 License.

Portions not contributed by visitors are Copyright 2013 Tangient LLC

Wackers, G.(2004) “Resonating Cultures: Engineering Optimization in the Design and (1991) Loss of the

Sleipner A GBS ,” Center of Technology, Innovation and Culture, University of Oslo, May, Web

Web-based Discussion Paper. This is a work in progress paper, with detailed discussions of… the

accident itself, as well as some discussion of the theory behind design parameters. Also includes

discussions of the appropriate way to approach investigations for failure modes and mechanisms.

Extrapolates to some cultural stuff, and then continues with an evaluation of changes to the design

of the new platform. Also talks about different forms of analysis, as well as the engineering of the

platform design.

Thompson, M., Jirsa, J., Breen, J. (2006) “Behavior and Capacity of Headed Reinforcement,” ACI Structural

Journal, Vol. 103, No. 4, pp. 522-530, July/August 2006

Technical Report. Mainly discusses design recommendations for headed reinforcement, and why

they are recommendations in the first place. Uses the Sleipner A failure as a model for the

importance of appropriate design of headed reinforcement.

Additional Reading

Holand, I., Lenschow, R. (1996) “Research Behind the Success of the Concrete Platforms in the North

Sea,” Proceedings of Mete A. Sozen Symposium – A Tribute From His Students, ACI SP-162, pp. 235-

272

Selby, R., Vecchio, F., Collins, M. (1996) “Analysis of Reinforced Concrete Members Subject to Shear and

Axial Compression,” ACI Structural Journal, Vol. 93, No. 3, May/June

Bea, R. (1994) “The Role of Human Error in Design, Construction, and Reliability of Marine Structures,”

Ship Structures Committee

Gudmestad, O., Holand, I., Jerson, E. (2000) “Design of offshore concrete structures,” 1st ed., Spon Press

The SINTEF reports on Sleipner A (STF22): A97725, A97854, A97857, A97859, A97861, A97833 (there

are 13 more available somewhere)