Fail Safe Validation
-
Upload
rishabhpuria -
Category
Documents
-
view
222 -
download
0
Transcript of Fail Safe Validation
-
8/10/2019 Fail Safe Validation
1/17
1
FAIL SAFETY VALIDATION OF IPS SYSTEMS FOR
INDIAN RAILWAYS AT CGL, INDORE
A Major Project (Phase-I ) Report submitted to Rajiv Gandhi ProudyogikiVishwavidyalaya, Bhopal (M.P.)
towards the partial fulfilment of the Degree of
Bachelor of Engineering
In
Electrical Engineering
Guided By: Submitted by:
Dr. R. K. Saxena JOYSINGHA PAL
DEPARTMENT OF ELECTRICAL ENGINEERING
SHRI G.S. INSTITUTE OF TECHNOLOGY AND SCIENCE, INDORE
[An Autonomous Institute]
DECEMBER 2014
-
8/10/2019 Fail Safe Validation
2/17
2
SHRI G.S. INSTITUTE OF TECHNOLOGY AND SCIENCE,
INDORE
[An Autonomous Institute]
RECOMMENDATION
The major project (Phase-I) entitled "FAIL SAFETY VALIDATION OF IPS SYSTEMS
FOR INDIAN RAILWAYS AT CGL, INDORE " submitted by Mr. Joysingha Pal,
towards the partial fulfilment of degree of Bachelor of Engineering (Electrical) of
Rajiv Gandhi Proudyogiki Vishwavidyalya , Bhopal is satisfactory account of the
progress made by him in dissertation work
Supervisor Prof. & Head
Dr. R.K.Saxena Dept. of Electrical Engg.
-
8/10/2019 Fail Safe Validation
3/17
3
SHRI S.G.S. INSTITUTE OF TECHNOLOGY AND SCIENCE,
INDORE
(An Autonomous Institute)
CERTIFICATE
This is to certify that the Major Project (Phase -I) entitled FAIL SAFETY
VALIDATION OF IPS SYSTEMS FOR INDIAN RAILWAYS AT CGL, INDORE,
submitted by Joysingha Pal, towards the partial fulfilment of the degree of
Bachelor of Engineering in Electrical Engineering, of Rajiv Gandhi ProudyogikiVishwavidyalaya, Bhopal is satisfactory account of the progress made by his
dissertation work.
Internal Examiner: External Examiner:
DATE: DATE:
-
8/10/2019 Fail Safe Validation
4/17
4
SHRI G.S. INSTITUTE OF TECHNOLOGY AND SCIENCE, INDORE
(An Autonomous Institute)
DECLARATION
I Joysingha Pal student of B.E.(PTDC) (ELECTRICAL) 7th semester hereby
declare that, I am working on this project under the guidance of Prof. Dr.
R.K.Saxena,(EED). The work done is original and all the material usedin this thesis / report is properly referenced and all references are taken
into account to the best of my beief.
Joysingha Pal
-
8/10/2019 Fail Safe Validation
5/17
5
ABSTRACT
Railway Transport for many years has been one of INDIAsfastest growing, environment friendly and the safest mode of
transport.
It is safest mode today because of the efforts of the railway
authorities of INDIA, one of which includes properly
organised advanced signalling systems.
Uninterrupted Power Supply plays a significant role in the
efficient working of Railway Signalling System. For this
purpose, Integrated Power Supply (IPS) is being progressively
installed on Indian Railways, due to its compact design and
reliability. Failure of IPS may affect the punctuality and
safety of trains.
Via this project I will be performing quality testing (hardware
and logical) of IPS systems used by Indian Railways at CGL,
Indore.
-
8/10/2019 Fail Safe Validation
6/17
6
CONTENTS
S.NO CHAPTERS PAGE1. Introduction 7-8
2. Literature Overview 9-10
3. Proposed Scheme 11-12
4. Proposed Methodology &
Analysis Completed tillNow
13-16
5. Bibliography 17
LIST OF FIGURES
S.NO FIGURE PAGE1. BLOCK DIAG. OF IPS 11
-
8/10/2019 Fail Safe Validation
7/17
7
CHAPTER - 1
INTRODUCTION
Power supply system is the heart of signaling system. For
a reliable signaling system installation, reliable power
supply system is most important.
RE Area (Railway Electrified):
In AC electrified area, the main power is derived from
the traction supply.
In RE area the source of power supply to signaling system
is through auxiliary transformer connected to OHE. This
supply is very reliable but its occasional interruption/ low
voltage cannot be ruled out leading to blank signals.
Non RE Area:
In non-electrified area, the main supply is obtained from
commercial power supply.
The source of power supply is through a rural feeder,
which is quite unreliable in respect of its availability and
voltage. The battery backup is provided in all the DC
circuit, which requires more maintenance. Due to
-
8/10/2019 Fail Safe Validation
8/17
8
frequent interruptions of supply, the signals are
becoming blank till the starting of Diesel Generators.
To overcome these problems a comprehensive powersupply scheme known as Integrated Power Supply system
has been developed by RDSO.
The function of Integrated Power Supply system is to
provide a stable and reliable AC and DC power supply to
the Railway signalling installations against all AC mains
variations or even interruptions. This is very essential for
proper movement of trains. As the name indicates, it is
designed and developed with a view to provide complete
power solutions from single system to all signalling
circuits. The IPS for Railway Signalling circuits shall be
manufactured as per RDSO specification No.
RDSO/SPN/165/2004, Amndt. 5.
RDSO approved Firms:
At present following are the RDSO approved firms for
supply and installation of IPS system on Indian Railways:
1. M/s Amara Raja Power Systems Pvt. Ltd.,
Tirupati.(A.P.)2.M/s Statcon Power Controls Ltd., Noida (U.P.)
3.M/s HBL Nife Power System Ltd., Hyderabad (A.P.)
4. Crompton Greaves Ltd., Indore(M.P.)
-
8/10/2019 Fail Safe Validation
9/17
9
CHAPTER - 2
LITERATURE OVERVIEW
This whole project is going to be performed under strict
guidelines provided by Indian Railway Authorities and certain
norms established by International Authorities. Some brief
information about them are as follows :
1.SIGNAL DIRECTORATE RESEARCH, DESIGNS &
STANDARDS ORGANISATION,LUCKNOW:
In India , For railway signaling systems there are
certain standards which are to be kept in mind which
are proposed and managed by above authority and isall provided in SPECIFICATION NO.-
RDSO/SPN/165/2012.
2.
EUROPEAN COMMITTEE FOR ELECTROTECHNICAL
STANDARDIZATION (CENELEC):
European standard EN-50129 was drafted and
approved by CENELEC in 2002 (which superseded
ENV-50129) which generally included norms for the
communication, signaling & processing systems.
-
8/10/2019 Fail Safe Validation
10/17
10
Now, standards given by above mentioned committees are
basically used as guidelines for the manufacturing &
testing of Signaling Systems, employed presently in
Indian Railways.
-
8/10/2019 Fail Safe Validation
11/17
11
CHAPTER - 3
PROPOSED SCHEME
-
8/10/2019 Fail Safe Validation
12/17
12
The IPS system basically consists of three major parts :
1.Float Rectifier Cum Boost Charger(FRBC) Panel:
Shown in Red colour. This panel consists of
FRBC or SMR module
Distribution/Supervisory control/Alarm (DSA) unit.
2.A.C. Distribution Panel(ACDP):
Shown in Blue colour. This panel consists of
Inverter.
Ferro resonant based Automatic Voltage Regulator
(AVR) or Bypass CVT.
Transformers.
3.
D.C. Distribution Panel(DCDP):
Shown in Purple Colour. This panel consists of
DC-DC Converters
Common Digital Voltmeters for measurements.
The Scheme proposed for testing of IPS systems
falls under the norms given by RDSO under
SPECIFICATION NO.- RDSO/SPN/165/2012.
-
8/10/2019 Fail Safe Validation
13/17
13
CHAPTER - 4
PROPOSED METHODOLOGY
&
ANALYSIS COMPLETED TILL NOW
Following will be the steps taken into account to cover the
whole project efficiently and properly within specified time
frame:
1. Collecting & Organizing the detailed information about the
system which is to be tested:
(a)Which further involves keeping track of recent
edification about the IPS.
2. Visiting the site (CGL, Indore) to physically acknowledge:
(a) the various parts of hardware of IPS (which are to be
tested).
(b) the various parameters which are to be tested.
(c) the various instruments required to perform testing
safely.
(d) the on-site availability of those instruments.
-
8/10/2019 Fail Safe Validation
14/17
14
3. Completing a thorough report on the whole project.
WORK DONE TILL NOW:
Following is a table briefly describing the various parameters
(which are to be tested), device required for testing, and on-
site availability of those devices:
1). DCDP:
(a) DC-DC converters
PARAMETERS DEVICE REQ. AVAILABILITY
I/P Current Multimeter A
I/P Voltage " A
Ripple C.R.O A
Psopho noise Psophometer A
O/P Current Multimeter A O/P Voltage " A
2). ACDP:
(a) Inverters
Parameters Device Availability
I/P Current Multimeter A
I/P Voltage " A
-
8/10/2019 Fail Safe Validation
15/17
15
O/P Current Power Analyzer A
O/P Voltage " A
T.H.D " A
Frequency Counter/C.R.O A
(b) Transformer(S.D.):
Parameters Devices Availability
I/P Voltage Power Analyzer A
O/P Current " A
O/P Voltage " A
(c)AVR:
Parameters Devices Availability I/P Voltage Power Analyzer A
I/P Current " A
I/P Power Manually A
O/P Voltage Power Analyzer A
O/P Current " A
O/P Power Manually A
Distortion Distortion level meter A Efficiency Manually A
Regulation " A
-
8/10/2019 Fail Safe Validation
16/17
16
3). FRBC Panel:
(a) S.M.R
Parameters Devices Availability
I/P Voltage Power Analyzer A
I/P Current " A I/P Power Manually A
P.F Power Analyzer A
V T.H.D " A
I T.H.D " A
O/P Voltage Power Analyzer A
O/P Current " A
O/P Power Manually A
Ripple C.R.O A
Psopho noise Psophometer A
Efficiency Manually A
The above mentioned tables are just to give the vague
knowledge about the whole testing procedures.
-
8/10/2019 Fail Safe Validation
17/17
17
BIBLIOGRAPHY
i. Railway applications-Communication, signaling and
processing systems-Safety related electronic systems
for signaling.
ii. Draft Specification For SMPS Based IPS (Version 3)
specification no.-IPS RDSO-SPN 165-2012.
iii.
Maintenance handbook on IPS (version3).iv. Performa for Acceptance Test (by RDSO).