FACULTY OF ENGINEERINGDEPARTMENT OF CIVIL ENGINEERING
2015-2016 SPRING SEMESTER
ASSOC.PROF.DR. İBRAHİM YİTMEN
CIVL 493 CONSTRUCTION MANAGEMENT
PROJECT DELIVERY SYSTEMSPART II
3
DESIGN-BUILD CONTRACT (CONT’D)
• More use by private owner vs. public owners
• DBIA estimates Design-build firms share 27% of non-residential market
• Total non-residential market is $320B
• Design-build market share - $86.4B
• 10 years ago, Design-build was less than 5% of non-residential market
4
DESIGN-BUILD CONTRACT (CONT’D)
• Reasons for increased popularity
• Owners are asking for it
TIME IS MONEY
• Enabling legislation/change of registration
• Information technology
5
ADVANTAGES OF DESIGN-BUILD CONTRACTFROM THE DESIGN-BUILD INSTITUTE • Time savings from 15% to 30%
• Cost savings from 3% to 15%.
6
PROJECT DELIVERY SYSTEMS
CostInfluence
Cost ofChange
+ +
Time
SD B* Fixed Price
Traditional
SDCD B
ConstructionManagement(PhasedConstruction)
* Fixed Price
CD
ConstructionCD B Construction
CD B ConstructionCD B Construction
SDSD DDDD
CDCDDesign/Build
ConstructionConstruction
* Fixed Price
DD
DD Construction
7
Departmentof Defense(non-appropriatedfunds)
GeneralServicesAdmini-stration
NavalFacilitiesEngineeringCommand
Departmentof VeteransAffairs
TimeSavings
18% NA 15% 28%
CostSavings
14% 3% 12% 0%*
*Costs are variable for all projects within department
TIME AND COST SAVINGS FOR SOME FEDERAL PROJECTS
8
DESIGN-BUILD ADVANTAGES (CONT'D)
• Fewer claims
• Design-build process averages 35% less than all-systems average
• Design-build process averages less than half the claims that Design-Bid-Build does
9
ADVANTAGES OF A DESIGN-BUILD CONTRACT (CONT'D)
• Single source responsibility
• Blended incentives
• Designer and constructor focused on same goals
• Owner doesn't have two separate contracts to coordinate
10
ADVANTAGES OF A DESIGN-BUILD CONTRACT (CONT'D)• Using performance criteria/specs is the only system
that rewards innovation
• Improved risk management: risk assigned to party best able to manage that risk
• Early knowledge of firm costs
11
DISADVANTAGES OF DESIGN-BUILD
• Fragile delivery system
• Complexity of process
• Unfamiliarity with process
• Lack of availability of insurance and bonds
12
DESIGN-BUILD DISADVANTAGES (CONT'D)
• Difficult to write performance-based specifications
• Case law is less extensive
• Designers and contractors must be experienced and qualified
13
ENGINEER/PROCURE/CONSTRUCT (EPC)
• Technology and process dependent
• Used in industrial construction
• Requires a significant amount of engineering
• Mechanical/electrical intensive (piping, instrumentation)
• Typically involves large pieces of engineered equipment (e.g. paper machines, vessels)
14
INDEFINITE DELIVERY/INDEFINITE QUANTITY
• Contracts signed for undetermined amount of work for limited time.
• Work executed through “task orders.”
• Task orders have dollar cap (relatively small).
• Task orders may be competitively bid or assigned.
15
COMMERCIAL CONTRACT TERMS
• Stipulated Sum Contract (Lump Sum Agreement)
• Contractor assumes risk, owner implicitly pays more
• Separate designer and contract entities in general
• Provides owner advance knowledge of construction costs
• Costs can only be changed with owner approval
• Competitive bid process usually used
16
COST-PLUS-FEE AGREEMENTS
• Separate designer and contract entities in general
• Shifts risk from contractor to owner
• Contractor is reimbursed for actual project cost plus an amount for profit and overhead
• The contract must clearly define what is reimbursable and what is included as overhead and profit
17
UNIT PRICE AGREEMENT• Separate designer and contract entities in general
• Often used for public works projects
• Material quantities are distributed to potential bidders for purposes of estimating unit cost
• Bidders base estimates on listed quantities and bid a unit price for each item
18
UNIT PRICE AGREEMENT (CONT'D)
• Payment based on the number of units installed
• Neither the owner nor the contractor know what the project cost will be
• Approach allows estimator to spend more time focusing on the most economical approach to the construction process
19
DELIVERY SYSTEMS & COMMERCIAL TERMS
• Project delivery systems and commercial terms can be cross-matched
20
DELIVERY METHODS, COMMERCIAL TERMS, & BASIS OF AWARD MATRIX
h
Delivery Methods(1)
Commercial Terms(2)
Basis of Award(3)
(a) Base Contract
Design-Bid-Build Stipulated LS Negotiated
Design-Bid-Build-Warranty
Unit Price Competitively Bid
Design-Build Cost Reimbursable Negotiated
Design-Build Stipulated LS Best Value
EPC Cost Reimbursable Negotiated
D-B-O-T Stipulated LS Competitively Bid
(b) Changes to Base Contract
Change Orders Time & Material Negotiated
21
ALTERNATE METHODS FOR CONTRACT AWARD
• A+B (Time + Cost, Multiparameter)
• Best Value (Price + Quality)
• Bid Averaging Method
• Optionally Combined Bidding
22
WHAT IS A+B BIDDING?
• Basic Formula
(A + B x RUC with I/D) or
(A + B x RUC with LD)
• Bid value = A + B x RUC
where, A= the contract amount
B = total number of days (working or calendar) proposed by the bidder
RUC = Road User Cost
23
WHAT IS A+B BIDDING? (CONT’D)
• Incentive
= (B - actual time charged) x $ RUC/day
• Disincentive
= (Actual time charged - B) x $ RUC/day
• Liquidated Damage - may be combined with or used instead of I/D
24
PROPOSED OTHER PARAMETERS
• Basic Formula
(A + B x RUC with I/D) or (A + B x RUC with LD)
• Other Biddable Parameters
• Warranty Credit -- Maryland DOT
• Safety -- Utah DOT
• Past Performance -- Ontario MOT, Canada
• Warranty with Performance Payments -- Alabama & Michigan DOTs
• Lane Rental -- Arkansas, Maine, and Virginia DOTs
25
PROPOSED OTHER PARAMETERS (CONT’D)
• Other Non-Biddable Parameters
• Warranty -- Indiana DOT
• Quality -- Consultant input
• Performance -- Construction Industry Institute (CII)
26
OTHER BIDDABLE PARAMETERS• Warranty Credit
• Bid is adjusted downward on a pro rata basis if the contractor provided more than the minimum required years of warranty
• Safety
• Contractor bids traffic management-related items separately on a lump sum basis
• Performance-related specifications are provided for traffic control
27
OTHER BIDDABLE PARAMETERS (CONT’D)• Past Performance
• Contractor’s bid is adjusted downward or upward based on past performance
• Example performance parameters
• Quality
• Schedule
• Cost
28
OTHER BIDDABLE PARAMETERS (CONT’D)
• Warranty with Performance Payments
• Warranted portion is bid lump sum
• Two methods
• Retainage system
• Bonus system
29
OTHER BIDDABLE PARAMETERS (CONT’D)
• Lane Rental
• Contractor bids on the total amount of time in days or hours that a lane, a shoulder, or a combination of lanes and shoulders are planned to be taken out of service
• A daily or hourly rental fee is assessed by the agency
• No Bonding required
30
OTHER BIDDABLE PARAMETERS (CONT’D)
• Warranty
• Contractor provides extended warranties on satisfactory performance of certain parts of or the whole project
• Quality
• Percent Within Limits (PWL) Concept
• Performance-Related Specifications (PRS)
31
OTHER BIDDABLE PARAMETERS (CONT’D)
• Performance
• Contractor is awarded incentives or assessed disincentives based on project performance
• Example performance parameters
• Quality
• Cost
• Schedule
• Safety
32
BEST VALUE (PRICE + QUALITY)
• Bidders submit price and technical/management proposal.
• Proposals are scored and parameters weighted.
• Bidders may be called for discussion, and submit best and final offer (BAFO).
• Contract awarded to most advantageous plan (best quality/price).
33
BID AVERAGING METHOD
• Contract awarded to bidder closest to average of all submitted bids.
• Reduces risk of awarding project to “bad” low bid, or contractor compromising quality to win or stay within bid.
• Contractor more likely to absorb changes/ less likely to file claims.
34
OPTIONALLY COMBINED BIDDING
• Projects divided into biddable packages, or grouped together to form larger package.
• Contractors allowed to bid on divided projects and combined project, or any combinations.
• Used to open competition among bidders and reduce contract costs to agency.
35
ProjectDeliverySystem
Example Unique Features
Design-bid-build
Manitowoc RiverBridge ProjectRoosevelt Bridge
-fosters competitive bidding-takes time for complete design-method-based specifications
Design/CM-bid-build(fast track)
World Wide Plazafrom Skyscraper
-time is money-design is just ahead of construction
EXAMPLES
36
ProjectDeliverySystem
Example Unique Features
Design-bid-build-warranty
WisDOT asphaltprojects (3 –1995, 4–1996, 2-1997)
-from method to performancespecifications- transferring quality assurance(QA) to contractor for a price
Engineer/procure/construct(industrialconstruction)
St. James Styreneplant
-time to market is important-mobilize to field (construction)when >50% design complete
EXAMPLES (CONT'D)
37
ProjectDeliverySystem
Example Unique Features
Design-build
I-15 SaltLakeCity,Utah
-designer and contractor can be separateentities or same organization-facilitates integration of design andconstruction
EXAMPLES (CONT'D)
38
FINANCING- OWNER/CONTRACTOR CONTRACT • Self-funded- small residential projects
• Banks- short term construction loans or long-term mortgage
• Taxes- used to pay for schools, roads and bridges (TEA-21), and other pubic works
39
FINANCING (CONT'D)• Bond issue- used when taxes do not cover expenses-
stadiums, large projects; must be approved by voters
• Bartering (in regions where money is scarce); e.g., services provided in the former Soviet Union for oil rights
40
EMERGENCY PROJECTS
• Tampa, FL... tanker exploded and destroyed a bridge- rebuilt in 17 days
• California - an earthquake destroyed a major bridge
• Caused ~$1M per day in economic damage to the region
• Contractor earned $14M in early completion incentives
• South Carolina - a large textile plant was destroyed and completely rebuilt in 181days
41
PRACTICAL RECOMMENDATIONS
• A successful project does not just happen!
• There are numerous factors, general and project-specific, that can influence the outcome of a project
• Project-dependent factors: certain types of projects have different signs of success