FACILITIES/TRANSPORTATION COMMITTEE MEETING AGENDA€¦ · 8/14/2017 · REPORT ON PLANT AND...
Transcript of FACILITIES/TRANSPORTATION COMMITTEE MEETING AGENDA€¦ · 8/14/2017 · REPORT ON PLANT AND...
WISSAHICKON SCHOOL DISTRICT
Ambler, Pennsylvania 19002-3496
BOARD OF SCHOOL DIRECTORS FACILITIES/TRANSPORTATION COMMITTEE MEETING AGENDA
August 14, 2017 5:30 PM Central Office Board Room
FACILITIES
1. Middle School Auditorium Update (Attachment A)
2. District Wide Summer Projects Update
3. High School Fab Lab (Attachment B)
TRANSPORTATION
1. Update on Bus Schedules for 2017-18
INFORMATIONAL
1. North Wales Water Authority work along Symphony Lane
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
DESIGN DEVELOPMENT PRESENTATION July 17, 2017
Attachment A
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
ESTIMATED COST
SITE WORK $400,000 BUILDING $4,216,100 DEMOLITION $220,000 RENOVATIONS $294,800 SUB TOTAL $5,130,900 SOFT COSTS $1,439,471 TOTAL $6,570,371
WISSAHICKONMIDDLESCHOOLDESIGN
BRESLIN ARCHITECTS
SCHEDULE February 21, 2017
NEW AUDITORIUM Commence Design March 2017 Start Land Development Approval Process March 2017 Complete Land Development December 2017 Receive Bids March 2018 Award Bids March 2018 Commence Construction April 2018 Substantial Completion June 2019
WISSAHICKONMIDDLESCHOOLDESIGN
REPORT ON PLANT AND EQUIPMENT
a. Recommendation for approval that the Board of School Directors authorizes the administration to continue with the Middle School Auditorium project contract with Breslin Architects, for design development and construction-bidding documents requiring approval prior to proceeding with the next phase. MOTION: Approval that the Board of School Directors authorizes the administration to
continue with the Middle School Auditorium project contract with Breslin Architects, for design development and construction-bidding documents requiring approval prior to proceeding with the next phase.
b. Recommendation to approve T&M Associates as part of the Middle School Auditorium project contract with Breslin Architects, in the amount of $60,000, allowance for the cost of Land Development, Site and Civil Consultant. MOTION: Approval of T&M Associates as part of the Middle School Auditorium project contract with Breslin Architects, in the amount of $60,000, allowance for the cost of Land Development, Site and Civil Consultant.
Existing Technology Education space D06/D08
• D06 Tech Production Laboratory/Classroom Closet/Storage Room
Attachment B - 1
Existing Technology Education space D06/D08
• D08 Tech/Electronics Classroom
Attachment B - 2
Attachment B - 3