Facilities Services
Located at 491 Cecelia Road
across the Street from the old
Burnside School.
![Page 3: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/3.jpg)
Introduction
Facilities Services is Responsible for;
Repair and Maintenance of all School District 61
• Buildings
• Grounds
• Equipment and Vehicles
• Custodial Services
• Facility Rentals
• Cartage and Mail Delivery
![Page 4: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/4.jpg)
Minor Capital Summer Projects
![Page 5: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/5.jpg)
• Campus View - Seismic and OSC Portable Move
– Move OSC Portable
– Extended Staff Parking Lot
– Paved play area at back of school
– Paved current pathway to Classroom Portables and OSC Unit
– Built Exterior Ramp
– Continue Seismic Upgrade Work
• Work at Richmond School for Braefoot Move
– Tec Package installations
– Office Installation, Classroom Upgrades
– Lighting Upgrades, Grounds Upgrades
Minor Capital Summer Projects Completed or
In Progress by SD Employees
![Page 6: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/6.jpg)
• 16 New Classroom Conversions
– Tec Packages
– 2 Portables Converted to classrooms
– Computer labs converted to classrooms
– Music carts and shelving built
– Moving walls to provide larger classrooms
– Cubbies or metal lockers installed
– Staff rooms moved to accommodate classrooms
• Security Alarm Upgrades – various schools
• Telephone and PA upgrades – various schools
• Sportsfield Upgrading
– Northridge, Oak Bay
Minor Capital Summer Projects Completed or
In Progress by SD Employees
![Page 7: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/7.jpg)
• Victor
– Renovations for Strong Start (bathroom and kitchen
installations)
– Hazmat remediation underway
– Renovate four classrooms for current student use
– Move students to Richmond and prepare rooms
• Roofing
– Victor, Hillcrest, Frank Hobbs and Cloverdale Portables
• Esquimalt Theatre – lights and painting
• Lambrick Park - Kitchen replacement
• Lighting Upgrades – various schools
• Quadra –irrigation, fencing and sod
• Quadra Warehouse – Renovations for Itinerant Staff
• HVAC, Painting, Flooring, Plumbing, Grounds Cleaned Up
Minor Capital Summer Projects Completed or
In Progress by SD Employees
![Page 8: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/8.jpg)
• Vic West
– Playground re-surfacing
• Shop Upgrades
– Monterey and Spectrum
• Lansdowne
– Gym Floor Replacement
• Lambrick Park
– Gym Floor resurfacing
• Mt. Doug
– Phase 2 Window Replacement
– Unit Ventilator Replacement – 5 classrooms
• Tillicum
– Fire Alarm Upgrade
Minor Capital Summer Projects
Completed by Contractors
![Page 9: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/9.jpg)
• Eagle View
– Inclusive Playground
• South Park
– Annex Slate Roof Replacement
– Annex Skylight Replacement
– Bike Shelter Roof Replacement
• Richmond
– Boiler Upgrade
– Unit Ventilator Installations
• Roof Replacements
– Macaulay, View Royal, Richmond
Minor Capital Summer Projects
Completed by Contractors
![Page 10: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/10.jpg)
• Unit 1 at Frank Hobbs Complete
– $4.6M in Ministry Funding
– Site Prep Completed for Doncaster
– Builds to begin for Doncaster and Tillicum in November
Minor Capital Child Care Studios – Built by SD Employees
![Page 11: Facilities Services€¦ · Northridge SPRFS complete Bank Street SPRFS complete SCHOOL DISTRICT 61 - SEISMIC PROGRAM School Status Completion Date CONSTRUCTION – 4 Schools Campus](https://reader033.fdocuments.net/reader033/viewer/2022051813/60346d69da560b7b185e38be/html5/thumbnails/11.jpg)
Braefoot
Vic High/S.J Willis
Cedar Hill
Shoreline
Seismic
SCHOOL DISTRICT 61 - SEISMIC PROGRAM
School Status
PLANNING - 7 Schools
Arbutus SPIR complete
Reynolds SPIR complete
Shoreline/Craigflower PDR underway
Lambrick Park SPIR complete
Cedar Hill PDR complete
Northridge SPRFS complete
Bank Street SPRFS complete
SCHOOL DISTRICT 61 - SEISMIC PROGRAM
School Status
Completion
Date
CONSTRUCTION –
4 Schools
Campus View Construction Underway 2020
Braefoot Construction Underway 2020
SJ Willis Renovations Construction Underway 2020
Vic High Design Underway 2022
COMPLETED –
16 Schools
South Park Completed 2004
Margaret Jenkins Completed 2008
Mount Doug Completed 2008
Monterey Completed 2009
Willows Completed 2010
James Bay Completed 2010
Central Completed 2011
Vic High Ph 1 Completed 2011
McKenzie Completed 2012
Lansdowne Completed 2013
Vic West Completed 2014
George Jay Completed 2015
Tillicum Completed 2015
Cloverdale Completed 2016
Quadra Completed 2016
Burnside Complete 2019