Facilities, Planning, and Construction April 14, 2014 Construction Report
description
Transcript of Facilities, Planning, and Construction April 14, 2014 Construction Report
![Page 1: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/1.jpg)
FACILITIES, PLANNING, AND CONSTRUCTIONApril 14, 2014 Construction Report
![Page 2: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/2.jpg)
Facilities under Construction:
V.R. Eaton High School 540,000 SF __________ Total 540,000 SF
Facilities in Planning/Bidding Stage:
Peterson E.S. Addition 14,000 SF Beck E.S. Addition 8,000 SFNHS Chiller Replacement NAPrairie View Drainage Improvement NA ____________ Total 22,000 SF
Total Projects under Construction, Planning and Bidding: 562,000 SF562,000 SF
Area Currently Under Construction/ Planning Area Currently Under Construction/ Planning
![Page 3: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/3.jpg)
V. R. Eaton High SchoolV. R. Eaton High SchoolArchitect: Corgan Associates Contractor: Pogue Construction CompanyConst. Start Date: Spring 2013Completion Date: August 2015
Status:Pier drilling is completeGeothermal wells are completeGrade beams are 95% completeFoundation slab is 50% completeRough electrical and plumbing is being installedSite grading and utility installation is underwaySteel erection is approximately 10% complete
(Please note that the aerial photo was taken in March and does not reflect April progress)
![Page 4: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/4.jpg)
May 2013
March 2014
![Page 5: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/5.jpg)
![Page 6: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/6.jpg)
![Page 7: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/7.jpg)
![Page 8: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/8.jpg)
![Page 9: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/9.jpg)
![Page 10: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/10.jpg)
Peterson Elementary School AdditionPeterson Elementary School AdditionArchitect: SHW ArchitectsContractor: Northstar BuildersConst. Start Date: Spring 2014Completion Date: August 2014
Status:Classroom concrete slabs have been pouredSteel has begun to be erected for classroomsGrade beams have been poured for stage/cafeteria/gym expansion
![Page 11: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/11.jpg)
January 2014
April 2014
![Page 12: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/12.jpg)
Beck Elementary School AdditionBeck Elementary School AdditionArchitect: SHW ArchitectsContractor: Balfour Beatty ConstructionConst. Start Date: Spring 2014Completion Date: August 2014
Status:Pier drilling is underwaySite work is underway
![Page 13: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/13.jpg)
Possible ONCOR Electric Power
Distribution Line
![Page 14: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/14.jpg)
Miscellaneous Maintenance Projects
• Prairie View Elementary School Drainage Improvement– Water drains toward the front of the building
during heavy rains and flows into the building– Project will be to route water to a retention pond
and ditch adjacent to FM 3433– Possible replacement of the front driveway
• Northwest High School– Replace a 22 year old chiller– Anticipating a major failure within the next year– Current chiller contains obsolete R-22 refrigerant– The repair cost does not justify the repair– The efficiency of the replacement chiller will
provide reduction in energy cost
![Page 15: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/15.jpg)
Pending Project Close-Out Change Orders
• Cox Elementary School• Love Elementary School• Subvarsity Stadium
![Page 16: Facilities, Planning, and Construction April 14, 2014 Construction Report](https://reader033.fdocuments.net/reader033/viewer/2022051419/56815878550346895dc5d6dd/html5/thumbnails/16.jpg)
FACILITIES, PLANNING, AND CONSTRUCTIONApril 14, 2014 Construction Report