Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

28
Data Center Power and Cooling Requirements C Info-Tech Research Group tools and template documents are provided for the free Group services. These documents are intended to supply general information only, intended to be used as a substitute for any kind of professional advice. Use thi document creation. To customize this document with corporate marks and titles, s Footer fields of this document. The data center's power, cooling and standby power supply must be able to adequa needs. Whether IT is building, refreshing, or moving the data center, it is impo requirements. Accurate estimates of facility requirements are a critical input t Once the load estimate has been determined, IT should seek professional expertis requires specialized skills. This tool can be used to determine a high level estimation for the data center's power requirements within a range of 10%-15% accuracy. Complete the white cells follow the arrows to determine final results. Note: Some calculations in this tool are adapted from APC information. Start Calculator

Transcript of Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Page 1: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Data Center Power and Cooling Requirements Calculator

Info-Tech Research Group tools and template documents are provided for the free and unrestricted use of subscribers to Info-Tech ResearchGroup services. These documents are intended to supply general information only, not specific professional or personal advice, and are notintended to be used as a substitute for any kind of professional advice. Use this document either in whole or in part as a basis and guide fordocument creation. To customize this document with corporate marks and titles, simply replace the Info-Tech Information in the Header andFooter fields of this document.

The data center's power, cooling and standby power supply must be able to adequately support current and future needs. Whether IT is building, refreshing, or moving the data center, it is important to understand these requirements. Accurate estimates of facility requirements are a critical input to the project’s final budget. Once the load estimate has been determined, IT should seek professional expertise as data center construction requires specialized skills.

This tool can be used to determine a high level estimation for the data center's power, cooling, and standby power requirements within a range of 10%-15% accuracy. Complete the white cells with required information and follow the arrows to determine final results.Note: Some calculations in this tool are adapted from APC information.

Start Calculator

Page 2: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Data Center Power and Cooling Requirements Calculator

Info-Tech Research Group tools and template documents are provided for the free and unrestricted use of subscribers to Info-Tech ResearchGroup services. These documents are intended to supply general information only, not specific professional or personal advice, and are notintended to be used as a substitute for any kind of professional advice. Use this document either in whole or in part as a basis and guide fordocument creation. To customize this document with corporate marks and titles, simply replace the Info-Tech Information in the Header and

The data center's power, cooling and standby power supply must be able to adequately support current and future needs. Whether IT is building, refreshing, or moving the data center, it is important to understand these requirements. Accurate estimates of facility requirements are a critical input to the project’s final budget. Once the load estimate has been determined, IT should seek professional expertise as data

This tool can be used to determine a high level estimation for the data center's power, cooling, and standby power requirements within a range of 10%-15% accuracy. Complete the white cells with required information and follow the arrows to determine final results.

Page 3: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Required Inputs

Input Table

Item Number

Total floor area in the data center (sq. ft)1200

Enter anticipated number of future servers to be added.50

DX System

240

5

191

Enter the required information into the white cells below and click on the "Next Step" buttons to continue through the calculator.

Which cooling device is used in the data center? (select from drop down).

Enter the three phase AC voltage provided at the service entrance. (kW)

Maximum number of people in the data center? (People that will be consistently working within the data center. A maximum number should be used to account for intermittent personnel and air exchange.)

Power distribution rating (Watts)?(Total power drawn from the power distribution unit in Watts.)

Page 4: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Next Step >>>

Page 5: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Existing Server Load Calculations

Inputs

Device Name Server Model Utilization Assumption AMPS

IT_NETPRO PROLIANT DL 360 G4p 30-70% 1.2IT_SURFWATCH PROLIANT DL 360 G2 30-70% 5PRD_CITRIX02 PROLIANT BL 20P G2 30-70%PRD_CITRIX03 PROLIANT BL 20P G2 30-70%PRD_CITRIX01 PROLIANT BL 20P G2 30-70%PRD_CITRIX04 PROLIANT DL 360 G4p 30-70%IT_DEVELOPMENT1 PROLIANT DL 320 G2 30-70%IT_REMOTEACCESS PROLIANT DL 320 G2 30-70%IT_SOURCESAFE PROLIANT DL 320 G2 30-70%IT_BESDMZ PROLIANT DL 320 G2 30-70%IT_AVTECH PROLIANT DL 320 G2 30-70%IT_SYNCSORT PROLIANT DL 320 30-70%PRD_MOBILEAPPS PROLIANT DL 320 G2 30-70%PRD_ANTGY PROLIANT DL 320 G5 30-70%PRD_ACCOUNTFND PROLIANT DL 360 G2 30-70%PRD_SCHEDULELEADS PROLIANT DL 360 G2 30-70%IT_SURFWATCH PROLIANT DL 360 G2 30-70%IT_EDIRECTORY PROLIANT DL 360 G2 30-70%PRD_FAS1 PROLIANT DL 360 G3 30-70%PRD_BES1 PROLIANT DL 360 G5 30-70%IT_LDDHCP1 PROLIANT DL 360 G3 30-70%IT_AD1 PROLIANT DL 360 G4p 30-70%IT_AD2 PROLIANT DL 360 G4p 30-70%IT_OPSMANAGER PROLIANT DL 360 G4p 30-70%PRD_LDMS PROLIANT DL 360 G4p 30-70%PRD_ONFUSE PROLIANT DL 360 G4p 30-70%PRD_HRDB PROLIANT DL 360 G4p 30-70%PRD_HUDAD1 PROLIANT DL 360 G4p 30-70%PRD_HUDFTP PROLIANT DL 360 G5 30-70%PRD_ECRMS PROLIANT DL 360 G5 30-70%

Enter server information, along with Amps and Volts into the table below to calculate the total server load in kW for the organization. Where a power utility or calculation tool is not available from the vendor to express power requirements as kW, nameplate ratings are used to arrive at a kW input.

This tool uses the following formula for this conversion:VOLT AMPS = AMPS x VOLTSWATTS = VOLT AMPS x 0.67 kW = WATTS/1000

List each server located in the data center in the table below. Use nameplate ratings to collect amps and volts for each device to determine the kW required. Be sure to include the device name for tracking purposes.

Page 6: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

PRD_SL45BY PROLIANT DL 360 G5 30-70%PRD_DUCTOR2 PROLIANT DL 580 G2 30-70%PRD_YISQL2 PROLIANT DL 580 G2 30-70%PRD_ICARE PROLIANT ML 350 G4 30-70%PRD_JLDSD PROLIANT DL 580 G2 30-70%PRD_HRES PROLIANT ML 350 G3 30-70%PRD_GRAPHICS PROLIANT ML 350 G4 30-70%IT_EXCHANGE PROLIANT DL 360 G4p 30-70%IT_VMWARE2 PROLIANT ML 370 G3 50-80%PRD_PTHNAVG PROLIANT ML 370 G3 30-70%PRD_FS1 PROLIANT DL 380 G5 30-70%IT_VERITAS PROLIANT DL 380 G5 30-70%PRD_INTRANET PROLIANT DL 380 G5 50-80%IT_VMWARE1 PROLIANT ML 570 G2 50-80%IT_SURFWATCH1 PROLIANT DL 360 G5 30-70%IT_EXCHANGE2 PROLIANT ML 370 G5 30-70%PRD_OSX Xserve 30-70%PRD_CITRIX PROLIANT DL 360 G4p 30-70%PRD_WILBR PROLIANT DL 360 G4p 30-70%PRD_AD PROLIANT DL 360 G4p 30-70%PRD_CLFS PROLIANT DL 380 G4 30-70%PRD_RDI1 PROLIANT DL 380 G5 30-70%PRD_PSLD10 Sunfire E6900 30-70%PRD_PSLD20 Sunfire E6900 30-70%PRD_PSLD30 Sunfire E6900 30-70%PRD_PSLD40 Sunfire E6900 30-70%PRD_SLUAT01 Sunfire 420 30-70%PRD_SLUAT02 Sunfire 420 30-70%PRD_SLWK10 Sunfire E450 30-70%IT_CHDS1 ProLiant DL360 G2 30-70%IT_HDS 9985 Sun StorageTek 9985 50-80%PRD_2K3IPS01 ProLiant DL360 G5 30-70%PRD_2K3IPS02 ProLiant DL360 G5 30-70%PRD_2K3IPS03 ProLiant DL360 G5 30-70%PRD_2K3IPS04 ProLiant DL360 G5 30-70%PRD_W2KIPSSQM1 ProLiant DL580 G2 30-70%PRD_2KIPSACT1 ProLiant DL380 G3 30-70%PRD_2KIPSACT2 ProLiant DL380 G3 30-70%IT_IPSSRV1 ProLiant DL360 G4 30-70%PRD_2K3GISAG1 ProLiant DL360 G4 50-80%PRD_2K3GISAG2 ProLiant DL360 G4 50-80%PRD_2K3GISAPP1 ProLiant DL360 G4 50-80%PRD_42K3GISWEB1 ProLiant DL360 G4 30-70%PRD_42K3GISWEB2 ProLiant DL360 G4 30-70%PRD_GISP03 Sun Fire X4200 30-70%PRD_GISP04 Sun Fire X4200 50-80%PRD_42K3WFAE1 PROLIANT DL 380 G5 30-70%PRD_42K3WFAE2 PROLIANT DL 380 G5 30-70%PRD_42K3WFCE PROLIANT DL 380 G5 30-70%PRD_42K3WFPE PROLIANT DL 380 G5 30-70%PRD_51K3WFPA PROLIANT DL 380 G5 30-70%PRD_51LNXDB1 PROLIANT DL 380 G5 30-70%PRD_51LNXDB2 PROLIANT DL 380 G5 30-70%PRD_HSLD50 Sun SPARC M5000 Srvr 30-70%

Page 7: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

PRD_51K3IPSUAT01 ProLiant DL360 G5 30-70%PRD_51PSUAT02 ProLiant DL360 G5 30-70%PRD_51UATACT ProLiant DL360 G5 30-70%

Page 8: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Inputs Outputs

VOLTS WATTS kW

240 192.96 0.1929678.79348 160.8 0.1608

684 684 0.684684 684 0.684

Average Server Load (kW)684 684 0.684336 336 0.336

0.906251 251 0.251251 251 0.251251 251 0.251251 251 0.251251 251 0.251171 171 0.171251 251 0.251194 194 0.194267 267 0.267267 267 0.267267 267 0.267267 267 0.267373 373 0.373481 481 0.481371 371 0.371336 336 0.336336 336 0.336336 336 0.336336 336 0.336336 336 0.336336 336 0.336336 336 0.336481 481 0.481481 481 0.481

Next Step >>>

Enter server information, along with Amps and Volts into the table below to calculate the total server load in kW for the organization. Where a power utility or calculation tool is not available from the vendor to express power requirements as kW, nameplate ratings are

List each server located in the data center in the table below. Use nameplate ratings to collect amps and volts for each device to

WATTS (Enter if volts and amps are not available)

Total Existing Server Load (kW)

Page 9: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

481 481 0.481715 715 0.715715 715 0.715572 572 0.572715 715 0.715513 513 0.513572 572 0.572336 336 0.336590 590 0.59572 572 0.572564 564 0.564564 564 0.564658 658 0.658998 998 0.998481 481 0.481613 613 0.613183 183 0.183336 336 0.336336 336 0.336336 336 0.336478 478 0.478564 564 0.564

9120 9120 9.129120 9120 9.129120 9120 9.129120 9120 9.12610 610 0.61610 610 0.61

1664 1664 1.664267 267 0.267

1860 1860 1.86481 481 0.481481 481 0.481481 481 0.481481 481 0.481715 715 0.715564 564 0.564564 564 0.564336 336 0.336336 336 0.336336 336 0.336336 336 0.336336 336 0.336336 336 0.336409 409 0.409409 409 0.409564 564 0.564564 564 0.564564 564 0.564564 564 0.564564 564 0.564564 564 0.564564 564 0.564

3198 3198 3.198

Page 10: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

481 481 0.481481 481 0.481481 481 0.481

Page 11: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Next Step >>>

Page 12: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Other Existing Equipment Load Calculations

Inputs

Device Name Type of Device AMPS VOLTS

PRD_6509 Cisco 6509PRD_B2610 Cisco 2610 1.5 240PRD_3500 Cisco 3500PRD_ASA1 Cisco 5510PRD_A2610 Cisco 2610 1.5 240PRD_A3500 Cisco 3500PRD_3750A Cisco 3750-48TSPRD_DLRemote1 Dlink DSS-24PRD_DLRemote2 Dlink DSS-24IT_FATTY FatPipeIT_KVM01 Raitan Dominion KX464IT_KVM03 Raitan Dominion KX464IT_KVM02 Raitan Dominion KX464IT_KVM04 Raitan Dominion KX464IT_KVM05 Raitan Dominion KX464IT_KVM07 Raitan Dominion KX464IT_KVMCLOSET1 Raitan Dominion KX464PRD_ADTRAN Adtran Netvanta 3430IT_6509 Cisco 6509PRD_ASA2 Cisco 5510PRD_C2610 Cisco 2610 1.5 240PRD_B3500 Cisco 3500APC Rack UPS x's 6 Rackmounted UPS's

Enter equipment information, along with Amps and Volts into the table below to calculate the total equipment load in kW for the data center. Where a power utility or calculation tool is not available from the vendor to express power requirements as kW, nameplate ratings are used to arrive at a kW input.

This tool uses the following formula for this conversion:VOLT AMPS = AMPS x VOLTSWATTS = VOLT AMPS x 0.67 kW = WATTS/1000

List each equipment device located in the data center in the table below (other equipment includes switches, routers, etc.). Use nameplate ratings to collect amps and volts for each device to determine the kW required. Be sure to include the device name for tracking purposes.

Page 13: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator
Page 14: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator
Page 15: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Inputs Outputs

WATTS kW

257 257 0.25713.657360 0.36

1608 1608 1.608150 150 0.15

Average Equipment Load (kW)360 0.361608 1608 1.608

0.14175 75 0.07549 49 0.04949 49 0.049

658 658 0.65829 29 0.02929 29 0.02929 29 0.02929 29 0.02929 29 0.02929 29 0.02929 29 0.02925 25 0.025

257 257 0.257150 150 0.15

360 0.361608 1608 1.6085880 5880 5.88

Enter equipment information, along with Amps and Volts into the table below to calculate the total equipment load in kW for the data center. Where a power utility or calculation tool is not available from the vendor to express power requirements as kW, nameplate ratings are used to arrive at a kW input.

List each equipment device located in the data center in the table below (other equipment includes switches, routers, etc.). Use nameplate ratings to collect amps and volts for each device to determine the kW required. Be sure to include the device name for tracking purposes.

WATTS (Enter if volts and

amps are not available)

Total Existing Equipment Load (kW)

Page 16: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator
Page 17: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator
Page 18: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Next Step >>>

Page 19: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Server Room Power and Load Requirements Estimates

The following table summarizes the power load requirements for the organization's data center environment based on the inputs gathered in Tabs 1-3.

Item Description

Power Requirement - Electrical

Existing or actual equipment load

Estimated future loads

Peak power draw from variation in critical loads

UPS inefficiency and battery charging Actual and future loads (kW).

Lighting

Total power required to support electrical demands

Power Requirement - Cooling

Power to support chiller system

Power to support DX system

Total power required to support cooling demands Power drawn from cooling devices.

Total Power Requirement

Size of Electrical Service Estimate

Regulator (i.e.NEC) requirements

Three phase AC voltage

Utility company estimate.

Ratings for servers and other equipment (calculated in Tab 3 and 4).

Based on the average server load and anticipated number of future servers to be added.The total steady state load. Based on current and future loads.

Based on the floor area in the server room.

Power drawn from servers, equipment, UPS, and lighting.

Based on the standard assumption that power required is 70% of total electrical demand.

Based on the standard assumption that power required is 100% of total electrical demand.

Total amount of power required to support both electrical and cooling demands

Total amount of power required that includes current and future needs for power and cooling.

Total electrical and cooling requirements multiplied by 1.25 to meet regulator's requirements.Existing AC voltage from building (can be found at service entrance).

Electrical service required from utility company (calculated in Amps)

Page 20: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Size of Standby Generator Estimate (if Applicable)

Critical loads that require generator backup

Cooling loads that require generator backup

Estimated size of generator required

Based on total power to support electrical demand.Based on total power to support cooling.

Page 21: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Server Room Power and Load Requirements Estimates

The following table summarizes the power load requirements for the organization's data center environment based on the inputs gathered in Tabs 1-3.

Subtotal kW

Power Requirement - Electrical 1150.615

92.450

45.283

144.620 535.064

44.075

2.400

191.094

Power Requirement - Cooling 0.959

N/A

191.094

191.094

Total Power Requirement

382.188

Size of Electrical Service Estimate

477.735

240.000

1150.615

Next Step >>>

Total electrical service required from utility company in Amps

Size of generator needed (estimated in

kW)

Electrical service required from utility

company in Amps per sq. ft

Page 22: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Size of Standby Generator Estimate (if Applicable)

248.422

286.641

535.064

Page 23: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Cooling Requirements Estimation

The following table summarizes the cooling load requirements for the organization's data center environment.

Item Description

Total existing server and storage load

Total existing equipment load

Estimated future loads

UPS inefficiency and battery charging

Power Distribution (PDU)

Lighting

People

Total Estimated Cooling Load

Total Estimated Cooling Load (in Tons)

Total heat given off from server and storage devices in the data center.Total heat given off from other equipment located in the data center.The amount of heat given off from expected future devices to be added in the data center.Total heat given off from the UPS or backup battery located in the data center.Total heat given off from the power distribution unit located in the data center.Amount of heat given off from lighting in the data center. Based on the total amount of floor area in the data center. (2.0 x Floor Area in sq. ft.)Amount of heat given off from the maximum number of employees working in the data center. The total size of cooling load required to cool the data center.

The required sizing for a cooling device measured in tons based on the total estimated cooling load/heat output.

Page 24: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Cooling Requirements Estimation

The following table summarizes the cooling load requirements for the organization's data center environment.

Watts BTUs per Hour

78792.76 268683.31

13657.00 46570.37

45283.20 154415.70

44074.55 150294.20

2756.57 9399.90

2400.00 8184.00

500.00 1705.00

187464.07 639252.48

53.27 TONS

Next Step >>>

Page 25: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Standby Power Requirements Estimation

The following table summarizes the standby power load requirements for the organizations' data center environment.

Item

Server load power requirements

Other equipment power requirements

Estimated future load requirements

Cooling load requirements

Emergency lighting power load

Total size of load requiring standby power

Page 26: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Standby Power Requirements Estimation

The following table summarizes the standby power load requirements for the organizations' data center environment.

Description kW

78.793

13.657

45.283

187.464

2.400

327.597

Next Step >>>

Total estimated power requirements for servers and storage devices located in the data center. Total estimated power requirements for other equipment (routers, computers, switches, convenience plugs etc.) located in the data center. Based on the average server load and anticipated number of future servers to be added.Total size of cooling load required to cool the data center based on the total heat output.Total load required to power emergency lighting in response to an outage.Total load that will require a standby power supply in the event of an outage.

Page 27: Facilities Management_1.7.2. Data Center Power and Cooling Requirements Calculator

Data Center Requirements Estimates Results Summary

Item Description Total Unit

Power Requirements Results Summary

Total Existing Server Load 78.793 kW

Average Server Load Average power load per server in the data center. 0.906 kW

Total Existing Equipment Load 13.657 kW

Average Equipment Load 0.141 kW

1150.615 Amps

0.959 Amps

Size of Generator Needed 535.064 kW

Cooling Requirements Results Summary

Total estimated cooling load (BTUs/Hr) 639252.480 BTUs

Size of cooling device required (in tons) 53.271 Tons

BTUs per square foot 532.710 Sq. ft

Number of 20-ton air conditioners required 2.664 AC Units

Standby Power Requirements Results Summary

Total data center load requiring standby power 327.597 kW

Over sizing for backup power at 75% 245.698 kW

UPS requirements Amount of load requiring a UPS system. 573.295 kW

Generator required in kW 573.295 kW

Generator required in kVA 687.954 kVA

The following table summarizes the complete results from Tabs 1 - 4 that estimate the organization's critical power, cooling, and standby power requirements for the data center.

Total power load required to support the data center's servers.

Total power load required to support other equipment in the data center.Average power load per piece of other equipment in the data center.

Total Electrical Service Required From Utility Company in Amps

Power to be requested from the utility company to aid in budgeting.

Total Electrical Service Required From Utility Company in Amps per Sq. Ft

Power to be requested from the utility company per square foot in the data center to aid in budgeting.

Size of generator required to support server and other equipment as backup power.

The total size of cooling load required to cool the data center based on the total heat output.The required sizing for a cooling device measured in tons required to cool the data center based on the total estimated cooling load/heat output.The amount of cooling required per square foot in the data center.

Cooling requirements distributed amongst 20-ton air handlers for the data center. If the number is not a whole number, it shoud lbe rounded up to the nearest whole number.

Total load that will require a standby power supply in the event of an outage.Over sizing for future load requirements with an additional 75% standby power supply.

Size of generator required to power data center in case of an outage. kVA calculations take a power factor of 0.8 into account.

Size of generator required to power data center in case of an outage. kVA calculations take a power factor of 0.8 into account.