Facilities Construction
NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT
Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION
2010 BOND
June 2015
Kallison Ranch High School
![Page 2: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/2.jpg)
KALLISON RANCH HIGH SCHOOL
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor GMP - $110,800,000.00 Construction Period – October 2014 – May 2017 (25% Complete) Project Scope – New 2800 Student High School
Building Permit and Notice to Proceed issued October 8, 2014. Site Construction began October 14, 2014. Site Grading, Piers, 1st ,2nd and 3rd Floor Framing and Columns, Underground Utilities in progress. Interior CMU partitions ongoing. Electrical, plumbing rough-in and hydronic piping started. Foundation Piers complete. Ductwork started.
![Page 3: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/3.jpg)
KALLISON RANCH HIGH SCHOOL Aerial View (May 19, 2015)
![Page 4: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/4.jpg)
KALLISON RANCH HIGH SCHOOL Front Entrance
![Page 5: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/5.jpg)
KALLISON RANCH HIGH SCHOOL (June 8, 2015)
![Page 6: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/6.jpg)
KALLISON RANCH HIGH SCHOOL (June 8, 2015)
![Page 7: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/7.jpg)
KALLISON RANCH HIGH SCHOOL (June 8, 2015)
![Page 8: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/8.jpg)
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH)
Architect – Noonan Rittimann Project Architect – John Rittimann NISD Project Manager – Thomas Curiel Contractor – Joeris General Contractor Construction Cost - $20,590,731.00 Construction Period – February 2014 – June 16, 2015 (96% Complete) Project Scope – New 800 Student Elementary School
Final punch inspections and misc. MEP and painting in final stages.
![Page 9: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/9.jpg)
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) Aerial View (May 19, 2015)
![Page 10: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/10.jpg)
BOLDT ELEMENTARY SCHOOL Front Entrance Perspective
![Page 11: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/11.jpg)
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (June 10, 2015)
![Page 12: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/12.jpg)
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (May 29, 2015)
![Page 13: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/13.jpg)
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (May 29, 2015)
![Page 14: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/14.jpg)
ELEMENTARY SCHOOL ISMS – (Integrated Security Mgmt System)
Consultant – Combs Consulting Group NISD Project Manager – Charles Pereira Contractor – Convergint Technologies Contract Amount – $13,422,826.29 Adjusted Contract Amount - $14,014,006.38 Total Contract Completed - $12,008,197.99 Contract Balance to Finish - $2,005,808.39 Construction Period – January 23,2013 – October 2015 Project Scope – Provide security surveillance cameras, access control
and integrate the existing intrusion alarm, motion and glass break sensors at all (75) elementary schools and (2) middle schools.
(90% Complete)
![Page 15: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/15.jpg)
ELEMENTARY SCHOOL ISMS – (Integrated Security Mgmt System)
Project Scope – continues
75 Elementary School Campuses have Punch List inspections completed
2 Middle School Campuses have Punch List inspections completed
75 Elementary School Campuses have Equipment and Software training
2 Middle School Campuses have Equipment and Software training
70 Campuses have Substantial Completion Certificates issued. 77 Campuses are cut over Integrated and have received training. 65 Close-Out documents have been received.
![Page 16: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/16.jpg)
NORTHSIDE SPORTS GYM
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke General Contractor Construction Budget – $26,326,724.00 Construction Period – May 2015 – October 2016 (1% Complete) Project Scope – Provide a District-Wide Sports Gymnasium at the Farris
Complex. GMP approved at the April Board Meeting. Site work demolition and grading in progress.
![Page 17: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/17.jpg)
SPORTS GYM Site Plan
![Page 18: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/18.jpg)
NORTHSIDE SPORTS GYM – Plaza View
![Page 19: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/19.jpg)
NORTHSIDE SPORTS GYM – Entry View
![Page 20: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/20.jpg)
NORTHSIDE SPORTS GYM – Seating View
![Page 21: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/21.jpg)
NORTHSIDE SPORTS GYM – Corner View
![Page 22: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/22.jpg)
VILLAGE at WESTPOINTE EAST ELEMENTARY SCHOOL
Architect – Noonan Rittimann Project Architect – John Rittimann NISD Project Manager – Chris Parker Contractor – Bartlett Cocke General Contractor Construction Amount - $25,371,707.00 Construction Period – April 2015 – June 30, 2016 (4% Complete) Project Scope – New 800 Student Elementary School
Building layout and pad construction in progress. Pier drilling and concrete form work in progress. Permanent permit approved by COSA. Underground utilities in progress.
![Page 23: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/23.jpg)
VILLAGE at WESTPOINTE EAST ELEMENTARY SCHOOL (Front Entrance)
![Page 24: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/24.jpg)
VILLAGE at WESTPOINTE EAST ELEMENTARY Aerial View (June 8, 2015)
![Page 25: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/25.jpg)
VILLAGE at WESTPOINTE EAST ELEMENTARY SITE PLAN (May 5, 2015)
![Page 26: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/26.jpg)
FM 471 # 3 ELEMENTARY SCHOOL
Architect – O’Neill Conrad Oppelt Project Architect – Mark Oppelt NISD Project Manager – Marilyn Sevedge Contractor – Joeris General Contractor Contract Amount - $24,615,127.00 Construction Period – April 2015 – June 30, 2016 (6% Complete) Project Scope – New 800 Student Elementary School
Conditional permit issued for foundation issued (including piers, underground utilities, excluding fire line). Pier drilling in progress. Site grading and pilot channel in progress.
![Page 27: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/27.jpg)
FM 471 # 3 ELEMENTARY SCHOOL Aerial View (May 19, 2015)
![Page 28: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/28.jpg)
FM 471 # 3 ELEMENTARY SCHOOL Front Entrance
![Page 29: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/29.jpg)
FM 471 # 3 ELEMENTARY SCHOOL Site Plan
![Page 30: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/30.jpg)
O’CONNOR HIGH SCHOOL AG UPGRADES
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – Baron-Long Construction, LTD Contract Amount - $818,000.00 Construction Period – March 2015 – July 2015 (18% Complete) Project Scope - Reconfigure Barns and Shop Renovation.
Classroom framing in progress. Pen panels installed at “R” building. Heaters and plumbing installation in progress.
![Page 31: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/31.jpg)
O’CONNOR HIGH SCHOOL AG UPGRADES (“R” Building Plan)
![Page 32: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/32.jpg)
O’CONNOR HIGH SCHOOL AG UPGRADES (“S” Building Plan)
![Page 33: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/33.jpg)
O’CONNOR HIGH SCHOOL AG UPGRADES (“N and Q” Building Plans)
![Page 34: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/34.jpg)
O’CONNOR HIGH SCHOOL AG UPGRADES (June 8, 2015)
![Page 35: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/35.jpg)
O’CONNOR HIGH SCHOOL AG UPGRADES (June 8, 2015)
![Page 36: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/36.jpg)
SECURITY LOBBIES AT (8) CAMPUSES
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – Marksmen Construction Contract Budget - $1,047,775.00 Construction Period – March 2015 – August 3, 2015 (10% Complete) Project Scope – New Security Lobby for (8) Elementary Schools
Under construction has begun. Demo work near completion. CMU underway and millwork is being delivered.
![Page 37: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/37.jpg)
SECURITY LOBBIES AT (8) CAMPUSES - McDermott Elementary (June 10, 2015)
![Page 38: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/38.jpg)
SECURITY LOBBIES AT (8) CAMPUSES - Meadow Village Elementary (June 10, 2015)
![Page 39: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/39.jpg)
SECURITY LOBBIES AT (8) CAMPUSES – Valley Hi Elementary (June 10, 2015)
![Page 40: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/40.jpg)
NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – D.L. Bandy Construction Amount - $3,565,000.00 Construction Period – May 2015 – October 2015 (1% Complete) Project Scope – Window Replacement ADA Upgrade; ALE Renovation and
Drainage. Demolition and abatement underway.
![Page 41: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/41.jpg)
NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (Site Plan)
![Page 42: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/42.jpg)
NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (South Elevation)
![Page 43: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/43.jpg)
NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (North Elevation)
![Page 44: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/44.jpg)
NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (East Elevation)
![Page 45: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/45.jpg)
NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (June 10, 2015)
![Page 46: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/46.jpg)
CLARK HS/ SCOBEE ES/ VILLARREAL ES - FLOORING REPLACEMENT
Architect – Chris Lammers Project Architect – Chris Lammers NISD Project Manager – Chris Parker Contractor – Gomez Floor Covering Construction Budget - $181,318.00 Construction Period – May 2015 – August 2015 (0% Complete) Project Scope – Replace Flooring
Meetings with campuses complete. Materials have been ordered and move out in progress.
![Page 47: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/47.jpg)
MARY HULL ES/JORDAN MS/NEFF MS/PEASE MS/STEVENSON MS/TAFT HS – 2015 DOOR HARDWARE PROJECT
Architect – Munoz & Company Project Architect – Randy Hohlaus NISD Project Manager – Jim Berg Contractor – Central Builders Construction Budget - $406,620.00 Tentative Construction Period – May 29, 2015 – August 2015 (0% Complete) Project Scope – Improvements and Upgrades of Door Hardware for Safety
and Security. Notice of Award issued to Custom Builders April 29, 2015.
![Page 48: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/48.jpg)
HOLMES HS/MARSHALL HS/NEFF MS/RAYBURN MS/HARDIN COMPLEX SOCCER FACILITY ATHLETIC UPGRADES & RENOVATIONS
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – STI General Contractors Construction Budget - $1,387,000.00 Tentative Construction Period – June 1, 2015 – August 3, 2015 Project Scope – Renovate Athletic/PE Areas; Replace Soccer Field
Portable Building with Permanent Building. Construction documents complete. Proposals received May 6, 2015. Mobilization in progress.
![Page 49: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/49.jpg)
RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – D.L. Bandy Contract Amount - $4,782,000.00 Tentative Construction Period – May 15, 2015 – August 1, 2016 Project Scope – New Science Classroom Addition and Renovation.
Notice of Award issued to D.L. Bandy April 29, 2015. Temporary fencing in place. Office set up and site work has begun.
![Page 50: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/50.jpg)
RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (New Site Plan)
![Page 51: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/51.jpg)
RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (Perspective)
![Page 52: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/52.jpg)
RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (1st Floor Plan)
![Page 53: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/53.jpg)
RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (2nd Floor Plan)
![Page 54: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/54.jpg)
RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (June 10. 2015)
![Page 55: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/55.jpg)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – Guido Brothers Construction Construction Amount - $3,198,000.00 Tentative Construction Period – June 2015 – June 2016 Project Scope – New Classroom Addition
![Page 56: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/56.jpg)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Site Plan)
![Page 57: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/57.jpg)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (1st Floor Plan)
![Page 58: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/58.jpg)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (2nd Floor Plan)
![Page 59: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/59.jpg)
LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Elevation)
![Page 60: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/60.jpg)
CHILD NUTRITION WAREHOUSE - Warehouse Renovation
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $3,000,000.00 Tentative Construction Period – January 2016 – May 2016 Project Scope – Warehouse Renovation
![Page 61: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/61.jpg)
GLENOAKS ELEMENTARY - Administration Upgrades
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $3,750,000.00 Tentative Construction Period – March 2016 – March 2017 Project Scope – Administration Upgrades
![Page 62: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/62.jpg)
ALLEN ES CLASSROOM - (ADDITION/ADA/WINDOW UPGRADES)
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $6,230,000.00 Tentative Construction Period – March 2016 – August 2016 Project Scope – Classroom Addition/ADA/Window Upgrades
![Page 63: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/63.jpg)
CODY ES & LEON VALLEY ELEMENTARY - (CAFE & KITCHEN RENOVATIONS)
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Tom Curiel Contractor – TBD Construction Budget - $6,500,000.00 Tentative Construction Period – February 2016 – August 2016 Project Scope – Renovations to Cafeteria and Kitchen
![Page 64: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/64.jpg)
ZACHRY MS BUS CANOPY MODIFICATIONS
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $1,100,000.00 Tentative Construction Period – February 2016 – July 2016 Project Scope – Bus Canopy Modifications
![Page 65: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/65.jpg)
LOCKE HILL ES, THORNTON ES, LEON VALLEY ES, POWELL ES, COON ES, MICHAEL ES, MARY HULL ES AND CABLE ES - (SECURITY LOBBIES)
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $480,000.00 Tentative Construction Period – January 2016 – August 2016 Project Scope – Security Lobbies
![Page 66: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/66.jpg)
BLOCK AQUATICS – ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – CT Construction Contract Amount – $45,998.00 Construction Period – June – August 14, 2015 (95% Complete) Project Scope – Roof Repair & Replacement
![Page 67: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/67.jpg)
CARSON ELEMENTARY – ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – Port Enterprises Contract Amount – $861,203.00 Construction Period – June – August 2015 (1% Complete) Project Scope – Roof Repair & Replacement.
Staging in progress.
![Page 68: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/68.jpg)
CODY ELEMENTARY – ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – Cram Roofing Contract Amount – $289,210.00 Construction Period – June – August 2015 (1% Complete) Project Scope – Roof Repair & Replacement.
Staging in progress.
![Page 69: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/69.jpg)
JORDAN MIDDLE SCHOOL – ROOFING PROJECT
Roofing Consultant – Austech Engineering Contractor – Port Enterprises Contract Amount – $1,822,741.00 Construction Period – June – August 21, 2015 (5% Complete) Project Scope – Roof Repair & Waterproofing.
Staging in progress.
![Page 70: Facilities Construction - Home | Northside … Construction N. NO. OR. ... plumbing rough-in and hydronic piping started. Foundation ... Baron-Long Construction, LTD Contract Amount](https://reader035.fdocuments.net/reader035/viewer/2022070608/5aafee717f8b9a07498df0d2/html5/thumbnails/70.jpg)
STEVENSON AND STINSON MIDDLE SCHOOL – ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – Cram Roofing Contract Amount – $566,300.00 Construction Period – June – August 2015 (1% Complete) Project Scope – Roof Repair & Waterproofing.
Staging in progress.