F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

download F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

of 25

Transcript of F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    1/25

     

    WHJ BH-L08

    ANDASSOCIATED PIPELINES 

    SURVEY SPECIFICATIONSFOR

    SUBSEA PIPELINES

    DOCUMENT NO. F2 -SUR-001 REV. 2  

    2 01/05/2001 ISSUED FOR WHJ BH-L08 RAB /RB R.A.B

    REV DATE DESCRIPTION BY CHECK APP.

    TABLE OF CONTENTS

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    2/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 2 of 25

    1 GENERAL .................................................................................................................................4 

    2 GEODETIC PARAMETERS ........... ........... .......... ........... ........... .......... .......... ........... ........... ...... ...5 

    2.1  SPHEROIDS AND PROJECTIONS................................................................................................................. 5 

    2.2  TRANSFORMATION PARAMETERS ........................................................................................................... 6 2.3  CO-ORDINATES..................................................................................................................................................6 

    2.4  COMPUTATION OF POSITION .....................................................................................................................6 

    3 OPERATIONAL REPORTING.....................................................................................................6 

    3.1  DAILY......................................................................................................................................................................6 

    3.2  PRELIMINARY REPORTS ............................................................................................................................... 6 

    3.3  FINAL REPORT...................................................................................................................................................7 

    4 BASIC SPECIFICATIONS FOR CONTRACTOR'S EQUIPMENT.... ........... ........... ...... .............. ...... 7 

    4.1  SURVEY VESSEL ............................................................................................................................................... 7 

    4.2  NAVIGATION SYSTEM .................................................................................................................................... 8 

    4.3  PRIMARY POSITIONING.........................................................................................................................................8 4.3.1  Calibration..................................................................................................................................................... 9 

    4.3.2  Secondary Positioning .............................................................................................................................. 9 

    4.3.3  GPS/DGPS Quality Indicators .............................................................................................................10 

    4.4  GYRO COMPASS.............................................................................................................................................10 

    4.5  COMPUTER SYSTEM..................................................................................................................................... 10 

    4.5.1  Minimum Specification............................................................................................................................ 11 

    4.6  BATHYMETRIC SYSTEM ............................................................................................................................... 11 

    4.6.1  Minimum Specifications .........................................................................................................................11 

    4.6.2   Acquisition of Bathymetry......................................................................................................................12 

    4.7  SIDE SCAN SONAR SYSTEM .....................................................................................................................12 

    4.7.1  Dual Frequency Side Scan Sonar .......................................................................................................12 

    4.7.2  Minimum Specifications .........................................................................................................................13 

    4.7.3  Calibration...................................................................................................................................................13 

    4.7.4  Digital Graphic Recorder  ........................................................................................................................13 

    4.7.5  Survey Coverage .......................................................................................................................................13 

    4.8  SUB-BOTTOM PROFILER ............................................................................................................................ 13 

    4.9  ELECTRONIC DISTANCE MEASURING AND SPIRIT LEVELLING EQUIPMENT.....................14 

    5 SURVEY OPERATIONS ...........................................................................................................14 

    5.1  PERSONNEL ...........................................................................................................................................................14 

    5.1.1  Manning Levels.......................................................................................................................................... 15 

    5.2  PIPELINE ROUTE PRE-ENGINEERING SURVEYS ..............................................................................15 

    5.3  PIPELINE ROUTE PRE-ENGINEERING JACKET RISER FACE SURVEYS................................. 17 

    5.4  PIPELINE ROUTE PRE-LAY/CONSTRUCTION CLEARANCE SURVEYS  .................................... 17 

    5.5  PRE-INSTALLATION ANCHOR CLEARANCE SURVEYS ..................................................................17 

    5.6  PIPELINE INSTALLATION SURVEY OPERATIONS ...........................................................................18 

    5.6.1  Positioning and Computer System .....................................................................................................18 

    5.6.2  Navigation System ...................................................................................................................................19 

    5.6.3  Monitoring of Touch Down Point..........................................................................................................20 

    5.6.4   Anchor Handling........................................................................................................................................20 

    5.6.5  Manning .......................................................................................................................................................20 

    5.7  PIPELINE AS-LAID CONDITION SURVEYS...........................................................................................20 

    5.7.1  Real Time Pipelay Records ...................................................................................................................21 5.8  POST-LAY PIPELINE AS BUILT/AS LAID SURVEYS. .......................................................................21 

    5.9  POST-INSTALLATION JACKET RISER FACE SURVEYS.................................................................21 

    5.10  POST INSTALLATION ANCHOR CLEARANCE SURVEYS ............................................................... 21 

    6 CHARTING AND REPORTING REQUIREMENTS ........... ........... .......... .......... ........... ........... .... ...21 

    6.1  PIPELINE ROUTE PRE-ENGINEERING SURVEYS ..............................................................................22 

    6.1.1  Data Processing .......................................................................................................................................22 

    6.1.2  Charting .......................................................................................................................................................22 

    6.2  PRE-ENGINEERING JACKET RISER FACE SURVEYS ...................................................................... 23 

    6.2.1  Data Processing .......................................................................................................................................23 

    6.2.2  Charting and Reporting ........................................................................................................................... 23 

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    3/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 3 of 25

    6.3  PIPELINE ROUTE PRE-LAY/CONSTRUCTION CLEARANCE SURVEYS  .................................... 23 

    6.4  PRE-INSTALLATION ANCHOR CLEARANCE SURVEYS ..................................................................23 

    6.4.1  Data Processing and Charting..............................................................................................................23 

    7 REPORTING...........................................................................................................................23 

    7.1  SURVEYS TO ESTABLISH THE AS LAID CONDITION OF THE PIPELINES ............................23 

    7.1.1  Data processing........................................................................................................................................23 

    7.2 

    POST-INSTALLATION JACKET RISER FACE SURVEYS..................................................................24 

    7.2.1  Data Processing .......................................................................................................................................24 

    7.3  POST INSTALLATION ANCHOR CLEARANCE SURVEYS................................................................24 

    7.3.1  Charting .......................................................................................................................................................24 

    7.3.2  Reporting..................................................................................................................................................... 24 

    8 FINAL REPORT.......................................................................................................................24 

    8.1  D ATA AND D ATA SUBMISSION............................................................................................................................ 25 

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    4/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 4 of 25

    1 GENERAL

    The contractor shall conduct survey works associated with the offshore construction requirements of

    the Contract Scope Of Work, namely:

    i. Pipeline Route Pre-Engineering Surveys

    ii. Pipeline Route Pre-lay/Construction Clearance Surveys

    iii. Pipeline Pre-Installation Anchor Clearance Surveys.

    iv. Pipeline Installation Survey Operations

    v. Surveys to establish the As Laid condition of the Pipeline and Appurtenances

    vi. Post-lay Pipeline As Built/As Laid Surveys.

    vii. Pipeline Post-Installation Anchor Clearance Surveys.

    Surveys i will require the contractor to produce a new and full set of charts and drawings.

    Surveys ii, iii, v and vii will require the contractor to update the existing QP Project Chart Folio as

    appropriate with data acquired during each particular Survey.

    The contractor shall use the charts updated as a result of the Pipeline Pre Installation AnchorClearance Surveys to produce his proposed anchor patterns.

     Approved Data acquired during the Engineering Surveys may be combined with dedicated data to

    produce e.g. the Pre Lay Construction Survey Charts.

    The Survey Specifications define the minimum Contract Survey requirements and apply to the

    contractor's survey personnel, survey vessels, installation barges, anchor handling tugs and all auxiliary

    vessels comprising the survey spread or attached to the project.

    Submissions shall be transm itted for approval in both hardcopy and in a 100% digital format

    fully compatible with, and for introduction into, QP's software packages (Word, Excel,

    AutoCAD 2000, Adobe Acrobat). All such submissions shall be subject to a dedicated and QP

    approved Document Management System.

     At least four weeks prior to the proposed mobilisation of any survey operations the contractor shall

    submit a Dedicated Survey Quality Assurance Manual for QP's approval. This manual shall specifically

    and comprehensively address and describe:

    - the proposed equipment and personnel dedicated to the project,

    - the equipment manufacturers’ relevant specifications and data sheets,

    - the contractor's standard operating procedures, including, but not

    limited to equipment operation, calibration, deployment and data handling and processing.

    The contractor shall provide a method statement for each and every operation, calibration or procedure

    intended as part of the works. The contractor shall deploy and operate all systems and equipment in

    accordance with the manufacturers' recommended practices. The contractor shall demonstrate thequality and format of the data expected from his proposed equipment and operational procedures.

    Copies of sample records shall be submitted with each method statement in hard copy and digital

    format. Such data will have been acquired by the contractor from previous operations using equipment

    similar to that proposed.

    The contractor shall submit and maintain a dedicated Survey Programme. All subsequent revisions to

    this Programme shall be transmitted for QP's receipt at least seven days prior to such revisions coming

    into force.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    5/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 5 of 25

    Demobilisation of or modifications to the contractor's survey personnel and equipment shall be subject

    to QP's written approval.

    The contractor warrants that all equipment supplied is thoroughly maintained and checked prior to

    deployment and that it meets and performs according to the manufacturers’ minimum specifications.

     An adequate level of spares and consumables shall accompany the equipment to maintain a

    continuous operation.

    The contractor shall maintain a record of his activities. Detailed logs are to be kept and shall be

    submitted to QP on a daily basis. As a minimum, the logs shall make reference to the dedicated

    survey personnel, their positions and responsibilities; equipment identification, calibration and user

    defined settings; details of system mal-function and downtime; survey vessel sailing itinerary,

    percentage completion status.

     Any anomalies between the contractor’s field data and the Project Chart Folio shall be quantified and

    resolved prior to the demobilisation of the survey spread.

    Immediately upon the completion of each survey and prior to the demobilisation of the survey spread,

    the contractor shall submit a preliminary report.

     A Final Report shall be prepared both in hardcopy and digital format for each phase of the works and

    shall be submitted for QP's approval within four weeks of his decommissioning /demobilising the survey

    spread.

    2 GEODETIC PARAMETERS

    2.1 SPHEROIDS and PROJECTIONS

    For all offshore operations, QP utilises the Universal Transverse Mercator (UTM) projection based on

    the Clarke 1880 Spheroid, with an established datum at Nahrwan.

    The following parameters define the QGPC system:

    ITEM DEFINITION 

    Spheroid Clarke 1880 

    Semi Major axis (a) 6378249.145

    Semi minor axis (b) 6356514.869

    Flattening (1/f) 293.465

    Horizontal Datum Nahrwan

    Projection UTM Zone 39 

    Central Meridian (CM) 51°E

    Latitude of Origin 0° 

    False Easting 500000

    False Northing 0

    Scale Factor on C.M. 0.9996

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    6/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 6 of 25

    2.2 TRANSFORMATION PARAMETERS

    Spheroid δx δy δz

    Nahrwan to WGS84 -250.20 -153.09 +391.70

    The above parameters shall be used for transforming the Primary and Secondary Positioning Systems'co-ordinates between the Clarke 1880 and WGS84 Spheroids. All co-ordinates transformed shall be

    computed via geocentric co-ordinates. DELTA NORTH and DELTA EAST factors SHALL NOT BE

    USED in a simple additive form.

    2.3 CO-ORDINATES

    The QP database containing UTM Grid co-ordinates for the offshore control stations shall be made

    available to the contractor. The contractor shall familiarise himself with this local survey network. The

    contractor shall extend the network as necessary. Prior to using any newly established stations, the

    observations, reductions, adjustments and final co-ordinates shall first be approved and confirmed

    suitable by QP. 

    The contractor shall propose his methods and procedures for establishing the Co-ordinates of any

    control station he may require in terms of the WGS 84 Spheroid.

    2.4 COMPUTATION OF POSITION

    Positions shall be presented as UTM Grid positions and computed by a least squares adjustment

    method. The standard deviation and range residuals, where applicable, shall be available as an integral

    part of each computation of position. The Quality Statement attached to the sub-surface computed

    positions should reflect the achieved accuracies of both the surface and sub-surface positioning

    systems.

    3 OPERATIONAL REPORTING

    The contractor shall develop and submit for approval a dedicated Survey Reporting Procedure. The

    Procedure shall be tailored to suit the particular requirements of each phase of the works.

    Comprehensive details of the proposed Reporting Procedures and a typical layout sheet shall be

    submitted for approval prior to mobilisation.

    3.1 DAILY

    The contractor shall maintain a continuous and comprehensive record of his activities. On a daily basis,

    he shall transmit daily reports to QP. Daily reports shall commence from the start of mobilisation.

    3.2 PRELIMINARY REPORTS

    Prior to demobilising the survey spread from the field, a Preliminary Report describing and concludingon the execution of the works and the results of each survey shall be prepared and formally transmitted

    to QP for examination and approval.

    The quality of the data and significance of the results shall be discussed and shall form an integral part

    of both the Preliminary and Final Reports. Any anomalies between this data and QP's existing

    database shall be quantified and resolved prior to the demobilisation of the survey spread.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    7/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 7 of 25

    3.3 FINAL REPORT

     A Report shall be prepared in 100% digital format for each phase of the works.

    4 BASIC SPECIFICATIONS FOR CONTRACTOR'S EQUIPMENT

    The contractor warrants that all equipment supplied is thoroughly maintained and checked prior to

    deployment and that it meets the manufacturer's specifications. An adequate level of spares and

    consumables shall accompany the equipment to sustain a continuous operation.

    The contractor shall calibrate, and maintain in calibration, his Equipment in accordance with his

    approved Quality Assurance Manual. Survey spread mobilisation shall include all wet testing and field

    calibrations. The equipment shall be formally accepted only when all tests and calibrations have been

    completed and accepted by QP.

    The contractor shall demonstrate the quality and format of the data to be expected from his proposed

    equipment and operational techniques. He shall include hardcopy samples of field records with each

    method statement or procedure. Such data shall have been acquired by the contractor from previous

    contracts using equipment similar to that proposed.

    The following shall be formally transmitted to QP prior to acceptance of the survey spread:

    - Calibration certificates

    - Navigation station descriptions

    - Computer configuration constants, geodetic parameters, run line data

    - Trial printouts from the computer system

    - Trial records from all sensors

    - Field test data for all systems

    4.1 SURVEY VESSEL

    In addition to the standard minimum requirements, each principal survey dedicated vessel shall have

    the following facilities:

    Bathymetric To include a Survey quality survey echo sounder producing heave

    compensated analogue and digital records.

     Accommodation In addition to suitable accommodation for the crew and contractor's

    PERSONNEL one single berth cabin with desk and chair shall be available for

    one QP REPRESENTATIVE.

    Survey Area Generous bridge space shall be available to allow for a smooth survey

    operation.

    Processing An area allocated for data processing/verification.

    Deck Equipment A small crane for deployment of the over the side survey sensors.

     At least one capstan or a winch drum to assist in recovering survey

    equipment.

    Photocopier, A3 capacity.

    Marine Fax link to QP in Doha (to send and receive on a 24 hr. basis)

    The facsimile facility is vital to the operations. The contractor's Survey Spread will be

    considered incomplete and unacceptable without such a facility. If communications via the

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    8/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 8 of 25

    contractor's facsimile facility are not available to QP's standard, local equipment and local

    charges, then the contractor shall, for the duration of the Survey Operations, install such

    facsimile receive/transmit facilities at the QP Communications Centre at RAA Doha.

     All Communications' Systems shall be suitably screened to avoid interference with the navigation

    systems.

    QP’s Marine, Survey and Safety Departments shall formally inspect and accept the survey vessel and

    any auxiliary vessel prior to mobilisation.

    4.2 NAVIGATION SYSTEM

    The contractor shall provide, maintain and operate a complete NAVIGATION SYSTEM, with sufficient

    spares, test and back-up equipment to sustain a continuous operation. The SYSTEM shall be

    configured such that for all areas of operations where positioning control is required, positioning control

    is available. Such a configuration shall take into account the potential occurrences of shadow zones,

    signal re-radiation and cancellation, obstructions and reflections. The approval of any item of navigation

    equipment shall be conditional upon the availability of sufficient spares and backup to complete the

    works without risk of delay.

    Procurement of the positioning systems' Frequency Licenses shall remain the responsibility of the

    contractor. A copy of the licenses shall be supplied prior to the mobilisation of the system. The

    licences shall remain valid for the duration of the works.

    For navigation control during the surveys, the Surface Positioning System shall comprise two

    independent means of deriving position, namely a Short range DGPS Primary System and a

    medium/long range DGPS Secondary System

    The contractor shall at all times be responsible for the maintenance and continuous operation of the

    positioning systems. He shall ensure that no ambiguities occur in the position of the survey vessel, of

    each system offset or of any features to be surveyed.

    The contractor shall independently establish, operate and maintain his approved base stations. Certainof the QP's offshore platforms may be available for the installation of base stations. Base stations

    deployed on operational or producing offshore platforms shall conform to Cenelec standards EN 50014

    and 50039 for the particular zone category.

    Comprehensive details of the complete arrangement shall be submitted for QP's approval at least four

    weeks prior to the proposed mobilisation/installation.

    4.3 Primary Positioning

    The contractor shall be responsible at all times for the acquisition of the Primary System generated

    signals. He shall provide a DGPS System with short range UHF or VHF locally generated Differential

    corrections.

    The contractor shall take into account the potential restrictions to operations caused by e.g. the non-

    availability of sufficient Satellites, an unacceptable Dilution of Precision and the potential interference to

    the transmission and reception of the locally generated Differential Corrections.

    The contractor's work programmes shall reflect the predicted non-availability of suitable GPS data.

    The contractor shall justify the local operational suitability of his proposed system and submit

    comprehensive details of his previous experiences with the system. Field trial reports, case histories

    and data sheets shall accompany all submissions.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    9/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 9 of 25

    The contractor's Primary positioning system shall operate with, as a minimum:

    - TRACKING: minimum of 8 parallel channels

    - PERFORMANCE: as a minimum: real time display of estimated Dilution of precision,

    Number of satellites in use, position quality statement.

    - POSITION: within a relative horizontal accuracy of +/- 3 metres

    The System shall not be used when less than 4 satellites are available for the computation of position.

    The contractor shall provide full details of the previous and expected performance and capabilities of his

    proposed system. Such performance shall indicate predicted satellite availability (SATVIZ) and

    corresponding DOP values likely to be experienced during his proposed operations, the areas where

    local masking of both the raw and differential signal is likely to occur and the system's resistance to the

    effects of multipath signals. The provision of performance data shall apply to the acquisition and

    processing of both the GPS data and the differential corrections.

    4.3.1 Calibration

    The System and spare equipment shall be subject to the following calibration:

    - Static Calibration- Positioning of WHJ by transit fixes.

    a) Static Calibration

     A static calibration shall be carried out and witnessed by QP. The calibration shall consist of

    measurements at existing WHJ survey control stations where data to establish the antenna UTM

    position will be acquired. From ≥15 minutes of valid data, the observed UTM position will be compared

    with QP's database to ensure the integrity of both Primary and Secondary Navigation Systems.

    b) Jacket Transits Position and Orientation Check

    QP shall designate those jackets available as offshore calibration points. The contractor shall confirm

    system calibration by transiting  the jacket in both directions, passing within 100m of the structure. Theobserved UTM centre position of the platform shall be determined from these fixes.

    4.3.2 Secondary Positioning

    The UTM positions derived from the secondary positioning system are required for comparative and

    Quality control purposes. The data obtained from the secondary positioning system shall be stand-

    alone. It shall not be used to influence the positions obtained from the primary positioning system.

    The contractor shall supply a medium range Differential Global Positioning System (DGPS) for all

    survey activities. He shall provide comprehensive details of his proposed DGPS equipment hardware

    and software. If proposed by the contractor, QP will consider the suitability of The Middle East

    Navigation Service (MENAS ) as a source for the secondary system differential corrections provided

    that the available MENAS reference stations can be selected manually.

    Both primary and secondary positions and the UTM co-ordinate differences of the datum shall be

    computed and presented at each position fix. Comparative data shall be carefully collated for

    subsequent analysis and for inclusion as a significant and dedicated section of the final report.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    10/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 10 of 25

    4.3.3 GPS/DGPS Quality Indicators

    Maintenance of the Quality Control and the Quality Assurance indicators shall remain the responsibility

    of the contractor. Such control shall include and indicate the Quality of the differential data-link, the

    differential reference station, the differential corrections, the raw GPS ranges themselves. compensation

    for system latency, satellite azimuth and elevation.

    The contractor shall monitor systems' performance in terms of the GPS SNR indicators; update rate;

    success rate of transmission and reception of differential corrections; quality data as predicted and

    achieved DOP values; LPME; discrimination between those satellites tracked and those used in

    computation. The post computation validity of any LPME figures shall be available, taking into account

    changes in individual velocities and range residuals.

    4.4 GYRO COMPASS

    The contractor shall provide a survey quality Gyro Compass aboard each vessel engaged in survey

    activities, anchor handling activities and aboard the installation barges. Gyro Compass installations

    shall be calibrated prior to deployment. The Gyro shall be interfaced to the survey computer system(s).

    The dynamic error of the survey gyro shall not exceed +/- 0.5 degree. The contractor shall submit for

    approval his proposed method of calibration, both alongside and in the field, prior to the acceptance

    trials. The gyrocompass calibration offsets shall be confirmed during and upon completion of the survey

    works.

    4.5 COMPUTER SYSTEM

    The contractor shall provide a Computer system or systems. The computer system shall be interfaced

    to:

    -the PRIMARY and SECONDARY positioning systems

    -the gyrocompass

    -the echo sounder (when specified)-the track plotter

    -the track guidance monitor(s)

    -the printer

    -TSS annotator or similar for annotation of all analogue records.

    The system shall include proven software capable of calculating the absolute datum UTM and offset

    UTM positions of all static and towed sensors, including those aboard the installation barge, where a

    surveying presence is required. The proposed configuration aboard the installation barges shall ensure

    that at all times, the contractor demonstrates adequate survey control of the operations

    Raw positioning and bathymetric data at the time of the event shall be logged to a magnetic medium for

    subsequent retrieval. The system shall be capable of providing on-line navigational control, of preparing

    track plots etc and of conducting standard survey computations.

    The calculation of UTM position from the redundant information shall use the method of least squares

    (minimum variance).

    The resulting standard deviation in the single position shall be used as a measure of precision. The

    software package shall include proven programs to plot S.D. histograms.

    During vessel survey operations, end of line histograms shall be produced for all position updates to

    show their Standard deviations and to confirm the vessel's across track error.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    11/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 11 of 25

    4.5.1 Minimum Specification

    The system shall be capable of simultaneously acquiring data from a minimum of two surface

    navigation systems. The software shall be capable of accepting and utilising the calibration constants

    relevant to gyro alignment and pitch and roll corrections.

     Antenna offsets shall incorporate gyro, pitch and roll etc. corrections. Positions shall be computed in

    real time.

    The system shall be capable of performing all necessary calibration computations and analysis, WHJ

    transiting computations and analysis may be achieved offline.

    The operator’s display(s) shall provide sufficient real time information for assessing the instantaneous

    and historical quality and status of the survey operations and acquired data. This shall include but not

    be limited to:

    - RMSE or standard deviation of a fix.

    - Current run lines and targets and the vessels position in relation to them.

    Display of approved field structure database

    Prior to commencing survey operations, the correct input and computation of all offsets shall be verified

    by manual computations.

    4.6 BATHYMETRIC SYSTEM

    The contractor shall provide, maintain and operate a complete BATHYMETRIC SYSTEM, with spares,

    test, calibration and back-up equipment to sustain a continuous operation, comprising the following:

    Heave Compensated Dual Frequency Echo Sounder

    The echo sounder system shall have typical operating frequencies of 33 kHz and 210 kHz with a

    minimum paper/recording width of 20 cm. Velocity of sound shall be adjustable up to 1580 m/sec.

    The system shall use a heave compensated transducer located as close to the centre line of the vessel

    as practical. The transducer draft shall be related to the vessel’s draft and measured at least twice a

    day.

    Velocity of sound observations shall be carried out prior to commencement and upon completion of

    each bathymetric survey session.

    4.6.1 Minimum Specifications

    - Simultaneous dual frequency transmission comprising a high frequency (+/- 200 kHz) and a

    low frequency (+/- 33 kHz).

    - transducers located as close as possible to the ship's centre line.

    - Heave compensation device of the accelerometer type only shall be acceptable.- Analogue records, and digital high or low frequency output to computer system.

    a) Records

    The analogue record shall be of good quality with the sea floor clearly represented throughout. The

    paper speed shall be set according to the bottom topography. In addition to field record annotations all

    unusual returns shall be highlighted. An attempt shall be made to quantify such returns or spurious

    echoes (fish, kelp, suspended anchor wires, fresh water or gaseous emissions etc.).

    b) Operating Standards

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    12/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 12 of 25

    The survey speed with echo sounder alone shall not exceed seven knots. However it will still be

    necessary to conform to the data density for the particular survey. The low and high frequency depths

    and the depth digitised shall always be displayed on the analogue trace.

    c) Calibration Procedures

    The echo sounder equipment shall be bench calibrated at least once a year to confirm that all

    electronic components remain within design specifications. The bench calibration report shall be

    supplied as part of the mobilisation.

    Field calibration of the echo sounder shall be performed at the start and end of each survey day. This

    calibration shall take place in the survey area and shall cover the whole water column. A bar check to

    20 metres shall be deployed to determine and effect the system transducer draft and scale corrections.

    The scale adjustment to the echo sounder shall be additionally obtained and confirmed by sound

    velocity probe, calibration transducer or salinity/temperature bridge. A minimum of 10 evenly spaced

    readings shall be obtained to compute the average sound velocity.

    The vessel draft shall be obtained with reference to the load line or other conspicuous and recoverable

    marks

    The velocity of propagation, if derived by means of temperature, salinity and depth measurements, shall

    be obtained from the empirical formula derived by CLAY and MEDWIN (1977):

    C = 1449.2 + 4.6 T - 0.055T2 + 0.00029 T3 + (1.34 - 0.01T) x (S-35) + 0.016D

    The temperature - salinity meter shall be capable of displaying temperature (deg C), salinity (0/00) and

    depth (m) to the following accuracies:

    § Temperature +/- 0.l deg C§ Salinity +/- 0.1 0/00

    Certified calibration certificates shall be submitted to QP prior to mobilisation.  

    4.6.2 Acquisition of Bathymetry

    The contractor shall ensure that the processed bathymetry data is available in ASCII format. Reduced

    Soundings submitted as such shall have their accompanying UTM position, E & N, thereby allowing

    immediate plotting and editing.

    4.7 SIDE SCAN SONAR SYSTEM

    The contractor shall provide, maintain and operate a complete SIDE SCAN SONAR SYSTEM, with

    spares, test and back-up equipment to sustain a continuous operation.

    4.7.1 Dual Frequency Side Scan Sonar

    The side scan sonar shall operate on a minimum of two frequencies and provide altimeter data for

    reduction purposes.

    Typical specifications of the side scan sonar transducer shall be:

    - Frequencies 100 kHz / 500 kHz or 100 kHz / 300 kHz;

    - Pulse length 0.1 / 0.02 msec.;

    - Horizontal beamwidth 1 deg. / 0.2 deg.;

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    13/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 13 of 25

    - Vertical beam width 40 deg. tilted 10 deg. - 20 deg. below horizontal.

    The contractor shall provide full details of his proposed means of positioning the Side Scan Sonar Fish.

    4.7.2 Minimum Specifications

    The Side Scan Sonar system shall, as a minimum, have the following features:

    - towfish - shall be available with 100 kHz and 500 kHz cards

    - Pulse duration 1ms

    - Horizontal beamwidth 1º 

    - Vertical beamwidth 40º  

    - Transducer inclination to horizontal, typically 10° but adjustable to 20° 

    - Rugged armoured tow cable with separate signal lead screened for cross-talk-free reception of

    sonar signals.

    - Minimum 30cm wide side scan record via a thermal paper recorder.

    - Minimum range scale of 25m on recorder.

    - Remote event marker.

    - Annotation capability

    The Side Scan Sonar towfish shall be deployed over a metering wheel. The arrangement shall be

    secured to the A-Frame or Towing davit by means of a spring loaded or strain-absorbing shackle. The

    metering wheel shall indicate the length of cable out via a remote read-out to the sonar recorder's

    operator. Winch controls shall be located at both the winch and at the sonar recorder operating

    location.

    4.7.3 Calibration

     As part of the pre-mobilisation acceptance tr ials, the sidescan sonar system shall be calibrated for the

    various water depths and laybacks expected during the surveys. The calibration of lateral sonar

    contacts shall be confirmed by "boxing in" and positioning previously identified in field structures e.g.

    sub-sea wellheads or mooring piles. The contractor shall submit a comprehensive procedure for all such

    sidescan sonar calibration operations, carefully identifying the relative and absolute determination of thevarious sub-sea features.

    4.7.4 Digital Graphic Recorder

    The digital graphic recorder, of type Waverly or similar, shall use thermal paper with a minimum

    recording width of 25 cm and have a minimum of three selectable channels.

    4.7.5 Survey Coverage

    200% coverage is required for all Side Scan Sonar work. The design of the proposed Survey line

    spacings shall clearly account for congested areas where the anticipated coverage will only be achieved

    by reducing the line spacing.

    4.8 SUB-BOTTOM PROFILER

    The contractor shall provide, maintain and operate a complete SUB-BOTTOM PROFILER system with

    sufficient spares and test equipment to sustain a continuous operation.

    The 2 kHz - 7 kHz system shall be capable of detecting the UTM position of buried pipelines and

    investigating the first sub layers of the seabed. For optimum resolution, (typically 0.5 metres,

    consistent with good penetration, typically 5 - 15 metres) output from the system shall be operated at

    the lowest power setting.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    14/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 14 of 25

    Data is to be displayed on a graphic recorder at the maximum scale available.

    Swell filtering is to be employed.

    4.9 ELECTRONIC DISTANCE MEASURING AND SPIRIT LEVELLING EQUIPMENT

    The contractor shall provide, maintain and operate a complete set of Electronic Distance Measuring

    equipment (infra red) comprising four stations (three reflector stations) suitable for forced centring.

    - Theodolite: direct reading to one second of arc.

    - Electronic Distance Measuring Unit Range 5 km, S.D. +/- 10 mm + 2 ppm.

    The Spirit Levelling Equipment shall be deployed during Installation and As Built Survey Operations,

    and seen capable of meeting the required tolerances

    5 SURVEY OPERATIONS

    The following Surveys shall be conducted as part of the Contract:

    i. Pipeline Route Pre-Engineering Surveysii. Pipeline Route Pre-lay/Construction Clearance Surveys

    iii. Pipeline Pre-Installation Anchor Clearance Surveys.

    iv. Pipeline Installation Survey Operations

    v. Surveys to establish the As Laid condition of the Pipeline and Appurtenances

    vi. Post-lay Pipeline As Built/As Laid Surveys.

    vii. Pipeline Post-Installation Anchor Clearance Surveys.

    5.1 Personnel

    The minimum requirements for personnel are as follows:

    Position   Category  Minimum Requirements 

    Party Chief A Formal qualification in Hydrographic Survey and 10 years

    field experience with 5 years in related works

    OR a minimum of 15 years field experience in related

    works.

    Senior Surveyor B Formal qualification in survey and 5 years field experience

    Senior Engineer C Formal qualification in electronics and 5 years field

    experience in related works

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    15/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 15 of 25

    5.1.1 Manning Levels

    The Survey Party Chief will supervise and be responsible for all Survey Operations and Survey Project

    Management. He will not operate as an On-Line Surveyor.

     ACTIVITY MINIMUM PERSONNEL CATEGORIESPER 12 HOUR SHIFT

    Pipeline Route Pre-Engineering Surveys B, C

    Pipeline Route Pre-lay/Construction Clearance Surveys B, C

    Pipeline Pre-Installation Anchor Clearance Surveys. B, C

    Pipeline Installation Survey Operations:

    i. Barge Operations

    ii. Anchor Handling

    B, B, C

    B per AHV

    Surveys to establish the As Laid Condition of the Pipeline

    and Appurtenances

    B, C.

    Post-lay Pipeline As Built/As Laid Surveys. As per the requirements of E-S-L 60.

    Pipeline Post-Installation Anchor Clearance Surveys B, C

    5.2 PIPELINE ROUTE PRE-ENGINEERING SURVEYS

    The surveys shall be undertaken for the engineering design of the proposed pipeline route and for all

    temporary and permanent construction features e.g. pipeline crossings' temporary protection and

    permanent supports, laydown areas and the pipeline anchorage areas. The contractor shall acquire

    data on the bathymetry, sea floor topography and first sub-bottom layers to identify the presence of any

    condition considered hazardous to the installation and operation of the pipeline. The contractor shall

    acquire sufficient data and in sufficient detail to enable the detailed engineering of the submarine

    pipelines and all appurtenances and to effect any modifications to the design of the pipeline's proposed

    alignment.

    The contractor shall, where necessary, increase the survey areas to ensure that all pre-engineering

    data required, is in fact acquired. If the proposed route is seen to be unsuitable and requires significant

    modification, then the contractor shall acquire sufficient extra data, if necessary outside the previously

    defined survey corridors, to allow the revised route pre-engineering works to continue, without delay, to

    completion.

    The following systems shall be deployed during the Pipeline Route Pre-Engineering Surveys and

    operated according to Section 4 above:

    Survey Vessel, Navigation System, Computer System, Bathymetric System, Sidescan Sonar System,

    Sub-Bottom Profiler, Electronic Distance Measuring and Spirit Levelling Equipment.

    The Pipeline Route Pre-Engineering Surveys shall be undertaken to establish the actual seabed

    conditions along and adjacent to the proposed pipeline route. The contractor shall determine the

    presence of all structures, pipelines and pipeline crossings, metallic and non-metallic obstructions and

    debris, undulations, outcrops and any other feature likely to influence the design or installation of the

    proposed pipeline. For the detection of metallic debris close to the proposed pipeline route, the

    contractor shall ensure that the equipment proposed is capable of detecting such debris and that as a

    result of the equipment's sensitivity and detection capabilities, whatever remains undetected, will not

    significantly affect the installation and operation of the pipeline. The contractor shall establish seabed

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    16/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 16 of 25

    conditions at the locations of all anticipated pipeline supports and at each proposed pipeline crossing or

    supported span. All such features shall be comprehensively described and uniquely identified. Their

    UTM co-ordinates shall accompany the descriptions of these features. The UTM Grid co-ordinates

    defining the limits of each feature shall also be available to QP in ASCII format.

    The Engineering Surveys comprise the Pipeline Route Pre-Engineering Surveys and the Pre-

    Engineering Jacket Riser Face Surveys. The contractor shall deploy, on all survey lines, a dual

    frequency sidescan sonar system, a sub-bottom profiler system and a dual frequency bathymetry

    system to record water depths, the presence of seabed features, obstructions and existing pipelines

    and structures. Seabed data will be acquired, examined and described with reference to the pre-

    engineering design works.

    Prior to each pipeline survey, the contractor shall submit, for QP approval, details of his proposed

    survey line layout and proposed line and event numbering system.

    Sufficient bathymetric data shall be acquired to ensure that intervals of no more than 5 metres appear in

    the data set. The raw bathymetric data shall be processed and reduced to Chart Datum by means of

    QP's Tidal Predictions. The processed and reduced bathymetry data shall also be available

    independently, as digital x, y, z data, for direct entry to QP's database.

    The positions of all Wellhead Jackets, sub-sea structures and pipelines falling within the prescribed

    survey areas shall be determined and compared with QP's current database. Any anomalies resulting

    from such comparisons shall be brought to QP's immediate attention. The anomalies of position,

    configuration, heading etc. shall be resolved prior to demobilisation of the survey spread.

    Preliminary charts and a report shall be produced and delivered to QP prior to demobilising the survey

    spread.

    The contractor shall satisfy himself and demonstrate that the survey is complete and free from

    ambiguities.

    The Pipeline Route Pre-Engineering Surveys shall be conducted for each pipeline within a corridor

    extending a minimum of 100 metres perpendicular to and on either side of the proposed pipelinecentreline.

    Pairs of straight and parallel survey lines shall be run at ≤ 25 metres line spacing. The orientation and

    selection of such lines relative to the proposed pipeline alignment shall be selected for optimum target

    detection. Adjacent sidescan sonar lines shall be run in opposite directions to achieve 200% sonar

    coverage. Cross lines, at intervals not greater than 200 metres, shall be run perpendicular to the

    proposed pipeline centreline.

     Additionally, survey lines acquiring bathymetry and sub-bottom profiler data shall be run along the

    centreline of each proposed or subsequently amended pipeline route.

    Maximum deviation from intended lines shall be +/- 5 metres for 95% of line length or contiguous length

    of line. All lines failing to achieve this level of vessel control shall be re -run.

    The UTM position and orientation of each terminating platform shall be determined and confirmed during

    the seabed survey.

    To supplement the seabed data acquired from the longitudinal lines, pairs of survey lines shall be run

    across the riser face(s) of each terminating jacket. The orientation of these transverse lines shall be

    determined on site, to suit local conditions. The side scan range and frequency for these pairs of

    transverse lines shall be selected for optimum target response.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    17/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 17 of 25

    The proposed crossings of existing pipelines and the areas of potential free-spans shall be further

    examined as a separate and dedicated operation. Pairs of lines, parallel and perpendicular to the

    existing pipeline, shall be run to "box in" and provide high definition sonargrams of the crossing, free-

    span and surrounding seabed. The examination shall extend at least 50 metres either side of the

    construction limits of each proposed pipeline crossing or suspected free span.

    Where significant obstructions or a potential hazardous condition are detected, additional survey lines,

    10 metres apart, shall be run with the towfish recording at 50 metres range. Line length and orientation

    shall be selected to best resolve the nature and extent of the hazardous condition. The UTM positions

    and limits of such features shall be available as ASCII format x, y data.

    The data shall be inspected during the course of the survey. The presence of seabed or sub-seabed

    conditions, likely to result in a modified route alignment, shall be brought to QP's immediate attention.

    5.3 PIPELINE ROUTE PRE-ENGINEERING JACKET RISER FACE SURVEYS

    These surveys shall be undertaken to verify the Engineering Design Drawings and to confirm these

    particular sections of the proposed route.

     A Riser face survey shall be conducted at each connecting jacket. The survey shall confirm the preciseconfiguration and alignment of the new pipeline route and all appurtenances between the sub-sea riser

    flange extending to the top of the risers and 5 metres above MSL at the Terminating Platform. The

    alignment of the pipeline and piggy backed appurtenances shall be described relative to existing

    features i.e. risers, riser clamps, anodes and centres of jacket legs, cross bracings etc.

    5.4 PIPELINE ROUTE PRE-LAY/CONSTRUCTION CLEARANCE SURVEYS

    Prior to the Installation of the pipeline and appurtenances, the contractor shall confirm the integrity of

    each pipeline route. The contractor shall ensure that the pipelay conditions established as a result of

    the Pipeline Route Pre-Engineering Surveys and upon which the pipeline route was designed have not

    significantly deteriorated.

    The contractor shall propose his means of establishing and confirming to QP that no significantchanges have occurred to the site conditions and that the integrity of the designed route has been

    maintained since the Pre Engineering Surveys were conducted.

    The contractor shall bring to QP's immediate attention the presence of newly found conditions

    likely to affect the integrity of the proposed pipeline route.

    5.5 PRE-INSTALLATION ANCHOR CLEARANCE SURVEYS

    Within a corridor, 1200 metres either side of each proposed pipeline route, the contractor shall conduct

    sufficient survey works utilising typically side-scan sonar, sub-bottom profiler equipment etc. to ensure

    that the charted sub-sea locations of all pipelines, cables, jackets, wrecks etc. and significant sea-bed

    features are as depicted by the QP 1:2500 database.

    In the absence of approved anchor patterns and for the purposes of line planning, the minimum anchor

    wire lengths shall be taken as 1200 metres.

    Upon completion of these and any subsequent and extra verification works, the contractor shall confirm

    or otherwise that the relevant QP Charts portray a complete, accurate and realistic indication of the

    water depths and the presence of all structures and seabed details within his proposed anchor patterns.

    The contractor shall quantify and resolve any anomalies between his data and QP's existing database

    prior to the demobilisation of the survey spread. The contractor shall update and submit for approval

    those QP charts revised by the contractor as a result of his surveys.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    18/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 18 of 25

    Thereafter, the contractor shall utilise the updated Project Folio of QP 1:2500 Charts as baseline data

    for the submission of his proposed anchor patterns.

    5.6 PIPELINE INSTALLATION SURVEY OPERATIONS

    The following systems shall be deployed during the Pipeline Installation Survey Operations and

    operated according to Section 4 above:

    Navigation System, Computer System, Survey Quality Gyrocompass, Electronic Distance Measuring

    Equipment.

    The pipeline, pipeline supports, pipeline anchorages and all temporary and permanent appurtenances,

    shall be constructed and installed to the specified Engineering tolerances. During pipeline construction,

    Survey operations shall be controlled and managed from the pipelay barge. The contractor shall

    produce a Survey Procedure detailing all survey operations and his proposed means of fulfilling the

    requirements of these operations.

    During construction and installation operations, the contractor shall maintain precise

    positioning and orientation control of the pipelines, of the start-up and lay-down heads, of the

    pipeline anchorages (dead-men anchors) and of the temporary and permanent pipelinesupports at pipeline crossings and along unsupported spans. This control, together with the

    proposed deployment of his personnel and equipment resources, shall be seen capable of

    achieving the required installation tolerances of position, elevation and orientation. The

    Navigation Systems and Gyro Compass shall be checked at intervals not exceeding 7 days.

    The contractor's proposed Installation Procedure shall make particular reference to the means by which

    he intends to position, install and check the location of all temporary works (pipeline supports, A & R

    Equipment, dead-man Anchors etc.).

    5.6.1 Positioning and Computer System

    The contractor shall prepare a comprehensive SURVEY INSTALLATION PROCEDURE adequately

    describing:Method of installation (pipelines, temporary sleepers, pipeline anchorages, start-up and

    lay down arrangements etc.)

    Monitoring of the installation,

    Survey personnel, their responsibilities and deployment,

    Proposed equipment.

    Throughout the installation of each Pipeline, the contractor shall provide a Positioning capability to

    maintain unambiguous control of the installation barge/vessel, the anchor handling vessels, the

    pipelines and all temporary and permanent facilities required to ensure that the installation tolerances

    can be achieved.

    The system shall prepare and display a Pipelay Database (background structure file) using the Project

    Chart Folio. This database shall include the positions of all pipelines and proposed pipeline crossings,structures and obstructions as identified during the Pre-Installation seabed survey and the anchor

    clearance survey. The database shall contain the pipeline route alignment data and details of all

    approved anchor pattern configurations, laydown areas and spoolpiece locations. The Structure files

    shall be inspected and approved by QP prior to use. In this case, they shall be provided as

     AutoCAD2000 compatible and editable data

    The core of the Computer system shall be installed in the laybarge Control Tower. The system shall

    include proprietary software dedicated to the pipeline construction environment. The system shall

    provide continuous real time UTM co-ordinates for the following:

    - The Navigation antennae.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    19/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 19 of 25

    - The pipeline touch down point (TDP).

    - The beadstall position.

    - Each Anchor Handling Vessel's stern offset.

    The graphics capability shall allow continuous display of the anchor locations, the design route

    centreline, the lay corridor and the as laid pipeline. These data shall be superimposed on the approved

    database (structure files).

    For each predicted TDP position, the following information, as a minimum, shall be available to the

    operator:

    - the layback distance to T.D.P.

    - the actual KP value.

    - the pipe joint number.

    - the "distance to go" to any selectable target (e.g. laydown location, tangent point, Tee

    Piece location, pipeline crossing etc.")

    - the distance offline.

    - the barge survey gyro heading.

    During pipelaying the computer system shall continuously portray and update the database

    with each successive determination of the predicted TDP. VDU presentation of the TDP, bargelocation and heading, design corridor and neighbouring pipelines, structures and obstructions

    shall be readily available in the control tower.

    5.6.2 Navigation System

    The Navigation system, its operation and calibration shall comply with the requirements of Section 4.

    Positions shall be computed and supplied in terms of UTM Grid co-ordinates. The proposed Navigation

    Systems shall be installed, calibrated and operated in accordance with the contractor's approved

    procedures. The systems are required to provide all data necessary to compute the datum and offset

    positions of the laybarge, the Anchor Handling Vessel and any other vessel requiring a surface

    positioning capability. The Navigation System shall be maintained operational until all construction

    survey activities have been successfully completed and approved by QP.

    Each Anchor Handling Vessel shall have a dedicated and calibrated survey Gyrocompass, linked to the

     Anchor Handling Vessel positioning system, to provide the UTM position of any offset. The vessel's

    heading shall be available during each anchor handling operation. The UTM position of the Anchor

    Handling Vessel and any offset shall be continuously available at the laybarge. The Anchor Handling

    Vessel shall transmit its position to the survey system in the control tower. The track progress of the

     Anchor Handling Vessel shall be logged and superimposed graphically on the database of existing

    pipelines, structures and obstructions. The Anchor Handling Vessel shall be conned to the required

    drop location. During anchor deployment and recovery, the track of the Anchor Handling Vessel shall be

    logged, displayed and monitored in the control tower. A comprehensive record of all anchor-handling

    activities, including the Anchor Handling Vessel track data and graphics shall be maintained and, on a

    daily basis, submitted to QP's representative offshore. The contractor shall assess the requirements of

    the Anchor Handling Activities and submit, for QP's approval, a suitable procedure to achieve theserequirements.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    20/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 20 of 25

    5.6.3 Monitoring of Touch Down Point.

    During pipeline installation, aboard the laybarge, the UTM co-ordinates for the predicted position of the

    Touchdown Point (TDP) shall be continuously plotted and logged to disk. The surveyor on watch shall

    maintain a permanent record of the water depth and of the predicted horizontal distance from stern

    datum to TDP.

    5.6.4 Anchor Handling

    The contractor shall maintain a history of each anchor deployment and recovery.

    The intended position, the dropped position, the monitored positions the recovered position and position

    differences OF EACH ANCHOR shall be recorded in UTM co-ordinates as a ms Excel worksheet.

    During deployment and recovery, the Survey System on board the Anchor Handling Vessel shall

    produce a continuous plot of the vessel's track.

    On a daily basis, the UTM position of each anchor shall be acquired and monitored to determine anchor

    drag or winch slip. Copies of the Tabulated positioning data and survey logs shall be maintained in anapproved format as a typical MS Excel spreadsheet.

    These data shall be used to determine the survey line coverage required during the Post lay Anchor

    Clearance Surveys.

    5.6.5 Manning

    The number and designation of Survey personnel dedicated to construction operations shall be

    sufficient to adequately fulfil the requirements of the construction programme. It is normal for operations

    to be continuous over a 24 hour period. Sufficient survey personnel shall be engaged to ensure the safe

    and proper navigation and operation of the laybarge, the Anchor Handling Vessel, the survey vessel and

    each auxiliary vessel; to perform the maintenance, repair and replacement of the survey equipment and

    to acquire, interpret and process the survey data.

    5.7 PIPELINE AS-LAID CONDITION SURVEYS

    Immediately upon the installation of each pipeline, the contractor shall conduct the Pipeline As Laid

    Condition Surveys. As a result of such surveys, the extent and nature of all construction remedial works

    shall be determined. For the whole length of the newly installed pipeline, and prior to his commencing

    any remedial works, the contractor shall establish the As Laid Condition and report on and submit in

    both hardcopy and ASCII file format, as a minimum, the following:

    1. At intervals not exceeding 5 metres, the As Laid UTM positions and KP values of the pipeline

    and of all appurtenances

    2. The UTM position, the KP value and the length of each unsupported section of pipeline.

    3. Side Scan records demonstrating that the pipeline has sustained no significant damage duringinstallation and a visual record of those sections of the pipeline where damage has occurred

    and where repair works may be necessary.

    The contractor's procedure for Conducting and Reporting on The As Laid Condition of the Pipeline and

     Appurtenances shall be approved prior to the laying of pipe.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    21/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 21 of 25

    5.7.1 Real Time Pipelay Records

     As laid charts at 1:2500 scale shall be maintained and updated daily to show the pipelay corridor, the

    design route, the successive as laid positions of the pipeline, details of all unsupported sections and

    areas of suspected damage.

    For each pipeline, and prior to his commencing any proposed remedial works, the contractor shall

    compile a preliminary Pipeline Installation Report for formal submittal to the QP offshore representative.

    5.8 POST-LAY PIPELINE AS BUILT/AS LAID SURVEYS.

    The pipeline As-Built Surveys shall be conducted on completion of all pipeline commissioning and

    testing works in accordance with Document ES-L-60.

    Sufficient data shall be acquired to accurately define, in terms of UTM co-ordinates, the pipeline

    position including the positions and construction details of all spoolpiece configurations, riser

    configurations, pipeline crossings and unsupported sections. These UTM positions shall be submitted

    in ASCII format for immediate entry into the QP Survey database.

    5.9 POST-INSTALLATION JACKET RISER FACE SURVEYS

    The contractor shall determine the precise alignment of the pipelines and all appurtenances at each

     jacket face, from riser bend to top of riser. Previously approved data acquired during the installation of

    these "vertical" sections of pipeline may be incorporated and will contribute to the Project As Built

     Alignment Records.

    The contractor shall confirm the integrity of this installation data and take advantage of data acquired

    and approved during the pre-installation jacket face surveys.

    5.10 POST INSTALLATION ANCHOR CLEARANCE SURVEYS

    The following systems shall be deployed during the Pipeline Post-Installation Anchor Clearance

    Surveys and operated according to Section 4 above:

    Survey Vessel, Navigation System, Computer System, Sidescan Sonar System, Electronic Distance

    Measuring Equipment.

    The contractor shall conduct post installation anchor clearance surveys and confirm that the integrity of

    QP structures and assets has been maintained during the execution of the construction and installation

    works. Prior to the start of each survey, the contractor shall submit, in ms Excel and AutoCAD2000

    format, for QP approval, confirmation of the actual limits of the installation barge/vessel anchor patterns.

    The contractor shall submit a proposed line and event numbering system for QP's approval prior to

    commencing any survey works.

    Parallel survey lines shall be run at ≤ 100 metre line centres. The line orientation shall be selected for

    optimum target detection and accurate delineation of each feature. Adjacent lines shall be run inopposite directions to achieve 200% sidescan sonar coverage.

    Crosslines at 200 metres centres shall be run perpendicular to the main survey lines.

    6 CHARTING AND REPORTING REQUIREMENTS

     A Project Chart Folio will be prepared comprising digital charts prepared by the contractor:

    • from scratch using data acquired during the Pre Engineering Surveys

    • using and updating/confirming QP baseline data

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    22/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 22 of 25

    Data from third party sources or data acquired from previous surveys shall be included provided that the

    provenance and reliability of all such data can be established.

    QP shall provide the titles and a numbering system for all final charts.

    The contractor shall supply Charts, tabulated data and certain specific drawings in both hard copy and

    digital form The digital data shall be suitable for detailed editing and subsequent inclusion, via QP's

     AutoCad2000 Software, into the QP Mapping database. The UTM positions of all pipelines, pipeline

    features, appurtenances, natural and artificial seabed features and structures shall be supplied as non-

    compressed digital data, ASCII format, capable of individual editing and further plotting at user

    determined scales. Text based documents shall be produced and submitted as MS Word doc. files.

    6.1 PIPELINE ROUTE PRE-ENGINEERING SURVEYS

    6.1.1 Data Processing 

    The data presented shall include bathymetry (reduced to ACD using Employer provided predicted

    tides), sea floor features and sub-bottom geology. The data processing may include suitable data

    acquired as a result of the Diver Surveys. Data shall be presented both on a stable medium, at a scale

    of 1:2500 and in a digital form, for subsequent development on the Employer's AutoCAD2000 package.

    Water depths and contour lines shall be additionally submitted as ASCII data. Charts shall be sub-

    divided horizontally into three sections. Where more than one sheet is required to depict the pipeline

    route, scale shall be constant for each plot sheet. Matchlines shall be indicated.

    6.1.2 Charting

    6.1.2.1 Top section - "Bathymetry and Sea Floor Topography"

    Compiled soundings shall be shown at an approximate interval of 1 per 25 metres. All structures,pipelines, significant pockmarks, obstructions etc. shall be labelled and shown. Special care shall beexercised to ensure that extreme values of sea floor topography are represented by the soundings. Thechart shall be contoured at 0.5 m intervals. All data shall be used for the deve lopment of contours. Side

    scan sonar data, such as structural features, pipelines, depressions and obstructions shall be suitablyannotated

    The final proposed alignment of each pipeline route shall be superimposed on this section and indicatedby a dashdot line. The line shall be annotated to indicate the new works' radii of curvatures KP values,location and number of each tangent and intersection point, pipeline crossing, bend and tie in spoolpiece, Tee piece junctions etc. The UTM grid co-ordinates of these annotated features shall be added,in tabular form, to this section. The dashdot line and all annotations and tables shall be plotted suchthat the original survey data is preserved. The KP values shall be added wherever matchline andpipeline alignment intersect.

    6.1.2.2 Middle section - "Centreline Profile"

     A bathymetric profile shall be constructed from the echo sounder data acquired along and across the

    pipeline route centreline. Care shall be taken to ensure that all extreme values are represented. Thepresence of any shallow seismic reflectors shall be shown on this same profile. The profile shall be

    produced at a horizontal scale of 1:2500. The vertical scale shall be selected to clearly depict riser

    bends and spool piece configurations, Tee pieces and other significant pipeline features shall be added

    to the bathymetric profile. KP values shall be inserted above the profile and matchlines as appropriate.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    23/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 23 of 25

    6.1.2.3 Bottom Section – “Sub-Sea Hazards".

     A plan at 1:2500 scale shall be prepared to indicate all Geological Isopachs and anomalous conditions

    considered hazardous to the works. These shall include areas of numerous pockmarks or shallow

    gassy sediments, pockets of very soft sediments, rocky ridges, coral outcrops etc. The vessel trackplot

    and fix numbers shall be plotted “behind” the isopachs etc.

    6.1.2.4 Reporting

     A detailed report is required in which the designed alignment, the construction details at each proposed

    pipeline crossing, laydown area and pipeline anchorage, the nature, position and dimensions of any

    hazardous condition are comprehensively discussed.

    6.2 PRE-ENGINEERING JACKET RISER FACE SURVEYS

    6.2.1 Data Processing

    The data from the Jacket riser face surveys shall be presented as a new and dedicated set of large

    scale, well annotated, survey standard drawings. Plans, cross sections and front elevations shall beprepared to show the jacket legs, cross members, risers, valves, anodes and clamps etc. All relevant

    field dimensions are to be inserted. The precise alignment of the new pipework shall be superimposed

    to clearly define the route from mudline to top of riser.

    6.2.2 Charting and Reporting

    Prior to commencing the survey, the contractor's proposed format for the Jacket Riser Face drawings

    and reports shall be submitted for QP's approval.

    6.3 PIPELINE ROUTE PRE-LAY/CONSTRUCTION CLEARANCE SURVEYS

    The Data shall be presented on charts from the Project Folio and according to the contractor's approved

    means of confirming, immediately prior to pipeline construction, the integrity of the pipeline route

    6.4 PRE-INSTALLATION ANCHOR CLEARANCE SURVEYS

    6.4.1 Data Processing and Charting

    The Anchor Clearance Surveys shall be presented on charts from the Project Folio and shall adequately

    demonstrate the integrity of these charts. Additionally, the processed bathymetry and contour lines

    (reduced to Chart datum) shall be submitted as ASCII data, for editing within the AutoCAD2000

    environment.

    7 REPORTING

    The quality of the data and significance of the results shall be discussed and shall form an integral partof both the Preliminary and Final Reports.

    7.1 SURVEYS TO ESTABLISH THE AS LAID CONDITION OF THE PIPELINES

    7.1.1 Data processing

    The contractor shall provide sufficient personnel and facilities to conduct data processing operations

    offshore, aboard the survey vessel, during the surveys. Project Folio Charts shall be prepared to

    indicate the as built positions of each pipeline, pipeline feature and of all natural and artificial features.

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    24/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    Page 24 of 25

    The data shall be compared with the pre-installation charts and the pipeline as-laid installation records.

     Any anomalies shall be further investigated and accounted for.

    The contractor shall additionally handover:

    1. On a magnetic medium and in a format suitable for subsequent incorporation into the QP

    survey database, AutoCAD2000, digital files containing:

    a. The as installed positions of each pipeline. The intervals for these data shall be selected to

    both realistically present each pipeline deviation and to allow further editing and subsequent

    plotting at a scale no smaller than 1:2500.

    b. In MS Excel format, a schedule detailing the final as built positions and limits of all pipeline

    crossings, unsupported freespans, pipeline tie-ins and spoolpieces, riser bends and all other

    significant construction features.

    7.2 POST-INSTALLATION JACKET RISER FACE SURVEYS

     Approved data acquired during the installation of the "vertical" sections of pipeline may be incorporated

    as part of the POST-INSTALLATION alignment. The contractor shall however confirm the integrity of this

    installation data and take advantage of data acquired and approved during the pre-installation jacket

    face surveys.

    7.2.1 Data Processing

    Sufficient data shall be acquired to update the relevant Contract Engineering Pipeline Alignment

    drawings and reflect the as installed status of the pipeline and all appurtenances.

    Copies of the updated Engineering Drawings, in AutoCAD2000 compatible format, shall form part of the

    preliminary as -built report.

    7.3 POST INSTALLATION ANCHOR CLEARANCE SURVEYS

    The contractor shall conduct Post Pipeline Installation Anchor Clearance Surveys for those areas within

    the deployed anchor patterns. The results will confirm or otherwise that the integrity of QP structuresand assets has been maintained during the execution of the pipeline construction and installation

    works.

    7.3.1 Charting

    Charts shall be updated and produced from the Project Chart Folio, at a scale of 1:2500, to show all

    pipelines, jackets, mooring piles, sub-sea wells, permanent moorings and seabed features considered

    potentially hazardous to future anchor handling activities.

    7.3.2 Reporting

    The quality of the data and significance of the results shall be discussed and shall form an integral part

    of both the Preliminary and Final Reports.

    8 FINAL REPORT

    The contractor shall submit a Final Report describing and concluding Contract Survey Operations

    namely:

    i. Pipeline Route Pre-Engineering Surveys

    ii. Pipeline Route Pre-lay/Construction Clearance Surveys

    iii. Pipeline Pre-Installation Anchor Clearance Surveys.

    iv. Pipeline Installation Survey Operations

  • 8/18/2019 F2-SUR-001Rev2 Survey Spec for Subsea Pipelines

    25/25

    SURVEY SPECIFICATIONS FOR BH-L08 SUBSEA PIPELINES

    DOC. NO. F2 SUR 001 REV2

    v. Surveys to establish the As Laid condition of the Pipeline and Appurtenances

    vi. Post-lay Pipeline As Built/As Laid Surveys.

    vii. Pipeline Post-Installation Anchor Clearance Surveys.

    The Final Report shall be first submitted in draft form, for QP's approval, and may comprise those final

    reports prepared and prepared during each individual survey.

    The DRAFT and FINAL REPORT shall be presented both in hard copy form and in 100% digital form.

    The text and charts shall be presented on a magnetic medium (CD) for subsequent processing on QP's

    word processing, Spreadsheet, Adobe Acrobat and AutoCAD2000 drafting packages.

    The Final Report shall, as a minimum, comprehensively describe and cover:

    the Scope of Work, the Survey Operations, the Geodetic Parameters, the Control Co-ordinates,

    the Proposed Pipeline Route Alignment Co-ordinates, the Anchor Clearance Surveys, the Survey

    Equipment operation and calibration, the Navigation Systems' performance, the As Built Pipeline

     Alignments, the Route KP's and lengths, pipeline suspension co-ordinates, the accuracy of surface,

    sub-surface and final quoted co-ordinates, the results of the As-Built and the Post Installation Anchor

    Clearance Surveys, the Anchor Handling Activities, the Survey Quality Control input, the Quality of all

    acquired data and subsequent computations, the performance of Personnel and Equipment, the Diaryof Events, the inclusion, preparation and production of all Charts, a discussion of the various error

    budgets.

    The following, as a minimum, shall be appended to the Final Report:

    the contractor's approved survey procedures and Quality Assurance Plans, the Control Station

    Descriptions, the Anchor Handling Records, vessel and lay-barge offset data, all equipment and system

    calibration data including original observations, abstracts, computations and results, a print of each as -

    built chart, anchor clearance chart and post installation anchor clearance chart.

    8.1 Data and Data Submission

     All raw survey data acquired by the contractor during the execution of the works shall remain theproperty of QP. During its acquisition, the contractor shall maintain a comprehensive inventory of all

    such data. The contractor shall retain all raw data until such a time as QP has formally approved and

    received the FINAL REPORT, whence the contractor shall formally handover this raw data and the final

    inventory to QP.

    Prior to the acquisition of Contract specific data, the contractor shall provide sample digital data to

    confirm the suitability and acceptability of his proposed data format.