Experimental Response and FRC Strengthening of Existing RC ...€¦ · Experimental Response and...
Transcript of Experimental Response and FRC Strengthening of Existing RC ...€¦ · Experimental Response and...
-
Experimental Response and FRC Strengtheningof Existing RC Members
Brian Stratman – Business Development Leader - MAPEIGiulio Morandini, Alberto Balsamo, Ciro Del Vecchio, Marco Di
Ludovico, Andrea Prota
University of Naples “Federico II”Dept. of Structures for Engineering and Architecture
Milano, Italy
-
Recent seismic events outlined the main structural weaknesses of existing RC buildings:
- Brittle failure of structural members due to lack ofproper seismic details
INTRODUCTION
- Joint panel shear failure due to the lack of stirrupsin the joint panel
- Buckling of longitudinal reinforcement due to thehigh spacing of stirrups (200-300 mm)
-
OBJECTIVES
- Identify the main structural weaknesses of the case study building viaexperimental tests
- Sampling of the specimens from real building damaged by the L’ Aquila 2009earthquake and demolished
- Design and testing of a proper seismic retrofit solution (HPC material) for shearstrengthening of beam-column joints
- Design and testing of a proper retrofit solution (HPC material) to improve theconfinement of columns
-
CASE STUDY BUILDING
Case Study 5 storey RC building built in 1963
severely damaged by the L’Aquila earthquake (2009)
-
Perimetral frame with corner joints
BUILDING DEMOLITION
The building was demolished due to:
- Economic inconvenience of structural retrofitting (after a detailed seimic assessment)
- Poor-quality concrete (fc < 8 MPa in some portion of the building)
-
Perimetral frame with corner joints
SPECIMEN SAMPLING
Two beamcolumn joints
were extractedat the first floor
JOINT 1
JOINT 2
-
350
500 6φ16
1350
Stir
rups
φ 6
/200
SPECIMEN SAMPLING
Column 2Column 1
Two Columnswere extractedat the second
floor of the same frame
-
(b)
S12
S7 + S17
S8
S9 S10
S11
S13
S14
S15
S1 – TRAVE PIANO TERRA
S2 – PILASTRO PRIMO PIANO
S3 – TRAVE PRIMO PIANO
S4 – PILASTRO PIANO SECONDO
S5 – PILASTRO PIANO TERRA
S6 – PILASTRO PIANO TERRA
COL 1 – COLUMN SECOND FLOOR
S16 – TRAVE PRIMO PIANO
S18 – PILASTRO PRIMO PIANO
S19 – PILASTRO PIANO TERRA S20 – PILASTRO PIANO TERRA
NON-DESTRUCTIVE TESTS
DESTRUCTIVE TESTS
EXTRACTED COLUMN
Investigated frame
fc =12 MPa
MATERIAL PROPERTIESDestructive and non-destructive material characterization tests were conducted on the entirebuilding and on the extracted portions
Concrete
Reinforcing steel diameter fy εsy Es εsh fu εsu [mm] [MPa] [mm/mm] [MPa] [mm/mm] [MPa] [mm/mm]
Longit. reinforc.
16 400.4 0.0020 203579 0.020 586.6 0.128 16 395.4 0.0022 178424 0.021 587.6 0.137 16 374.1 0.0019 196000 0.024 548.3 0.135 Mean (16) 390.0 0.0020 192667 0.022 574.2 0.133 12 360.4 0.0019 192217 0.024 504.4 0.236 12 357.5 0.0020 181415 0.022 501.9 0.148 12 362.5 0.0024 149463 0.014 506.3 0.010 14 364.2 0.0021 171254 0.019 526.2 0.213 Mean (12/14) 361.1 0.0021 173587 0.020 509.7 0.152
Stirrups
6 447.0 0.0025 181691 0.016 574.0 0.070 6 433.2 0.0027 160459 0.013 548.0 0.060 6 392.0 0.0018 213043 0.011 550.0 0.150 6 400.0 0.0026 153846 0.010 549.0 0.110 Mean (6) 418.1 0.0024 177260 0.013 555.3 0.098
smooth internal reinforcements
-
2080
1450
500
400
500
6φ12
Fd
constructionjoint
1600
400
400
FRP
wra
ppin
g
400400
FRP wrapping
+
400
500
1450
400
230
400
400
FRP
wra
ppin
g400
40
190
St. φ
6/20
0St
. φ6/
200
St. φ6/200
Setup steel pipeφ=130mm s=2mm
High strength mortar s=40mm
2φ14
2φ12
2φ14+2φ12
30
30
A
A
B
B
Stirrups with 90°bend
1450
500
400
500
4φ12350
400
FRP
wra
ppin
g400
1450
400
230
400
400
FRP
wra
ppin
g400
40
190
St. φ
6/20
0St
. φ6/
200
St. φ6/200
Setup steel pipeφ=130mm s=2mm
High strength mortar s=40mm
3φ14
30
30
C
C
Transverse beam (C-C)
2φ16
2φ14+2φ16
400
500
30
2φ14+1φ12
Top column (E-E)
EE
FFBottom column (F-F)
2φ16
2φ14+2φ16
400
30
2φ14+1φ12
550
250
250 200
HPFRCC jacketingjoint T_SJ
Lack of stirrups in the joint panel
- Smooth internal reinforcements
- Lack of transverse reinforcements (φ6 /200mm)
- No stirrups in the joint panel
- Bad quality construction joint
STRUCTURAL DETAILS
-
AC
TUA
TOR
Hc
= 3.
40 m
L = 1.65 m
TEST FRAME STEEL HINGE
PRESTRESSEDBAR
LOAD CELL
+
STRONG FLOOR
Fd
Stiff steel frames
TEST SETUP
Constant axial loadon the column
Cyclic displacementat the beam end
-
TEST RESULTS – AS-BUILT JOINT
Poor seismic performancedue to the joint panel shearfailure (in the positive loaddirection)
Beam yielding (in thenegative load direction)
-
-50
-40
-30
-20
-10
0
10
20
30
40
50
-7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7
Vc[kN]
Drift [%]
T_CJ
Beam yieldingVc= 19kN
Joint panel shear failure
Vc= 35 kN
TEST RESULTS – AS-BUILT JOINT
-
TEST RESULTS – AS-BUILT JOINT
-
TEST RESULTS – AS-BUILT JOINT
Close-up on the joint panel
-
Concrete cover removal (40 mm by using a
jackhammer to have a rough surface)
Stiff and hydraulic sealed formwork
Anti-corrosioncementitious mortar
HPC STRENGTHENING
Cast of the HPC strengthening
-
View of the strengthened specimen
HPC STRENGTHENING
-
Beam hinge in both the
directions
TEST RESULTS- HPC JOINTHigh effectiveness of theHPC strengthening whichavoided the joint panelshear failure promoting amore ductile failure mode
-
TEST RESULTS- HPC JOINT
-
TEST RESULTS- HPC JOINT
Close-up on the joint panel
-
COMPARISON
-50
-40
-30
-20
-10
0
10
20
30
40
50
-7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7
Vc[kN]
Drift [%]
T_HPCT_CJTh. Beam yielding (My-)Th. Beam yielding (My+)
Joint shear failure
+38% Strength
+54% Strength
+85% Dissipated energy
More details can be found in:
Del Vecchio C., Di Ludovico M., Balsamo A., Prota A. (2018)Seismic Retrofit of Real Beam-Column Joints Using Fiber-Reinforced Cement Composites. ASCE Journal of StructuralEngineering. Vol. 144(5), https://doi.org/10.1061/(ASCE)ST.1943-541X.0001999
https://doi.org/10.1061/(ASCE)ST.1943-541X.0001999
-
Experimental performances of sampled columns
COLUMNS
-
0
500
1000
1500
2000
2500
3000
0 2 4 6 8 10 12 14
N [kN]
d [mm]
TEST RESULTS-AS-BUILT COLUMN
Concrete crushing and barbuckling limited the axialload capacityMega testing machine (30.000 kN,
3000 tons axial capacity)
-
Ing. Ciro Del Vecchio
PRE-DAMAGE ON COLUMN 2
0.0
500.0
1000.0
1500.0
2000.0
2500.0
3000.0
0 2 4 6 8 10 12 14
N [kN]
d [mm]
Column 2 was pre-damageduntil the spalling of concretecover and then repaired andstrengthened
-
Ing. Ciro Del Vecchio
HPC STRENGT. COLUMN 2Concrete cover removal (by using a jackhammer to have a rough surface)
Stiff and hydraulic sealed formwork Cast of the HPC
strengthening
-
Experimental test demonstrated the high effectiveness of the HPC strengtheningincreasing the axial load capacity and delaying bar buckling
TEST RESULTS - HPC COLUMN
Cut of the HPC jacketbefore the test(it is working only inconfinement)
-
0
500
1000
1500
2000
2500
3000
3500
4000
0 5 10 15 20 25 30 35 40
N [kN]
d [mm]
Col_1Col_2Col_2-FRC
The confinement by using the HPCstrengthening increased the axial loadcapacity about the 37%
Strengthincrease (+37%)
COMPARISON
-
The experimental results can be summarized as follows:
• The premature shear failure of poorly detailed beam-column joints maysignificantly limit the seismic performance of existing buildings
FINAL REMARKS
• An innovative strengthening solution consisting of a thin FRC jacketing hasbeen proposed and tested
• The experimental test outlined the high effectiveness of the proposedstrengthening solution which changed the brittle failure mode in a ductile one(+38 to 54% strength increase, +85% energy dissipation)
• The same strengthening technique has been used also for columnconfinement with satisfactory results (+37% strength increase)
-
Thank you
Giulio Morandini, Alberto Balsamo, Ciro Del Vecchio, Marco Di Ludovico, Andrea Prota
University of Naples “Federico II”, ItalyDept. of Structures for Engineering and Architecture
Milano, Italy
Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28