Expectation Damages Contracts – Prof. Merges April 5, 2011.

54
Expectation Damages Contracts – Prof. Merges April 5, 2011
  • date post

    21-Dec-2015
  • Category

    Documents

  • view

    216
  • download

    0

Transcript of Expectation Damages Contracts – Prof. Merges April 5, 2011.

Page 1: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Expectation Damages

Contracts – Prof. Merges

April 5, 2011

Page 2: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Expectation – in depth

• “Loss in value” plus “other loss”

• Rest. 2d formula

• Concepts:– “Loss in value”– Other loss,– Minus cost avoided (i.e., saved by breach)

Page 3: Expectation Damages Contracts – Prof. Merges April 5, 2011.

What do these terms mean?

• “Loss in value” = direct loss; e.g., drop in price (for seller), price increase (for buyer)

• Other loss: 2nd order effects of the breach (e.g., loss in related contract); also incidental expenses (arranging cover, arranging resale, etc.)

Page 4: Expectation Damages Contracts – Prof. Merges April 5, 2011.

What about the “minus term”?

• Less cost avoided

• Simple example: Gross revenue – cost of production = profit

• If breach saves cost of production, must subtract this from damage award

Page 5: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Example

• K from S to B to split and sell firewood for $100

• B breaches before S has done any work

• Would have cost S $40 to split the wood; no other loss to S

• S gets (100 + 0) – 40 = 60

Page 6: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Vitex v. Caribtex

CARIBTEX

Page 7: Expectation Damages Contracts – Prof. Merges April 5, 2011.
Page 8: Expectation Damages Contracts – Prof. Merges April 5, 2011.
Page 9: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Vitex

• What was the deal?

Page 10: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Vitex

• What was the deal?

• Wool processing to escape import tariffs; quota system

• 125,000 yds cloth, 25 cents per yard

Page 11: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Basic damages calculation

• Gross profit (revenue): $31,250

• Direct costs: $10,136

• Profit: $21,114

Page 12: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Uncertainty in amounts?

• Who gets the benefit of the doubt?

• P. 610

Page 13: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Caribtex’s

• What is Caribtex’s argument re: “overhead expenses”

• Why do they argue this?

Page 14: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Overhead vs. “direct” costs

Costs

Profit

Rev-enue

Page 15: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Overhead vs. “direct” costs

Costs

Profit

Rev-enue

Page 16: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Numerical example

• Revenue – cost = profit (damages)

• $31,250 – 10,136 = 21,114

• $31,250 – 15,136 = 16,114

• Add $5000 in costs, save $5000 in damages owed

Page 17: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Opinion

• IF a portion of overhead should be allocated to the K, then Vitex “tacitly” recovered these expenses as part of its damages award

• Overcompensates Vitex for the breach, p. 610, bottom

Page 18: Expectation Damages Contracts – Prof. Merges April 5, 2011.

“Breach economics”

• The more costs the breaching party can attribute to the contract, the lower the aggrieved party’s damages

• And vice versa . . .

Page 19: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Overhead

• What is the difference between “overhead” and “direct costs”?

• Why does reallocating an expense from “overhead” to “direct costs” have the effect of lowering damages?

Page 20: Expectation Damages Contracts – Prof. Merges April 5, 2011.

• Why does re-allocating an expense from direct cost to overhead have the effect of increasing damages?

Implicit treatment of “overhead” as coming out of “profit” – overhead adds to damages (if it was anticipated); direct costs subtract from damages

Page 21: Expectation Damages Contracts – Prof. Merges April 5, 2011.

The key question

• Which costs are directly attributable to the K, and which are “general costs of doing business”?

Page 22: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Relevance of the UCC

• Does not directly apply (why not?)

• Applies by analogy

• Specifically mentions “overhead” in section on seller’s damages

Page 23: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Overhead and Individual Contracts

Overhead expenses

K1

K2

K3

K4

Page 24: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Overhead and Individual Contracts

Overhead

K1

Page 25: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Overhead and Individual Contracts

Overhead

K2

K3

K4

Page 26: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Laredo Hides Co. v. H&H Meat Products

Page 27: Expectation Damages Contracts – Prof. Merges April 5, 2011.

H&H Foods

Salvadore “Papa”

Hinojosa

Page 28: Expectation Damages Contracts – Prof. Merges April 5, 2011.
Page 29: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Performance and breach

• P. 614: What did H&H do? Who was actually in breach, according to the court?

H&H motive here?

Page 30: Expectation Damages Contracts – Prof. Merges April 5, 2011.

• UCC 2-711

• 2-712

• 2-713

“All about cover”

Page 31: Expectation Damages Contracts – Prof. Merges April 5, 2011.

§ 2-711. Buyer's Remedies In General; Buyer's Security Interest In Rejected Goods(2) If the seller is in breach of contract, the buyer, to

the extent provided for by this Act or other law, may: . . . .

(d) cover and have damages under Section 2-712 as to all goods affected whether or not they have been identified to the contract;

(e) recover damages for nondelivery or repudiation under Section 2-713 . . . .

(j) in other cases, recover damages in any manner that is reasonable under the circumstances.

Page 32: Expectation Damages Contracts – Prof. Merges April 5, 2011.

§ 2-712. "Cover"; Buyer's Procurement Of Substitute Goods

(1) If the seller wrongfully fails to deliver or repudiates or the buyer rightfully rejects or justifiably revokes acceptance, the buyer may "cover" by making in good faith and without unreasonable delay any reasonable purchase of or contract to purchase goods in substitution for those due from the seller.

(2) A buyer may recover from the seller as damages the difference between the cost of cover and the contract price together with any incidental or consequential damages under Section 2-715, but less expenses saved in consequence of the seller's breach.

Page 33: Expectation Damages Contracts – Prof. Merges April 5, 2011.

(3) Failure of the buyer to effect cover within this section does not bar the buyer from any other remedy.

Page 34: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Basic principles

• “Loss in value” plus “other loss”

• Rest. 2d formula

• Concepts:– “Loss in value”– Other loss,– Minus cost avoided (i.e., saved by breach)

Page 35: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Basic principles: applied

Loss in value: difference between hides contracted for and hides purchased on cover market: $142, 254.48

Other loss: transportation and handling: $3,448.95

Page 36: Expectation Damages Contracts – Prof. Merges April 5, 2011.

§ 2-712. "Cover"; Buyer's Procurement Of Substitute Goods

(1) If the seller wrongfully fails to deliver or repudiates or the buyer rightfully rejects or justifiably revokes acceptance, the buyer may "cover" by making in good faith and without unreasonable delay any reasonable purchase of or contract to purchase goods in substitution for those due from the seller.

(2) A buyer may recover from the seller as damages the difference between the cost of cover and the contract price together with any incidental or consequential damages under Section 2-715, but less expenses saved in consequence of the seller's breach.

Page 37: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Laredo Hides

• What was H&H’s argument?

• What did the court say?

• Why no requirement to prove that aggrieved party paid only “market price”?

Page 38: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Intentional inflation of damages – what result?

• Can Laredo “take H&H to the woodshed” because H&H breached?

Page 39: Expectation Damages Contracts – Prof. Merges April 5, 2011.

RE Davis v. Chem Corp v. Diasonics

Page 40: Expectation Damages Contracts – Prof. Merges April 5, 2011.
Page 41: Expectation Damages Contracts – Prof. Merges April 5, 2011.

RE Davis v. Chem Corp v. Diasonics

• Facts

• History

Does RE Davis have a defense in the suit by Diasonics? What can RE Davis do here?

Page 42: Expectation Damages Contracts – Prof. Merges April 5, 2011.

What is the damages issue?

Page 43: Expectation Damages Contracts – Prof. Merges April 5, 2011.

What is the damages issue?

• Did Diasonics suffer any injury or loss due to the RE Davis breach?

• P. 619, middle: “Diasonics later resold the equipment to a third party for the same price . . .”

Page 44: Expectation Damages Contracts – Prof. Merges April 5, 2011.

“Lost volume seller”

Page 45: Expectation Damages Contracts – Prof. Merges April 5, 2011.

“Lost volume seller”

X

Page 46: Expectation Damages Contracts – Prof. Merges April 5, 2011.
Page 47: Expectation Damages Contracts – Prof. Merges April 5, 2011.

X

Page 48: Expectation Damages Contracts – Prof. Merges April 5, 2011.
Page 49: Expectation Damages Contracts – Prof. Merges April 5, 2011.
Page 50: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Diasonics’ argument

UCC § 2-718: Liquidation or Limitation of Damages; Deposits

(1)[Liquidated damages]

(2) [Return of deposit, less $500]

(3) [Less seller’s offset for other damages]

Page 51: Expectation Damages Contracts – Prof. Merges April 5, 2011.

§ 2-706. Seller's Resale Including Contract For Resale

(1) In an appropriate case involving breach by the buyer, the seller may resell the goods concerned or the undelivered balance thereof. If the resale is made in good faith and in a commercially reasonable manner, the seller may recover the difference between the contract price and the resale price together with any incidental or consequential damages allowed under Section 2-710, but less expenses saved in consequence of the buyer's breach.

Page 52: Expectation Damages Contracts – Prof. Merges April 5, 2011.

§ 2-708. Seller's Damages

(1) Subject to subsection (2) and to Section 2-723:

(a) the measure of damages for nonacceptance by the buyer is the difference between the contract price and the market price at the time and place for tender together with any incidental or consequential damages provided in Section 2-710, but less expenses saved in consequence of the buyer's breach; and

(b) the measure of damages for repudiation by the buyer is the difference between the contract price and the market price at the place for tender at the expiration of a commercially reasonable time after the seller learned of the repudiation, but no later than the time stated in paragraph (a), together with any incidental or consequential damages provided in Section 2-710, less expenses saved in consequence of the buyer's breach.

Page 53: Expectation Damages Contracts – Prof. Merges April 5, 2011.

(2) If the measure of damages provided in subsection (1) or in Section 2-706 is inadequate to put the seller in as good a position as performance would have done, the measure of damages is the profit (including reasonable overhead) that the seller would have made from full performance by the buyer, together with any incidental or consequential damages provided in this Article (Section 2- 710).

Page 54: Expectation Damages Contracts – Prof. Merges April 5, 2011.

Holding, p. 622-23

“We agree with Diasonics that under some circumstances the measure of damages [under 2-708(1)] will not put a reselling seller in as good a position as it would have been had the buyer performed . . .”

Issues on remand