EXPANSION OF TRANSMISSION SYSTEMS IN A DEREGULATED ENVIRONMENT Yong Zheng Saskatchewan Power...
-
Upload
damaris-drakes -
Category
Documents
-
view
216 -
download
0
Transcript of EXPANSION OF TRANSMISSION SYSTEMS IN A DEREGULATED ENVIRONMENT Yong Zheng Saskatchewan Power...
EXPANSION OF TRANSMISSION SYSTEMSEXPANSION OF TRANSMISSION SYSTEMSIN A DEREGULATED ENVIRONMENTIN A DEREGULATED ENVIRONMENT
Yong ZhengYong ZhengSaskatchewan Power CorporationSaskatchewan Power Corporation
N.A.ChowdhuryN.A.ChowdhuryUniversity of SaskatchewanUniversity of Saskatchewan
Regulation:Regulation:
Regulated MonopolyRegulated Monopoly
Deregulation:Deregulation:
Re-structuring of the MarketRe-structuring of the Market
Re-regulationRe-regulation
Unbundling of ServicesUnbundling of Services
CompetitionCompetition
PrivatizationPrivatization
Open accessOpen access
Electrical Industry Regulation and Electrical Industry Regulation and DeregulationDeregulation
GenerationTransmission DistributionRetail Sale
Traditional regulated System Model
Deregulated System Model
Generation Company
Transmission Company Distribution Company
Retailers
Customers Customers
Monopoly FranchiseLimited Benefit Return
Generation & Retailing - DeregulatedTransmission & Distribution - Regulated
GOALS OF DEREGULATIONGOALS OF DEREGULATION
Lower utility ratesLower utility rates Choice of electricity providersChoice of electricity providers Efficient, cost based pricingEfficient, cost based pricing Encouraging renewable energy Encouraging renewable energy
sourcessources Customer specific servicesCustomer specific services
Transmission System CongestionTransmission System Congestion
Transmission system congestion means that one or several transmission lines in the system are overloaded.
G1
G2
Load1
Load2
Line1 Limit: 80MW
Power Flow: 90MW
150MW60MW
0MW
90MW
$20/MW
$40/MW
Transmission System CongestionTransmission System Congestion
The introduction of competition in electric The introduction of competition in electric power market has made power flow power market has made power flow control issues more complex and difficult control issues more complex and difficult than ever before. than ever before.
The scarcity of transmission capacity and The scarcity of transmission capacity and a continued demand for power from less a continued demand for power from less expensive sources lead to transmission expensive sources lead to transmission system congestion.system congestion.
Causes of CongestionCauses of Congestion
Market participants are blind to Market participants are blind to system operating conditions system operating conditions
Generation schedule is determined Generation schedule is determined by competitive marketby competitive market
System operator has no right to System operator has no right to interfere with market-based interfere with market-based generation schedule unless generation schedule unless congestion occurscongestion occurs
Consequences of CongestionConsequences of Congestion
Unsolved congestion will threaten Unsolved congestion will threaten system securitysystem security
Congestion relief will increase system Congestion relief will increase system operating costoperating cost
Congestion will bring extra cost to Congestion will bring extra cost to electrical userselectrical users
Congestion will hinder fair competition Congestion will hinder fair competition between generatorsbetween generators
Ways to Relieve CongestionWays to Relieve Congestion
Generation rescheduleGeneration reschedule
Interruptible load curtailmentInterruptible load curtailment
Transmission system expansionTransmission system expansion
Congestion ReliefCongestion Relief
G1
G2
Load1
Load2
Line1 Limit: 80MW
Power Flow: 80MW
110MW60MW
40MW
90MW
$20/MW
$40/MW
New Added Line
Research ObjectivesResearch Objectives
To develop methods to optimize To develop methods to optimize generation re-schedule when congestion generation re-schedule when congestion happenshappens
To include the effect of short-term power To include the effect of short-term power market on transmission network market on transmission network expansionexpansion
To assess several alternatives to find the To assess several alternatives to find the optimal transmission expansion in case optimal transmission expansion in case of congestionof congestion
Optimization of Generation RescheduleOptimization of Generation Reschedule
Mathematical Model of Optimum Mathematical Model of Optimum Generation Reschedule Generation Reschedule
AC Optimal MethodAC Optimal Method
Mathematical Model for Re-dispatchMathematical Model for Re-dispatch
i= 1
n
Min Ci *PGiObjective Function:Objective Function:
Subject toSubject to PL = 0i= 1
n
PGi
Ci = re-dispatch price submitted by Generator re-dispatch price submitted by Generator ii
PGi = active power variation of Generator active power variation of Generator ii
PL = change in transmission losschange in transmission loss
n = number of generators number of generators
AC Optimal MethodAC Optimal Method Based on AC power flow methodBased on AC power flow method
Linearized relationship between power Linearized relationship between power flow variation and generation variation flow variation and generation variation
Linearized relationship between Linearized relationship between transmission loss variation and transmission loss variation and generation variationgeneration variation
Takes transmission loss into accountTakes transmission loss into account
90MW
60M
W
G5(90MW)
T3
G4(0MW)
G1(45MW)
T1
G2(45MW)
T2
90MW(T3)
90MW(T1+T2)
G3
1 2
3 45
6
A System with Three TransactionsA System with Three Transactions
45 MW 0 MW MW
50
-30
70
-40
20
Price($/MWh) Price($/MWh) Price($/MWh)
G1 & G2 G4 G5
90
Reloading BidsReloading Bids
Active power flows before and after re-dispatchActive power flows before and after re-dispatch
Line Line No.No.
From From
ToTo Initial FlowInitial Flow
(MW)(MW)Flow After Re-Flow After Re-dispatch (MW) dispatch (MW)
111 1
22 29.45 29.45 29.6229.62
221 1
33 104.05104.05 89.6089.60
331 1
55 - 88.49- 88.49 -73.95-73.95
442 2
33 74.2974.29 59.4559.45
553 3
44 92.0692.06 61.3061.30
663 3
66 92.0692.06 92.0792.07
The increased cost due to the re-dispatch The increased cost due to the re-dispatch is $954.384/hr. is $954.384/hr.
Load function can be expressed as:Load function can be expressed as:P(t) = Q0 + Q(t) + Q(r); t = 1, 2, 3, ……, 24
Q0 andand Q(t) are non-price responsive partsare non-price responsive parts
Q(r) is the price responsive partis the price responsive part
Load ModelLoad Model
Benefit Function can be expressed as:Benefit Function can be expressed as:B(PGi) = F(PGi) + M(PGi)
Bidding ModelBidding Model
Cost function:Cost function: F(PGi) = PGi2 + PGi +
Profit function:Profit function: M(PGi) = k* PGi
Bidding price function:Bidding price function:H(PGi) = B(PGi)/PGi = 2PGi + + k
n
iGiit PBB
1
Total generating cost as seen by the ISOTotal generating cost as seen by the ISO
rQtQQrn
iii
0
1
Market Clearing Price, r can be found by Market Clearing Price, r can be found by solvingsolving
Actual bidding price curve
Linear bidding price function
$/MWh
Pmin Pmax MW
Bidding Price CurveBidding Price Curve
Transmission System ExpansionTransmission System Expansion
Expanding transmission system is more Expanding transmission system is more economic if congestion fee is higher than the economic if congestion fee is higher than the investment cost of building new transmission investment cost of building new transmission line.line.
Future short-term power market should be Future short-term power market should be considered when planning transmission considered when planning transmission system expansion.system expansion.
Different expansion options should be Different expansion options should be assessed when selecting the most acceptable assessed when selecting the most acceptable expansion scheme.expansion scheme.
Steps involved in transmission Steps involved in transmission system expansion planningsystem expansion planning
Forecast short-term market generation schedule Forecast short-term market generation schedule on the basis of typical load curves and bidding on the basis of typical load curves and bidding price functions.price functions.
Combine the predicted short-term generation Combine the predicted short-term generation schedule with long-term generation schedule to schedule with long-term generation schedule to evaluate system power flow distribution and evaluate system power flow distribution and congestion fee.congestion fee.
Select new lines that can relieve congestion with Select new lines that can relieve congestion with investment cost less than congestion fee.investment cost less than congestion fee.
Summary and ConclusionsSummary and Conclusions Deregulation makes power flow control more Deregulation makes power flow control more
complicatedcomplicated
Market-driven generation schedule results in Market-driven generation schedule results in transmission system congestiontransmission system congestion
Congestion will threaten system security and must Congestion will threaten system security and must be relieved be relieved
Generation reschedule will increase system Generation reschedule will increase system operating costoperating cost
Expansion of transmission becomes economic if Expansion of transmission becomes economic if the investment cost of building new transmission the investment cost of building new transmission facilities is less than the congestion fee. facilities is less than the congestion fee.
Question?