Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015

Transcript of Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio...

Page 1: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

Expanded Public Works Programme(EPWP)

Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works

23 June 2015

Page 2: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

2

Presentation Outline Quarter 4 performance analysis

Work opportunities

Full Time Equivalents

Designated Groups

Spatial Analysis: Sector Performance

Financial Performance and Integrated Incentive Grant Performance

Beyond the numbers

Outputs and services rendered

Enterprise Development & NSF Funded Training

Progress on Institutionalising the PEP – IMC

EPWP Reporting System

Challenges

Measures put in place to address challenges

Page 3: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

3

Overall EPWP Annual Targets (5 Years) per financial year

Financial Year

EPWP annual work opportunity

targets

EPWP cumulative

work opportunity

targets

EPWP annual FTE

targets

EPWP cumulative FTE targets

2014/15 1 045 520 1 045 520 420 952 420 952

2015/16 1 127 186 2 172 706 450 462 871 414

2016/17 1 343 154 3 515 860 519 724 1 391 138

2017/18 1 406 736 4 922 596 574 089 1 965 227

2018/19 1 455 840 6 378 436 591 846 2 557 073

Total 6 378 436 2 557 073Source: EPWP Phase 3 Targets (dated : 30 April 2014 )•Work Opportunities: Paid work created for an individual on an EPWP project for any period of time. The same person can be employed on different projects and each employment period will be counted as a work opportunity •FTE (Full Time Equivalence) : person days of work and training divided by 230 days

Page 4: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

Discussion on Performance of the EPWP in Q4

4

Work opportunities: •By Q4 of the 2014/15 FY, 1 103 983 Work Opportunities (WO) were reported against the annual set target of 1 045 520 which translates to 106%•The following sectors: Infrastructure, Social and Non-State: NPOs & CWP have reached their annual targets, except the Environment & Culture Sector which has created 221 090 WO against the set target of 227 650 (97%%) leading to a shortfall of 6 560 WO.•The major contributor of the WO reported in quarter 4 are from the Infrastructure Sector with 409 209 WO & Non-State Sector (NPOs & CWP) 249 078 WO.Full Time Equivalence:•A total of 387 278 Full Time Equivalents (FTEs) were created against the set target of 420 952 translating to 92%.•The only sectors that have reached their annual set FTEs targets is Infrastructure sector and the NSS:CWP with100% and 102% achieved respectively.•While the other sectors have achieved 91% - Environment & Culture, 82% - Social and the NSS: NPOs – 73%•The under performance on FTEs can be attributed to the shorter durations in the WO reported.

Page 5: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

5

Overall Progress to date against 2014-15 Targets(1 April 2014 – 31 March 2015)

Work opportunities (WO)

Source: EPWP Phase 3 Targets (dated 30 April 2014)•Work Opportunities: Paid work created for an individual on an EPWP project for any period of time. The same person can be employed on different projects and each employment period will be counted as a work opportunity •FTE (Full Time Equivalence) : person days of work and training divided by 230 days

Page 6: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

6

Overall progress against 2014-2015 targetsFull Time Equivalents (FTEs)

Page 7: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

7

Overall Analysis across all sectors and spheres of government:

(Q4: 1 April 2014 – 31 March 2015)

 

Infrastructure Environmental & Culture

Non-StateNPOs

Social Community Work

Total

Number of projects/ sites 7 035 3 377 36 4 927 171 15 836

Work opportunities (WO) 409 209 221 090 50 371 224 606 198 707 1 103 983

Average Duration of WO 69 77 91 94 126 87

FTEs 123 442 77 169 19 887 92 202 74 578 387 278

Page 8: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

Discussion on Performance of the Programme in Q4All Spheres of Govt

8

National Govt Depts:•The NSS: CWP has reported 198 707 WO against an annual target of 187 000 translating to 106%, whilst the NSS: NPOs Programme has reported 49 960 WO against a target of 49 000 translating to 104%.•All the other sectors at a national level were unable to reach their annual set targets.

Provincial & Municipalities•All provinces except for the FS and NC have exceeded their combined (provincial and municipal) annual targets on work opportunities.•The leading provinces in terms of performance is KZN with 173 774 WO reported at 130%, followed by EC with 109 850 WO reported translating to 129%. •For the combined performance, the lowest performing province is the Northern Cape with 74% achieved.

Page 9: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

9

National Government Departments progress against 2014-15 annual targetsWork opportunities and FTEs (1 April ‘14 – 31 March ‘15)

Source: Infra & Enviro Targets – EPWP Phase 3 targets (Apr 2014): NPO & CPW targets – EPWP Phase 3 targets (Apr 2014)

Non State sector Directorate, (July 2014)

% - Percentage of work opportunities or FTE reported against targetWork Opportunities (WO) – Work Opportunities reported by reporting bodies Full Time Equivalence (FTE) – person days of work and training divided by 230 days

SectorsWO

annual target

WO WO %FTE

annual target

FTE FTE %

Infrastructure 20 000 13 509 68 6 522 4 361 67

Environment & Culture 113 995 96 948 85 47 085 38 391 82

Social 42 218 39 326 93 15 052 9 360 62

Non-State:

Comm Work 187 000 198 707 106 73 174 74 578 102

Non-State: NPO 49 000 50 371 103 27 205 19 887 73

TOTAL 412 213 398 861 97 169 037 146 577 87

Page 10: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

10

Infrastructure, Environment and Culture and Social Sectors (TOTAL)

(Prov Govt Depts & Municipalities): Work opportunities against 2014-15 targets by Province

(Q4: 1 April 2014 – 31 March 2015)

Provinces Municipalities Total

Annual Target

Wk Opp Reported

% Annual Target

Wk Opp

Reported

% Annual Target

Wk Opp Reported

%

EC 40 276 82 477 205 45 117 27 373 61 85 393 109 850 129

FS 22 385 21 799 97 17 732 11 971 68 40 117 33 770 84

GP 48 377 51 385 106 63 670 74 664 117 112 047 126 049 112

KZN 87 637 112 156 128 45 893 61 618 134 133 530 173 774 130

Lim 39 131 32 916 84 23 690 32 407 137 62 821 65 323 104

Mp 24 879 34 269 138 19 239 16 198 84 44 118 50 467 114

NC 17 339 12 104 70 6 744 5 688 84 24 083 17 792 74

NW 27 613 39 971 145 16 698 12 668 76 44 311 52 639 119

WC 31 496 25 018 79 42 947 50 440 117 74 443 75 458 101

Total 339 133 412 095 122 281 730 293 027 104 620 863 705 122 114

% - Percentage of work opportunities reported against target

Wk Opp Reported – Work Opportunities reported to date

Source: Targets – Infra and Social sectors: EPWP Business Plan (Dated April 2014)

Environment & Culture Sector: E&C Sector Plan (June 2014)

Page 11: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

11

Work opportunities as percentage of Designated groups by Sector (1 April 2014 – 31 March 2015)

Page 12: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

12

Municipalities Reporting per Province 1 Apr 2014 – 31 March 2015 (Quarter 4)

Prov No of munics in Prov(18 May 2011 munic boundaries)

No munics reporting

Annual WO target (14-15)

WO reported(Q3 14-15)

WO progress against annual targets(%)

Eastern Cape

45 45 45 550 27 373 60%

Free State 24 23 17 580 11 971 68%

Gauteng 12 12 63 703 74 664 117%

KwaZulu-Natal

61 61 47 541 61 618 130%

Limpopo 30 30 23 610 32 407 137%

Mpumalanga 21 21 19 226 16 198 84%

Northern Cape

32 31 6 531 5 688 87%

North West 23 23 16 993 12 668 75%

Western Cape

30 30 43 198 50 440 117%

TOTAL 278 276 283 932 293 027 103%

Page 13: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

SPATIAL ANALYSIS: SECTOR PEFORMANCE

13

Social :•Social Sector targets only exist at a District and Metro level. •The performance on FTEs and WOs largely the same trend, i.e. those Districts exceeding their WO target also exceed their FTE targets.

Enviro:•More Local Municipalities and metros have exceeded their WO target than their FTE targets. •107 Local Municipalities and 5 metros exceeded their WO targets while 90 Local Municipalities and 4 metros exceeded their FTE targets.•There are more District that exceeded their WO targets than those that exceeded their FTE targets. There are 18 District exceeding the WO targets while 11 District exceeded their FTE targets.

Infra:•There are more Local Municipalities and metros that exceeded their WO target than their FTE targets. •103 Local Municipalities and 4 metros exceeded their WO targets while 60 Local Municipalities and 3 metros exceeded their FTE targets.•Similarly there are more District that exceeded their WO targets than those that exceeded their FTE targets. There are 10 District exceeding the WO targets while 4 District exceeded their FTE targets.

Page 14: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.
Page 15: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

15

Spatial distribution of work opportunities 1 Apr 2014 – 31 March 2015

• All 8 metropolitan municipalities are in the top 10 municipalities i.t.o WO.

• The WO reported in the top 10 municipalities represent 32% of the total 1 103 983 WO reported in the 2014-15 financial year.

Munic code Munic Name Prov Projects WO

CPT City of Cape Town Metro WC 1 540 63 568JHB City of Johannesburg Metro GP 493 59 534TSH City of Tshwane Metro GP 300 58 834ETH Ethekwini Metro KN 302 56 940BUF Buffalo City Metro EC 153 33 246EKU Ekurhuleni Metro GP 173 18 422NMA Nelson Mandela Bay Metro EC 189 17 431EC157 King Sabata Dalindyebo EC 153 16 665MP325 Bushbuckridge MP 522 16 483MAN Mangaung Metro FS 213 15 975

Page 16: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.
Page 17: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

Spatial distribution: Full Time Equivalent (FTE)1 April 2014 – 31 March 2015

.•The total FTEs reported in the top 10 municipalities represent 32% of the 123 234 FTEs reported in total for the 2014-15 financial year.

Local munic code

Local Munic Name District code District name Prov Projects WO FTE

JHB City of Johannesburg Metro JHB City of Johannesburg Metro GP 493 59 534 23 250

ETH Ethekwini Metro ETH eThekwini Metro KN 302 56 940 19 433

TSH City of Tshwane Metro TSH City of Tshwane Metro GP 300 58 834 17 188

CPT City of Cape Town Metro CPT City of Cape Town Metro WC 1 540 63 568 15 259

BUF Buffalo City Metro BUF Buffalo City Metro EC 153 33 246 14 035

KZN225 Msunduzi DC22 Umgungundlovu KN 89 13 245 7 018

MP322 Mbombela DC32 Ehlanzeni MP 277 15 378 6 981

EKU Ekurhuleni Metro EKU Ekurhuleni Metro GP 173 18 422 6 927

NW383 Mahikeng DC38 Ngaka Modiri Molema NW 197 15 868 6 637

MP325 Bushbuckridge DC32 Ehlanzeni MP 522 16 483 6 506

EC442 Umzimvubu DC44 Alfred Nzo EC 73 15 004 6 072

EC157 King Sabata Dalindyebo DC15 O.R.Tambo EC 153 16 665 5 836

NMA Nelson Mandela Bay Metro NMA Nelson Mandela Bay Metro EC 189 17 431 5 512

MAN Mangaung Metro MAN Mangaung Metro FS 213 15 975 5 268

NC091 Sol Plaatjie DC9 Frances Baard NC 127 10 189 4 752

Page 18: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

18

EPWP INTEGRATED GRANT PERFORMANCE

Page 19: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

19

Expenditure as at end of March 2015 – Integrated grant to provinces

Provinces Final Grant Allocation

Actual YTD Transfers

% Actual YTD Transfers

Total Expenditure to date

Exp % on Allocation

(R'000) (R'000) (R'000)

Eastern Cape 69,544 69,544 100% R 64,986 93%

Free State 26,601 26,601 100% R 23,737 89%

Gauteng 23,565 23,565 100% R 20,526 87%

Kwa-Zulu Natal 97,945 97,945 100% R 94,235 96%

Limpopo 32,247 31,004 96% R 26,619 83%

Mpumalanga 39,928 39,928 100% R 35,946 90%

Northern Cape 20,348 20,348 100% R 18,076 89%

North West 14,249 14,249 100% R 13,846 97%

Western Cape 24,520 24,520 100% R 21,796 89%

Total 348,947 347,704 100% R 319,767 92%

Page 20: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

Expenditure as at end of March 2015 – Integrated grant to Provinces

• The EPWP Integrated Grant to Provinces was completely disbursed to all provinces with the exception of Limpopo province where 96% of the grant was disbursed.

• This was because funds for Limpopo Departments of Education and Corporate Governance and Traditional Affairs were stopped due to non-compliance.

• The expenditure for the EPWP integrated grant to provinces is at 92%.

• Provincial Departments did not have full expenditure mainly due to delays in implementation of projects.

Page 21: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

21

Expenditure as at end of March 2015 – Integrated grant to Municipalities

Summary by provinceAllocated (R'000) Transferred to

date (R'000)Transfers as %

allocationExpenditure

to date (R'000)

Expenditure as %

allocation

Eastern Cape

100,628 100,628 100%

71,533 71%

Free State

31,592

31,592 100% 22,929 73%

Gauteng

89,799

89,799 100% 77,801 87%

Kwa-Zulu Natal

129,712 129,712 100%

89,030 69%

Limpopo

49,931

49,931 100% 37,432 75%

Mpumalanga

54,506

54,506 100% 39,314 72%

Northern Cape

38,757

38,757 100% 26,551 69%

North West

40,919

40,919 100% 27,397 67%

Western Cape

58,731

58,731 100% 40,541 69%

TOTAL

594,575 594,575 100%

432,528 73%

Page 22: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

Expenditure as at end of March 2015 – Integrated grant to Municipalities

• The EPWP Integrated Grant to Municipalities was completely disbursed to all eligible municipalities.

• The expenditure for the EPWP integrated grant to municipalities was 73% at 31st of March 2015.

• Municipalities have until the 30th of June 2015 to spend their full allocation.

Page 23: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

23

Expenditure as at end of March 2015 – Social Sector Incentive grant

Provinces Final Grant Allocation

Actual YTD Transfers

% Transfers to date

Total Expenditure to date

Exp % on Allocation

(R'000) (R'000) (R'000)

Eastern Cape 41,714 41,714 100% R 40,709 98%

Free State 11,700 11,700 100% R 10,028 86%

Gauteng 73,338 73,338 100% R 71,653 98%

Kwa-Zulu Natal 19,544 19,544 100% R 18,756 96%

Limpopo 18,632 18,632 100% R 17,826 96%

Mpumalanga 18,844 18,844 100% R 17,439 93%

Northern Cape 22,018 22,018 100% R 18,742 85%

North West 26,306 26,306 100% R 25,436 97%

Western Cape 25,876 25,876 100% R 24,548 95%

Total 257,972 257,972 100% R 245,137 95%

Page 24: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

Expenditure as at end of March 2015 – Social Sector Incentive Grant

•For the EPWP Social Sector grant to provinces, 100% of the allocation has been disbursed.

•The overall expenditure of the grant is 95%.

•The Northern Cape, Mpumalanga and Free State had lower expenditure than other provinces.

Page 25: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

• Outputs and services rendered • Enterprise Development• NSF Training• EPWP Reporting • Progress on Institutionalizing the PEP - IMC

25

BEYOND THE NUMBERS

Page 26: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

26

OUTPUTS – INFRASTRUCTURE SECTOR

Sector Description

Actual Outputs Reported

Infrastructure Fence installed 33 070 Km

Pipelines installed 109 923 Km

Roads constructed to standards

7 942 Km

Sidewalks constructed to standards

450 Km

Storm water drains constructed

64 632 Km

Roads Maintained 14 291 Km

Page 27: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

27

OUTPUTS – ENVIRONMENT & CULTURE SECTOR

Sector Description

Actual Outputs Reported

Environment and Culture

Hectares of areas treated for alien vegetation

1 366 Ha

Hectares of land controlled, protected and rehabilitated

51 Ha

Fence erected 10 112 KmStreets cleaned 7 942 Km

Households serviced (Waste Collection)

92 677

Trees planted 20 045Waste management programme established

5 023

Dumping sites cleaned 3 969 sqmGrass cutting areas 25 077 sqm

Page 28: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

28

OUTPUTS – ENVIRONMENT & CULTURE SECTOR

Sector Programme Description

Actual Outputs Reported

Social Sector

Home Community Based Care

HCBC practitioners recruited 19 570

Victims receiving support under the Victim Empowerment Programme (VEP)

1 134

National School Nutrition Programme

Learners benefitting from the National School Nutrition Programme (NSNP)

1 542 830

Early Childhood Development (ECD)

Children supported through the Child and Youth care worker services.

1 838

Safety and Security Volunteers reported in the Safety and Security programme.

12 510

Teacher Assistant Programme.

Learners supported through the Teacher Assistant Programme.

184 321

Page 29: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

29

ENTERPRISE DEVELOPMENT Through the Enterprise Development:

1.A total of 322 Small Medium and Micro Enterprises (SMMEs) have been supported.

2. Out of the SMMEs supported, 482 beneficiaries have benefited, with 247 out of this beneficiaries representing the Youth.

3. In addition, a total of 178 co-operatives have received the following training respectively:

Introduction to Entrepreneurship Training.

Diagnostic Assessment Training.

Practical exercise on Costing and Pricing Tendering, and

Co-operative Workshop.

Page 30: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

30

BREADKDOWN OF SMMEs and Coops SUPPORTED

Page 31: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

EPWP TRAINING

31

The EPWP received funding for training from the Department of Higher Education and Training (DHET) through the National Skills Fund (NSF) for the period 2010 – 2016.

The funding was allocated as follows:

R200 million for Short Courses, R110 million for Skills Programmes, R52 million for Artisan Development and Learnerships and R7.1 million for NECSA training.

Through further engagements with the various Sector Education and Training Authorities (SETA”s); the programme also managed to source R1,6 million from the FPMSETA discretionary grants for training of 639 EPWP participants on FPMSETA skills programmes i.e. chainsaw, brush-cutter, forestry etc.

Page 32: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

EPWP TRAINING…Cont’d

32

As per the NSDS III initiative, the EPWP has partnered with 3 various SETA’s up until the 31st March 2016, to assist with the rollout of the EPWP various training programmes.

The various SETA’s partnered with are AgriSETA, CATHSSETA and MerSETA to ensure that quality training is provided to beneficiaries.

Through AgriSETA, 120 Learnerships will be implemented on animal production and poultry production and 2 521 EPWP beneficiaries will go through Skills Programme on horticulture and plant production.

The CATHSSETA will implement skills Programme to 1 170 EPWP beneficiaries on public area cleaning, culture site guide, craft production, sports coaching and the logistics preparation of the implementation has already commenced.

The merSETA will implement the Artisan Development Programme on various trades including electricians, diesel mechanic, boilermakers to 109 EPWP beneficiaries. Subsequently, for the duration of the training the learners will be placed at Volkswagen South Africa, Toyota SA, Mercedes Benz.

Page 33: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

EPWP TRAINING…Cont’d

33

Short Courses Skills Programme Learnerships Artisan Development Programme

Province Multiskilling Headcount No of Participants of Trained

No of Participants Enrolled

No of Participants

EC 5 044 1 548 61 60 10

GP 3 659 1 125 476 0 22

LP 2 739 1 549 843 20 10

NW 2 719 1 981 201 20 5

MP 1 868 1 089 1348 100 14

NC 1 841 830 180 0 0

KZN 1 762 997 274 50 8

WC 1 568 814 192 0 13

FS 1 477 800 120 20 7

Total 22 697 10 733 3 695 270 89

Page 34: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

34

EPWP Phase 3 Reporting System• The EPWP Phase III new reporting will be conducted via a single source

reporting system which introduces new built validations.

• Real time application of validation rules will include ID number validations with the Department of Home Affairs and the DPSA for PERSAL information.

• An exciting development for the new system is the integration of biometric capability for better quality control. The biometrics will be used as a secondary identifier together with the EPWP participant ID number.

• Parallel recording for fingerprint recognition, where possible, will allow for the link of participant data to the data sets of other government systems.

• The system will be set up to accommodate various biometric measurements

• To date, the EPWP M&E Unit has conducted a number of training workshops with all the sectors and the implementing public bodies.

• All Public bodies are currently capturing the 2015/16 Quarter 1 (April to June 2015) data on the new system.

Page 35: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

35

Progress on Institutionalizing the PEP - IMC• The first sitting of the Public Employment Programme Inter-Ministerial Committee

is scheduled for the 08th July 2015 coupled by site visits to EPWP Projects in Gauteng Province.

• The PEP-IMC will be chaired by the Hon. Deputy President Mr Cyril Ramaphosa comprising of Ministers for the following core departments:

• Public Works

• Social Development

• Environmental Affairs

• Corporative Governance and Traditional Affairs

• Other Ministers from National Treasury, Small Business Development, Rural Development, Labour, Trade & Industry and Economic Development are critical members of the PEP-IMC and will be invited as and when required.

Page 36: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

36

Key Challenges

• Low technical capacity of public bodies to implement EPWP.

• Non attainment of person with disability and youth targets

• Non-attainment of FTEs targets – due to shorter duration of work opportunities.

• Social Sector Programme such as the National School Nutrition Programme (NSNP) not adhering to the minimum daily wage stipulated in the ministerial determination.

Page 37: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

37

Measures put in place to address challenges

• Technical support is being provided to public bodies to help them

implement their projects labour-intensively and to report effectively.

• Engagements are being held with Organisations that represent persons

with disabilities to improve their participation in EPWP.

• Engagements are being held with different programmes to enable them

adhere to the EPWP minimum wage.

Page 38: Expanded Public Works Programme (EPWP) Progress report for the roll-out of EPWP Phase 3 to Portfolio Committee on Public Works 23 June 2015.

38

Labour Market Dynamics Survey Results

From the 2014 Labour Market Dynamics survey released by StatsSA, the following has been

reported:Awareness about the Expanded Public Works Programme and other government job creation programmes has increased from 42,8% to 52,0% in 2014.

Women are more likely to participate in these programmes, with the share of women among those who participated increasing from 59,3% in 2011 to 63,1% in 2014.

In 2011, a larger proportion of youth participated (51,1%), but by 2014 this had reversed in favour of adults (54,4%).

In both 2011 and 2014, participation in the Expanded Public Works Programme was dominated by persons with an educational qualification lower than matric (65,6% and 69,9%).

In 2014, Eastern Cape accounted for 22,7% of those who participated in these programmes, followed by Gauteng (17,0%) and KwaZulu-Natal (14,9%).

In 2014, seven out of ten of those who participated in the EPWP and other government job creation programmes were employed.” This was up from 56.9% in 2011.

The survey also found that 4 out of every 5 participants who were employed had a formal sector job.