Excitation Test

download Excitation Test

of 16

Transcript of Excitation Test

  • 7/28/2019 Excitation Test

    1/16

    Generator Reactivity Limit

    Testing

    Workshop Presentation

    WECC Generator Testing Task Force

  • 7/28/2019 Excitation Test

    2/16

    What it is and what it isnt

    It is a quick and relatively easy test. It verifies reactive capability for only

    one set of conditions at 2 points.

    It does not verify generator capabilityfor all conditions.

    It does not verify all points in thegenerator capability curve.

  • 7/28/2019 Excitation Test

    3/16

    Letter Defining Requirement

  • 7/28/2019 Excitation Test

    4/16

  • 7/28/2019 Excitation Test

    5/16

    Testing Requirements

    All synchronous machines greater than 10 MVA

    Operating conditions should be as close to

    normal as practicable, including loading, unittemperatures, and pressures.

    Tests should be performed during periods of

    operation which maximize the MVAR in/outputof the machine (when system voltage is mostadvantageous to yield these results).

    When possible, other synchronous machines orpower system components should be used toobtain the most advantageous terminal voltage

    during these tests.

  • 7/28/2019 Excitation Test

    6/16

    Testing Requirements

    While operating in a steady state mode at netdependable MW capability (near rated output),

    raise excitation in automatic voltage control untilone of the following conditions occurs:

    The 100% MVA rating of the machine isreached (reached capability curve)

    Rated field current or field voltage is reached

    Terminal voltage limit is reached

    Generator temperature limits are reached

  • 7/28/2019 Excitation Test

    7/16

    Testing Requirements

    Maximum/over excitation limiter is

    reached/alarms Maximum reference adjuster travel or limit is

    reached

    Maximum auxiliary bus voltage is reached

    Hold unit at this level for a minimum of 15minutes (30 minutes is a preferable duration),then take measurements

  • 7/28/2019 Excitation Test

    8/16

    Testing Requirements

    While operating in a steady state mode at netdependable MW capability lower excitation in

    automatic voltage control until one of thefollowing conditions occurs:

    UELs are activated

    100% MVA rating is reached Generator temperature limits are reached

    Minimum reference adjuster travel or limit isreached

    Minimum auxiliary bus voltage is reached

    Minimum terminal voltage limit is reached

  • 7/28/2019 Excitation Test

    9/16

    Example Hydrogenerator

  • 7/28/2019 Excitation Test

    10/16

    Nom Voltage

    Min Voltage

    Max Voltage

  • 7/28/2019 Excitation Test

    11/16

    Application to Testing

    The rated MVA and 95% PFoverexcited point is at nominalterminal voltage. (blue line)

    This machine will not producerated MVA and 95% PF whenterminal voltage is at the

    maximum. (turquoise line) This unit passes the reactive

    capability test because Tests

    should be performed duringperiods of operation whichmaximize the MVAR in/outputof the machine (when system

    voltage is most advantageousto yield these results). (red)

    Min

    Nom

    Max

  • 7/28/2019 Excitation Test

    12/16

    Application to Capability

    The Generator Capability Curve should stateminimum capability for all rated conditions:

    terminal voltage, ambient temperature, etc.

    Internal and external events that limit capability

    normally considered separately. It may not bepossible to produce all limiting conditionssimultaneously.

    The reactive capability test does not validatethe machine capability curve.

  • 7/28/2019 Excitation Test

    13/16

    Machine Capability Maintenance

    Owners should be aware of changes and updatemachine capability curves.

    Operational events that indicate potentialcompromise of capability should be investigated.

    Due to the complicated nature of validatingcapability for all operational conditions andconsidering the potential impact to system

    operation, it is not prudent to mandate re-validation of capability.

    Operational events and routine maintenancenormally reveal potential problems.

  • 7/28/2019 Excitation Test

    14/16

    Benefits of Reactive Capability Testing

    Testing can detect significant degradation.

    Tests are simple and cause little risk.

    Tests confirm capability under nominal

    conditions. If the unit fails to meet the reactive capability

    under the most favorable conditions, it isproven to fail to meet the machine capabilitycurve on record.

  • 7/28/2019 Excitation Test

    15/16

    Reactive Capability Testing Limitations

    Passing reactive capability testing is a necessarybut not sufficient condition to assure machinecapability curve is accurate.

    May not detect outer loop control (SCADA) limits

    if tested under local control.

    Tests are done steady state with gentle moves

    approaching limits. Design for abnominalconditions may require more restrictive SCADAlimits.

  • 7/28/2019 Excitation Test

    16/16

    The End