Excelsior-Vryheid 132 kV Powerline - biothermenergy.com · This is the 2nd monthly report submitted...
Transcript of Excelsior-Vryheid 132 kV Powerline - biothermenergy.com · This is the 2nd monthly report submitted...
RE_OW_0046-007-CON-SAV-30EC-002-01
Excelsior-Vryheid 132 kV Powerline Western Cape Province
EA Ref: 14/12/16/3/3/1/1478
Environmental Monitoring Report No. 2
February 2019
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Prepared by:
Prepared for:
Amstilinx (RF) Proprietary Limited
Building 1, Leslie Avenue East,
Design Quarter District,
Fourways
2021
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page ii
PROJECT DETAILS
Title : Environmental Monitoring Report No.2 for the Excelsior-Vryheid 132 kV
Powerline.
EA Ref: 14/12/16/3/3/1/1478
Authors : Savannah Environmental (Pty) Ltd
Mr Lungani Zwane
Client : Amstilinx (RF) Proprietary Limited
Mr Ludwig Van Aarde
Report Revision : Revision 1
Date : February 2019
When used as a reference this report should be cited as: Savannah Environmental (2019) Environmental
Monitoring Report No.2 for the Excelsior-Vryheid 132 kV Powerline being developed in, Swellendam,
Western Cape Province.
COPYRIGHT RESERVED
This technical report has been produced for Amstilinx (RF) Proprietary Limited The intellectual property
contained in this report remains vested in Savannah Environmental (Pty) Ltd. No part of the report may be
reproduced in any manner without written permission from Savannah Environmental (Pty) Ltd or Amstilinx (RF)
Proprietary Limited.
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page iii
TABLE OF CONTENTS
PROJECT DETAILS ........................................................................................................................................................... ii
TABLE OF CONTENTS ..................................................................................................................................................... iii
DECLARATION ............................................................................................................................................................... vi
Chapter 1 : SUMMARY................................................................................................................................................... 1
Chapter 2 : INTRODUCTION .......................................................................................................................................... 1
Chapter 3 : OVERVIEW OF CONSTRUCTION PROGRESS TO DATE.............................................................................. 2
Chapter 4 : MONITORING AND REVIEWING................................................................................................................ 5
Description of observations, incidents and non-conformities identified during this monitoring and
reporting period ............................................................................................................................................................ 5
Description of measures implemented to reduce impact on the environment ......................................... 5
Chapter 5 : PUBLIC INVOLVEMENT ............................................................................................................................... 6
Chapter 6 : DUST MONITORING .................................................................................................................................... 6
Chapter 7 : PROTECTED VEGETATION .......................................................................................................................... 6
Chapter 8 : PROTECTION OF AVIFAUNA ..................................................................................................................... 7
Chapter 9 : HERITAGE .................................................................................................................................................... 7
Chapter 10 : EROSION ................................................................................................................................................... 7
Chapter 11 : REHABILITATION ....................................................................................................................................... 7
Chapter 12 : WASTE MANAGEMENT ............................................................................................................................ 8
Solid waste ....................................................................................................................................................... 8
Liquid waste ..................................................................................................................................................... 8
Hazardous waste ............................................................................................................................................ 8
Recycled waste .............................................................................................................................................. 8
Chapter 13 : ENVIRONMENTAL PERFORMANCE ......................................................................................................... 9
Environmental Management Programme - Results.................................................................................... 9
Environmental Authorisation - Results ........................................................................................................ 11
Management Plan – Results ........................................................................................................................ 13
Chapter 14 : OTHER NOTABLE EVENTS ....................................................................................................................... 15
Stormwater system investigation ................................................................................................................ 15
Chapter 15 : CONCLUSION AND RECOMMENDATIONS .......................................................................................... 15
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page iv
LIST OF TABLES, FIGURES/PHOTOS & FIGURES:
Photograph 1: Excavation of bases at the Vryheid Substation ................................................................................... 3
Photograph 2: Spoil material at the Vryheid Substation ............................................................................................... 3
Photograph 3: Mobile toilet at the Vryheid Substation ................................................................................................. 4
Photograph 4: General waste skip at the contractor site camp ................................................................................ 4
Table 1: Summary of waste removed from Excelsior WEF for February 2019. .......................................................... 7
Table 2: Percentage compliance score with the EMPrs for February 2019 .............................................................. 8
Table 3: Percentage compliance score with the EAs for February 2019 ................................................................10
Table 4: Percentage compliance score with the Management Plans for February 2019 ..................................12
Figure 1: Percentage compliance score with the EMPrs for February 2019 ............................................................. 9
Figure 2: Percentage compliance score with the EAs for February 2019 ...............................................................11
Figure 3: Percentage compliance score with the Management Plans for February 2019 .................................13
APPENDICES
Appendix A : Environmental Authorisation Checklist
Appendix B : Environmental Management Programme Checklist
Appendix C : Complaints Register
Appendix D : Incident Register
Appendix E : Permit to Pluck Protected and Unprotected Flora Checklist
Appendix F : Management Plans Checklist
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page v
LIST OF ACRONYMS, ABBREVIATIONS AND DEFINITIONS
DEA Department of Environmental Affairs
DAFF Department of Agriculture Forestry and Fisheries
DWS Department of Water and Sanitation
EA Environmental Authorisation
ECO Environmental Control Officer
EMPr Environmental Management Programme
EMS Environmental Management System
EO Environmental Officer
INCIDENT An incident is an event that may cause harm or potential harm to the environment.
These incidents must be reported to the ECO immediately and formally though means
of a flash report. For the purpose of this report, Reportable Environmental Incidents will
refer to incident that requires reporting in terms of National Environmental Management
Act (NEMA) section 30 (1) and / or National Water Act (NWA) section 20 (1). NEMA
Section 30 defines an Incident as ‘an unexpected sudden occurrence. Including a
major emission, fire or explosion leading to serious danger to the public or potentially
serious pollution of or detriment to the environment, whether immediate or delayed’.
The responsible ECO together with license holder HSE manager will determine whether
the incident is reportable in terms of NEMA or NWA. Chemical spills not more than 50
litres that do not occur in environmental sensitive areas will be recoded on site
spill/incident register.
MSDS Material and Safety Data Sheet
NCR Non-Compliance Report
NON-
COMPLIANCE
Non-compliance is defined as any deviation from the approved Environmental
Authorisation (EA), Environmental Management Programme (EMPr), Licenses, Permits or
Method Statements. This also include deviations from regulations that could directly or
indirectly lead to damage to the environment. For the purpose of this report, a non-
compliance is an issue or event identified on site which is recorded in a checklist that is
used to determine the percentage compliance in a monitoring report.
NON-
CONFORMANCE
A non-conformance is a report issued to the EPC by the ECO where incidents have not
received attention or where the same incidents have been recorded repetitively. NC’s
may also be issued immediately where deviation from EA, EMPr, Licenses, Permits and /
or Method Statements and all applicable legislations has or may have resulted in
negative impact to the environment, illness, injury, fatality or property damage. It is a
formal process that is recorded in a register and is used on site to address issues and
non-compliances.
NEMA National Environmental Management Act
NEM: AQA National Environmental Management: Air Quality Act
MSDS Material and Safety Data Sheet
OHSACT Occupational Health and Safety Act
PROJECT
COMPANY
Amstilinx (RF) Proprietary Limited
SAHRA South African Heritage Resources Agency
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page vi
DECLARATION
I, Lungani Zwane, in my capacity as ECO, hereby declare that I –
» Act as an independent consultant;
» Do not have any financial interest in the undertaking of the activity, other than remuneration for
the work performed;
» Have and will not have vested interest in the activity;
» Have no, and will not engage in, conflicting interests in the undertaking of the activity;
» Undertake to disclose any material information that has or may have the potential to influence the
decision of the competent authority or the objectivity of any report, plan or document;
» Will provide the competent authority with access to all information at my disposal regarding the
report, whether such information is favourable to the Client or not;
» Based on information provided to me by the Client and in addition to information obtained during
the course of this study, have presented the results and conclusion within the associated document
to the best of my professional ability;
» Reserve the right to modify aspects pertaining to the present investigation should additional
information become available through on-going research and/or further work in this field;
» Undertake to have my work peer reviewed on a regular basis by a competent specialist.
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 1
CHAPTER 1 : SUMMARY
Zero (0) incidents and Zero (0) non-conformances were opened during this reporting period. In total, there
are zero (0) incidents and zero (0) NCRs that have been opened to date. An overall compliance score of
100% was achieved for specifications from the EMPr currently active on site. Compliance with the
Powerline EA is 100%. Waste Management, Alien Plant Management and Search and Protection
Management Plans were scored at 100%; while Rehabilitation was not audited due to the electrical
subcontractor having not commenced with the activity on site.
CHAPTER 2 : INTRODUCTION
This is the 2nd monthly report submitted to the client for the Excelsior-Vryheid 132 kV Powerline located in
the Western Cape Province (with EA Ref: 14/12/16/3/3/1/1478).
» Power Line – Construction of a 132kV Overhead Transmission Line from the authorised Excelsior WEF
to the existing Vryheid Substation. The power line received Environmental Authorisation (EA Ref:
14/12/16/3/3/1/1478) on 1 March 2016, with one amendment (EA Ref: 14/12/16/3/3/1/1478/AM3,
Amendment to the road layout as contained within the approved final layout).
» A permit to pluck protected and unprotected flora was issued by the Western Cape CapeNature -
Permit number: CN37-28-4821.
A full-time on-site Environmental Control Officer (ECO), Lungani Zwane, was appointed by the Project
Company (through Savannah Environmental (Pty) Ltd) to monitor the implementation of mitigation
measures and compliance with conditions of the Environmental Authorisations (EA). Monitoring is
undertaken in accordance with the provisions of the EMPr as stipulated under Condition 21 of the
powerline EA. Details of the ECO were submitted to the Director: Compliance Monitoring of the
Department of Environmental Affairs before commencement of construction activities on 08 August 2018.
This report serves to outline the progress of authorised construction activities for the month of February 2019
and the level of compliance achieved by the Project Owner and the EPC contractor as recorded by the
on-site ECO.
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 2
CHAPTER 3 : OVERVIEW OF CONSTRUCTION PROGRESS TO DATE
List of Contractors and Subcontractors
» Goldwind 4 Renewable Energy (EPC Contractor)
» Optipower (Subcontractor)
The following activities have taken place during this reporting period (i.e. February 2019):
Vryheid Substation
» Surveying
» Access Permit
» Barricading
» Stone Removal / Plinth Removal
» Foundation Setting-Out
» Excavation
132kV Overhead Line
» Soil Nominations
The following new activity is expected to take place from March 2019:
Vryheid Substation
» Concrete Works / Curing of Concrete
» Backfilling
» Steel Works
» Trenching
» Preparation of Cable Trench Ramp
» Installation of Cable Curbs
» Plant Installation – Primary and Secondary
» Yard Stone Cleaning
» Stone Replacement and Levelling
132kV Overhead Line
» Excavations
» Rebar
» Concrete Pad
» Concrete Plinth
» Backfilling
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 3
Photograph 1: Excavation of bases at the Vryheid Substation
Photograph 2: Spoil material at the Vryheid Substation
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 4
Photograph 3: Mobile toilet at the Vryheid Substation
Photograph 4: General waste skip at the contractor site camp
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 5
CHAPTER 4 : MONITORING AND REVIEWING
Daily compliance monitoring is undertaken by the on-site ECO, Lungani Zwane. Incidents noted during
these daily site inspections are reported to the contractor by means of a Construction Incident and Project
Issues register which contains further details regarding incidents recorded within this reporting period (refer
to Appendix A) and daily diary to the Client.
Description of observations, incidents and non-conformities identified during this monitoring and
reporting period
This section provides a description of all observations that have been opened during this reporting month.
The incident register is attached to this monthly report (refer to Appendix D). No incidents and zero (0) non-
conformances were opened during this reporting period. In total, zero (0) incidents and zero (0) non-
conformances opened to date.
Description of measures implemented to reduce impact on the environment
During this reporting period, the following measures have been implemented to reduce the potential for
on-going impacts on the environment:
» Toolbox talks were conducted by the ECO, EPC contractor and the subcontractor on matters
pertaining to the environment to 15 personnel; this figure includes visitors on site. The following topics
were discussed during the February 2019 reporting period:
∗ Barricading
∗ Traffic Management
∗ Emergency Procedure
∗ Blue crane
∗ Environmental Management
» The EPC contractor provided environmental induction and awareness training to on-site staff.
Attendance records are kept by the EPC contractor.
The daily monitoring events are focused on best environmental practices, rather than regulatory
compliance. During construction, findings of the daily site inspections will also be reported in weekly
meetings between the ECO and the EPC contractor HSE officer. These meetings will involve discussions of
open incidents and measures to be taken by the contractor to ensure compliance to the conditions of the
EA, EMPr and all relevant environmental legislation.
Through daily site inspections by the ECO on the Excelsior-Vryheid Powerline, these are measures which are
recommended to be implemented to minimise potential impact on the environment:
» The EPC must implement more preventative measures; such as making spill kits available, construct
bunded areas and the use of drip trays on hydrocarbon spillages onsite.
» The development footprint should be clearly defined and all areas outside the site boundary should be
clearly marked.
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 6
Internal audits are to be conducted by the EPC contractor and the subcontractor. Audits shall be based
on the requirements of the EMPrs and EAs associated with the project. This will assist the contractor in
being proactive to potential concerns.
CHAPTER 5 : PUBLIC INVOLVEMENT
Two (2) grievances were received by the project to date. The EPC contractor has placed the contact
details of the onsite HSE officer and the CLO at the site office and the security gate, where grievances can
be lodged. Attached to this monitoring report is the complaints register (Appendix C)
The two grievances were due to the pre-employment requirements of the WEF; specifically the issues of
criminal checks and the five year residency requirement. The grievances came from some community
leaders who were not informed of the pre-employment requirement of the Excelsior-Vryheid Powerline and
did not attend the previous engagements held in 2018 with the community. The matter was resolved after
this discussion.
CHAPTER 6 : DUST MONITORING
No close by residences or communities has been affected by the dust to date and the contractor is also
somewhat limited to the extent that dust can be controlled due to the fine texture of the soils
CHAPTER 7 : PROTECTED VEGETATION
One permit was issued for the relocation and removal of protected vegetation within the development
footprint of the project. No search and rescue activities were conducted in this reporting period, the ECO
recorded no protected plant species. The EPC Contractor is obliged to conduct search and rescue of
these protected plants within the footprint of the development as per the CapeNature flora permit
requirements - Permit number: CN37-28-4821; in all of the affected construction area’s along with the ECO.
The EPC contractor is currently in the process of appointing an ecological specialist to assist in identifying
any protected species in the construction area prior to commencing with construction activities.
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 7
CHAPTER 8 : PROTECTION OF AVIFAUNA
The Project Company enlisted the assistance of Chris van Rooyen Consulting to conduct an assessment of
the Excelsior Wind Energy Facility and the Excelsior-Vryheid Powerline in 2012. The need for this assessment
was identified through a due diligence review of the Avifaunal Impact Assessment Study (2011) and pre-
construction monitoring report (2012) compiled by Chris van Rooyen Consulting.
The assessment found that a robust, appropriately designed, and long-term biodiversity monitoring and
evaluation program is to be integrated into the client’s management program. Monitoring will be
conducted both during the construction phase; through the use of 5 environmental monitors to be trained
as carcass searchers and to perform various other environmental monitoring duties.
A number of priority species nests, (including Blue Cranes) and roosts will be monitored during the
construction phase in order to assess the potential impact of the construction activities on the breeding
birds, and to devise mitigation measures (if need be) to minimise the risk of displacement due to
disturbance.
A process of engagement with Eskom be initiated, which should include a survey of all the existing
powerlines and a demarcation of high-risk sections, with a view to getting all dangerous powerlines
marked with Eskom approved bird flight diverters BFD’s to reduce the risk to Blue Cranes.
CHAPTER 9 HERITAGE
Section 10.5.1 of the EIA report states that there were 28 archaeological materials documented on site;
mostly dating to the Later Stone Age period. The archaeological finds are spread very thinly, randomly
and unevenly over the surrounding landscape. There is no spatial patterning in the distribution of the finds.
As recommended by the specialist these areas are avoided by the development. There were no
archaeological structures identified during site inspections by the ECO on the site. No heritage findings or
incidents were recorded during this reporting period.
CHAPTER 10 : EROSION
In this reporting period no erosion issues occurred. All mitigation measures as detailed in the relevant
management plans should be implemented by the responsible EPC contractor.
CHAPTER 11 : REHABILITATION
Rehabilitation must commence in areas where construction work has been completed. Construction work
has not commenced on any of the sites and no rehabilitation has been done.
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 8
CHAPTER 12 : WASTE MANAGEMENT
Table 1 shows summary of waste removed from Excelsior WEF and Excelsior-Vryheid Powerline project to
date. For the purposes of reporting, the total waste figures of all the EPC contractor and subcontractors
involved in the Excelsior WEF and Excelsior – Vryheid 132kV Powerline are combined and divided into the
following categories:
Solid waste
Solid waste is contained in waste bins provided at the respective work areas on site, and disposed of in the
waste skips at the end of the day. Ten (10) m3 of solid waste has been disposed of by the WEF and the
Excelsior-Vryheid Powerline in this reporting period, the EPC contractor is yet to provide a SDC for the
disposal.
Liquid waste
Liquid waste is currently only limited to sewage effluent. Chemical ablution facilities are available at the
offices and respective work areas. This liquid waste stream is collected and disposed of at the Witzenberg
Municipality waste treatment plant via a service provider. 550L has been disposed of by the WEF and the
Excelsior-Vryheid Powerline for the month of February 2019, the SDCs from the previously disposed waste
were provided to the ECO. The only outstanding SDCs are from the month of February 2019.
Hazardous waste
No hazardous waste originated from the current operations at the site as yet.
Recycled waste
A waste contractor was appointed to collect waste that is suitable for recycling. The collective quantities
of all the recycled waste streams (wood, plastic, paper etc.) are included in this report. No recycling
occurred for this reporting period.
Table 1: Summary of waste removed from Excelsior WEF and the Excelsior-Vryheid Powerline (February
2019).
Month Solid Waste
(m3) Liquid Waste (L)
Hazardous Waste Recycled
Waste
(kg)
Medical
waste
(kg)
Concrete
Waste
(m3) Solid (m3) Liquid (L)
Nov-18 0 450 0 - 0 0 0
Dec-18 - 300 - - - - -
Jan-19 - 350 - - - - -
Feb-19 10m3 550 - - - - -
Total 10m3 1650 0 0 0 0 0
YTD 10m3 1650 0 0 0 0 0
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 9
CHAPTER 13 : ENVIRONMENTAL PERFORMANCE
Environmental Management Programme - Results
A checklist was derived from the specifications of the Excelsior-Vryheid 132 kV Powerline EMPr currently
active for the project (refer to Appendix B). Some of the elements were not audited as a result of the
electrical subcontractor that have not commenced with activities. A rating for individual relevant
elements of the checklist derived from the specifications of the approved EMPr has been scored on the
following basis:
» A rating of 3: best practice/full conformance,
» A rating of 2, satisfactory (>50% conformance),
» A rating of 1: unsatisfactory (<50% conformance),
» A rating of 0: nothing in place and a rating of N/A: not at this time.
The following percentage compliance scores have been calculated at the end of this reporting period.
These percentage scores have been calculated without weighing any issues (i.e. all environmental
specifications have the same weighing). The Project Company has set its percentage compliance target
as 90% which is represented by the black line in the graphs below. The target will be reviewed as the
project progresses.
Table 2: Percentage compliance scores with the EMPr for February 2019
Summary of Results
Compliance with: As %
PRE-CONSTRUCTION & DESIGN PHASE 98
SITE ESTABLISHMENT 100
SITE & WORKER MANAGEMENT 100
SOCIAL ENGAGEMENT 0
MINIMISATION OF FOOTPRINT 100
SOIL DEGRADATION & EROSION 80
MINIMISE IMPACTS ON FAUNA 100
STORMWATER MANAGEMENT 0
HERITAGE RESOURCES 100
VISUAL IMPACT ASSOCIATED WITH CONSTRUCTION 100
APPROPRIATE HANDLING AND MANAGEMENT OF WASTE 100
HANDLING & STORAGE OF CHEMICALS & HAZARDOUS SUBSTANCES 100
TOTAL SCORE 88
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 10
Figure 1: Percentage compliance scores with the EMPr for February 2019
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 11
An overall compliance score of 88% was achieved for this reporting period.
Specifications that require feedback from the EPC contractor should be attended to and have been
highlighted in red in the checklist (refer to Appendix B). Continuous monitoring is however required and it is
recommended that the contractor do a full internal audit on all the relevant specifications of the EMPr
and EA. Soil degradation and Erosion scored due to not having a stormwater management plan in place.
Environmental Authorisation - Results
A checklist was derived from the conditions of the EA currently active for the project (please refer to
Appendix A). The following percentage compliance scores have been calculated at the end of this
reporting period.
Table 3: Percentage compliance scores with the EAs for February 2019
Summary of Results
Compliance with EA: As %
Powerline 100
AVERAGE 100
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 12
Figure 2: Percentage compliance scores with the EA for February 2019
Environmental Monitoring Report. No.2 for the Excelsior-Vryheid 132 kV Powerline February 2019
Page 13
Management Plan – Results
A checklist was derived from the specifications of the topsoil management plan (please refer to Appendix
D). An overall compliance score of 99% was achieved for specifications from the topsoil management
plan. The holder of the EA and the EPC contractor need to improve on its compliance to the Waste
Management Plan, as it is a crucial aspect in Environmental Compliance.
Table 4: Percentage compliance score with the Management Plans for February 2019
Summary of Results
Compliance with As% Comments
Erosion Management 96
Waste Management 100
Soil Management 100
Alien Plant Management 100
Emergency Response 100
Average 99
Environmental Monitoring Report. No.2 February 2019
Page 14
Figure 3: Percentage compliance scores with the Management Plans for Project to date
Environmental Monitoring Report. No.2 February 2019
Page 15
CHAPTER 14 : OTHER NOTABLE EVENTS
Stormwater system investigation
The EMPr states the following regarding stormwater: All stormwater mitigation measures must be
implemented according to the Stormwater Management Plan (refer to Appendix E).
It is recommended that the completion of the final plan of the powerline be expedited to ensure
compliance with this specification.
CHAPTER 15 : CONCLUSION AND RECOMMENDATIONS
Most of the construction work is still related to earthwork activities.
The holder of the Environmental Authorisation was committed to compliance with the Environmental
Authorisations and Environmental Management Programmes during this reporting month. There was
always a good level of communication between the ECO, EPC contractor, and the Owner. This was
considered to be advantageous to the progress of the project. The EPC contractors made use of the
advice and recommendations they received from the ECO, which helped to avoid the opening of new
non-conformances.
The recommendations from this report are summarised below:
» Safe disposal waste certificates and training records must be submitted to the ECO on or before the
25th of every reporting month.
» It is recommended that the stormwater plan be investigated to ensure compliance with this
specification.
» Internal audits should be undertaken by the EPC contractor and the subcontractor to establish areas
where compliance should be improved. Audits should be based on the requirements of the EMPrs and
EAs relevant to the project.
» Additional toolbox talks should be given on the management of Hazardous Chemical Substances and
spillage management.
This report was prepared by:
Name : Lungani Zwane
Signature :
Designation : Environmental Control Officer – Excelsior Wind Energy Facility
Contact no. : 081 044 1177
Email : [email protected]
Compliant P
Not Compliant O
Insufficient Evidence
N/A = Not Applicable
Yes No
1
The preferred route Alternative 1, for the proposed construction of a 132kV power line
form the authorised Excelsior Wind Energy Facility to the Vryheid Substation within the
Swellendam Local Municipality of Overberg District in the Western Cape Province, with the
above coordinates is approved.
N/A N/A P 3
2
The construction will take place within the preferred Alternative 1 (300m wide corridor) (of
the three assessed alternatives) for the proposed power line and associated infrastructure
as is deemed most suitable by all specialists.
N/A N/A P 3
3
Authorisation of the activity is subject to the conditions contained in this environmental
authorisation, which form part of the environmental authorisation and are binding on the
holder of the authorisation.
N/A N/A P 3
4
The holder of the authorisation is responsible for ensuring compliance with the conditions
contained in the this authorisation. The includes any person acting on the holder's behalf,
including but not limited to , an agent, servant, contractor, sub-contractor, employee,
consultant or person rendering a service to the holder of the authorisation.
P 3
5 The activities authorised may only be carried out at the property as described above. N/A N/A P 3
6
Any changes to, or deviations from, the project description set out in this environmental
authorisation must be approved, in writing, by the Department before such changes or
deviations may be effected. In assessing whether to grant such approval or not, the
Department may request such information as it deems necessary to evaluate the
significance and impacts of such changes or deviations and it may be necessary for the
holder of the authorisation to apply for further environmental authorisation in terms of the
regulations.
N/A N/A P 3
7
The holder of an environmental authorisation must apply for an amendment of the
environmental authorisation with the competent authority for any alienation, transfer or
change of ownership rights in the property on which the activity is to take place
N/A N/A P 3
8
This activity must commence within a period (5) years fro the date of issue of this
environmental authorisation. If commencement of the activity does not occur within that
period, the authorisation lapses and a new application for environmental authorisation
must be made in order for the activity to be undertaken.
P 3
9Commencement with one activity listed in terms of this environmental authorisation
constitutes commencement of all authorised activities.P 3
10
The holder of the authorisation must notify every registered interested and affected party,
in writing and within 14 (fourteen) calendar days of the date of this environmental
authorisation, of the decision to authorise the activity.
N/A NEMA EIA Regulations P 3
11
The notification referred to must:
11.1 - Specify the date on which the authorisation was issued;
11.2 - Inform the interested and affected party of the appeal procedure provided for in
the National Appeals Regulations, 2014;
11.3 - Advise the interested and affected party that a copy of the authorisation will be
furnished on request; and
11.4 - Give the reasons of the competent authority for the decision.
N/A NEMA EIA Regulations P 3
Action/Info Score
ENVIRONMENTAL AUTHORISATION CHECKLIST FOR THE POWERLINE ASSOCIATED WITH EXCELSIOR WIND ENERGY FACILITY: WESTERN CAPE
Project: Excelsior Wind Energy Project
Holder of EA: Amstilinx (RF) Proprietary Limited
# EA Condition Permit Type Legislation Ref
Amendment 1:
Amendment 2:
Amendment 3:
Compliance
EA POWER LINE REF NR: 14/12/16/3/3/1/1478
SCOPE OF AUTHORISATION
Authorisation Register Number: 14/12/16/3/3/1/1478
Date Issued: 01/03/2016
Last update to this document: 23/01/2019 by Lungani Zwane (ECO Savannah Environmental)
NOTIFICATION OF AUTHORISATION & RIGHT TO APPEAL
Appendix A - EA checklist
2019/02/28 1
Yes NoAction/Info Score# EA Condition Permit Type Legislation Ref
Compliance
12
The holder of the Authorisation must publish a notice:
12.1 - Informing I&APs of the decision
12.2 - Informing I&APs where the decision can be accessed: and
12.3 - Drawing the attention of the I&APs to the fact that an appeal may be lodged
against this
N/A NEMA EIA Regulations P 3
12
The holder of the Authorisation must publish a notice:
12.1 - Informing I&APs of the decision
12.2 - Informing I&APs where the decision can be accessed: and
12.3 - Drawing the attention of the I&APs to the fact that an appeal may be lodged
against this decision in terms of the National Appeal Regulations, 2014.
N/A NEMA EIA Regulations P 3
15
The Environmental Management Programme (EMPr) dated December 2015, submitted as
part of the Application for EA is hereby approved. This EMPr must be implemented and
adhered to.
DEA approval N/A P 3
21
The holder of the authorisation must appoint a suitably experienced independent
Environmental Control Officer (ECO) for the construction phase of the development that
will have the responsibility to ensure that the mitigation/rehabilitation measures and
recommendations referred to in this authorisation are implemented and to ensure
compliance with the provisions of the EMPr.
21.1 - The ECO shall be appointed before commencement of any authorised activities. P 3
21.2 - Once appointed, the name and contact details of the ECO must be submitted to
the Director: Compliance Monitoring of the Department.P 3
21.3 - The ECO shall keep record of all activities on site, problems identified, and
transgressions noted and a task schedule of tasks undertaken by the ECO. P 3
21.4 - The ECO shall remain employed until all rehabilitation measures, as Required for
implementation due to construction damage, are completed and the site is ready for
operation.
P 3
22
All documentation e.g. audit/monitoring/compliance reports and notifications, required
to be submitted to the Department in terms of this authorisation, must be submitted to the
Director: Compliance Monitoring at the Department.
P 3
23
The holder of the authorisation must, for the period during which the authorisation and
EMPr remain valid, ensure that project compliance with the conditions of the
environmental authorisation and the EMPr are audited, and that the audit reports are
submitted to the Director: Compliance Monitoring of the Department.
P 3
24
The frequency of auditing and of submission of the environmental audit reports must be as
per the frequency indicating in the EMPr, taking into account the processes for such
auditing as prescribed in Regulation 34 of GN R.982.
P 3
25
The holder of the authorisation must, in addition, submit an environmental audit report to
the Department within 30 days of completion of the construction phase (i.e. within 30 days
of site handover) and a final environmental audit report within 30 days of completion of
rehabilitation activities.
P 3
26
The environmental audit reports must be compiled in accordance with appendix 7 of the
EIA Regulations, 2014 and must indicate the date of the audit, the name of the auditor
and the outcome of the audit in terms of compliance with the environmental
authorisation conditions as well as the requirements of the approved EMPr.
P 3
27Records relating to monitoring and auditing must be kept on site and made available for
inspection to any relevant and competent authority in respect of this development.P 3
13The authorised activity shall not commence within twenty (20) days of the date of
signature of the authorisation.P 3
MONITORING
RECORDING AND REPORTING TO THE DEPARTMENT
MANAGEMENT OF ACTIVITY
COMMENCEMENT OF ACTIVITY
Appendix A - EA checklist
2019/02/28 2
Yes NoAction/Info Score# EA Condition Permit Type Legislation Ref
Compliance
14
In terms of section 43(7), an appeal under section 43 of the National Environmental
Management Act, 1998 will suspend the environmental authorisation or any provision or
condition attached thereto. In the instance where an appeal is lodged you may not
commence with the activity/ies until such time that the appeal is finalised.
P 3
28
A written notification of commencement must be given to the Department no later than
fourteen (14) days prior to the commencement of the activity. Commencement for the
purposes of this condition includes site preparation. The notice must include a date on
which it is anticipated that the activity will not commence, as well as a reference number.
P 3
29A written notification of operation must be given t the Department no later than fourteen
(14) days prior to the commencement of the activity operational phase.P 3
30
Should the activity ever cease or become redundant, the holder of the authorisation must
undertake the required actions as prescribed by the legislation at the time and comply
with all relevant legal requirements administered by any relevant and competent
authority at that time.
N/A
31
A pre-construction check of the final pylon positions must be conducted by the
ecological and the avifaunal specialists to ascertain if any Red Data species nests are
present and the no pylons will be located within drainage lines and within the intact
vegetation adjacent to the drainage lines that will result habitat loss. The findings of the
walkthrough must inform the EMPr amendment and be submitted to the Department for
approval.
P 3
32Access and maintenance roads must avoid intact fragments and no permanent roads
must be established within intact fragments. P 3
33 The construction camp area must be demarcated outside of sensitive areas. P 3
34
Indigenous vegetation clearing beneath the power line servitude must not be done prior
to a relevant permit being granted by the Department of Agriculture Forestry and
Fisheries.
The Project has a CapeNature flora removal permit P 3
35
The power line must be marked with Bird Flight Diverters (BFDs) for 4km from Excelsior Wind
Energy Facility up to where the line joins up with the R319, on the earth wire of the line, 5
metres apart, alternating black and white to eliminate potential collision risk to Blue
Cranes and Denham's Bustards.
Construction of the powerline has not yet
commenced, monitoring of this condition will
commence with construction of it.
N/A
36 Bird perching brackets must be fitted to the top of the pole to eliminate electrocution.
Construction of the powerline has not yet
commenced, monitoring of this condition will
commence with construction of it.
N/A
37
The visual impact of the new power line must be reduced by aligning vertical structures
adjacent to existing power line structures and keeping alignment of power line as close to
the existing line as possible.
Construction of the powerline has not yet
commenced, monitoring of this condition will
commence with construction of it.
N/A
38All necessary roads must have runoff control features which redirect water flow to prevent
the risk of erosion.
Construction of the powerline has not yet
commenced, monitoring of this condition will
commence with construction of it.
N/A
39
If any human remains (or any other concentrations of heritage material) are exposed
during construction, all work to cease and it must be reported immediately to SAHRA, so
that a systematic and professional investigation can be undertaken. Sufficient time should
be allowed to investigate and to remove/collect such material. Recommendations will
follow from the investigation.
Construction of the powerline has not yet
commenced, monitoring of this condition will
commence with construction of it.
N/A
40All excavations must be clearly demarcated and site activities must be kept minimal in
order to restrict the impact on flora and fauna.
Construction of the powerline has not yet
commenced, monitoring of this condition will
commence with construction of it.
P 3
41Areas that have been stripped off must be dampened periodically to avoid excessive
dust.
Construction of the powerline has not yet
commenced, monitoring of this condition will
commence with construction of it.
P 3
42Regular erosion and alien monitoring must be done annually for at least two years
construction to ensure that no problems have developed as a result of the disturbance.
Construction of the powerline has not yet
commenced, monitoring of this condition will
commence with construction of it.
N/A
SITE CLOSURE AND DECOMMISSIONING
NOTIFICATION TO AUTHORITIES
OPERATION OF THE ACTIVITY
SPECIFIC CONDITIONS
Appendix A - EA checklist
2019/02/28 3
Yes NoAction/Info Score# EA Condition Permit Type Legislation Ref
Compliance
43
An integrated waste management approach must be implemented that is based on
waste minimisation and must incorporate reduction, recycling, re-use and disposal where
appropriate. Any solid waste must be disposed of at a landfill licensed in terms of section
20(b) of the National Environment Management Waste Act, 2008 (Act No. 59 of 2008).
The Project has a waste management plan in place
and it is being implementedP 3
44
A copy of this authorisation, the audit and compliance monitoring reports, and the
approval EMPr, must be must be made available for inspection and copying -
44.1 - At the site of the authorised activity;
44.2 - To anyone on request; and
44.3 - Where the holder of the environmental authorisation has a website, on such publicly
accessible website.
P 3
45
National government, provincial government, local authorities or committees appointed
in terms of the conditions of this authorisation or any other public authority shall not be
held responsible for any damages or losses suffered by the applicant or his suffered by the
holder of the authorisation or his/her successor in the title in any instance where
construction or operation subsequent to construction be temporarily or permanently
stopped for reasons of non-compliance by the holder of the authorisation with the
conditions of this authorisation as set out in this document or any other subsequent
document emanating from these conditions of authorisation.
P 3
46
National government, provincial government, local authorities or committees appointed
in terms of the conditions of this authorisation or any other public authority shall not be
held responsible for any damages or losses suffered by the applicant or his successor in
title in any instance where construction or operation subsequent to construction be
temporarily or permanently stopped for reasons of non-compliance by the applicant with
the conditions of the authorisation as set out in this document or any other subsequent
document emanating from these conditions of authorisation.
P 3
38
TOTAL SCORE 114
AS AVERAGE 3,0
AS PERCENTAGE 100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Each element of the checklist is scored on the following basis:
GENERAL
Appendix A - EA checklist
2019/02/28 4
OBJECTIVES
ITEMSOPERATION PHASE As % Comments
1ENSURE THE FACILITY DESIGN RESPONDS TO IDENTIFIED ENVIRONMENTAL
CONSTRAINTS AND OPPORTUNITIES98
Total 98
C1 SITE ESTABLISHMENT 100
C2 SITE & WORKER MANAGEMENT 100
C3 SOCIAL ENGAGEMENT 0
C6 MINIMISATION OF FOOTPRINT 100
C8 SOIL DEGRADATION & EROSION 80
C10 MINIMISE IMPACTS ON FAUNA 100
C13 HERITAGE RESOURCES 100
C14 VISUAL IMPACT ASSOCIATED WITH CONSTRUCTION 100
C14 APPROPRIATE HANDLING AND MANAGEMENT OF WASTE 100
C16 HANDLING & STORAGE OF CHEMICALS & HAZARDOUS SUBSTANCES 100
Total 88
R1 OBJECTIVE 1 : REHABILITATION OF DISTURBED AREAS Rehabilitation has not commenced
O2 MINIMISE LOSS OF VEGETATION Powerline is not operational
O3 ALIEN INVASIVE CONTROL Powerline is not operational
O4 VISUAL IMPACT Powerline is not operational
O5 MINIMISE SOIL DEGRADATION Powerline is not operational
O6 MANAGEMENT OF DUST AND AIR EMISSION Powerline is not operational
O7 FIRE MANAGEMENT PLAN Powerline is not operational
O8 LOCAL BUSINESS & EMPLOYMENT Powerline is not operational
O8 MANAGEMENT OF HAZORDOUS WASTE Powerline is not operational
TOTAL 89
Summary of Results
PRE-CONSTRUCTION & DESIGN PHASE
CONSTRUCTION
REHABILITATION
OPERATION
Savannah Environmental 1 2019/03/12
Yes No
EMPr, pg. 34 PowerlinePlan and conduct pre-construction activities in an
environmentally acceptable mannerP 3 Pre-construction
Developer/Own
er
EPC Contractor
EMPr, pg. 34 PowerlineDevelop a comprehensive construction rehabilitation
plan for the site.P 3 Pre-construction
Developer/Own
er
EMPr, pg. 34 Powerline
The terms of this EMPr and the Environmental
Authorisation must be included in all tender
documentation and Contractors contracts.
P 3 Tender process
Developer/Own
er
EPC Contractor
EMPr, pg. 34 Powerline
Implement a stormwater management plan for
hard/compacted surfaces (e.g. substation footprints) as
part of the final design of the project.
O 0The site design is currently not complete, the stormwater
plan will only be developed once this is completed.
Design phase/
Pre-constructionProponent
EMPr, pg. 34 Powerline
Obtain any additional environmental permits required
(biodiversity permits, etc.) based on final positioning of
infrastructure.
P 3 Proponent Planning
EMPr, pg. 34 Powerline
Undertake negotiations with affected landowners and
agree on landowner-specific conditions for construction
and maintenance
P 3 Planning Proponent
EMPr, pg. 34 PowerlineBird-friendly (Eskom approved or similar) power line tower
and conductor designs must be used.P 3 Design EPC Contractor
EMPr, pg. 34 Powerline
Plan to install best available (at the time of construction)
Eskom approved or similar, anti-bird collision line marking
devices on the earth wire of the power line. This should
preferably be a dynamic device, i.e. one that moves, as
it is believed that these are more effective in reducing
collisions. It is recommended that a durable device be
used.
P 3 Design EPC Contractor
EMPr, pg. 34 Powerline
Any new access roads are required to be carefully
planned and constructed to minimise the impacted area
and prevent unnecessary excavation, placement, and
compaction of soil. Construction vehicles also need to
consider the load carrying capacity of road surfaces and
adhere to all other prescriptive regulations regarding the
use of public roads by construction vehicles.
P 3Planning/
Design Phase
Engineer/
Contractor
EMPr, pg. 34 Powerline
Tender documentation should contain guidelines for the
involvement of labour, entrepreneurs, businesses, and
Small, Medium and Micro Enterprises (SMMEs) from the
local sector.
P 3Planning/
Preconstruction
Project
Company/
Contractor and
subcontractors
EMPr, pg. 35 Powerline Confine activities to the demarcated construction site. N/AThe EPC contractor's electrical contractor has not
established on site.
Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 35 Powerline
Compile a Project Specific Grievance Mechanism
Procedure for the public to be implemented during both
the construction and operational phases of the facility.
This procedure should include details of the contact
person who will be receiving issues raised by interested
and affected parties, and the process that will be
followed to address issues.
P 3
Pre-construction
(construction
procedure)
Pre-operation
(operation
procedure)
Proponent
EMPr, pg. 35 Powerline
Develop and implement a grievance mechanism for the
construction, operational and closure phases of the
project for all employees, contractors, subcontractors
and site personnel. This procedure should be in line with
the South African Labour Law.
P 3
Pre-construction
(construction
procedure)
Pre-operation
(operation
procedure)
Proponent
EMPr, pg. 36 Powerline
Ensure that the contents of this document are
communicated to the Contractor site staff and that the
Site Manager and Contractor are constantly made
aware of the contents through discussion.
P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 36 Powerline
Ensure that the compliance of the EMPr, EA and the
legislation is monitored through regular and
comprehensive inspection of the site and surrounding
areas.
P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
OBJECTIVE 1: PRE-CONSTRUCTION & DESIGN PHASE REQUIREMENTS
Applicable EMPrLocation TimeframeEnvironmental SpecificationCompliance
Score
PERIOD: February 2019
If no, corrective action taken/required
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 4: To ensure effective communication mechanism
CommentPhoto record ref
No/Doc No
SITE: Excelsior Wind Energy Facility
Responsibility
Savannah Environmental 2 2019/03/12
Yes No
OBJECTIVE 1: PRE-CONSTRUCTION & DESIGN PHASE REQUIREMENTS
Applicable EMPrLocation TimeframeEnvironmental SpecificationCompliance
Score If no, corrective action taken/requiredCommentPhoto record ref
No/Doc NoResponsibility
EMPr, pg. 36 Powerline
Monitoring and verification must be implemented to
ensure that environmental impacts are kept to a
minimum, as far as possible.
P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 36 Powerline
Ensure that the Site Manager has input into the review
and acceptance of construction methods and method
statements.
P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 Powerline
Ensure all specifications and legal constraints specifically
with regards to the environment are highlighted to the
Contractor(s) so that they are aware of these.
P 3Duration of
Contract
Construction
Manager, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 PowerlineEnsure that Amstilinx (RF) and its Contractor(s) are made
aware of all stipulations within the EMPr.P 3
Duration of
Contract
Construction
Manager, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 Powerline
Ensure that the EMPr is correctly implemented throughout
the project by means of site inspections and meetings.
This will be documented as part of the site meeting
minutes through input from the independent ECO.
P 3Duration of
Contract
Construction
Manager, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 Powerline
Be fully conversant with the EIA for the project, the EMPr,
the conditions of the Environmental Authorisation, and all
relevant environmental legislation.
P 3Duration of
Contract
Construction
Manager, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 PowerlineBe fully knowledgeable with the contents of the EIA and
risk management.P 3
Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 PowerlineBe fully knowledgeable with the contents and conditions
of the Environmental Authorisation. P 3
Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 Powerline Be fully knowledgeable with the contents of the EMPr. P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 Powerline
Be fully knowledgeable with the contents of all relevant
environmental legislation, and ensure compliance with
these.
P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 Powerline Conduct audits to ensure compliance to the EMPr. P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 Powerline
Ensure there is communication with the Technical
Director, the ECO, the Internal Environmental Officer and
relevant discipline engineers on matters concerning the
environment.
P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 38 Powerline
Ensure that no actions are taken which will harm or may
indirectly cause harm to the environment, and take steps
to prevent pollution on the site.
P 3Duration of
Contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 39 Powerline
Submit independent reports to the DEA and other
regulating authorities regarding compliance with the
requirements of the EMPr, EA and other environmental
permits.
P 3Duration of
ContractECO
EMPr, pg. 40 Powerline
Must be fully knowledgeable on all environmental
features of the construction site and the surrounding
environment.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 Powerline
Ensure a copy of the Environmental Authorisation and
EMPr must be easily accessible to all on-site staff
members.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 Powerline
Ensure contractor employees are familiar with the
requirements of this EMPr and the environmental
specifications as they apply to the construction of the
proposed facility.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 Powerline
Ensure that prior to commencing any site works, all
contractor employees and subcontractors must have
attended an environmental awareness included in the
induction training which must provide staff with an
appreciation of the project's environmental
requirements, and how they are to be implemented.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
Savannah Environmental 3 2019/03/12
Yes No
OBJECTIVE 1: PRE-CONSTRUCTION & DESIGN PHASE REQUIREMENTS
Applicable EMPrLocation TimeframeEnvironmental SpecificationCompliance
Score If no, corrective action taken/requiredCommentPhoto record ref
No/Doc NoResponsibility
EMPr, pg. 40 Powerline
Ensure that any complaints received from the public are
duly recorded and forwarded to the Site Manager and
Contractor.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 Powerline
Manage the day-to-day on-site implementation of this
EMPr, and for the compilation of regular (usually weekly)
Monitoring Reports.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 Powerline
Keep record of all activities on site, problems identified,
transgressions noted and a task schedule of tasks
undertaken, including those of the Independent ECO.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 PowerlineStaff will be informed of environmental issues as deemed
necessary by the Independent ECO.P 3
Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 PowerlineEnsuring adherence to the environmental management
specifications.P 3
Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 Powerline
Ensuring that Method Statements are submitted to the
Site Manager (and ECO) for approval before any work is
undertaken.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 PowerlineEnsuring that any instructions issued by the Site Manager
on the advice of the ECO are adhered to.P 3
Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 Powerline
Ensuring that a report is tabled at each site meeting,
which will document all incidents that have occurred
during the period before the site meeting.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 PowerlineEnsuring that a register is kept in the site office, which lists
all transgressions issued by the ECO.P 3
Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 PowerlineEnsuring that a register of all public complaints is
maintained.P 3
Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 41 Powerline
Ensuring that all employees, including those of sub-
contractors receive training before the commencement
of construction in order that they can constructively
contribute towards the successful implementation of the
EMPr (i.e. ensure their staff are appropriately trained as to
the environmental obligations).
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
43
TOTAL SCORE 126
AS AVERAGE 2,9
AS PERCENTAGE 97,7
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Each element of the checklist is scored on the following basis:
Savannah Environmental 4 2019/03/12
Yes No
EMPr, pg. 42 PowerlineSecure site, working areas and excavations in an
appropriate manner.P 3
Site
establishment,
and duration of
construction
EPC Contractor
EMPr, pg. 42 Powerline Fence and secure contractor’s equipment camp. P 3Site
establishmentEPC Contractor
EMPr, pg. 42 Powerline
Where the public could be exposed to danger by any of
the works or site activities, the contractor must, as
appropriate, provide suitable flagmen, barriers and/or
warning signs in English, Afrikaans and any other relevant
local language/s, all to the approval of the Site Manager.
P 3
Site
establishment
and duration of
contract
ECO, EPC
Contractor and
sub-contractor/s
EMPr, pg. 42 Powerline
All unattended open excavations must be adequately
demarcated and/or fenced. Adequate protective
measures must be implemented to prevent unauthorised
access to the working area and the internal access/haul
routes.
P 3
Site
establishment
and duration of
contract
EPC Contractor
EMPr, pg. 42 Powerline
Establish SABS 089: 1999 Part 1 approved bunded areas
for storage of hazardous materials and hazardous waste
(i.e. fuel/chemicals to be required during construction).
P 3Site
establishmentEPC Contractor
EMPr, pg. 42 Powerline
Establish the necessary ablution facilities with chemical
toilets and provide adequate sanitation facilities and
ablutions for construction workers (1 toilet per every 15
workers) at appropriate locations on site.
P 3
Site
establishment
and duration of
construction
EPC Contractor
EMPr, pg. 42 PowerlineAblution or sanitation facilities should not be located
within 50 m of water courses and wetlands.P 3
Site
establishment
and duration of
construction
EPC Contractor
EMPr, pg. 43 Powerline
Supply adequate weather and vermin proof waste
collection bins and skips (covered at minimum with
secured netting or shade cloth) at site where construction
is being undertaken. Separate bins should be provided for
general and hazardous waste. As far as possible, provision
should be made for separation of waste for recycling.
P 3
Site
establishment
and duration of
construction
EPC Contractor
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
Location
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
SITE: Excelsior Wind Energy Facility
PERIOD: February 2019
OBJECTIVE 1: Minimise impacts related to inappropriate site establishment
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc NoApplicable EMPr Score
ComplianceCommentEnvironmental Specification
Savannah Environmental 5 2019/03/12
Yes NoLocation
OBJECTIVE 1: Minimise impacts related to inappropriate site establishment
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc NoApplicable EMPr Score
ComplianceCommentEnvironmental Specification
EMPr, pg. 43 Powerline
Supply adequate (closable, tamper proof) waste
collection bins at site where construction is being
undertaken
P 3
Site
establishment
and duration of
construction
EPC Contractor
EMPr, pg. 43 PowerlineSeparate bins should be provided for general and
hazardous wasteP 3
Site
establishment
and duration of
construction
EPC Contractor
EMPr, pg. 43 PowerlineAs far as possible, provision should be made for
separation of waste for recyclingP 3
Site
establishment
and duration of
construction
EPC Contractor
11
TOTAL SCORE 33
AS AVERAGE 3,0
AS PERCENTAGE 100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Each element of the checklist is scored on the following basis:
Savannah Environmental 6 2019/03/12
Yes No
EMPr, pg. 40 Powerline
All litter must be deposited in a clearly marked, closed,
animal-proof disposal bin in the construction area.
Particular attention needs to be paid to food waste.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 40 PowerlineNo one may disturb flora or fauna outside of the
demarcated construction area/s.P 3
Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 44 Powerline
Information distributed as part of the existing HIV/Aids
awareness campaigns should again be focused on and
communicated to the local workforce.
P 3Information is shared in the HSE induction and HSE
AwarenessConstruction
Owner
EPC Contractor
and sub-
contractor/s
EMPr, pg. 44 PowerlineMinimise clearing of natural vegetation and levelling for
equipment storage area(s)/ laydown area(s)P 3
Site
establishment,
and during
construction
EPC Contractor
and sub-
contractor/s
EMPr, pg. 44 Powerline
The siting of the construction equipment camp/s must
take cognisance of any sensitive areas identified by the
EIA studies and reflected on the site layout plan included
within this EMPr. No temporary site camps will be
allowed outside the footprint of the development area.
P 3 Pre-construction EPC Contractor
EMPr, pg. 44 Powerline
Ensure that all personnel have the appropriate level of
environmental awareness and competence to ensure
continued environmental due diligence and on-going
minimisation of environmental harm. This can be
achieved through the provision of appropriate
environmental awareness training to all personnel.
Records of all training undertaken must be kept.
Topics must include:
» What is meant by “Environment”
» Why the environment needs to be protected and
conserved
» How construction activities can impact on the
environment
» Awareness of emergency and spills response provisions
» Social responsibility during construction of the power
line e.g. being considerate to local residents
P 3Duration of
ConstructionEPC Contractor
EMPr, pg. 45 Powerline
Employees must use chemical toilets/ablution facilities
situated at designated areas of the site; no ablution
activities will be permitted outside the designated areas.
A minimum of one toilet shall be provided per 15 persons
or less at each working area such as the Contractor’s
camp.
P 3Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 45 Powerline
Ensure ablution facilities are appropriately maintained.
Ablutions must be cleaned regularly and associated
waste disposed of at a registered/permitted waste
disposal site. Portable ablutions must be removed from
site when construction is completed.
P 3
Site
establishment
and duration of
construction
EPC Contractor
and sub-
contractor/s
OBJECTIVE 2: Appropriate management of the construction site and construction workers
Environmental SpecificationCompliance
Score Comment Timeframe
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
If no, corrective actionApplicable EMPrLocation ResponsibilityPhoto record ref
No/Doc No
Savannah Environmental 7 2019/03/12
Yes No
OBJECTIVE 2: Appropriate management of the construction site and construction workers
Environmental SpecificationCompliance
Score Comment TimeframeIf no, corrective actionApplicable EMPrLocation ResponsibilityPhoto record ref
No/Doc No
EMPr, pg. 45 Powerline
Cooking/meals must take place in a designated area.
No firewood or kindling may be gathered from the site
or surrounds. Designate smoking areas as well as areas
for cooking, where the fire hazard could be regarded as
insignificant.
N/A No cooking is done on siteDuration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 45 PowerlineFire-fighting equipment and training must be provided
before the construction phase commences.P 3
Duration of
Contract
EPC Contractor
and sub-
contractor/s
EMPr, pg. 45 Powerline
Sub-contractors appointed by the Contractor must
ensure that all workers are informed at the outset of the
construction phase of the conditions contained on the
Code of Conduct, specifically consequences of stock
theft and trespassing on adjacent farms.
P 3 Construction
EPC Contractor
and sub-
contractor/s
EMPr, pg. 45 Powerline
On completion of the construction phase all
construction workers must return to their place of origin
within two days of their contract ending.
N/AThe EPC contractor's electrical contractor has not
completed works on site.
Duration of
Contract
EPC Contractor
and sub-
contractor/s
10
TOTAL SCORE 30
AS AVERAGE 3,0
AS PERCENTAGE 100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Each element of the checklist is scored on the following basis:
Savannah Environmental 8 2019/03/12
Yes No
EMPr, pg. 47 Powerline
Employment of local community members (i.e. source
labour from within the municipal area focused on the
communities in closest proximity to the site) should be
undertaken where possible.
O 0The contractor has not yet employed from the local
community
Duration of
construction
EPC Contractor
Owner
1
0
0,0
0,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 3: Maximise local employment and business opportunities associated with the construction phase
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
Location Applicable EMPr Environmental SpecificationCompliance
Score Comment
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc No
TOTAL SCORE
AS AVERAGE
Yes No
EMPr, pg. 53 PowerlineAreas to be cleared must be clearly marked on-site to
eliminate the potential for unnecessary clearing.P 3
Duration of
constructionEPC Contractor
EMPr, pg. 53 Powerline
The extent of clearing and disturbance to the native
vegetation must be kept to a minimum so that impact
on flora and fauna and their habitats are restricted
P 3
Site
establishment
and duration of
contract
EPC Contractor
EMPr, pg. 53 PowerlineNo activities must take place out of the demarcated
construction siteP 3
Site
establishment
and duration of
contractEPC Contractor
EMPr, pg. 53 Powerline
Any fill material required must be sourced from a
commercial off-site suitable/permitted source, quarry or
borrow pit. Where possible, material from foundation
excavations must be used as fill on-site
N/ANo fill material has yet been sourced for construction
activities
Duration of
contractEPC Contractor
3
9
3,0
100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
AS AVERAGE
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc No
TOTAL SCORE
Location Applicable EMPr Environmental SpecificationCompliance
Score Comment
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 6: Minimisation of development footprint
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
Savannah Environmental 10 2019/03/12
Yes No
EMPr, pg. 56 PowerlineIdentify disturbance areas and restrict construction
activity to these areas.P 3
Before and
during
constructionEPC Contractor
EMPr, pg. 56 PowerlineRehabilitate disturbance areas as soon as practicable
when construction in an area is complete.N/A No construction activity has required this action
During and after
construction EPC Contractor
EMPr, pg. 56 Powerline
Access roads to be carefully planned and constructed
to minimise the impacted area and prevent unnecessary
excavation, placement, and compaction of soil.
P 3Design and
constructionEPC Contractor
EMPr, pg. 56 PowerlineMinimise removal of vegetation which adds stability to
soil.P 3 Construction EPC Contractor
EMPr, pg. 56 Powerline
Erosion control measures: Run-off attenuation on slopes
(sand bags, logs), silt fences, storm water catchpits,
shade nets, gabions or temporary mulching over
denuded area as required.
N/A No construction activity has required this action
Erection: Before
construction
Maintenance:
Duration of
contract
EPC Contractor
EMPr, pg. 56 Powerline
Excavated topsoil must be stockpiled in designated
areas separate from base material at a maximum height
of 2m and covered (during windy conditions) or
vegetated until replaced during rehabilitation
N/A No construction activity has required this action
Site
establishment &
duration of
contract
EPC Contractor
EMPr, pg. 56 PowerlineTopsoil must not be stripped or stockpiled when it is
raining or when the soil is wet as compaction will occur.N/A No construction activity has required this action
Site
establishment
Maintenance:
for duration of
contract
EPC Contractor
EMPr, pg. 56 Powerline
Implement appropriate erosion control measures (i.e. run-
off attenuation on slopes (sand bags, logs), silt fences,
storm water catch-pits, shade nets, or temporary
mulching over denuded area as required)
N/A No construction activity has required this action
Erection: Before
construction
Maintenance:
Duration of
contract
EPC Contractor
EMPr, pg. 56 PowerlineControl depth of excavations and stability of cut
faces/sidewalls using appropriate methodsP 3
Duration of
contractEPC Contractor
EMPr, pg. 56 PowerlineImplement an appropriate stormwater management
planO 0
The site design is currently not complete, the stormwater
plan will only be developed once this is completed.
Duration of
constructionEPC Contractor
5
12
2,4
80,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
AS AVERAGE
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc No
TOTAL SCORE
Location Applicable EMPr Environmental SpecificationCompliance
Score Comment
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 8: Minimise soil degradation and erosion
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
Savannah Environmental 11 2019/03/12
Yes No
EMPr, pg. 54 Powerline
Areas to be cleared must be clearly marked in the field
to eliminate unnecessary clearing. In this regard,
staff/employees must be educated to keep construction
activities within the demarcated areas
P 3 Preconstruction
Contractor in
consultation with
Specialist
EMPr, pg. 54 Powerline
The extent of clearing and disturbance to the native
vegetation must be kept to a minimum so that the
impact on flora is restricted
P 3
Site
establishment &
duration of
contract
EPC Contractor
EMPr, pg. 54 Powerline A site rehabilitation programme must be implemented N/A No construction activity has required this actionDuration of
contract
Contractor in
consultation with
Specialist
EMPr, pg. 54 Powerline
Protected plants identified within the development
footprint must not be disturbed or removed prior to a
relevant permit being granted
P 3 Preconstruction EPC Construction
EMPr, pg. 54 PowerlineEmployees must be prohibited from harvesting wild
plants for any purposeP 3
Duration of
contractEPC Contractor
EMPr, pg. 55 Powerline
A speed limit of 60 km/h needs to be implemented on
the access roads to the site and a 40 km/h speed limit
on the construction sites and for the cranes.
P 3Duration of
constructionEPC Contractor
EMPr, pg. 55 PowerlineRestrict construction activities to post-dawn and predusk
Contractor ConstructionP 3 Construction EPC Contractor
EMPr, pg. 55 PowerlineEO must inspect the site and immediate area for
evidence of snares.N/A No construction activity has required this action Construction
EPC Contractor /
EO
6
18
3,0
100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
AS AVERAGE
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc No
TOTAL SCORE
Location Applicable EMPr Environmental SpecificationCompliance
Score Comment
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 10 Minimise the impacts on fauna
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
Savannah Environmental 12 2019/03/12
Yes No
EMPr, pg. 59 Powerline
Areas required to be cleared during construction must be
clearly marked in the field to avoid unnecessary
disturbance of adjacent areas (which will not be
surveyed in detail by a heritage specialist).
P 3Pre-construction
EPC Contractor
in
consultation with
Specialist
EMPr, pg. 59 Powerline
Project employees and any contract staff will maintain, at
all times, a high level of awareness of the possibility of
discovering heritage sites. Familiarise all staff and
contractors with procedures for dealing with heritage
objects/sites
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 59 Powerline
If a heritage object is found, work in that area must be
stopped immediately, and appropriate specialists
brought in to assess to site, notify the administering
authority of the item/site, and undertake due/required
processes.
P 3Duration of
contract
EPC Contractor
in consultation
with Specialist
3
9
3,0
100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
AS AVERAGE
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc No
TOTAL SCORE
Location Applicable EMPr Environmental SpecificationCompliance
Score Comment
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 13: Protection of heritage resources
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
Savannah Environmental 13 2019/03/12
Yes No
EMPr, pg. 60 Powerline
Restrict the activities and movement of construction
workers and vehicles to the immediate construction site
and existing access roads.
P 3 Construction EPC Contractor
EMPr, pg. 60 Powerline
Ensure that rubble, litter, and disused construction
materials are appropriately stored (if not removed daily)
and then disposed regularly at licensed waste facilities
P 3 Construction EPC Contractor
EMPr, pg. 60 Powerline
Reduce and control construction dust using approved
dust suppression techniques as and when required (i.e.
whenever dust becomes apparent)
P 3 Construction EPC Contractor
EMPr, pg. 60 Powerline
As far as possible, restrict construction activities to
daylight hours in order to negate or reduce the visual
impacts associated with lighting. The construction
tender documentation should specify that lighting at
the construction site office should be restricted to
security lighting and that such lighting should be
restricted to the site area and immediate surrounds
and should be down lighting and not up-lighting.
Similarly, if night work is required in work areas, lighting is to
be down lighting and not up-lighting and directed away
from neighbouring farmsteads and the R319 where
possible, particularly in close proximity to such areas.
P 3 Construction EPC Contractor
EMPr, pg. 60 Powerline
Rehabilitate all disturbed areas, construction areas, roads,
and servitudes to acceptable visual standards after
completion of construction works.
N/AThe EPC contractor's electrical contractor has not
established on site.Construction EPC Contractor
EMPr, pg. 60 PowerlineEnsure that vegetation is not unnecessarily removed
during the construction periodP 3 Planning EPC Contractor
EMPr, pg. 60 Powerline
Reduce the construction period as far as possible through
careful logistical planning and productive implementation
of resources
N/AThe EPC contractor's electrical contractor has not
established on site.Planning EPC Contractor
EMPr, pg. 60 Powerline
Plan the placement of laydown areas and temporary
construction equipment camps in order to minimise
vegetation clearing (i.e. in already disturbed areas)
wherever possible
P 3 Construction EPC Contractor
6
18
3,0
100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
AS AVERAGE
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc No
TOTAL SCORE
Location Applicable EMPr Environmental SpecificationCompliance
Score Comment
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 14: Minimisation of visual impacts associated with construction
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
Savannah Environmental 14 2019/03/12
Yes No
EMPr, pg. 62 Powerline
Construction contractors must provide specific detailed
waste management plans to deal with all waste
streams.
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Specific areas must be designated on-site for the
temporary management of various waste streams, i.e.
general refuse, construction waste (wood and metal
scrap), and contaminated waste as required. Location
of such areas must seek to minimise the potential for
impact on the surrounding environment, including
prevention of contaminated runoff, seepage, and
vermin control.
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Where practically possible, construction and general
wastes on-site must be reused or recycled. Bins and
skips must be available on-site for collection,
separation, and storage of waste streams (such as
wood, metals, general refuse etc.).
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Disposal of waste must be in accordance with relevant
legislative requirements, including the use of licensed
contractors.
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Hydrocarbon waste must be contained and stored in
sealed containers within an appropriately bunded area
and clearly labelled.
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Waste and surplus dangerous goods must be kept to a
minimum and must be transported by approved waste
contractors to sites designated for their disposal
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
The storage of flammable and combustible liquids such as
oils must be in designated areas which are appropriately
bunded, and stored in compliance with Material Safety
Data Sheets (MSDS) files.
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Any spills will receive the necessary clean-up action.
Bioremediation kits are to be kept on-site and used to
remediate any spills that may occur. Appropriate
arrangements to be made for appropriate collection and
disposal of all cleaning materials, absorbents and
contaminated soils (in accordance with a waste
management plan)
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Any storage and disposal permits/approvals which may
be required must be obtained, and the conditions
attached to such permits and approvals will be complied
with
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Routine servicing and maintenance of vehicles is not to
take place on-site (except for emergency situations or
large cranes which cannot be moved off-site). If repairs
of vehicles must take place on site, an appropriate drip
tray must be used to contain any fuel or oils
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 PowerlineTransport of all hazardous substances must be in
accordance with the relevant legislation and regulationsP 3
Duration of
contract
EPC
Contractor
EMPr, pg. 62 Powerline
Documentation (waste manifest) must be maintained
detailing the quantity, nature and fate of any hazardous
waste
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 62 PowerlineAn incident/complaints register must be established and
maintained on-siteP 3
Duration of
contract
EPC
Contractor
If no, corrective action Timeframe ResponsibilityPhoto record
ref No/Doc NoLocation
Applicable
EmpireEnvironmental Specification
ComplianceScore Comment
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 15: Appropriate handling and management of waste
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
Savannah Environmental 15 2019/03/12
Yes NoIf no, corrective action Timeframe Responsibility
Photo record
ref No/Doc NoLocation
Applicable
EmpireEnvironmental Specification
ComplianceScore Comment
OBJECTIVE 15: Appropriate handling and management of waste
EMPr, pg. 62 Powerline
Hazardous and non-hazardous waste must be separated
at source. Separate waste collection bins must be
provided for this purpose. These bins must be clearly
marked and appropriately covered
P 3
Erection:
during site
establishment
Maintenance:
for duration of
Contract
within a
particular area
EPC
Contractor
EMPr, pg. 64 PowerlineUnder no circumstances may solid waste be burnt or
buried on siteP 3
Erection:
during site
establishment
Maintenance:
for duration of
Contract
within a
particular area
EPC
Contractor
EMPr, pg. 64 PowerlineSupply waste collection bins at construction equipment
and construction crew campsP 3
Erection:
during site
establishment
Maintenance:
for duration of
Contract
within a
particular area
EPC
Contractor
EMPr, pg. 64 Powerline
Construction equipment must be refuelled within
designated refuelling locations, or where remote
refuelling is required, appropriate drip trays must be
utilised
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 64 PowerlineFuel storage areas must be inspected regularly to ensure
bund stability, integrity and functionP 3
Duration of
contract
EPC
Contractor
EMPr, pg. 64 PowerlineConstruction machinery must be stored within a bunded
area and on a sealed surfaceP 3
The machinery on site currently are stored on an unsealed
surface, but drip trays are in place.
Duration of
contract
EPC
Contractor
EMPr, pg. 64 Powerline
Spilled cement and concrete must be cleaned up as
soon as possible and disposed of at a suitably licensed
waste disposal site
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 64 Powerline
Corrective action must be undertaken immediately if a
complaint is made, or potential/actual leak or spill of
polluting substance identified. This includes stopping the
contaminant from further escaping, cleaning up the
affected environment as much as practically possible
and implementing preventive measures
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 64 Powerline
Any contaminated/polluted soil removed from the site
must be disposed of at a licensed hazardous waste
disposal facility
P 3Duration of
contract
EPC
Contractor
EMPr, pg. 64 PowerlineUpon the completion of construction, the area will be
cleared of potentially polluting materialsP 3
Completion of
construction
EPC
Contractor
23
69
3,0
100,0
3 - best practice/full compliance
2 - satisfactory (via >50% compliance)
1 - unsatisfactory (via <50% compliance)
0 - nothing in place
n/a - not applicable
AS AVERAGE
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
TOTAL SCORE
Savannah Environmental 16 2019/03/12
Yes No
EMPr, pg. 65 PowerlineAppropriate spill kits must be made available on-site for
the clean-up of spills and leaks of contaminantsP 3
Duration of
contractEPC Contractor
EMPr, pg. 65 Powerline
The sediment control and water quality structures used
on-site must be monitored and maintained in an
operational state at all times
P 3Duration of
contractEPC Contractor
EMPr, pg. 66 Powerline
Any contaminated/polluted soil can be stored onsite to
a maximum of 90 days before removed from the site
and must be disposed of at a licensed hazardous waste
disposal facility
N/A No incidents have occurred Construction EPC Contractor
EMPr, pg. 66 Powerline
Corrective action must be undertaken immediately if a
complaint is made, or potential/actual leak or spill of
polluting substance identified. This includes stopping the
contaminant from further escaping, cleaning up the
affected environment as much as practically possible
and implementing preventive measures. Refer to
Emergency Response procedure included in the
appendices.
N/A No incidents have occurred Duration of
contractEPC Contractor
EMPr, pg. 66 Powerline
In the event of a major spill or leak of contaminants, the
relevant administering authority must be immediately
notified as per the notification of
emergencies/incidents.
N/A No incidents have occurred Duration of
contractEPC Contractor
EMPr, pg. 66 Powerline
Spilled cement must be cleaned up as soon as possible,
stored as hazardous waste and disposed of at a suitably
licensed waste disposal site.
N/A No incidents have occurred Duration of
contractEPC Contractor
EMPr, pg. 66 Powerline
Routine servicing and maintenance of vehicles must not
take place on-site (except for emergencies). If repairs of
vehicles must take place, an appropriate drip tray must
be used to contain any fuel or oils.
P 3Duration of
contractEPC Contractor
EMPr, pg. 66 PowerlineFuel storage areas must be inspected regularly to
ensure bund stability, integrity, and function.P 3
Duration of
contractEPC Contractor
EMPr, pg. 66 Powerline
The storage of flammable and combustible liquids such
as oils will be in designated areas which are
appropriately bunded, and stored in compliance with
Material Safety Data Sheets (MSDS) files and applicable
regulations and safety instructions.
P 3The storage areas are appropriately bunded and the
flammable store is close to completion
Duration of
contractEPC Contractor
EMPr, pg. 66 Powerline
Any storage and disposal permits/approvals which may
be required must be obtained, and the conditions
attached to such permits and approvals will be
complied with.
P 3Duration of
contractEPC Contractor
If no, corrective action Timeframe ResponsibilityPhoto record ref
No/Doc NoLocation Applicable EMPr Environmental Specification
ComplianceScore Comment
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
OBJECTIVE 16: Appropriate handling and storage of chemicals, hazardous substances
ENVIRONMENTAL MANAGEMENT PROGRAMME CHECKLIST FOR EXCELSIOR-VRYHEID 132 kV POWERLINE, WESTERN CAPE:
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
Savannah Environmental 17 2019/03/12
Yes NoIf no, corrective action Timeframe Responsibility
Photo record ref
No/Doc NoLocation Applicable EMPr Environmental Specification
ComplianceScore Comment
OBJECTIVE 16: Appropriate handling and storage of chemicals, hazardous substances
EMPr, pg. 66 Powerline
Transport of all hazardous substances must be in
accordance with the relevant legislation and
regulations.
P 3Duration of
contractEPC Contractor
EMPr, pg. 66 PowerlineDrip trays must be placed under stationery machineries
in sensitive areasP 3
Duration of
contractEPC Contractor
EMPr, pg. 66 PowerlineAll small chemical substances used onsite must be
accompanied by a portable drip tray to store themP 3 Construction EPC Contractor
EMPr, pg. 66 Powerline
Small construction machineries (i.e. stumpers,
generators etc.) must be stored in an appropriately
sealed area
P 3 Construction EPC Contractor
EMPr, pg. 66 Powerline
Construction vehicles must be washed within
designated area, agreed with the EO and the site
manager
P 3Duration of
contractEPC Contractor
EMPr, pg. 66 PowerlineUpon the completion of construction, the area must be
cleared of potentially polluting materialsN/A
The EPC contractor's electrical contractors activities are
not complete.
Completion of
constructionEPC Contractor
11
33
3,0
100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
AS AVERAGE
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
TOTAL SCORE
Savannah Environmental 18 2019/03/12
Doc. No.: RE_OW_0046_007-CON-
AMX-30TP-009-00
Initiated Date 26-01-2018
Revision: 0
Latest Revised Date
Date
Action
Logged
Issue IDIssue Finding
Trigger
Issue
Source/Findin
g Issuer
Finding/Action Item/Issue DescriptionESHS MS
ElementIFC PS Proposed Corrective Action Preventative Action ESHS Category Priority
Responsible
Organisation
Responsible
PersonTarget Date
Revised Due
DateAction Status
Corrective Action Taken/Closure
Comment/Progress/HyperLink to the
Closure Evidence
Date Completed
12-Feb-19 EXC-HSE PI-025Community
Grievance
Affected
Community
Communities in the area had is the issue of the
criminal checks for general workers
Incidents-
Grievance and
Non-
Conformances
Performance Standard 2: Labor and
Working Conditions
Social/Commun
ity
Medium - 14-21
Days to rectifyBioTherm Energy Jasan Johnson 26-Feb-19 Complete
The mentioned grievances was not
from any applicant but from
community leaders who was
uninformed about the process. And
also those who did attend the
previous engagement that was last
year. This was discussed during the the
pre-screening process, we went
through the recruitment proses with
them and we also had the original
advertisement that was posted in all
public spaces.
12-Feb-19
12-Feb-19 EXC-HSE PI-026Community
Grievance
Affected
Community
Communities in the area had is the issue of the
five year residence pre-employment requirement
Incidents-
Grievance and
Non-
Conformances
Performance Standard 2: Labor and
Working Conditions
Social/Commun
ity
Medium - 14-21
Days to rectifyBioTherm Energy Jasan Johnson 26-Feb-19 Complete
The mentioned grievances was not
from any applicant but from
community leaders who was
uninformed about the process. And
also those who did attend the
previous engagement that was last
year. This was discussed during the the
pre-screening process, we went
through the recruitment proses with
them and we also had the original
advertisement that was posted in all
public spaces.
12-Feb-19
ESHS Management System
IN Status Category Project Discipline Issued by Nature of Incident Contractor / Subcontr Area / Location Description Date OpenedRequired
Closing Date
Days from
OpeningOfficial Closing Date
Days Taken for
ClosureNC No. Action Taken to Rectify (Owner / ECO comment) EPC Feedback Doc # Image
INCIDENT LIST FOR THE EXCELSIOR-VRYHEID POWERLINE, WESTERN CAPE
REV 00
2019/03/12
METHODOLOGY O P
Each element of the Daily checklist is to be scored on the following basis: Not compliant Compliant
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
The total score, average score and percentage compliance for each aspect (all elements) is calculated.
Page Condition Number Yes No
3 Standard 1
The holder of this permit shall return it together with a return of the
species flora and the number of each species which he/she plucked
thereunder, to the Chief Executive Officer, Western Cape Nature
Conservation Board, Private bag X29, Gatesville, 7766, within fourteen
days from the expiry thereof.
P 3Owner & EPC
contractor
3 Standard 2 THIS PERMIT IS SUBJECT TO SPECIAL CONDITIONS N/A NoteOwner & EPC
contractor
4 Special 1
THE MANAGER OF THE RELEVANT CONSERVATION AREA(S) (IF ANY)
MUST BE INFORMED TIMEOUSLY BEFORE ANY CONSERVATION AREA IS
ENTERED FOR COLLECTING OR RESEARCH PURPOSES AND THE
MANAGER'S WRITTEN PERMISSION TO ENTER SUCH RESERVE MUST BE
AQUIRED BEFOREHAND. THIS PERMIT DOES NOT GRANT THE PERMIT
HOLDER AUTOMATIC ACCESS TO ANY NATURE RESERVE,
CONSERVATION AREA, WILDERNESS AREA AND / OR STATE FOREST. ANY
OTHER / FUTHER CONDITIONS OR RESTICTIONS THAT THE MANAGER
MAY STIPULATE AT HIS/HER DISCRETION MUST ALSO BE ADHERED TO.
THE PERMIT MUST BE AVALABLE TO BE SHOWN ON DEMAND.
P 3Owner & EPC
contractor
4 Special 2
The owner of any other land concerned (be it privately or publicly
owned land) must give WRITTEN consent allowing the permit holder
to enter said property to collect flora / fauna. This written permission
must reflect the full name and address of the property owner (or of
the person authorised to grant such permission), the full name and
address of the person to whom the permission is granted and the
number and species of the flora / fauna, the date or dates on which
such flora / fauna may be picked / collected and the land in respect
of which permission is granted. Copies of this written permission must
be made available to the Western cape Nature Conservation Board
upon request.
P 3Owner & EPC
contractor
4 Special 3
Type-specimens of any newly described / discovered species or other
taxon collected must be lodged with a recognised South African
scientific institution / museum / herbarium (preferably within the
Province of Western Cape) where such material will be available to
other researchers. For every flora specimen collected on a Western
Cape Nature Conservation Board Herbarium at Jonkershoek (c/o MJ
Simpson, Private Bag X5014, Stellenbosch 7599).
P 3Owner & EPC
contractor
4 Special 4
A list of all collected specimens / material including the; species
name, the number collected, the collection data and the precise
locality of the collection must be submitted within 14 days from the
date of expiry of your permit to The Chief Executive Officer:
CapeNature, Private Bag X29, Gatesville, 7766.
P 3Owner & EPC
contractor
4 Special 5
The maximum number of specimens per species specified in the
permit (if t all) may not be exceeded without the prior permission of
The Chief Executive Officer: Western Cape Nature Conservation
Board.
P 3Owner & EPC
contractor
4 Special 6
For projects of more than one year's duration a progress report must
be submitted to The Chief Executive Officer: Western Cape Nature
Conservation Board before 31 December of each year.
P 3Owner & EPC
contractor
TimeframeEnvironmental SpecificationCompliance
Score Comment If no, corrective action taken/requiredLocation
Permit To Pluck Protected and Unprotected Flora - CN37-28-4821
PERMIT TO PLUCK PROTECTED AND UNPROTECTED FLORA - CHECKLIST FOR EXCELSIOR WIND ENERGY FACILITY AND POWERLINE, WESTERN CAPE
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
Responsibility
Savannah Environmental 2 2019-03-12
Page Condition Number Yes NoTimeframeEnvironmental Specification
ComplianceScore Comment If no, corrective action taken/required
Location
Permit To Pluck Protected and Unprotected Flora - CN37-28-4821
Responsibility
4 Special 7
One copy of all completed reports, publications, or articles (including
books, videos, CDs, DVDs etc.) resulting from the project / collection
must be submitted to The Chief Executive Office: Western Cape
Nature Conservation Board free of charge.
P 3Owner & EPC
contractor
4 Special 8
Should a report, publication, article or thesis arise from this project /
collection, an acknowledgement to Western Cape Nature
Conservation Board must be included.
P 3Owner & EPC
contractor
4 Special 9
The Forest Act of 1984 (Act 122 of 1984) and regulations, the Nature
Conservation Ordinance, 1974 (Ordinance 19 of 1974) and all
regulations in terms of the Ordinance must be adhered to.
P 3Owner & EPC
contractor
4 Special 10
Should it be envisaged to export any material / specimens across the
boundaries of the Western Cape province, an export permit will be
required in respect of certain species and a further application form
will have to be completed. The permit holder must confirm with the
Western cape Nature Conservation Board whether an export permit is
require BEFORE exporting any material / specimens from the Western
Cape Province.
P 3Owner & EPC
contractor
4 Special 11
No species that appear on the Red Data List or species listed as
endangered in terms of the Nature Conservation Ordinance, 1974
(Ordinance 19 of 1974) may be collected, except for those
mentioned on the permit.
P 3Owner & EPC
contractor
4 Special 12
Unless otherwise specifically indicated in writing, no material or
specimens collected with this permit or material or specimens bred or
propagated, from material or specimens collected with this permit,
may be donated, sold or used for any commercial purpose by any
party.
P 3Owner & EPC
contractor
4 Special 13IF APPLICABLE, ETHICS CLEARANCE MUST BE ACQUIRED FROM YOUR
RESEARCH INSTITUTE PRIOR COLLECTION.P 3
Owner & EPC
contractor
14
TOTAL SCORE 42
AS AVERAGE 3.0
AS PERCENTAGE 100.0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Each element of the checklist is scored on the following basis:
Savannah Environmental 3 2019-03-12
Yes No
Soil loss will be greater during wet periods than dry periods. Intense rainfall
events outside of the wet season, such as occasional summer thunder storms
can also cause significant soil loss. Therefore precautions to prevent erosion
should be present throughout the year.
P 3Construction
phase
Owner & EPC
contractor
Soils loss will be greater on steeper slopes. Ensure that steep slopes are not
devegetated and subsequently become hydrophobic (i.e. have increased
runoff and a decreased infiltration rate) increasing the erosion potential.
P 3Construction
phase
Owner & EPC
contractor
Soil loss is related to the length of time that soils are exposed prior to
rehabilitation or stabilisation. Therefore the gap between construction
activities and rehabilitation should be minimised. Phased construction and
progressive rehabilitation are therefore important elements of the erosion
control strategy.
P 3Construction
phase
Owner & EPC
contractor
The extent of disturbance will influence the risk and consequences of erosion.
Therefore site clearing should be restricted to areas required for construction
purposes only. As far as possible, large areas should not be cleared at a one
time, especially in areas where the risk of erosion is higher.
P 3Construction
phase
Owner & EPC
contractor
Roads should be planned and constructed in a manner which minimises their
erosion potential. Roads should therefore follow the contour as far as possible.
Roads parallel to the slope direction should be avoided as far as possible.
P 3Construction
phase
Owner & EPC
contractor
Where necessary, new roads constructed should include water diversion
structures present with energy dissipation features present to slow and disperse
the water into the receiving area.
P 3Construction
phase
Owner & EPC
contractor
Roads and other disturbed areas should be regularly monitored for erosion.
Any erosion problems recorded should be rectified as soon as possible and
monitored thereafter to ensure that they do not re-occur.
P 3Construction
phase
Owner & EPC
contractor
Compacted areas should have adequate drainage systems to avoid pooling
and surface flow. Heavy machinery should not compact those areas which
are not intended to be compacted as this will result in compacted
hydrophobic, water repellent soils which increase the erosion potential of the
area. Where compaction does occur, the areas should be ripped.
P 3Construction
phase
Owner & EPC
contractor
All bare areas should be revegetated with appropriate locally occurring
species, to bind the soil and limit erosion potential.N/A
There are currently no bare areas that
require revegetation, once such areas
are found mitigation must be put in
place.
Construction
phase
Owner & EPC
contractor
Silt fences should be used where there is a danger of topsoil or material
stockpiles eroding and entering streams and other sensitive areas.P 3
Construction
phase
Owner & EPC
contractor
Gabions and other stabilisation features should be used on steep slopes and
other areas vulnerable to erosion to minimise erosion risk as far as possible.N/A
At this point gabions and other
stabilisation features are built due to
the cut and fill activity not yet requiring
at those features
Construction
phase
Owner & EPC
contractor
Activity at the site after large rainfall events when the soils are wet and erosion
risk is increased should be reduced.P 3
Construction
phase
Owner & EPC
contractor
Timeframe Responsibility
Erosion
Management Plan,
pg. 2
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
EROSION MANAGEMENT PLAN
CommentIf no, corrective action
taken/requiredScore
EROSION MANAGEMENT PLAN - CHECKLIST FOR EXCELSIOR WIND FACILITY AND POWERLINE, WESTERN CAPE
Erosion
Management Plan,
pg. 3
Erosion
Management Plan,
pg. 3
Erosion
Management Plan,
pg. 3
Erosion
Management Plan,
pg. 3
Erosion
Management Plan,
pg. 2
Erosion
Management Plan,
pg. 2
Location Environmental SpecificationCompliance
Erosion
Management Plan,
pg. 2
Erosion
Management Plan,
pg. 2
Erosion
Management Plan,
pg. 2
Erosion
Management Plan,
pg. 2
Erosion
Management Plan,
pg. 2
Yes NoTimeframe ResponsibilityComment
If no, corrective action
taken/requiredScoreLocation Environmental Specification
Compliance
Topsoil should be removed and stored separately during construction
activities, and should be reapplied where appropriate as soon as possible in
order to encourage and facilitate rapid regeneration of the natural vegetation
on cleared areas (where applicable – not applicable to farmland /
agricultural areas).
P 3Construction
phase
Owner & EPC
contractor
Regular monitoring of the site for erosion problems during construction
(ongoing) and operation (at least twice annually) is recommended,
particularly after large summer thunderstorms have been experienced.
P 3Construction
phase
Owner & EPC
contractor
Erosion control measures to be implemented before and during the
construction period, including the final stormwater control measures (post
construction).
P 3Construction
phase
Owner & EPC
contractor
The location, area/extent (m²/ha) and specifications of all temporary and
permanent water management structures or stabilisation methods must be
indicated within the Stormwater Management Plan.
O 1
The EPC has a draft document in
place while awaiting final design
approval
Construction
phase
Owner & EPC
contractor
An onsite Engineer or Environmental Officer to be responsible for ensuring
implementation of the erosion control measures on site during the construction
period.
P 3Construction
phase
Owner & EPC
contractor
The Developer holds ultimate responsibility for remedial action in the event
that the approved stormwater plan is not correctly or appropriately
implemented and damage to the environment is caused.
P 3Construction
phase
Owner & EPC
contractor
16
TOTAL SCORE 46
AS AVERAGE 2,9
AS PERCENTAGE 95,8
Each element of the checklist is scored on the following basis:
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Erosion
Management Plan,
pg. 4
Erosion
Management Plan,
pg. 4
Erosion
Management Plan,
pg. 4
Erosion
Management Plan,
pg. 4
Erosion
Management Plan,
pg. 3
Erosion
Management Plan,
pg. 3
Yes No
The Environmental Officer must develop, implement and maintain a waste
inventory reflecting all waste generated during construction for both general
and hazardous waste streams.
P 3Construction
phase
Owner & EPC
contractor
Construction method and materials should be carefully considered in view of
waste reduction, re-use, and recycling opportunities.P 3
Construction
phase
Owner & EPC
contractor
Once a waste inventory has been established, targets for recovery of waste
(minimisation, re-use, recycling) should be set.P 3
Construction
phase
Owner & EPC
contractor
Each subcontractor must implement their own waste recycling system, i.e.
separate bins for food waste, plastics, paper, wood, glass, cardboard, metals,
etc.
P 3Construction
phase
Owner & EPC
contractor
Portable toilets must be monitored and maintained daily. P 3Construction
phase
Owner & EPC
contractor
Below ground storage of septic tanks, if installed, must withstand the external
forces of the surrounding environment. The area above the tank must be
demarcated to prevent any vehicles or heavy machinery from driving around
the area.
N/A
The Contractor will be using an
above-ground conversancy
tank
Construction
phase
Owner & EPC
contractor
Waste collection bins and hazardous waste containers must be provided by
the principal contractor and placed at various areas around site for the
storage of organic, recyclable and hazardous waste.
P 3Construction
phase
Owner & EPC
contractor
A dedicated waste area must be established on site for the storage of all
waste streams, before removal from site.P 3
Construction
phase
Owner & EPC
contractor
Hazardous waste must be stored within a bunded area constructed according
to SABS requirements. The volume of waste stored in the bunds must not
exceed 110% of the bund capacity.
P 3Construction
phase
Owner & EPC
contractor
The location of all temporary waste storage areas must aim to minimise the
potential for impact on the surrounding environment, including prevention of
contaminated runoff, seepage, and vermin control.
P 3Construction
phase
Owner & EPC
contractor
Waste storage shall be in accordance with all Regulations and best-practice
guidelines and under no circumstances may waste be burnt on site.P 3
Construction
phase
Owner & EPC
contractor
Timeframe Responsibility
WASTE MANAGEMENT PLAN
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
Score
WASTE MANAGEMENT PLAN - CHECKLIST FOR EXCELSIOR WIND FACILITY AND POWERLINE, WESTERN CAPE
Waste
Management
Plan, pg. 3
Waste
Management
CommentIf no, corrective action
taken/required
Waste
Management
Plan, pg. 3
Waste
Management
Waste
Management
Plan, pg. 3
Waste
Management
Plan, pg. 3
Location Environmental SpecificationCompliance
Waste
Management
Plan, pg. 3
Waste
Management
Waste
Management
Plan, pg. 4
Waste
Management
Plan, pg. 4
Waste
Management
Plan, pg. 4
Yes NoTimeframe ResponsibilityScore Comment
If no, corrective action
taken/requiredLocation Environmental Specification
Compliance
Vegetation removed from the site must be chipped, removed from the site
and disposed of at an appropriate waste disposal facility or used as mulch on
site.
N/ANo vegetation has required
chipping and disposal.
Construction
phase
Owner & EPC
contractor
A dedicated waste management team must be appointed by the principal
contractor’s EO, whom will be responsible for ensuring the continuous sorting
of waste and maintenance of the area. The waste management team must
be trained in all areas of waste management and monitored by the EO.
P 3Construction
phase
Owner & EPC
contractor
All waste removed from site must be done so by a registered/ licensed
subcontractor, whom must supply information regarding how waste recycling/
disposal will be achieved. The registered subcontractor must provide waste
manifests for all removals at least once a month.
P 3Construction
phase
Owner & EPC
contractor
The position of all waste storage areas must be located away from water
courses and ensure minimal degradation to the environment. The main waste
storage area must have a suitable storm water system separating clean and
dirty storm water.
P 3
Waste storage areas must be under roof or the waste storage containers must
be covered with tarpaulins (or similar material) to prevent the ingress of water.P 3
Collection bins placed around site and at subcontractors’ camps must be
maintained and emptied on a regular basis by the principal contractor.P 3
Waste must be stored in designated containers and not on the ground. P 3
Inspections and maintenance of bunds must be undertaken daily. Bunds must
be inspected for leaks or cracks in the foundation and walls. P 3
It is assumed that any rainwater collected inside the bund is contaminated
and must be removed and stored as hazardous waste, and not released into
the environment. If any leaks occur in the bund, these must be removed
immediately.
P 3
Waste generated on site must be removed on a regular basis, as determined
by the EO. This frequency may change during construction depending on
waste volumes generated at different stages of the construction process.
P 3
Waste
Management
Plan, pg. 4
Waste
Waste
Management
Waste
Management
Plan, pg. 4
Waste
Management
Plan, pg. 4
Waste
Management
Plan, pg. 4
Waste
Management
Plan, pg. 4
Waste
Management
Plan, pg. 5
Waste
Management
Plan, pg. 4
Waste
Management
Plan, pg. 4
Yes NoTimeframe ResponsibilityScore Comment
If no, corrective action
taken/requiredLocation Environmental Specification
Compliance
Waste must be removed by a suitably qualified contractor and disposed at an
appropriately licensed landfill site. Proof of appropriate disposal must be
provided by the contractor.
P 3
Only waste that has been
removed from site is sewarage
waste, waste manifests have
been submitted to the ECO on a
monthly basis
Documentation (waste manifest, certificate of issue or safe disposal) must be
kept detailing the quantity, nature, and fate of any regulated waste for audit
purposes.
P 3
Only waste that has been
removed from site is sewarage
waste, waste manifests have
been submitted to the ECO on a
monthly basis
Waste management must form part of the monthly reporting requirements in
terms of volumes generated, types, storage and final disposal.P 3
Only waste that has been
removed from site is sewarage
waste, waste manifests have
been submitted to the ECO on a
monthly basis
Training and awareness regarding waste management shall be provided to all
employees and contractors as part of the toolbox talks or on-site awareness
sessions.
P 3
23
TOTAL SCORE 69
AS AVERAGE 3,0
AS PERCENTAGE 100,0
Each element of the checklist is scored on the following basis:
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Waste
Management
Plan, pg. 5
Waste
Management
Plan, pg. 5
Waste
Management
Plan, pg. 5
Waste
Management
Plan, pg. 5
Yes No
Before beginning work on site, topsoil (0-25 cm) should be stripped from all areas that
will be disturbed by construction activities. Appropriate equipment must be used and
appropriate work practices must be implemented for soil stripping as mishandling soil
can have an adverse effect on its properties.
P 3Construction
phase
Owner & EPC
contractor
Topsoil should be stripped in the driest condition possible. P 3Construction
phase
Owner & EPC
contractor
Topsoil must be retained on site in order to be used in site rehabilitation. The correct
handling of the topsoil layer is in most cases the key to rehabilitation success.P 3
Construction
phase
Owner & EPC
contractor
Topsoil and subsoil layers must never be mixed. The mixture of topsoil with the deeper
sterile soil hinders the germination of seeds which are buried too deep in the soil layer.
Mixture of soil layers also leads to the dilution of nutrient levels which are at highest
concentration within the topsoil, resulting in lower levels of nutrients available for new
seedlings.
P 3Construction
phase
Owner & EPC
contractor
To enable soil to be reused on site at a later stage, it needs to be stored in temporary
stockpiles to minimise any damage or loss of function. Stockpiles should not be higher
than 2m. Alternatively topsoil berms can be created on the site boundaries. There
are a number of important considerations when creating stockpiles - including soil
erosion, pollution to watercourses and the risk of flooding. These will be affected by
the size, height and method of forming stockpiles, and how they are protected and
maintained.
P 3Construction
phase
Owner & EPC
contractor
Topsoil must be stored separately from other soil in heaps until construction in an area
is complete.P 3
Construction
phase
Owner & EPC
contractor
The duration of topsoil storage should be minimised as far as possible. Storing topsoil
for long periods leads to seed bank depletion following germination during storage,
and anoxic conditions develop inside large stockpile heaps.
P 3Construction
phase
Owner & EPC
contractor
On many sites subsoil will not need to be stripped but merely protected from damage.
However, on other sites it might need to be temporarily removed. Where subsoil is
required to be stripped, this should be undertaken before commencement of
construction from all areas that are to be disturbed by construction activities or driven
over by vehicles.
P 3Construction
phase
Owner & EPC
contractor
Soil Management
Plan, pg. 3
Soil Management
Plan, pg. 3
Soil Management
Plan, pg. 3
Soil Management
Plan, pg. 2
Soil Management
Plan, pg. 2
Soil Management
Plan, pg. 2
Soil Management
Plan, pg. 2
Soil Management
Plan, pg. 2
TimeframeEnvironmental SpecificationCompliance
Score CommentIf no, corrective action
taken/required
SOIL MANAGEMENT PLAN - CHECKLIST FOR EXCELSIOR WIND FACILITY AND POWERLINE, WESTERN CAPE
SOIL MANAGEMENT PLAN
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
ResponsibilityLocation
Savannah Environmental 6 2019/03/12
Yes NoTimeframeEnvironmental Specification
ComplianceScore Comment
If no, corrective action
taken/requiredResponsibilityLocation
Subsoil stripping depths depend on the correct identification of the sub-soil types on
an ad-hoc basis, where no formal survey data exists.P 3
Construction
phase
Owner & EPC
contractor
To enable soil to be reused on site at a later stage, it needs to be stored in temporary
stockpiles to minimise any damage or loss of function. There are a number of
important considerations when creating stockpiles - including soil erosion, pollution to
watercourses and the risk of flooding. These will be affected by the size, height and
method of forming stockpiles, and how they are protected and maintained.
P 3Construction
phase
Owner & EPC
contractor
All stockpiles must be positioned away from drainage lines. P 3Construction
phase
Owner & EPC
contractor
Sediment fencing should be erected downslope of all stockpiles to intercept any
sediment and upslope runoff should be diverted away from stockpiles.P 3
Construction
phase
Owner & EPC
contractor
12
TOTAL SCORE 36
AS AVERAGE 36,0
AS PERCENTAGE 100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Soil Management
Plan, pg. 3
Soil Management
Plan, pg. 3
Soil Management
Plan, pg. 3
Soil Management
Plan, pg. 3
Each element of the checklist is scored on the following basis:
Savannah Environmental 7 2019/03/12
Yes No
A prevention strategy should be considered and established, including regular surveys
and monitoring for invasive alien plants, effective rehabilitation of disturbed areas and
prevention of unnecessary disturbance of natural areas.
P 3Construction
phase
Owner & EPC
contractor
Monitoring plans should be developed which are designed to identify Invasive Alien
Plant Species shortly after they arrive in the project area. Keeping up to date on which
weeds are an immediate threat to the site is important, but efforts should be planned to
update this information on a regular basis.
P 3Construction
phase
Owner & EPC
contractor
When new Invasive Alien Plant Species are recorded on site, an immediate response of
locating the site for future monitoring and either hand‐pulling the weeds or an
application of a suitable herbicide should be planned.
P 3Construction
phase
Owner & EPC
contractor
If any alien invasive plants are found to become established on site, action plans for their
control should be developed, depending on the size of the infestations, budgets,
manpower considerations and time. Separate plans of control actions should be
developed for each location and/or each species.
P 3Construction
phase
Owner & EPC
contractor
Appropriate registered chemicals and other possible control agents should be
considered in the action plans for each site/species. P 3
Construction
phase
Owner & EPC
contractor
Alien control programs are long-term management projects and should include a
clearing plan which includes follow up actions for rehabilitation of the cleared area. P 3
Construction
phase
Owner & EPC
contractor
Different species require different clearing methods such as manual, chemical or
biological methods or a combination of both. Care should however be taken that the
clearing methods used do not encourage further invasion. As such, regardless of the
methods used, disturbance to the soil should be kept to a minimum.
N/A NoteConstruction
phase
Owner & EPC
contractor
Mechanical Control. This entails damaging or removing the plant by physical action.
Different techniques could be used, e.g. uprooting, felling, slashing, mowing, ringbarking
or bark stripping. This control option is only really feasible in sparse infestations or on small
scale, and for controlling species that do not coppice after cutting. Species that tend to
coppice, need to have the cut stumps or coppice growth treated with herbicides
following the mechanical treatment. Mechanical control is labour intensive and
therefore expensive, and could cause severe soil disturbance and erosion.
N/ANo removal of alien and invasive
species has occurred on site.
Construction
phase
Owner & EPC
contractor
Chemical Control. Although it is usually preferable to use manual clearing methods
where possible, such methods may create additional disturbance which stimulates alien
invasion and may also be ineffective for many woody species which resprout. Where
herbicides are to be used, the impact of the operation on the natural environment
should be minimised by observing the following:
N/AThe Contractor does not store any
herbicides
Construction
phase
Owner & EPC
contractor
* Area contamination must be minimised by careful, accurate application with a
minimum amount of herbicide to achieve good control.N/A
The Contractor does not store any
herbicides
Construction
phase
Owner & EPC
contractor
* All care must be taken to prevent contamination of any water bodies. This includes due
care in storage, application, cleaning equipment and disposal of containers, product
and spray mixtures.
N/AThe Contractor does not store any
herbicides
Construction
phase
Owner & EPC
contractor
* Equipment should be washed where there is no danger of contaminating water
sources and washings carefully disposed of in a suitable site.N/A
The Contractor does not store any
herbicides
Construction
phase
Owner & EPC
contractor
* To avoid damage to indigenous or other desirable vegetation, products should be
selected that will have the least effect on non-target vegetation.N/A
The Contractor does not store any
herbicides
Construction
phase
Owner & EPC
contractor
* Coarse droplet nozzles should be fitted to avoid drift onto neighbouring vegetation. N/AThe Contractor does not store any
herbicides
Construction
phase
Owner & EPC
contractor
* The appropriate health and safety procedures should also be followed regarding the
storage, handling and disposal of herbicides.N/A
The Contractor does not store any
herbicides
Construction
phase
Owner & EPC
contractor
Contractors using herbicides need to have a valid Pest Control Operators License
(limited weeds controller) according to the Fertilizer, Farm Feeds, Agricultural Remedies
and Stock Remedies Act (Act No. 36 of 1947). This is regulated by the Department of
Agriculture, Forestry and Fisheries.
N/A
The Contractor does not store any
herbicides on site. But if required a
PCO with a license will be
requested.
Construction
phase
Owner & EPC
contractor
ALIEN PLANT MANAGEMENT PLAN - CHECKLIST FOR EXCELSIOR WIND FACILITY AND POWERLINE, WESTERN CAPE
Alien Plant and Open
Space Management
Plan, pg. 3
Alien Plant and Open
Space Management
Alien Plant and Open
Space Management
Plan, pg. 3
ALIEN PLANT MANAGEMENT PLAN
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
Alien Plant and Open
Space Management
Plan, pg. 3
Location Environmental SpecificationCompliance
Score Timeframe Responsibility
Alien Plant and Open
Space Management
Plan, pg. 3
Alien Plant and Open
Space Management
Plan, pg. 3
CommentIf no, corrective action
taken/required
Alien Plant and Open
Space Management
Plan, pg. 4
Alien Plant and Open
Space Management
Plan, pg. 5
Yes NoLocation Environmental Specification
ComplianceScore Timeframe ResponsibilityComment
If no, corrective action
taken/required
Biological weed control consists in the use of natural enemies to reduce the vigour or
reproductive potential of an invasive alien plant. Biological control agents include
insects, mites, and micro‐organisms such as fungi or bacteria. They usually attack
specific parts of the plant, either the reproductive organs directly (flower buds, flowers or
fruit) or the seeds after they have dropped. The stress caused by the biological control
agent may kill a plant outright or it might impact on the plants reproductive capacity. In
certain instances, the reproductive capacity is reduced to zero and the population is
effectively sterilised. All of these outcomes will help to reduce the spread of the species.
N/A NoteConstruction
phase
Owner & EPC
contractor
Establish an ongoing monitoring programme for construction phase to detect and
quantify any alien species that may become established and identify the problem
species.
P 3Construction
phase
Owner & EPC
contractor
Alien vegetation regrowth on areas disturbed by construction must be immediately
controlled once recorded throughout the entire site during construction and operation.P 3
Construction
phase
Owner & EPC
contractor
Care must be taken to avoid the introduction of alien invasive plant species to the site.
Particular attention must be paid to imported material such as building sand or dirty
earth‐moving equipment. Stockpiles should be checked regularly and any weeds
emerging from material stockpiles should be removed.
P 3Construction
phase
Owner & EPC
contractor
Cleared areas that have become invaded by alien species can be sprayed with
appropriate herbicides provided that these are such that break down on contact with
the soil. Residual herbicides should not be used.
P 3Construction
phase
Owner & EPC
contractor
The effectiveness of vegetation control varies seasonally and this is also likely to impact
alien species. Control early in the wet season will allow species to re-grow and follow-up
control is likely to be required. It is tempting to leave control until late in the wet season
to avoid follow-up control. However, this may allow alien species to set seed before
control and hence will not contribute towards reducing alien species abundance.
Therefore, vegetation control should be aimed at the middle of the wet season, with a
follow-up event towards the end of the wet season. There are no exact dates that can
be specified here as each season is unique and management must therefore respond
according to the state and progression of the vegetation.
P 3Construction
phase
Owner & EPC
contractor
Alien management is an iterative process and it may require repeated control efforts to
significantly reduce the abundance of a species. This is often due to the presence of
large and persistent seed banks. However, repeated control usually results in rapid
decline once seed banks become depleted.
P 3Construction
phase
Owner & EPC
contractor
Alien Plant and Open
Space Management
Plan, pg. 6
Alien Plant and Open
Space Management
Plan, pg. 6
Alien Plant and Open
Space Management
Plan, pg. 5
Alien Plant and Open
Space Management
Plan, pg. 6
Alien Plant and Open
Space Management
Plan, pg. 6
Alien Plant and Open
Space Management
Plan, pg. 6
Alien Plant and Open
Space Management
Plan, pg. 6
Yes NoLocation Environmental Specification
ComplianceScore Timeframe ResponsibilityComment
If no, corrective action
taken/required
Regular vegetation control to reduce plant biomass within the site should be
conducted. This should be timed so as to coincide with the critical growth phases of the
most important alien species on site. This will significantly reduce the cost of alien
management as this should contribute towards the control of the dominant alien species
and additional targeted control will be required only for a limited number of species.
P 3Construction
phase
Owner & EPC
contractor
No alien species should be cultivated on-site. If vegetation is required for aesthetic
purposes, then non-invasive, water-wise locally-occurring species should be used.P 3
Construction
phase
Owner & EPC
contractor
During operation, surveys for alien species should be conducted regularly. It is
recommended that this be undertaken every 6 months for the first two years after
construction and annually thereafter. All aliens identified should be cleared using
appropriate means.
P 3Construction
phase
Owner & EPC
contractor
Photographic records must be kept of areas to be cleared prior to work starting and at
regular intervals during initial clearing activities. Similarly, photographic records should
be kept of the area from immediately before and after follow‐up clearing activities.
Rehabilitation processes must also be recorded.
P 3Construction
phase
Owner & EPC
contractor
Simple records must be kept of daily operations, e.g. area/location cleared, labour units
and, if ever used, the amount of herbicide used.P 3
Construction
phase
Owner & EPC
contractor
It is important that, if monitoring results in detection of invasive alien plants, that this leads
to immediate action.P 3
Construction
phase
Owner & EPC
contractor
18
TOTAL SCORE 54
AS AVERAGE 3,0
AS PERCENTAGE 100,0
Each element of the checklist is scored on the following basis:
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Alien Plant and Open
Space Management
Plan, pg. 7
Alien Plant and Open
Space Management
Alien Plant and Open
Space Management
Alien Plant and Open
Space Management
Plan, pg. 7
Alien Plant and Open
Space Management
Plan, pg. 7
Alien Plant and Open
Space Management
Plan, pg. 6
Yes No
All equipment refuelling, servicing and maintenance activities should only be
undertaken within appropriately sealed designated areas.P 3
Constructio
n phase
Owner & EPC
contractor
All maintenance materials, oils, grease, lubricants, etc. should be stored in a
designated area in an appropriate storage container.P 3
Constructio
n phase
Owner & EPC
contractor
No refuelling, storage, servicing, or maintenance of equipment should take
place within 50m of drainage lines or sensitive environmental resources in order
to reduce the risk of contamination by spills.
P 3Constructio
n phase
Owner & EPC
contractor
No refuelling or servicing should be undertaken without absorbent material or
drip pans properly placed to contain spilled fuel.P 3
Constructio
n phase
Owner & EPC
contractor
Any fluids drained from the machinery during servicing should be collected in
leak-proof containers and taken to an appropriate disposal or recycling facility.P 3
Constructio
n phase
Owner & EPC
contractor
Chemical toilets used during construction must not be placed within 50m of
drainage lines or sensitive environmental resources in order to reduce the risk of
contamination by spills. These facilities must be regularly cleaned. Chemicals
used in toilets are also hazardous to the environment and must be controlled.
Portable chemical toilets could overflow if not pumped regularly or they could
spill if dropped or overturned during moving. Care and due diligence should
be taken at all times.
P 3Constructio
n phase
Owner & EPC
contractor
Contact details of emergency services and HazMat Response Contractors are
to be clearly displayed on the site. All staff are to be made aware of these
details and must be familiar with the procedures for notification in the event of
an emergency.
P 3Constructio
n phase
Owner & EPC
contractor
On many sites subsoil will not need to be stripped but merely protected from
damage. However, on other sites it might need to be temporarily removed.
Where subsoil is required to be stripped, this should be undertaken before
commencement of construction from all areas that are to be disturbed by
construction activities or driven over by vehicles.
P 3Constructio
n phase
Owner & EPC
contractor
8
TOTAL SCORE 24
AS AVERAGE 3,0
AS PERCENTAGE 100,0
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
EMERGENCY RESPONSE PLAN
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
EMERGENCY RESPONSE PLAN - CHECKLIST FOR EXCELSIOR WIND FACILITY AND POWERLINE, WESTERN CAPE
Emergency Response
Plan, pg. 3
Location Environmental SpecificationCompliance
Score Timeframe ResponsibilityPhoto record ref
No/Doc No
Emergency Response
Plan, pg. 2
Emergency Response
Plan, pg. 2
CommentIf no, corrective action
taken/required
Each element of the checklist is scored on the following basis:
Emergency Response
Plan, pg. 3
Emergency Response
Plan, pg. 3
Emergency Response
Plan, pg. 3
Emergency Response
Plan, pg. 3
Emergency Response
Plan, pg. 4
Yes No
Immediately after replacing topsoil in disturbed areas, the soil surface must be
revegetated with a suitable plant cover. N/A
The Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
It is expected that soil seed banks of indigenous vegetation will be present to
initiate initial vegetation cover. However, simply applying this topsoil to a well
prepared rehabilitation site does not result in the same species richness and
diversity as the surrounding areas. In some areas the natural regeneration of the
vegetation may be poor and the application of seed to enhance vegetation
recovery may be required.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Where possible, seed should be collected from plants present at the site during
plant rescue operations. Indigenous seeds may also be harvested for purposes of
re-vegetation in areas that are free of alien or invasive vegetation, either at the
site prior to clearance or from suitable neighbouring sites.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Seed collection should be undertaken by a suitably qualified specialist who is
familiar with the various seed types associated with the plant species and
rehabilitation in the area.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Seed collection may be done throughout the year as seed ripens, but can also be
restricted to summer, when a large amount of the perennial seed should have
ripened. The collection of unripe seeds will reduce the percentage germination
thereby reducing the effectiveness of the rehabilitation efforts. Seeds should be
stored in paper or canvas bags dusted with insecticide, and sown at the onset of
the rainy season.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Seed can be sown onto the soil, but should preferably be applied in conjunction
with measures to improve seedling survival such as scarification of the soil surface
or simultaneous application of mulch. Additional organic material may be added
to the soil mix, if required, to assist with water retention during the early stages of
seedling establishment.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
REVEGETATION AND REHABILITATION PLAN - CHECKLIST FOR EXCELSIOR WIND FACILITY AND POWERLINE, WESTERN CAPE
Revegetation and
Rehabilitation Plan,
pg. 3
Revegetation and
Rehabilitation Plan,
pg. 3
Revegetation and
Rehabilitation Plan,
pg. 3
REVEGETATION AND REHABILITATION PLAN
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
Revegetation and
Rehabilitation Plan,
pg. 3
Location Environmental SpecificationCompliance
Score Timeframe Responsibility
Revegetation and
Rehabilitation Plan,
Revegetation and
Rehabilitation Plan,
pg. 3
CommentIf no, corrective action
taken/required
Yes NoLocation Environmental Specification
ComplianceScore Timeframe ResponsibilityComment
If no, corrective action
taken/required
It should be ensured that the seed mix is as diverse as possible in the first season.
After the first season, when pioneer plant communities have successfully
established, attempts should be made to re-sow and replant the area with more
perennial and woody species. It is a process that will require several follow-ups.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Planting is dependent on species involved. Planting of species recommended for
rehabilitation should be carried out as far as is practicable to coincide with the
onset of the first significant rains. In general however, planting should commence
as soon as possible after construction is completed in order to minimise the
potential for erosion.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
The final vegetation cover should resemble the original (non-encroached and
indigenous) vegetation composition and structure as far as practicably possible.N/A
The Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Progressive rehabilitation is an important element of the rehabilitation strategy and
should be implemented where feasible. Re-vegetation of disturbed surfaces must
occur immediately after construction activities are completed.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Once revegetated, areas should be protected to prevent trampling and erosion. N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
No construction equipment, vehicles or unauthorised personnel should be
allowed onto areas that have been vegetated.N/A
The Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Where rehabilitation sites are located within actively grazed areas, they should be
fenced.N/A
The Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Fencing should be removed once a sound vegetative cover has been achieved. N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Revegetation and
Rehabilitation Plan,
pg. 3
Revegetation and
Rehabilitation Plan,
pg. 3
Revegetation and
Rehabilitation Plan,
pg. 4
Revegetation and
Rehabilitation Plan,
Revegetation and
Rehabilitation Plan,
Revegetation and
Rehabilitation Plan,
Revegetation and
Rehabilitation Plan,
Revegetation and
Rehabilitation Plan,
pg. 4
Yes NoLocation Environmental Specification
ComplianceScore Timeframe ResponsibilityComment
If no, corrective action
taken/required
Any runnels, erosion channels or wash always developing after revegetation
should be backfilled and consolidated and the areas restored to a proper stable
condition.
N/AThe Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Re-vegetated areas should be monitored every 4 months for the first 12 months
following construction.N/A
The Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Re-vegetated areas showing inadequate surface coverage (less than 20% within
12 months after re-vegetation) should be prepared and re-vegetated;N/A
The Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
Any areas showing erosion, should be re-contoured and seeded with indigenous
grasses or other locally occurring species which grow quickly.N/A
The Project is currently not in the
Rehabilitation phase.
Construction
phase
Owner & EPC
contractor
0
TOTAL SCORE N/A
AS AVERAGE
AS PERCENTAGE
Each element of the checklist is scored on the following basis:
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Revegetation and
Rehabilitation Plan,
pg. 5
Revegetation and
Rehabilitation Plan,
pg. 5
Revegetation and
Rehabilitation Plan,
pg. 5
Revegetation and
Rehabilitation Plan,
pg. 5
Yes No
Species can be removed from their original habitat with minimal damage to
the plant, especially the roots.N/A
Currently no species have been
removed or relocated.
Construction
phase
Owner & EPC
contractor
All plants removed are safely stored and treated according to their specific
requirements prior to being transplanted again.N/A
Currently no species have been
removed or relocated.
Construction
phase
Owner & EPC
contractor
They are relocated into a suitable habitat and protected from further
damage and all disturbances to aid their re-establishment.N/A
Currently no species have been
removed or relocated.
Construction
phase
Owner & EPC
contractor
Timing of planting activities is planned with the onset of the growing season. N/ACurrently no species have been
removed or relocated.
Construction
phase
Owner & EPC
contractor
Steps are taken where necessary to aid the initial establishment of
vegetation, including occasional watering.N/A
Currently no species have been
removed or relocated.
Construction
phase
Owner & EPC
contractor
A permit is required to translocate or destroy any listed and protected species
even if they do not leave the property. This permit should be obtained prior
to any search and rescue operations being undertaken.
P 3Construction
phase
Owner & EPC
contractor
Where suitable species are identified, a search and rescue operation of these
species should be undertaken within the development footprint prior to the
commencement of construction.
P 3Construction
phase
Owner & EPC
contractor
As far as possible, timing of search and rescue activities should be planned
with the onset of the growing season.P 3
Construction
phase
Owner & EPC
contractor
Affected individuals should be translocated to a similar habitat outside of the
development footprint and marked for monitoring purposes. For each
individual plant that is rescued, the plant must be photographed before
removal, tagged with a unique number or code and a latitude longitude
position recorded using a hand‐held GPS device.
N/ACurrently no species have been
removed or relocated.
Construction
phase
Owner & EPC
contractor
PLANT SEARCH AND PROTECTION PLAN - CHECKLIST FOR EXCELSIOR WIND FACILITY AND POWERLINE, WESTERN CAPE
Alien Plant and Open
Space Management Plan,
pg. 2
Alien Plant and Open
Space Management Plan,
pg. 2
Alien Plant and Open
Space Management Plan,
pg. 2
PLANT SEARCH AND PROTECTION PLAN
PERIOD: February 2019
SITE: Excelsior Wind Energy Facility
COMPLETED BY: Lungani Zwane - Savannah Environmental (ECO)
Alien Plant and Open
Space Management Plan,
pg. 2
Location Environmental SpecificationCompliance
Score Timeframe Responsibility
Alien Plant and Open
Space Management Plan,
Alien Plant and Open
Space Management Plan,
pg. 2
Comment If no, corrective action taken/required
Alien Plant and Open
Space Management Plan,
pg. 2
Alien Plant and Open
Space Management Plan,
pg. 2
Alien Plant and Open
Space Management Plan,
pg. 2
Yes NoLocation Environmental Specification
ComplianceScore Timeframe ResponsibilityComment If no, corrective action taken/required
The rescued plants must be planted into a container to be housed within a
temporary nursery on site or immediately planted into the target habitat. N/A
Currently no species have been
removed or relocated.
Construction
phase
Owner & EPC
contractor
Rescued plants, if re‐planted back in the wild, should be placed as close as
possible to where they were originally removed. Re‐planting into the wild
must cause as little disturbance as possible to existing natural ecosystems.
The position of the rescued individual/s must be recorded to aid in future
monitoring of that plant.
N/ACurrently no species have been
removed or relocated.
Construction
phase
Owner & EPC
contractor
During construction, the ECO must monitor vegetation clearing at the site.
Any deviations from the plans that may be required should first be checked
for listed species by the ECO or Environmental Officer and any listed species
present which are able to survive translocation should be translocated to a
safe site.
P 3Construction
phase
Owner & EPC
contractor
Any listed species suitable for translocation observed within the development
footprint that were not previously observed be translocated to a safe site.N/A No species have been translocated
Construction
phase
Owner & EPC
contractor
The collecting of plants or their parts should be strictly forbidden. Staff should
be informed of the legal and conservation aspects of harvesting plants from
the wild as part of the environmental induction training.
P 3Construction
phase
Owner & EPC
contractor
Sensitive habitats and area outside project development should be clearly
demarcated as no go areas during the construction and operational phase
to avoid accidental impacts.
P 3Construction
phase
Owner & EPC
contractor
6
TOTAL SCORE 18
AS AVERAGE 3,0
AS PERCENTAGE 100,0
Each element of the checklist is scored on the following basis:
3 - best practice/full compliance
2 - satisfactory (viz >50% compliance)
1 - unsatisfactory (viz <50% compliance)
0 - nothing in place
n/a - not applicable
Alien Plant and Open
Space Management Plan,
pg. 2
Alien Plant and Open
Space Management Plan,
pg. 3
Alien Plant and Open
Space Management Plan,
pg. 3
Alien Plant and Open
Space Management Plan,
pg. 2
Alien Plant and Open
Space Management Plan,
pg. 2
Alien Plant and Open
Space Management Plan,
pg. 2