Excav & Deep Foundations Fall 09

126
Foundations &Excavation Leaning Tower of Pisa Professor Richard Luxenburg, AIA

Transcript of Excav & Deep Foundations Fall 09

Page 1: Excav & Deep Foundations Fall 09

Foundations&Excavation

Leaning Tower of Pisa

Professor Richard Luxenburg, AIA

Page 2: Excav & Deep Foundations Fall 09

Foundations

Purpose; Transfer Building Loads to the

Earth

Basic TypesShallow: Transfer Load @ Base of

Substructure Deep: Penetrate Unsuitable Soil to

Reach Competent Soil or Rock

Page 3: Excav & Deep Foundations Fall 09

Deep Foundations - Purposetransfer building loads deep into the earth

Basic typesDrilled (&

poured)

Driven

Page 4: Excav & Deep Foundations Fall 09

Caissons

Similar to a column footing -

only deep

Drilled to required bearing

capacity

Point bearing (exception -

socketed)

Page 5: Excav & Deep Foundations Fall 09

Caisson Installation Sequence

Hole drilled with a large drill rig

Casing installed (typically)

Bell or Tip enlargement (optional)

Bottom inspected and tested

Reinforced

Concrete placement (& casing removal)

Page 6: Excav & Deep Foundations Fall 09
Page 7: Excav & Deep Foundations Fall 09
Page 8: Excav & Deep Foundations Fall 09
Page 9: Excav & Deep Foundations Fall 09
Page 10: Excav & Deep Foundations Fall 09
Page 11: Excav & Deep Foundations Fall 09
Page 12: Excav & Deep Foundations Fall 09
Page 13: Excav & Deep Foundations Fall 09
Page 14: Excav & Deep Foundations Fall 09
Page 15: Excav & Deep Foundations Fall 09
Page 16: Excav & Deep Foundations Fall 09
Page 17: Excav & Deep Foundations Fall 09
Page 18: Excav & Deep Foundations Fall 09
Page 19: Excav & Deep Foundations Fall 09
Page 20: Excav & Deep Foundations Fall 09
Page 21: Excav & Deep Foundations Fall 09
Page 22: Excav & Deep Foundations Fall 09
Page 23: Excav & Deep Foundations Fall 09

casing being removed

Page 24: Excav & Deep Foundations Fall 09

Driven Piles

Two basic types of Piles

End bearing pile - point loading

Friction pile - load transferred by friction resistance between the pile and the earth

Page 25: Excav & Deep Foundations Fall 09

Pile material

Steel; H- piles, Steel pipeConcrete; Site cast or PrecastWood; TimberComposite

Page 26: Excav & Deep Foundations Fall 09

Pile Driver

Massive Rig - Crane w/Leads (Guide Rails)

Logistics and Sequence Considerations (Level Site)

Noise , Vibration

Single Acting - Lift and Drop

Double Acting - Steam, Compressed Air or Hydraulics, Diesel

Page 27: Excav & Deep Foundations Fall 09
Page 28: Excav & Deep Foundations Fall 09
Page 29: Excav & Deep Foundations Fall 09
Page 30: Excav & Deep Foundations Fall 09

Pile Caps

Page 31: Excav & Deep Foundations Fall 09

Site Cast Concrete Piles

Cased Piles Uncased Piles

Page 32: Excav & Deep Foundations Fall 09

Deep Foundations

Units of MeasureDrilling & Driving

#, Lineal foot, & Size

Major Productivity IssuesType of Material (Soil)Material & Equipment

AccessQuantity (Total & # per

cap/cluster)

Page 33: Excav & Deep Foundations Fall 09

Differential Settlement

Page 34: Excav & Deep Foundations Fall 09
Page 35: Excav & Deep Foundations Fall 09
Page 36: Excav & Deep Foundations Fall 09

shallow foundation with perimeter spread footing

Page 37: Excav & Deep Foundations Fall 09

Soils

What Architects & Engineers look for:

• Structural Properties

• Particle Size

• Drainage / Water Retention

• Cohesiveness

Page 38: Excav & Deep Foundations Fall 09

ClaysPorous(sandy)

Page 39: Excav & Deep Foundations Fall 09

Soil Distribution

Rarely one type - often a Mixture and/or Different Strata

Distribution of soil type and Particle Size Important in Predicting:Load Bearing CapacitySoil StabilityDrainage Characteristics

Page 40: Excav & Deep Foundations Fall 09

Loadbearing Capacity

Page 41: Excav & Deep Foundations Fall 09

Soil Borings / Penetration Tests

Common on projects with high loadings

Bearing Capacity - # Blows/Unit (ft)

Soil Strata & Water Table Data

Soil Samples & Testing

Sample Holes Strategically Located

Information used to prepare Soils Report

Page 42: Excav & Deep Foundations Fall 09

Foundation Design & Building Codes

Sample IBC Provisions Maximum loadbearing values for

soil types Design criteriaSoil investigation & testing

requirementsMinimum foundation dimensions

Purpose: to ensure an adequate building foundation system.

Page 43: Excav & Deep Foundations Fall 09

Test boring equipment

Page 44: Excav & Deep Foundations Fall 09

Rocks & Soil

RocksMineral particles are firmly bonded

togetherLocated beneath layer(s) of soil

SoilUnconsolidated mineral particles or

conglomerates located at the top layer of the earth’s crust

Most foundations are supported on soil, except when the soil strength is not adequate

Page 45: Excav & Deep Foundations Fall 09

Soil classification

Particle size Coarse grained (gravel & sand) Fine grained (silt & clay)

Particle shape Spherical or ellipsoidal, shaped by mechanical

weathering Gravel, sand & silt

Flat, plate-like, large surface area to volume ratio Behavior influenced by electrostatic forces and

presence of waterCohesion Cohesive soils are fine grained and particles are

attracted to each other in the presence of water. Non-cohesive soils are course grained and are not

attracted to each otherOrganic soils consist of fully or partially decayed plant

matter, compressive and unsuitable for foundations

Page 46: Excav & Deep Foundations Fall 09

Soil characteristics by particle size

Page 47: Excav & Deep Foundations Fall 09

Soil properties &

Foundation design• Engineering properties

• Soil bearing capacity• Particle size distribution

• Stability & drainage• Nature of excavation• Depth of water table

• Drainage and dewatering• Compressivity

• Foundation settlement

Page 48: Excav & Deep Foundations Fall 09

Soil sampling and testing

Soil samplingTest pit methodTest boring method

Also allows for standard penetration test on site

Laboratory testingSieve analysis

Determines particle size distribution Soil classification

Moisture contentDry densityLiquid limit, plastic limitCompressive strengthShear strength

Page 49: Excav & Deep Foundations Fall 09

Test boring log

Page 50: Excav & Deep Foundations Fall 09

Earthwork

Units of MeasureExcavation & Backfill Cubic

Yards (CY)Grading Sq. Ft. or Sq. Yd.

Major Productivity Issues

Type of Operation (Mass to Ltd./Confined))

Type of Material (Soil)Material TransportationExpected Environmental

Conditions

Page 51: Excav & Deep Foundations Fall 09

Slope SupportDeep Excavations

Types of Site Conditions

Unrestricted Site – area sufficiently larger that the building footprint

Restricted Site – area constricted / limited

Page 52: Excav & Deep Foundations Fall 09

Unrestricted Site

Bench and/or Angle of Repose

Must have perimeter clearance

ConsiderationsBank ErosionWater DiversionSafetyStorage of Backfill (& cost)

Most likely - least expensive

Page 53: Excav & Deep Foundations Fall 09

Sloped Excavation@ the ‘Angle of Repose’

Page 54: Excav & Deep Foundations Fall 09

Benched Excavation

Page 55: Excav & Deep Foundations Fall 09

Excavation in Clay(A Cohesive Soil)

Page 56: Excav & Deep Foundations Fall 09

Restricted Site

Types of Sheeting

Soldier Beams and Lagging

Sheet PilingWoodSteel Precast

Slurry Wall

Page 57: Excav & Deep Foundations Fall 09

Supports for deep excavations

Sheet pilesInterlocking vertical steel

sheets driven into soil prior to excavation

Lower part of sheet remains buried, providing cantilever

Deep excavations braced (> 15 ft.)

BracingCross-bracingDiagonal bracingTieback

Page 58: Excav & Deep Foundations Fall 09

Profile of steel sheet piles

Page 59: Excav & Deep Foundations Fall 09

Sheet piles driven into soil with diesel hammer

Page 60: Excav & Deep Foundations Fall 09

Drilling for tiebacks

Page 61: Excav & Deep Foundations Fall 09

Close-up: drilling for tiebacks

Page 62: Excav & Deep Foundations Fall 09

Tieback hole

Page 63: Excav & Deep Foundations Fall 09

Tendon as tieback

Page 64: Excav & Deep Foundations Fall 09

Connection of lagging to soldier piles

Page 65: Excav & Deep Foundations Fall 09

Plan: contiguous bored piles

Page 66: Excav & Deep Foundations Fall 09

Contiguous bored piles support deep urban excavation

Page 67: Excav & Deep Foundations Fall 09

Secant piles

Page 68: Excav & Deep Foundations Fall 09

Reinforced concrete wall using bentonite slurry

Page 69: Excav & Deep Foundations Fall 09

Section: soil nailed excavation support

Page 70: Excav & Deep Foundations Fall 09

View of soil nailed excavation

Page 71: Excav & Deep Foundations Fall 09

Solder Beam & Lagging

Page 72: Excav & Deep Foundations Fall 09

with tiebacks

Page 73: Excav & Deep Foundations Fall 09

Sheet Pile Options

Page 74: Excav & Deep Foundations Fall 09

Steel Sheeting

Page 75: Excav & Deep Foundations Fall 09

Steel Sheeting Interlock

Page 76: Excav & Deep Foundations Fall 09

Slurry Wall

StepsLayout

Excavate the soil

Interject Slurry to

prevent Collapse as

Excavation Continues

Install Reinforcing

Place Concrete

(replaces the slurry mix)

Page 77: Excav & Deep Foundations Fall 09

Restricted Site

Sheeting Support

Unbraced - CantileveredBraced

Crosslot BracingRackers and Heel BlocksTiebacks

Page 78: Excav & Deep Foundations Fall 09

Bracing

Crosslot

Rackers

Tiebacks

Page 79: Excav & Deep Foundations Fall 09

Crosslot Bracing

Page 80: Excav & Deep Foundations Fall 09

Tieback Installation

Rotary Drill Hole

Insert & Grout Tendons

Tendons Stressed & Anchored

Page 81: Excav & Deep Foundations Fall 09
Page 82: Excav & Deep Foundations Fall 09

Dewatering

A process of removing Water and/or lowering the Water Table within a construction site

Purpose: To Provide a Dry working platform - (typically required by Code and Specification)

If the Water Table is above the working platform;Options:

Keep water out Let water in & remove it Combination

Page 83: Excav & Deep Foundations Fall 09

Sump Pumps

Sump Pump ConsiderationsPump(s) Placed in Low points

Water collected & Pumped Out

Requires clearance around

excavation

Most Common

Often - Least expensive

Page 84: Excav & Deep Foundations Fall 09

Well Points

Keeping water out of the excavation by

Lowering the water table

Page 85: Excav & Deep Foundations Fall 09

Suction Pumps

Discharge Line

Well Point

Header Pipe

Page 86: Excav & Deep Foundations Fall 09

Watertight Barrier Walls

Keep Water OutBarrier must reach an impervious strataTypesSlurry WallsSheeting w/

pumpsMust resist hydrostatic pressure

Page 87: Excav & Deep Foundations Fall 09

Major Building Parts

Superstructure

Substructure

Foundation

Page 88: Excav & Deep Foundations Fall 09

Seismic Base Isolation

Page 89: Excav & Deep Foundations Fall 09

Underpinning

a process of strengthening and/or stabilizing the foundation of an existing building

Reasons it may be requiredFailure of existing foundationChange in building useNew construction adjacent to

existing

Page 90: Excav & Deep Foundations Fall 09

Underpinning Methods and Problems

MethodsEnlarge existing foundationInstall a new foundationStabilize surrounding soil

Problems/ConcernsDangerousTemporary support and existing

conditionsLimited work space, slow process,

expensive

Page 91: Excav & Deep Foundations Fall 09

Retaining walls Design Elements to Prevent

Failure

Relieve H2O pressureCrushed stone Weeps

OverturningCantilevered

FootingReinforcing

SlidingKey

Page 92: Excav & Deep Foundations Fall 09

Waterproofing

Two basic approaches to WaterproofingWaterproof Membranes, orDrainageGenerally - both used in tandem

Page 93: Excav & Deep Foundations Fall 09

Waterproofing Membranes

MaterialsLiquid or Sheet (Plastic, asphaltic,

synthetic rubber)Coatings (asphaltic)Cementitious Plasters & admixturesBentonite clay

AccessoriesProtection BoardWaterstop

Unit of Measure - SF, Mils (thickness)

Page 94: Excav & Deep Foundations Fall 09
Page 95: Excav & Deep Foundations Fall 09
Page 96: Excav & Deep Foundations Fall 09

DampproofingTypically, a liquid asphalt

applied with a roller or sprayer

Not an effective barrier for water under pressure.BUT, will prevent ground

‘moisture’ from migrating through a wall.

Typically used in conjunction will drainage pipe.

Page 97: Excav & Deep Foundations Fall 09

Site preparation prior to construction

Fencing site

Locate and mark utility lines

Demolish unneeded structures and utility lines

Remove trees, brush, topsoil

Page 98: Excav & Deep Foundations Fall 09

ExcavationThe process of removing soil or rock from its original location in preparation for construction

Depth of excavation depends on Foundation type (deep or shallow)Soil type

Types of excavationsOpen. Large and sometimes deep

excavationsTrenches. Linear excavations for

utilities or footingsPits. Excavations for footing of one

column, elevator shaft, etc.

Page 99: Excav & Deep Foundations Fall 09

Controlling groundwater

Prevent surface water from entering excavation

Draining soil around the foundationSumpsWell points

Page 100: Excav & Deep Foundations Fall 09

Sumps collect and pumps discharge groundwater after it

enters the excavation

Page 101: Excav & Deep Foundations Fall 09

Wellpont system prevents water from entering

excavation

Page 102: Excav & Deep Foundations Fall 09

Footing types

Page 103: Excav & Deep Foundations Fall 09

Presumptive allowable bearing capacity of soils

Class of Material Allowable bearing capacity

Crystalline bedrock 12.0 ksf

Sedimentary and foliated rock 4.0 ksf

Soil types GW and GP 3.0 ksf

Soil types SW, SP, SM, SC, GM, & GC

2.0 ksf

Soil types CL, ML, MH, and CH

1.5 ksf

Page 104: Excav & Deep Foundations Fall 09

Commonly used deep foundations

Page 105: Excav & Deep Foundations Fall 09

Grade beam and drilled piers

Page 106: Excav & Deep Foundations Fall 09

Formwork: Grade beam and drilled piers

Page 107: Excav & Deep Foundations Fall 09

Grade beam and drilled piers

Page 108: Excav & Deep Foundations Fall 09

Wood light frame on grade beam and drilled piers

Page 109: Excav & Deep Foundations Fall 09

Structural slab on drilled pier, note void boxes below slab

Page 110: Excav & Deep Foundations Fall 09

Grade beams and under slab utilities in place

Page 111: Excav & Deep Foundations Fall 09

Void boxes being placed prior to constructing structural slab

Page 112: Excav & Deep Foundations Fall 09

Interior of structural slab on ground supported on pier caps

Page 113: Excav & Deep Foundations Fall 09

Below grade waterproofing

Prevent water from reaching foundationDirect surface run-off away

from building

Waterproof below grade structureApply waterproof layerIncorporate a foundation

drainage system

Page 114: Excav & Deep Foundations Fall 09

Waterproofing layer

Applied to outside surface ofbasement wall basement floor

Cold systems most commonly used todayRubberized asphalt or

thermoplastic sheets60 mil thick, self-adhering rolls

Liquid applied elastomeric compoundsSprayed on or rolled

Page 115: Excav & Deep Foundations Fall 09

Drainage system

Purpose of system is to collect, drain and discharge subsoil water away from buildingSystem includes Drainage mats

Placed against the waterproofing or insulation layer

Open structure allows water to drain downward Reduce or eliminate water pressure on below

grade wall Protect waterproofing

Foundation drain pipe sloped to carry water away from foundation to storm drain or sump pit

4 in to 6 in perforated pipe at base of foundation Laid in bed of crushed rock Protected by filter fabric that prevents clogging

from soil

Page 116: Excav & Deep Foundations Fall 09

Typical foundation waterproofing and drainage

system for subgrade wall

Page 117: Excav & Deep Foundations Fall 09

Positive-side, negative-side and blind-side

waterproofing

Positive-side added to exterior wall Most effective and commonly used Protects wall against water seepage, mold growth,

corrosion Backfilled after completion

Negative-side applied to interior side of wall Used in remedial applications, not as effective as

other optionsBlind-side is applied to the outside of a wall that becomes inaccessible after construction Structural wall placed directly against excavation

support system that acts as formwork. Applied directly to excavation support system

Page 118: Excav & Deep Foundations Fall 09

Blind-side waterproofing

Page 119: Excav & Deep Foundations Fall 09

Constructing a basement foundation using blind-side

waterproofing

Page 120: Excav & Deep Foundations Fall 09

Reinforcement placed in preparation for interior

formwork.

Page 121: Excav & Deep Foundations Fall 09

Symbols used is USCS

G Gravel

S Sand

M Silt

C Clay

Pt Peat

O Organic

W Well-graded

P Poorly-graded

L Low plasticity

H High plasticity

Page 122: Excav & Deep Foundations Fall 09

Increasing moisture content in fine-grained soil

Page 123: Excav & Deep Foundations Fall 09

Definitions

Plastic limit (PL)- moisture content at which soil becomes plastic (putty-like)

Liquid limit (LL)- moisture content at which soil becomes liquid (slurry)

Plasticity index (PI) - difference between Liquid limit and Plastic limit

LL - PL = PI

Page 124: Excav & Deep Foundations Fall 09
Page 125: Excav & Deep Foundations Fall 09
Page 126: Excav & Deep Foundations Fall 09

Combination Spread & Strip Footing