12 March 2008 1New Tasks, New Tools
European Grid Development, Market Development and Renewable Energy
International Energy Conference
Copenhagen, 12 March 2008
Peter Jørgensen
Vice President, Planning
12 March 2008 2New Tasks, New Tools
Agenda
Third Package - Infrastructure Development
Unique Role of TSO’s
From National to Regional and European Planning
From Planning to Investment Decisions – Incentives and Criteria’s
Public Authorization Procedures
12 March 2008 3New Tasks, New Tools
Third Liberalization Package - infrastructure development
Unbundling
Avoid distorted investment incentives within integrated companies
Strong national regulators
Review investment plans of TSOs
Monitor network security and reliability
ACER – Agency for the Cooperation of Energy Regulators
Perform regulatory oversight of ENTSO – 10-year investment plans
Decide on regulatory regime applicable to infrastructure
ENTSO – European Network of Transmission System Operators
Identify, manage and finance research and innovation
Coordinate grid operation according to agreed codes
Perform investment planning – coordinated long term planning
Prepare system adequacy forecasts for summer, winter and long term
12 March 2008 4New Tasks, New Tools
Responsibility of TSO’s- from long term planning to real-time operation and settlement
Market operation and settlement
System operation
Building and maintenance of infrastructure
Planning and R&D
-25 year -1 year -1 month -1 week -1 day Real-time
Operation
Unique strength of TSOs to embrace the full responsibility!
12 March 2008 5New Tasks, New Tools
From National to Regional Planning- the Nordel example
3 Nordic Grid Master Plans in last 10 years
Reinforcements in 5 prioritized cross sections proposed in 2004
Comprehensive analysis based on common data and models
4 projects decided – 1 pending
Sweden
Finland
Denmark
NetherlandsGermany
Poland
Norway
Balticum
Great Britain
Sweden
Finland
Denmark
NetherlandsGermany
Poland
Norway
Balticum
Great Britain
23
7
8
2625
20
221921
12
17
17
18
17
9
10
15
2
3
13
14
27
6
5
16
14
1128
3031
2423
7
8
2625
20
221921
12
17
17
18
17
9
10
15
2
3
13
14
27
6
5
16
14
1128
3031
24
Nordic Grid Master Plan 2008
Nordel Scenarios for 2015 and 2025
Proposals for internal and external reinforcements
12 March 2008 6New Tasks, New Tools
Nordic Grid Master Plan
Market functioning
Price formation in the integrated NordPool spot market – statistics and modeling
Security of supply
power and energy balances – statistics and modeling
margins to market failure and system failure – statistics and modeling
12 March 2008 7New Tasks, New Tools
Nordic Grid Master Plan
Reinforcements
Internal and external reinforcements analyzed
Reinforcement of external Nordic interconnections in general shows a positive cost-benefit
Investments
Level for infrastructure investments will be tripled
12 March 2008 8New Tasks, New Tools
Danish Grid Development
Major reinforcements will be triggered by international power market and off-shore wind
Urgent need for:
New guidelines on the use of overhead lines/underground cables
Efficient and faster public authorisation procedures
Gørløsegård
Bjæverskov
Hovegård
Fraugde
Kassø
Endrup
Idomlund
Askær
Ferslev
Tjele
Trige
Vester Hassing
LanderupgårdHerslev
Konti-SkanKS 1&2
NorgeSweden
Germany
Sweden
Germany
Kontek
Kingstrup
Tjele
Rødsand
Ishøj
Glentegård
København
OVerloaded connectionsOverload > 150 %Overload > 125 <= 150 %Overload <= 125 %
Alternative 1
StorebæltSB 1&2
SkagerrakSK 1&2SK 3&4
12 March 2008 9New Tasks, New Tools
Detected Bottlenecks during n-1 conditions of UCTE Detected Bottlenecks during n-1 conditions of UCTE “Scenario North”“Scenario North”
DPL
P. E
F
DK2
H
SKCZ
ACH.
NL.
B.
SI
...
.
..
HR
BiH
FYROM
. FRY.
AL.
GR.
BG
.
RO
(UA)..
DE
PL
PTES
FR
DK
HU
SK
CZ
ATCH
NL
BE
SI HR
BA CS
.GR
BG
RO
(UA)
IT
MKAL
DPL
P. E
F
DK2
H
SKCZ
ACH.
NL.
B.
SI
...
.
..
HR
BiH
FYROM
. FRY.
AL.
GR.
BG
.
RO
(UA)..
DE
PL
PTES
FR
DK
HU
SK
CZ
ATCH
NL
BE
SI HR
BA CS
.GR
BG
RO
(UA)
IT
MKAL
(NORDEL)
TIE-LINES
INTERNAL ELEMENTS
source: EWIS study
Obvious need for planning and investment decisions on European level!
12 March 2008 10New Tasks, New Tools
From planning to investment decisions - incentives and criteria’s for investment decisions
New interconnector capacity may cause considerable redistribution of wealth compared to the net socio-economic benefit - distributed in several countries!
Gen Con Cap Net
Regulation, allocation of congestion rents & compensation mechanisms must support socio-economic optimal investments on regional/European level!
Optimal interconnector capacity differs significantly between private and socio-economic welfare criteria’s
12 March 2008 11New Tasks, New Tools
SummarySome basic prerequisites for the timely development of infrastructure to support a well-functioning European electricity market, security of supply and massive integration of RES are:
Efficient TSO-cooperation on European and regional level
coordinated and qualified planning procedures and investment decisions
Strong national and European regulation
investment criteria’s based on socio-economic welfare
incentives for investments supporting goals on regional and European level
Politically supported guidelines for new infrastructure
Efficient public authorization procedures