EUROPEAN CARBON CAPTURE & STORAGE Accelerating the successful deployment of CCS in Europe 31 January 2013 Allan Baker Managing Director - Global Head of Power Advisory & PF Tel.: 44 (0) 20 7762 4821 Mob: 44 (0) 7870258164 [email protected]

Transcript of EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the...

Page 1: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

EUROPEAN CARBON CAPTURE & STORAGE

Accelerating the successful deployment of CCS in Europe

31 January 2013

Allan Baker Managing Director - Global Head of Power Advisory & PF Tel.: 44 (0) 20 7762 4821 Mob: 44 (0) 7870258164 [email protected]

Page 2: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

2 31/01/2013

The contents of this document are given for purely indicative purposes and have no contractual value.

Any views, opinions or conclusions contained in this document are indicative only, are not based on independent research and do not represent any commitment from Société Générale. This document does not constitute an offer, a solicitation, an invitation to make an offer, advice or a recommendation from Société Générale to purchase or sell a product or to enter into a transaction or provide investment services. The market information displayed in this document is based on data at a given moment and may change from time to time and Société Générale will not notify the recipient of any such amendment or change. The accuracy, completeness or relevance of the information which has been drawn from external sources is not guaranteed although it is drawn from sources reasonably believed to be reliable. No responsibility or liability (express or implied) is accepted for any errors, omissions or misstatements by Société Générale except in the case of fraud or any other liability which cannot lawfully be excluded.

The commercial merits or suitability or expected profitability or benefit of any investment services described in this document to the recipient's particular situation should be independently determined by the recipient. Any such determination should involve an assessment of the legal, tax, accounting, regulatory, financial, credit and other related aspects of any such transaction, based on such information and advice from the recipient's own advisers and such other experts as the recipient deems relevant. Société Générale shall not be liable for any failure by the recipient to obtain such information and advice.

This document is to be treated in the strictest confidence and is not to be disclosed directly or indirectly to any third party. It is not to be reproduced in whole or in part, nor used for any purpose except as expressly authorised by Société Générale.

This document is issued in the U.K. by the London Branch of Société Générale. Société Générale is a French credit institution (bank) authorised by the Autorité de Contrôle Prudentiel (the French Prudential Control Authority). Société Générale is subject to limited regulation by the Financial Services Authority in the U.K. Details of the extent of our regulation by the Financial Services Authority are available from us on request.

Page 3: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

3 31/01/2013

THE CCS COST REDUCTION TASK FORCE ......

UK Government initiative: ● Established in March 2012 by DECC as “an industry-led joint task force

established by Government to assist with the challenge of making CCS commercially available for operation by the early 2020s.”

● Chaired by Geoff Chapman (CCSA), project managed by the Crown Estate ● Analytical and other support from Poyry

● Broadly representative of the stakeholders in CCS and international - 23

members drawn from industry, trade associations, developers, finance and academia

“The objective of the Task Force is to publish a report to advise Government and industry on reducing the cost of CCS so that projects are financeable and competitive with other low carbon technologies in the early 2020s.”

Page 4: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

4 31/01/2013

TASK FORCE METHODOLOGY ......

Identification of three key areas of potential cost reduction: ● Planning & Infrastructure (Mike Saunders / Alastair Rennie) ● Commercial & Financial ( Allan Baker) ● Generation & Capture (Leigh Hackett / Tom Stringer)

Consultation: ● Work stream work shops ● Questionnaire – cost reduction opportunities & impact ● One-to-one interviews with stake holders

Modelling & Analysis – led by Poyry: ● Review of existing analysis in the public domain ● Challenge of assumptions ● Analysis

The report: ● is a representation of the Task Force members view of the opportunities for cost

reduction in CCS ● is not a list of government or other stakeholder actions or a detailed model /

representation of CCS project costs

Page 5: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

5 31/01/2013

THE IMPORTANCE OF COST REDUCTION ......

The role of CCS in the UK generation mix is crucial to the low carbon strategy of the UK ● Decarbonisation of generation needs CCS

● CCS facilitates Nuclear and intermittent renewable development

CCS Commercialisation and the support mechanisms now in place can kick start the development of commercial CCS ● Commercialisation grant

● Feed-in Tariff /Contracts for Difference

● Emissions Performance Standard

UK poised take a leading role (again !)

Cost reduction is the essential step from FOAK to Nth-of-a-kind ● CCS has to be cost competitive to deliver potential

● Desired outcome should be operational plants and a clear cost reduction trajectory

● “No regrets strategy” – planning for success

Source: Department of Energy and Climate Change

Page 6: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

6 31/01/2013

KEY CONCLUSIONS FROM THE INITIAL REPORT ......

Need for a supportive regulatory landscape:

Commercialisation program provides an

opportunity to resolve many of these issues and create a template for future

industry development

Within this environment tangible cost savings can come from: ● Planning & infrastructure developments

● Generation & capture technology development

● Evolution of commercial and financing arrangements

Deliverability is not the responsibility of government alone Development of CCS requires constructive full engagement of all stakeholders

Page 7: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

7 31/01/2013

PLANNING AND INFRASTRUCTURE DEVELOPMENT ......

Achieving optimal scale in CO2 storage

● Storage reservoir development represents a significant part of CO2 storage cost ● Expensive process so benefit on focussing on “high volume” opportunities ● Substantial risk (cost) reduction from storage clusters

Essentially a volume business – higher volume = lower per unit cost

Optimisation of transport infrastructure

● Cost of increasing a pipe size grows at a slower rate than the volume transported – lower per unit transport cost

● Trunk lines and local feeder pipes from a hub provide volume benefits over early point to point ● Distance matters – shorter less complex routes have obvious cost benefits

Planning and investing for future projects in the first projects could lead to significant reductions in per unit of CO2 stored in follow on-projects

Page 8: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

8 31/01/2013

GENERATION AND CAPTURE TECHNOLOGY DEVELOPMENT ......

Early plants unlikely to be optimal – optimising would improve per unit: ● Capital equipment costs ● Capture operating costs ● Energy penalties

Benefit of experience ● Reduced redundancy in design and execution

● Process optimisation

● Better integration

● Piggy-backing on commercial, regulatory, planning and other existing knowledge

Page 9: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

9 31/01/2013

ACHIEVING AFFORDABLE FINANCING ......

Appropriate risk allocation across the full chain – never easy in a new industry !

● Complex mix of disciplines and “cross border” risks and liabilities ● Appropriate allocation on FOAK is unlikely to be the allocation for the Nth-of-a-kind : improvement

with experience

Role of Government, developers, insurance industry and finance being defined

● Real time risk allocation discussion under way – Commercialisation Competition ● We don’t know what we don’t know – pragmatic approach from all stakeholders

Continued engagement with finance and insurance industry crucial

● Genuine interest now – momentum needs to be retained High cost of capital in early projects offers scope for material cost reductions if a

replicable template emerges from the Commercialisation competition

Page 10: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

10 31/01/2013

POTENTIAL DELIVERABLE COST REDUCTIONS ......

Page 11: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

11 31/01/2013

POTENTIAL DELIVERABLE COST REDUCTIONS ......

Page 12: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

12 31/01/2013

CONCLUSIONS .......

A cost of generation with CCS at or below £100/MWh is achievable by the 2020s

This is confirmation that CCS is comparable with traditional renewables – even more so when it’s ability to back up intermittency is taken into account

Clear that the industry needs to capitalise on the Commercialisation competition but to realise the full potential a credible long term commitment is required by all stakeholders

Cost savings will only come from multiple operating full chain projects with a well conceived transport and storage solution

Challenge is to look beyond the Commercialisation phase

and plan for success

Page 13: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

13 31/01/2013

ADDITIONAL INFORMATION .......

Information relating to the CCS Cost Reduction Task Force is available on the DECC web site

The Final Report of the Task Force will be delivered to the Minister in Spring 2013

A number of “Candidate Actions” have been identified by the Task Force and these will be taken forward

Page 14: EUROPEAN CARBON CAPTURE & STORAGE - … CARBON CAPTURE & STORAGE ... This document is issued in the U.K. by the London Branch of Société ... commercially available for operation

14 31/01/2013

SOCIETE GENERALE AND CCS .......

Leading Financial institution in the CCS sector:

Financial Advisor to one of the short-listed commercialisation projects

Financial Advisor to Abu Dhabi “full chain” CCS (Masdar) project

Financial Advisor to Powerfuel IGCC, UK

Financing Feasibility study for Hydrogen Energy California

EEPR guarantee facility for the 2Co Don Valley CCS project

Member of the UK Government CCS Forum

CCS Cost Reduction Task Force Member