ETSAP Annex IX Technical Conference Energy Models … Import , wet shoulder IMP-IN Import, dry...
Transcript of ETSAP Annex IX Technical Conference Energy Models … Import , wet shoulder IMP-IN Import, dry...
Heng KunleangDeputy Director
Energy Development DepartmentMinistry of Industry, Mines and Energy
Taipei, April 4-7, 2005
ETSAP Annex IX Technical ConferenceEnergy Models Users’ Group, Global and
Regional Energy Modelling
Analysis of Power Supply Options for the Interconnected Grid
Country Profile of Energy Sector• Territory: 181,035 sq. km • Borders: THL-West, VN-East, LAO PDR-North,
Gulf-south• Population: 12 million• GDP US$ 280 per capita
• Lowest energy consumption : 45 kWh/capita• Highest electricity price in the region• High potential of hydroelectricity:
10,000 MW in northern and 1,000 MW in WesternLong distance between sources and load center: Difficult to developed
Country Profile of Power Sector (continued)
• Main Energy consumption: Wood• Electrification rate:
– Connect to the grid: 15%• Urban: 53.6%, Rural: 8.6%• Tariff: US¢ 9 – 25 per kWh
– Rural generation and battery: 35%• Tariff: US¢ 40 – 80 per kWh
• Principal generation Fuel Oil (DO and HFO)• Main consumption sector: Household
Installed electricity capacity in 2000, MW
Medium Speed Diesel
34%
High Speed Diesel
27%
Steam13%
Hydro1%
Low Speed Diesel
25%
Average Daily Load Curve by Month
30
40
50
60
70
80
90
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
January February March April May June July August September October November December
Source: EDC 2004
Current Structure of Electricity Sector
Cambodia's Electricity BusinessEDCPEU PECIPP
Ownership of EDCPolicy; Planning; Development; Technical standardTariff, license, Review the Planned Investments,finances and performance; Enforce the regulations, rules and standards
Royal Government of Cambodia
Ministry of Industry, Mines and Energy
Ministry of Economic and Finance
OwnerPolicy maker
Electricity Authority of Cambodia
Regulation
To provide an adequate supply of energy throughout Cambodia at reasonable and affordable price,
To ensure a reliable and secured electricity supply at reasonable prices, which facilitates the investments in Cambodia and developments of the national economy,
To encourage exploration and environmentally and socially acceptable development of energy resources needed for supply to all sectors of Cambodia economy,
To encourage the efficient use of energy and to minimize the detrimental environmental effects resulted from energy supply and consumption.
Power Sector Policy
Cambodian Power Development Plan (2004-2008)
Promoting Private sector Participation in these development is needed
• 2004: Commissioning 10 MW HFO in Siem Reap (Japanese Grant Aid).• 2005: Develop an IPP-KEP of 32 MW• Import from Thailand for North-Western Grid• 2006: Expect to add 10 MW HFO (Japanese Grant Aid).
• 2007: Import from Vietnam 80 MW for the first step from Thailand 20 MW
• 2008: Commissiong of Kirirom III 13 MW Hydropower Plant
Representation of electricity system
Grid interconnection
Grid expansion to rural areas
HV imports/exports
MV imports
Phnom Penh
North-westNorth-east
South-west
Rural areas Rural areas
Rural areas
Rural areas
Vietnam
Vietnam
Thailand
Electricity Demand Forecast - GWh
0
2000
4000
6000
8000
10000
12000
14000
16000
2000 2005 2010 2015 2020 2025 2030 2035
Year
North West (isolated) North East (isolated)South West (isolated) Phnom Penh (isolated)interconnected system
Seasonal and Diurnal Time Definitions
08:0000:00OctoberMayOff peak - WetW-N
22:0018:00OctoberMayPeak - WetW-D
08:0000:00AprilNovemberOff peak - DryS-N
22:0018:00AprilNovemberPeak - DryS-D
00:0022:00
18:0008:00AprilNovemberPartial peak - DryI-N
00:0022:00
18:0008:00OctoberMayPartial peak - WetI-D
ToFrom ToFrom
TimeSeasonDescriptionTime
Slice
MARKAL Representation of the Electricity System
Thailand
Vietnam Transmission Electricity
Distribution Electricity
InterconnectedConsumer Electricity
Transmission Grid
Distribution Grid
Interconnected Consumer Demand
HV Generation
MV Generation
On-Grid Rural
Demand
Rural Supply Options
North West Electricity
North WestDemand
North EastDemand
South WestDemand
Phnom PenhDemand
North East Electricity
South West Electricity
Phnom Penh Electricity
Off-Grid Rural
Demand
Rural Supply Options
North East Generation (isolated)
North West Generation (isolated)
South West Generation (isolated)
Phnom Penh
Generation (isolated)
LV Generation
Laos
MARKAL Modelling of Electricity TradeEXP-ID Export , wet shoulderEXP-IN Export, dry shoulder
HV HYDRO EXP-SD Export, dry peakGEN EXP-SN Export, dry off-peak
EXP-WD Export, wet peakEXP-WN Export, wet off-peak
IMP-ID Import , wet shoulderIMP-IN Import, dry shoulderIMP-SD Import, dry peakIMP-SN Import, dry off-peakIMP-WD Import, wet peakIMP-WN Import, wet off-peak
MV GEN LV GEN
HV THERMALGEN
ILC ILCL
Constraint Constraint FIXG FIXT
EDGRID ECGRID DEMAND
IDSITS
ELINKE
ELINKI
ETGRID
ELINKH
Thermal Installed Capacity (MW) - Case - BASE - Base data - Crude 40$/bbl - No trade
0
500
1000
1500
2000
2500
2000 2005 2010 2015 2020 2025 2030 2035
Middle speed diesel (fuel oil) Private diesel Low speed diesel (Fuel oil)Middle speed diesel (diesel) Oil steam (Phnom Penh) New oil steam (Sihanoukville)OCGT (diesel) HV High speed diesel OCGT (diesel) MVCCGT (gas) CCGT (Dsl) OCGT (gas) HVOCGT (gas) MV
Hydro Installed Capacity (MW) - Case - BASE - Base data - Crude 40$/bbl - No trade
0200400600800
100012001400160018002000
2000 2005 2010 2015 2020 2025 2030 2035Kirirom hydro Stung Atay hydro Sambor hydro (storage) Lower Russey Chrum hydro
Lower Sre Pok 2 hydro Battambang 1 hydro Battambang 2 hydro Upper Russey Chrum hydro
Lower Sesan 2 hydro Kamchay hydro Battambang 3 hydro Middle Russey Chrum hydro
Stung Cheay Areng hydro Stung Metoeuk hydro Stung Tatay Sambor hydro (run of river)
Capacity Balance (MW) - Case - BASE - Base data - Crude 40$/bbl - No trade
0
500
1000
1500
2000
2500
3000
3500
4000
2000 2005 2010 2015 2020 2025 2030 2035
Thermal Hydro Import Peak Demand
Long Run Marginal Costs at Consumer LevelConsumer LRMC contributions by time slice (Usc/kWh) - Case - BASE - Base data - Crude
40$/bbl - No trade
0.00
2.00
4.00
6.00
8.00
10.00
12.00
2000 2005 2010 2015 2020 2025 2030 2035
Dry Peak Dry Shoulder Dry Off-peak Wet Peak Wet Shoulder Wet Off-peak
Electricity Imports by Time Slice (GWh) - Case - IN50 - Electricity import w ith no capacity credit
0
500
1000
1500
2000
2500
2000 2005 2010 2015 2020 2025 2030 2035Dry Peak Dry Shoulder Dry Off-peakWet Peak Wet Shoulder Wet Off-peak
Electricity Import Capacity (MW) - Case - IN50 - Electricity import w ith no capacity credit
050
100150200250300350400450500
2000 2005 2010 2015 2020 2025 2030 2035Import Maximum
Import Energy and Capacity Contributions
Hydro Installed Capacity (MW) - Case - X87 - Export energy 87%
0
1000
2000
3000
4000
5000
6000
2000 2005 2010 2015 2020 2025 2030 2035Kirirom hydro Stung Atay hydro Sambor hydro (storage) Battambang 2 hydro
Sambor hydro (run of river) Middle Russey Chrum hydro Lower Russey Chrum hydro Lower Sre Pok 2 hydro
Battambang 1 hydro Upper Russey Chrum hydro Stung Cheay Areng hydro Lower Sesan 2 hydro
Kamchay hydro Battambang 3 hydro Stung Metoeuk hydro Stung Tatay
Hydro Development Scenario for Optimum Exports
CONCLUSIONS
1. System expansion Using Existing Supply Options• Cambodia has the highest electricity generation cost in the region
• There is a substantial potential for developing local hydro, to operate in conjunction with the thermals. The hydro production is seen to be extremely seasonal, with the price of electricity still dictated by the HFO diesel plant in the dry season and the wet season peak. Due to this reason, even with the full flexibility of hydro development, the marginal electricity costs at consumer level is seen fall only to around 8 USc/kWh.
• The seasonality of hydro generation indicates a strong possible electricity export potential in the wet season.
CONCLUSIONS (Cont.)2. Electricity Trade Options
• Due to the strong seasonality of hydro generation, electricity imports are only viable in the dry season and exports only in the wet season.
• With the import capacity limit of 15% of total generation, for maximum imports during dry season only, the long run average incremental value of imports is about 7.8 USc/kWh with only HFO diesels providing the thermal alternative in local generation. This means that Cambodia stands to gain for any negotiated import price of less than this amount for maximum imports during the dry season from 2010.
• The long run incremental cost of electricity exports for a 3000 MW export capacity with maximum exports during the wet season only is around 1.7 USc/kWh. This means that Cambodia stands to gain for any negotiatedexport price of more than this amount for maximum exports during the wet season from 2020.