ESTIMATION 1 Lesson 4 - Excavation. Excavation Excavation is the biggest unknown element in...
-
Upload
cecil-barber -
Category
Documents
-
view
224 -
download
3
Transcript of ESTIMATION 1 Lesson 4 - Excavation. Excavation Excavation is the biggest unknown element in...
ESTIMATION 1
Lesson 4 - Excavation
Excavation
Excavation is the biggest unknown element in construction and therefore has a high risk for additional costs in terms of variations.
Estimating the cost of excavation is highly specialized and therefore this lesson will only touch on the basic understanding
Excavation
Excavation
Excavation
Ability to read plans and specifications Understanding of surveying and civil
engineering terminology Understanding of environmental and
legal requirements Ability to estimate quantities based on
m3 i.e cut and fill
Excavation
The estimate is separated into two types of quantities General quantities – work where you can
use motorised equipment such as scrapers, hoes and loaders and it is based on production rates
Special quantities – ie anything that reduces production rates and requires extra care Rock excavation Excavation around sewer pipes, existing
buildings
Excavation
Quantities in excavation are mainly m3 The cost of excavation is on labour and
equipment (cost/hour) needed to complete the work i.e It is based on the (volume) m3 of material moved
Programme of works- time is important factor and is a huge consideration for the type of equipment you are going to use
Excavation
The most expensive equipment (cost/hr) is the most productive. However the machine with the largest capacity isn't always the best to use
Good equipment selection will help reduce costs
Excavation
Considerations when estimating excavation
Desk top study
Site visit
Excavation – Desk top study
Review plans and specifications Existing utilities lines
How accurate Phone the companies to locate the lines for
you. Need to give them advanced notice Check what permits are required
Resource consent Aborist report/permits Sediment control
Excavation
Review plans and specifications Public records might give additional
information Soil conditions Water problems Abandoned utility lines
Excavation
Setting out carried out by the engineer If not cost to get the site surveyed
Under cutting Might need to remove dirt from below the
existing finishing line if in rock Underground services – may have to cut
the trench deeper for the bedding of the pipe
Excavation
• Cut and fill Consider is there enough fill on site from the
spoil heaps. If not where will you transport it from ? Is it available?? – Snapper rock subdivision Conversely will you have to transport excess fill
off site If so.. Where will you transfer it to? How much are tipping fees?
Excavation
• Top soil requirements Is there enough on site ? Can you keep it in spoil heaps on site ? Will you have to bring additional material in?
• Special excavation Rock ? Hire of specialist equipment Removal of existing structures
Excavation
• Review utility lines – Not only new lines but connection to existing
• Review drainage, new roads, parking lots and consider the base, sub bases for estimating
• Review the building/basement structure for estimating
Excavation – site visit
AccessibilityLocation of the site –
How remote ? Are the roads undeveloped or narrow ? Can you get the equipment you want on site? Bream Bay Sub division
If you are having to bring the dirt out – what is the best route to the tipping site? – Can the trucks use that route
Excavation
If the surrounding area is heavy traffic. Will you require additional traffic management ? Do you require a wheel wash facility (Kensington Park)
Noise restriction – if the site is in a built up area are there noise restrictions
Are there any bridge weight restrictions in the area which will affect what equipment you use
Excavation
Degree of Difficulty Are there steep slopes on site that
need different equipment – slopes that are steeper than 1 in 3 will need track machines which are slower.
Other considerations are buildings, trees, underground services, overhead electricity lines.
Excavation
Surface Conditions Drainage – what happens to the water
across the site. It can’t flow into the existing roads
Sediment control is important Permit/consents are required Silt ponds Sand bags Protect existing waterways
Excavation
Surface Conditions Trees
Consents are required Do you have to protect trees If they are to be removed – who will take them?
Can they be sold for firewood? Are you allowed burning on site?
Excavation
Sub surface Conditions Geotech reports
These reports are expensive. They show the soil conditions however the bore readings taken maybe limited - Ibis Hamiliton, Snow planet
If you are working below the water table level you may have to pump the water… Where is this water going to go
Excavation
Sub surface Conditions Some site have been used as fill sites… these
areas will need to be removed and new fill imported
Soft spots can be found in any excavation… make sure you either make allowances or tag it out your tender – Ibis Rotorua
Excavation
Utilities Utility lines may not be in the correct location and
if they are hit by a digger it becomes expensive Check manholes are in the right location and they
are at the correct depth and have the right no of inlets/outlets
Check overhead lines. Can you machines get under them. Get the electricity company to put sleeves on the lines or flags – Current roadworks in Remeura.
If Utilities need to be moved – check out how much and how long it will take.
Excavation
Project sizeCheck if the site is large enough to store all the equipment and spoil heaps
Traffic ControlTraffic management systems are becoming paramount – they are very expensive
Excavation
Security Check the security issues of leaving the big
machines on site. They wont take the machines but they will take the batteries !! Bream Bay
Do you need to hire security ?? Do you have to fence the site for public
safety??
Excavation
Time of year works are completed Existing and imported soils
Earthworks are carried out in the spring and summer If the weather is wet then the machines are slower,
wet and heavy soil costs more to move than dry light soils
Compaction of the soil is very important and this is affected by the moisture content.
If the soil doesn’t dry out by natural means then additives such as lime has to be used
Conversely if the soil is too dry, then water trucks have to be used
Excavation – types of machines
Excavator with back actor and front loading bucketavailable on wheels or trackCapable of trench, basement and foundation excavation. Can load spoil into trucks
Excavation
Face shovelParticularly suitable working against banks, forming cuttings and embankments
Excavation
GrabUsed to load loose material into spoil heaps
on site
Excavation
GradersLevel out deposit fill
Excavation
RollersUsed for compaction
Excavation
Compaction and bulking factors
bulking factor compaction factor
1.00 1.25 0.90
In place loose Compacted
Excavation
Bulking factors% by volume
Gravel 10%Sand 12.5%Ordinary earth 25%Clay 33%Chalk 33.3 %Rock 50%
Excavation
By hand factorsOrdinary ground has a value of 1 Type of ground multiplerSand 0.75Stiff clay 1.25Compacted gravel 1.50Soft chalk 2.50Soft rock 4.00
Excavation - calculations
Excavate to reduced levelsRequirements – excavator with a banksmanThe output of the excavator includes digging
and loading directly onto a waiting truckSay Banksman is $20.00/hrExcavator and driver is $40.00/hrHourly cost of operation – excavator $40.00
Banksman $ 20.00 TOTAL
$60.00/hr
Excavation
Excavate to reduced levels – cont’d
Output of excavator - $15m3/hr
So cost/m3 = $60.00/15 = $4.00/m3
Excavation
Excavate trenchesRequirement 90% completed by machine,
10% completed by hand. Banksman required for machine
All in hourly rate is as before - $60.00/hrAssume excavator is 9m3/hrCost for excavation = $60/9
= $6.67/m3
Excavation
Excavate trenches – cont’dHand digging – labour = $15.00/hr1 labour digs 1 m3 in 2.5 hours Cost/m3 = $15.00 x 2.5 =$37.50/m3
Total cost90% of machine cost – 90% x $6.67 = $6.0010% of hand digging – 10% x $37.50 = $3.75
TOTAL = $9.75/m3
Excavation
Disposal of waterRequirement – 2 pumps for 8 weeks of
excavationLabour – ½ a day in attendanceLabour - $15.00 /hr
Hire of a pump $150/weekCost of fuel/pump $20/week Total cost of pump $170/week
Excavation
Disposal of water – cont’dHire of pump – 2 x $170 x 8 weeks =
$2,720.00Cost of labour0.50 hour x (8 x 5) days x $15.00/hr
=$2,420.00TOTAL = $5,140.00
Excavation
Removal of excavated materialRequirement – the excavation is loaded
directly onto 10 tonne lorriesThe cost of the excavation is included in the
excavation rateFor the excavator to work efficiently, once
one truck is loaded another one comes through the gate.
Excavation
Removal of excavated material – cont’dNo of vehicles =
time taken to load + total journey time
time taken to load
Lorry and driver = $95/hrTipping fees = $ 40/load
Excavation
Removal of excavated material – cont’dWeight of earth = 1.60tonnes/m3 so a 10
tonne lorry with a full load takes 10 tonnes/1.6 = 6.5m3
Allow for bulking factor of 25%
6.5m3 = 6.5m3 x 100/125 = 5 m3
Excavation
Removal of excavated material – cont’dTime taken to load 5 m3 assume the
excavator is 9m3/hr= 5/9 = 33 minsAssume tip is 10k from siteOutward journey 15 minsTipping time 5 minsReturn journey 12 minsTotal time 32 mins
Excavation
Removal of excavated material – cont’dTherefore no of lorries needed are33 mins + 32 mins = 2 no aprox 33 mins
Cost of operation = 2 no lorries x $95/hr = $190
Excavation
Removal of excavated material – cont’dExcavator is working continously and the
quantity of excavated material removed in 1 hour is 9m3
Cost /m3 = $190/9 = $21.11/m3Tipping charge $40/loadCost/m3 = 40/5m3 = $8.00/m3Total cost/m3 = $21.11 + $8.00
= $29.11/m3
Excavation
ReferencesEstimating excavation – Deryl BurchEstimating and tendering building works –
R.C Smith