Esb Overview Deck

download Esb Overview Deck

of 80

Transcript of Esb Overview Deck

  • 8/10/2019 Esb Overview Deck

    1/80

  • 8/10/2019 Esb Overview Deck

    2/80

    OVERARCHING MESSAGE

    There is a compelling need as well as an economic case

    for reducing greenhouse gas emissions in existingbuildings. The Empire State Building case study providesan example of how this can be done. However, significant

    challenges remain that must be addressed in order toquickly and cost-effectively capture the full greenhouse

    gas reduction opportunity for building retrofits on awidespread basis.

    2

  • 8/10/2019 Esb Overview Deck

    3/80

    PRESENTATION OVERVIEW

    I. Motivation: The retrofit of the Empire State Building was motivated by the owners desirereduce greenhouse gas emissions, to demonstrate how to retrofit large commercial buildings effectively, and to demonstrate that such work makes good business sense.

    II. Project Development Process: Using ESB as a convening point, a collaborativeteam was formed to develop the optimal retrofit solution through an iterative process that invexperience, energy and financial modeling, ratings, metrics, and robust debate.

    III. Key Findings: At current energy costs, ESB can cost-effectively reduce energy use by38% and save (a minimum of) 105,000 metric tons of CO2 over the next 15 years.

    IV. Implementation: Three different stakeholders will implement the 8 savings measures ova 5-year period using various implementation mechanisms.

    V. Key Lessons: Key lessons relate to strategies to maximize cost-effective savings,balancing CO2 savings with economics, and streamlining the project development process.

    VI. Industry Needs: Challenges in each stage of the retrofit process are hindering theachievement of long-term goals.

    3

  • 8/10/2019 Esb Overview Deck

    4/80

    VI. NeedsV. Key LessonsIV. Implementation

    III. Key FindingsII. Process

    I. MOTIVATION

    The retrofit of the Empire State Building was motivated by the buildingownerships desire to:

    1) Prove or disprove the economic viability of whole-building energ

    efficiency retrofits.2) Create a replicable model for whole-building retrofits.

    3) Reduce greenhouse gas emissions.

    I. Motivation

  • 8/10/2019 Esb Overview Deck

    5/80

    5

    Prior to 2008, the Empire State Buildings performance was average compareto most U.S. office buildings.

    Annual utility costs:

    $11 million ($4/sq. ft.) Annual CO2 emissions:

    25,000 metric tons (22 lbs/sq. ft.)

    Annual energy use: 88 kBtu/sq. ft.

    Peak electric demand: 9.5 MW (3.8 W/sq. ft. inc. HVAC

    I. MOTIVATION1) Prove or disprove the economic viability of whole-building energy efficretrofits.

  • 8/10/2019 Esb Overview Deck

    6/80

    0

    20

    40

    60

    80

    100

    120

    T o t a l E S B C a p

    i t a l B u d g e

    t ( m

    i l l i o n

    $ )

    Capital Budget Adjustments for Energy Efficiency Projects

    6

    With a $500 million capital improvement program underway, ownershipdecided to re-evaluate certain projects with cost-effective energy efficiencand sustainability opportunities in mind.

    I. MOTIVATION1) Prove or disprove the economic viability of whole-building energy efficretrofits.

    2008Capital

    Budget forEnergy-Related

    Projects =$93m+ 0%

    EnergySavings

    Sum of adds /changes / deletes

    = +$13m

    New CapitalBudget w /EfficiencyProjects =

    $106m+ 38% Energy

    Savings

  • 8/10/2019 Esb Overview Deck

    7/807

    Energy efficiency and sustainability provide amenities (lower energy costeasier carbon reporting, daylighting, etc.) that set the building apart fromsurrounding tenant space.

    ($30,000)

    ($25,000)

    ($20,000)

    ($15,000)

    ($10,000)

    ($5,000)

    $0

    $5,000

    $10,000

    $15,000

    1 2 3 4 5 6 7 8 9 10 11 12

    N o m

    i n a l

    D o l

    l a r s

    ( $ )

    Year in Lease

    Illustrative: Tenant Utility Cash Flow

    Annual cost/savings NPV

    If tenants understand (and cancapture) the value of extrainvestments up front, they aremore likely to make them.

    I. MOTIVATION1) Prove or disprove the economic viability of whole-building energy efficretrofits.

  • 8/10/2019 Esb Overview Deck

    8/80

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. Process

    I. MOTIVATION

    The retrofit of the Empire State Building was motivated by the buildingownerships desire to:

    1) Prove or disprove the economic viability of whole-building energ

    efficiency retrofits.2) Create a replicable model for whole-building retrofits.

    3) Reduce greenhouse gas emissions.

    I. Motivation

  • 8/10/2019 Esb Overview Deck

    9/809

    I. MOTIVATION2) Create a replicable model for whole-building retrofits.

    There are known opportunities to cost-effectively reduce greenhouse gasemissions, yet few owners are pursuing them.

    Building efficiency measures are identifiedas having negative costs.

    Source: NRDC - http://www.nrdc.org/globalwarming/blueprint/default.asp

    Cutting U.S. Global Warming Pollution 80% by 2050: Cost & Payoff by Sector

  • 8/10/2019 Esb Overview Deck

    10/8010

    ESB ownership wants to demonstrate how to cost-effectively retrofit a larmulti-tenant office building to inspire others to embark on whole-buildingretrofits.

    I. MOTIVATION2) Create a replicable model for whole-building retrofits.

    8

  • 8/10/2019 Esb Overview Deck

    11/80

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. Process

    I. MOTIVATION

    The retrofit of the Empire State Building was motivated by the buildingownerships desire to:

    1) Prove or disprove the economic viability of whole-building energ

    efficiency retrofits.2) Create a replicable model for whole-building retrofits.

    3) Reduce greenhouse gas emissions cost-effectively.

    I. Motivation

  • 8/10/2019 Esb Overview Deck

    12/801

    We need to reduce greenhouse gas emissions by 75% by 2050 to stabilizethe climate.

    I. MOTIVATION3) Reduce Greenhouse Gas Emissions

    Business as usual global emissions*

    5562

    85

    64%68%

    76%

    2008 2030 2050

    We need to be at20 GtCO2e by2050 to mitigateclimate change

    Today, were at55 GtCO2e

    *Source: McKinsey Analysis, IPCC, Stern Review (2006)

  • 8/10/2019 Esb Overview Deck

    13/801

    The building sector must be a large part of the solution as it is the largestcontributor to U.S. greenhouse gas emissions.

    We need to be at20 GtCO2e by2050 to mitigateclimate change

    Source: EIA data - Table 12.2: http://www.eia.doe.gov/emeu/aer/envir.html

    0

    500

    1,000

    1,500

    2,000

    2,500

    1980 1984 1988 1992 1996 2000 2004

    M i l l i o n

    M e t r i c

    T o n s o f

    C a r

    b o n

    D i o x i d e

    Year

    U.S. CO2 Emissions by End-Use Sector: 1980 - 2006

    Buildings Industry Transportation

    Buildings are responsible for 38%

    of CO2 emissions in the U.S.

    I. MOTIVATION3) Reduce Greenhouse Gas Emissions

  • 8/10/2019 Esb Overview Deck

    14/801

    Nearly 75% of U.S. commercial buildings are over 20 years old (and thusready for retrofit). Retrofitting existing buildings must be part of the solut

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    14,000

    Before 1920 1920 to 1945 1946 to 1959 1960 to 1969 1970 to 1979 1980 to 1989 1990 to 1999 2000 to 2003

    M i l l i o n s q u a r e

    f e e t o f

    C o m m e r c i a l

    B u i l d

    i n g

    Year Constructed

    U.S. Commercial Building Space by Age

    Source: EIA data - Table 12.2: http://www.eia.doe.gov/emeu/aer/envir.html

    72% of the U.S. commercial stockwas constructed before 1990.

    I. MOTIVATION3) Reduce Greenhouse Gas Emissions

  • 8/10/2019 Esb Overview Deck

    15/80

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. Process

    I. MOTIVATION

    I. Motivation

    The goal with ESB has been to define intelligent choices whichwill either save money, spend the same money more efficiently,or spend additional sums for which there is reasonable paybackthrough savings. Addressing these investments correctly willcreate a competitive advantage for ownership through lowercosts and better work environment for tenants. Succeeding inthese efforts will make a replicable model for others to follow.

    - Anthony E. Malkin

  • 8/10/2019 Esb Overview Deck

    16/80

    II. PROJECT DEVELOPMENT PROCESS

    Using ESB as a convening point, a collaborative team was formed todevelop the optimal solution through a rigorous and iterative process thatinvolved experience, energy and financial modeling, ratings systems,technical advice, and robust debate. Key points include:

    1) Five key groups and a host of contributors used a collaborative aniterative approach.

    2) A 4-phase project development process helped guide progress.

    3) A variety of complementary tools were used and developed totriangulate to the best answer.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

  • 8/10/2019 Esb Overview Deck

    17/8017

    II. PROJECT DEVELOPMENT PROCESS1) Five key groups and contributors used a collaborative and iterative appr

    The project development process, which the team focused on, is the first towards executing and verifying the success of a retrofit.

    Project development is focused on understanding current performance, analyzing

    opportunities, and determining which projects to implement.

    ProjectExecution

    Measurement &Verification

    2010 2025Retrofit Project Timeline

  • 8/10/2019 Esb Overview Deck

    18/8018

    Core team members for the project development process included the CliClimate Initiative (CCI), Johnson Controls Inc. (JCI), Jones Lang LaSalleRocky Mountain Institute (RMI), and the Empire State Building (ESB).

    Owner Empire State

    Building Company LLC

    Project Manager Jones Lang LaSalle

    Energy ServiceCompany

    Johnson Controls Inc.

    Project Advisor Clinton Climate Initiative

    Design Partner &Peer Reviewer

    Rocky Mountain

    Institute

    OperationsReviewer Empire State

    Building Operations

    II. PROJECT DEVELOPMENT PROCESS1) Five key groups and contributors used a collaborative and iterative appr

    Team Organization Chart

  • 8/10/2019 Esb Overview Deck

    19/8019

    Many other contributors, in addition to the core team, provided additionalexpertise to fully explore all opportunities.

    II. PROJECT DEVELOPMENT PROCESS1) Five key groups and contributors used a collaborative and iterative appr

    Leasing agents

    3rd party review

    Financialexperts

    M&V experts

    Architects

    Ownership/

    Management

    EngineersSustainabilityExperts

    EnergyModelers

    Contractors

    GoalSetting

    BrainstormingCharrettes

    Benchmarking

    Contractor Estimates

    DesignDrawings

    EnergyModeling

    Financial/LCCAModeling

    ToolDevelopment

    FieldVerification

    ProjectDevelopment

  • 8/10/2019 Esb Overview Deck

    20/80

    II. PROJECT DEVELOPMENT PROCESS

    Using ESB as a convening point, a collaborative team was formed todevelop the optimal energy efficiency retrofit solution through a rigorousiterative process that involved experience, energy and financial modelingratings systems, technical advice, and robust debate. Key points include:

    1) Five key groups and a host of contributors used a collaborative aniterative approach.

    2) A 4-phase project development process helped guide progress.

    3) A variety of complementary tools were used and developed totriangulate to the best answer.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

  • 8/10/2019 Esb Overview Deck

    21/8021

    Project activities (audits, workshops, presentations, analyses, reports, etc.were divided into 4 phases.

    II. PROJECT DEVELOPMENT PROCESS2) A 4-phase project development process helped guide progress.

    Phase I: Inventory& Programming

    Phase II: DesignDevelopment

    Phase III: DesignDocumentation

    Phase IV: Final Documentation

    Tenant Initiatives (prebuilts,design guidelines, energymanagement) Report

    Tuned eQUEST model

    Model (eQUEST, financial,GHG) outputs

    Integrated SustainabilityMaster Plan Report (inc.Energy Master Plan)

    April 14th kick-off meeting May 7 th /May 14th team

    workshops June 2 nd Presentation to

    Ownership

    Baseline Capital ProjectsReport

    Baseline EnergyBenchmark Report

    June 18 th TheoreticalMinimum workshop

    July 2 nd workshop July 15 th Presentation to

    ownership

    July 30 th Tenant Focusworkshop

    August 13th eQUESTworkshop

    August 27 th Presentation toOwnership

    Sept. 10 th workshop Sept 29th Presentation to

    Ownership October 6-8 th Finance

    workshop (Boulder) Nov 10 th Presentation to

    Ownership

    A c t

    i v i t i e s

    O u t p u

    t s

  • 8/10/2019 Esb Overview Deck

    22/80

  • 8/10/2019 Esb Overview Deck

    23/80

    23

    Significant time was spent 1) refining energy and financial model inputs to eoutputs were accurate and 2) understanding the critical relationship betweeneconomics and CO2 reductions.

    II. PROJECT DEVELOPMENT PROCESS2) A 4-phase project development process helped guide progress.

    2008 2010 2012 2014 2016 2018 2020 2022 D o l l a r s

    ( $ )

    Incremental Cash Flow for

    each Package of Measures

    2008 2010 2012 2014 2016 2018 2020 2022

    A b s o l u t e

    M e t r i c

    T o n s o f

    C O 2

    CO2 Emissions for each

    Package

  • 8/10/2019 Esb Overview Deck

    24/80

  • 8/10/2019 Esb Overview Deck

    25/80

    25

    Industry standard and newly developed design tools, decision-making tooand rating tools helped to evaluate and benchmark existing and futureperformance.

    II. PROJECT DEVELOPMENT PROCESS3) A variety of tools were used and developed to triangulate to the best an

    Design Tools Decision-Making Tools Rating Tools

  • 8/10/2019 Esb Overview Deck

    26/80

    III. KEY FINDINGS

    At current energy costs, the Empire State Building can cost-effectivelyreduce energy use by 38% and save (a minimum of) 105,000 metric tonsCO2 over the next 15 years.

    1) Eight interactive levers ranging from base building measures totenant engagement deliver these results.

    2) Key reductions in peak cooling and electric loads are possible.

    3) Enhanced work environments are created.

    4) Various green certifications can be obtained.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    27/80

    27

    The Empire State Building can achieve a high level of energy and CO2reduction cost-effectively.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    NPV Max

    NPV Mid

    NPV Neutral

    Max CO2

    Reduction

    ($25,000)

    ($5,000)

    $15,000

    $35,000

    0 40,000 80,000 120,000 160,000

    N e t

    P r e s e n t

    V a l u e o f

    P a c

    k a g e o f

    M e a s u r e s

    T h

    o u s a n

    d s

    Cumulative metric tons of CO2 saved over 15 years

    15-Year NPV of Package versus Cumulative CO2 Savings

    There are diminishing (andexpensive) returns forgreater efficiency.

    A solution thatbalances CO2reductions andfinancial returns isin this range.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    28/80

    28

    Achieving an energy reduction greater than 38% appears to be cost-prohib

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    ($2,000)

    $0

    $2,000

    $4,000

    C o s

    t p e r

    M e t r i c

    T o n o f C

    O 2

    Cost per Metric Ton of CO2 by Individual Measure

    The average cost per ton of carbon dioxide saved for

    the first 90% of the savings is -$200/tonwhile theaverage cost per ton for the last 10% is over $300

    per ton.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    29/80

    29

    Energy and CO2 savings in the optimal package result from 8 key projects

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    9% 6%5%

    5%5% 3% 3% 2%

    0

    100,000

    200,000

    300,000

    A n n u a

    l E n e r g y

    U s e

    ( k B t u )

    T

    h o u s a n

    d s

    Annual Energy Savings by Measure

    38%Reduction

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    30/80

    30

    Taking the right steps in the right order ensures loads are minimized prior investigating expensive new equipment or controls.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    Reduce Loads

    Use Efficient Technology

    Provide Controls

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    31/80

    31

    WINDOWS:Remanufacture existing insulated glass units (IGU) within theEmpire State Buildings approximately 6,500 double-hung windows to includesuspended coated film and gas fill.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    32/80

    32

    RADIATIVE BARRIER:Install more than six-thousand insulated reflectivebarriers behind radiator units located on the perimeter of the building.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    33/80

    33

    TENANT DAYLIGHTING / LIGHTING / PLUGS:This measure involvesreducing lighting power density in tenant spaces, installing dimmable balland photosensors for perimeter spaces, and providing occupants with a pluload occupancy sensor for their personal workstation.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    34/80

    34

    CHILLER PLANT RETROFIT:The chiller plant retrofit project includes theretrofit of four industrial electric chillers in addition to upgrades to controlvariable speed drives, and primary loop bypasses.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    35/80

    35

    VAV AIR HANDLING UNITS:Replace existing constant volume units withvariable air volume units using a new air handling layout (two floor-moununits per floor instead of four ceiling-hung units).

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    36/80

    36

    DDC CONTROLS:The measure involves upgrading the existing controlsystems at the Empire State Building.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    37/80

    37

    DEMAND CONTROL VENTILATION:This project involves the installation ofCO2 sensors for control of outside air introduction to chiller water and DXHandling Units.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    38/80

    38

    TENANT ENERGY MANAGEMENT:This project will provide tenants withaccess to online energy and benchmarking information as well as sustainabtips and updates.

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    39/80

    39

    Though it is more informative to look at financials for the package of meacapital costs and energy savings were determined for each individual mea

    III. KEY FINDINGS1) Eight interactive levers ranging from base building measures to tenantengagement deliver these results.

    ProjectDescription

    ProjectedCapital Cost

    2008 CapitalBudget

    IncrementalCost

    EstimatedAnnualEnergy Savings*

    Windows $4.5m $455k $4m $410k

    Radiative Barrier $2.7m $0 $2.7m $190k

    DDC Controls $7.6m $2m $5.6m $741k

    Demand Control Vent Inc. above $0 Inc. above $117k

    Chiller Plant Retrofit $5.1m $22.4m -$17.3m $675k

    VAV AHUs $47.2m $44.8m $2.4m $702kTenant Day/Lighting/Plugs $24.5m $16.1m $8.4m $941k

    Tenant Energy Mgmt. $365k $0 $365k $396k

    Power Generation (optional) $15m $7.8m $7m $320k

    TOTAL (ex. Power Gen) $106.9m $93.7m $13.2m $4.4m

    *Note that energy savings are also incremental to the original capital budget.

  • 8/10/2019 Esb Overview Deck

    40/80

    III. KEY FINDINGS

    At current energy costs, the Empire State Building can cost-effectivelyreduce energy use by 38% and save (a minimum of) 105,000 metric tonsCO2 over the next 15 years.

    1) Eight interactive levers ranging from base building measures totenant engagement deliver these results.

    2) Key reductions in peak cooling and electric loads are expected.

    3) Enhanced work environments are created.

    4) Various green certifications can be obtained.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

  • 8/10/2019 Esb Overview Deck

    41/80

    41

    The selected package of measures reduces peak cooling requirements by 3(1600 tons) enabling immediate and future CapEx avoidance.

    III. KEY FINDINGS2) Key reductions in peak cooling and electric loads are expected.

    NPV Max Package

    NPV Mid Package

    NPV NeutralPackage

    CO2 Max Package-20,000

    -10,000

    0

    10,000

    20,000

    30,000

    40,000

    0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 N e t

    P r e s e n t

    V a l u e

    ( $ )

    T h

    o u s a n

    d s

    Reduction in Peak Cooling Capacity

    Cost of Cooling Efficiency

    The 1600-ton load reduction allows forthe chiller retrofit instead ofreplacement/adding capacity.

  • 8/10/2019 Esb Overview Deck

    42/80

    42

    The optimal package of measures also reduces peak electrical demand by MW, benefitting both the building and the utility.

    III. KEY FINDINGS2) Key reductions in peak cooling and electric loads are expected.

    0

    2

    4

    6

    8

    10

    12

    O f f i c e

    B u i

    l d i n g P e a

    k D e m a n

    d ( M W )

    CurrentPeak

    Capacity

    Office Building Electrical Capacity

    FuturePeak

    Capacity

    If on-site back-up generation is desired,options include:

    Cogeneration; Gas-fired/bio-fuel fired generation; Fuel cells; Renewables (PV/wind); and Purchasing new capacity from Con

    Edison

  • 8/10/2019 Esb Overview Deck

    43/80

    III. KEY FINDINGS

    At current energy costs, the Empire State Building can cost-effectivelyreduce energy use by 38% and save (a minimum of) 105,000 metric tonsCO2 over the next 15 years.

    1) Eight interactive levers ranging from base building measures totenant engagement deliver these results.

    2) Key reductions in peak cooling and electric loads are expected.

    3) Enhanced work environments are created.

    4) Various green certifications can be obtained.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    GS

  • 8/10/2019 Esb Overview Deck

    44/80

    44

    This package of measures also results in enhanced indoor environmentalquality and additional amenities for tenants:

    III. KEY FINDINGS3) Enhanced work environments are created.

    Better thermal comfort resulting from better windows, radiativebarrier, and better controls;

    Improved indoor air quality resulting from DCV; and Better lighting conditions that coordinateambient and task lighting.

  • 8/10/2019 Esb Overview Deck

    45/80

    III. KEY FINDINGS

    At current energy costs, the Empire State Building can cost-effectivelyreduce energy use by 38% and save (a minimum of) 105,000 metric tonsCO2 over the next 15 years.

    1) Eight interactive levers ranging from base building measures totenant engagement deliver these results.

    2) Key reductions in peak cooling and electric loads are expected.

    3) Enhanced work environments are created.

    4) Various green certifications can be obtained.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    46/80

    46

    This recommended package of measures helps to earn 12 LEED EBOMpoints, an Energy Star score of 90, and a 72% Green Globes score.

    III. KEY FINDINGS4) Various green certifications can be achieved.

    Package EnergySavings* Energy Star LEEDPoints

    GreenGlobes

    NPV Max 20% 82 8 64%

    NPV Mid 38% 90 12 72%

    NPV Neutral 45% 91 13 76%

    CO2 Max 48% 92 13 78%

    III KEY FINDINGS

  • 8/10/2019 Esb Overview Deck

    47/80

    47

    The Empire State Building will be pursuing the Energy Star label as well aGold certification under the LEED for Existing Buildings: Operation &Maintenance Rating System.

    III. KEY FINDINGS4) Various green certifications can be achieved.

  • 8/10/2019 Esb Overview Deck

    48/80

    IV. IMPLEMENTATION

    Clear energy targets and responsible parties must be determined for each the 8 major savings measures to fully maximize the environmental andeconomic benefits.

    1) Three stakeholders, with different implementation mechanisms, wdeliver the savings.

    2) The project will be financed out of cash flow, though other financopportunities are being investigated.

    3) Work has already started and will be complete by 2013 (55% of thsavings will be in place by December 31, 2010).

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    IV IMPLEMENTATION

  • 8/10/2019 Esb Overview Deck

    49/80

    49

    Johnson Controls, the Empire State Building, and Tenants are eachresponsible for delivering some of the total savings.

    IV. IMPLEMENTATION1) Three stakeholders, with different implementation mechanisms, will dethe savings.

    61%

    22%17%

    0

    50,000,000

    100,000,000

    150,000,000

    200,000,000

    250,000,000

    Adjusted Baseline JCI ESB Tenant NPV Mid

    A n n u a

    l E n e r g y

    S a v

    i n g s

    ( k B t u )

    Energy Savings by Implementation Stakeholder

    IV IMPLEMENTATION

  • 8/10/2019 Esb Overview Deck

    50/80

    50

    Who implements each project?Project Description Implementer

    Windows Johnson Controls

    Radiative Barrier Johnson Controls

    DDC Controls Johnson Controls

    Demand Control Vent Johnson Controls

    Chiller Plant Retrofit Johnson Controls

    VAV AHUs Empire State Building

    Tenant Day/Lighting/Plugs Tenants & Empire State Building

    Tenant Energy Mgmt. All

    IV. IMPLEMENTATION1) Three stakeholders, with different implementation mechanisms, will delthe savings.

    IV IMPLEMENTATION

  • 8/10/2019 Esb Overview Deck

    51/80

    51

    Johnson Controls Inc will deliver 61% of the total savings using a performcontract mechanism. Five different performance contracts have a total cos$20 million and guaranteed savings of ~20% percent.

    IV. IMPLEMENTATION1) Three stakeholders, with different implementation mechanisms, will dethe savings.

    How does the Performance Contract work? 1. ESB pays JCI guaranteed maximum price for capital cost of all

    projects2. ESB accrues energy savings as a result of the

    retrofit projects if savings are too low,

    JCI pays ESB the difference.3. Savings guarantee term is 15 years JCI

    61%ESB22%

    ESB/Tenants

    17%

    IV. IMPLEMENTATION

  • 8/10/2019 Esb Overview Deck

    52/80

    52

    Empire State Building will deliver 22% of the total available savings as aihandling units and pre-built spaces are replaced over the next 4 years.

    IV. IMPLEMENTATION1) Three stakeholders, with different implementation mechanisms, will dethe savings.

    JCI61%

    ESB22%

    ESB/Tenants

    17%

    IV. IMPLEMENTATION

  • 8/10/2019 Esb Overview Deck

    53/80

    53

    ESB is responsible for helping/incentivizing tenants to pay for and achievnearly 20% of the total available energy savings as spaces turnover.

    IV. IMPLEMENTATION1) Three stakeholders, with different implementation mechanisms, will dethe savings.

    JCI61%ESB

    22%

    ESB/Tenants

    17%

    IV. IMPLEMENTATION

  • 8/10/2019 Esb Overview Deck

    54/80

    54

    The team has identified 3 programs that will help to reduce and manage teenergy use:

    IV. IMPLEMENTATION1) Three stakeholders, with different implementation mechanisms, will dethe savings.

    1. Tenant pre-built program: The proposed green pre-built design will save $0.7- $0.90/sq. ft. in operating costs annually for an additional cost of $6/sq. ft. ahelp ESB demonstrate design principles for all tenants to endorse.

    2. Tenant design guidelines: Design guidelines, based on the pre-built program,will provide green ESB standards. Tenants can verify the economic validity orecommendations by accessing the eQUEST model or tenant financial tool.

    3. Tenant energy management program: ESB will begin sub-metering all tenantspaces and manage a feedback/reporting tool to inform tenants about theirenergy use. This program will also assist tenants with their own carbon reporefforts.

  • 8/10/2019 Esb Overview Deck

    55/80

    IV. IMPLEMENTATION

    Clear energy targets and responsible parties must be determined for each the 8 major savings measures to fully maximize the environmental andeconomic benefits.

    1) Three stakeholders, with different implementation mechanisms, wdeliver the savings.

    2) The project will be financed out of cash flow, though other financopportunities are being investigated.

    3) Work has already started and will be complete by 2013 (55% of thsavings will be in place by December 31, 2010).

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    IV. IMPLEMENTATION

  • 8/10/2019 Esb Overview Deck

    56/80

    56

    The additional $13.2 million required for energy efficiency projects will bfor out of cash flow.

    V. O2) The project will be financed out of cash flow, though other financingopportunities are being investigated.

    0

    20

    40

    60

    80

    100

    120

    T o t a l E S B C a p i

    t a l B u d g e

    t ( m

    i l l i o n

    $ )

    Capital Budget Adjustments for Energy Efficiency Projects

    2008Capital

    Budget forEnergy-

    RelatedProjects =$93m+ 0%

    EnergySavings

    Sum of adds /changes / deletes

    = +$13m

    New CapitalBudget w /EfficiencyProjects =

    $106m+ 38% Energy

    Savings

  • 8/10/2019 Esb Overview Deck

    57/80

    IV. IMPLEMENTATION

    Clear energy targets and responsible parties must be determined for each the 8 major savings measures to fully maximize the environmental andeconomic benefits.

    1) Three stakeholders, with different implementation mechanisms, wdeliver the savings.

    2) The project will be financed out of cash flow, though other financopportunities are being investigated.

    3) Work has already started and will be complete by 2013 (55% of thsavings will be in place by December 31, 2010).

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    IV IMPLEMENTATION

  • 8/10/2019 Esb Overview Deck

    58/80

    58

    The projects to be implemented via the Johnson Controls performance conwill be complete by October 2010. The remaining projects will be compleDecember 2013.

    IV. IMPLEMENTATION3) Work has already started and will be complete by 2013.

    April2009

    October2010

    December2013

    Chiller Plant Retrofit Finalengineering &subcontractor

    awards

    DDC Controls

    Demand Control Ventilation

    Windows

    Radiators

    AHU replacement

    Tenant Energy Management

    Tenant Lighting, Daylighting, Plugs

  • 8/10/2019 Esb Overview Deck

    59/80

    V. LESSONS LEARNED

    Key lessons learned for the retrofit of large commercial office buildingsinclude:

    1) The maximum cost-effective savings are achieved by:

    a) Taking a whole-systems, dynamic, life-cycle approach;b) Coordinating projects with equipment replacement cycles; andc) Addressing tenant spaces.

    2) At a certain point, there is tension between CO2 savings andbusiness value (even with anticipated CO2 regulations).

    3) The process can and must be streamlined.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    V LESSONS LEARNED

  • 8/10/2019 Esb Overview Deck

    60/80

    60

    A. Teams must take a whole-systems, dynamic, life-cycle approach.

    V. LESSONS LEARNED1) Several approaches help maximize cost-effective savings.

    Reduce Loads

    Use EfficientTechnology

    Provide Controls

    Capital Cost

    Utility Savings

    Utility Rebates

    Tax Implications

    O&M Impacts

    Escalation Assumptions

    Discount Rate

    Future Cost of CO2

    Tenant Utility Structure

    V LESSONS LEARNED

  • 8/10/2019 Esb Overview Deck

    61/80

    61

    B. Projects are most cost-effective when coordinated with equipmentreplacement cycles.

    V. LESSONS LEARNED1) Several approaches help maximize cost-effective savings.

    ($100,000,000)

    ($80,000,000)

    ($60,000,000)

    ($40,000,000)

    ($20,000,000)

    $0

    $20,000,000

    $40,000,000

    0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000

    N e t

    P r e s e n t

    V a l u e o f

    P a c

    k a g e o f

    M e a s u r e s

    Cumulative metric tons of CO2 saved over 15 years

    15-Year NPV of Package versus Cumulative CO2 Savings

    IncrementalCapEx

    AbsoluteCapEx

    V LESSONS LEARNED

  • 8/10/2019 Esb Overview Deck

    62/80

    62

    V. LESSONS LEARNED1) Several approaches help maximize cost-effective savings.

    C. More than half the savings exist within tenant spaces dont ignore them!

    Balance of DDC

    Retrofit Chiller

    Tenant Daylighting/Lighting/Plugs

    VAV AHU's

    Bldg Windows

    Tenant EnergyManagement

    Radiative Barrier Tenant DCV

    0

    10,000,000

    20,000,000

    30,000,000

    40,000,000

    50,000,000

    60,000,000

    Measures that only affect the Base Building Measures within Tenant Space

    A n n u a l

    E n e r g y

    S a v

    i n g s

    ( k B t u )

    Energy Savings: Base Building vs. within Tenant Space

  • 8/10/2019 Esb Overview Deck

    63/80

    V. LESSONS LEARNED

    Key lessons learned for the retrofit of large commercial office buildingsinclude:

    1) The maximum cost-effective savings are achieved by:a) Taking a whole-systems, dynamic, life-cycle approach;b) Coordinating projects with equipment replacement cycles; andc) Addressing tenant spaces.

    2) At a certain point, there is tension between CO2 savings andbusiness value (even with anticipated CO2 regulations).

    3) The process can and must be streamlined.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    V LESSONS LEARNED

  • 8/10/2019 Esb Overview Deck

    64/80

    64

    V. LESSONS LEARNED2) At a certain point, there is tension between CO2 savings and business v

    Maximizing business value leaves considerable CO2 on the table.

    20%

    19%

    7%3%

    0

    50,000,000

    100,000,000

    150,000,000

    200,000,000

    250,000,000

    Adjusted Baseline NPV Max NPV Mid NPV Neutral CO2 Max Year 15

    A n n u a l

    E n e r g y

    C o s

    t i n

    D o l

    l a r s

    Energy Cost Savings by Package

    Choice package to

    maximize NPV.

    V LESSONS LEARNED

  • 8/10/2019 Esb Overview Deck

    65/80

    65

    V. LESSONS LEARNED2) At a certain point, there is tension between CO2 savings and business v

    Attempting to save CO2 faster may be cost prohibitive.

    NPV Mid

    NPV Mid Acclerated

    ($40,000,000)

    ($30,000,000)

    ($20,000,000)

    ($10,000,000)

    $0

    $10,000,000

    $20,000,000

    $30,000,000

    $40,000,000

    0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000

    N e t

    P r e s e n t

    V a l u e o f

    P a c

    k a g e o f

    M e a s u r e s

    Cumulative metric tons of CO2 saved over 15 years

    15-Year NPV of Package versus Cumulative CO2 Savings

    Acceleration reduces theNPV as projects become

    out of sync withreplacement cycles

    V LESSONS LEARNED

  • 8/10/2019 Esb Overview Deck

    66/80

    66

    V. LESSONS LEARNED2) At a certain point, there is tension between CO2 savings and business v

    Anticipated CO2 regulation in the U.S. doesnt change the solution set though European levels of regulation would.

    ($30,000,000)

    ($20,000,000)

    ($10,000,000)

    $0

    $10,000,000

    $20,000,000

    $30,000,000$40,000,000

    $50,000,000

    0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000

    N P V ( $ )

    Cumulative CO2 Savings (Metric Tons)

    15-Yr NPV and Cumulative CO2 Savings at Fluctuating Carbon Costs

    No Regulation .33% CA: Low Carbon Economy Act1.34%: RGGI 2% CA: Lieberman Warner

    8.8% CA: EU OTC

  • 8/10/2019 Esb Overview Deck

    67/80

    V. LESSONS LEARNED

    Key lessons learned for the retrofit of large commercial office buildingsinclude:

    1) The maximum cost-effective savings are achieved by:a) Taking a whole-systems, dynamic, life-cycle approach;b) Coordinating projects with equipment replacement cycles; andc) Addressing tenant spaces.

    2) At a certain point, there is tension between CO2 savings andbusiness value (even with anticipated CO2 regulations).

    3) The process can and must be streamlined.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    V LESSONS LEARNED

  • 8/10/2019 Esb Overview Deck

    68/80

    68

    V. LESSONS LEARNED3) The process can and must be streamlined.

    Several opportunities to reduce the time and cost of the project developmprocess exist.

    Project DevelopmentTime

    Improved Process Apply Insights Improved Tools Optimized ProjectDevelopment Time

    T i m e a n

    d C o s

    t s

    Opportunities to Improve Project Development Process

    Reduction intime and costs?

  • 8/10/2019 Esb Overview Deck

    69/80

    VI. INDUSTRY NEEDS

    This project was a great test lab, but what now? If all buildings need to beretrofitted to profitably reduce greenhouse gas emissions by 75% by 2050we have a lot of work to do in a short amount of time.

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    Opportunity Areas: Residential, Commercial, Industrial

    Barriers: What is preventing us from reaching our goal?

    Outcome: 75% Reduction by 2050

    Strategies: What is the most impactful way to overcome barriers?

    Coordination: Who is working on what and what can you do?

    VI INDUSTRY NEEDS

  • 8/10/2019 Esb Overview Deck

    70/80

    Project

    Origin

    Project

    Development

    Construction &

    Commissioning

    Financing&

    Contracting

    Measurement

    & Verification

    70

    VI. INDUSTRY NEEDS

    Barriers exist in each phase of the retrofit process. Below are the major bathis team believes are paramount to overcome in order to reach our 2050

    Retrofit Project Phases

    c. Projectdevelopmentanalysis tools

    c. Policye. Engineering

    capacityf. Cost of

    measures

    g. Financing(base buildingand tenant)

    h. Performance-based designandconstructioncontracts

    TBD TBDa. Selecting theright buildingsfor whole-systemsretrofits

    b. Developingsolutions forall buildingtypes

    VI. INDUSTRY NEEDS

  • 8/10/2019 Esb Overview Deck

    71/80

    71

    VI. INDUSTRY NEEDSa) Select the right buildings for whole-systems retrofits

    Retrofitting the right buildings in the right order can reduce the societal c($/metric ton) for carbon abatement.

    1

    3

    2

    4

    VI. INDUSTRY NEEDS

  • 8/10/2019 Esb Overview Deck

    72/80

    72

    VI. INDUSTRY NEEDSb) Develop solutions for small to mid-range commercial buildings.

    Most retrofit or energy service companies only address large commercialbuildings or residential buildings. Yet 95% of the U.S. building stock is smmid-sized buildings that consume 44% of total energy use.

    Source: EIA data

    VI. INDUSTRY NEEDS

  • 8/10/2019 Esb Overview Deck

    73/80

    73

    VI. INDUSTRY NEEDSc) Develop better project development tools.

    Significant time was spent creating the energy and financial models for thbuilding and then iterating between them. Quicker and simpler tools coulaccelerate the process.

    VI. INDUSTRY NEEDS

  • 8/10/2019 Esb Overview Deck

    74/80

    74

    d) Use policy and regulation to incentivize deeper savings and to make theprocess cheaper and more transparent.

    Federal stimulus money, city or state mandated retrofits, and more sharedon opportunities and performance will make retrofits faster and cheaper.

    Source: Recovery.gov

    MAYOR BLOOMBERGAND SPEAKER QUINN

    ANNOUNCE MAJORPACKAGE OFLEGISLATION TOCREATE GREENER,

    GREATER BUILDINGSPLAN FOR NEW YORKCITY

    VI. INDUSTRY NEEDS

  • 8/10/2019 Esb Overview Deck

    75/80

    75

    e) Increase workforce capacity of whole-systems trained auditors, engineeroperators, and commissioning agents.

    There is a lack of American engineers who are trained and ready to rebuilefficient buildings, cities, and cars.

    Source: RAND Issue paper - http://www.rand.org/pubs/issue_papers/IP241/IP241.pdf

    Science &Engineering

    There is no negawatt university Amory Lovins

    VI. INDUSTRY NEEDSf ff

  • 8/10/2019 Esb Overview Deck

    76/80

    76

    f) Determine how to make efficiency measures and renewable energytechnologies more cost-effective.

    Value-chain analyses can help determine opportunities for cost reductionstechnologies that can save significant amounts of energy.

    Additional controls; Easy to install methods to retrofit exterior wall systems to increase thermal

    resistance; LED lighting; DALI lighting controls; Chilled beam systems; Heat recovery systems;

    Green roofs; Rainwater collection; Condenser water savings; Dessicant systems; and Even higher performance windows.

    VI. INDUSTRY NEEDS

  • 8/10/2019 Esb Overview Deck

    77/80

    77

    g) Determine solutions for both base building and tenant financing.

    Availability of capital is a major hurdle and a variety of innovative solutiowork for large, small, owner-occupied, and leased spaces is needed.

    VI. INDUSTRY NEEDS

  • 8/10/2019 Esb Overview Deck

    78/80

    78

    h) Standardize (and use) performance-based design and construction contra

    Design and engineering parties are often incentivized by different outcomthus deterring the group from optimizing energy efficiency.

    Get paid for what you save, not what you spend.

    CONCLUSION

  • 8/10/2019 Esb Overview Deck

    79/80

    CONCLUSION

    VI. NeedsV. Key LessonsIV. ImplementationIII. Key FindingsII. ProcessI. Motivation

    There is a compelling need as well as an economic casefor reducing greenhouse gas emissions in existing

    buildings. The Empire State Building case study providesan example of how this can be done. However, significantchallenges remain that must be addressed in order to

    quickly and cost-effectively capture the full greenhousegas reduction opportunity for building retrofits on a

    widespread basis.

    For more information please contact:

  • 8/10/2019 Esb Overview Deck

    80/80

    Rocky Mountain Institute

    For more information, please contact:

    Kathy Baczko

    Clinton Climate InitiativeNew York City Director +1 646 981 [email protected]

    Anthony E. MalkinEmpire State BuildingOwner

    Iain Campbell

    Johnson Controls, Inc.VP & GM, NA Solutions, Building Efficiency+1 414 524 [email protected]

    Ray QuartararoJones Lang LaSalleNortheast Regional Manager, International Director +1 212 812 [email protected]

    Amory LovinsRocky Mountain InstituteChief Scientist+1 970 927 [email protected]

    More project information available at:www.esbsustainability.com