ES - 92 Project Management
-
Upload
easter-phoebe-durias-paglinawan -
Category
Documents
-
view
218 -
download
0
Transcript of ES - 92 Project Management
-
8/9/2019 ES - 92 Project Management
1/38
Project Management
-
8/9/2019 ES - 92 Project Management
2/38
Introduction Project Management can be used to
manage complex projects
Alm os t e ve ry in du s t ry worrie s a bou t how to
m a n a g e la rge -sca le ,
com p lica te d p ro je ct s
e f e ct ive ly. It is a d i cu lt
p rob le m , a nd the s ta ! e s
a re h ig h .
" h e # r s t s t e p in p la n n in g a n d
s ch e d u lin g a p r o je c t is t o d e ve lop t h e wor ! b r e a ! d own s t r u c t u r e .
-
8/9/2019 ES - 92 Project Management
3/38
"his involves identi$ying the activities that must beper$ormed in the project. "here may be varyinglevels o$ detail, and each activity may be bro!eninto its most basic components. "he time, cost,resource re%uirements, predecessors, andperson&s' responsible are identi#ed $or each
activity.
( o r ! ) r e a ! d own * t r u c t u r e .
-
8/9/2019 ES - 92 Project Management
4/38
-
8/9/2019 ES - 92 Project Management
5/38
*teps o$ P " and PM
/e#ne the project and all o$ its signi#cantactivities or tas!s.
01
/evelop the relationships among the activities./ecide which activities must precede others.2
/raw the networ! connecting all o$ theactivities.
3 Assign time and4or cost estimates to each
activity.5 ompute the longest time path through thenetwor! 6 critical path .7
8se the networ! to help plan, schedule,monitor, and control the project.0
-
8/9/2019 ES - 92 Project Management
6/38
-
8/9/2019 ES - 92 Project Management
7/38
-
8/9/2019 ES - 92 Project Management
8/38
+uestions answered byP "
(hen will the entire project be completed;1 (hat are the critical activities or tas!s in the
project, that are, the ones that will delay theentire project i$ they are late;
2
(hich are the noncritical activities, that are, theones that can run late without delaying the
entire project
-
8/9/2019 ES - 92 Project Management
9/38
+uestions answered byP "
At any particular date, is the project on schedule,behind the schedule, or ahead o$ schedule;7
=n any given date, is the money spent e%ual to,less than, or greater than the budgeted amount;0
Are there enough resources available to #nishthe project on time;
>
I$ the project is to be #nished in a shorteramount o$ time, what is the best way toaccomplish this at the least cost;
?
-
8/9/2019 ES - 92 Project Management
10/38
/rawing the P " :etwor! "wo common techni%ues@
Activity-on-node &A=:'
nodes represent the activities
1
Activity-on-arc &A=A'arcs represent the activities
2
-
8/9/2019 ES - 92 Project Management
11/38
Activity-on-node &A=:' In constructing, there should be one
node representing the start o$ theproject and one node representingthe #nish o$ the project.
-
8/9/2019 ES - 92 Project Management
12/38
eneral 9oundry, Inc. xample
eneral 9oundry, Inc., a metalwor!s plant in ebuity, has long been trying to avoid the expense o$
installing a air pollution control e%uipment. "he local
environmental protection group has recently giventhe $oundry 10 wee!s to install a complex air #ltersystem on its main smo!estac!. eneral 9oundrywas warned that it will be $orced to close unless thedevice is installed in the allotted period. "he PlantManager, wants to ma!e sure that installation o$ the#ltering system progresses smoothly and on time.
-
8/9/2019 ES - 92 Project Management
13/38
eneral 9oundry, Inc. xample
ACTIVITY DESCRIPTION IMMEDIATEPREDECESSORS
A )uild internal components --) Modi$y roo$ and Boor --
onstruct collection stac! A
/ Pour concrete and install $rame )
)uild high-temperature burner9 Install control system
Install air pollution device /,
C Inspect and test 9,
-
8/9/2019 ES - 92 Project Management
14/38
eneral 9oundry, Inc. xample
*tart
A)uild
Internalomponents
)Modi$y oo$
and 9loor
onstructollection
*tac!
/Modi$y oo$
and 9loor
9Installontrol
*ystem
InstallPollution/evice
)uild)urner
CInspect and
"est9inish
-
8/9/2019 ES - 92 Project Management
15/38
Activity "imes Optimistic Time (a) D time an activity will ta!e i$
everything goes as well as possible. "here should be only a small
probability &say, 141EE' o$ thisoccurring.
Pessimistic Time (b) D time an activity would ta!eassuming very un$avourable
conditions. "here should also be only asmall probability that the activity willreally ta!e this long
-
8/9/2019 ES - 92 Project Management
16/38
Activity "imes Most likel time (m) D most realistic time
estimate to complete the activity.
! P " o$ten assumes that time estimates $ollow thebeta probabilit distribution"
Probability o$ 1 in1EE o$ a occurring
P r o
b a b i l i t
y
Most =ptimistic
"ime&a'
Most Fi!ely "ime
&m'
Most Pessimistic "ime
&b'
Probability o$ 1 in1EE o$ b occurring
Activity "ime
-
8/9/2019 ES - 92 Project Management
17/38
Activity "imes "he e#pected activit time (t) , $rom beta
distribution@
t D &a G 5m G b' 4 0 "he variance o$ activit completion time%
variance D H&b 6 a' 4 0 2
-
8/9/2019 ES - 92 Project Management
18/38
"ime estimates &(ee!s' $or eneral 9oundry, Inc.
Activity
Optimistic, a MostPro a le,
m
Pessi!mistic,
b
E"pecte#
Time, t
Variance
A 1 2 3 2 5430) 2 3 5 3 5430
1 2 3 2 5430
/ 2 5 0 5 10430
1 5 > 5 30430
9 1 2 J 3 054303 5 11 7 05430
C 1 2 3 2 5430
-
8/9/2019 ES - 92 Project Management
19/38
A 2
:etwor! with xpected Activity "imes $or eneral 9oundry, Inc.
*tart
B 3
C 2
D 4
F 3
E 4
G 5
H 2
9inish
-
8/9/2019 ES - 92 Project Management
20/38
9inding the ritical Path Critical Path 6 longest time path route through the
networ!.
9inding the critical path, we need to determine the$ollowing %uantities $or each activity in the networ!@
Earliest start time ( *'@ the earliest time an activity canbegin without violation o$ immediate predecessor
re%uirements
1
Earliest &nish time ( 9'@ the earliesttime at which an activity can end.
2
-
8/9/2019 ES - 92 Project Management
21/38
-
8/9/2019 ES - 92 Project Management
22/38
arliest "imes
earliest #nish time D earliest start time G expected activitytime 9 D * G t
1
earliest start D largest o$ the earliest #nishtimes o$ immediate predecessors * D largest 9 o$ immediatepredecessors
2
!be$ore an activit can be started all o$ its predecessorsactivities must be completed *n other words we search $or thelargest E+ $or all o$ the immediate predecessors in determiningE,"
-
8/9/2019 ES - 92 Project Management
23/38
arliest "imes
A t=2
ES = 0 EF = 0 + 2 = 2
*tart
B t=3
ES = 0 EF = 0 + 3 = 3
-
8/9/2019 ES - 92 Project Management
24/38
A 2
0 2
arliest *tart & *' K arliest 9inish & 9' "imes $or eneral 9oundry, Inc.
*tart
B 3
0 3
C 2
2 4
D 4
3 7
F 3
4 7
E 4
4 8
G 5
8 13
H 2
13 15 9inish
"he #nish time $or the project will be 17 wee!s, which is the 9 $oractivity C.
8sing +orward Pass through the networ!@
-
8/9/2019 ES - 92 Project Management
25/38
-
8/9/2019 ES - 92 Project Management
26/38
A 2
0 2
0 2
arliest *tart & *' K arliest 9inish & 9' "imes $or eneral 9oundry, Inc.
*tart
B 3
0 3
1 4
C 2
2 4
2 4
D 4
3 7
4 8
F 3
4 7
10 13
E 4
4 8
4 8
G 5
8 13
8 13
H 2
13 15
13 15
9inish
9or activity , which is the immediate predecessor $or two activities & K9', the latest #nish time is the smaller o$ the latest start times &5 K 1E'$or K 9 activit .
8sing -ackward Pass through the networ!@
-
8/9/2019 ES - 92 Project Management
27/38
-
8/9/2019 ES - 92 Project Management
28/38
*lac! in ritical Path$or eneral 9oundry, Inc.
Activity
EarliestStart,
ES
Earliest$inish,
E$
%atestStart,
%S
%atest$inish,
%$
Slac& OnCriticalPath'
A E 2 E 2 E Les
) E 3 1 5 1 :o
2 5 2 5 E Les
/ 3 > 5 ? 1 :o
5 ? 5 ? E Les
9 5 > 1E 13 0 :o
? 13 ? 13 E LesC 13 17 13 17 E Les
Activities A, , , , and C have no slac! time this means thatnone o$ them can be delayed without delaying the entire project.
"hese are called, critical activities and are said to be on criticalath .
-
8/9/2019 ES - 92 Project Management
29/38
A 2
0 2
0 2
ritical Path $or eneral 9oundry, Inc.
*tart
B 3
0 3
1 4
C 2
2 4
2 4
D 4
3 7
4 8
F 3
4 7
10 13
E 4
4 8
4 8
G 5
8 13
8 13
H 2
13 15
13 15
9inish
-
8/9/2019 ES - 92 Project Management
30/38
Probability o$ Project ompletion P " uses the variance o$ critical path activities to
help determine the variance o$ the overall project.I$ the activity times are statistically independent,the project variance is computed by summing thevariances o$ the critical activities@
project variance D N variances o$ activities on the critical path
-
8/9/2019 ES - 92 Project Management
31/38
Probability o$ Project ompletion
Cence, the project variance isproject variance D 5430 G 5430 G 30430G 05430 G 5430 D 3.111
CriticalActivity
Variance
A 5430
5430
30430
05430
C 5430
-
8/9/2019 ES - 92 Project Management
32/38
Probability o$ Project ompletion
17 (ee!s& xpected ompletion
"ime'
*tandard /eviation D1.>0 (ee!s
project standard deviation D σ T D &projectvariance' 142
D &3.111' 142 D 1.>0 (ee!s
-
8/9/2019 ES - 92 Project Management
33/38
Probability o$ Project ompletion
O D &due date 6 expected date o$completion' ÷ σ T
D &10 -17 (ee!s ' ÷ 1.>0D E.7>
eneral 9oundry,Inc. E#ample
where . is the number o$ standard
deviations the due date or target datelies $rom the mean or expected date
-
8/9/2019 ES - 92 Project Management
34/38
Probability o$ eneral 9oundry *tandard/eviation
10 (ee!s "ime
xpected "i me is 17 (ee!s
Probability&" 10
(ee!s'is >1.0Q
-
8/9/2019 ES - 92 Project Management
35/38
(hat P " was able to Provide
"he project
-
8/9/2019 ES - 92 Project Management
36/38
(hat P " was able to Provide
"hree activities &), /, 9' are not critical buthave some slac! time built in. "his means thatresources can be borrowed, i$ needed,
possibly to speed up the entire project.
5
A detailed schedule o$ activity starting andending dates has been made available.
7
-
8/9/2019 ES - 92 Project Management
37/38
*ensitivity Analysis andProject Management
Predecessor /ctivit 0 one that must be completedbe$ore the given activit can be started
,uccessor /ctivit 0 an activit that can be started
onl a$ter the given activit is &nished
Parallel /ctivit 0 an activit that does not directldepend on the given activit
-
8/9/2019 ES - 92 Project Management
38/38
*ensitivity Analysis andProject Management
ActivityTime
S(ccessorActivity
Parallel Activity Pre#ecessorActivity
arliest *tart Increase&decrease'
:o change :o change
arliest9inish
Increase&decrease'
:o change :o change
Fatest *tart Increase&decrease'
Increase&decrease'
:o change
Fatest 9inish Increase&decrease'
Increase&decrease'
:o change
*lac! :o change Increase&decrease'
:o change