EPCOR Distribution & Transmission Inc. · transformers, distribution electrical switchgear,...
Transcript of EPCOR Distribution & Transmission Inc. · transformers, distribution electrical switchgear,...
Decision 3206-D01-2015
EPCOR Distribution & Transmission Inc. Disposition of Substation Property February 25, 2015
Alberta Utilities Commission
Decision 3206-D01-2015
EPCOR Distribution & Transmission Inc.
Disposition of Substation Property
Proceeding 3206
Application 1610546-1
February 25, 2015
Published by the:
Alberta Utilities Commission
Fifth Avenue Place, Fourth Floor, 425 First Street S.W.
Calgary, Alberta
T2P 3L8
Telephone: 403-592-8845
Fax: 403-592-4406
Website: www.auc.ab.ca
Decision 3206-D01-2015 (February 25, 2015) • i
Contents
1 Introduction ........................................................................................................................... 1
2 Background ........................................................................................................................... 2
3 Legislation .............................................................................................................................. 5
4 Issues ...................................................................................................................................... 6 4.1 Ordinary retirement or extraordinary retirement............................................................ 6 4.2 Disposition of the asset and the ordinary course of the business ................................. 11 4.3 Assessment of harm ..................................................................................................... 18 4.4 Adjustment due to disposition ...................................................................................... 21
5 Order .................................................................................................................................... 23
Appendix 1 – Proceeding participants ...................................................................................... 25
Appendix 2 – Summary of Commission directions .................................................................. 26
List of tables
Table 1. EDTI – disposition of assets outside of ordinary course of business since the
Stores Block appeal ................................................................................................... 17
Decision 3206-D01-2015 (February 25, 2015) • 1
Alberta Utilities Commission
Calgary, Alberta
Decision 3206-D01-2015
EPCOR Distribution & Transmission Inc. Proceeding 3206
Disposition of Substation Property Application 1610546-1
1 Introduction
1. On May 5, 2014, EPCOR Distribution & Transmission Inc. (EPCOR or EDTI) filed an
application with the Alberta Utilities Commission (AUC or Commission) requesting approval to
dispose of a distribution substation property, which included the land and a substation building,
Substation No. 250 (substation), located at 9724 - 118 Avenue Northwest, Edmonton, Alberta.
EDTI submitted that the disposition was outside the ordinary course of business of the utility and
accordingly required the approval of the Commission pursuant to Section 101(2)(d) of the Public
Utilities Act, RSA 2000, c. P-45.
2. On May 7, 2014, the Commission issued a notice of application that required interested
parties to submit a statement of intent to participate (SIP) by May 21, 2014. In their SIPs, parties
were to indicate whether they supported or objected to the application, the reasons for their
position, the need for further process and the supporting rationale.
3. The Commission received SIPs from the Consumers’ Coalition of Alberta (CCA) and
AltaLink Management Ltd. (AML). In its SIP, the CCA requested the opportunity to test the
application with a process involving information requests, argument and reply argument. In its
SIP, AML indicated that it would choose to participate in the proceeding if certain issues became
material in nature. ATCO Electric Ltd. also registered as a participant in this proceeding, but it
did not file a SIP.
4. The Commission determined that the application would be considered by way of a
minimal written process described in Bulletin 2010-161 and issued the following schedule on
May 28, 2014.
Process step Deadline
Information requests to EDTI June 11, 2014
Information responses from EDTI June 25, 2014
Argument July 9, 2014
Reply argument July 23, 2014
5. On July 8, 2014, the Commission received a letter from EDTI requesting approval for an
extension to the deadline for filing argument and reply argument in order to allow for the filing
of a Phase II Environmental Assessment report for the substation property in response to a
Commission information request. In a July 9, 2014 letter, the Commission granted the extension
1 Bulletin 2010-16, Performance Standards for Processing Rate-Related Application, April 26, 2010.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
2 • Decision 3206-D01-2015 (February 25, 2015)
request and set the dates for filing argument and reply argument as July 16, 2014 and August 1,
2014, respectively.
6. After reviewing the record of the proceeding, the Commission determined that additional
information was required from EDTI. In a September 12, 2014 letter, the Commission reopened
the record and issued a supplemental round of information requests to EDTI, with a deadline for
responses of September 26, 2014. Parties were requested to provide submissions on the need for
additional argument and reply argument by September 19, 2014, and if no submissions were
received, the Commission would consider the close of record to be September 26, 2014.
7. On September 19, 2014, the Commission received a letter from the CCA indicating that
the CCA could not comment on the need for any additional process, including the need for
additional argument and reply argument, until it had the opportunity to review the supplemental
round of information responses submitted by EDTI.
8. On October 17, 2014, the Commission determined that after review of the information
responses from EDTI, that it required additional information and clarification from EDTI and the
CCA. The Commission issued a third round of information requests to both EDTI and the CCA,
with a deadline for responses of October 31, 2014. The Commission also established a
supplemental round of argument and reply argument to be provided from both parties, to be
submitted by November 14, 2014 and November 28, 2014, respectively. The Commission
considers the record for this proceeding to have closed on November 28, 2014.
9. In reaching the determinations set out in this decision the Commission has considered all
relevant materials comprising the record of this proceeding. References in this decision to
specific parts of the record are intended to assist the reader in understanding the Commission’s
reasoning relating to a particular matter and should not be taken as an indication that the
Commission did not consider all relevant portions of the record with respect to this matter.
2 Background
10. In the application, EDTI is requesting approval to dispose of a substation building, the
land on which the substation is located (and the remaining substation assets including
transformers, distribution electrical switchgear, protective relaying, and communications and
supervisory control and data acquisition (SCADA) equipment (collectively, the substation
electrical assets). The substation building and land upon which the substation building is located
are collectively referred to as the substation property. The substation electrical assets, the
substation building and the land are collectively referred to as the substation assets.
11. The bi-level substation housing five-kilovolt (kV) distribution feeders was built in 1957
and from 1957 to 2000, the substation was used by Edmonton Power Inc. The substation was
transferred to EPCOR Distribution Inc. the predecessor company of EDTI, on December 28,
2000. EDTI stated that the substation remained in service until 2012. The building has a footprint
of 1,748 square feet of main floor space, and an additional basement footprint of 1,748 square
feet beneath the main floor. Located on the east-side of the substation building are two
distribution substation (15/five kV) power transformers.
12. In 2012, EDTI commenced a program to convert the five-kV distribution feeders to
15-kV distribution feeders supplied through either EDTI’s Namao or Victoria substations, and
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 3
the program was completed in 2013. As a result, EDTI decommissioned the five-kV feeders at
the substation when they were merged into a nearby 15-kV circuit, and the substation was no
longer required for distribution electricity service in 2012. In AUC-EDTI-05,2 EDTI indicated
that the decommissioning process was planned in two stages. The first stage involved the
decommissioning of the five-kV feeders, while the second stage was to decommission the
substation building and land. EDTI estimated a total cost of $125,000 to decommission the
substation, which would be an operating cost to EDTI not paid by ratepayers. EDTI stated that
the substation building was not decommissioned at the same time as the five-kV feeders because
“the overall 5kV conversion project required a significant amount of work and certain portions
need to be scheduled around other higher priority work.”3 EDTI stated that service from the
substation is no longer required and the property otherwise plays no role in the provision of safe
and reliable service to ratepayers.4
13. In the application, EDTI indicated that it would undertake a “one off” project in 2014 to
decommission the remaining infrastructure located at the substation. EDTI explained that the
scope of this work would include the decommissioning and removal from service of EDTI’s
remaining substation electrical assets installed at the substation. This project would take
approximately three months to complete and would be scheduled pending Commission approval
of the disposition.
14. EDTI retained Gettel Appraisals Ltd. (Gettel) to perform land and building valuations for
the substation property for the future sale of the property. EDTI stated that it would sell the
substation property within the price range of $365,000 to $400,000, the estimated fair market
value, as determined by Gettel. In addition, the sale would also be conditional upon an
environmental assessment indicating that there are no environmental issues related to the lot,
thus insulating ratepayers from potential remediation costs.5
15. The substation property is recorded as a distribution asset in EDTI’s rate base. EDTI
provided its accounting records, and calculated the 2014 mid-year net book value of the
substation building in the amount of $103,092 using the direct life method (DLM) approach of
depreciation as of December 31, 2014, and the rate base value of the land as $1,492.6 EDTI
stated that the DLM approach only recognizes half a year of depreciation in the year of an
addition or a removal of an asset. The only asset that is not fully depreciated is the substation
building, including capital additions to the building. EDTI stated that the net book value of the
substation building was not removed from rate base during 2014 and depreciation continued to
be charged.7 EDTI stated that its DLM method uses a square-curve amortization approach for all
property classes. Therefore, all assets decommissioned as part of this project, including the
substation building, were depreciated using a square-curve method.8
16. With respect to the substation electrical assets, EDTI stated that the “redundant”
transformers, distribution electrical switchgear, protective relaying and communications and
SCADA equipment are no longer required to provide service to customers, as the load previously
2 Exhibit 11.01.
3 Exhibit 11.01, AUC-EDTI-05.
4 Exhibit 1, application, paragraph 13.
5 Exhibit 1, application, paragraph 11.
6 Exhibit 11.01, Table AUC-EDTI-01-1.
7 Exhibit 11.01, AUC-EDTI-01(a).
8 Exhibit 23.01, AUC-EDTI-07(c).
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
4 • Decision 3206-D01-2015 (February 25, 2015)
handled by the substation had been transferred to the 15-kV distribution system. EDTI confirmed
that, “… none of these [substation electrical assets] have been decommissioned. They are not
being used but the electrical equipment is still energized.”9
17. EDTI explained that it was not able to identify the original investment relating to the
substation electrical assets that it will decommission as part of this project. Therefore, it is not
able to calculate the accumulated depreciation for each of these assets at the time it
decommissions these assets. However, although the substation building has not been fully
depreciated, EDTI confirmed that the substation electrical assets have been fully depreciated and
retired from EDTI’s accounting records based on each assets type’s average service lives
consistent with the DLM approach. The average service life (in years) and the year of retirement
for each type of substation electrical asset were provided in response to AUC-EDTI-10.10
18. In assessing any harm to its ratepayers, EDTI stated that the proposed disposition of the
substation property will have no adverse effect on the quality and quantity of the service being
offered to ratepayers, and it will not create additional operating costs for the future. The
proposed disposition will also not a cause a break in the continuity of safe and reliable service to
ratepayers. The distribution feeders originating from the substation have been decommissioned
and as a result, electricity service from this substation is no longer required.11
19. The proposed disposition will lead to a small reduction in the costs currently borne by
ratepayers because the book value of the land ($1,492), and the remaining book value of the
substation building ($103,092) will be removed from EDTI’s distribution rate base. EDTI
confirmed that ratepayers will not be harmed by the disposition because service will not be
impacted and EDTI will pay the transaction costs arising from the disposition, such as the
$125,000 operating costs to decommission the substation, land appraisal fees, land agent fees and
legal fees, as all transaction costs will be netted against the proceeds from the property sale.12
EDTI stated that it would likely sell any equipment that is salvaged through the
decommissioning (such as old transformers) for scrap at an insignificant value expected to be
$2,750.13
20. EDTI proposed to remove the property from its revenue and rates at the time of a cost-of-
service rebasing at the end of the performance-based regulation (PBR) term in 2018. EDTI also
stated that if the sale and disposition of the property occurs prior to 2018, then the adjustment to
PBR revenue for the sale will still occur in the 2018 rebasing, and not during the current PBR
term.
21. In the rebasing application, EDTI stated that it would credit customers for the
accumulated depreciation relating to the substation building. The accumulated depreciation for
the substation building would be in the amount of $21,327, as of December 31, 2014,14 if the
disposition is approved by the Commission and the asset was disposed in 2014, which would
effectively pay customers back for their contribution to the facility. EDTI would then reduce its
rate base by the net book value of the substation building by removing the original cost to EDTI
9 Exhibit 23.01, AUC-EDTI-07(d).
10 Exhibit 28.01, AUC-EDTI-10.
11 Exhibit 1, application, paragraphs 12-13.
12 Exhibit 1, application, paragraph 14.
13 Exhibit 23.01, AUC-EDTI-07(a).
14 Exhibit 11.01, Table AUC-EDTI-01-1.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 5
from its predecessor and accumulated depreciation for the facility at the date that the property is
sold. EDTI will include any difference between the amount received from the sale of land, less
agent commissions and other costs incidental to the sale of the substation property, the original
cost of the building ($123,188) and the land ($1,492), in Account 922, Gains and Losses from
disposition of utility facility.15 The recording of the original cost of the land and the building in
Account 922 would result in the expected gain being to the account of the shareholder and not to
customers.
3 Legislation
22. As a designated owner of a public utility pursuant to Section 101(1) of the Public
Utilities Act and its regulation, EDTI is subject to Section 101(2) of the Public Utilities Act,
which states:
101(1) The Lieutenant Governor in Council may by regulation designate those owners of
public utilities to which this section and section 102 apply.
(2) No owner of a public utility designated under subsection (1) shall
…
(d) without the approval of the Commission,
(i) sell, lease, mortgage or otherwise dispose of or encumber its
property, franchises, privileges or rights, or any part of them, or
(ii) merge or consolidate its property, franchises, privileges or rights,
or any part of them,
and a sale, lease, mortgage, disposition, encumbrance, merger or
consolidation made in contravention of this clause is void, but nothing in
this clause shall be construed to prevent in any way the sale, lease,
mortgage, disposition, encumbrance, merger or consolidation of any of
the property of an owner of a public utility designated under subsection
(1) in the ordinary course of the owner’s business.
23. EDTI was deemed subject to the Public Utilities Designation Regulation, AR 194/2006
as if it had been designated under that regulation.16 Accordingly, Section 101(2)(d) applies to
EDTI.
15
Exhibit 11.01, AUC-EDTI-04. 16
The designated public utilities under the Public Utilities Designation Regulation, to which sections 101 and 102
of the Public Utilities Act apply, include in Section 1(1)(n) EPCOR Distribution Inc. and in Section 1(1)(o)
EPCOR Transmission Inc. In Decision 2006-134 for EPCOR Utilities Holdings Inc., EPCOR Distribution Inc.,
EPCOR Transmission Inc., Amalgamation and Related Tariff Amendments, Application 1487073,
December 22, 2006, the Alberta Energy and Utilities Board ordered: “EDTI is deemed to be subject to sections
101, 102 and 109 of the PUBA [Public Utilities Board Act, RSA 2000 c. P-45] following the completion of the
transaction and until such time as EDTI may be designated a “public utility” under the PUD Regulation [Public
Utilities Designation Regulation, AR 194/2006].”
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
6 • Decision 3206-D01-2015 (February 25, 2015)
4 Issues
4.1 Ordinary retirement or extraordinary retirement
24. EDTI indicated that the substation assets were no longer required for electric distribution
service effective upon the decommissioning of the five-kV feeders at the substation, and merger
into a nearby 15-kV circuit in 2012. EDTI stated that the remaining electrical assets and
substation building were not decommissioned at the same time as the five-kV feeders because
“the overall 5kV conversion project required a significant amount of work and certain portions
need to be scheduled around other higher priority work.”17 The application for the sale and
disposition of the substation property was filed in May 2014.
25. Although the substation electrical assets were fully depreciated at the time they ceased to
be used for electric distribution service, capital additions to the building had not been fully
depreciated and depreciation expense continues to be included in customer rates. A preliminary
issue for the Commission to determine is the proper accounting treatment in respect of the
undepreciated capital costs of the capital additions to the substation building, between the time
that the substation assets ceased to be used for electric distribution service and the time of the
final decommissioning, salvage or disposition of those assets and the substation building in
accordance with the application.
26. In a series of information requests the Commission referred to the Uniform System of
Accounts (USA),18 to Decision 2013-417,19 the Utility Asset Disposition (UAD) decision and to
the discussion in that decision with respect to “ordinary retirements” and “extraordinary
retirements” and the consequent responsibility for unrecovered capital costs at the time of an
asset’s retirement.20
27. The Commission asked EDTI to explain the retirement of the substation building and the
substation electrical assets and whether the decommissioning of the five-kV feeders at the
substation and merger into a nearby 15-kV circuit in 2013, which resulted in the building no
longer being required for distribution utility service in 2012, constituted an ordinary or an
extraordinary retirement. EDTI stated in response:
… the substation assets (with the exception of the land and building) were fully
depreciated and retired from EDTI’s accounting records at the end of their average
service life in line with EDTI’s DLM [direct life method] practice. The retirement of the
substation land and building is not an ‘extraordinary item’ as that term is used in the
USA. More specifically, it depends “primarily on decisions or determinations by
management or owners” as set out in the CIAC [sic] [Canadian Institute of Chartered
Accountants (CICA)] Handbook Section 3480, which is referenced in Item 7 on page 5 of
the USA General Instructions.21
28. In a supplemental information request, EDTI was asked to provide additional information
on the reasoning as to why the retirement of the land and substation building was not an
17
Exhibit 11.01, AUC-EDTI-05. 18
Bulletin 2006-25, Announcing the Approval in Principle of the Form and Content of a Uniform System of
Accounts and Minimum Filing Requirements for Alberta Electric Utilities, July 12, 2006. 19
Decision 2013-417: Utility Asset Disposition, Proceeding 20, Application 1566373, November 26, 2013. 20
Decision 2013-417, see in particular paragraphs 302-305. 21
Exhibit 23.01, AUC-EDTI-07(f).
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 7
“extraordinary item,” based on the CICA Handbook Section 3480, Item 2 on page 4 of the USA
General Instructions, which stated the following:
02 Extraordinary items are items which result from transactions or events that have all
of the following characteristics:
(a) they are not expected to occur frequently over several years;
(b) they do not typify the normal business activities of the entity; and
(c) they do not depend primarily on decisions or determinations by management or
owners.”22
29. In response to the Commission’s information request, EDTI stated that the retirement of
the substation land and building meet characteristics (a) and (b), but did not meet characteristic
(c), as used in the USA General Instructions and defined by Section 3480 of the CICA
Handbook. EDTI indicated that retirement of the substation land and building does depend
“primarily on decisions or determinations by management or owners.” As a result, the retirement
of the substation land and building do not meet all of the required characteristics, and is therefore
not an “extraordinary item.”23
30. EDTI stated that when originally installed, the five-kV voltage service provided by the
substation was a standard voltage. However, the five-kV voltage service is now a non-standard
voltage within EDTI’s service area, and all new circuits are now constructed either at 15 kV or
25 kV. EDTI indicated that its customers were converted from the five-kV distribution feeders
from the substation to 15-kV distribution feeders from other existing substations because
replacing the existing five-kV equipment with 15-kV equipment at the same substation would
not be practical given space constraints and the potential for significant outages.24
31. EDTI also noted that the average age of its five-kV substations is 58 years. As a result,
most of the equipment in these substations is obsolete and is no longer being supported by the
manufacturer. The five-kV system is also becoming increasingly difficult to maintain
economically. If it were to retain the five-kV system, EDTI would be required to maintain a third
distribution voltage within its system, which would require a variety of different types of
infrastructure assets such as insulators to be held in stock. There has also been load growth
within its service area. Increasing the voltage level of the distribution primary feeder from
five kV to 15 kV allows for greater capacity using less current, less voltage drop and decreased
line losses.25
32. EDTI confirmed that the substation electrical assets were fully depreciated and were
retired from the accounting records at the end of their average service lives in accordance with
the DLM approach whether or not they were physically decommissioned at the same time. EDTI
further noted that it does not track [these] individual assets in its accounting records, and that the
total asset additions for a given year in a category are retired at mid-year in the year in which
their service life expires.26
22
CICA Handbook Section 3480, Item 2, page 4. 23
Exhibit 28.01, AUC-EDTI-09(a). 24
Exhibit 28.01, AUC-EDTI-09(e) and (f). 25
Exhibit 28.01, AUC-EDTI-09(e) and (g). 26
Exhibit 28.01, AUC-EDTI-10.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
8 • Decision 3206-D01-2015 (February 25, 2015)
33. When asked by the Commission if the substation became no longer required for utility
service as the result of causes that were or were not reasonably assumed to have been anticipated
or contemplated in prior depreciation or amortization provisions, EDTI indicated the following:
… EDTI decommissioned the 5kV feeders in 2012 when they were merged into a nearby
15kV circuit. At this time, the substation electrical equipment assets were already fully
depreciated. As these assets were installed 57 years ago, EDTI no longer has historical
records (including depreciation studies) going back far enough to confirm whether causes
such as this were ever anticipated or contemplated in prior depreciation or amortization
provisions. Further, causes such as this were not mentioned in EDTI’s 2003 depreciation
study included in Appendix O of EPCOR Distribution Inc.’s 2004 Distribution Tariff
Application.27
34. Finally, EDTI submitted that the terms “ordinary retirement” and “extraordinary
retirement” are not relevant to electric utilities, as these terms are reserved for gas utilities under
the Uniform Classification of Accounts for Gas Utilities Regulation, AR 546/1963.28
35. No submissions were provided by the CCA on this issue.
Commission findings
36. The Commission does not consider it necessary to determine if the decommissioning of
the five-kV feeders or the remaining electrical equipment and substation building constitute
either an ordinary retirement or an extraordinary retirement given:
(a) EDTI’s expressed intention at the time it decommissioned the five-kV feeders to also
decommission the remaining electrical equipment and the substation building when other
service priorities would allow, and
(b) the Commission’s findings in Section 4.2 below that the proposed disposition of the
substation building and land constitutes a disposition outside of the ordinary course of
EDTI’s business with all costs of disposition and all proceeds or losses accruing to the EDTI
shareholder.
37. The determination of ordinary or extraordinary retirement is relevant to the question of
accountability for any unrecovered net book value of an asset at the time of retirement. However,
where the intention is expressed to dispose of the asset at the time that the asset ceases to be used
for electric distribution service and the planned disposition is outside of the ordinary course of
business of the utility, the nature of the retirement is generally moot. If the time period between
the time that an asset ceases to be used for electric distribution service and the time that the asset
is disposed of, is unreasonable or material in the circumstances, the Commission may be required
to consider the asset to have retired at the time it ceased to be used for utility operational
purposes and it may be required to consider whether that retirement was ordinary or
extraordinary. This will be the case in circumstances where ratepayers continue to pay
depreciation expense in respect of the asset that is no longer required for utility purposes and is
intended for salvage or disposition. The time period between when the substation ceased to
provide electric distribution service and the anticipated time of disposing of the substation
property is discussed further below.
27
Exhibit 28.01, AUC-EDTI-09(e) and (g). 28
Exhibit 29.01, supplemental EDTI argument, paragraph 9.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 9
38. In support of the above findings, the Commission refers to the following EDTI evidence
which provide the reasons for decommissioning the substation in a two-stage process: the
intention to dispose of the substation building made at the time that the five-kV feeders were
decommissioned, the reasons why undepreciated capital costs on the building had not been fully
recovered at the time that the five-kV feeders were decommissioned and the efforts taken to
complete the two-stage decommissioning and asset disposition process:
The substation was built in 1957.
The average age of a five-kV substation is 58 years.
The five-kV voltage service is now a non-standard voltage within EDTI’s service area,
and all new circuits are now constructed at either 15 kV or 25 kV.
Replacing the existing five-kV equipment with 15-kV equipment at the same substation
would not be practical, given factors such as space constraints and the potential for
significant outages to customers as the old five-kV equipment is removed and new 15-kV
equipment is installed.
Most of the equipment in the substation is obsolete and is no longer being supported by
the manufacturer, making the five-kV system increasingly difficult to maintain. If EDTI
were to retain the five-kV system, it would be required to maintain a third distribution
voltage with its system. This would also require a variety of types of infrastructure assets
such as insulators to be held in stock.
In 2012, EDTI commenced a program to convert its remaining five-kV distribution
feeders to 15-kV distribution feeders shortly after the filing of its 2012 Phase I and II
Distribution Tariff and its 2012 Transmission Facility Owner Tariff application
(Proceeding 1596, Application 1607944,) on November 30, 2011.
In AUC-EDTI-05, EDTI indicated that the decommissioning process was planned in two
stages. The first stage involved decommissioning the five-kV feeders, while the second
stage was to decommission the substation building and property. EDTI estimated a total
cost of $125,000 to decommission the substation, which would be an operating cost to
EDTI not paid by ratepayers. EDTI stated that the substation building was not
decommissioned at the same time as the five-kV feeders because, “the overall 5kV
conversion project required a significant amount of work and certain portions need to be
scheduled around other higher priority work.” 29
EDTI indicated that while the electrical distribution assets were fully depreciated, the net
book value of the building was $101,860 and accumulated depreciation of the substation
building was $21,327, as of December 31, 2014.30 The direct life method of depreciation
used by EDTI, retires assets from service at the end of the average service life approved
as part of the depreciation study or review, regardless of whether they ceased to be used
prior to, or continue to be used after, the end of the average service life. As a result, while
it appears that that substation building was retired from the accounting records at the end
29
Exhibit 11.01, AUC-EDTI-05. 30
Exhibit 11.01, Table AUC-EDTI-01-1.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
10 • Decision 3206-D01-2015 (February 25, 2015)
of its estimated 50 year service life, there remains historical costs being recovered
through EDTI’s direct life method that are related to 1996 to 2007 maintenance capital
additions to the building which have resulted in the recovery of accumulated depreciation
related to the building in rates. The fact that the capital additions to substation building
were not fully depreciated at the time that it ceased to be used for electric distribution
service appears to be the result of this depreciation methodology.
39. While the Commission has determined that in the circumstances of the present
proceeding that it need not determine if the decommissioning of the five-kV feeders or the
subsequent retirement of the remaining electrical assets and substation building constituted an
ordinary or an extraordinary retirement, the Commission remains concerned with respect to the
timing of the disposition process for the substation. The length of time between when the
substation ceased to provide electric distribution services in 2012 and the application to dispose
of the substation building in May 2014 serves to emphasis that it is incumbent on EDTI to act
promptly in removing assets from rate base that are no longer required to be used for electricity
service, so as not to prejudice ratepayers. Once an asset is no longer required for utility purposes,
the utility must act expeditiously in taking prudent steps to salvage or to sell the asset in order to
mitigate depreciation costs and/or return and taxes paid by ratepayers.
40. Regardless of whether a retirement would be considered as an ordinary retirement or as
an extraordinary retirement, or whether a disposition is within or outside of the ordinary course
of business, when an asset ceases to provide utility services, it should be retired and salvaged or
otherwise disposed of within a reasonable period of time in order to mitigate depreciation costs
and/or return and taxes included in rates. As noted by the Alberta Court of Appeal in Atco Gas
and Pipelines Ltd v. Alberta (Utilities Commission) 2014 ACA 28 (Salt Caverns II decision):
65. In summary:
1. Assets not being used or required to be used for utility service are not to be
included in the rate base; and
2. a utility has the responsibility to withdraw assets from the rate base once the
assets are no longer used or required to be, and no Commission approval is
required. Such removal is, of course, subject to a prudency review by the
Commission.
41. Should assets not be retired, salvaged or disposed of, within a reasonable period after
they cease to be used in providing utility service, the Commission may disallow depreciation
costs and/or return and taxes that would otherwise not have been collected from ratepayers had
the assets been retired, salvaged or disposed of within a reasonable time period.
42. EDTI had the obligation to take reasonable measures to salvage or otherwise dispose of
the substation building upon the decommissioning of the five-kV feeders in order to mitigate the
impact to ratepayers of the remaining depreciation expense, return and taxes in respect of the
capital additions made to the building. Although the Commission remains concerned with the
period of time that elapsed subsequent to the decommissioning of the five-kV feeders until EDTI
proceeded with steps to decommission the building, the Commission is prepared, given the
unique circumstances of this case, to accept EDTI’s explanation with respect to why it did not
undertake the “one off” project to decommission the building and equipment sooner. EDTI
indicated that its management made the decision to delay the decommissioning work required for
the substation building because the overall five-kV conversion project required a significant
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 11
amount of work and certain portions needed to be scheduled around other higher priority work.
The Commission also accepts that the decommissioning delay had no impact on customers with
respect to quality and quantity of service. It also did not have a significant impact on customer
costs given the minimal impact of the accumulated depreciation collected from customers in
2012 and 2013. For these reasons, the Commission will not disallow the recovery of depreciation
expense associated with the substation building capital additions after the asset ceased to provide
electric distribution service.
4.2 Disposition of the asset and the ordinary course of the business
43. EDTI has indicated that its proposed disposition of the substation property is outside the
ordinary course of business and therefore requires the prior consent of the Commission pursuant
to Section 101(2)(d) of the Public Utilities Act. The CCA stated that the disposition is within the
ordinary course of business.
44. EDTI stated that the determination of whether a gain is recorded on the building
retirement and disposition is based on whether the disposition is classified as being within or
outside the ordinary course of business. If the disposition is within the ordinary course of
business, no gain would be recorded. If the disposition is outside the ordinary course of business,
a gain would be recorded on the account of the shareholder. If the building retirement and
disposition was classified as being within the ordinary course of business, EDTI would account
for the disposition in a manner such that no gain would be recorded by crediting the value of the
proceeds of the building (less disposal costs) to the asset account in which the cost of the
building was originally recorded.31
45. EDTI submitted that the relevant criteria in determining whether a disposition is outside a
utility’s ordinary course of business were clarified in Decision 2013-417, the UAD decision.
Rather than requiring a utility to consider the ten items previously delineated in Decision
2011-450,32 the Commission determined in that decision that a utility only needs to regard the
criteria previously articulated in the Alberta Energy and Utilities Board’s (the board) Order
U2001-196.33 That order confirmed that consideration of proceeds of disposition or quantum,
materiality, net book value, frequency and type of sale are the relevant factors for an assessment
of whether a disposition is within or outside the ordinary course of business. In that decision, the
board stated the following:
… The Board confirms that it must first determine whether the disposition of an asset is
outside the ordinary course of business for a utility. The proceeds of disposition, NBV,
frequency and type of sale would be among the factors considered by the Board in that
determination. The quantum, and materiality (in relation to the total rate base) of the
proceeds of disposition and the NBV would all be considered. For example in this case,
the NBV of $2,163,801 would be at the bottom end of the range of dispositions the Board
would consider as outside the ordinary course of business. With respect to the frequency
and type of sale the Board does not agree with NGTL that acquiring and divesting
regional service centres, maintenance facilities, and field offices are necessarily in the
ordinary course of NGTL’s business. The Board considers that NGTL’s ordinary
31
Exhibit 28.01, AUC-EDTI-09(h). 32
Decision 2011-450: ATCO Gas (a Division of ATCO Gas and Pipelines Ltd.), 2011-2012 General Rate
Application Phase I, Proceeding 969, Application 1606822, December 5, 2011. 33
Order U2001-196: In the Matter of the Sale of the Athabasca Maintenance Facility Application 2001112,
File 6417-04, August 3, 2001.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
12 • Decision 3206-D01-2015 (February 25, 2015)
business is the owning and operating of a pipeline, not the acquiring and divesting of real
estate.34
46. In its supplemental argument, EDTI stated that the disposition of the substation land and
building is outside the ordinary course of its business, and any gain on the disposition is for the
account of the utility. EDTI stated that the factors it identified are generally consistent with the
factors described in Decision 2011-450, as being relevant to determine that the disposition is
outside the ordinary course of business.
47. In a series of information requests, the Commission asked EDTI and the CCA for the
criteria or considerations that should be employed in determining whether the disposition of the
substation property is within or outside the ordinary course of the business. EDTI was asked to
identify factors such as: the frequency and type of disposition, materiality of the proceeds of
disposition in relation to the total rate base, net book value, whether the disposition is a normal
business activity of EDTI, whether the disposition depends primarily on a decision of
management, whether the functionality of the asset being disposed has been relocated, or any
other factors that were considered by EDTI in determining whether a disposition would be in, or
outside, the ordinary course of business. EDTI provided the following responses in respect of
each of the requested factors:
Materiality – EDTI explained that the estimated proceeds of the disposition is
approximately $370,000 to $400,000, and is material. This assessment of materiality is
based on the Commission’s other previous approved dispositions as outside the ordinary
course of business. In this case, EDTI stated that it considers the proceeds of a sale
amount to be material if it is greater than $500,000. Lastly, EDTI’s previous four
dispositions, approved by the Commission, were considered to be outside the ordinary
course of business.
Relocation of the functionality of the asset – EDTI explained that no portion of the
functionality of the land or the building has been relocated to an existing facility or will
be relocated to a new facility.
Frequency and type of asset dispositions – EDTI stated that the disposition of this type of
asset occurs infrequently (less than once per year over 2011 to 2013).
Market value – EDTI stated that the anticipated proceeds are expected to be consistent
with the market value assessment provided by Gettel. EDTI stated that it expects to
dispose of the building for an amount within the fair market value range contained in the
assessment.35
48. EDTI stated that it “acknowledges that the anticipated proceeds from this disposition will
be just below the materiality threshold of $0.5 million suggested in EDTI’s response to AUC-
EDTI-08 (d). However, given the infrequency and type of this transaction, along with the fact
that the assets will not be relocated, EDTI submitted that this disposition should be categorized
as falling outside the ordinary course of business.”36 In addition, acquiring and divesting property
34
UAD Decision 2013-417, paragraph 72. 35
Exhibit 28.01, AUC-EDTI-08 and Exhibit 29.01, EDTI supplemental argument, paragraph 3. 36
Exhibit 29.01, EDTI supplemental argument, paragraph 6.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 13
is occasionally incidental to EDTI’s operations but its ordinary business is the ownership and
operation of distribution and transmission facilities.
49. In response to the Commission’s information request, the CCA made the argument that
the proposed disposition was within the ordinary course of business, and that the proceeds should
be retained by EDTI for customers and applied to utility service. The CCA indicated that
Decision 2011-450 established $1.5 million as the threshold for ATCO Gas. The ATCO Gas
threshold and the guidelines for a threshold was affirmed in the UAD decision and the
Commission indicated that other utilities could apply for monetary threshold guidelines to
determine if a transaction is within or outside the ordinary course of business. However, EDTI
did not apply for such a threshold in this proceeding, and did not provide its rationale for how the
$500,000 threshold amount was selected in this application.37
50. In its supplemental reply argument, the CCA proposed that EDTI’s threshold should be
$500,000 or $750,000, based on ATCO Gas’s mid-year rate base of $1.86 billion as compared to
EDTI’s mid-year rate base of $906 million or roughly 50 per cent of ATCO Gas’s rate base.
Therefore, EDTI’s threshold should be 50 per cent of ATCO Gas’s threshold established in
Decision 2013- 417, which is $750,000.
51. The CCA stated that EDTI also failed to pass its own very low materiality threshold,
therefore, the transaction does not appear to be outside the ordinary course of business.
52. In regard to the frequency criterion, the CCA indicated that frequency helps to provide
assistance where there are multiple transactions over a short period of time which would suggest
that the transaction is within the ordinary course of business, however the opposite is not
necessarily true. The CCA stated that infrequent transactions do not necessarily mean that the
transaction is outside of the ordinary course of business. The CCA noted that EDTI had four
sales in approximately eight years, however little weight should be attached to the frequency
measure.38
53. The CCA proposed that an additional criterion be added to the factors outlined in
Decision 2011-450, and the Commission should consider the reason for the disposition. The
CCA added that the disposition should depend primarily on a management decision, and that this
disposition appears to be a management decision in determining when to decommission the
facility. However, if management’s determination does not otherwise fit the rest of the criteria,
then the disposition cannot be considered outside the ordinary course of business. Since the
disposition amount did not exceed the materiality threshold, a management’s decision or
determination would be irrelevant in this proceeding. Therefore, the disposition of the assets
related to five-kV voltage service would be inside the ordinary course of business.39
54. In response to the CCA, EDTI stated that although materiality is a relevant consideration,
the $1.5 million threshold does not apply to EDTI because this threshold was established for
ATCO Gas. EDTI stated that the Commission should give little weight to the CCA’s reasoning
that the frequency criterion is inconsistent with Decision 2013-417, because the decision
specifically confirms frequency as a factor relevant to the determination of whether a transaction
37
Exhibit 31.01, CCA supplemental reply argument, paragraphs 4-13. 38
Exhibit 31.01, CCA supplemental reply argument, paragraphs 10-13. 39
Exhibit 30.01, CCA supplemental argument, paragraphs 24-27.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
14 • Decision 3206-D01-2015 (February 25, 2015)
is outside the ordinary course of business. EDTI stated that transactions similar to the proposed
disposition occur very rarely, at a rate of less than once a year. Therefore, frequency is a key
consideration to assessing whether the sale of property is outside its ordinary course of business.
In addition, EDTI’s ordinary business is the ownership and operation of distribution and
transmission facilities not the acquisition and sale of property.40
Commission findings
55. Section 101(2)(d) of the Public Utilities Act as it has been determined to apply by the
Commission to EDTI, prevents a designated owner of a public utility from disposing of assets
outside the ordinary course of business without first obtaining the prior consent of the
Commission. Any disposition without such prior consent is void.
56. In the application, EDTI proposed to remove the substation building and land from its
rate base through a sale to a third party at fair market value pursuant to a transaction that has yet
to be determined.
57. The Commission must determine whether the disposition of the substation property is
within, or outside, the ordinary course of EDTI’s business. The term “ordinary course of
business” has existed in law for many years, and as noted by the Supreme Court in ATCO Gas &
Pipelines Ltd. v. Alberta (Energy & Utilities Board), 2006 SCC 4 (Stores Block), the
Commission’s predecessors, determined the approval of public utilities sale of property outside
of the ordinary course of business as early as 1915.41
58. As noted above, Order U2001-196, described the factors to be considered on whether the
disposition of an asset is outside the ordinary course of business, as follows:
… The Board confirms that it must first determine whether the disposition of an asset is
outside the ordinary course of business for a utility. The proceeds of disposition, NBV,
frequency and type of sale would be among the factors considered by the Board in that
determination. The quantum, and materiality (in relation to the total rate base) of the
proceeds of disposition and the NBV would all be considered. For example in this case,
the NBV of $2,163,801 would be at the bottom end of the range of dispositions the Board
would consider as outside the ordinary course of business. With respect to the frequency
and type of sale the Board does not agree with NGTL that acquiring and divesting
regional service centres, maintenance facilities, and field offices are necessarily in the
ordinary course of NGTL’s business. The Board considers that NGTL’s ordinary
business is the owning and operating of a pipeline, not the acquiring and divesting of real
estate.42
59. Other factors previously considered by Commission, or its predecessors, were also
identified in paragraph 276 of Decision 2011-450:
276. This panel of the Commission concurs with the earlier decisions of the
Commission and its predecessor that materiality and frequency are relevant factors to
consider when determining whether the disposition of an asset is within or outside of the
ordinary course of business. The Commission considers that the approach outlined by
Ms. Wilson at the oral hearing provides a satisfactory balance between bringing multiple
40
Exhibit 32.02, EDTI supplemental reply argument, paragraph 6. 41
Stores Block, paragraph 55. 42
Order U2001-196, pages 3-4.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 15
minor applications to the Commission for review while ensuring that substantive
transactions are brought forward for consideration. The Commission agrees that $1.5
million is a reasonable transaction value at this time to use as a threshold guideline.
Should the transaction price be over $1.5 million, AG will be required to bring an
application for Commission approval under Section 26(2)(d) of the Gas Utilities Act. If
the transaction price is less than $1.5 million, AG should consider if there are other
factors that would suggest that the transaction is outside of the ordinary course of
business and therefore require the consent of the Commission to the disposition. Those
other factors would include:
the quantum and materiality of the proceeds of disposition in relation to the total
rate base of the utility
the quantum and materiality of the net book value of the asset in relation to the
total rate base of the utility
whether all or any portion of the functionality of the asset being disposed of has
been relocated to an existing facility or relocated to a new facility
the frequency and type of disposition of like assets
the other party(ies) to the transaction and if the transaction involves an affiliate,
whether the ATCO Group Inter-Affiliate Code of Conduct has been complied
with
the market value of the asset when compared to the consideration received on the
disposition
the allocation of sale proceeds between depreciable and non-depreciable property
the net book value of the assets
whether the asset was a utility or non-utility asset
any other unique or distinguishing aspect of the asset or of the transaction.43
60. In the UAD decision, the Commission clarified the application of the criteria to be
applied in determining whether a disposition is within or outside the ordinary course of business
of a particular utility:
321. The Commission considers that the criteria articulated in Order U2001-196 are
sufficient for the utility to determine whether a disposition is inside or outside the
ordinary course of business for the purpose of determining if an application for approval
of the disposition must be filed. While the additional criteria provided for in Decision
2011-450 may be useful to the Commission in evaluating specific cases, the Commission
does not consider that these criteria are necessary for the utility to consider in making a
determination of whether it must apply for approval of a disposition. … [T]he utilities
may limit the criteria they use in determining whether an application in respect of a
proposed disposition of an asset is necessary to the criteria described in Order U2001-
196.44
61. In the present circumstances, the Commission considers that the determination of whether
the substation disposition is to be considered inside or outside the ordinary course of EDTI’s
business must be assessed given the nature of the transaction, the factors set out in Order
U2001-196 and the evidence disclosed on the record.
43
Ibid., paragraph 276. 44
Decision 2013-417, paragraph 321.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
16 • Decision 3206-D01-2015 (February 25, 2015)
62. EDTI submits that the disposition of the substation property should be considered to be
outside the ordinary course of business, because of the following factors:
The materiality of the proceeds of disposition; and the fair market value of the asset.
The frequency of the transactions for the disposition of the type of asset.
Relocation of the functionality of the asset.
63. The CCA stated that the reason for the disposition and whether the disposition is within
management’s control are additional factors that should be considered by the Commission.
64. With respect to the substation disposition, the Commission provides its findings on the
factors raised in this proceeding on whether the disposition of the substation property is inside or
outside the ordinary course, in the subsections below.
Materiality
65. As noted above, in Decision 2011-450, the Commission established a transaction value
materiality threshold of $1.5 million for ATCO Gas in assessing whether an asset disposition is
outside of the ordinary course of business. However, if the transaction value was found to be less
than $1.5 million, then ATCO Gas was directed to consider if there are other factors that would
suggest that the transaction is outside of the ordinary course of business.
66. In the UAD decision, the Commission provided the following on materiality thresholds
with respect to regulated utilities:
322. The $1.5 million threshold established for ATCO Gas in Decision 2011-450 as a
guideline for determining when a transaction will be considered to be outside of the
ordinary course of business will continue to apply. Each other utility may apply for a
monetary threshold guideline applicable to their company in determining if a transaction
is within or outside of the ordinary course of business.45
67. EDTI submitted that the $1.5 million threshold that was established for ATCO Gas is
specific to that company and should not be applied to EDTI. In AUC-EDTI-08(d), EDTI
suggested a materiality threshold of $500,000. EDTI did not provide a complete basis for the
$500,000 suggested materiality threshold but noted in its supplemental argument that the
proposed threshold amount should not be determinative in the present application, stating:
EDTI acknowledges that the anticipated proceeds from this disposition will be just below
the materiality threshold of $0.50 million suggested in EDTI’s response to AUC-EDTI-
08 (d). However, given the infrequency and type of this transaction, along with the fact
that the assets will not be relocated, EDTI submits that this disposition should be
categorized as falling outside the ordinary course of business.46
68. In Decision 2011-211,47 the Commission considered an EDTI disposition of substation
land with a fair market value for the portion of land to be sold of $1,007,000. The Commission
45
Decision 2013-417, paragraph 322. 46
Exhibit 29.01, EDTI supplemental argument, paragraph 6. 47
Decision 2011-211: EPCOR Distribution &Transmission Inc., Disposal of Substation Land, Proceeding 1091,
Application 1607037, May 17, 2011.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 17
determined that the transaction was outside the ordinary course of business and approved the sale
of the substation land.
69. The CCA filed a table from Proceeding 2191, the 2013 Generic Cost of Capital
proceeding,48 with respect to the transaction value and frequency of past EDTI dispositions
considered outside the ordinary course of business commencing in 2006 which is reproduced
below as Table 1. As seen in Table 1, dispositions approved by the Commission have ranged
from a sales price of $101,000 to $2,261,000:
Table 1. EDTI – disposition of assets outside of ordinary course of business since the Stores Block appeal
($000) A B C= A-B D E F= D-E G
Transaction
year
Original cost
(land)
Original cost
(building)
Original cost total
Accumulated depreciation
Net book value
Sale price
Selling costs
Net proceeds
Total gain on
sale
West Service Center
2006 245 266 510 147 363 2,261 95 2,166 1,802
Meter Hall 2006 107 75 182 45 138 268 14 253 116
West Edmonton
Storage Site 2007 - - 12 2 10 101 8 93 83
Substation Land (300 and 360)
2011 2 0 2 0 2 1,007 0 1,007 1,005
70. The Commission agrees that the materiality threshold proposed and accepted for ATCO
Gas should not be applied to EDTI, however given the wide range of EDTI transactions
approved as being outside of the ordinary course of business and without further explanation and
testing of the proposed $500,000 threshold amount and how it might apply in general to EDTI
dispositions, the Commission will not establish a generic materiality threshold amount for EDTI
at this time. However, given that both the value of the proposed transaction and the net book
value at the time of disposition, fall within the range of prior approvals, the Commission
considers that this factor suggests that the proposed disposition is outside of the ordinary course
of EDTI’s business.
Frequency and type
71. EDTI noted that it did not normally engage in the selling of property, and that its primary
function is to provide electric distribution services to customers within its service territory.
72. Table 1 above demonstrates that although the disposition of land and buildings do occur,
EDTI distribution engages in these types of transactions infrequently and not as part of any core
activity necessary to provide electric distribution services. Further, the disposition of a substation
has occurred only once in the past four years. Accordingly, the frequency and type of disposition
which is the subject of this application suggests that the proposed disposition is outside of the
ordinary course of EDTI’s business.
48
Proceeding 2191, Application 1608918, the table was reproduced from Exhibit 136.01 of the Generic Cost of
Capital proceeding.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
18 • Decision 3206-D01-2015 (February 25, 2015)
Conclusion
73. Based on the above analysis, the Commission finds EDTI’s proposed sale of the
substation land and building is a disposition outside of the ordinary course of EDTI’s business
and requires the prior consent of the Commission pursuant to Section 101(2)(d) of the Public
Utilities Act.
4.3 Assessment of harm
74. In deciding whether an application for Commission approval of a disposition outside of
the ordinary course of business under Section 101(2)(d) if the Public Utilities Act, the
Commission and its predecessor, the board, have traditionally applied a “no harm” test in
assessing whether the disposition will negatively affect service quality or quantity, or rates.
75. In the application, EDTI confirmed that the proposed disposition will have no adverse
effect on the quality and quantity of the customer services, nor will it create additional operating
costs in the future.49
76. With respect to service quality and quantity, EDTI indicated that the proposed disposition
will not impact the continuity of safe and reliable service to ratepayers because the distribution
feeders which originated from the substation have been decommissioned. The substation
property no longer plays a role in the provision of safe and reliable service to EDTI’s
ratepayers.50
77. With respect to rate impacts, EDTI stated that the proposed disposition would lead to
slight savings for ratepayers once EDTI removed the substation from its rate base. EDTI also
indicated that ratepayers would be protected from potential environmental clean-up costs on the
property51 and that EDTI would bear all remediation expenses prior to the disposition.52
Remediation requirements were identified in the Phase II Environmental Assessment report
completed by Blanchard Environmental Consulting (Blanchard) and filed with the Commission
on July 15, 2014. This report identified hydrocarbon levels exceeding guidelines in soil samples
near the transformer pad on the property, as well as boron concentrations that exceeded
guidelines on the eastern portion of the site. Remediation will delay the decommissioning and
disposition of the property until sometime in 2015.
78. In addition, EDTI confirmed that ratepayers would not pay transaction costs such as land
appraisal fees, land agent fees and legal fees because transaction costs will be netted against the
proceeds from the sale of the property.
79. The CCA stated that the cumulative impact on revenue requirement would amount to
approximately $50,000 over the five-year PBR term given that the substation generated an
annual revenue amount of $10,000 reflected in the PBR base rates of EDTI. In the CCA’s view,
customers should not have to pay $50,000 for an asset that is no longer used and useful.53
49
Exhibit 1, application, paragraph 12. 50
Exhibit 1, application, paragraph 13. 51
Exhibit 1, application, paragraph 14. 52
Exhibit 17.01, EDTI argument, paragraph 8. 53
Ehbitit 15.01, CCA argument, paragraph 9.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 19
80. In reply argument, EDTI indicated that the $50,000 figure was based on speculation and
was unsupported by any evidence.54
81. EDTI stated that based on its Phase II Environmental Assessment report, the cumulative
impact on its revenue requirement would likely be $30,000 (or less), not the $50,000 amount
identified by the CCA. EDTI stated that the $30,000 is an insignificant amount which would
have very little impact on customers rates and would not “certainly exceed any regulatory
proceeding costs” when the cumulative costs of all parties’ time and expenses are determined.55
Commission findings
82. The no harm test traditionally applied by the Commission and its predecessors has been
reviewed in several board, Commission and court decisions56 and was summarized in Decision
2000-41,57 where the board stated:
The Supreme Court of Canada has stated that the Board’s jurisdiction to “safeguard the
public interest in the nature and quality of the service provided to the community by
public utilities” is “of the widest proportions.” The Board has also noted that its
governing legislation provides no specific guidance for the exercise of the Board’s
direction in approving an asset disposition by a designated owner of a public utility.
The Board has held that its discretion under essentially similar provisions of the GU Act
must be exercised according a “no-harm” standard. More specifically, the Board has held
that it must be satisfied that customers of the utility will experience no adverse impact as
a result of the reviewable transaction.
…
The Board believes that its duty to ensure the provision of safe and reliable service at just
and reasonable rates informs its authority to approve an assets disposition by a public
utility pursuant to Section 91.1(2) of the PUB Act. Therefore, the Board is of the view
that, subject to those issues which can be dealt with in future regulatory proceedings …,it
must consider whether the disposition will adversely impact the rates customers would
otherwise pay and whether it will disrupt safe and reliable service to customers. As
already noted, the Board also accepts that it must assess potential impacts on customers
in light of the policy reflected in the EU Act, namely the unbundling of the generation,
transmission and distribution components of electric utility service and the development
of competitive markets and customer choice. As a result, rather than simply asking
whether customers will be adversely impacted by some aspect of the transactions, the
Board concludes that it should weight the potential positive and negative impacts of the
transactions to determine whether the balance favours customers or at least leaves them
no worse off, having regard to all of the circumstances of the case. If so, then the Board
considers that the transactions should be approved.58
(footnotes omitted)
83. The Supreme Court of Canada stated in Stores Block, the board determined that where
there was no harm or risk of harm from the sale and the board, “should only exercise its
54
Exhibit 19.01, EDTI reply argument, paragraph 3. 55
Exhibit 19.01, EDTI reply argument, paragraphs 5-6. 56 See for example the Stores Block decision, at paragraphs 83-84. 57 Decision 2000-41: TransAlta Utilities Corporation Sale of Distribution Assets, Application 2000051,
File 6404-3, July 5, 2000. 58
Ibid., pages 7-8.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
20 • Decision 3206-D01-2015 (February 25, 2015)
discretion to act in the public interest when customers would be harmed or would face some risk
of harm.”59
84. In ATCO Gas and Pipelines v. Alberta (Energy and Utilities Board) 2009 ABCA 171
(Harvest Hills), the Court of Appeal of Alberta considered the “no harm” test in the context of
the sale of land by ATCO Gas that had previously been in rate base. The Court of Appeal of
Alberta addressed the circumstances in which the no harm test should be applied, and referred to
the Supreme Court of Canada’s Stores Block decision. The court found:
In Stores Block, the Board found that there would be no harm to customers as a result of
the sale. In the Supreme Court, Bastarache J. observed that even by the Board’s own
reasoning, it should only exercise its discretion to act in the public interest when
customers would be harmed or would face some risk of harm (at para. 84). In our view,
the harm contemplated by the Supreme Court must be harm related to the transaction
itself.
85. An application of the no harm test requires the Commission to consider whether or not
the transaction will adversely affect rates or the quantity or quality of service. For the reasons
that follow, the Commission finds that the disposition of the substation property will not result in
adverse rate or service impacts.
86. The Commission has reviewed the concerns raised by both parties in regard to the
remediation costs and the results of the Phase II Environmental Assessment report. The
Commission accepts EDTI’s confirmation that the costs of salvage, disposal, and site
remediation costs will be borne by EDTI. The Commission is satisfied that EDTI will perform
the required remediation process identified by Blanchard prior to the disposition of the property.
The Commission accepts that the remediation process will delay the decommissioning and
disposition of the property until later in 2015. Accordingly, the Commission is satisfied that
EDTI will commit to bearing all remediation, and there will not be a resulting impact to rates for
remediation costs.
87. In respect of service level impacts, the substation property is no longer required for the
provision of electricity service, and therefore the proposed disposition will have no adverse
effect on the quality and quantity of utility service. There will be no harm to customers in terms
of service quality if the substation property is removed from EDTI’s revenue used to establish
customer rates.
88. The Commission accepts EDTI’s reasoning that the cumulative revenue impact
associated with the revenue requirement of the substation assets embedded in the PBR rates
represents an amount of $30,000, or less, will have a negligible effect on the revenue ultimately
charged to customers through rates. The Commission accepts that this disposition will not create
any adverse financial impact to rate payers.
89. Given EDTI’s proposal for the disposition of property at fair market value and the fact
that remediation will be undertaken and the resulting remediation costs will be absorbed by the
utility, the Commission finds that the disposition of the substation property will not result in
harm to customers and the substation property that is no longer required for the provision of
59
Stores Block, paragraph 84.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 21
electricity service should be removed from rate base. The Commission approves the proposed
disposition of EDTI’s substation property, as filed.
4.4 Adjustment due to disposition
90. EDTI stated that it would remove the substation land and building from its revenue and
rates during the cost-of-service rebasing at the end of the PBR term in 2018. EDTI further noted
that should the sale of these assets take place prior to 2018, then an adjustment to PBR revenue
for the disposition would still occur during rebasing expected to be in 2018, and not during the
current PBR term.
91. In terms of the adjustment to PBR revenue, EDTI stated that in cases where the disposal
of land and buildings are outside the ordinary course of business, the net proceeds, if any, from
the sale of these assets are treated in the manner prescribed by the Supreme Court of Canada in
the Stores Block case with any net proceeds accruing to the EDTI shareholder. In regard to the
removal of the asset, EDTI would first credit customers for the accumulated depreciation relating
to the substation building, in the amount of $21,327 assuming the disposition is approved by the
Commission and assuming the asset disposed in 2014, now expected in 2015. This would
effectively pay customers back for their contribution to the facility.
92. Second, EDTI would reduce its rate base by the net book value of the substation property
by removing the original cost and accumulated depreciation for the property at the date that the
property is sold. EDTI will include any difference between the amount received from the sale of
land, less agents’ commissions and other costs incidental to the sale, the original cost of the
building ($123,188) and the land ($1,492), in Account 922, Gains and Losses from disposition of
utility facility.60
93. The CCA stated that if the proceeds go into general revenue or to the I-X (indexing
mechanism) component of the PBR revenue requirement, then this would be the same as treating
the disposition of the substation building as being disposed of outside the ordinary course of
business. In this case, the benefits would accrue to EDTI under the indexing mechanism portion
of the revenue requirement.
94. The CCA proposed that the proceeds from the disposition should be included in the
capital revenue requirement and therefore ultimately be included in the K factor accounting test
to determine the application of a K factor.61
95. The CCA stated that the $50,000 cumulative revenue be removed from the indexing
mechanism under PBR, or from the capital tracker increment for 2014 onwards, whichever is
easier.62
96. EDTI confirmed that the substation property cannot be sold until at least 2015 because of
the remediation process to be undertaken, three years prior to any rebasing of its revenue
requirement and rates under PBR. EDTI stated that $30,000 is an insignificant amount and it
60
Exhibit 11.01, AUC-EDTI-04. 61
Exhibit 31.01, CCA supplemental reply argument, paragraphs14-15. 62
Exhibit 15.01, CCA argument, paragraphs 9-12.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
22 • Decision 3206-D01-2015 (February 25, 2015)
should not be required to refund customers the cumulative revenue impact from disposing the
substation property.63
Commission findings
97. The Commission does not accept the CCA’s proposal that EDTI’s cumulative revenue be
removed from the indexing mechanism under PBR, or the capital tracker increment for 2014
onwards. The Commission directs EDTI to remove the net book value of the substation property
from its distribution rate base, at the end of the current PBR term.
98. In paragraph 88 of Decision 2012-237,64 Rate Regulation Initiative, Distribution
Performance-Based Regulation, the Commission stated:
88. The Commission considers the second alternative is in keeping with the decision
to use 2012 approved rates rather than 2012 actual costs as the basis for going-in rates.
The 2012 rates have been tested and approved by the Commission as just and reasonable
for 2012. Accordingly, the 2012 approved rates are the correct starting point on which to
base going-in rates. The Commission confirms the findings in Decision 2009-035[65] that
adjustments to going-in rates should not be made to reflect actual results. Further,
adjustments should not be made selectively but, rather, should only be made in the
context of a full rate case. Adjustments may be made in exceptional situations, however,
like the case of the short term incentive plan adjustment approved in the ENMAX
decision.
99. PBR is intended to decouple a company’s revenues from costs for the duration of the
PBR term. The Commission will not require EDTI to make any adjustments to remove the
substation property and cumulative revenue prior the expiry of the current PBR term given the
Commission’s direction in the Decision 2012-237 that adjustments to going-in rates are not to be
made to reflect actual events during the PBR term. In that decision, the Commission considered
that adjustments to going-in rates should only be made in the context of a full rate case.
Consistent with Decision 2012-237, the Commission finds that the removal of the substation
property and other substation assets from rates should be reflected in EDTI’s next revenue
requirement application, which may take the form of a rebasing of EDTI’s PBR plan or, in the
event that a full rebasing of EDTI’s PBR plan does not occur, it may take the form of a full rate
case after a subsequent PBR term.
100. The Commission also finds that all net proceeds of sale and net gain arising from the
disposition are to be for the account of the utility shareholders, in accordance with the Stores
Block decision. At paragraph 69 of the Stores Block decision, the court stated in part: “Despite
the consideration of utility assets in the rate-setting process, shareholders are the ones solely
affected when the actual profits or losses of such a sale are realized; the utility absorbs losses and
gains, increases and decreases in the value of assets, based on economic conditions and
occasional unexpected technical difficulties, but continues to provide certainty in service both
with regard to price and quality.”
63
Exhibit 19.01, EDTI reply argument, paragraphs 5 and 6. 64
Decision 2012-237: Rate Regulation Initiative Distribution Performance-Based Regulation, Proceeding 566,
Application 1606029, September 12, 2012. 65
Decision 2009-035: ENMAX Power Corporation, 2007-2016 Formula Based Ratemaking, Proceeding 12,
Application 1550487, March 25, 2009.
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 23
101. With respect to the accumulated depreciation relating to the substation building, which
was calculated in 2014 as $21,327, the Commission considers that no adjustment for
accumulated depreciation is required given the findings in Section 4.1 of this decision.
102. EDTI is directed to provide confirmation and details of the substation disposition,
including the net proceeds of the disposition, in its next revenue requirement application. The
Commission also directs EDTI to file in its next revenue requirement application, the net book
value of the substation property and other substation assets as of the date of the disposition and
the proposed adjustment to its closing and opening-rate base, to reflect the findings and
directions in this decision. The final adjustment to rate base as a result of the substation
disposition will be reviewed in that proceeding.
5 Order
103. It is hereby ordered that:
(1) EPCOR Distribution & Transmission Inc.’s application to dispose of the land and
substation building located at located at 9724 - 118 Avenue Northwest,
Edmonton, Alberta, known as Substation No. 250, is approved.
(2) EPCOR Distribution & Transmission Inc. shall file the details of the disposition,
including the net proceeds of sale of the substation property, related to the
disposition of the substation land and building, in its next revenue requirement
application.
(3) EPCOR Distribution & Transmission Inc. shall also file, in its next revenue
requirement application, the net book value of the substation property and other
substation assets as of the date of the disposition and the proposed adjustment to
its closing and opening rate base, in order to reflect the findings and directions in
this decision.
Dated on February 25, 2015.
Alberta Utilities Commission
(original signed by)
Tudor Beattie, QC
Commission Member
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
Decision 3206-D01-2015 (February 25, 2015) • 25
Appendix 1 – Proceeding participants
Name of organization (abbreviation) counsel or representative
EPCOR Distribution & Transmission Inc. (EPCOR or EDTI)
ATCO Electric Ltd.
Bennett Jones LLP
AltaLink Management Ltd. (AML) Consumers’ Coalition of Alberta (CCA)
Alberta Utilities Commission Commission panel T. Beattie, QC, Commission Member Commission staff
B. McNulty, (Associate general counsel) A. Sabo (Commission counsel) P. Genderka S. Allen
Disposition of Substation Property EPCOR Distribution & Transmission Inc.
26 • Decision 3206-D01-2015 (February 25, 2015)
Appendix 2 – Summary of Commission directions
This section is provided for the convenience of readers. In the event of any difference between
the directions in this section and those in the main body of the decision, the wording in the main
body of the decision shall prevail.
1. The Commission does not accept the CCA’s proposal that EDTI’s cumulative revenue be
removed from the indexing mechanism under PBR, or the capital tracker increment for
2014 onwards. The Commission directs EDTI to remove the net book value of the
substation property from its distribution rate base, at the end of the current PBR term.
.......................................................................................................................... Paragraph 97
2. EDTI is directed to provide confirmation and details of the substation disposition,
including the net proceeds of the disposition, in its next revenue requirement application.
The Commission also directs EDTI to file in its next revenue requirement application, the
net book value of the substation property and other substation assets as of the date of the
disposition and the proposed adjustment to its closing and opening-rate base, to reflect
the findings and directions in this decision. The final adjustment to rate base as a result of
the substation disposition will be reviewed in that proceeding. ................... Paragraph 102