Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing...

65
Environmental Monitoring Report Semestral Report December 2019 Project 47274-003 Loan 3590/3591-VIE: SECONDARY GREEN CITIES DEVELOPMENT PROJECT - HUE CITY SUBPROJECT Prepared by Hue Project Management Unit under Thua Thien- Hue Provincial Department of Planning and Investment for Thua Thien -Hue Provincial People’s Committee and the Asian Development Bank.

Transcript of Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing...

Page 1: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

Environmental Monitoring Report

Semestral Report December 2019

Project 47274-003

Loan 3590/3591-VIE: SECONDARY GREEN CITIES

DEVELOPMENT PROJECT - HUE CITY SUBPROJECT

Prepared by Hue Project Management Unit under Thua Thien- Hue Provincial Department of

Planning and Investment for Thua Thien -Hue Provincial People’s Committee and

the Asian Development Bank.

Page 2: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

2

ABBREVIATIONS

ADB - Asian Development Bank

BOD - Bilological oxygen demand

COD - Chemical oxygen demand

CPC - City People’s committee

DOC - Department of Construction

DOLISA - Department of Labor, Invalids and social Assistance

DONRE - Department of Environment and Natural Resources

DPI - Department of Planning and Investment

EA - Executing Agency

EIA - Environment Impact Assessment

EMP - Environmental Management Plan

CEMP - Contractor Environmental Management Plan

EO - Environmental Officer

IA - Implementing agency

IEE - Initial Environmental Examination

IES - International Environmental Specialist

NES - National Environmental Specialist

PMU - Project management unit

HPMU - Hue project management unit

GOV - Government of Viet Nam

PMCS - Project Management & Supervision Consulting Services

PPC - Provincial People’s committee

SO - Safeguards Officer

UXO - Unexploded ordnance

Page 3: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

3

WEIGHTS AND MEASURES

dB(A) – Decibel (weighted average) ha – hectare kg/d – kilogram per day km – kilometer km2 – square kilometer m – meter m2 – square meter m3 – cubic meter m3/d – cubic meters per day m3/s – cubic meters per second mg/m3 – milligrams per cubic meter mm – millimeter

NOTE

(i) In this report, "$" refers to US dollars. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 4: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

4

TABLE OF CONTENTS

I. INTRODUCTION ......................................................................................................... 6 1.1. Project background ..................................................................................................... 6 1.2. Project objectives ........................................................................................................ 6 1.3. Project progress .......................................................................................................... 9 1.4. IMPLEMENTATION OF SAFEGUARDS PLANS .......... Error! Bookmark not defined. 1.5. Updated EMPs, Incorporation of Environmental Requirements into Project .............. 11 II. ENVIRONMENTAL IMPLEMENTATION MONITORING ........................................... 13 2.1. Present status of implementation of the Environmental Management Plan (Mitigation measures) ............................................................................................................................ 15 2.2. Health and Satety ...................................................................................................... 23 III. ENVIRONMENTAL QUALITY MONITORING ........................................................... 26 3.1. Monitoring plan .......................................................................................................... 26 3.2. Monitoring activities in the reporting period ............................................................... 26 3.3. Review the monitoring results in Q4 / 2019 ............................................................... 29 IV. COMPLIANCE WITH ENVIRONMENT LOAN COVENANTSError! Bookmark not defined. V. COMMUNITY CONSULTATION, INFORMATION DISCLOSURE AND INSTITUTIONAL STRENGTHEN......................................................................................... 35 VI. GRIEVANCE REDRESS MECHANISM .................................................................... 35 VII. CONCLUSION .......................................................................................................... 35 VIII. APPENDIXES ........................................................................................................... 37 8.1. Appendix 1. Checklist: Site instruction of Consultant ................................................. 37 8.2. Appendix 2. Checklist: Labor contracts, Labor safety and fire and explosion prevention training ................................................................................................................................. 45 8.3. Appendix 3. Checklist: Registering machinery and equipment of the contractors ...... 51 8.4. Appendix 4. Environmental quality monitoring results in Quarter 4/2019 ................... 55 8.5. Appendix 5. Agreement minutes of waste disposal ................................................... 64

LIST OF TABLES

Table 1. Responsibilities of stakeholders in implementing EMP ............................................. 7 Table 2. Packages of Hue subproject under the SCDP ........................................................ 10 Table 3. Project overview, Summary of project Environmental progress .............................. 11 Table 4. EMP requirement and Summary of approved Contractor Environmental Management Plan (CEMP) and relevant documents............................................................ 12 Table 5. Compliance with EMP requirements ...................................................................... 15 Table 6. Health and Safety Issues ....................................................................................... 23 Table 7. Location for environmental quality monitoring in Q4 / 2019 .................................... 26 Table 8. Result of analyzing ambient air quality – package HU- CW01 ................................ 29 Table 9. Results of surface water quality - package HU-CW01 ............................................ 31 Table 10. Results of analyzing ambient air quality - package HU-CW04 .............................. 32 Table 11. Results of analyzing ambient air quality - package HU-CW05 .............................. 34 Table 12. Pending issues and Corrective action .................................................................. 35

Page 5: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

5

LIST OF FIGURES

Photo 1. Photos of the construction site package HU-CW01, December 2019 .................... 22 Photo 2. Photos of the construction site package HU-CW04, December 12/2019 ................ 22 Photo 3. Photos of the construction site package HU-CW05, December 12/2019 ................ 23 Photo 4. Typical safety issues on site .................................................................................. 26 Photo 5. Monitoring map package HU-CW01, December, 2019 .......................................... 28 Photo 6. Monitoring map package HU-CW05 – October & November, 2019 ........................ 29 Photo 7. Monitoring map package HU-CW05 – December, 2019 ........................................ 29 Photo 8. Content of ambient air parameters, package HU-CW01 ........................................ 30 Photo 9. The chart shows noise parameters, package HU-CW01 ........................................ 31 Photo 10. Content of ambient air parameters, package HU-CW04 ...................................... 33 Photo 11. Content of noise parameters, package HU-CW04 ............................................... 33 Photo 12. Comparison of ambient air quality with QCVN, package HU-CW05 ..................... 34

Page 6: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

6

I. INTRODUCTION

1.1. Project background

The Secondary Green Cities Development Project (the project) will support environmentally

sustainable and socially inclusive development in the cities of Vinh Yen, Hue, and Ha Giang

in Viet Nam to enhance their economic competitiveness. It will (i) control urban stormwater

runoff and reduce flood risks, (ii) improve sanitation for public health, (iii) enhance green

landscaping and public amenities, (iv) upgrade urban road networks and their connectivity,

and (v) promote public participation in planning. The project will demonstrate green and

climate-resilient development approaches that will be scaled up for nationwide secondary

green city development in Viet Nam.

The Hue subproject (Output 2 of the Project) will deliver the three components: (i) Improving

the drainage capacity, water environment, and livability of the inner and surrounding areas of

the Citadel by upgrading 21.9 km of drainage pipelines, rehabilitating 15.9 km of road

pavement and drainage, and dredging 6.2 ha of water-retention ponds; (ii) Protecting 9.0 km

of river embankments with environment-friendly materials and improved public access; (iii)

enhancing 17.2 ha of green spaces and landscaping for public amenities; and (iv) extending

access to a clean water supply to the poor Phu Son commune. The urban road connectivity

and tourist access improvement component will connect missing links of the urban road

network to a 7.2 km road and three bridges to reduce traffic congestion and improve access

for increasing numbers of tourists. The green flagship grant component will involve

consultations with climate-vulnerable communities to identify their needs, and will fund the

required equipment procurements, small works, and activities.

1.2. Project objectives

Long-term objectives:

- Improve and expand the transportation network, step by step complete synchronous

urban infrastructure; Meanwhile, it will create a driving force for urban development,

promote the development of trade and service business, exploit tourism potentials, as

well as create employment opportunities to increase people’s income.

- Improve environmental sanitation conditions and urban environmental landscape,

thereby improve the health and living quality for the people.

Short-term objectives:

- Improve environmental infrastructure including drainage systems, embankments and

dredging for better flood prevention; management of water supply, sanitation and

wastewater; upgrade solid waste treatment facilities to improve environmental

conditions.

- Contribute to refurbish the urban cities to become clean and green and develop in

accordance with the National Strategy on Green Growth period 2014-2020 by the

Government.

- Upgrade urban road networks and their connectivity.

Page 7: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

7

1.3. EMP implementation arrangement

Institutional setup and responsibilities of stakeholders in implementing EMP are stated in

section VII. Institutional setup and responsibilities in updated EMPs approved by ADB.

Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440

/ SKHĐT-BQLDA dated September 10, 2018 on establishing the Secondary Green Cities

Development Project Management Unit - Thua Thien Hue subproject which clearly states the

Department of Environment, Resettlement and Social Safeguards with 04 people to ensure

the environmental management plan is implemented in all project items. In addition,

Consultant supports project management and develops the capacity to mobilize

environmental experts to support the Environmental Working Group in implementing project

environmental safety.

Responsibilities of the executing agency, Implementing Agency, HPMU, Project Supervision

and Management Consultancy (PMCS), contractors in EMP implementation are described in

the table below.

Table 1. Responsibilities of stakeholders in implementing EMP

Parties Responsibilities

Executing agency (Thua

Thien Hue Provincial

Peoples Committee)

1. Ensure the compliance with the loan contract;

2. Approve bidding plans, bidding dossiers, bid evaluation and awarding

contracts, including environmental management plans.

3. Submit quarterly and annual reports of the subproject to ADB, including

reports related to the implementation of the Environmental Management Plan;

4. Ensure the compliance with subproject implementation in accordance with

ADB environmental and social policies and guidelines;

5. Approve proposed activities in cases of adverse financial audits or

monitoring and evaluation reports.

Implementing agency –

Department of Planning

& Investment

1. Coordinate and supervise the implementation of Project Management Unit

(PMU) activities including environmental protection activities;

2. Coordinate the Project Management Unit (HPMU) capacity development

program,

3. Submit necessary approvals from relevant departments and organizations

such as DONRE before awarding civil construction contracts;

4. Assist the Environmental Management Division/ Project Management Unit

(HPMU) in implementing the Environmental Management Plan,

5. Coordinate periodic reports of the Project Management Unit (HPMU) to the

Executive Agency on the implementation of the Environmental Management

Plan;

6. Perform periodic quality control checks of project items,

7. Manage the handover of project items to the units responsible for operation

and maintenance.

Department of Natural

Resources &

Environment (DONRE)

1. Periodically certify the subproject's compliance with the environmental

protection regulations and standards, and provide technical support in the

grievance redress mechanism when necessary.

Department Labor,

Invalids, and Social

Assistance (DOLISA)

1. Ensure that regulations on worker and community safety are not violated

during the implementation of the subproject.

Hue Monuments 1. Support design consultancy on suitable designs for packages located in

Page 8: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

8

Parties Responsibilities

Conservation Center

(HMCC)

or adjacent to the Complex of Hue Monuments area.

2. Review and approve the detailed design.

3. Regular field supervision to ensure the Contractor complies with CEMP,

including cultural heritage conservation.

Project Management

Unit(PMU)

1. Disseminate of Grievance Redress Mechanism (GRM)

2. Ensure the environmental management plan is initiated by responsible

parties as defined in this environmental management plan.

3. Prepare and submit semi-annual reports of subprojects / components

including environmental monitoring reports;

4. Monitor contractors on the implementation of the Environmental

Management Plan;

5. Ensure the Environmental Management Plan is incorporated in detailed

designs and civil construction contracts.

6. Ensure the implementation of the Environmental Management Plan; submit

periodic monitoring reports to the Project Implementing Agency and the

Executing Agency.

Safeguards Officer (SO)

of PMU

1. Managing the implementation of EMP, CEMP. Control and coordinate with

consultant and Contractors

Project Supervision and

Management

Consultancy (PMCS)

1. The supervision consultant is responsible for supervising the number of

environmental protection mitigation measures.

2. Review the management and safety plans on site in accordance with the

safety plans approved by the investor, contractual tasks and current

regulations.

3. Support the Project Implementing Agency to implement community

consultation with affected people, other relevant partners and document of

consultation results in periodic monitoring reports.

4. Identify relevant areas of biodiversity conservation and environmentally

sensitive areas; provide measures to prevent and protect these areas.

5. Instructure Contractor to make forms and monitor mitigation measures

during the construction process.

6. Prepare semi-annual monitoring reports on compliance with ADB's

environmental safeguard policies.

Contractor

1. Implement of the requirements of the Environmental Management Plan and

related reporting requirements;

2. Prepare and submit Consultant to approve Contractor Environmental

Management Plan CEMP at specific siteto meet the requirements of the

Environmental Management Plan (EMP)

3. Obtain the necessary permits for the construction of the components

4. Appoint a qualified full-time employee to coordinate the implementation of

the Environmental Management Plan (EMP), including environmental, health

and safety issues;

5. Cooperate with the Project Management Unit (PMU) to resolve complaints

under the Grievance Redress Mechanism.

6. Assign an environmental management officer, who will be responsible for

ensuring that the environmental effects mitigation measures are implemented

and regularly reported.

Page 9: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

9

1.4 Institutonal Strengtherning

During the reporting period, some activities related to community consultation, information

disclosure and institutional strengthen were conducted.

i. Participate in training organized by ADB:

- Time: from October 21 to October 22, 2019;

- Location: Hanoi

- Program: Implementation of ADB's Environmental Safeguards Policy in ADB-funded

projects;

- Organizer: Asian Development Bank (ADB)

- Trainees: Safeguards Officer of PMU and Consultant (Ms Le Thi Thuy Tien - PMU;

Ms Le Thi Vinh - Environmental Specialist).

- Trainer: ADB Environmental Specialist

ii. Training on labor safety, fire and explosion prevention at construction site -

HU-CW01 package

- Time: November 10, 2019;

- Location: Executive Board of the construction site of HU-CW01, Phu Son, Huong

Thuy town

- Program: Training on safety, fire and explosion prevention at the construction site

- Organizer: Haweicco Company

- Trainees: 25 officials and workers on the construction site

- Trainer: Commanders, safety officers.

- Details of the training list, see the Appendix of this report.

iii. Training on labor safety, fire and explosion prevention group III on the

construction site - package HU-CW05

- Time: From November 29, 2018 to December 1, 2018;

- Location: Rao Trang 3 Hydropower Office

- Program: Safety training group 3 (as stipulated in Decree 44/2016 / ND-CP dated

May 15, 2016 of the Government).

- Trainees: All workers and technical staffs of the company

- Trainer: Thua Thien Hue Vocational College

- Details of the training list, see the Appendix of this report.

II. PROJECT IMPLEMENTATION PROGRESS

Civil construction are grouped into the 07 packages, summarized as follows:

Page 10: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

10

Table 2. Packages of Hue subproject under the SCDP

No Name of packages Symbol Construction

Progress Detail activities

1 Water Supply System to Phu Son Solid Waste Management Facility and Villages Subproject

HU-CW01 2%

Delivered various HDPE sizes estimated equivalent length of 3000 meters; ii. Excavation, sand bedding and backfilling works continues and installed DN160mm HDPE pipe with total length of 682m / 29,408m or 18% on physical progress.

2 Dredging and Embankment of Ke Van, An Hoa, An Cuu and Nhu Y rivers

HU-CW02 0%

Contract has not been awarded

3 Dredging, Drainage, Pavement and Lake in 4 Inner City Wards, and Embankment of Lap and Dong Ba rivers

HU-CW03 0%

Contract has not been awarded

4 Park, Path, and Square of Provincial Administration Center

HU-CW04 0%

The Contractor has provided construction fence and project sign at the site; No major work has been started.

5 Park, Path, Drainage and Lighting in new An Van Duong Development area

HU-CW05 0%

The Contractor has stated the excavation work for the storm drainage longitudinal line and prepare concrete pipe cradle (base) at To Huu Road; Delivered reinforced concrete (RC) pipes DN600 and still awaiting QA/QC of the pipes from the contractor and supplier/manufacturer’s company profile, prior to acceptance of the construction materials;

6 Bui Thi Xuan and Huyen Tran Cong Chua Roads

HU-CW06 0% Contract has not been awarded

7 Vy Da Bridge Expansion, and 100m Access Road

HU-CW07 0% Contract has not been awarded

Overall progress 2%

HU-CW01 - Water Supply to Phu Son Villages and Municipal Solid Waste Treatment

Facility: The contract with Hanoi water electric installation construction joint stock company

was signed on 3 May 2019 and issuing commencement letter on October 20, 2019. By the

end of December 2019, the contractor has been executing 2.5 months.

HU-CW02 - Dredging and Embankment of Ke Van, An Hoa, An Cuu and Nhu Y rivers; It

is predicted to conduct contractor selection in Q II/2020.

HU-CW03 - Dredging, Drainage, Pavement and Lake in 4 Inner City Wards, and

Embankment of Dong Ba river. It is predicted to conduct contractor selection in Q 3/2020.

HU-CW04 - Park, Path, and Square of Provincial Administration Center: Contract was

awarded to Urban Infrastructure Development Investment Corporation on 27 June 2019 and

Page 11: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

11

issuing commencement letter on December 19, 2019. By the end of December 2019, the

contractor has been executing 10 days.

HU-CW05 - Pavement, Drainage and Lighting in An Van Duong New Urban Area. This

package has been bid and awarded to Thanh Dat Joint Stock Company on 26 April 2019

and issuing commencement letter on October 10, 2019. By the end of December 2019, the

contractor has been executing 2.5 months.

HU-CW06 - Bui Thi Xuan and Huyen Tran Cong Chua Roads. It is predicted to conduct

contractor selection in Q 3/2020.

HU-CW07: Vy Da Bridge Expansion, and 100m Access Road. It is predicted to conduct

contractor selection in Q 2/2020.

Table 3. Project overview, Summary of project Environmental progress

English name and code

of project:

Construction and Investment Project Management Unit (HPMU) -

Secondary Green Cities Development Project – Thua Thien Hue

subproject.

Loan No.3590-VIE

Safeguards Policy Environment B

Report period: From October to December 2019 (from the time of signing the Contract)

Previous Report: Not yet

The main Environmental

safeguard activities have

been carried out

• Awarding contracts: section 5 - construction packages

• Progress of work (% of physical completion): see details in the

following table

• Present status of approving safety issues/ licenses/ agreements:

• Approving the environmental management plan at the site of 03

packages under construction of HU-CW01; HU-CW04; HU-CW05.

• Approved the periodical environmental monitoring outline during

the construction process of the packages HU-CW01; HU-CW04;

HU-CW05.

• Disseminate safety procedures in accordance with the ADB

Safeguard Policy and compliance process of preparing –

submitting – approving of environmental safety reports (CEMP,

monthly environmental report), issuing monthly Environmental

report form for 3 contractors HU-CW01; HU-CW04; HU-CW05 in

November 2019.

Prepared by: Project Management & Supervision Consulting Services (PMCS) – Joint

Venture APAVE - HALCOM

III. REVIEW OF ENVIRONMENT SAFEGUARD COMPLIANCE

3.1. Updated EMPs, Incorporation of Environmental Requirements into Bidding and Contract Documents

Updated environmental management plan is required for all subprojects. By the end of

December 2019, all environmental management plans have been submitted and approved

by ADB. The approval schedule for the updated environmental management plan for each

subproject is specified in the table below:

Page 12: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

12

Table 4. EMP requirement and Summary of approved Contractor Environmental

Management Plan (CEMP) and relevant documents

Packages EMP requirements in bidding documents

and contracts

Time for submission and approval

of CEMP and related documents

HU-CW01 -

Water Supply to

Phu Son Villages

and Municipal

Solid Waste

Treatment

Facility

In section VI of the EMP. The environmental

monitoring plan specifies the terms and

procedures for implementation of the

environmental monitoring plan, Table 5.

Environmental compliance monitoring plan

specifies location, method, frequency,

responsibility for implementation and

monitoring.

Submitted on 5/12/2019.

Approved on 6/12/2019 in official letter

No. 260/ TB-BQLDA.

HU-CW02 -

Dredging and

Embankment of

Ke Van, An Hoa,

AnCuu and Nhu

Y rivers.

In section VI of the EMP. The environmental

monitoring plan specifies the terms and

procedures for implementation of the

environmental monitoring plan, Table 5.

Environmental compliance monitoring plan

specifies location, method, frequency,

responsibility for implementation and

monitoring.

Contract has not been awarded

HU-CW03 -

Dredging,

Drainage,

Pavement and

Lake in 4 Inner

City Wards, and

Embankment of

Lap and Dong

Ba rivers.

In section VI of the EMP. The environmental

monitoring plan specifies the terms and

procedures for implementation of the

environmental monitoring plan, Table 5.

Environmental compliance monitoring plan

specifies location, method, frequency,

responsibility for implementation and

monitoring.

Contract has yet been awarded

HU-CW04 -

Park, Path, and

Square of

Provincial

Administration

Center.

In section VI of the EMP. The environmental

monitoring plan specifies the terms and

procedures for implementation of the

environmental monitoring plan, Table 5.

Environmental compliance monitoring plan

specifies location, method, frequency,

responsibility for implementation and

monitoring.

Submitted on 28/11/2019

Approved on 31/12/2019 in the official

letter No. 270A/TB – BQLDA.

HU-CW05 -

Pavement,

Drainage and

Lighting in An

Van Duong New

Urban Area.

In section VI of the EMP. The environmental

monitoring plan specifies the terms and

procedures for implementation of the

environmental monitoring plan, Table 5.

Environmental compliance monitoring plan

specifies location, method, frequency,

responsibility for implementation and

monitoring.

Submitted on 30/12/2019

Approved on 31/12/2019 in the official

letter No. 296/TB – BQLDA.

HU-CW06 - Bui

Thi Xuan and

Huyen Tran

Cong Chua

In section VI of the EMP. The environmental

monitoring plan specifies the terms and

procedures for implementation of the

environmental monitoring plan, Table 5.

Environmental compliance monitoring plan

Contract has yet been awarded

Page 13: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

13

Packages EMP requirements in bidding documents

and contracts

Time for submission and approval

of CEMP and related documents

Roads. specifies location, method, frequency,

responsibility for implementation and

monitoring.

HU-CW07: Vy

Da Bridge

Expansion, and

100m Access

Road

In section VI of the EMP. The environmental

monitoring plan specifies the terms and

procedures for implementation of the

environmental monitoring plan, Table 5.

Environmental compliance monitoring plan

specifies location, method, frequency,

responsibility for implementation and

monitoring.

Contract has yet been awarded

Section VI of the EMP specifies that the contractor must develop site-specific environmental

management plan to fully meet the ADB's Environmental Management Plan. The Contractor

must include action plans in the bidding documents to commit to understanding and

complying with the IFC Guidelines for environmental health and safety (2007).

3.2. Compiance with environment safeguard loan covernant

Plan Index Agreement Note/

Compliance Status

5 6 The Borrower will not award any Construction

Contract until (a) the Borrower has received ADB's

notice of the relevant IEE; And (b) if there are

involuntary resettlement impacts, the Borrower has

prepared and submitted to the final ADB RP based

on the Project's detailed design and received ADB

notification of RP.

Being complied with.

5 6 The Borrower requires project implementing

agencies to ensure the site and all access rights

required by the Project are provided to the Contractor

according to the agreed schedule in the related

Construction Contract and all land acquisition and

resettlement activities are implemented in

accordance with (a) all applicable Borrower's laws

and regulations relating to land acquisition and

involuntary resettlement; (B) Involuntary

Resettlement Safeguards Measures; And (c) all the

measures and requirements outlined in the

Resettlement Plan, and any corrective or preventive

action taken in the Safeguards Monitoring Report..

Being complied with.

5 7 Without limiting the application of Resettlement

Safeguards Measures or Resettlement Plans, the

Borrower will require Project Executing Agency to

ensure that there are no physical or economic

changes related to Project until:

(A) Payment of compensation and other entitlements

made to affected persons under the Resettlement

Plan; And

Being complied with.

Page 14: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

14

Plan Index Agreement Note/

Compliance Status

(B) an income restoration and livelihood restoration

program has been established in accordance with the

Resettlement Plan.

5 8 The project is expected to have no impact on ethnic

minorities. However, if there is any such impact, the

Borrower, through the Project Implementing Agency,

will ensure that this impact complies with the

Borrower's current laws and regulations and the

Safeguards Policy Report. . If there is a discrepancy

between the Security Policy Statement and the

Borrower's laws and regulations, the Safeguards

Policy Statement will apply.

Being complied with.

5 9 The Borrower will require project implementing

agencies to provide the necessary budget and

manpowers to fully implement the Environmental

Management Plan and Resettlement Plan.

Being complied with.

5 10 The Borrower will require project executing agencies

to ensure that all bidding documents and construction

contracts contain provisions that require the

contractor to: (a) comply with relevant measures.

regarding the contractor mentioned in the Initial

Environmental Inspection Report, Environmental

Management Plan and Resettlement Plan, and any

corrective or preventive action outlined in the

Safeguards Monitoring Report; (B) provide budget for

all environmental and social measures; And (c) Notify

the Borrower with written notice of any environment,

resettlement, ethnic minorities and social risks or

impacts that arise during construction,

implementation or operation of the Project that were

not considered in the IEE, the EMP, and the RP.

Being complied with. Budget

is available. The bidding

documents contain provisions

that require the contractor to:

(a) comply with relevant

measures. regarding the

contractor mentioned in the

Initial Environmental

Inspection Report,

Environmental Management

Plan and Resettlement Plan,

and any corrective or

preventive action outlined in

the Safeguards Monitoring

Report; (B) provide budget for

all environmental and social

measures; And (c) Notify the

Borrower with written notice of

any environment,

resettlement, ethnic minorities

and social risks or impacts

that arise during construction,

implementation or operation of

the Project that were not

considered in the IEE, the

EMP, and the RP.

5 11 The Borrower will require Project Implementation

Agencies to do the following: (a) submit the Periodic

safeguards Monitoring Report to ADB and disclose

relevant information from those reports to the

affected persons timely; (B) If any unexpected

environmental and / or social risks or impacts occur

during the construction implementation or operation

Being complied with.

Safeguards Monitoring

Reports are well prepared and

submitted to PMU and ADB

for review and approval.

Page 15: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

15

Plan Index Agreement Note/

Compliance Status

of the Project that are not included in the Initial

Environmental Examination(IEE), the Environmental

Management Plan(EMP) and Resettlement Plan(RP),

should promptly notify ADB of such Risks or impacts,

describe in detail the issues and propose a remedial

action plan; And (c) report any actual or potential

violations of compliance with the measures and

requirements set out in the Environmental

Management Plan or Resettlement Plan as soon as

the violations are identified.

IV. EMP IMPLEMENTATION MONITORING

4.1. Implementation of the Environmental Management Plan

During the reporting period, construction have been commenced in 3 packages including

HU-CW01; HU-CW04 and HU-CW05. For the HU-CW01 package, due to the construction

site along the route away from dense residential areas, the impact on the surrounding

environment is negligible.

Table 7. Compliance with EMP requirements where issues are identified when assessing

compliance with the implementation of mitigation measures in the approved EMP and CEMP.

If a request is fully complied with, there is usually no need for further action.

Table 5. Compliance with EMP requirements

EMP requirements Compliance status

(Yes, No, Partial)

Comment or Reason

for noncompliance Action to do next

1. HU-CW01 - Water Supply to Phu Son Villages and Municipal Solid Waste Treatment Facility -

Hương Thủy town

1.1. Soil pollution:

concrete batching

plants, using asphalt,

construction waste,

rock and soil unloaded

from the construction

site and exploited from

mines

Being complied with. The

contractor digs ditches to

put pipes and gathers

the excavated soil neatly

along the route.

The Contractor has

made an Agreement

minutes of waste

disposal with the Local

Government (See the

Appendix of this report)

Page 16: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

16

EMP requirements Compliance status

(Yes, No, Partial)

Comment or Reason

for noncompliance Action to do next

1.2. Surface water

pollution: due to

workers' activities, raw

material storage,

concrete batching

plants, asphalt and

wastewater from

construction sites

Being complied with.

Workers are fully

furnished with good

hygienic conditions,

without affecting the

water source.

The contractor plans to

purchase raw materials

and use them

immediately, restricting

to backlog many

materials on the site.

1.3. Social issues,

security and order

Being complied with.

There has been no

disorder or insecurity in

the reporting period.

1.4 Air pollution (dust

and noise) due to

procurement,

transportation of raw

materials, waste,

concrete batching

plants, road

construction (sub-base

layer, base layer,

asphalt)

Being complied with.

Materials transported on

covered trucks.

The vehicles are

regularly maintained and

verified according to the

regulations of the

authorities (See detailed

appendix)

The location of the

construction site is in the

forest, the distance to

people's houses is

sparse, so the impact

ability is negligible.

1.5 Waste

management (daily-life

solid waste, solid and

liquid construction

waste, hazardous

waste)

Partial complied.with

Domestic waste is

collected and processed

by Urban Environment

Company.

Some waste oil

containers are not

gathered in the right

place.

Gathering to the

location of the rented

house at the end of the

working day, not

promptly cleaning up

Machines after finishing

use must be temporarily

stored in warehouse or

transported to other

places.

Containers of oil and

hazardous waste should

be gathered in covered

warehouses, walls, high

ground, away from water

sources.

1.6 Management of

rock and soil unloaded

from the construction

site and exploited from

Being complied with

The contractor has a

waste disposal site (See

the Appendix of this

Page 17: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

17

EMP requirements Compliance status

(Yes, No, Partial)

Comment or Reason

for noncompliance Action to do next

mines, restoring rock

and stone mines

report

1.7 Traffic Safety

Management

Being complied with The

contractor arranges

people on duty at both

ends of the pipeline

routes, safety line and

warning signs to ensure

traffic safety

1.8.Water drainage

system

Being complied with.

Natural sloping terrain,

construction scope does

not affect the drainage

capacity of the area.

Construction process

does not generate site

waste water.

Domestic wastewater of

workers is collected by

households' sewer.

1.9.Discover cultural

heritage

No heritage has been

discovered in the

construction process

1.10 Labor Safety and

Health /Community

Being complied withIn the

construction work camps,

the contractor is

equipped with first aid

kits.

Workers and technicians

are given annual health

checkups.

Workers are periodically

allocated labor protection

and trained in Safety.

1.11 Work camps

Being complied with -

Contractors lease private

houses to be the office of

the construction site and

accommodation for

workers: have adequate

water supply and

drainage systems and

hygienic WC.

- Fully equipped with

Page 18: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

18

EMP requirements Compliance status

(Yes, No, Partial)

Comment or Reason

for noncompliance Action to do next

medicine cabinets, fire

extinguishers,

construction site rules.

HU-CW04: Park, Path, and Square of Provincial Administration Center

1.1. Soil pollution:

concrete batching

plants, using asphalt,

construction waste,

rock and soil unloaded

from the construction

site and exploited from

mines

Being complied with The

package commenced on

December 19, 2019,

there is no construction

activity so no pollution

has arisen.

1.2. Surface water

pollution: due to

workers' activities, raw

material storage,

concrete batching

plants, asphalt and

wastewater from

construction sites

Being complied with

Workers are fully

furnished with good

hygienic conditions,

without affecting the

water source.

The contractor plans to

purchase raw materials

and use them

immediately, restricting to

backlog many materials

on the site.

1.3. Social issues,

security and order

Being complied with

There has been no

disorder or insecurity in

the reporting period.

1.4 Air pollution (dust

and noise) due to

procurement,

transportation of raw

materials, waste,

concrete batching

plants, road

construction (sub-base

layer, base layer,

asphalt)

Being complied with

Materials transported on

covered trucks.

The vehicles are

regularly maintained and

verified according to the

regulations of the

authorities

Page 19: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

19

EMP requirements Compliance status

(Yes, No, Partial)

Comment or Reason

for noncompliance Action to do next

1.5 Waste

management (daily-life

solid waste, solid and

liquid construction

waste, hazardous

waste)

Being complied with The

package has not been

constructed yet, so no

waste has been

generated.

1.6 Management of

rock and soil unloaded

from the construction

site and exploited from

mines, restoring rock

and stone mines

N/AThe package has not

been constructed yet, so

no waste has been

generated.

1.7 Traffic Safety

Management

Being complied with. The

package has no main

construction activities;

the site scope is isolated

and fenced with the

surrounding area.

1.8.Water drainage

system

Being complied with. The

route has drainage ditch

system, natural sloping

terrain; construction

scope does not affect the

drainage capacity of the

area.

1.9.Discover cultural

heritage

No heritage has been

discovered in the

construction process

1.10 Labor Safety and

Health /Community

Being complied with. In

the construction work

camps, the contractor is

equipped with first aid

kits.

Workers and technicians

are given annual health

checkups.

Workers are periodically

allocated labor protection

and trained in Safety.

1.11 Work camps

Being complied with -

Contractors lease private

houses to be the office of

the construction site and

accommodation for

workers: have adequate

water supply and

Page 20: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

20

EMP requirements Compliance status

(Yes, No, Partial)

Comment or Reason

for noncompliance Action to do next

drainage systems and

hygienic WC.

- Fully equipped with

medicine cabinets, fire

extinguishers,

construction site rules

HU-CW05: Pavement, Drainage and Lighting in An Van Duong New Urban Area

1.1. Soil pollution:

concrete batching

plants, using asphalt,

construction waste,

rock and soil unloaded

from the construction

site and exploited from

mines

Being complied with. The

contractor digs ditches to

put pipes and gathers

the excavated soil neatly

along the route.

1.2. Surface water

pollution: due to

workers' activities, raw

material storage,

concrete batching

plants, asphalt and

wastewater from

construction sites

Being complied with.

Workers are fully

furnished with good

hygienic conditions,

without affecting the

water source.

The contractor plans to

purchase raw materials

and use them

immediately, restricting to

backlog many materials

on the site.

1.3. Social issues,

security and order

Being complied with.

There has been no

disorder or insecurity in

the reporting period.

1.4 Air pollution (dust

and noise) due to

procurement,

transportation of raw

materials, waste,

concrete batching

plants, road

construction (sub-base

layer, base layer,

asphalt)

Being complied with.

Materials transported on

covered trucks.

The vehicles are

regularly maintained and

verified according to the

regulations of the

authorities.

1.5 Waste

management (daily-life

solid waste, solid and

liquid construction

waste, hazardous

waste)

Being complied with.

Domestic waste is

collected and processed

by Urban Environment

Company.

Some waste oil

Page 21: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

21

EMP requirements Compliance status

(Yes, No, Partial)

Comment or Reason

for noncompliance Action to do next

containers are not

gathered in the right

place.

1.6 Management of

rock and soil unloaded

from the construction

site and exploited from

mines, restoring rock

and stone mines

Being complied with.

The contractor has a

waste disposal site (See

the Appendix of this

report)

1.7 Traffic Safety

Management

Partly complied with.

The contractor arranges

people on duty at both

ends of the pipeline

routes, safety line and

warning signs to ensure

traffic safety

1.8.Water drainage

system

Partly complied with. The

route has a drainage

system along the road,

construction scope does

not affect the drainage

capacity of the area.

Status of standing

water in ditches laying

pipes.

The contractor should

have water pumping in

the foundation pit to

ensure safety for

construction workers and

electrical safety.

1.9.Discover cultural

heritage

No heritage has been

discovered in the

construction process

1.10 Labor Safety and

Health /Community

Being complied with. In

the construction work

camps, the contractor is

equipped with first aid

kits.

Workers and technicians

are given annual health

checkups.

Workers are periodically

allocated labor protection

and trained in Safety.

1.11 Work camps

Being complied with.

- Contractors lease

private houses to be the

office of the construction

site and accommodation

for workers: have

adequate water supply

and drainage systems

and hygienic WC.

- Fully equipped with

medicine cabinets, fire

Page 22: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

22

EMP requirements Compliance status

(Yes, No, Partial)

Comment or Reason

for noncompliance Action to do next

extinguishers,

construction site rules.

Photo 1. Photos of the construction site package HU-CW01, December 2019

Photo 2. Photos of the construction site package HU-CW04, December 12/2019

Page 23: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

23

Photo 3. Photos of the construction site package HU-CW05, December 12/2019

4.2. Health and Satety

Contractors of packages HU-CW01; HU-CW04 and HU-CW05 have implemented mitigation

measures in the EMP to ensure safety and health for workers and the community. The work

camps requirements are fully followed by the contractors.

There have been no safety incidents on the construction sites during the reporting period and

no incidents affecting workers' health. Construction supervision consultants are regularly

present at the site to inspect, supervise and remind contractors about the implementation of

safety measures.

Some of the safety issues at the construction site have not been fully complied with, and

more solutions are listed in the Table. Health and Safety Issues.

Table 6. Health and Safety Issues

Issues Action to do Responsibility and

time Solution

Package HU-CW01

Hazardous waste

management: waste oil

containers

Gathering at the

prescribed position,

periodically transported

to other places

Contractor

(Haweicco

Company), PMCS

The contractor complies

with the committed

CEMP.

PMCS monitors the

implementation.

Page 24: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

24

Issues Action to do Responsibility and

time Solution

Package HU-CW04

The package has just

been commenced, the

contractor has not

implemented the

training program on

HIV AIDS, labor safety

and fire explosion

prevention for workers.

Organize training for

workers according to

the existing program.

Contractor (UDIC

Company)

Schedule suitable

construction plan for

workers to participate in

training to raise

awareness about HIV-

AIDS and Occupational

Safety.

Package HU-CW05

Note the periodic water

pumping from the pits

The contractor

arranged the pumps to

periodically pump water

from the pits

Contractor (Thanh

Dat Company),

PMCS

The contractor complies

with the committed

CEMP.

PMCS monitors the

implementation.

Construction signs and barricade, package HU-

CW01

Project Sign, package HU-CW01

Page 25: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

25

Waste oil tank gathered at the worker house,

package HU-CW01

Ditches placed pipes, package HU-CW01

Project Sign, package HU-CW04

Construction perimeter fence, package HU-CW04

Project Sign, package HU-CW05

Construction signs and barricade, package HU-

CW05

Page 26: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

26

Status of standing water at foundation pit,

package HU-CW05

Status of standing water at foundation pit,

package HU-CW05

Photo 4. Typical safety issues on site

4.3. Environment quality monitoring Monitoring plan

The environmental monitoring plan is focused on the ongoing construction activities at each

package and includes environmental indicators, locations, sampling frequencies, and data

collection methods. The purpose of the monitoring plan is to determine the effectiveness of

the mitigation measures, and to record any unintended positive or negative environmental

impacts of the subproject.

For the monitoring plan in the reporting period, the number of concentrated monitoring

samples in 3 packages includes HU-CW01; HU-CW04 and HU-CW05.

The monitoring requirements presented in the Environmental Monitoring Plan also include

the requirements specified in EIA, IEE and EMP reports of subproject..

4.4. Monitoring activities in the reporting period

During the reporting period from October to December 2019, the contractors signed a

contract with the subcontractor, the Center for Natural Resources and Environment

Monitoring of Thua Thien Hue Province to plan taking monitor sampling of environmental

indicators according to the updated EMP monitoring plan of subproject.

Detailed monitoring sampling outlines have been developed for the packages HU-CW01,

HU-CW04; HU-CW05 are the Contractors that commenced the construction. Analytical

sampling was conducted in the fourth quarter of 2019. For the remaining packages, due to

the evaluation of bidding and have not been signed contracts with contractors yet, the outline

of monitoring and sampling will be prepared and submitted by the Contractor later and

described in the next semi-annual reports of the subproject.

The contractor's construction site supervision activities are regularly conducted by the Project

Supervision and Management Consultancy (PMCS). When detecting a problem of non-

compliance, the supervision consultant will make a Site Instruction requesting the contractor

to fix it and send it to the PMU at the same time.

Table 7. Location for environmental quality monitoring in Q4 / 2019

Date

(dd/mm/yy)

Sample

symbol

Coordinates Monitoring criteria Characteristics of

monitoring places

HU-CW01 – Air quality

Page 27: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

27

Date

(dd/mm/yy)

Sample

symbol

Coordinates Monitoring criteria Characteristics of

monitoring places

09/12/2019 KPS X= 1800066,

Y= 574657.

SO2, NO2, Noise, Total

suspended solid

- Focusing on

construction activities

- Sampling conditions:

Open area, light

sunshine, light wind,

occasional people and

cars passing by

HU-CW01 – Surface water

10/12/2019 NMPS:

Temperature, TSS, DO,

COD, BOD5, NH4+, NO3-,

PO43- ,Cl-, Fe, Oil, Coliform

Underground slot K13

near the project

implementation area

HU-CW04 – Air quality

05/11/2019;

11/12/2019 KĐTX

X= 1800066,

Y= 574657.

SO2, NO2, Noise, Total

suspended solid

- Focusing on

construction activities

- Sampling conditions:

Open area, light

sunshine, light wind,

occasional people and

cars passing by

HU-CW05 – Air quality

15/10/2019

KX1

(KX281/5/1)

X= 1820979,

Y = 0565451

SO2, NO2, HC, Noise,

temperature, humidity,

suspended solid

- Intersection center

Vo Nguyen Giap, To

Huu, An Dong ward,

Hue city.

- Focusing on

construction activities

- Sampling conditions:

Open area, light

sunshine, light wind,

occasional people and

cars passing by

11/11/2019 KX1

(KX308/2/1)

X = 1820979,

Y = 0565451

SO2, NO2, HC, Noise,

temperature, humidity,

suspended solid

- Intersection center

Vo Nguyen Giap, To

Huu, An Dong ward,

Hue city.

- Focusing on

construction activities

- Sampling conditions:

Open area, light

sunshine, light wind,

occasional people and

cars passing by

11/12/2019 KVNG X = 1820866,

Y = 565104.

SO2, NO2, HC, Noise, Total

suspended solid

On the construction site

of Vo Nguyen Giap

- Focusing on

Page 28: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

28

Date

(dd/mm/yy)

Sample

symbol

Coordinates Monitoring criteria Characteristics of

monitoring places

construction activities

- Sampling conditions:

Open area, light

sunshine, light wind,

occasional people and

cars passing by

Photo 5. Monitoring map package HU-CW01, December, 2019

Photo 6. Monitoring map package HU-CW04, 11-12/2019

Page 29: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

29

Photo 7. Monitoring map package HU-CW05 – October & November, 2019

Photo 8. Monitoring map package HU-CW05 – December, 2019

4.5. Review the monitoring results in Q4 / 2019

Results of monitoring the quality of air, soil and surface water at the construction sites of the

packages will be shown in the Appendix of this report.

• Package HU-CW01:

Table 8. Result of analyzing ambient air quality – package HU- CW01

Page 30: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

30

No The parameters Unit Results QCVN/ TCVN

KPS

I Air quality

Inorganic QCVN 05:2013/BTNMT (1h)

1 TSP µg/m3 < 30 300

2 SO2 µg/m3 <20 350

3 NO2 µg/m3 < 35 200

4 CO µg/m3 < 500 30000

II Noise QCVN 26:2010/BTNMT (8h)

1 Sound Level (Leq) dBA 64,0 70

Legend:

QCVN 05: 2013 / BTNMT, National technical regulation on ambient air quality, average of 01 hour.

QCVN 26: 2010 / BTNMT: National technical regulation on noise level.

Based on the results of monitoring ambient air quality, the graphs show the content of

ambient air parameters:

- Content of SO2, NO2, CO, TSP at monitoring sites are respectively <20 µg / m3, <25 µg /

m3, <500 µg / m3, <30 µg / m3 within the permitted limits of QCVN 05: 2013 / BTNMT (1h)

(SO2: 350 µg / m3, NO2: 200 µg / m3, CO: 30000 µg / m3, TSP: 300 µg / m3).

Photo 9. Content of ambient air parameters, package HU-CW01

Page 31: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

31

- Noise monitoring result in the project area show that: noise (Leq) at the monitoring site is

below the permissible limits according to the Regulation of QCVN 26: 2010 / BTNMT -

National Technical Regulation on noise.

Photo 10. The chart shows noise parameters, package HU-CW01

Table 9. Results of surface water quality - package HU-CW01

No The parameters Unit Results

QCVN 08:2015/BTNMT,

column B1 NMPS

I Surface water

1 Temperature oC 21,4

2 DO mg/l 6,5 >4

3 BOD5 mg/l <1 15

4 COD mg/l <9 30

5 TSS mg/l <3,2 50

6 NH4 mg/l 0,026 0,9

7 Cl- mg/l <6 350

8 NO3 mg/l 0,024 10

9 PO4 mg/l 0,052 0,3

10 Oil mg/l <0,3 1

11 Fe mg/l 0,49 1,5

12 Coliform MPN/100ml 150 7,500

Page 32: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

32

Note:

QCVN 08: 2015 / BTNMT, National technical regulation on surface water quality, column B1 - used for irrigation water supply purposes or other purposes requiring similar or similar quality requirements. Purpose of use as type B2.

The monitoring results show that all 12 indicators measured at the sampling point of the HU-CW01 package are within the permitted limits of QVCN.

• Package HU-CW04:

Table 10. Results of analyzing ambient air quality - package HU-CW04

No The parameters Unit Result

QCVN/ TCVN Nov/2019 Dec/2019

KĐTX

I Air quality

I.1 Non organic QCVN 05:2013/BTNMT

(1h)

1 TSP µg/m3 36,0 59,7 300

2 SO2 µg/m3 <20 <20 350

3 NO2 µg/m3 <25 38,9 200

I.2 Organic

4 HC µg/m3 4900 1170 5000

II Tiếng ồn QCVN 26:2010/BTNMT

(8h)

1 Noise (Leq) dBA 59,3 58,9 70

Legend:

QCVN 05: 2013 / BTNMT, National technical regulation on ambient air quality, average of 01 hour.

QCVN 26: 2010 / BTNMT: National technical regulation on noise level.

Page 33: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

33

Photo 11. Content of ambient air parameters, package HU-CW04

Photo 12. Content of noise parameters, package HU-CW04

Based on the results of monitoring ambient air quality, the graphs show the content of

ambient air parameters.:

- Content of SO2, NO2, TSP at the monitoring site from November to December 2019 is within the permitted limits of QCVN 05: 2013 / BTNMT (1h) (SO2: 350 µg / m3, NO2: 200 µg / m3, TSP: 300 µg / m3).

- The hydrocarbon content (HC) ranges from 1170 - 4900 µg / m3 within the permitted limits of QCVN 06: 2009 / BTNMT (1h) (5000 µg / m3).

- The results of noise monitoring in the project area show that: noise (Leq) at the monitoring sites in the three periods of November and December 2019 are within the permitted limits according to the provisions of QCVN 26: 2010. / BTNMT - National Technical Regulation on noise.

Page 34: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

34

• Package HU-CW05:

Table 11. Results of analyzing ambient air quality - package HU-CW05

No The parameters Unit

Results

QCVN/ TCVN KX 281/5/1 (Oct/2019)

KX 308/2/1 (Nov/2019)

KVNG (Dec/2019)

1 TSP µg/m3 124 97 < 30 300

2 SO2 µg/m3 35 41 <20 350

3 NO2 µg/m3 39 40 36,5 200

4 HC µg/m3 226 211 1340 5000

5 Noise: Sound level (Leq)

dBA 59 59 58,0 70

Legend:

QCVN 05: 2013 / BTNMT, National technical regulation on ambient air quality, average of 01 hour.

QCVN 26: 2010 / BTNMT: National technical regulation on noise.

Based on the results of monitoring ambient air quality, the graphs show the content of

ambient air parameters.:

- Content of SO2, NO2, TSP at the monitoring site from October to December 2019 is within the permitted limits of QCVN 05: 2013 / BTNMT (1h) (SO2: 350 µg / m3, NO2: 200 µg / m3, TSP: 300 µg / m3).

- The hydrocarbon content (HC) ranges from 211 - 1340 µg / m3 within the permitted limits of QCVN 06: 2009 / BTNMT (1h) (5000 µg / m3).

- The results of noise monitoring in the project area show that: noise (Leq) at the monitoring sites in the three periods of October - November and December 2019 are within the permitted limits according to the provisions of QCVN 26: 2010. / BTNMT - National Technical Regulation on noise.

Photo 13. Comparison of ambient air quality with QCVN, package HU-CW05

Page 35: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

35

V. COMMUNITY CONSULTATION, INFORMATION DISCLOSURE AND GRIEVANCE

REDRESS MECHANISM

5.1. GRM organization:

The PMU has made the information disclosure about ADB's grievance redress mechanism

on the province's television and broadcasting.

Specifically, on August, 9th, 2019, PMU issued an official letter No. 122/BC-BQLDA to the

local authorities in the project-affected area about the public coordination of ADB's grievance

redress mechanism to the GreenCity project community to implement information disclosure

to all households, communities of affected areas on the Contract Package HU-CW05:

“Pavement, Drainage and Lighting in An Van Duong New Urban Area” and package HU-

CW01 “Water Supply to Phu Son Villages and Municipal Solid Waste Treatment Facility -

Hương Thuy town” on letter no 125/BC-BQLDA.

More ever, on December, 18th, 2019, information disclosure of contract package HU-CW04”

Park, Path, and Square of Provincial Administration Center” has been sent to relevant parties

on Official letter no 280/BC-BQLDA.

VI. SUMMARY OF ENVIRONMENT COMPLIIANCE DURING MONITORING PERIOD

During Environmental monitoring period from October to December, 2019, Environmental and Safety pending issues are listed as follow:

Table 12. Pending issues and Corrective action

No Contract package Pending issues Corrective actions

1

HU-CW01 - Water

Supply to Phu

Son Villages and

Municipal Solid

Waste Treatment

Facility - Hương

Thuy town

Some waste oil containers are not gathered in the right place. Gathering to the location of the rented house at the end of the working day, not promptly cleaning up

Machines after finishing use

must be temporarily stored

in warehouse or transported

to other places.

Containers of oil and hazardous waste should be gathered in covered warehouses, walls, high ground, away from water sources.

2

HU-CW04: Park, Path, and Square of Provincial Administration Center

Contractor has just set up construction site and fence. No environmental and safety issues are raised during monitoring period.

Not implemented training course on Labour safety, fire protection, HIV – AIDS awareness training.

Staffs and workers must be trained before commence date.

3

HU-CW05: Pavement, Drainage and Lighting in An Van Duong New Urban Area

Water drainage system: Status of standing water in ditches laying pipes.

The contractor should have water pumping in the foundation pit to ensure safety for construction workers and electrical safety.

VII. CONCLUSION

Compliance with the Environmental Management Plan of the subprojects is being fully

implemented by the PMU in coordination with the parties. During the implementation of the

Page 36: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

36

contract from October 2019 to the end of December 31, 2019, environmental documents and

processes such as CEMP, Outline of monitoring and sampling of environmental analysis,

Monthly report, the approval process for the above-mentioned products is discussed and

resolved by PMU, Environmental Specialist of PMCS in collaboration with related

contractors. However, in order to achieve greater effectiveness in the implementation of the

environmental management plan, there are some recommendations:

- Require serious contractors to make monthly reports to the Consultant and PMU to

promptly grasp the issues and provide solutions. The Contractor's monthly

Environmental Report should be timely updated and completed by the 15th of the

following month or submitted earlier depending on the progress of the PMCS semi-

annual report or other progress reports as requested by PMU and ADB.

- Request the Contractor and the Consultant to strengthen coordination with the PMU,

to report as soon as the contractor's problem is detected so that the PMU takes timely

measures, not to get to the end of the month.

- Regarding the results of environmental quality monitoring: In general, the

environmental quality of all packages of the Project at the time of monitoring is valid

within the permissible limits of the Vietnamese Regulation.

Page 37: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

37

VIII. APPENDIXES

8.1. Appendix 1. Checklist: Site instruction of Consultant

Page 38: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

38

Page 39: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

39

Page 40: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

40

Page 41: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

41

Page 42: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

42

Page 43: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

43

Page 44: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

44

Page 45: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

45

8.2. Appendix 2. Checklist: Labor contracts, Labor safety and fire and explosion

prevention training

Package HU-CW01

Page 46: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

46

Page 47: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

47

Page 48: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

48

Package HU-CW05

Page 49: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

49

Page 50: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

50

Page 51: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

51

8.3. Appendix 3. Checklist: Registering machinery and equipment of the

contractors

Package HU-CW01

Page 52: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

52

Page 53: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

53

Package HU-CW05

Page 54: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

54

Page 55: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

55

8.4. Appendix 4. Environmental quality monitoring results in Quarter 4/2019

Sampling surface water NMPS, package HU-CW01

Sampling air, noise, package HU-CW01

Sampling air, noise, package HU-CW05

Sampling air, noise, package HU-CW05

Page 56: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

56

Package HU-CW01

Page 57: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

57

Page 58: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

58

Page 59: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

59

Package HU-CW04

Page 60: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

60

Page 61: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

61

Package HU-CW05

Page 62: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

62

Page 63: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

63

Page 64: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

64

8.5. Appendix 5. Agreement minutes of waste disposal

Page 65: Environmental Monitoring Report€¦ · Regarding environmental safety issues, the Implementing Agency issued Decision No. 2440 / SKHĐT-BQLDA dated September 10, 2018 on establishing

65