ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... ·...

155
Environment Protection Committment –Water Supply System in My Phuoc Urban and Industry Employer: Binh Duong Water Supply Sewerage Environment Co., Ltd BINH DUONG PROVINCIAL PEOPLE’S COMMITTEE BINH DUONG WATER SUPPLY, DRAINAGE AND ENVIRONMENT ONE NEMBER LIMITED COMPANY ----------------------- ENVIRONMENTAL ASSESSMENT AND ENVIRONMENTAL MANAGEMENT PLAN FOR VIETNAM URBAN WATER SUPPLY AND WASTEWATER PROJECT MY PHUOC URBAN AND INDUSRIAL WATER SUPPLY SUB-PROJECT BINH DUONG PROVINCE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... ·...

Page 1: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

BINH DUONG PROVINCIAL PEOPLE’S COMMITTEEBINH DUONG WATER SUPPLY, DRAINAGE AND ENVIRONMENT ONE

NEMBER LIMITED COMPANY-----------------------

ENVIRONMENTAL ASSESSMENT ANDENVIRONMENTAL MANAGEMENT PLAN

FOR

VIETNAM URBAN WATER SUPPLY ANDWASTEWATER PROJECT

MY PHUOC URBAN AND INDUSRIAL WATER SUPPLYSUB-PROJECT BINH DUONG PROVINCE

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb370910
Typewritten Text
E2609
wb370910
Typewritten Text
v.1
Page 2: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 1

CONTENT

Page

LIST OF TABLE ................................................................................................ 4LIST OF PICTURE ........................................................................................... 5SUMMARY OF CONTENTS OF ENVIRONMENT IMPACTASSESMENT REPORT .................................................................................... 81. INTRODUCING SUBPROJECT AREA AND ABOUT THESUBPROJCET ................................................................................................. 101.1 INTRODUCING SUBPROJECT AREA .................................................... 101.2 INTRODUCTION THE SUBPROJECT .................................................... 102. POLICY AND LEGAL FRAMWORK OF EIA........................................ 122.1 Regulations, legal basis of Vietnam and technical background that theproject must comply with ................................................................................... 122.2 Requirements of World Bank ...................................................................... 143. DESCRIPTION OF PROJECT .................................................................. 163.1 Project name ................................................................................................. 163.2 Project Employer........................................................................................... 163.3 Position for components of the project ........................................................ 16

3.3.1 Position of raw water pumping station and raw water transmission main.......................................................................................................................... 173.3.2 Position of water treatment plant ........................................................... 183.3.3 Position for transmission main from Tan Hiep W.T.P to booster stationand Booster station........................................................................................... 18

4. SELECTING IMPLEMENTING METHOD FOR THE SUBPROJECT............................................................................................................................. 194.1 Selecting water source................................................................................... 194. 2 Selecting construction site for components of the subproject and technologyfor the treatment plant ......................................................................................... 19

4.2.1 Intake work – raw water pumping station and raw water mains ........... 194.2.2 WATER TREATMENT PLANT ......................................................... 234.2.3 Transmission and distribution network .................................................. 294.2.4 Booster station ........................................................................................ 30

4.3 Construction investment items of water supply system in My Phuoc urban area............................................................................................................................. 30(1) Raw water pumping station .......................................................................... 30(2) Raw water transmission mains ..................................................................... 30(3) Water treatment plant ................................................................................... 30

(4) Transmission distribution pipelines .......................................................... 32(5) Booster station............................................................................................ 32

5. FOUNDATION ENVIRONMENT OF THE SUBPROJECT ................. 33

Page 3: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 2

5.1 NATURAL, ECONOMIC AND SOCIAL CONDITIONS OF THESUBPROJECT ................................................................................................... 33

5.1.1 NATURAL CONDITIONS.................................................................... 33a.Location......................................................................................................... 33b. Climate......................................................................................................... 345.1.2 ECONOMIC AND SOCIAL STATUS IN THE SUBPROJECT AREA.......................................................................................................................... 35

(1) Demographic features in wards, communes ................................................ 35(2) Economic and environment sanitary in communes/wards ........................... 35

a. Jobs and income source ............................................................................... 35b. Living standard ............................................................................................ 37c.Water use situation ....................................................................................... 37d. Health situation and health care of people .................................................. 39

(3) Cultural assets in project area ....................................................................... 415.2 ENVIRONMENT QUALITY SITUATION IN PROJECT......................... 42

5.2.1 Air quality situation ................................................................................ 425.2.2 Surface water situation in project area .................................................. 425.2.3 Sludge quality from treatment plant ....................................................... 47

6. ENVIRONMENTAL IMPACTS AND RELEVANT MEASURES OFITS MITIGATION............................................................................................ 486.1 Useful Impacts of the project ........................................................................ 51

6.2 Environmental impacts and mitigation measures during construction ofwater treatment stations....................................................................................... 51

6.2.1 Impacts and mitigation measures due to land requisitioning ................ 516.2.2 Impacts and Mitigation Measures due to plant demolishment............... 516.2.3 Impacts and mitigation measures due to flooding and subsidence ....... 516.2.4 Impacts of land from construction process and spread of dust andmitigation measures ........................................................................................ 526.2.5 Impacts due to noise during site preparation and construction andmitigation measures ........................................................................................ 536.2.6 Site Drainage........................................................................................... 546.2.7 Impacts on environment of surface water, ground water, land andmitigation measures ......................................................................................... 55

6.3 Environmental impacts and mitigation measures during construction of rawwater pumping stations, booster pump stations, water transmission main ........ 556.3.1 Impact and mitigation measures due to land requisition ......................... 55

6.3.2. Disturbance to local residents and businesses activities ....................... 566.3.3 Impacts and mitigation measures due to construction process .............. 57

6.4. Impacts and mitigation measures during operation of the treatment plant . 676.5 Impacts and minimise measures for operating transmission and distribution

system ................................................................................................................ 746.6 Urgent measures of the subproject ............................................................... 75

Page 4: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 3

7. KẾ HOẠCH QUẢN LÝ MÔI TRƯỜNG .................................................. 777.1 Environment management program under the project ................................. 777.2 Requirement on reporting and monitoring ................................................... 907.3 Supervision program .................................................................................... 90

(1) Supervise contractor .................................................................................. 90(2) ) Supervise environment quality ................................................................ 90(3) Cost estimate for environment monitoring program ................................. 93(4) Training program on environment ............................................................ 98(5) Totaling environment protection costs .................................................... 100

7.4. Organize environment supervision and reporting...................................... 1017.4.1 Organize environment supervision....................................................... 1017.4.2. Reporting ............................................................................................ 105

8. COMMUNITY CONSULTATION........................................................... 1078.1 COMMUNITY CONSULTATION AND PUBLIC INFORMATION ..... 1078.2 SUMMARY TABLE OF COMMUNITY CONSULTATION................. 108

APPENDIX 1: PROJECT MAPAPPENDIX 2: PICTURES OF PROJECTS

APPENDIX 3: A SAMPLE FORM CHECKAPPENDIX 4:COMMUNITY CONSULTATIONAPPENDIX 5:THE ENVIRONMENTAL COMMITMENT

APPENDIX 6:LOCATIONMAP OF ENVIRONMETAL MONITORI

Page 5: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 4

LIST OF TABLESPage

Table 2. 1: Safety Policy of World Bank ........................................................... 14

Table 4.1: Sample result of water in Dong Nai river ......................................... 24

Table 4.2: Comparing advantages and disadvantages of 3 options .................... 29

Table 5.1.Economic structure in wards/communes in the project ar.................. 35

Table 5.2. Average income per capita/year in wards/communes in project area............................................................................................................................. 36

Table 5.3: Poor/rich level based on households’ evaluation and investigators’evaluation in model form ................................................................................... 37

Table 5.4. Use purpose of water source classified by regions .......................... 38

Table 5.5: water and environment sanitation related diseases ........................... 39

Table 5.6: Community awareness on disease causes.......................................... 40

Table 5.7: Result of air quality measurement in residential area hamlet 6 – MyPhuoc 3 industrial park ....................................................................................... 42

Table 5.8: Analysis result of water quality in Dong Nai river ........................... 43

Table 5.9: Analysis result of sludge from Tan Hiep water treatment plant........ 47

Table 6.1: Overall Assessment Matrix of Project Environmental Impacts ...... 49

Table 6.2. Maximum noise level from operations of vehicles and mechanicalconstruction equipment ....................................................................................... 53

Table 6.3 :Emission amount caused by vehicles during leveling . ..................... 59

Table 6.4: Maximum noise level from operations of vehicles and mechanicalconstruction equipment ....................................................................................... 61

Table 6.5. Characteristics of traffic obstructing impact ..................................... 63

Table 7.1. Environment management program .................................................. 79

Table 7.2: Cost estimate for environment supervision in construction phase ... 94

Table 7.3: Cost estimate for environment supervision during operation ........... 95

Table 7.4: Training on environment.................................................................... 98

Table7.5 : Totalling environment protection costs ........................................... 100

Table 8.1: The sum of community consultation ............................................ 109

Page 6: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 5

LIST OF FIGURESPage

Figure 3.1: : General layout of Water Supply System in My Phuoc Industry andUrban .................................................................................................................. 17

Figure 3.2: Layout of raw water pumping station and raw water transmission.. 18

Figure 4.1: Intake work of Tan Hiep W.T.P ....................................................... 22

Figure4.2: Raw water pumping station of Tan Hiep W.T.P 22

Figure 4.3: Raw water transmission main on ĐT 746 road ................................ 23

Figure 4.4: Area of water treatment plant .......................................................... 23

Figure 6.1:Waste water treatment process at treatment station .......................... 72

Figure 7.1: Amendment and feedback mechanism........................................... 106

Page 7: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 6

LIST OF ABREVIATIONS

BOD Biochemical Oxygen Demand Nhu cầu oxy sinh hóa COD Chemical Oxygen Demand Nhu cầu oxy hóa học CPC Commune People’s Committee Ủy ban xã DO Dissolved Oxygen Oxy hòa tanDONRE Department of Natural

Resources and EnvironmentSở Tài nguyên và Môi trường

DPC District People’s Committee Ủy ban quận, huyện EA Environmental Assessment Đánh giá môi trường EC Environmental Consultant Tư vấn môi trường EG Environmental Guideline Hướng dẫn môi trường EIA Environmental Impact

AssessmentĐánh giá tác động môi trường

EMO Environmental ManagementOffice

Phòng quản lý môi trường

EMP Environmental ManagementPlan

Kế hoạch quản lý môi trường

EO Environmental Officer Nhân viên môi trường EPC Environmental Protection

CommitmentCam kết bảo vệ môi trường

ES Environmental Supervisor Người giám sát môi trường FS Feasibility Study Nghiên cứu khả thi GOV Government of Vietnam Chính phủ Việt Nam IBRD The International Bank for

Reconstruction andDevelopment

Ngân hàng tái thiết và phát triển

IDA International DevelopmentAssociation

Hội liên hiệp phát triển quốc tế

IEC Independent EnvironmentalConsultant

Nhà tư vấn môi trường độc lập

BIWASE Binh Duong Water Supply –Sewerage – Environment Co.,LTD

Công ty TNHH MTV cấp thoát nước – môi trường Bình Dương

MABUTIP Management Board ofTechnical InfrastructureDevelopment Project

Dự án mở rộng quản lý phát triển cơ sở hạ tầng kỹ thuật

MONRE Ministry of Natural Resourcesand Environment

Bộ Tài nguyên và Môi trường

NGO Non-GovernmentalOrganization

Tổ chức phi chính phủ

OP Operational Policy Chính sách vận hành PC Public Consultation Ý kiến cộng đồng PM Particulate MatterPMU Project Management Unit Đơn vị quản lý dự án PPC Provincial People’s Committee Ủy ban tỉnh PWSC Provincial Water Supply Công ty cấp nước cấp tỉnh

Page 8: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 7

CompanyROW Right of Way Biện pháp thích hợp RP Resettlement Plan Kế hoạch tái định cư TDS Total Dissolved Solids Tổng chất rắn hòa tan TPC Town People’s Committee Ủy ban thị trấn TSS Total Suspended Solids Tổng chất rắn lơ lửng VDIC Vietnam Development

Information CenterTrung tâm thông tin phát triển Việt Nam

VUWSDP I First Vietnam Urban WaterSupply Development Project

Dự án phát triển cấp nước đô thị Việt Nam đầu tiên

VUWSWP Vietnam Urban Water Supplyand Wastewater Project

Dự án phát triển cấp nước và nước thải đô thị Việt Nam

VUWSP Vietnam Urban Water Supplyand Wastewater Project

Dự án cấp nước và nước thải đô thị Việt Nam

WB The World Bank Ngân hàng thế giới WTP Water Treatment Plant Nhà máy xử lý nước thải

Page 9: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 8

SUMMARY OF CONTENTS OF ENVIRONMENT IMPACTASSESMENT REPORT

Water Supply System in My Phuoc Urban and Industrial Park subproject is acomponent of Vietnam Urban Water Supply Wastewater Project. The subprojectwill develop and improve water supply for My Phuoc urban area, including 02communes Chanh Phu Hoa, My Phuoc townlet in Ben Cat district. Water supplysubproject include installing equipments for Raw water pumping station, whichexploit raw water in Dong Nai river, and newly build Water Treatment Plant,capacity 30,000 m3/day, transmission system and distribution system to enlargecoverage area for more households and commercial units to get drinking water.The coverage area is expected to reach 90% in My Phuoc urban area after thecompletion of Water Supply System in My Phuoc Urban and Industrial ParkSubproject.

Water Supply System in My Phuoc Urban and Industrial Park Subproject isclassified as type B project by World Bank. This requires an EnvironmentAssessment and Environment Management Plan (EA/EMP) to be prepared forWater Supply System in My Phuoc Urban and Industrial Park, to meetrequirements of environmental protection by World Bank.

Consulting affected households, People’s Committee at commune, districtlevels, Fatherland Front Committee, where the subproject go through wasorganised at office of People’s Committees in Thoi Hoa, Ben Cat, Tan Hiep,Uyen Hung on 16 and 17 September 2010, to get their opinion and concern onthe subproject. In such meeting, contents of the subproject and environmentalprotection required for the subproject was presented to local people andparticipants. Matters given out in the meetings were almost related to publicsafety with operations of erosion, depression, hindering traffic, dust pollution,surface water etc. All participants agreed with contents of results of theenvironmental protection commitment in subproject. Participants confirmed thatno cultural property and other values affected by the subproject. Department ofNatural Resources and Environment in Binh Duong province and Tan UyenPeople’s Committee also confirmed that no wild animal in danger or rare animalin the project area. In the EA/EMP, potential impacts by the subproject aremostly temporary, impacts by construction activities do not affect much onliving environment, ecological source and cultural property. While positiveimpacts by the clear water supply increase more value than short term impactsby related construction activities. Usual impacts by construction phase are dust,noise, traffic hinder, removal from construction can be prevented or reduced byeliminate measure as proposed in the environment protection commitment.During operation phase of the subproject, it should have measure to ensure thatraw water pumping station can manage chemicals for treatment in accordance

Page 10: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 9

with standard of Vietnam, sludge from treatment process is managed underregulations of the Vietnam Environment Law. Wastewater and solid wastewatergenerated from components of the subproject are treated in standard andregulation of Vietnamese law before discharging.

EMP for this subproject include measures to eliminate impacts and requiremonitoring the environment quality for management and monitor unexpectedand expected impacts by the subproject. This EMP also defines responsibilitiestoorganise and develop capacity and request to train staff of PMU underBIWASE to be able to control the implementation of EMP. To implement EMPrequires assistance from Environment Consultant (EC), andIndependentEnvironment Consultant (IEC) to audit EMP. Cost for EMPimlementing cover cost for EC to assist kiwaco / PMU to carry out the EMP.

Page 11: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 10

1. INTRODUCING SUBPROJECT AREA AND ABOUT THESUBPROJECT

1.1 INTRODUCING SUBPROJECT AREAMy Phuoc Urban (MP) located in the center of Ben Cat district, away Thu

Dau Mot town about 18 km in north. It began construction in 2002 under thedirection of a combination of industrial activities and development of residentialand commercial to ensure long term and sustainable. The entire of Phuoc MyUrban (except MP4) occupying an area of about 5,100 hectares.

The total area of MP3 is 2,242 hectares, in which 1,027 ha for urbandevelopment (45% of total area), 998 ha for industrial parks and 217 hectares forother purposes. By January 7 / 2009 population of MP3 is about 31,000 people;the detailed planning residential of MP3, population of this area will reach90,000 by 2015 and 122,000 people in 2020. Urban MP3 will be the place tolive and work of the people, the resettlement households, immigrant workersand specialists of MP3, workers in MP1, MP2 and the surrounding area.

The water system of MP3 is under the demand for water increasingrapidly. It is a pressing need for continuous growth and social economicdevelopment of MP3 and surrounding areas.

With the purpose to supply enough water for people in urban and socialeconomic development the water supply systems of MP3 need to be newconstruction and upgrades

1.2 INTRODUCING THE SUBPROJECT

In 2007, Government of Vietnam (The Government) and World Bank(WB) agreed a preparation for the Vietnam Urban Water Supply andWastewater Project(VUWSWP).

Objective of the VUWSWP aimed at improving clear water supply sourcefor urban areas in Vietnam. My Phuoc Urban and Industrial Park belongs toBinh Duong province, which represents for one of the five subprojects atprovincial level of the VUWSWP. Other subprojects are chosen for Kien Giang,Dak Lak, Quang Nam and Quang Ninh.

General objective of the My Phuoc project is to provide clean water for

households and economic activities, social ...of the MP3 urban area in stage of

development until 2020. Thereby it contributes to improving the living

conditions of people, creating prerequisites for the establishment of industrial

development, investment attraction as well as long term, contributing to push

economic development of Binh Duong Province.

Page 12: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 11

The scope of the project is to serve MP3 urban area (1,027 hectares),including residential area (house, apartment and housing group), producinghandicrafts, offices, commercial establishments and services.

Proposed service area of the subproject does not include MP3 industrialpark (998ha), because this industrial park will be partly supplied with waterfrom existing underground system of MP3-1, MP3-2 station and partly from TanHiep Water Plant – phase 2, capacity 30,000m3/day (to be final inspected andhanded over in end 2010.

To ensure subprojects priority supply water for MP3, BIWASE mustcommit to ensure the water supply rate of household must be at least 90% aftercompleted sub-projects. When MP3 unused full capacity it will open valveconnected to support urban residential MP1, MP2.

Page 13: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 12

2. POLICY AND LEGAL FRAMWORK OF EIA

2.1 Regulations, legal basis of Vietnam and technical background that theproject must comply with

Environmental Protection Law of Vietnam No. 52/2005/QH11 ratified byNational Assembly of Socialist Republic of Vietnam on 29/11/2005, validfrom 01/07/2006.

Water Resource Law No. 08/1998/QH10 ratified on 20/05/1998 byNational Assembly of Socialist Republic of Vietnam, section X, Thirdmeeting.

Construction Law No. 16/2003/QH11 ratified on 26/11/2003 by NationalAssembly of Socialist Republic of Vietnam.

Land Law No. 13/2003/QH11 ratified on 26/11/2003 by NationalAssembly of Socialist Republic of Vietnam.

Fire Prevention and Fighting law No. 27/2001/QH10 ratified on29/06/2001 by National Assembly of Socialist Republic of Vietnam.

Labour Law dated 23/06/1994 of the Socialist Republic of VietnamDecree No. 80/2006/NĐ-CP dated 09/08/2006 of the Government on “Detail regulations and instruction to implement articles of theEnvironment Protection Law”.

Decree No. 117/2009/NĐ-CP dated 31/12/2009 of the Government on “To fine administrative violence in environmental protection”

Decree No.21/2008/NĐ-CP dated 28/02/2008 of the Government on changing, supplementing some articles of Decree No. 80/2006/NĐ-CP of the Government on detail regulations and instruction to implement somearticles of Environment Protection Law.

Circular No. 05/2008/TT-BTNMT of Ministry of Natural Resources andEnvironment issued on 8/12/2008 promulgating environmentalassessment, strategy and environmental impact assessment andcommitment to protect the environment.

Decree No. 04/2007/NĐ-CP dated 08/01/2007 of the Government on changing supplementing some articles to Decree No. 67/2003/NĐ-CP dated 13/06/2003 of the Government on “Environmental Fee charged towastewater”

Decree No. 149/2004/NĐ-CP dated 27/07/2004 of the Government on “Regulations to give license for investigating, exploiting and using waterresource and discharging waste water into receiving water sources”

Page 14: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 13

Decree No. 59/2007/NĐ-CP dated 09/04/2007 of the Government on solid waste management.

Decree No. 88/2007/NĐ-CP dated 28/05/2007 of the Government on drainage in urban and industrial park

Decree No. 35/2003/Nđ-CP dated 4/4/2003 of the Government on detail regulation to implement some articles of Fire Prevention & Fighting Law

Circular No. 12/2006/TT-BTNMT dated 26/12/2006 of Ministry ofNatural Resources & Environment promulgating “Conditions to dobusiness and procedure to set up file, registration, granting license, solidwaste management code”

Circular No. 39/2008/TT-BTC dated 19/05/2008 of Ministry of Financeinstructing implementation of Decree No. 174/2007/NĐ-CP dated 29/11/2007 of the Government on environmental protection fee chargedto solid waste.

Circular No. 02/2005/TT-BTNMT dated 24/06/2005 of Ministry ofNatural Resources & Environment instructing implementation grantinglicense to investigate, exploit and to use water resources and to dischargewastewater into water sources.

Circular No. 04/2004/TT-BCA dated 31/03/2004 of Ministry of Policeinstructing implementation of Decree No. 35/2003/NĐ-CP dated 4/4/2003 of the Government promulgating details to implement articles of the FirePrevention & Fighting Law.

Circular No. 37/2005/TT-BLĐTBXH dated 29/12/2005 of Ministry of Labor, Social Disable instructing training on work safety and worksanitary.

Decision No. 23/2006/QĐ-BTNMT dated 26/12/2006 of Ministry of Natural Resources & Environment giving “List of hazardous waste”

Decision No. 3733/2002/QĐ-BYT dated 10/10/2002 of Ministry of Health promulgating “21 standards on labor sanitation, 05 principles and07 parameters of labor sanitation”

Decision No. 22/2006/QĐ-BTNMT issued by Ministry of Natural Resources and Environment dated 18/12/2006 forcing to comply withenvironmental standards.

National Technical Standards on planning construction No. 04/2008/QĐ-BXD dated 3/4/2008 of Minister of Construction.

Decision No. 04/2008/QĐ-TNMT dated 18/07/2008 promulgating national technical standard on environment.

Page 15: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 14

Decision No. 16/2008/QĐ-BTNMT dated 31/12/2008 of Ministry of Natural Resources & Environment issuing national technical standard onenvironment.

Decision No. 68/QĐ-UBND dated 12/12/2008 of Binh Duong Provincial People’s Committee on protecting the environment in Binh Duongprovince

Decision No. 1929/QĐ-TTg dated 20/11/2009 of Prime Minister approving Development Orientation for water supply system in urban andindustrial park in Vietnam in 2025 and oriented to 2050.

General Planning of water supply system in Binh Duong province, phase2005-2010 and oriented to 2020 approved by Binh Duong ProvincialPeople’s Committee in the decision No. 78/2005/QĐ-UB dated 24/05/2005.

General Planning of My Phuoc Urban area in Binh Duong province

2.2 Requirements of World BankAll requirements of EIA issued by World Bank are presented in operation policy(OP) and banking procedures (BP) of World Bank. Requirement for EIA isdescribed by OP / BP 3.01. Depending on different OP/BP, safety policy can beactivated. Policies are based on the VUWSWP listed in below table 2.1

Table 2. 1: Safety Policy of World Bank

Safety policy based on VUWSWP Yes No

Environment Assessment (OP/BP3.01) X

Natural Environment (OP/BP 3.04) X

Harmful disease management (OP 3.09) X

Cultural Property (OPN 11.03, OP 3.11) X

Resettlement & Removal (OD 3.30)** X

Native inhabitant (OD 4.10) X

Forest (OP/BP 3.36) X

Dam Safety (OP/BP 3.37) X

Dispute [OP/BP/GP 8.60)* X

Page 16: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 15

Safety policy based on VUWSWP Yes No

International river way project (OP/BP 8.50) X

Table 1. 2:vbhnb,mnm,n.,,.m.m./,./jkv

* Updated from appraising documents of VUWSDP 1** Resettlement Plan was prepared by another report

Page 17: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 16

3. DEBSRIPTION OF PROJECT

3.1 Project name:

VIETNAM URBAN WATER SUPPLY WASTEWATER PROJECTWATER SUPPLY SYSTEM IN MY PHUOC INDUSTRY AND URBAN

(CAPACITY: 30,000M3/DAY)

The project consists of:

Raw water pumping station; Raw water transmission main; Water treatment plant; Treated water transmission main from the plant to booster station; Booster station.

3.2 Project Employer

Name: Binh Duong Water Supply Sewerage Environment Co., Ltd

Address: 11- Ngo Van Tri street, Phu Loi ward, Thu Dau Mot town, Binh Duongprovince

Tel: 0650.3827789 Fax: 0650.3827738

Business registration of the company: No. 3700145694, seventh adjustment onJanuary 22, 2010 issued by Binh Duong Department of Planning and Investment.

Represented by: NGUYEN VAN THIEN Position: General Director

Nationality : Viet Nam

3.3 Position for components of the project

All components of Water Supply System in My Phuoc Industry andUrban are located in Tan Uyen district (raw water pumping station, raw watertransmission main, water treatment plant), Thu Dau Mot town (transmissionmain from water treatment plant to booster station), Ben Cat district (boosterstation) in Binh Duong province. Position of project components is presented inthe Binh Duong map as follows:

Page 18: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 17

3.3.1 Position of raw water pumping station and raw water transmissionmain

+ Raw water intake work and raw water pumping station are placed in UyenHung townlet, Tan Uyen district, Binh Duong province. Position of the pumpingstation as follows:

In west: 300m far from DT 747 road In East: Dong Nai river In North: agricultural land In South: household who exploiting sand

+ Raw water transmission main in this project has diameter of D=1,000mm, beinginstalled along DT 746 and DT 747 road and closed to existing raw water pipeline

Firgure3.1: General layout of Water Supply System in My Phuoc Industry and Urban

Page 19: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 18

DN=800mm, which across Uyen Hung commune, Khanh Binh commune, Tan Hiepcommune, Tan Uyen district, Binh Duong province.

Figure 1.1: Layout of raw water pumping station and raw water transmission

3.3.2 Position for water treatment plant

The water treatment plant in this project will be built in reserved land for futureexpansion of Tan Hiep water treatment plant, which border to South East connerof Binh Duong Urban Industry Service Complex (outside the industrial park),located in Tan Hiep commune, Tan Uyen district, Binh Duong province.

3.3.4 Position for transmission main from Tan Hiep W.T.P to boosterstation and Booster station

Transmission main from Tan Hiep W.T.P to booster station

Transmission main from Tan Hiep W.T.P to booster station has diameterof D=1,000mm, going through Binh Duong Urban Industry Service Complex,Kim Huy industrial park, VSIP industrial park, Phu Gia industrial park, Đong An 2 industrial park with total length of 10,800m.

Booster station

My Phuoc booster station is placed within My Phuoc 3.2 water treatment plant,on XE1 road in My Phuoc 3 industrial park, Ben Cat district, Binh Duongprovince. Total area of the station is 25,128 m2

Page 20: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 19

4. SELECTING IMPLEMENTING METHOD FOR THE SUBPROJECT

4.1 Selecting water source

The underground water source in the project area is being deteriorated in bothvolume and quality due to careless exploitation previously. Thus, it shouldrestrict further exploiting and have protective method or strict management tokeep this source as reservation for the area. It should firstly study and investigatethe volume in an accurate manner to have believable basis for planning theexploitation when needed.

Surface water source which can be used as raw water source to treat in thisproject is taken from Đong Nai river. According to updated data on this river and through real construction and development in upstream of this river (atposition closed to the project’s position), it has shown that taking raw waterfrom Đong Nai river will have some advantages as follows:

- Some currently construction works of water supply system in Binh Duongsuch as: South Thu Dau Mot water supply project funded by ADB, TanHiep water treatment plant financed by ODA loan of the Netherland. Allthese two projects selected surface water in Đong Nain river to treat.

- On the other hand, if surface water in Đong Nai river is chosen to provide raw water to treat in this project, there would be some advantages such as:good surface conditions, can utilise the same raw water intake work, rawwater pumping station of Tan Hiep plant, just need to install more pumpsand equipments.

From above evaluation, surface water in Đong Nai river is selected for treatment serving the My Phuoc urban area, Binh Duong province for development phaseoriented to 2020.

4. 2 Selecting construction site for components of the subproject andtechnology for the treatment plant

4.2.1 Intake work – raw water pumping station and raw water transmissionmain

(1) Raw water pumping stationTo take water from Đong Nai river serving for the subproject and to build

intake gate-raw water pumping station on the river side, within distance fromUyen Hung townlet to Tan Ba is considered the most suitable. Building intakework – raw water pumping station on this river distance combine with selectingposition for raw water transmission main from the intake work leading totreatment plant, located in reserved land for the subproject.

Page 21: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 20

Alternatives :

Through actual investigation, there are 03 relative good and feasible alternativesfor consideration to build the intake work – raw water pumping station asfollows:

a. Alternative 1 :

Intake work, raw water pumping station is placed in hamlet 3A, Khanh Binhcommune, Tan Uyen district (near Binh Chanh chapel). From there,transmission main will go through the field to road ĐT 747 in straight angle with this road (at T-junction ĐT 747 and road leading to Binh Duong brick plant), acrossing the field, field, form products and residential area in hamlet 3B, KhanhBinh commune (Ba chapel) leading to ĐT 746 (near Khanh Binh People’s Committee). From there, transmission main continues in paralell with road ĐT 746 (on right way going to the plant), going to Ben San bridge, acrossing fieldand coming to treatment plant.

This alternative shows that:

- At raw water pumping station :

o Relative flat terrain, large;

o Mostly fruit tree garden.

o Need to move 02 class 4 houses of people living there.

- Along raw water transmission main:

o Total length: 7,500m.

o Across field and hill with no traffic system, about 3,000m.

o Need to move some class 4 houses in hamlet 3B and at beginning T-junction leading to Binh Duong brick plant on ĐT 747.

b. Alternative 2 :

Position for intake work, raw water pumping station is at Tan Hiep raw waterplant, which is about 200m far from the intake work and raw water pumpingstation in upstream and about 19km far from MP3 in south east. From there, rawwater line acrosses alsphated road invested by the project owner leading to ĐT 747, then it goes through bare land (vehicles can go) in almost straigth directionto road ĐT 746, about 1,000m from Khanh Binh People’s Committee in north east. Then the pipeline will go in paralell with road ĐT 746 leading to treatment plant, which is relative similar to alternative 1.

Intake work has been invested for capacity of 120.000m3/day, therefore it does

not need new intake work for MP3.

Page 22: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 21

If following this alternative:

o Intake work has been invested for capacity of 120.000m3/day, therefore itdoes not need new intake work for MP3.

o In raw water pumping station:

o Terrain if flat, large and higher than surrounding

o Quality and flow of raw water at this gate is stable, no salinity, usingevaluation data of Tan Hiep W.T.P.

o Land has been already compensated in Tan Hiep project.

- Along raw water transmission main:

o Total length: about 7,800m.

o Considering terrain of the main, easy implementing method, low pressureloss.

o Acrossing bare land (field, hill…) about 2,300m, in which 1,200m ofwalking road that vehicles can transport

o No house or construction work on this route.

c. Alternative 3 :

Intake work, raw water pumping station is placed in downstream of intendedposition for pumping station and intake gate as mentioned in alternation 1 andabout 1,800m from there. Raw water transmission main will go through the fieldand residential area along road ĐT 747 (at T-junction ĐT 747 and red soil road leading to Phu Binh brick plant), along the red soid road going to Ben San, thengoing through the field to road ĐT 746 at the position after Ben San bridge (as in alternative 1 & 2) and coming to treatment plant as in alternative 1 and 2.

If following this alternative :

- At raw water pumping station:

o There are field, living land and garden

o Need to move 02 house of class 4.

- Along raw water transmission main:

o Total length: about 7,400m.

o At distance going through the field, there is no traffic road and vehiclescan not travel, its length about 2,500m.

o It will affect some houses along road ĐT 747 and red soil road

Selecting alternative :

Page 23: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 22

Considering the mentioned above alternatives, it shows that the alternative 2 hasmany advantages and the most feasible as follows (particularly in groundclearance)

- It only needs to invest more equipments (pump, electric system etc..) but canuse the same covering structure of intake work-raw water pumping station ofTan Hiep plant. The surface is available that land acquisition is not necessaryto carry out and reduce time and cost for land clearance, as well as preventrisk (due to not able to clear the land), any hinder (long negotiation time),which affect the subproject implementing process (time, coast, etc.)

- Terrain for raw water pumping station and raw water transmission main isrelative flat that can save cost and time for ground clearance

- On raw water transmission main, most of vehicles can easily travel which isadvantageous for construction and reduce cost and time for initial cost tobuild the road.

- Can combine to supply raw water for future Khan Bin water plant

- From such explanation, it recommends to select construction site for rawwater pumping station and intake work as in alternative 2.

Figure4.1: Intake work of Tan Hiep W.T.PFigure 4.2: raw water pumping station of Tan

Hiep W.T.P

Raw water transmission main

In 2020, estimated demand for clean water of the people living in My Phuoc 3 urbanarea is 30,000 m3/day. However, to fully meet the demand on clean water fordevelopment of My Phuoc 3 urban area, it requires 60,000 m3/day to 80,000 m3/day ofcapacity. Considering available construction surface, actual water demand and lifecycle of the water supply work, it recommends to invest a DN 1,000 raw watertransmission main in this project. Raw water transmission main will be placed intechnical corridor on road ĐT 746, distance in Tan Hiep commune, Khanh Binh commune and Uyen Hung townlet. The road owner of DT 746 is Becamex under

Raw water intake gate Awaiting pipe in raw water PS

Page 24: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 23

BOT contract as in decision No. 1353/QĐ-UBND dated 13/05/2010). Becamex and Biwase agreed in writing on position for water pipe. During construction phase of theroad, Becamex compensated and made resettlement, thus it does not need landacquisition.

Figure 4.3: Raw water transmission main on ĐT 746 road

4.2.2 Water treatment plant

Position for water treatment plant

Because of the importance and urgency to build a water treatment plantserving for demand on clear water in My Phuoc urban area, the water treatmentplant will be built in reservation land of Tan Hiep W.T.P. Planned capacity ofTan Hiep is 120,000m3/day, but it is operating at 30,000 m3/day in present time.The area of Tan Hiep is about 80,000 m2, which was planned enough land forall treatment facilities having capacity of 200,000m3/day. Thus, the surface isavailable for construction and does not need land acquisition.

Figure 4.4: Area of water treatment plant

Pipe position on road ĐT746

Reservation land for treatment

Page 25: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 24

Selecting treatment technology

Testing result of water taken in Dong Nai river serving for the subprojectgive out quality as follows:

Table 4.1: Sample result of water in Dong Nai river

No Norm Unit Dryseason

Rainyseason

VN Standard01:2009/BYT

1 pH 6.59 6.57 6.5-8.52 TDS mg/l 19 27 10003 Turbidity NTU 37.2 67 2.04 Color Pt-Co 10.73 82 155 Acid mg/l

CaCO3

6 16 -

6 Alkali mg/lCaCO3

18 18 -

7 Hardness Ca mg/lCaCO3

3.2 4 300

8 Clorua mg/l 8 10 2509 NO2

- -N mg/l 0.085 0.12 3.010 NO3

- -N mg/l 0.32 0.74 5011 NH4

+ -N mg/l kph 0.14 3.012 PO4

3- mg/l 0.06 0.09 -13 SO4

2- mg/l 2.07 7.73 25014 FeTC mg/l 1.97 1.98 0.315 Al mg/l 0.028 0.034 0.216 Cu mg/l 0.03 0.02 1.017 Zn mg/l 0.04 0.05 3.018 Mn mg/l 0.024 0.057 0.319 Oxydise mg/l 0.68 2.7 -20 DO mg/l 6.67 6.17 -21 COD mg/l 22 20 -22 BOD(20 ¨C) mg/l 0.06 0.3 -

According to Vietnam standard 01:2009/BYT : National Technical Standard onDrinking water quality issued by Ministry of Health, to supply water for allobjects in the region, this water source need treatment. Basing on capacity ofconstruction site and natural conditions of the region, operation management

Page 26: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 25

and actual experience, the treatment technology can be built following the underoptions :

Option 1 :

Option 2 :

Resevoir Filtration tankReaction tank with

suspended floculation

Clear water P.SDistribution

network

Clo

Lime Alum

Intake work

Raw water PS

Verticalmixing tank

Clo

Raw water pipe

Don

gN

airi

ver

Lime Alum

Intake work

Raw water PS

Verticalmixing tank

Filtration tank Horizontalsedimentation

Reaction tank withsuspended floculation

Resevoir Clear water P.S Distributionnetwork

Clo

Clo

Raw water pipe

Don

gN

airi

ver

Page 27: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 26

Option 3 :

In water treatment plant, it just gives out comparison of raw watertreatment technology (treatment group0 to select the optimal option. Othersupportive items such as clear water pumping station, chemical house, resevoiretc.. in all options are similar that no comparsion made for this part.

According to the introduced above technology lines, three optionsproposed for treatment plant as follows:

a. Option 1 :

Treatment items included in this technology as: vertical mixing tank,reaction tank with suspended flocculation, horizontal sedimentation tank, rapidfiltration tank.

Reaction tank with suspended flocculation is built in connection withhorizontal sedimentation tank. Calculation result (see note for basic design)shows that: with capacity 30,000m3/day, size of unit treatment items as follows:

- Rapid filtration tank: LxBxH = 25,5mx11,5mx5,7m.

Resevoir Filtration tankAccerlator

Sedimentationtank

Clear water P.S Distributionnetwork

Clo

Lime Alum

Intake work

Raw water P.S

Verticalmixing tank

Clo

Raw water pipe

Don

gN

airi

ver

Page 28: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 27

- Reaction tank with suspended flocculation in connection with horizontalsedimentation tank: Xbox = 45, 9mx13, 8mx5, 7m.

b. Option 2 :

Treatment items included in this technology as: vertical mixing tank,sedimentation tank with suspended flocculator, rapid filtration tank. When usingthis technology, it does not need to build reaction tank due to the reactionprocess taken in suspended floculator in sedimentation tank. Calculation result(see note for basic design) shows that size of unit treatment items as follows:

- Sedimentation tank with suspended floculator: LxBxH = 17mx36mx5m

- Rapid filtration tank: LxBxH = 25,5mx11,5mx5,7m

c. Option 3 :

Treatment items included in this technology as: vertical mixing tank,accelator sedimentation tank with suspended flocculator, rapid filtration tank.When using this technology, it does not need to build reaction tank due to thereaction process taken in suspended floculator in sedimentation tank.Calculation result (see note for basic design) shows that size of unit treatmentitems as follows:

- Accelator sedimentation tank : working size of tank D = 25m, H = 5,0m

- Rapid filtration tank: LxBxH = 25,5mx11,5mx5,7m

d. Analysing to select option:

here, it is just different in reaction tank and sedimentation tank, theselecting construction option will base on analysis and comparison theseitems between two options:

d1. Advantage and disadvantage of option 1

Advantages :

- Stable and safety working

- High treatment efficiency, less affected by change in raw water source(flow, quality) as well as impacts by surrounding natural conditions

- High ability to run overloaded.

- Easy operational management .

- Have experiences from some other similar works in the region.

- Similarly being used in Tan Hiep water plant, that high synchronous andeffective for operation and management

Disadvantages :

Page 29: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 28

- About 4% more construction area required.

- Bigger construction size and more investment cost.

d.2. Advantage and disadvantage of option 2

Advantages:

- Higher operating efficiency so that smaller construction size

- Less investment work, save cost (about 4% of sedimentation tank

- Less land required

- Reaction process is combined in suspended floculation that savechemicals for treatment.

Disadvantages :

- Treatment effectiveness is affected by raw water quality or flow of rawwater is suddenly changed ( >10%)

- If horizontal sedimentation tank stop operation or any change in quality,flow of input raw water, it needs about 1-2 hours (since the tank operatesagain or any change) to resettle operation of the tank and reach therequirements. This is ineffective period of the tank, quality of water aftersedimented not ensured, bad impacts to operation of other treatmentfacilities.

- Because working scheme of the sedimentation tank must be relativestable, more or less affected by change in surrounding naturalenvironment, specially change in temperature. On the other hand, it alsorequires strict operational management with higher requirements.

d3. Advantage and disadvantage of option 3

Advantages:

- Average treatment efficiency

- Smaller size, less land required for construction and lower investment costcompared with option 1.

- Not yet have experience in management and operation.

Disadvantages :

- Treatment efficiency depends on equipments, purchasing equipments isalso complicated

- Due to many corridors and partitions with narrow size (0,8m x 1,0m) andbig depth (5,0m), it is difficult in construction phase

Page 30: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 29

- Require high experience and proffesionals to operate and to manage.

- Limited and complicated for sludge disposal

- Not good overloading working

d4.- Selecting the option :

from analysing advantages and disadvantages of three options, we have acomparison as follows:

Table 4.2: Comparing advantages and disadvantages of 3 options

No Compared elements Option 1 Option 2 Option 3

1 Treatment efficiency High High Average

2 Stable working scheme High Average Average

3 Ability to run overloaded Good Average Average

4 Operational management Simple Complicate Complicate

5 Construction area Big Average Average

6 Initial construction cost High Average Average

7 Operational cost(chemical)

Average Low Average

8 Maintenance and repaircost

Low Average Average

9 Experience to operate andmanage of the employer

Much Less No

By comparing it shows that option 1 has more advantages than option 2 andoption 3, simpler and safer for operational management, stable working, highefficiency, less affected by change in surrounding natural environment, beside itis synchronous with existing work that is easy to operate and gain highereffectiveness. Therefore, option I is proposed to invest for this subproject.

4.2.3 Transmission and distribution network

Main transmission pipeline go through Binh Duong Urban IndustryService Complex, distribution network locate in My Phuoc 3 urban area, atpresent, technical infrastructure in the area has been completed that it does notneed land acquisition.

Page 31: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 30

4.2.4 Booster station

It lies in area of my Phuoc 3-2 water plant with available surface that it doesnot need land acquisition.

4.3 Construction investment items of water supply system in My Phuoc urbanarea

(1) raw water pumping station

Use the same covering house of tan Hiep raw water pumping station

- Install more equipments :

o 03 centrifugal pumps (02 working, 01 standby) with technicalspecification Q=750m³/h, H=65m

o Install clock valve and fittings

- Electric system :

o Install 01 transformer, 03 phase, capacity 1,000 KVA

o Install 01 diesel generator 03 phase, capacity 1,000 KVA,started by baterry 24 Vdc.

o Install ATS panel

(2) raw water transmission main

Install 9,000m of ductile iron pipe D1,000.

(3) Treatment plant

a. Vertical mixing tank:

- Quantity: 01 tank (building for total capacity up to 60,000 m3/day)

- Construction dimension: 01 round shape tank

- Diameter: D=6m

- Cylinder part: H = 1m

- Cone part: small bottom: d = 1.4m, big bottom D=6m

- Ferro- concrete structure made on site

b. Treatment group :

Building treatment group for capacity of 30,000m³/day, with dimension as :

Reaction tank with suspended floculator :

- Quantity: 03 cells

- Size of each cell: LxBxH = 7.4mx7.4mx5.8m

Page 32: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 31

- Ferro- concrete structure

Horizontal sedimentation tank:

- Quantity: 03 cells

- Size of each cell: LxBxH = 36mx7.4mx5.8m

- Ferro- concrete structureRapid filtration tank

- Quantity: 04 cells

- Size of each cell: LxBxH = 11.5mx 5mx5.37m

- Ferro- concrete structure

c. Clear water tank :

- Quantity: 01 tank having dimension as follow

- Build half on the ground and half under ground with ferro-concretestructure

- Size of the surface: LxB = 48.4m 48.4m

- Height of underground part: 2.0m

- Height of on the ground part: 3.0 m

d. Chemical house :

Chemical used for treatment are lime, alum and clo with quanity as follows:

- Lime : 15 g/m³ = 0,015kg/m³

- Alum : 35g/m³ = 0,035 kg/m³

- Clo : 5 g/m³ = 0,005 kg/m³

o construct 02 slakelime cells, size of each cell axbxh = 2.2m x 2.2m x 1m

o construct 02 consumed lime cells, size of each cell axbxh = 2.3m x 2.3m x1.75m

o construct 02 alum mixing and consumed cells, useful volume of each cellis 10,5m3

o install lime, alum and chlorine dosing equipments

o the cover house is built for lime, alum and chlorine, having size 10m x25m and divided into different specific rooms.

e. Clear water pumping station

Page 33: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 32

- Build half on the ground and half under ground

- Install equipments: 01 variable speed pump system including 03pumps (02 working, 01 standby), technical specification of each pump:Q = 750m3/h, H = 40m.

f. Electric system :

- Install 01 transformer, 03 phase, capacity 1,250 KVA

- Install 01 diesel generator 03 phase, capacity 1,250 KVA, started bybaterry 24 Vdc.

- Install lighting system within the plant area.

(4) Transmission distribution pipelines

To supply water for customers, the subproject will install about 66,800 mpipe of different diameters as follows:

- DI pipe D1000 : 3,000 m

- DI pipe D800 : 7,800 m

- DI pipe D600 : 4,000 m

- DI pipe D400 : 3,000 m

- uPVC D200 : 5,000 m

- uPVC D150 : 4,000 m

- HDPE D100 : 5,000 m

- HDPE D50-D90 : 35,000 m

- Meters and household connection pipe D20 : 13,500 sets

(5) Booster station

- Use resevoir of My Phuoc 3-2 water plant

- Booster station 30,000 m³/day: reuse covering structure of clear waterpumping station of MP3-2, install 01 frequency converter systemincluding 03 pumps, each pump has technical specification:Q=500m³/h, H=30m.

- Electric system :

o Install 01 transformer, 03 phase, capacity 250 KVA

o Install 01 diesel generator 03 phase, capacity 250 KVA, startedby baterry 24 Vdc.

o Install lighting system within the plant area.

Page 34: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 33

5. FOUNDATION ENVIRONMENT OF THE SUBPROJECT

5.1 NATURAL, ECONOMIC AND SOCIAL CONDITIONS OF THESUBPROJECT

5.1.1 NATURAL CONDITIONS

a. Location:

My Phuoc 3 urban and industrial park is a part of My Phuoc urban andIndustry Area in Ben Cat district, Binh Duong province. MP3 is about 2km inSouth East from My Phuoc townlet, 16km from Thu Dau Mot provincial townand 45km from Ho Chi Minh city in North.

My Phuoc 3 urban and industrial park belongs to Thoi Hoa commune andChanh Phu Hoa commune, Ben Cat district. In MP3, there is national rout No.13crossing (or Binh Duong boulevard). Boundary road No.4 also go through thecenter of MP3 in west-east direction.

Boundaries of My Phuoc 3 as follows:

- In North West : MP1area

- In North : MP2 area

- In South East : Binh Duong new city

- In East : Hoa Loi commune

- In south west : MP4 area

Thoi Hoa commune

It is a suburd commune of Thu Dau Mot town, Binh Duong province.People here mostly earn income by selling services and handicraft. Rate ofpeople living by working, agriculture production is very low. Based on statisticdata in 2008, population here including temporary immigrants in Thoi Hoacommune is about 33,000 inhabitants. Its geographical location is as follows:

- In North: road 7B – My Phuoc 2

- In South: Palanxi road

- In East: DT 741 road

- In West: National route No.13

Chanh Phu Hoa commune

Population of Chanh Phu Hoa commune estimated in end of 2008 wasabout over 15,000 inhabitants, with its geographical location as follows:

Page 35: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 34

- In North: residential area

- In South: existing residential area

- In East: My Phuoc 3 Industrial Park

- In West: National Route No. 13

b. Climate

Area of the subproject belongs to tropical moonson region with twodistinct seasons: rainy season starts from May to November and dry season fromDecember to April of the following year.

+ Air temperature:

- Annual average temperature : 250C

- highest temperature month in year is April : 28.80C

- lowest temperature month in year is January : 210C

+ Moisture

- Annual average moisture : 76,6%

- absolute minimum moisture : 65,2%

- absolute maximum moisture : 83%

+ Rain:

Rainy season starts from May to November, in those months, more than20 rainy days in a month. Most rain is in August, September and October(occupies 90% of annual rainfall). In dry season, there is almost no rain(January)

- Annual average rainfall : 2.177 mm

- Maximum rainfall : 2.638 mm

- Minimum rainfall : 1.961 mm

+ Evaporation

- Annual average evaporation : 1.350,5 mm

- daily average evaporation : 3,7 mm

- maximum daily evaporation : 13,8 mm

+ Wind

- two main wind direction: South west: from May to November; East-South East: from January to April

Page 36: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 35

- average windspeed at second and third class. Binh Duong province isalmostly not affected by storm.

5.1.2 ECONOMIC AND SOCIAL STATUS IN THE SUBPROJECT AREA

(1) Demographic features in wards, communes

According to statistic data of communes/wards in end of 2009, there were7,532 households with 19,809 inhabitants in total, at scale of 2.7 person/house,2,837 households with 11,511 person in total, at scale of 4 person/house.

(2) Economic and environment sanitary in communes/wards

a. Jobs and income source

With the development of the country, economic growth rate in BinhDuong has been very fast in recent years (over 10% of annual growth), greatlycontributed for industry development in the province. At present, Binh Duongplanned 25 industrial parks, of which 15 industrial park put into operation.These industrial parks solve job problems for lcal people and attracted manylabors from other provinces, thus many types of services established based onthat symptom.

Economic structure of Binh Duong strongly increased in industry,services, agricultural production occupied very small rate in economic structure.If in end of 2005, structure of Industry-Service-Agriculture in the province was63,8 % - 28,2 % - 8 % , this rate in 2008 was 64,8% - 29,5% - 5,7%respectively.

In strudying area for the project, economic structures of wards/communesare presented in below table:

Table 5.1. Economic structure in wards/communes in the project area

Economic structure (%) Thoi Hoa Chanh Phu Hoa

Industry 64,5 45

Commerce - Services 29,7 24,25

Agriculture 5,8 30,75

Page 37: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 36

Chart 5.1. Economic structure in wards/communes in project area

0

10

20

30

40

50

60

70

Thới

Hòa

Chánh

Phú

Hòa

Công nghiệp

Thương mại - Dịch vụ

Nông nghiệp

From above data, it showed that economic structure in wards/communesin project area had high industry rate, then commerce and service, andagriculture the lowest rate. Particularly in Thoi Hoa, agriculture rate was verylow, which showed that people mostly live by selling service and working infactories in the industrial park. On the contrary, in Chanh Phu Hoa, Ben Catdistrict, which is closed to Thu Dau Mot town, most of people live byagriculture activities that agriculture rate in Chanh Phu Hoa occupied the highestrate at 30.75%.

According to evaluation by officials in wards/communes, in recent years,average income per capita in wards/communes increased at rather high rate.

Table 5.2. Average income per capita/year in wards/communes in project area

Unit: 1,000 đ

Year Thoi Hoa Chanh Phu Hoa

2007 7500 7800

2008 9600 9200

2009 12200 16000

(Source: Avaliable data – Economic-Social Investigation Program)

Page 38: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 37

b. Living standard

In general, income and living standard of people in the project area israther high. If basing on new standard by Ministry of Labour Disable SocialAffairs (MOLISA): poor family is the family only has incomer under 260,000dong/person/month, poor rate in the project area is not much. However, due toliving in high economic development region, living cost is also high that there isa separate criteria to evaluate the rich/the poor. According to this criteria, anyfamily has average income per capita under 500,000đ/month is classified the poor. According to the criteria proposed by the local, the poor rate in communeswas defined as: 17 households in Thoi Hoa, occupied 3.26%, 35 households inChanh Phu Hoa, occupied 6.73%.

On the other hand, this economic-social investigation program was carriedout on some fixed form, about 5% over total households in the region, thus thisreport give out statistic data from the investigation program under two differentvision, based on criteria of poor level proposed by local community. Firstly, it isa self-evaluation on poor level of households, secondly it is evaluation byinvestigator based on established criteria combined with actual observation theinvestigation process.

Table 5.3: Poor/rich level based on households’ evaluation and investigators’ evaluationin model form

Evaluated by the community Evaluated by investigator

TTWards/commune

s PoorAvera

geFair Rich

Unknown

PoorAverage

FairRich

1 ThoiHoa

17 72 144 90 11 15 95 144 90

2 ChanhPhu Hoa

35 32 54 55 10 35 32 54 55

3 Total 52 104 198 145 21 50 127 198 145

(Source: Questionaires of Social Investigation Report of the project –2010) .

c.Water use situation

notwithstanding some population area on the main pipeline, closed todistribution pipeline of Tan Hiep water plant connected to clear water supplysystem, remaining areas in the project area, people must use different watersources as opened well, drilled well, rainwater, water in pond/river. Dependingon water demand, households can combined using 1 or 2 water supply sources,

Page 39: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 38

but most of people use 1 water supply source, number of families use two watersupply sources stand for the second. Number of families use three water supplysoucres is not much.

In avaialbe water supply sources, beside tap water, water from drilled wellis the most popular. This source is used in most of daily demand such as eating,drinking, bathing, washing and using for doing business and services.

In 520 investigated families, there are 52 families used tap water, 429families used drilled well, 34 families use opened well, 5 families use water inpond/river.

However, the families can combine using different water supply sources.

Table 5.4. Use purpose of water source classified by regions

Use purpose

Eat/Drink Bath/WashingWater sources

Number Rate (%) Number Rate (%)

Opened well

Thoi Hoa 10 29.4% 30 36,5%

Chanh Phu Hoa 24 70.6% 52 63.5%

Total 34 100.0% 82 100.0%

Drilled well

Thoi Hoa 198 46.1% 198 46.1%

Chanh Phu Hoa 231 53.9% 231 53.9%

Total 429 100.0% 429 100.0%

River/pond

Thoi Hoa 0 0 2 40.0%

Chanh Phu Hoa 0 0 3 60.0%

Total 0 0% 5 100%

Tap water

Thoi Hoa 32 61.5% 25 59.5%

Chanh Phu Hoa 20 38.5% 17 40.5%

Total 52 100.0% 42 100.0%

(Source: Questionaires of Social Investigation Report of the project –2010).

Page 40: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 39

For drilled well or opened well, people often apply preliminary filtrationbefore use by sand, grave filter tank.

As mentioned above, families can combine using different water supplysources. However, rate of families who use drilled well still occupies thehighest, about 70-80%, of which the highest in Chanh Phu Hoa has 231households, occupied 53.9%, rate of hosehold use drilled well in Thoi Hoa has198 households, occupied 46.1%.

There are totally 34 households using opened well, of which number ofhousehold using opened well water for eating, drinking is 34 households andnumber of households using this water source for bathing and washing is 82households. The highest rate of households using opened well water in ChanhPhu Hoa occupied about 70.6%.

The survey result showed that there are still 5 households using waterfrom pond/river for bathing and washing. This is very polluted water source.Though local people are good aware of risk of diseas if using this water, but theyare lack of clear water source and continue using at present time.

The survey result of households in studied area under this project showedthat 52 households have tap water, it implied that tap water system is availablein this region, at present about 105 of households living in Thoi Hoa communesare supplied with clear water. Among families using tap water, number ofhouseholds in Thoi Hoa occupied a large number, about 60-70%

d. Health situation and health care of people

Usual diseases are influenza, headache, diarrhoea and allergy and skindiseases. These diseases are being catched by the poor and fair income familiesin communes, besides, other diseases as parasistic worms, stomach ache,hepatitis type A, amebic dysentery. Other water related diseases as: diarrhoea,parasistic worm, itching, gynaecology, which are caused by unensured sanitationconditions in the region, water sources being used by local people are polluted.

Ideas of families is summarised in the following table .

Table 5.5: water and environment sanitation related diseases

Types of diseases Number of HH Rate (%)

Influenza 225 43.2

Headache 204 39.2

Diarrhoea 328 63.0

Amebic dysentery 104 20.0

Page 41: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 40

Types of diseases Number of HH Rate (%)

Sore eyes 104 20.0

Cholera 92 17.5

Allergy 108 20.7

Gynaecology 87 16.7

Parasistic worms 52 10.0

Hepatitis type A 78 15.0

Stomach problems 282 54.2

Skin problems 205 39.4

(Source: Questionaires of Social Investigation Report of the project –2010).

Diarrhoea, allergy and skin diseases are the most related and affected byenvironment and water source. Rate of evaluated households related to watersource and environment sanitation of these three diseases is 63.0%, 20.7% and39,4% accordingly.

Table 5.6: Community awareness on disease causes.

Causes Number ofHh

Rate (%)

Dank house 58 11.1

Fly, mosquito fromwaste/disintergrated droppings

323 62.1

Flooded/muddy road 124 23.8

Noise/dust from factories 156 30.0

Polluted water sources 436 83.8

(Source: Questionaires of Social Investigation Report of the project –2010).

Talking about cause of these diseases, there is 83,8% opinion claimed itfor polluted water, 62.1% by environment, fly, mosquito from rubbish not yet

Page 42: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 41

collected and treated. Thus, water source pollution and unensured environmentsanitation are main causes for related diseases.

(3) Cultural assets in project areaPeople’s Committee of Tan Uyen district, Ben Cat district and Thu Dau Mottown confirmed that there is no cultural assets and sensitive areas properlyinfluenced by this subproject.

Page 43: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 42

5.2 ENVIRONMENT QUALITY SITUATION IN PROJECT

5.2.1 Air quality situation

According to analysis result of air quality in project area showed that it meetquality for air in ambient environment as standard QCVN 05:2009/BTNMT vàQCVN 06:2009/BTNMT of Ministry of natural Resources and Environment.

Table 5.7: Result of air quality measurement in residential area hamlet 6 – My Phuoc 3industrial park

Result

No Norm/Unit Position1

Position 2 Position 3Standard

05:2009/BTNMT

1 Identify dust content (µg/m3)(*) 29 19 19 300

2 Identify CO content (µg/m3)(*) 99 71 56 30.000

3 Identify SO2 content (µg/m3)(*) 29 27 17 350

4 Identify NO2 content (µg/m3)(*) 12 10 10 200

5 Identify temperature (0C) (*) 33 33 33 -

6 Identify moisture (%) (*) 65 67 67 -

Note: (*) recognised by standard ISO/IEC 17025Position1: crossroad of NE2 and DE1; Position 2: Kindergarten and park area;Position 3: near land lot H3 on road NA7

5.2.2 Surface water situation in project area

Binh Duong Water Supply Sewerage Environment Co., Ltd coordinated withNatural Resource and Environment Monitoring Center to take sample of surface waterfrom different points in Dong Nai river as follows:

Position 1: upstream of Dong Nai river, 500m far from intake point (closed to riverbank, near the pumping station)

Position 2: upstream of Dong Nai river, 500m far from intake point (in the middle ofriver)

Position 3: upstream of Dong Nai river, 500m far from intake point (closed to riverbank, opposite to the pumping station )

Position 4: at the intake point, 5m from pumping sewer

Position5: at the intake point, in the middle of the river

Position 6: downstream of Dong Nai river, 500m far from intake point (closed to river

Page 44: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 43

bank near the pumping station)

Position7: downstream of Dong Nai river, 500m far from intake point (in the middle ofriver)

Position 8: at intake point, near river bank, opposite to pumping station

Position 9: downstream of Dong Nai river, 500m far from intake point (closed to riverbank, opposite to the pumping station)

Table 5.8: Analysis result of water quality in Dong Nai river

Page 45: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 44

ResultNo Norm/Unit

Testmethod/measurement

equipmentPosition1 Position2 Position3 Position4 Position5 Position6 Position7 Position8 Position9

Standard

08:2008/

BTNMT(A2)

1 Identify Ph (*) TCVN 6492-99 7,2 7,2 6,5 6,2 6,3 6,1 7,5 7,6 7,7 6-8,5

2Dissolvedoxygen (DO)(mg/L)

Machine TOA 22A 5,21 5,18 5,20 5,21 5,32 5,29 5,18 5,46 5,28 ≥5

3Nitrate (NO3 –N) (mg/L) (*)

HACH 8171 – 98 0,6 0,6 0,3 0,3 0,3 0,2 0,3 0,5 0,5 5

4Nitrite (NO2 –N) (mg/L) (*)

HACH 8507 – 98 0,008 0,009 0,010 0,009 0,007 0,006 0,009 0,008 0,007 0,02

5Suspendid solid(SS) (mg/L) (*)

APHA-2540-(D)-95 67 68 65 70 72 71 68 76 74 30

6

Chemicaloxygen demand(COD) (mg/L)(*)

HACH 8000 – 98 11 6 8 8 6 7 8 6 6 15

7

Bio-Oxygendemand after 5days (BOD5)(mg/L) (*)

TCVN 6001 – 95 5 3 4 4 3 3 4 3 3 6

8Total iron(Total Fe)(mg/L) (*)

HACH 8008-98 1,72 1,63 1,49 1,74 1,69 1,76 1,83 1,53 1,48 1

9 (Cl-)(mg/L) (*) APHA-4500-Cl-(B)95 91,18 91,25 82,31 81,89 81,54 81,18 94,72 123,79 123,37 400

10(NH4

+)(based on N)

HACH 8038-98 0,69 0,68 0,67 0,67 0,70 0,68 0,71 0,61 0,58 0,2

Page 46: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 45

(mg/L) (*)

11(PO4

3-)(mg/L) (*)

HACH 8048-98 0,78 1,74 1,14 0,94 0,87 0,91 1,10 0,36 0,35 0,2

12Coliform(MPN/100mL)

TCVN 6187-1-96 300 1.900 2.000 1.100 900 1.200 300 900 800 5.000

13Asenic (As)(mg/L)

TCVN 6626-2008 KPH KPH KPH KHP KPH KPH KPH KPH KPH 0,02

14 Lipid (mg/L) TCVN 7875-2008 KPH KPH KPH KPH KPH KPH KPH KPH KPH 0,02

15

Surfaceactivatedsubstances(mg/L)

HACH 8028 -98 0,101 0,094 0,0099 0,098 0,098 0,097 0,089 0,079 0,079 0,2

Page 47: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 46

Remarks: all the analysed norms are in compliance with the Vietnamese standardQCVN 08:2008/BTNMT. Except for SS, which exceeds the standard from 2.17 to 2.53times, total Fe which exceed the standard from 1.48 to 1.83 times; NH4

+ which exceedthe standard from 2.9 to 3.55 times; PO4

3- which exceed the standard from 1,75 to 8,7times. However, raw water shall be treated in the water treatment plant beforepumping into transmission network in My Phuoc urban and industrial park.

Page 48: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 47

5.2.3 Sludge quality from treatment plant

Based on analysis result of sludge from Tan Hiep water treatment plant withsimilar treatment process of raw water, the analysis showed that heavy metal insludge is very low compared to the standard QCVN 03:2008/BTNMT. Analysisresult from Tan Hiep water treatmenr plant as follows:

Table 5.9: Analysis result of sludge from Tan Hiep water treatment plant

No Norm Unit ResultStandard QCVN03:2008/BTNMT

1As mg/kg KPH <12

2Pb mg/kg 1.8 <300

3Cd mg/kg 1.3 <10

4Cu mg/kg 4 <100

5Zn mg/kg 5 <300

Note:

- Result valid only on testing sample

- KPH: not found

Page 49: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 48

6. ENVIRONMENTAL IMPACTS AND RELEVANT MEASURES OFITS MITIGATION

According to the Environmental Protection Law No. 52/2005/QH11andDecree No. 21/2008/ND-CP, My Phuoc urban and industrial park water supplyproject classified as a project that does not require report of environmentalimpact assessment. Based on the Law and the Decree, a commitment toenvironmental protection is required. The structure of the commitment must becompliant with the guidance of Circular No. 05/2008/TTBTNMT issued by theMinistry of Natural Resources and Environment dated December 8, 2008. Ingeneral, most of the impacts arising from the construction project is active. Asstated in the content of cultural property in Section 5.1.2, the scope of theproject does not affect the work of religious beliefs, sensitive areas and none ofthe house, cultural works need to be dismantled and relocated, so there is noimpacts on the cultural facilities, sensitive areas. The scale of the project is notlarge, short construction period of about three years, some activities such asexcavation, installation of piping, material and waste transportation ... areconsidered just cause local, short and temporary impacts, and they can bemitigated. Overall impact assessment of the project is in Table 6.1

Page 50: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 49

Table 6.1: Overall Assessment Matrix of Project Environmental Impacts

Project

activitiesImpacts Impacted Objects

ImpactCharacteristi

cs

Scopeof

Impacts

Level of Impacts Measures of Mitigation

I. Phase 1. Basic Construction

1. Levelling,construction

- Society-Economy- Landscape

Certain, short-term

Narrow- Weak- Average

2. Transportationof Constructionmaterials, plants,equipment…

- Transportation- Soil environment- Atmosphereenvironment

Mobile,short-term

Broad- Strong- Weak- Average

3. Excavationand levelling ofsand, soil

- Construction

solid wastes,

domestic solid

wastes…

- Dusts,

hazarous

exhaust fumes

(CO, NOx,

SOx,…)

- Noise,

vibration

- Society-Economy- Occupational Safety- Atmosphereenvironment- Water environment- Landscape

Certain, short-term

Broad

- Weak- Average- Weak- Weak- Strong

- Construction of rolling, a reasonableschedule of construction, clean up wherecompletion.

- Watering to extinguish dust, usingvehicles with low fuel emission,selecting reasonable construction times.

- Construction of temporary toilets,advanced septic system, collectrainwater into a temporary trenchsystem.

- Re-creation of landscape by: plantingtrees.

Page 51: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 50

4. Constructionof basic andtemporaryworks...

- Domestic

wastewater

- Lubricants,

chemicals...

- Society-Economy- Occupational Safety- Public health- Atmosphereenvironment- Water environment- Landscape- Transportation- Soil environment

Certain, short-term

Narrow

- Weak- Average- Average- Average- Weak- Average- Average- Weak

- To ensure safety during construction

II. Phase 2. The project is put into operation1. Supplydomestic wateron pipelines

2. Operation oftanks

(Almost no impacts)

3. Activities ofstaff

- Noise,

- Domestic

wastewater;

- Hazarouswastes:Lubricants,chemicals;....

- Atmosphereenvironment- Water environment- Soil environment- Public oder &security

Certain, long-term

Narrow Insignificant

- Collect and process in compliance withhygiene regulations ...- Plant trees, ensure safe isolationdistance of residential areas ...- Construction of temporary toilets,advanced septic system, wastewatertreatment system and collect rainwaterinto a temporary trench system…

Page 52: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 51

6.1 Useful Impacts of the project

In 2009, water supply capacity for the MP3 area was 9.000m3/day (MP3-1 andMP3-2), with the above growth rate, so far the system has operated at fullcapacity. Water supply of the industrial park accounted for about 96% of watersold, the percentage of households in the MP3 which supplied water was only3%. Approximately 97% of the remaining households had to use other watersources of poor quality and unsafe. When My Phuoc urban and industrial parkwater supply project is put into operation, the rate of households water supplymust be at least 90% in MP3 with the population using clean water expected toreach is 90,000 people in 2015 and 122,000 people by 2020 with a standard ofwater supply is 120 liters / person / day&night.

6.2 Environmental impacts and mitigation measures during construction ofwater treatment stations

6.2.1 Impacts and mitigation measures due to land requisitioning

The treatment plant using land reserved for development of Tan Hiep WaterPlant (Tan Hiep WTP) which has completed clearance works and has beenissued Land Using Entitlement Certification No. BA 179271 by Department ofNatural Resources and Environment, so there is no cases of relocation,resettlement.

6.2.2 Impacts and Mitigation Measures due to plant demolishment

The land area of treatment plant was leveled by BIWASE in the project ofTan Hiep water treatment plant. According to surveys at the actual constructionarea of water treatment station, now the project area is mainly a weed growthlayer covering the area, a tree and three Lele brushwood. If we do not proceed toclean the surface thoroughly before leveling, the remaining biomass shall bedisintegrated causing soil and groundwater pollution.

To mitigate the negative impacts caused by the demolishment of biomass onsoil and groundwater, the following measures shall be implemented:

All biomass at the treatment plant area must be completely removed.

Removal biomass shall be collected and processed by the local urbanenvironment company.

6.2.3 Impacts and mitigation measures due to flooding and subsidence

The treatment station located in the reserved land of Tan Hiep WaterTreatment Plant so its rainwater drainage infrastructure has been complete.

Page 53: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 52

Water arising from the project construction shall be completely drained, there istherefore no flooding and subsidence.

In general, the construction area of the treatment plant built on the groundwhich is covered with a old layer of alluvium soil with relatively good loadingcapacity, it is convenient for work construction with R> 2kg/cm2. From theabove reasons the construction of treatment station can not cause subsidence tothe surrounding works and itself.

6.2.4 Impacts of land from construction process and spread of dust andmitigation measures

As mentioned above, the treatment station shall be built on a leveled area,land from the plant construction process arisen from building water tank with10.000 m3 volume, according to design the tank located underground 2.5 m andan area of 2.500 m2, land volume excavated for building the tank is about 6.250m3, correspondent to 9063tons (average soil density is 1.45). The amount ofland shall be used partly to reinforce the construction foundation, the rest sold tounits in need of leveling.

Dust arising from the surplus land transportation in the treatment plant can beestimated as follows:

In which: E: coefficient of dust pollution (kg/ton).k: particle size; 0.5.s: amount of land on the road; 8.9%S: average speed of vehicles; 20 km/hW: weight of vehicles; 10 tonsw: number of wheels; 6 wheelsp: number of rainy days during the year (116 days)

Replace number into the formula, we have: E = 0.375 kg/ton. With thenumber of soil need to be transferred is 9063 tons, the amount of arising dust is3398kg. Dust load incurred in the day is 5.6 kg/day (construction works for 2years). This effect is moderate, unavoidable.

To minimize these impacts, BIWASE shall require constructioncontractor must comply with following measures:

In the dry season, especially when strong winds, he shall carry out thewatering works at the construction site where vehicles density is high withfrequency of 4 times per day, from 9 am to 5 pm. The company shall usewater trucks to wet the entire construction area of the treatment plant.

0,7 0,5365

(1,7)12 48 2,7 4 365

s S W w pE k

Page 54: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 53

During the land transportation, vehicles will also be covered by canvas inorder to minimize the affects of dust dropped and diffused by the wind,the distance between the land and the canvas surface is minimum 30cm.

Speed of movement in the construction are of the treatment plant isalways below 20km/hour. Land prior to shipment has to reach at least12% humidity

All vehicles must meet the prescribed standards of the National RegisterAgency on the level of technical and environmental safety for itsoperational permit during the implementation of the treatment plant.

6.2.5 Impacts due to noise during site preparation and construction andmitigation measures

The main sources of noise include transportation of vehicles andequipment/machinery operations.

Generated noise level which is away 1 m from these noise sources ispresented in Table 6.2. The noise level decreased by increasing distance and it iscalculated based on the following formula:

Lp (x) = Lp (xo) + 20 log10 (xo/x)Lp (xo): the noise level away 1 m from the source (dBA)xo = 1 mLp (x): noise level at the position needs to be calculated (dBA)x: distance from measuring point to the source (m)

Table 6.2. Maximum noise level from operations of vehicles and mechanicalconstruction equipment

The noise level away 1m from the source

No. Transportvehicles andmechanicalconstructionequipment

Approximate Average

The noiselevel away20 m fromthe source

The noiselevel away50 m fromthe source

01 Bulldozer - 93,0 67,0 59,0

02 Road roller 72,0 – 74,0 73,0 47,0 39,0

03 Machine withfront bucket

72,0 – 84,0 78,052,0 44,0

04 Tractor 77,0 – 96,0 86,5 60,5 52,5

Page 55: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 54

The noise level away 1m from the source

No. Transportvehicles andmechanicalconstructionequipment

Approximate Average

The noiselevel away20 m fromthe source

The noiselevel away50 m fromthe source

05 Earth scraper 80,0 – 93,0 86,5 60,5 52,5

06 Paving machine 87,0 – 88,5 87,7 61,7 53,7

07 Trucks 82,0 – 94,0 88,0 62,0 54,0

08 Concrete mixer 75,0 – 88,0 81,5 55,5 47,5

09 Mobile crane 76,0 – 87,0 81,5 55,5 47,5

10 Power generator 72,0 – 82,5 77,2 51,2 43,2

11 Air compressor 75,0 – 87,0 81,0 55,0 47,0

12 Pile-driver 95,0 – 06,0 100,5 74,5 66,5

TCVN 5949-1998: public and residential noises: 50-75 dBA (8-18h)

Standard of Ministry of Health: noise generated at work place: in 08 working hours is 85dBA

Source: Mackernize, 1985

Remarks: Above results indicates that maximum noise level due tooperations of vehicles and mechanical construction equipment at the positionaway 20 meters from the source is lower than the allowed limit of standardTCVN 5949-1998.

To minimize the negative impacts caused by noises in the constructionprocess of the treatment plant, all trucks and other mechanical constructionequipment must meet the prescribed standards of the National Register Agencyof the level of technical and environmental safety for operation.

6.2.6 Site Drainage

The treatment plant built on reserved land for development of Tan Hiep WTPwhich its rainwater and wastewater drainage system has been completed, soduring the treatment plant construction, all water arising from the entireconstruction process will drain off to the existing drainage system of Tan HiepWTP to ensure timely drainage of water so as not to cause flooding.

Page 56: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 55

6.2.7 Impacts on environment of surface water, ground water, land andmitigation measures

- Domestic wastes

The amount of wastes arising from activities of construction workers at the sitecan be estimated based on the maximum number of workers working at the site.Estimates of total about 100 workers working at the site, maximum wastewateris 8.0 m3/day. According to TTQTNMT's experience, if there is no measures ofmitigation, the pollution load from domestic wastewater is about 3.2 kgCOD/day (80 g COD/day/person).

Domestic solid wastes: maximum generated quantity is 15.0 kg/day (0.15kg/person/day). If there is no appropriate pollution control measures, domesticwastes will pollute the soil and groundwater environment. Particularly fordomestic wastewater, in case of building a septic tank, amount of domesticwastewater pollution can be reduced to 2 times.

To minimize negative impacts caused by domestic wastewater duringconstruction phase, the following measures shall be implemented:

o Stage of construction: installation of temporary toilets at thetreatment plant area.

o Septic tank shall be built before doing other works.

o Using toilets of Tan Hiep WTP for construction workers.

To minimize negative impacts caused by domestic wastes duringconstruction and operation, the following measures shall be implemented:

No collective kitchen at the project area.

Domestic wastes will be collected in appropriate containers and makecontracts with local urban environmental companies for collectionand treatment.

- Rainwater runoff

The turbidity of local stream water can be increased due to rainwater runoff.However, this is only a local effect only occurred in a short time. If largeamounts of soil washed down to the stream, the deposition process will beincreased and may affect the stream water quality.

6.3 Environmental impacts and mitigation measures during construction ofraw water pumping stations, booster pump stations, water transmissionmain

6.3.1 Impact and mitigation measures due to land requisition

Page 57: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 56

- Raw water pumping stations will use the covering and civil building ofthe raw water pumping stations of Tan Hiep WTP which its clearance workshave been completed and has been issued Land Using Entitlement CertificationNo. BA 179271 by Department of Natural Resources and Environment, so thereis no cases of relocation, resettlement.

- Raw water pipeline with diameter of = 1000mm parallel with the rawwater pipeline of Tan Hiep WTP with diameter = 800mm, in which:

+ The pipe runs along the technological corridor of DT 746 with a lengthof l = 9000m. DT 746 route managed by the Becamex Investment andDevelopment Centre (Becamex IDC), the route construction has been completedincluding the technical corridor clearance. Becamex IDC has allowed to use ofthe technical corridor of DT 746 for pipeline installation in Letter No. 462/CVdated 01/10/2010.

- Transmission pipeline runs through the Binh Duong Industry – Service –Urban complex, currently the technical infrastructure in the area has beencompleted. There is no need for clearance works, it is only to make anagreement with infrastructure management unit of My Phuoc Industrial Park(Becamex) on position of pipe location on the road corridor, BIWASE made acontract with Becamex on providing land and creating favorable conditionswhen installing water supply systems. Therefore, there is no relocation andresettlement.

- Booster Pumping Station use reserved land area of My Phuoc 3.2 whichthe clearance has been completed by Becamex and Becamex has handed overfor use in Letter No. 09A/HD- CTN dated 15/5/2006, so there is no clearance,relocation and resettlement and land acquisition for the Booster PumpingStation.

6.3.2. Disturbance to local residents and businesses activities

Shops and restaurants, particularly small shops or restaurants locatedfacing the street will likely be revenue losses due to no entrance, because ofnoise and dust. Generally, these businesses will hardly have opportunity toattract customers during the period of construction of this system. According tosurvey results, a total of 98 business households scattered along the DT746 shallbe affected, no households be affected in respect of land, relocation andresettlement. Among those affected, there is no ethnic minority. Therefore,report of ethnic minority development plan (EMDP) in accordance with OP 4.10policy is not be considered in this project. The presence of labor forces may alsobe a cause of social unrest, causing conflicts with local residents. Somemeasures to limit effects of obstructing the entrance to households, shops andavoid conflicts arising between workers and local residents are as follows:

- Coordinate construction works in the same area to facilitate trafficmovement and minimize impacts.

Page 58: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 57

- Make temporary walkways where necessary to avoid material,equipment transports during peak hours where possible.

- Calculate the temporary walkways before starting date and upgrade ifnecessary.

- Carry out restoration of current status as soon as possible.

- The excavation for installation of water pipes should be emphasizedand implemented in line with the ability and site conditions so that theentire pipelines will be filled back in the day and the length ofexcavating holes in an area can not exceed 100 m. Vietnam StandardTCVN 5308:1991 should be strictly complied with.

- Cash compensation for losses of income during the transition period,equivalent to the net average income of each month, at least for 3months.

- Compensation for business works, productive materials lost as a fullreplaceable cost of the works, without depreciation.

- If the business location has to be moved, provide alternative places ofbusiness which accepted by affected person, cash compensation forlost area under replaceable cost, plus transportation costs forsupporting relocation of assets, productive materials.

To avoid problems arising from the presence of the labor forces, willmake an information dissemination on proposed activities to be conducted forlocal residents as well as construction workers.

6.3.3 Impacts and mitigation measures due to construction process

(a) Raw water pumping stations use the covering and civil building of raw waterpumping station of Tan Hiep WTP. Raw water pumping stations just need toinstall pumps, technical pipelines, power supply and control equipment for watersupply project for My Phuoc urban and industrial park water supply project, sothere is no environmental impacts during construction of raw water pumpingstations.

(b) Booster pump station is intended to re-use clean water tanks of MP3-2, re-use the existing covering structure of water pumping station of MP3-2, just needto install pumps, technical pipelines, power supply and control equipment, sothere is no environmental impacts during construction of raw water pumpingstations.

(c) Impacts of the excavating period for laying the transmission pipelinesystem, will generate more dust, gas emissions and noises into the naturalenvironment:

1. Impacts of dust and gas emissions and mitigation measures

Page 59: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 58

* Impacts of dust, gas emissions and noises

– The amount of dust generated in the process of excavating ditches forarranging transmission main of raw water, building the plant, clean water main.

– Emissions such as dust, SO2, NOx, CO, THC ... arising from transportationvehicles, mechanical construction equipment.

– Dusts generated during construction of temporary surface water drainageditches, temporary housing for workers, temporary toilets, water treatmentstations.

– Heat radiation from the construction process with heating, welding fumes.

– Noises and vibration due to mechanical construction vehicles and transports.

– Odors generated from wastes, wastewater of worker activities.

Pollution caused by dusts arising from the process of excavating, leveling,surplus land transportation to arrange the water transmission pipeline system.Soil dust is only generated in the raw water and clean water pipelines. Theimpact of dust is calculated as follows:

The amount of excavated land for building pipelines is calculated accordingto construction norms:

M= D x R x C x 1,3 = 12,000m x 1,0m x 2 m x 1,3 = 31,200 m3 of soil. Inwhich:

+ D: length of pipeline+ R: width of pipeline

+ C: depth of pipeline+1.3: Excavating coefficient (according to the estimatedconstruction norm in 2006)

However, after excavating to lay pipelines, the project will re-use land forleveling, with the height of re-leveled land layer is about 1 meter from the top ofpipe to the ground surface, therefore the amount of removal soil is account for50% excavated volume. Thus, the total excavated volume is about 15.600 m3equivalent to 22.620 tons (with an average amount of sand is 1.45 ton/m3).

The amount of soil transported by 10 tons trucks, DO fuel is used. Content ofSulfur (S) in the DO is 0.5%. Based on the volume of transported soil and soil,sand need to be leveled with load of each 10 tons truck, we can determine thetotal times of vehicles in and out during leveling process is 4.524 times/months,or an average 26 times per day.

Impact of the leveling process

Coefficient of diffusion of dust pollution from leveling process can beestimated as follows:

Page 60: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 59

1,3

1,4

/ 2, 20,16

/ 2,0

UC k

M

- C: pollution coefficient (kg/ton)

- k: particle size 0.5

- U: wind speed (3.0 m/s)

- M: average moisture of material (18% for soil).

Replace numbers into the formula, we have: E = 0.0088 kg/ton. With theamount of land need to be leveled is 22.620 tons, the amount of arising dust is199kg. Dust amount incurred in the day is 1.1 kg/day

Impact of dust during transportation of surplus land.

Coefficient of dust pollution during transportation of surplus land in theproject area can be estimated as follows:

In which: E: coefficient of dust pollution (kg/ton).k: particle size; 0.5.s: amount of land on the road; 8.9%S: average speed of vehicles; 20 km/hW: weight of vehicles; 10 tonsw: number of wheels; 6 wheelsp: number of rainy days during the year (116 days)

Replace numbers into the formula: E = 0.375 kg/ton. With the amount ofshipping land is 22.620 tons, the amount of arising dust is 8482.5kg. Dustamount incurred in the day is 47.12 kg/dayImpact of transport emissions

The project will use types of 10 tons trucks using DO fuel oil with sulfur (S)content in the DO is 0.5% for transportation of excavating and leveling sand. Asassessed by the World Health Organization (WHO) for use of transport vehiclesusing DO fuel with a capacity from 3.5 to 16 tons, can estimate the totalemissions caused by excavating and leveling activities of the entire surface ofworks in the following table 6.3:

Table 6.3: Emission amount caused by vehicles during leveling.

No. Emissions Amount/1.000km

(kg)

Length oftransportation

(km)

Truckamount/day

(kg)

Totalamount

(kg/day)

0,7 0,5365

(1,7)12 48 2,7 4 365

s S W w pE k

Page 61: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 60

1 Dust 0,9 18 0,02 0,52

2 SO2 2,075S 18 0,02 0,52

3 NOx 14,4 18 0,23 5,98

4 CO 2,9 18 0,05 1,3

5 VOCs 0,8 18 0,01 0,26

Source : Coefficient of dust pollution of WHO/1993

Note: Account for the number of vehicles is 26 times/day

Besides the effects mentioned above, the increase in vehicle density in a shorttime will increase possibility of traffic accidents in the project area, causing dustand noises during transportation, affecting the people living along the route.

* Measures to minimize dust, emissions and noises

In order to control dust pollution, emissions and noises at the routes ofwhich trucks transport sand, stone and materials and at excavating routes forexecution of drainage pipelines, the company will apply the following measures:

- During the construction process, it is necessary to have specific plansand appropriate and sequential staff allocation, avoid overlappingbetween the stages of construction.

- Use of modern construction machinery, advanced methods ofconstruction, mechanical construction operations to the maximumextent to minimize dust generated from these machines.

- Suitable distribution of vehicle density transporting materials, avoidtraffic jams causing dust pollution for the region.

- Vehicles transporting construction materials, soil, cement andexcavating land must be closely covered, to avoid spillage of materialson roads and causing dust during transportation.

- Road traffic area must be watered regularly, the site must be clean,supplies sand and soil must be in order daily.

- Equipment, machinery and construction vehicles have emissionsstandards in accordance with Vietnam standards as QCVN 19:2009.

- Repair of damaged roads in time to reduce spillage of raw materials,limiting road dust swept into the air.

- Workers unloading of materials must have labor protection equipmentto limit dusts affecting their health.

Page 62: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 61

- Planning for reasonable uses of infrastructure in the area, restore thecurrent status of infrastructure after completion.

2. Impact of noise- Impacts due to noises during site preparation and construction

The main sources of noises include transportation vehicles andequipment/machinery for construction.

Generated noise level which is away 1 m from these noise sources ispresented in Table 6.4. The noise level decreased by increasing distance and it iscalculated based on the following formula:

Lp (x) = Lp (xo) + 20 log10 (xo/x)Lp (xo): the noise level away 1 m from the source (dBA)xo = 1 mLp (x): noise level at the position needs to be calculated (dBA)x: distance from measuring point to the source (m)

Table 6.4. Maximum noise level from operations of vehicles and mechanicalconstruction equipment

The noise level away 1 mfrom the source

No. Transportvehicles andmechanicalconstructionequipment

Approximate Average

Thenoiselevelaway20 mfromthe

source

Thenoiselevelaway50 mfromthe

source

01 Bulldozer - 93,0 67,0 59,0

02 Road roller 72,0 – 74,0 73,0 47,0 39,0

03 Machinewith frontbucket

72,0 – 84,0 78,0

52,0 44,0

04 Tractor 77,0 – 96,0 86,5 60,5 52,5

05 Earth scraper 80,0 – 93,0 86,5 60,5 52,5

06 Pavingmachine

87,0 – 88,5 87,761,7 53,7

Page 63: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 62

The noise level away 1 mfrom the source

No. Transportvehicles andmechanicalconstructionequipment

Approximate Average

Thenoiselevelaway20 mfromthe

source

Thenoiselevelaway50 mfromthe

source

07 Trucks 82,0 – 94,0 88,0 62,0 54,0

08 Concretemixer

75,0 – 88,0 81,555,5 47,5

09 Mobile crane 76,0 – 87,0 81,5 55,5 47,5

10 Powergenerator

72,0 – 82,5 77,251,2 43,2

11 Aircompressor

75,0 – 87,0 81,055,0 47,0

12 Pile-driver 95,0 – 06,0 100,5 74,5 66,5

TCVN 5949-1998: public and residential noises: 50-75 dBA (8-18h)

Standard of Ministry of Health: noise generated at work place: in 08working hours is 85 dBA

Source: Mackernize, 1985

Remarks: Above results indicates that maximum noise level due tooperations of vehicles and mechanical construction equipment at the positionaway 20 meters from the source is lower than the allowed limit of standardTCVN 5949-1998.

* Measures to minimize noise

To limit noise pollution to residential areas during construction of transmissionnetwork. Construction works will be conducted with the following conditions:

- Notify local people about construction plans, including the time forconstruction and project completion time.

- Construction process will be conducted during normal working hours,limiting construction on rest times of people (noon, night).

- Installation of silencers or the rubber grip, anti-vibration spring in partsof machines with large-capacity that easily cause noise.

Page 64: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 63

- Workers in the region generated more noises (drilling, cutting ...) mustbe equipped with specialized equipment to protect their ears.

(d) Impact of vibration and mitigation measures

In construction of water transmission network, environment lithosphere willtransmit vibration causing shocks to the buildings in the area.

To control the vibration from machinery and equipment, the company hasinstalled stable foundation to put machines on large and firm space. Thecompany regularly maintains equipment, machinery, lubricates parts that maycause noises and only use loading equipment and transports that ensure technicalrequirements. Time for using a machine with large vibration from 8 am to 11 amand from 2 pm to 4:30 pm is the time that less affects people's lives around theconstruction areas, to ensure local habits of residents living around.

(e) Impact on local traffic and mitigation measures

Traffic obstruction: this activity can hinder pedestrians along two roadsides thatare doing installation and construction of pipelines.

Table 6.5. Characteristics of traffic obstructing impact

No. Affected Objects Ward//Town/Commune Town/DistrictImpact

characteristics

1

Locals/Pedestrians

Uyen Hung town Tan Uyen Low,unavoidable,medium term,can becontrolled

2

Locals/Pedestrians

Khanh Binh commune Tan Uyen Low,unavoidable,medium term,can becontrolled

3

Locals/Pedestrians

Tan Hiep commune Tan Uyen Low,unavoidable,medium term,can becontrolled

4

Locals/Pedestrians

Tan Phu ward Thu Dau Mot Low,unavoidable,medium term,can be

Page 65: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 64

No. Affected Objects Ward//Town/Commune Town/DistrictImpact

characteristics

controlled

5

Locals/Pedestrians

Hoa Lan ward Thu Dau Mot Low,unavoidable,medium term,can becontrolled

6

Locals/Pedestrians

Thoi Hoa ward Ben Cat Low,unavoidable,medium term,can becontrolled

Measures to limit effects of obstructing traffic are:

- Coordinate construction works in the same area to facilitate trafficmovement and minimize impacts.

- Make temporary walkways where necessary to avoid materials andequipment transportation during peak hours where possible.

- Calculate the temporary walkways before starting date and upgrade ifnecessary.

- Carry out restoration of current status as soon as possible.

- The excavation for installation of water pipes should be emphasizedand implemented in line with the ability and site conditions so that theentire pipelines will be filled back in the day and the length ofexcavating holes in an area can not exceed 100 m. Vietnam StandardTCVN 5308:1991 should be strictly complied with.

(f) Safety

During construction process may occur environmental incidents resulted inmajor impacts and construction progress of the project. Environmental incidentsthat may occur are as follows:

Fire and explosion incidents

During construction, vehicles, machinery and equipment will be used fuelsources from petrol and DO fuel. The fuels are stored in containers and placed instorage. If workers operate machinery without proper technique, careless use of

Page 66: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 65

fire may cause fires and explosions, direct threat to lives and properties of theproject.

Incidents of foundation, work geology.

Construction process for dredging, excavating, pouring concrete, concrete pilingwill affect the soil environment, regional geology. The problems will causelandslide, rock, impacting the groundwater source and can cover and fillequipment and machinery causing damages.

Traffic accidents and occupational accidents

Traffic accidents occurred in the region due to the excavation, land filling whichwill make the road surface muddy, slippery, damages together with constructionduring the rainy season, so it easily occurs traffic accidents.

Occupational accidents caused by failure to properly operate the technicalprocess of machinery, construction, careless employees, not implement safetymeasures during the construction.

Risks of accidents can happen to workers at construction sites as well as forresidents in the project area, especially children and the elderly.

To prevent these incidents to ensure safety for workers at the site and peoplearound the project area, the company will apply the following measures:

- There are reasonable construction plans, advanced methods of constructionto ensure environmental hygiene, occupational safety.

- During construction, the Company will coordinate with constructioncontractor to require workers to comply with regulations on occupationalsafety, pay attention to problems of machinery, equipment and measures toprevent accidents.

- Build fences separating hazardous areas on the site. Install lights whereneeded at night.

- Build temporary houses for storages of materials, machinery and equipment.The storages should be arranged at locations without high sensitivity to theenvironment.

- For the storage of construction materials: cement is gathered and stored inwarehouses, sand preserved outdoor with canvas against rain and dust androcks, bricks, .. with little dust are kept outdoor, not need preserve regime.

- Limit leakage of fuels during pumping, sucking process and have collectionsystems.

- Workers will be equipped with full necessary personal clothing.

- Building collective camps for construction workers, local hygiene catering,ensure personal hygiene conditions for workers.

Page 67: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 66

- Coordinate with local police to set out rules of order and security in theregion, not gather gambling, drinking and limit other social evils.

- Set out specific regulations for workers working at construction sites that donot allow gathering for drinking, causing fights and disorder in the region. Ifanyone violates the regulation, there shall have disciplinary measures fromwarning to even sacking if it is repeated.

(g) Hygiene

During construction period in the rainy season, rainwater runoff throughsite surface rolling soil, sand, wastes especially lubricants causingenvironmental impacts of surface water in the region. Measures to limit theimpacts of rainwater runoff affecting the water environment can be carried outas follows:

– To collect and thoroughly process wastes arising from construction activities(soil, sand, cement, domestic wastes of workers ...).

– Building temporary drainage system to collect rainwater. These drainageditches shall have manholes for sediment of sand, stones, rubbish .... beforepouring into canals.

– Limit leakage of fuels during pumping, sucking process and have collectionsystems. In process of repairing machinery, lubricants must be collected withoutdropping or pour out the area surface.

– Foundation of storage areas are higher than surrounding areas.

– Taking good drainage measures, avoid water stagnant on roads, in the site(due to volume of water arising from the process of excavating road) causingroad surfaces muddy, unsanitary, traffic obstruction and causing environmentalpollution.

– Restore the current status of the environment after completion of excavation,avoid occurrence of eutrophication.

Water for construction workers at the site will be purchased fromhouseholds living near the construction site. If wastewater generated from areaswith high concentrations of workers is not treated, it easily cause environmentalimpacts to the area. Currently, the most effective measure to treat wastewater ofworkers at the site is to invest portable toilets (often used in holidays, fairs andfestivals in the city center as Ho Chi Minh, Hanoi, Da Lat ....). Such portabletoilets are very convenient because the employers do not need to take land areafor building them and can be moved during construction (where constructionshall put the toilets there). Currently, at major construction works, they usuallyapply the model of such potable toilets in their building process. The employersmay contact suppliers of such environmental equipment for uses.

Page 68: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 67

The concentration process of large numbers of workers will generate alarge amount of daily wastes, which will cause long term damages if not treated.Project owners will invest and arrange garbage containers in the region oftemporary houses for workers. The generated amount of wastes will be collecteddaily by the company (frequency of collection is one time per day) by specialvehicles and transported to the regional landfill for treatment. Apply somemeasures to disseminate and educate the community to minimize indiscriminatelittering into canals narrowing the flows, affecting drainage of the canals andcausing difficulties for later operation, maintenance.

(h) Damages to infrastructure during excavation/construction

Earthwork activities for laying sewer system will generate more sewage, sludgethat make road construction in the area deteriorated, affecting the travel of localpeople in the region.

During project construction, heavy trucks transporting raw materials for thework as well as surplus sludge from excavation process in the project area willalso make the road system in the area damaged and rapidly degraded. Besides,its movement also created a large amount of dust dropping that causes reducingbeauty of the surrounding infrastructure. However, because construction periodis relatively short (about 6 months) so this is only a temporary effect and itsimpact severity is not great. To minimize this impact, the company will applythe following measures:

– Repair damaged roads in time to reduce spillage of raw materials, limitingroad dust swept into the air.

– Planning for reasonable infrastructure use in the area, restore the currentstatus of infrastructure after work completion.

– During construction process shall have specific plans and appropriate staffallocation, sequentially, avoid overlapping between the stages of construction.

– Distribution density of the vehicle transporting the materials suitable, avoidtraffic jams for dust pollution for the region.

– Traffic roads in the area shall be watered regularly, the site must be clean,supplies soil and sand must be in order daily.

6.4. Impacts and mitigation measures during operation of the treatmentplant

(a) Risks of water pollution from related sources

Construction of water treatment plant built to take water from Dong Nai River toprovide for urban residents in the My Phuoc urban and industrial park. Theconstruction work is not large scale, mainly for residential area. Each year withstable production, the plant shall take 30.000m3/day but not alter the river flow.

Page 69: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 68

However, in 2013, when the plant is put into stable operation. According towater monitoring program in 2010 of Binh Duong province, water quality ofDong Nai river is relatively stable, good quality water, many water qualitycriteria of Dong Nai river below the permitted limits for sources of class Astandard QCVN 08:2009. The most concern is that there is no discharge sourceand canals discharging at hydrant location. But towards the upstream about200m - 500m, Dong Nai river receives water from the Đen canal, and water from Lo Ren canal which the water quality are not defined, besides Uyen Hungmarket will also impact to the water quality in the future. Also, another concernis the growth of the Nam Tan Uyen Industrial Park that will affect the waterquality of Dong Nai river. And rasing fish by rafts in the river also has a certainimpact to this issue.

However, at present, according to the province's regulations on sourcesdischarging into water environment must meet class A, so issues impacting towater quality from wastewater of Nam Tan Uyen Industrial Park, the canals arenegligible. The policy of the province has also banned fish raising by rafts in theriver so this will be thoroughly solved.

Besides, the Employer will submit Binh Duong Provincial People's Committeeto issue the surface water protection following Decision no. 628/BXD-CSXDissued by the Ministry of Construction and the Vietnam standards TCVN ISO5525 and 33-83: 1995 on the protection of water sources, within the watersource protection area will not have construction works, waste pits, grazing ...

(b) Waste sludge management

Waste sludge generated from the treatment plant

o Solid wastes are lime, alum and sludge sediments:

Lime sediment: 200 kg/day

Lime is to stabilize the pH of water. Dose of lime estimated to put intosource water is 10 mg/l, pure lime needed for a day is 300 kg/day. Used lime istrade lime of 60% pure lime, so the amount of lime to be used is 500 kg/day andthe amount of lime sediment discharged from the mix tank is respectively 200kg/day.

Alum sediment : 487 kg/day

Alum is used to flocculate sediment particles in the water source, formingthe residue cotton that can be deposited. Alum dose required is estimated 900kg/day. Alum purity is 85% when dissolved in water, goods alum required is1059 kg/day, corresponding to 1 gram of alum is 0.46 g residue Al (OH) 3 willbe deposited to the bottom of the tank together with residue in raw water andremoved to sludge drying yard. The amount of alum sediment is 487 kg/day.Alum sediment to be deposited togehter with residue in raw water at the bottomof sediment tank and periodically discharged into the grade II sludgecompressing tank.

Page 70: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 69

Sludge sediment :

From the recovered filter tank

+ Rinsing and Pumping Flow: Q = 540m3/h+ Time of water rinse: t = 8-9 minutes+ The water amount of oil refinery: 24 m2 x (1 m + 1.2 m) = 52.8 m3+ Total water amount of consecutive rinse by two filter sections after a filtrationcycle

W: (52,8 + 81) x 2 = 267,6 m3

+ Time of water saved in recovery tank for sludge sedimentation is 2 hours, timeof circulating pump of rinsing water to the flow separating tank is 4 hours(simultaneously it is required 1.5 h to pump out to the sludge drying yard)+ Total volume of filter material of 10 tank sections: 240 m3

+ Volume of empty slots containing residues of 1m3 VLL: 110 liters.+ Residue content (already dried) can be contained in 1 liter empty slot of VLLis: 20 - 50 g/l, taking the average value of 25g/l.+ Total residue amount can be retained in the VLL of each filter tank for eachcycle:

240 x 110 x 25 = 660 000 g+ Content of residue after Accelerator as calculated and as well as standarddesign will be about 10 mg/l+ With the capacity 30.000m3/day (24h) the total amount of residue retained inthe VLL

30.000m3/day x 10g/m3 = 300,000 g/day = 300 kg/day

From sludge compressing tank

Sludge compressing tank closely operated in relation to the sediment tank toprotect the sludge circulation in the sedimentation area, at the bottom of residuewater receiver (with 08 sludge discharge hydrants D = 60). Due to takingaccount of the amount of alum remaining in sludge sediment with content ofabout 5-8% of alum amount for daily use. Sludge compressing tank is chosenaccording to the solution of Elutrifient tank with two tier in order to salvagepartly recovery of surplus alum in sludge, and also to increase the activity ofsludge separating water in the sediment tank.

Sludge amount generated from sediment tank :

20 g/m3 x 30.000 m3/day&night = 600.000 g/ day&night = 600 kg/day&night

Total of sludge amount discharged daily:

300 + 600 = 900 kg/day

Sludge treatment of the plant is carried out as follows:

Page 71: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 70

Lime, alum sediment discharged from the lime mixing tank is gathered togetherfor transportation to landfills, together with sludge transportations to drying yardor sell them to areas where demand for alum treatment ponds or cover ground.As calculated above, the amount of lime sediment generated is 200kg/day, theamount of alum sediment generated in Phase 2 is 487 kg/day. Total volume ofsediment generated is 687 kg per day.

Sludge generated from the sediment tank is pumped to the sludge compressingtank. At the sludge compressing tank, alum residual amount remaining in sludgesediment and sludge separating water of the sediment tank is pumped back tothe mixing tank and sludge sediment in the compressing tank is discharged intodrying yard.

Lime, alum and sludge sediments from the compressing tank is transported andtreated in accordance with requirements by the Waste Treatment Enterpriseunder BIWASE. Thus, waste residues and sludge are collected and treatedthoroughly, not discharged directly into rivers or drainage systems, so as not toaffect the surrounding environment.

(c) Dust emissions from uncompleted areas

Inside the treatment plant area, especially in areas where are not covered withconcrete surface or asphalt, dust may be dispersed into the atmosphere duringstrong winds or transportation of chemicals and waste sludge. Therefore,planting trees or other dust mitigation measures such as regular watering onthese surfaces to reduce dust and improve the landscape of the treatment plant.

(d) Chemical safety

The Plant uses Chlorine (Hypochlorite Natri) with the need of 150kg/day (0.005kg/m3 of raw water, clean water). Currently, chlorine is supplied from Bien HoaChemical Factory in standard steel pressure sealing vessels, Chlorine extractedinto water by a device which is completely sealed, so chlorine leakage is verylow. However, the company will have measures to prevent incident of chlorineleakage as follows:

Fully equipped facilities in liquid Chlorine storage as:

- The wind top: to help determine the wind direction when incidents ofchlorine leakage occurred.

- Exhaust fan installed in the position up to 1.5 m above the ground. Becausechlorine is heavier than air, so it will be low and be exhausted, not affect theprocessing operations.

- Emergency eye-washing faucet: water is the best means to treat damagedskin and eyes caused by chlorine.

- Chlorine emergency regimen.

Page 72: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 71

- Treatment regimen when incidents chlorine leakage occurred.

- 5% ammonia Bottle helps to quickly detect where chlorine leakageoccurred.

- Facilities for dealing with chlorine leakage at the body, head, bottle valve.

- Fully equipped labor protection facilities (respirators, goggles, boots ...)

- Implement proper safety techniques in the preservation, storage and useliquid chlorine.

The transportation of chlorine vessels must be carried out by exclusivevehicles.

Always have contingency plans for all types of incidents.

The plant always has training program "transportation - storage and use ofliquid chlorine"

(e) wastewater from treatment plant

Wastewater from treatment station include following types:

Wastewater from backwashing process, washing sedimentation tank andwater from sludge drying bed

o Backwash flow with period 2,2 days having flow Q = 267,6 m3;

o Flow of wastewater from washing sedimentation tank: Q = 44 m3/h ;

o Flow of wastewater from sludge drying bed Q = 3,6 m3/h.

Component of this wastewater mianly contain sediments and residual alum insedimented sludge with content of about 5-8% over used alum amount.

Wastewater generated from this process is circulated to mixing tank for reusetogether with raw water, not letting out the environment.

Wastewater from washing lab tools, measurement equipments to dilutechemicals

Flow of about 500l/day, components of this wastewater does not containhazardous factor and not continuous that it is not remarkable, therefore, waterfrom lab room is led to common collection system with domestic wastewatergoing to local treatment system in Tan Hiep water treatment plant for treating.

Wastewater from staff

Water supply estimated for use is 100 liters/person/day. Thus, domesticwastewater amount is calculated for 10 staffs in treatment station as:

10 person x 100 liters/person/day x 80% = 800 liters/day

Page 73: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 72

This wastewater is locally treated before discharging into the environment.

To control pollution by wastewater from treatment station, the Company applyfollowing methods:

o Wastewater from water treatment process has features as muchsludge, alkali (lime dreg), acid (alum solution)…if directlydischarge in the environment, it will cause pollution. However,when calculating the design, all wastewater of this type will betreated in sludge drying bed. These sediment and dregs will besedimented down to bottom of the bed and then removed todumping place. Clear water on the surface will be circulated forfloculation process. Wastewater from filtration washing,sedimentation washing will go with separated circulation waterline back to floculation process.

o Domestic wastewater will be draftly treated by septic tank, thengoing together with wastewater from washing lab tools inhamonized pond, then to be treated in biofor tank. Wastewater islated disinfected and self absorb. Treatment process is as follows:

Figure 6.1: wastewater treatment process at treatment station

(f) Control impacts for surface water

Control influence to surface water source:

Wastewater from labtool washing

Domestic wastewaterafter septic tank

Hamonize tank

Biofor flitration tank

Disinfection tank

Self-absorb

Page 74: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 73

In dry season, surface water contain much alum, alluvium that requirepreliminary treatment by filtration membrane before going to pumping station toreduce alum, alluvium, to increase capacity of raw water transmission and watertreatment capacity.

Controlling impacts to Dong Nai river.

Advising Provincial People’s Committee to issue regulation on raw waterprotection in exploitable area, which clearly not allow any construction,agricluture activity, growing fish etc within protected area (500m from upstreamto intake point, 200m from downstream to intake point) to assure quality of riversurface water.

(g) Security for treatment station

To prevent not-functional people going into treatment area, it should build afence and install lighting system and regularly controlled. Moreover, securitystaff should be hired to take care of security for treatment station.

(h) Safety while operating the treatment station

Operation of chemical house, specially if chloride room is not strictly managed,it may cause negative impacts on air environment and health for people in caseof chloride gas leakage. During operation phase, it should strictly obeyregulations and procedures, absolutely ensure working safety. Worker whodirectly work in chloride room must be equipped with special protective clothsand tools as: face mask, glass for eyes, boot, etc. Transporting chloride bottlemust use specilised truck and often check equipments, cointaner and chemicalwarehouse.

When operating water pump and equipments, noise will be given out orvibration which properly cause direct impact on health of workers. Equipmentsto be included in this subproject must be modern and manufactured bydeveloped countries, which do not give out noise, vibration that excess thestandard. However, it should also has measures to minimize negative impacts onworkers’ health, it needs to consider measure to prevent noise, vibration duringdesign phase such as: sound reducer in pumping station, workshop, antivibration method for equipments by designing thick enough frame forequipments, install rubber gasket and anti vibration spring.

To prevent fire and exploison in the plant, it should synchrously apply technicalmethod, orgainzing training, education and legislation. About technical method,beside general methods including:

- Mechanicalise, automatic in dangerous treatment step.

- Ensure equipments, not let oil/lubricant out

- Isolate inflamable phase far from other areas

- Minimize exploisive substances in treatment area

Page 75: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 74

These matters should be carried out in accordance with instruction on firepreventing and fighting issued by Ministry of Police.

Electric equipments should be calculated having suitable electric transmissionline with circuit speed, protective equipment for overload. In high temperaturearea, electric line should be underground or have protection layer.

Equipments and machine used in treatment process of the plant should haveenogh profile documents and technical specification for checking andmonitoring.

Anti lightening system should be installed at highest point over the building

Enhacing good awareness for worker on fire prevention and fighting. Besideassistance from specialised fire fighter, the plant and raw water pumping stationarea should be equipped facilities used for fire fighting to minize damage in caseof accident.

6.5 Impacts and minimise measures for operating transmission anddistribution system(a) Maintenance related issues

When operating water transmission system, some problem may happen such aspipe burst, stuck drainage pipe make water overflow out in the environment andcause flooding. Therefore, to prevent this problem, the subproject set out somemeasures as follows:

– Uasually monitor and ensure good condition for operating the watertransmission system.

– Prepare periodic checking plan for transmission main system.

– Timely and quickly discover and solve damage.

– Carefully prepare and prepare enough for work and equipments to beoperated in peak time in a year.

– Strictly obey principles on working safety and arrange in logical way usualchecking facilities.

– Planning training, improve knowledge for technicans and increase theirresponsibilities for checking, maintaining the system periodically

(b) polluted risk from wastewater collection system

Risk of contaiminating from wastewater collection system may happen ifdistance between drainage sewer and water supply pipe not in compliance withthe standard defined in 20TCN 33-85. Such impacts may take place if whenoperating transmission main for new drainage system built by local people orlocal government, it is near the water supply line. On the other hand, illegalconnection to water supply system also pollute clear water. These impacts canbe minimised if absolutely obey regulation on safe distance as well as usual

Page 76: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 75

maintenance of water system. Moreover, constructing drainage system or othercivil work within area used for water supply network must obtain opproval bylocal authority.

6.6 Urgent measures of the subproject

During operation phase of the treatment station, if we change quality ofwater supplied, it could affect community health. This is because abnomalfactors or sudden change in raw water quaility may happen that in excess oftechnical capacity, or damage in water transmission system causing pollution ortreatment process facing some problems. When there is sudden change inchemical component of water, specially illustrated in parameters that show thepollution or contain disease virus, operator of the treatment station should findout the cause and report the problem to the project employer and Tan uyendistrict people’s committee and other related agencies for sollution.

Mistake from operation phase of treatment station should be found outtimelt and have technical sollution to deal with. This solution should be appliedby the operators of the station. In circumstance it is over the ability andresponsibility of the operators, operating the station should be stopped rightaway for overcoming measure.

To reduce negative impacts by power cut-off, standby generator will beinstalled to provide electric for pumping station and water treatment station.

Using chloride is similar to disinfection component, safety for usingchemical is very essential to health of the operator in station and communityhealth and the environment as a whole. Contacting with strong concerntrationmay poison the burn the skin, eyes, nose and mucous membrance. Chlorine maynot cause serious problem if workers are good trained on using it. Therefore, toprevent, monitor and cope with risk by chemicals, workers must strictly respectsafety instruction of the manufacture or instruction for use and maintenance. Inother side, operators in station should be trained knowledge on safety,technology, health protection, procedures to solve the problem and they areoften checked their knowledge in this field before receiving the task, to assurethat risk from chemicals for them, local community and environment should beeliminated. Following instructions is for safety when contacting with chlorine:

Provide instruction and adequately monitor operators of the treatmentstation;

Provide breathing tool for operators in area using and keeping chlorine;

Keep all breathing tools out off the chlorine area;

Prepare plan to escape the region in case of chlorine leakage. Rememberto move in upstream and wind direction;

Never keep inflammable materials near chlorine bottle;

Never boil the chlorine bottle;

Page 77: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 76

Never try to weild chlorine gas transmission pipe without before cleaningit with air;

Install water jets and eyes wash basin near to equipments contactingchlorine;

If leakage, at least two person work with repair;

Never watering on chlorine bottle that have leakage, this action will makethe situation worse;

When entering working area that contain chlorine, hollow breath until youare sure that there is no chlorine leakage;

Using equipments to make up clhorine to directly put out chlorine gas;and

Tighly kkep chlorine bottle by chain, matress or axis.

Beside, to control and deal with urgent situation, following measures shall beimplemented:

Build and carry out action plan to cope with urgent situation.

Ensure water is always available for use if problem happen;

Not allow worker to smoke in working area

Equipments for fire fighting must be often checked

Periodic check for electric system to prevent fire. The electric systemshould be installed in safe distance and divided in many sections to makegood conditions for periodic check.

Train workers on instruction, safety measure for electric; glooves,protective cloths for electricians,

Page 78: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 77

7. ENVIRONMENT MANAGEMENT PROGRAM

7.1 Environment management program under the project

Environment management program – EMP- is necessary for

environmental limitation management in which some environmental changes

shall be forecasted and some preventing as well as minimizing methods shall be

made to deal with environmental changes. The EMP consists of reducing

program to the environment, program to follow reducing measures to the

environment, report requirements, organization structure to implement the EMP

and plan to urgently deal with some problems may happen. Target of the EMP

under projects is to provide instructions so that each project is assured about

environment with criterion as follows :

To be compliance with the current Vietnamese environment laws.

To organize environmental protection task to ensure in carrying

reducing measures in each stage under the project .

To manage and monitor reducing measures proposed in the EIA

prepared by the contractor .

To provide reservation plan for urgent first aid methods for accidents,

environment problem happening .

To manage environmental protection issues during implementing period of

works items under the project and time after taking the works into use, the investor

shall prepare an environmental management program including the following

content :

1/ Request construction contractor to carry out reducing measures to the

environment, life of people in the project area and workers directly executing,

which is considered as an obligatory article stated in the contract with the

contractor.

2/ Hire consultant to supervise on environmental protection to assure on

carrying out the following content :

Carrying out the environmental monitoring program;

Make survey, collect basic data to prepare assessment report on

effectiveness of reducing measures, adjustment, updating reducing

methods shall be made if necessary, in oder that environmental

protection under the project gets high effectiveness and feasibility ;

Carrying out and effectivness of reducing measures to the

environment from the project.

Page 79: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 78

The environment management program proposed as follows:

Page 80: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 79

Table 7.1. Environment management program

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

1 Preparation stage

1.1 - Compensation plan,

supporting and

resettlement for

effected households

- Eco-social impacts to

households permanently or

temporary effected inside

or surrounding project area

.

- Completed due to use of Tan

Hiep and My Phuoc 3-2

WTP’s layout which were

already finished site clearance

and these projects have been

taken into use.

- Investor; Under Tan

Hiep and My

Phuoc 3-2

WTP,

completed

1.2 - Collect, gather and

transfer and treat

vegetation cover on

land .

- Impacts to ecosystem of

the project area and

surrounding places;

- Air environment ;

- Land environment ;

- Water environment;

- Workers, engineers

directly implementing .

- Make public disclosure on

progress and implementation

period.

- Collected, gathered,

transferred and treated in

compliance with regulations

on discharging by the Waste

Treatment Enterprise under

Binh Duong Water Supply

Sewerage Environment Co.,

Ltd ;

- Investor;

- Contractor ;

- the Waste

Treatment

Enterprise under

Binh Duong

Water Supply

Sewerage

Environment

Co., Ltd ;

Construction

cost

2 Construction stage

Page 81: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 80

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

2a Impacts relating to waste- implementing period

2.1 Build works items under

the project :

- Digging, leveling

construction area of

works items under the

project .

- Intake works –pumping

station Q=30,000m3/h

- Raw water mains .

- Treating station,

capacity of

30,000m3/day.

- Treated water pumping

station, capacity of

700m3/h

- Network of

transmission,

distribution and service

- Household connections

Make temporary works

* Air environment

- Exhaust fumes, dust from

construction activities and

means of transportation;

- Exhaust fumes, dust from

digging, leveling,

transporting construction

materials ;

- Dust from street surface ;

- Impacts from noise,

vibration of equipments

used for implementing,

transferring and

constructing ;

- Transporting means,

machinery, equipments must

be periodically checked,

maintained .

- Ensuring in investing a tank

serving for street watering at

site works, especially during

dry period .

- Use special vehicles and fully

covered with canvas when

moving in or out the

construction area.

- The construction area should

be covered with canvas to

minimize to discharge dust into

air and surrounding areas .

- Implementation shall be made

in scrolling type, finish each

stage;

- There is a program to control

- Contractor;

- Investor;

Construction

cost

Construction

Page 82: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 81

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

vehicles moving in and out in a

reasonable way;

- The project do not have

transporting activities

construction materials in

residential area during break

time (in the evening and early

morning , from 06:00PM of

previous day to 07:00 AM of

next day and in the afternoon,

from 11:30 AM to 01:30PM).

cost

2.2

for workers

Transferring of soil,

stone, machinery,

equipment, construction

materials

* Water environment

- Waste water from

implementing activities

and waste water from

activities of workers .

- Over flow water rain ;

- Waste water from on-site

construction activities ;

- Install a mobile sanitary room

with septic tank complying

with permitted standards at the

construction site before being

disposed into local sewerage

system .

- Contractor assigns sanitary

workers in charge of

collecting domestic waste to

waste bin and then being

taking to the local waste

- Contractor;

- Investor; ;

Construction

cost

Page 83: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 82

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

treatment area 1-2times /week

;

- For overflow water rain: It is

necessary to have channel,

ditch for temporary sewerage

in the area.

- Reducing measures due to

gathering workers : equip

workers with entertainment

equipments: television, radio,

newspaper, hold some

together activities for workers,

issue site regulations, not

allow to gather for drinking

alcohol, beer, play cards. . .

and give reward or penalty

based on the site regulations. .

Page 84: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 83

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

2.3 * Impact of solid waste(SW)

– and hazardous solid waste

(HSW)

- Domestic SW, plan cut

down during site clearance

period

- HSW from lubricant to

operate machinery

- Waste from dredging mud

in old Dong May reservoir

;

- All type of normal SW (soil,

stone, construction materials, .

.. .) shall be collected to fill in

the lower area for leveling

layout .

- The remaining SW shall be

collected , transported and

treated by the Waste

Treatment Enterprise under

Binh Duong Water Supply

Sewerage Environment Co.,

Ltd;

- Contractor;

- Investor; ;

the Waste

Treatment

Enterprise under

Binh Duong

Water Supply

Sewerage

Environment Co.,

Ltd;

Construction

cost

2b Impacts not related to waste- construction period

2.4 Build works items under

the project :

- Digging, filling,

leveling layout in the

area of the project’s

works items .

- Intake works – raw

- Impacts caused by

gathering workers that may

create social evils

- Periodically carry out

monitoring environment: land,

clean water, waste water, air,

solid waste during

implementing period.

- Contractor;

- Investor ;

Construction

cost

Page 85: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 84

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

2.5 - Impacts on transportation :

obstruct on traffic due to

use a part of area for

gathering materials and

implementing; increase

density of traffic in

implementing roads.

- Gathering materials,

machinery for implementation

at right and appropriate

positions ;

- Limit to transgress bed roads,

carry out fully completion in

implementing, recover layout

when finishing ;

- Cooperate with local to

control traffic .

- Employer;

- local authority

Construction

cost

2.6

water pumping station

Q=750m3/h

- Raw water mains .

- Treatment station with

capacity of

30,000m3/day.

- Treated pumping

station with capacity of

750m3/h

Networks of

transmission, distribution

and service \

- Household connections

Make temporary works

for construction workers

Build power supply

system

Activities of

transportation, land,

stone, machinery,

- Eco-social life - Place sign board, light . . . at

the site works ;

- Disposal at permitted place

and being periodically

collected ;

- It is necessary to give strict

regulations for implementing

Contractor ;

- Consultancy of the

community’s comments .

- Investor;

- Contractor

Construction

cost

Page 86: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 85

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

2.7 - Scenery - Gathering, transferring

materials to permitted place ;

- Carry out rolling

implementation ;

- Use tale, wood or tree fence ;

- Regularly educate for workers

on awareness of

environmental protection. .

2.8

construction materials

- Labour safety and

preventing problems- Training on operating,

maintaining machinery,

equipments for workers \;

- Equip devices, labour safety

clothes ;

- Regularly monitoring,

checking machines,

equipments ;

- Training workers to be

friendly with first aid when

problem occurring .

- Investor;

- Contractor

Construction

cost

Page 87: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 86

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

2.9 - Stucking pipe, cable,

network- Cooperate with suppliers in

the implementing area;

- Investor;

- Related units .

Construction

cost

2.10 - Stucking and risk of traffic

accident- Class traffic on roads under

implementation with an

appropriate way ;

- Place sign board and light at

implemented area ;

- Prior inform about progress

and time to implement .

- Investor ;

- Local

authorities ;

Construction

cost

3 Water supply system operation stage

3a Impacts related to waste –operation stage

3.1 * Air environment

- Noise, vibration, dust from

activities of plant, means

for operation ;

- Odor from burnt material

and chemical warehouse ;

- Means of transportation,

machines, equipments used

need to be periodically

checked .

- It is necessary to cover by

canvas during time of disposed

mud transportation ;

Investor; Construction

cost

3.2

- Operate system of the

treatment plant ;

- Provide water in

distribution and service

network ;

* Solid waste Investor; Construction

Page 88: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 87

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

- Disposed sludge during

time treating water at

sludge sedimentation tank ;

- Solid waste arising –waste

disposed by workers’ daily

activities .

- Collecting in sludge

sedimenting tank and

periodically collected ;

- Domestic solid waste collected

and treated at public sanitary

area in the water treatment

plant .

cost

3.3 * Water environment

- Domestic waste water

from workers operating the

plant .

- Over flow water rain ;

- Washing water from

treatment system ;

- Water from laboratory

- It is necessary to build a public

sanitary area with septic tank

to ensure waste water to be

treated before being discharged

into the environment ;

- There is collecting, drainage

system in the water treatment

plant ;

- Water after washing pipe and

filter to be taken to sludge

sedimentation tank, outlet

waste water in compliance

with permitted discharging

standard (TSS<100mg/l).

Investor; Construction

cost

Page 89: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 88

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

- Waste water from laboratory,

domestic waste water from

septic tank to be collected to

treatment system of the

treatment for treatment in

accordant to standard QCVN

24:2009/BTNMT;

3b Impacts not related to waste –operation stage

3.4 - Operate system of

treatment plant ;

- Provide water in

distribution and service

network ;

Safety and fire, exploding

preventing

- There is medical room, fire

preventing system, sufficiently

equip workers with safe labour

clothes, devices, regularly

organize training course for

staff to deal with fire

preventing when happening

fire, exploding and first aid

when a labour accident

happens .

- Prepare regulations, rules, . . .

.for activities in the plant and

give appropriate reward or

penalty .

- Investor;

- Staff, officer,

engineer

operating the

treatment plant ;

Page 90: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 89

No. Project activitiesNegative impacts to

environment

The reducing measures to

environmentImplementer Cost

- Periodically permit staff and

officer to have their health

checked (every 06 months ).

3.6 - Leaking chemical and

breaking pipe joining

works

- Periodically check in chemical

and joining pipes ;

- Having detailed regulations on

chemical containing area and

regularly to be checked .

- Investor;

3.7 - Partial flooded - Designing collecting, drainage

system at the treatment plant

area .

- Investor;

Page 91: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 90

7.2 Requirement on reporting and monitoring

The environment monitoring program describe monitoring activities toassure negative impacts could be reduced and the environment management planto be implemented. The environment monitoring program includes monitoringparameters chosen to show the level of environment impacts. It also describeshow to do, when and where the monitoring activities are carried out, who will doand who to receive the monitoring report. More important, it also coversproposal to carry out monitoring activities in compliance with the environment.As in Article 14 of Decree 80/2006/NĐ-CP dated August 09th, 2006, BIWASE-the project employer will be responsible for the environment monitoringprogram in line with what have been stated in the approved environmentprotection commitment. In the circular 05/2008/TTBTNMT dated December12th 2008 of MONRE and decision No. 68/2008/QĐ-UBND dated December 12th 2008 of Bin Duong people’s committee, the environment monitoringprogram will include: (I) monitor waste, (ii) monitor the surroundingenvironment and (iii) other monitoring, specifically :

Monitor the waste require to clearly identify volume of waste generated inone day and pollutant in the waste according to the standard and existingregulations of Vietnam, at frequency al least every 3 months

Monitor the surrounding environment requires to monitor pollutedparameters according to the standard and existing regulations of Vietnam, atfrequency al least every 3 months

Other monitoring requires to monitor symptoms as erosion, landslide, withsuitable monitoring frequency to see their change according to time andenvironment. The project’s environment monitoring program is as follows:

7.3 Supervision program

(1) Supervise contractor

PMU will supervise construction work of the contractors, ensuring thatthey carry out the mitigation measures for environment impacts in theenvironment impact assessment report of the project. If any contractor fails tocomply with, he will be reminded and set up minutes, if he violate more thantwo times, his contract will be terminated.

(2) Supervise environment quality

Construction phase

The company shall coordinate with professional organization to periodicallymonitor the environment during construction phase of the project. The companywill report to WB, Tan Uyen people’s committe. Supervision program inconstruction phase as follows:

Page 92: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 91

(1). Monitoring quality of air and noise

– Selected parameters : dust SO2, NOx, CO, NH3, H2S, noise, vibration

– Monitoring position: raw water transmission main; position to be changeddepending on construction progress

– Requency: every 3 months .

Collective tools and analysis method: as standard .

– Compared standard : standard on Vietnamese environment (QCVN 05-2009.QCVN 06-2009, TCVN 5949 – 1998 and other standards of Ministry of Health).

– Time for measuring noise and vibration is during 1 day

(2). Monitoring surface water quality

– Selected parameters : pH, EC, turbidity, DO, COD, BOD5, SS, totalN, NH4

+, NO2-, NO3

- , total P, total coliform.

– Monitoring position: raw water transmission main; 03 point/basin

– Requency: every 3 months .

Collective tools and analysis method: as standard .

Compared standard: QCVN 08-2009.

(3). Monitoring solid waste management status

– Monitoring position: construction site of the project

– Diary for solid waste management (collection, transport and treatment) iscomplied with the regulation and is kept carefully, periodically reported to localenvironmental management organization.

(4)monitoring erosion protection

– To see whether there is any measure to control erosion in the right positionand right fuction as mentioned above.

– No standard

– Frequency: 01 time/month

Operational phase

Page 93: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 92

In the operational phase of the project, the project employer shallcoordinate with professional agency on environmental management to monitorquality of the environment within the project area, provide information for WB,DONRE in Tan Uyen district, Binh Duong province and contribute toenvironment management for the district.

(1) Supervise working environment

- Monitoring parameters: Dust, SO2, CO, NO2, noise, temperature, moisture, chlorine gas (at WTP)

- Monitoring position: 01 point at raw water pumping station, 2 points atWTP and 01 point at booster station

- Monitoring frequency: every 3 months

- Compared standard: Sanitary labour standard attached in Decision No.3733/2002/QĐ-BYT issued by Ministry of Health.

(2) Supervise surrounding air environment

- Monitoring parameters: Dust, SO2, CO, NO2, noise, temperature,moisture

- Monitoring position: 01 point at the security house’s entrance

- Monitoring frequency: every 3 months

Compared standard: QCVN 05:2009/BTNMT

(3) Supervise quality of supplied water

- Monitoring parameters: pH, DO, TSS, COD, BOD5, NH4+, hardness,

NO2-,PO43-, As, Cd, Pb, Cu, Zn, Ni, Fe, Cr3+, surface activated

substance, vegetable protection chemical, organic Clod, Coliform.

- Monitoring position: 01 point before the raw water PS and 01 pointafter the WTP.

- Monitoring frequency: after each working shift of the WTP and rawwater PS.

- Compared standard: QCVN 08:2008/BTNMT, QCVN 02/2009/BYTand

QCVN 01/2009/BYT.

(4) Supervise wastewater:

- Monitoring parameters: pH, COD, BOD5, SS, Coliform.

- Monitoring position: after local water treatment system in WTP, gas

Page 94: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 93

chamber for connection of the booster station and waste water collectionsystem in My Phuoc 3 industrial park.

- Monitoring frequency: every 03 months

- Compared standard: QCVN 24:2009/BTNMT.

(5) Supervise underground water

Monitoring parameters: pH, Sulphat, Fe, Mangan, lead, Clo, Coliformand Faecal Coliform.

- Monitoring position: drilled well in raw water PS .

- Monitoring frequency: every 03 months

- Compared standard: QCVN 09:2008/BTNMT.

(6) Supervise sludge from WTP

- Monitoring parameters: sludge amount from treatment station.

- Monitoring position: sludge drying bed in treatment plant .

- Monitoring frequency: every 03 months

Mentioned above data shall be regularly updated, evaluated and recordedthe result. The project will inform immediately for the local authority forsuitable solving measures.

Drawing of monitoring position is in Appendix…..

(3) Cost estimate for environment monitoring program

Cost estimate for environment monitoring program is prepared based onCircular 83/2002/TTBTC issued by Ministry of Finance on September 25th,2002 and Circular 15/2005/TTLT-BTC-BTNMT issued by MONRE onFebruary 22th 2005. Cost estimate for environment monitoring program ispresented in table 7.2

Page 95: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 94

Table 7.2: Cost estimate for environment supervision in construction phase

No Measurement index Unit price (VND)Number of

samples/year

Totalamount(VND)

I. Air quality 9600000

1 Total dust 50000 20 1000000

2 SO2 60000 20 1200000

3 NO2 60000 20 1200000

4 CO 60000 20 1200000

6 Noise 100000 20 400000

7 Vibration 300000 20 1200000

8 H2S 60000 20 1200000

9 NH3 60000 20 1200000

10 Sample taking labor 50000 20 1000000

II. Supervise surface water quality 9200000

1 pH 15000 12 60000

2 COD 70000 12 280000

3 BOD5 60000 12 240000

4 SS 35000 12 140000

5 EC 35000 12 240000

6 Turbidity 35000 12 240000

7 DO 35000 12 400000

9 Mineral oil 100000 12 400000

10 NH4- 60000 12 720000

11 Flo 100000 12 1200000

12 Fe 100000 12 1200000

13 Mangan 100000 12 1200000

14 Nitrat 100000 12 1200000

Page 96: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 95

15 Nitrit 100000 12 1200000

16 Coliform 60000 12 240000

17 Sample taking labor 20000đ/sample 12 240000

III. Supervise erosion protection 500000 12 6000000

IV. Vehicle cost to take sample andkeeping sample

800.000đ/trip 4 3200000

V. Other cost

1 Reporting 1.000.000 đ/time 4 4000000

2 Office supplies 200.000 đ/time 4 800000

Total: Twenty six million eight hundred thousand dong 26800000

Funding source to carry out the environment supervision during construction isfrom the project cost .

Table 7.3: Cost estimate for environment supervision during operation

I. Air in working environment and in surrounding

No Index

Unit price(thousand dong)

Quantity Total amount(thousanddong)

1 Temperature

2 Moisture 50 7 350

3 Dust 100 7 700

4 Noise 50 7 350

5 CO 250 7 1750

6 SO2 250 7 1750

7 NO2 250 7 1750

8 Chlorine gas 150 2 300

Total 6.600

II.Supervise water supply quality

No Index Unit price Quantity Total amount

1 pH 30 02 60

2 DO 60 02 120

3 Hardness 50 02 100

4 COD 80 02 160

5 BOD 80 02 160

6 SS 50 02 100

Page 97: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 96

7 N-NH4 60 02 120

8 Nitrit 60 02 120

9 Total P 80 02 160

10 Cd 120 02 240

11 As 120 02 240

12 Surface activated substance 120 02 240

13 Cr 150 02 300

14 Pb 120 02 240

15 Cu 60 02 120

16 Fe 60 02 120

17 Ni 150 02 300

18 Zn 60 02 120

19 Plantation protection chemicals 1200 02 2400

20 Organic clo 1200 02 2400

21 Coliform 60 02 120

Total 7940

III. Supervise wastewater

No Index Unit price Quantity Total amount

1 pH 30 01 30

2 COD 80 01 80

3 BOD5 80 01 80

4 SS 50 01 50

5 Coliform 60 01 60

Total 300

IV.Supervise underground water quality

No Index Unit price Quantity Total amount

1 pH 30 01 30

2 Sunfat 80 01 80

3 Total iron 60 01 60

4 Mn 120 01 120

5 Pb 120 01 120

6 Clo 60 01 60

7 Coliform 60 01 60

8 E.coli 60 01 60

Total 590

V. Sludge and soil

No Index Unit price Quantity Total amount

1 pH 100 01 100

2 Total N 300 01 300

3 Total P 150 01 150

4 Cd 200 01 200

Page 98: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 97

5 Cu 200 01 200

6 Pb 200 01 200

7 Zn 200 01 200

1350VI. Vehicles cost to take sample andkeeping samples

800/trip 4 3200

VII. Other costs

1 Reporting 1.000/time 4 4000

2 Office supplies 200/time 4 800

Total 24780

Funding source to carry out the environment quality supervision in operationphase is from the operating money of the project.

Page 99: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 98

(4) Training program on environment

Training on environment is one of the activities in the project’s preparation, to assist the staffs, workers, engineers,

contractors, the public etc to carry out well the environment supervision, apply effectively mitigation measures and reporting

mechanism.

Training on environment is summazied as follows:

Table 7.4: Training on environment

ParticipantsTraining

courseTraining contents

Implementing

frequency

Cost (VND) Fund source

PMU

- Fulltime staff/

environment

management

- Supervise;

- Environment

reporting

- General environment management

- coordinate with related offices ;

- environment supervision: content,

reporting, schedule and supervision

responsibility;

- instruct supervising the contractor;

- listen to community ideas;

- since the

project start

and during

implementing

process

20,000,000

Project’s

construction

cost

Contractor:

- representative

who take care

of reporting to

PMU

- implement

mitigation

measures ;

- Periodic

report

- present summary of periodic supervision

work ;

- supervise task of the contractor as in

contract;

Monthly report (or at request): content,

objects, supervision method; implement

mitigation measures, define occurred

problem and solution, submitting report,

- periodically

as requested

15,000,000 Project

construction

cos

Page 100: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 99

ParticipantsTraining

courseTraining contents

Implementing

frequency

Cost (VND) Fund source

responsibility

Workers, staffs

– Workers,

staffs (key

staffs)

- Safety and

environment

sanitation

- social and environment safety issues

- Task of workers and staffs

- Manage environment safety and

sanitation in work

- reduce proposals

- Working safety method and problem

prevention;

- Coping method for urgent situation

- Before and

after the

project

completion.

15, 000,000 Project

construction

cos

Community:

- team

leader/vice team

leader of the

local people

group

- représentative

frome sensitive

area

- Observe and

monitor the

site

- brief supervision on environment

- task of the community ;

- Content and form of supervising;

- Recoding method at site;

- Receive, gather query of the people;

- Summary and report to PMU

- Right at the

project start

20, 000,000 Project

construction

cos

Total : 70, 000,000 VND

Page 101: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 100

(5) Totaling environment protection costs

Environment protection costs in presented in table 7.5 as follows :

Table 7.5 : Totalling environment protection costs

No Contents Cost (VND) Funding source

1 Environmentmanagement

- In construction contracts of the subproject

2 Environment monitoring 51,580,000 Construction and operation costs of thesubproject

3 Training 70,000,000 Construction cost

Total : 121,580,000 VND .(exclude environment management cost due to it is included in constructioncontracts of the subproject)

Page 102: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 101

7.4. Organize environment supervision and reporting

7.4.1 Organize environment supervision

To organize environment supervision play big role to reduce negative

impacts. Functions, responsibilities and role of related bodies are presented as

follows:

Project Management Unit (PMU)

PMU is responsible for implementing and supervising the environmentmanagement plan. With assistance from the Independent Supervison Monitor(ISM) and Construction Management Consultant (CMC), PMU will supervisethe contractors in implementing measure to mitigate impacts during constructionphase. PMU will coordinate with local authority to push up the cummunityparticipation in preparation phase, implementing phase and operation phase ofthe project. PMU also take responsibility for reporting the implementation ofenvironment management plan to World Bank and Department of NaturalResources and Environment, based on actual observation on site, conclusion inmeetings and monthly progress report prepared by ISM/CMC.

For environment supervision, task of PMU as follows:

- Ensure that all terms related to Environment Management Plan must be

specified in construction contract;

- Select and coordinate with independent consultant (on environment and

social) to design and implement the environment supervision program;

- Supervise contract implementation of consultants, who are selected based

on the environment supervision matters and mitigate measures stated in

TOR;

- Check mobilization and construction plan proposed by contractor to

discover any potential impacts and suddenly check measures to reduce

impacts of the contractor;

- Ensure that construction supervisor, community consultant who are

selected to assist the environment supervision activities, complete their

responsibilities clearly stated in approved TOR;

- Employ and assist ISM in implementing supervision services to set up and

measure supervision parameters and report requirements of PMU;

Community’s representative

In household connection, community’s representative is encouraged to

participate in the environment supervision program, through those

Page 103: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 102

representatives and under the organization to implement and management of

PMU as well as local administrative offices (ward/commune people’s

committee). Community supervision will directly participate in supervision

before and during construction phase on supervising the implementation of

measures to reduce environmental impacts and public related matters.

Supervison measure basing on the community shall be assisted in professional

by independent management organizaton – IMO. Specific task of community

supervision as follows:

- Join training course to improve environment supervison ability (held by

DONRE or related offices) and will become the trainers in their

community;

- Directly implement environment supervision with specific supervision

methods to be set up in coordination with ISM;

- Collect data on the site to make it the base for measuring impacts/benefits

of the project.

- Prepare periodic supervision report (every week or every month) and

submit the report to PMU and related PC, depending on specific

requirements at specific time.

- Propose admendment to the plan and implementing schedule to reduce the

environment impacts on the local.

- Assist in advertising the project information, capacity building program

and provide feedback to queries to support the measures as neccesary

toward project related environment impacts.

Construction Management Consultant (CMC)

Main task of CMC is to supervise procedures of basic construction,

supervising operation procedures to reduce environment impacts as described in

the Environment Assessment. This task will be clearly defined in TOR for the

CMC and in contract between CMC and PMU. These two documents must be

checked by World Bank before issuing No objection letter”. Under instruction of

the PMU, main task of CMC in reducing impacts and supervising include: (but

not limited) the following issues:

- Assist, coordinate with ISM in designing, collecting and providing

information related to environment norm nessecary for the site and

construction implementing;

- Ensure construction work to comply with the environment management

plan and related norms and standard operation procedures of the contract

documentation on mitigation measures and supervising the environment

impacts;

Page 104: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 103

- Supervise the implementing mitigation measures of the contractor, timely

propose and implement interfere measures to complete the mitigation

measures to meet requirements on safety for environment management;

- Prepare action plan/urgent solution to deal with environment problems,

urgent situation and possible damages ruing construction phase;

- Prepare weekly/monthly/quaterly report as required at specific time;

- Recommend the PMU to stop construction, either a part or a whole of the

construction items if requirements on working safety and environment

sanitation are not met;

- Orgainze meeting between related parties, receive to provide necessary

information about the project, carry out schedule and working plan to

improve community awareness and identify possible problem happened in

the community and to look for solution to solve the problem occured

before construction work;

Independent Safety Monitor (ISM)

The ISM will take care the designing of safety protection supervisionprogram as required by the regulations of WB and Government of Vietnam.After checking and approving activities to carry out the project and ensurepolicy on environment safety to be approved by GOV and WB, which later isapplicable and monitored through the following tasks:

- Ensure the environment managemeny plan to be approved and all

conditions in the loan agreement for the project related to environment

protection to be applied and strictly respected during the project

implementing time;

- Ensure to prepare mitigation measures for environment impacts as

required for all aspects of the project implementing in environment

management system, which includes:

+ Prepare and implement supervision measures and mitigation

measures to reduce environment impacts and responsibilities of

PMU, including cost estimate and personnel planning;

+ Evaluate the effectiveness of the mitigation measures that the

contractor and CMC stated in the mobilization plan to propose and

recommend to PMU improved measures that are essential to

satisfy the safety requirements

Page 105: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 104

+ Cleary report to PMU about situation that may need more studying

and/or comsult the local authority to define potential problems and

mitigation measures for them;

- Set up standard procedures, methodology and form to assist PMU and

CMC to evaluate progress of the contractor in implementing mitigation

measures and reducing environment impacts;

- Assist PMU and supervisor and reduce environment impacts as required

by the PMU to check the detail design and related contents in the

contractual document to ensure the fitness of environment protection

policy and supervision requirements and impact reduction

- Identify and prepare database necessary for the environment management

plan, together with related parties (DONRE), community consultation

specialist and community representative to assist monitoring

implementing index of the project;

- Through instruction by PMU, prepare and maintin coordination with

CMC to ensure related environmental regulations, supervision measures,

and mitigation measures and method to be clearly understood and

included in working plan of the CMC and reporting procedures including

suitable criteria and proposed procedures to stop construction activity

when and where the contractor did not comply the requirements of

environment safety and protection.

- Assist ISM to prepare and apply the urgent action plan, if neccesary for

environment loss or encountered probelem during construction phase;

- With coordination of the PMU and CMC, provide assistance and

neccesary instruction for the contractor to:

+ Mention any problem or query that may meet and relate to

environment impact and provide recommendation and mitigatiom

measures;

+ Gathering neccesary environmental information and evaluate

special and diificult problem properly happen in construction

phase;

+ Provide necessary assistance and support the community

representative in preparing and implementing the environment

management plan;

+ Asist PMU to prepare and maintain management and organization

system, monitoring and reporting together with coordination from

related office and local community

Page 106: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 105

+ Provide assistance and support training course on environment and

building the capacity and coordinate with community consultation

specialist;

+ Assist the PMU to carry out survey on environment and meeting to

coordinate with the local representatives during construction

phase;

+ Provide general instruction on environment required by PMU to

enhance the implementing the project result.

7.4.2. Reporting

Reports of environment supervision program and mitigation measures forenvironment impacts will be prepared by the project employer – BIWASE orenvironment supervison consultant hired by the project employer, at least everythree months, the report should be submitted to WB and Tan Uyen People’sCommittee for approval. Based on the reporting results, WB and tan Uyenpeople’s Committee may require the project employer to more implement theenvironment monitoring plan and comply with mitigation measures forenvironment impacts. If the environment protection measures and mitigationmeasures for environment impacts are not adequate for the actual conditions,replacement measures will be proposed and consulted by the local environmentmanagement office – DONRE in Tan Uyen district and consulted by the public.The below chart show amendment and feedback mechanism.

Page 107: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 106

Figure 7.1: Amendment and feedback mechanism

Implement mitigation measures

Supervise

Report to WB and Tan Uyen people’scommittee

FailPass

Reconsider the mitigationmeasures

Consulting local environmentoffice and public

Implement replaced mitigationmeasures

Page 108: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 107

8. COMMUNITY CONSULTATION

8.1 COMMUNITY CONSULTATION AND PUBLIC INFORMATION

In the process of review of environmental impact, households living around thearea planned for construction of the collection work, treatment plant and pipesystem are consulted about the environmental impact of sub-project. Thepurpose of this consultation is to seek measures to minimize negative impacts onthe environment during construction and operation phase of the project. Themitigation measures have also been mentioned in the EnvironmentalManagement Plan, basic design and bidding document.

People's Committee of Uyen Hung town, the People's Committee of Tan Hiepcommune, People's Committees Khanh Binh commune and People's Committeeof Thoi Hoa commune, Ben Cat district had invitations for communityconsultation to most of households affected and community consultation wereheld in People's Committee of Uyen Hung town, the People's Committee of TanHiep commune, People's Committees Khanh Binh commune and People'sCommittee of Binh Thoi Hoa commune, Ben Cat District on September 16th,2010 and September 17th, 2010 (the minutes of the meetings are shown in theappendix). Participants in the public consultation included:

Leadership of People's Committee of Uyen Hung town, the People'sCommittee of Tan Hiep commune, People's Committees Khanh Binhcommune and People's Committee of Thoi Hoa commune, Ben Cat district

Representative of the investor;

Representative of the consultant: Environmental Specialist

People are affected

The public consultation meeting took place in about 2.0 hours (With thefollowing contents)

Brief content of the project and benefits of the project:

The environmental expert presented a summary of the negativeenvironmental impacts arising from construction of the project andmitigation measures;

The participants ask questions and discuss.

Conclusions and closing.

All delegates agree with the presentation of environmental specialists aboutenvironmental impacts, mitigation measures and expect the project is deployedsoon to meet urgent promotion of clean water for local people. The delegatesalso asked the investor to comply with environmental protection measures in the

Page 109: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 108

whole process of the project as presented in the environmental assessment reportprepared by the consultants.

The public consultation meetings were held separately People's Committee ofUyen Hung town, the People's Committee of Tan Hiep commune, People'sCommittees Khanh Binh commune and People's Committee of Binh Thoi Hoacommune, Ben Cat District on September 16th, 2010 and September 17th,2010. Focus the following content:

1. Consensus and support of residents in the local area for sub-projectimplementation. Based on the situation of current water use, people wereaware that the project will have positive effects on health status and theirliving conditions, so they absolutely support sub-project implementation.

2. Other discussion of the people.

Minutes of these meetings are provided in the appendix.

In short, all the delegates support and expect that the project is implemented asschedule to ensure the need of clean water for local people. In the course ofproject implementation, the investor must comply with environmental protectionmeasures as proposed in the environmental assessment report.

8.2 SUMMARY TABLE OF COMMUNITY CONSULTATION

Page 110: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 109

Table 8.1: The sum of community consultation

Location TimeNumber of

participantsCommunity Opinions Summary of comments

Feedback of the investor andconsultant about opinions/

concerns of the people

People’scommitteeof TanHiepcommune

8am

September15th, 2010

14

Preparation phase, construction phase

+ 85.7% of households agree with the proposedenvironmental impact:

Dust and noise from vehicles, machineries forconstruction of pipe and water treatment plant;

Discharging solid waste in construction and activitiesof workers;

Partial flood

Impact on water environment;

Impact on soil environment;

Impact on ecosystems, landscape and socio-economiclife;

Risk and environmental accidents...

Safety at work

Traffic jam and traffic accidents ...

+ Contribute more influence in the process ofpreparation and construction of the project:

People and vehicles move on the roads which areexecuted;

Ground is not tight, causing landslides, obstructing

+ Most of households agree tosolutions for minimizing impactson environment andsocioeconomic.

+ The investor shouldestablish monitoring team andcoordinate local government tosolve problems of thecommunity during constructionand operation phase;

+ The construction progressof construction projects will besynchronous rolling, and notspreading to affect beauty andthe life of the people;

+ Construction process of theproject should take into accounteffect of work, suit time,location and does not interferewith the surroundingcommunity.

+ Mitigation measures mustbe applied as presented in the

The investor agree torecommendation of thecommunity and will carry outthe following measures:

+ The investor shouldestablish monitoring teamand coordinate localgovernment to solve arisingproblems of the communityduring construction andoperation phase;

+ As proposed opinion, theconstruction progress ofconstruction projects will besynchronous rolling, and notspreading to affect beautyand the life of the people;

+ Construction will payattention to time and locationof construction and does notaffect activities of thesurrounding community.

+ The investor commitimplementing mitigationmeasures as presented in the

Page 111: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 110

structures on the ground.

Impact on existing structures

Accidents are caused by motor vehicles, dust affectsthe health of the community ...

The impact on timetable of community;

Social evils;

+ 92.9% of households agreed with the proposedmitigation measures:

The water environment;

Air environment;

Soil environment;

Minimize the impact of discharging of waste andcollect solid waste from construction and activities;

Forecasting risk and environmental incidents;

Comply with measures of industrial safety;

Separate traffic reasonably;

Inform people of time of the project ...

+ Contribute mitigation measures:

Community supervision;

Listen to suggestions, complaints of citizens;

Each region is implemented fast ;

Light, signage, fencing ...

Use strong sanctions with construction contractors,and even terminate the contract if need;

summary report of EIA;

+ Return the initial state forarchitectural works affected bythe project.

+ Compensate, support peoplewho were withdrawn land, work,crop on the land, households losejobs will be supported to changejob and have new jobs aftertraining;

+ Find out the problems,current situation and promote theconstruction schedule regularly.

+ Strong sanctions will beapplied if the contractor doe notabide by the conventions.

summary report of EIA

+ The investor will returnthe initial state forarchitectural works affectedby the project.

+ Compensate, supportpeople who were withdrawnland, work, crop on the land,households lose jobs will besupported to change job andhave new jobs after training;

+ To ensure themanagement, the investorwill hold communityconsultation regularly to findout the problems, currentsituation to promote theprogress of construction andapply sanctions when thecontractor cause influence tocommunity activities.

Page 112: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 111

Compensation for damages caused by the project;

Execution in the rolling, handle works definitely;

- Operation phase:

+ 100% of households agree to the proposals aboutenvironmental impact:

Sludge deposit after the process of water supplytreatment;

Waste gas and dust from equipments;

Problems occur in operation of the system ...

+ Contribute mitigation measures in operation phase:

Security in area of water treatment plant;

Social conflict;

Training workers and engineers to operate equipmentsand machines well;

Training on the environment;

+ 100% of households agree to mitigation measures:

The measures for collecting and treating solid waste,waste sludge;

Safety at work

Security within the project area;

Security in pipelines, water treatment plants;

+ Contribute measures to minimize impacts of operationphase:

Listen to reflect the community;

Page 113: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 112

Monitor incidents of the work ...

People’scommitteeof BinhKhanhcommune

8:30 amSeptember16th, 2010

12

Preparation and construction phase

+ 83.3% of households agree to the proposedenvironmental impact:

Dust and noise from vehicles, machineries forconstruction of pipe and water treatment plant;

Discharging solid waste in construction and activitiesof workers;

Impact on soil environment;

The impact on ecosystem, landscape and socio-economic life;

Risk and environmental accidents...

Safety at work

Traffic jam and traffic accidents ...

+ Contribute more influence in the process ofpreparation and construction of the project:

People and vehicles move on the roads which areexecuted;

The impact on timetable of community living;

Social evils;

+ 91.7% of households agreed to the proposedmitigation measures:

The water environment;

+ Most of households agree tosolutions for minimizing impactson environment andsocioeconomic.

+ The investor shouldestablish monitoring team andcoordinate local government tosolve problems of thecommunity during constructionand operation phase;

+ The construction progressof construction projects will besynchronous rolling, and notspreading to affect beauty andthe life of the people;

+ Construction process of theproject should take into accounteffect of work, suit time,location and does not interferewith the surroundingcommunity.

+ Mitigation measures mustbe applied as presented in thesummary report of EIA;

+ Compensate, support people

The investor agree torecommendation of thecommunity and will carry outthe following measures:

+ The investor shouldestablish monitoring teamand coordinate localgovernment to solve arisingproblems of the communityduring construction andoperation phase;

+ As proposed opinion, theconstruction progress ofconstruction projects will besynchronous rolling, and notspreading to affect beautyand the life of the people;

+ Construction will payattention to time and locationof construction and does notaffect activities of thesurrounding community.

+ The investor commitimplementing mitigationmeasures as presented in thesummary report of EIA

+ Compensate, supportpeople who were withdrawn

Page 114: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 113

Air environment;

Soil environment;

Minimize impacts of discharging of waste and collectsolid waste from construction phase and activities;

Forecasting risk and environmental incidents;

Comply with safety measures for workers;

Separate traffic reasonably;

Inform people of time of the project ...

+ Contribute mitigation measures:

Each region is implemented fast ;

Establish monitoring team and listening tosuggestions, complaints of citizens.

Use strong sanctions with construction contractors,and even terminate the contract if need;

- Operation phase:

+ 100% of households agree to the proposedenvironmental impact:

Waste gas and dust from equipments;

Problems in the operation of the system ...

+ Contribute more influence in the process ofpreparation of the project.

Security in area of construction;

Training workers and engineers to operate equipmentsand machines well;

who were withdrawn land, work,crop on the land, households losejobs will be supported to changejob and have new jobs aftertraining;

+ Find out the problems,current situation and promote theconstruction schedule regularly.

+ Strong sanctions will beapplied if the contractor doe notabide by the conventions.

+ Ensure quality of pipelineon the technical requirementswith capacity of 30,000m3/day.

land, work, crop on the land,households lose jobs will besupported to change job andhave new jobs after training;

+ To ensure the management,the investor will holdcommunity consultationregularly to find out theproblems, current situation topromote the progress ofconstruction and applysanctions when the contractorcause influence tocommunity activities.+ In course of construction,the investor commits usingconstruction materials withhigh quality and will inspectconstruction workperiodically.

Page 115: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 114

Regulate water demand during dry season

Training on the environment;

+ 100% of households agree to mitigation measures:

The measures for collecting and treating solid waste,waste sludge;

Educate, propagandize to engineers, staff;

Safety at work

Security within the project area;

+ Contribute measures to minimize impacts of operationphase:

Listen to reflect of the community;

Monitor work incidents ...

People’scommitteeof UyenHungtown

2 pm

September17th, 2010

10

Preparation phase, construction phase

+ 80% of households agree to the proposedenvironmental impact:

Dust and noise from vehicles, machinery forconstruction of pipe and raw water pumping station;

Discharging solid waste in construction and activitiesof workers;

Partial flood

Impact on water environment;

Impact on soil environment;

The impact on ecosystem, landscape and socio-economic life;

+ Most of households agreeto solutions for minimizingimpacts on environment andsocioeconomic.

+ The investor shouldestablish monitoring team andcoordinate local government tosolve problems of thecommunity during constructionand operation phase;

+ The construction progressof construction projects will besynchronous rolling, and notspreading to affect beauty andthe life of the people;

The investor agree torecommendation of thecommunity and will carry outthe following measures:

+ The investor shouldestablish monitoring teamand coordinate localgovernment to solve arisingproblems of the communityduring construction andoperation phase;

+ As proposed opinion, theconstruction progress ofconstruction projects will besynchronous rolling, and notspreading to affect beauty

Page 116: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 115

Risk and environmental accidents...

Safety at work

Traffic jam and traffic accidents ...

+ Contribute more influence in the process ofpreparation and construction of the project.

People and vehicles move on the roads which areexecuted;

The impact on timetable of community living;

Social evils;

+ 90% of households agree with the proposed mitigationmeasures:

The water environment;

Air environment;

Soil environment;

Minimize impacts of discharging of waste and collectsolid waste from construction phase and activities;

Forecasting risk and environmental incidents;

Comply with safety measures for workers;

Separate traffic reasonably;

Inform people of time of the project ...

+ Contribute measures to minimize impacts:

Community supervision;

Each region is implemented fast ;

Listen to suggestions, complaints of citizens.

+ Construction process of theproject should take intoaccount effect of work, suittime, location and does notinterfere with thesurrounding community.

+ Mitigation measures must beapplied as presented in thesummary report of EIA;

+ Compensate, support peoplewho were withdrawn land,work, crop on the land,households lose jobs will besupported to change job andhave new jobs after training;

+ Find out the problems,current situation andpromote the constructionschedule regularly.

+ Strong sanctions will beapplied if the contractor doenot abide by theconventions.

+ Calculating time and volumeof exploited water not to affectproduction and daily life of thecommunity.

and the life of the people;

+ Construction will payattention to time and locationof construction and does notaffect activities of thesurrounding community.

+ The investor commitimplementing mitigationmeasures as presented in thesummary report of EIA

+ Compensate, supportpeople who were withdrawnland, work, crop on the land,households lose jobs will besupported to change job andhave new jobs after training;

+ To ensure themanagement, the investorwill hold communityconsultation regularly to findout the problems, currentsituation to promote theprogress of construction andapply sanctions when thecontractor cause influence tocommunity activities.

+ The project hascalculated the amount ofexploited water with flow ofwater in river and waterdemand of production,community living along the

Page 117: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 116

Use strong sanctions with construction contractors,and even terminate the contract if need;

- Operation phase:

+ 100% of households agree with the proposed mitigationmeasures:

Waste gas and dust from equipments in the raw waterpumping station;

Problems in the operation of the pump system...

+ Contribute more influence in the process ofconstruction of the project.

Security in raw water pumping station;

Calculating time and volume of exploited water not toaffect production and daily life of the community.

Training workers and engineers to operate equipmentsand machines well;

+ 100% of households agree to mitigation measures:

The measures for collecting and treating solid waste,waste sludge;

Security in the project area

Industrial safety in the raw water pumping station;

+ Contribute measures to minimize impacts of operationphase:

Coordinate with local government to solve problemsarising during operation phase

Operate with regulated capacity.

+ Raw water pumping station isoperated with capacitycommitted, not to affect waterresources and ensure safe of thesystem.

Dong Nai River in Tan Uyenarea.

+ The investor commit theraw water pumping stationexploited with capacitypresented in the summary ofEIA report.

Page 118: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 117

APPENDIX 1:PROJECT MAP

Page 119: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 118

Page 120: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 119

Page 121: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 120

APPENDIX 2:PICTURES OF PROJECTS

Page 122: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 121

1. COLLECTING GATE AND RAW PUMPING STATION

2. LAND FOR EXECUTION OF RAW WATER PIPELINE

Page 123: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 122

Page 124: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 123

3. RESERVED LAND AREA FOR CONSTRUCTON OF THE TREATMENT PLANTAND PRESSURE PUMPING STATION

Page 125: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 124

APPENDIX 3A SAMPLE FORM CHECK

Page 126: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 125

Page 127: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 126

Page 128: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 127

Page 129: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 128

Page 130: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 129

Page 131: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 130

Page 132: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 131

APPENDIX 4:COMMUNITY CONSULTATION

Page 133: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 132

Page 134: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 133

Page 135: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 134

Page 136: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 135

Page 137: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 136

Page 138: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 137

Page 139: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 138

Page 140: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 139

Page 141: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 140

Page 142: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 141

Page 143: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 142

Page 144: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 143

Page 145: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 144

Page 146: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 145

Page 147: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 146

Page 148: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 147

Page 149: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 148

Page 150: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 149

APPENDIX 5:THE ENVIRONMENTAL COMMITMENT

Page 151: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 150

Page 152: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 151

Page 153: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 152

APPENDIX 6

LOCATIONMAP OF ENVIRONMETAL MONITORI

Page 154: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 153

Page 155: ENVIRONMENTAL ASSESSMENT AND ... - The World Bankdocuments.worldbank.org/curated/en/... · ENVIRONMENTAL ASSESSMENT AND ... ES Environmental Supervisor Người giám sát môi trường

Environment Protection Committment –Water Supply System in My Phuoc Urban and IndustryEmployer: Binh Duong Water Supply Sewerage Environment Co., Ltd

Page | 154