Engineers India Limited MEGA PROJECTS- A Project Management Perspective Niraj Sethi 8 th July 2017 National Seminar on Project Management Objectives and Challenges Kolkatta

Transcript of Engineers India Limited MEGA PROJECTS- A Project ...EILL12.pdf · Engineers India Limited MEGA...

  • Engineers India Limited

    MEGA PROJECTS-A Project Management Perspective

    Niraj Sethi 8th July 2017

    National Seminar on Project Management Objectives and ChallengesKolkatta

  • 11 July 2017 2

    Table of Contents

    1Overview

    2Project Implementation Plan- Choices

    3

    Key challenges to project implementation

    Phases of a Project

    Key Strategies Schedule

    1

    Cost Monitoring/ Management

    2

    3

    4

    5

    6

    Conclusion7

  • 11 July 2017 3

    Maha Dhamaka- Bumper Sale It appears MEGA is the Mantra of the day !

    Overview

  • 11 July 2017 4

    Overview

    Vintage Refineries had Capacities of the order of 0.6 MMTPA against the current trends of MEGA Refineries around 20 MMTPA

    Refineries were fuels only refineries compared to todays MEGAintegrated complexes

    Time cycles have shrunk from 71 months to 36 months

    Todays MEGA Refineries entail High CAPEX investments

    Current Indian refining capacity is 232 MMTPA

    India is now a refining hub, exporting nearly 80 MMTPA of products.

    Fiscal prudence doesn't permit Cost/ Schedule over runs in MEGA Projects

  • 11 July 2017 5

    Overview

    Projects are growing in size and complexity-Today it is common to think in terms of projects involving investments of Rs. 40,000 Cr and more.

    Integration for value addition characterizes most projects e.g. Refinery-Petrochemicals. The future could see Refining-Petrochemicals-Derivatives and coal gasification integrations.

    Increasing complexity and size accompanied by a need to cut implementation time and cost

    The net result is a set of major challenges that the Project Owners, Consultants, Contractors and Suppliers have to face jointly and overcome at each stage of a project

  • 11 July 2017 6

    Key challenges to project implementation

    Competitive Environment

    Enhanced Project Sizes/ Investments

    Compressed Project Schedules

    Inadequate Experienced manpower

    Limited Number of Resourceful & Experienced Construction Companies

    Logistic Constraints /difficult landlocked terrains

    Inflexible procedures with limited Leeway for maneuvering Vendor/ Contractor failures

    Empowerment , Decentralization of Powers/authority for quick action

  • 11 July 2017 7

    EPCMLow Cost / Diffused schedule

    LSTKHigh Cost/

    Large Overall schedule

    OBEEPCM costs/

    LSTK Schedules

    Project

    Project Implementation Plan Choices

    Implementation Modes Experienced in the recent past

  • 11 July 2017 8

    Project Implementation Plan EPCM Vs EPC son

  • 11 July 2017 9

    Project Implementation Plan - Remains a choice

    Panipat Refinery Expansion of 6 MMTPA implemented on a Hybridmode. A combination of Conventional and LSTK.

    Mega Grass Roots Refineries such as GGSRL 9 MMTPA andBina 6 MMTPA Implemented on Conventional Route

    Euro IV Project Set the trend of OBE mode of projectImplementation in Preference to LSTK for major schedule gainstowards the Award Cycle of LSTK

    Integrated MRPL Expansion chose an Ultimate Hybrid ofConventional, OBE and LSTK

    PNCP 0.8 MMTPA Integrated Complex & Paradeep Refinery chosethe other Extreme of Total LSTK mode of Implementation

    Facilities on BOO basis have also been installed

    Recent Projects indicate no one way preference

  • 11 July 2017 10

    Phases of a Project

    A Mega Project has the following broad Phases

    TAKE OFFENGINEERINGPROCUREMENTMANUFACTURING/ DELIVERYCONSTRUCTIONMC/ COMMISSIONING

    Project Implementation Plan has to ensure an approach for Each Phase

  • 11 July 2017 11

    Take Off / Front end Activities

    Process/Front end

    Formulation of an Exhaustive Project Design Basis

    Early Development of Plot Plan as the mother Document

    PFDs/ P&IDs and Dimensioned Equipment Layouts

    Process and Engineering Design Basis

    Clear Definition of Scope for Deliverables from Licensors

  • 11 July 2017 12

    Take Off/ Front End Activities

    Process/Front end Standardization of Piping Material specifications and Instrumentation

    Philosophy with Licensors for minimization of variety and hencereduction in Cost Towards spares while maximizing Interchangeability

    Mechanical Design of Static equipment including internals with FirmDefinition of hardware

    Complete Thermal design of all the Heat Exchangers and Air coolers forFirm Definition of Hardware

    API data sheets and Front end Thermal Design /Conceptual Mechanicaldesign of all Furnaces for Firm Definition of Hardware

    Primary selection of pumps to finalize the seal arrangement and flushing/utility connectivity

    Clear definition of control System including sizing of all Control valvesand safety valves for Clear Definition of hardware

  • 11 July 2017 13

    Take Off/ Front End Activities

    Front end Detailing

    Development of Load list, SLD, Electrical Substation layouts andElectrical System study for Clear definition of hardware

    Clear guidelines to perform Residual Basic Engineering including ISBLutility Distribution P&Ids in Units

    Dimensioned Equipment layouts incorporating experience fromEngineering considerations & Owners maintenance practices

    Hazop Study on P&Ids and evolution of recommendations to beincorporated in design

    Finalization of Interfaces for the contractors

    Development of Conceptual UG piping System and Generalarrangements with guidelines for Detailed Engineering

  • 11 July 2017 14

    Take Off/ Front End Activities

    Front end Detailing

    Safety Audit of the Equipment Layout and Finalization of other safetyRequirements

    Development of all Architectural drawings for the Buildings Envisagedincorporating Owners Inputs for Clear definition of requirements

    Detailed Equipment Layout Plan and Elevation Sections Drawings

    Control System and Specifications Definition for DCS/PLC and Plantsafeguarding system to clearly define the hardware

    Overall Layout Drawings for UG Piping System, Cooling water System,Fire water System, Cable layouts for electrical and Instrumentationsystem

    Development of Clear Design basis documents for all utility systemsidentifying the Hardware clearly in the documents

  • 11 July 2017 15

    Engineering

    Task force working for synergy in engineering etc. regular Interdiscipline reviews.

    Hold management system to be in place.

    Majority of front (Drawings/ Material/ Physical) shall be made availableto the civil and structural contractors at the time of mobilization.

    Majority of front (Drawings/ Material/ Physical) shall be made availableto the Composite contractor at the time of mobilization.

    Piping & Civil/ Structures to be opening batsmen!.

    Minimize Mid Course Changes

  • 11 July 2017 16

    Engineering

    Exhaustive 3D model review to avoid surprises/ re-engineering andprocurement of additional material.

    MTOs and AFC drawing extraction from Model

    IBR (System Isometrics) & Utility System Isometrics to be extractedfrom The Model

    Vendors encouraged to be accountable for drawings, fabrication etc.

    Building contract shall include all associated infrastructures such asAC system, Lighting, Fire alarm system etc.

    Monthly meeting shall be organized with the contractors/ vendors forLong Lead and critical items/ Package.

  • 11 July 2017 17

    Procurement

    ORDERING/ MANUFACTURING/ DELIVERY

    Fast track ordering on competitive basis

    Zero deviation bid and exhaustive discussion before submission ofbids may be adopted.

    Pre Tender/ Pre Bid meetings

    Static , Rotating Equipment may be bulked (Bottom line purchase) foravailing advantages of economies of scale

    Accuracies of First piping Bulk MTO are critical to Project success

    Umbrella contracts for supply of standard equipment Motors/Transformers/ Switchgear etc.

  • 11 July 2017 18

    Description Columns Vessels Heat Exch

    Air Coolers

    Compressor Pumps Misc

    Unit Nos Nos Nos Nos Nos Nos Nos

    CDU/VDU 6 28 47 10 - 47 25

    MS Block 17 68 59 11 11 42 27

    DHDT 6 24 16 6 2 12 13

    DCU 9 23 19 9 1 34 20

    VGO HDT 7 34 26 7 3 25 13

    PFCC 10 30 45 6 3 49 31

    PP 3 31 5 1 5 24 38

    U&O 0 17+

    64 Tanks

    0 0 1 70 9

    TOTAL 58 255 217 50 26 303 176

    Major Equipment- Typical Refinery

    Procurement

    Bulk Procurement is the Key

  • 11 July 2017 19

    Resort to bulking to minimize vendors Bulk material

    Procurement

    210 km

    5 Lakhs

    2.2 Lakhs

    1.1 Lakhs

    (Excl. P/L)

    Chart1

    168000508752226618114468

    39800393733471563

    1869403348397

    220000513092230313116428

    PIPES

    FITTINGS

    FLANGES

    VALVES

    Sheet1

    PIPESFITTINGSFLANGESVALVESHV CABMV CAB

    REFINERY1680005087522266181144683130003900000

    COT39800393733471563

    PIPE LINE1869403348397

    OEVRALL220000513092230313116428

    To resize chart data range, drag lower right corner of range.

  • 11 July 2017 20

    UG Piping material procurement to be prioritized to ensure majormaterial availability prior to the contractor mobilization

    Minimize site work- Major fabrication in shop.

    ODCs sourcing through PORT based vendors

    Across the table review of drawings/ documents.

    Composite mechanical contract comprising of Mechanical, piping,electrical, Insulation, painting

    3D Modeling Review done at 3 stages

    3D Modeling accorded priority and Target Major Engineeringcompletion 9 Months prior to MC

    Procurement

  • 11 July 2017 21

    Construction

    Field engineering cell along with associated 3D model software.

    Peak manpower deployed on large Projects: 20,000/ Over 50 Millionman-hours

    Tenders for Machinery to facilitate construction

    Piling Contractors encouraged to use Hydraulic rigs vis--visConventional.

    Designs tweaked to suit site conditions- Water Table, Hard Rock etc.

    Fabrication Yards

    Provision of Extensive Storage Warehouses/ yards

  • 11 July 2017 22

    Prioritize UG works and pavement to facilitate uninterruptedconstruction works

    Modular Construction

    Pre-fabricated Manholes, Trenches

    Tenders to augment failing contractors

    Awards for Safe working

    Constructability studies including Rigging studies for ODC andmega lifts

    Contractors encouraged to establish fabrication facility (AutoWelding) at site. Provides Large Inch-Dia daily progress.

    Construction

  • 11 July 2017 23

    Engineering design to be Construction Friendly

    Monsoon Combat Plan & Designs to be in place for uninterrupted site works

    Credentials of perennially non performing vendors to be reviewed

    Equipment Tracking (GPS) and Logistic Expertise/ Monitoring system to be improved

    Possibility of Swing Contracts for supplementing failing construction agencies to be explored (e.g. Hiring Cranes and Manpower Resources)

    Construction

  • 11 July 2017 24

    Review if Major ODCs could be fabricated at site If space is available.

    Typical Past project advantage in Site Fabricated ODCs

    Provide Major cranes for Erection and handling of prefabricated RCC /Steel structures and Erection of ODCs.

    Major Site fabricated equipment Duration in months

    COLUMNS Dia (M) Height (M) Weight (MT) Fabrication time(Ahead of sch.)

    CDU 7 67.85 642 3 months

    VDU 12 60.3 810 3 months

    Coke Chambers 9.1 34 340 2 months delay

    Reactor 13.8 62 415 1 months

    Regenerator 15.3 25 514 1 months

    Construction

  • 11 July 2017 25

    Work breakdown for Civil work for units and offsite

    With Volumes involved- RMC, Batching Plants, Free Issue of Cement & Steel are areas for deliberation

    Construction

    Chart1

    17100

    19200

    9200

    9000

    12500

    25200

    25200

    48500

    170000

    RCC

    Sheet1

    RCCST STEELSeries 3

    CDU/VDU1710054002

    MS BLOCK1920037002

    DHDT920020003

    DCU900021005

    VGO HDT125002150

    PFCC252006700

    PP252002900

    OFFSITE485005800

    OVERALL17000030750

  • 11 July 2017 26

    Work breakdown for structural work

    With Volumes involved- Free Issue of Steel , Pre fabricated Steel delivered from external shops, Modularization are areas for

    deliberation

    Construction

    Chart1

    5400

    3700

    2000

    2100

    2150

    7200

    2900

    5800

    31250

    ST STEEL

    Sheet1

    ST STEELSeries 3

    CDU/VDU54002

    MS BLOCK37002

    DHDT20003

    DCU21005

    VGO HDT2150

    PFCC7200

    PP2900

    OFFSITE5800

    OVERALL31250

  • 11 July 2017 27

    MC/ Commissioning

    System checks to start 06 months prior to Mechanical Completion for system wise monitoring/ completion/ handover

    Extensive Formatting to Checklist and identify the remedial measures

    Timely Availability of Utilities (Say N2/ CW/ Steam) to aid schedule

    Lining up of specialized agency to facilitate pre-commissioning / commissioning

    Adequate spares for last minute use

    Vendors on standby/ call for Commissioning assistance

  • 11 July 2017 28

    Key Strategies - Schedule

    Target schedule shall be at least 2-3 months before the contractualschedule.

    Integrated Project Master Schedule, integrating all the workpackages level detailed schedules from Major Contractors, Vendors

    Critical Path & Near Critical path analysis at regular intervals usingPrimavera software

    Multi-tiered Project review system Daily / Weekly meetings with Key Contractors Monthly progress review meetings by Senior Management

    War Room approach for Project Monitoring & Control Extensive reporting systems with regular Management reviewsand meetings

  • 11 July 2017 29

    Key Strategies - Schedule

    Long Lead and Critical Activities to be always in focus

    Bonus and incentive scheme to encourage vendors/ contractors toimprove delivery.

    Long lead items shall be floated with preliminary data which shall beupdated through amendments before award.

    Across the Table Drawing approvals to expedite Manufacture anddelivery

  • 11 July 2017 30

    Cost Monitoring / Management

    Ensure clear / succinct inputs for costing

    Consolidate all previous project data through database system

    Cost Status Reports to be monitored closely for analysis, feedback and corrective action

    Value based engineering for optimization, standardization and effective solutions

    Close vigil on SOR quantities to restrict variation and exercise schedule control

    Monitor variations in rates of Inputs, FE, Taxes/ Duties etc.

  • 11 July 2017 31

    VENDORS CONTRACTORS

    PROJECT MANAGEMENT

    OWNER MANAGEMENT

    CONFIGURATION & DESIGN BASIS

    PROCESS DESIGN

    DETAIL ENGG.

    BID PACKAGE &

    CONTRACTOR SELECTION

    FRONT END ENGG

    EQUIPMENT DELIVERIES

    CONSTRUCTION

    COMMISSIONING & HANDING OVER

    EXTERNAL LINKAGES INCLUDING STATUORY

    Project Management

    Managing all players and Meeting All Challenges !

  • 11 July 2017 32

    Conclusion Large projects increasing in Complexity Resources are an

    imperative

    All Phases are critical i.e. Pre-Project/ Engg. / Proc. / Const.

    Increased standardization, coupled with Proper planning and appropriate Project controls can help to mitigate the challenges

    Good Project definition is the key to meeting time and cost

    Success depends on use of Key Past Learnings and preparedness for eventualities

    Collaborative approach will work(Vendors & Contractors- Partners in progress)

  • 11 July 2017 33

    Thanks for your patience

    Slide Number 1Slide Number 2OverviewOverviewOverviewKey challenges to project implementationSlide Number 7Project Implementation Plan EPCM Vs EPC sonProject Implementation Plan - Remains a choicePhases of a Project Take Off / Front end ActivitiesTake Off/ Front End ActivitiesTake Off/ Front End ActivitiesTake Off/ Front End ActivitiesEngineeringEngineeringProcurement Procurement Slide Number 19Slide Number 20 Construction Construction Construction Construction Construction Construction MC/ CommissioningKey Strategies - ScheduleKey Strategies - ScheduleCost Monitoring / Management Slide Number 31ConclusionSlide Number 33