Engineers India Limited
MEGA PROJECTS-A Project Management Perspective
Niraj Sethi 8th July 2017
National Seminar on Project Management Objectives and ChallengesKolkatta
-
11 July 2017 2
Table of Contents
1Overview
2Project Implementation Plan- Choices
3
Key challenges to project implementation
Phases of a Project
Key Strategies Schedule
1
Cost Monitoring/ Management
2
3
4
5
6
Conclusion7
-
11 July 2017 3
Maha Dhamaka- Bumper Sale It appears MEGA is the Mantra of the day !
Overview
-
11 July 2017 4
Overview
Vintage Refineries had Capacities of the order of 0.6 MMTPA against the current trends of MEGA Refineries around 20 MMTPA
Refineries were fuels only refineries compared to todays MEGAintegrated complexes
Time cycles have shrunk from 71 months to 36 months
Todays MEGA Refineries entail High CAPEX investments
Current Indian refining capacity is 232 MMTPA
India is now a refining hub, exporting nearly 80 MMTPA of products.
Fiscal prudence doesn't permit Cost/ Schedule over runs in MEGA Projects
-
11 July 2017 5
Overview
Projects are growing in size and complexity-Today it is common to think in terms of projects involving investments of Rs. 40,000 Cr and more.
Integration for value addition characterizes most projects e.g. Refinery-Petrochemicals. The future could see Refining-Petrochemicals-Derivatives and coal gasification integrations.
Increasing complexity and size accompanied by a need to cut implementation time and cost
The net result is a set of major challenges that the Project Owners, Consultants, Contractors and Suppliers have to face jointly and overcome at each stage of a project
-
11 July 2017 6
Key challenges to project implementation
Competitive Environment
Enhanced Project Sizes/ Investments
Compressed Project Schedules
Inadequate Experienced manpower
Limited Number of Resourceful & Experienced Construction Companies
Logistic Constraints /difficult landlocked terrains
Inflexible procedures with limited Leeway for maneuvering Vendor/ Contractor failures
Empowerment , Decentralization of Powers/authority for quick action
-
11 July 2017 7
EPCMLow Cost / Diffused schedule
LSTKHigh Cost/
Large Overall schedule
OBEEPCM costs/
LSTK Schedules
Project
Project Implementation Plan Choices
Implementation Modes Experienced in the recent past
-
11 July 2017 8
Project Implementation Plan EPCM Vs EPC son
-
11 July 2017 9
Project Implementation Plan - Remains a choice
Panipat Refinery Expansion of 6 MMTPA implemented on a Hybridmode. A combination of Conventional and LSTK.
Mega Grass Roots Refineries such as GGSRL 9 MMTPA andBina 6 MMTPA Implemented on Conventional Route
Euro IV Project Set the trend of OBE mode of projectImplementation in Preference to LSTK for major schedule gainstowards the Award Cycle of LSTK
Integrated MRPL Expansion chose an Ultimate Hybrid ofConventional, OBE and LSTK
PNCP 0.8 MMTPA Integrated Complex & Paradeep Refinery chosethe other Extreme of Total LSTK mode of Implementation
Facilities on BOO basis have also been installed
Recent Projects indicate no one way preference
-
11 July 2017 10
Phases of a Project
A Mega Project has the following broad Phases
TAKE OFFENGINEERINGPROCUREMENTMANUFACTURING/ DELIVERYCONSTRUCTIONMC/ COMMISSIONING
Project Implementation Plan has to ensure an approach for Each Phase
-
11 July 2017 11
Take Off / Front end Activities
Process/Front end
Formulation of an Exhaustive Project Design Basis
Early Development of Plot Plan as the mother Document
PFDs/ P&IDs and Dimensioned Equipment Layouts
Process and Engineering Design Basis
Clear Definition of Scope for Deliverables from Licensors
-
11 July 2017 12
Take Off/ Front End Activities
Process/Front end Standardization of Piping Material specifications and Instrumentation
Philosophy with Licensors for minimization of variety and hencereduction in Cost Towards spares while maximizing Interchangeability
Mechanical Design of Static equipment including internals with FirmDefinition of hardware
Complete Thermal design of all the Heat Exchangers and Air coolers forFirm Definition of Hardware
API data sheets and Front end Thermal Design /Conceptual Mechanicaldesign of all Furnaces for Firm Definition of Hardware
Primary selection of pumps to finalize the seal arrangement and flushing/utility connectivity
Clear definition of control System including sizing of all Control valvesand safety valves for Clear Definition of hardware
-
11 July 2017 13
Take Off/ Front End Activities
Front end Detailing
Development of Load list, SLD, Electrical Substation layouts andElectrical System study for Clear definition of hardware
Clear guidelines to perform Residual Basic Engineering including ISBLutility Distribution P&Ids in Units
Dimensioned Equipment layouts incorporating experience fromEngineering considerations & Owners maintenance practices
Hazop Study on P&Ids and evolution of recommendations to beincorporated in design
Finalization of Interfaces for the contractors
Development of Conceptual UG piping System and Generalarrangements with guidelines for Detailed Engineering
-
11 July 2017 14
Take Off/ Front End Activities
Front end Detailing
Safety Audit of the Equipment Layout and Finalization of other safetyRequirements
Development of all Architectural drawings for the Buildings Envisagedincorporating Owners Inputs for Clear definition of requirements
Detailed Equipment Layout Plan and Elevation Sections Drawings
Control System and Specifications Definition for DCS/PLC and Plantsafeguarding system to clearly define the hardware
Overall Layout Drawings for UG Piping System, Cooling water System,Fire water System, Cable layouts for electrical and Instrumentationsystem
Development of Clear Design basis documents for all utility systemsidentifying the Hardware clearly in the documents
-
11 July 2017 15
Engineering
Task force working for synergy in engineering etc. regular Interdiscipline reviews.
Hold management system to be in place.
Majority of front (Drawings/ Material/ Physical) shall be made availableto the civil and structural contractors at the time of mobilization.
Majority of front (Drawings/ Material/ Physical) shall be made availableto the Composite contractor at the time of mobilization.
Piping & Civil/ Structures to be opening batsmen!.
Minimize Mid Course Changes
-
11 July 2017 16
Engineering
Exhaustive 3D model review to avoid surprises/ re-engineering andprocurement of additional material.
MTOs and AFC drawing extraction from Model
IBR (System Isometrics) & Utility System Isometrics to be extractedfrom The Model
Vendors encouraged to be accountable for drawings, fabrication etc.
Building contract shall include all associated infrastructures such asAC system, Lighting, Fire alarm system etc.
Monthly meeting shall be organized with the contractors/ vendors forLong Lead and critical items/ Package.
-
11 July 2017 17
Procurement
ORDERING/ MANUFACTURING/ DELIVERY
Fast track ordering on competitive basis
Zero deviation bid and exhaustive discussion before submission ofbids may be adopted.
Pre Tender/ Pre Bid meetings
Static , Rotating Equipment may be bulked (Bottom line purchase) foravailing advantages of economies of scale
Accuracies of First piping Bulk MTO are critical to Project success
Umbrella contracts for supply of standard equipment Motors/Transformers/ Switchgear etc.
-
11 July 2017 18
Description Columns Vessels Heat Exch
Air Coolers
Compressor Pumps Misc
Unit Nos Nos Nos Nos Nos Nos Nos
CDU/VDU 6 28 47 10 - 47 25
MS Block 17 68 59 11 11 42 27
DHDT 6 24 16 6 2 12 13
DCU 9 23 19 9 1 34 20
VGO HDT 7 34 26 7 3 25 13
PFCC 10 30 45 6 3 49 31
PP 3 31 5 1 5 24 38
U&O 0 17+
64 Tanks
0 0 1 70 9
TOTAL 58 255 217 50 26 303 176
Major Equipment- Typical Refinery
Procurement
Bulk Procurement is the Key
-
11 July 2017 19
Resort to bulking to minimize vendors Bulk material
Procurement
210 km
5 Lakhs
2.2 Lakhs
1.1 Lakhs
(Excl. P/L)
Chart1
168000508752226618114468
39800393733471563
1869403348397
220000513092230313116428
PIPES
FITTINGS
FLANGES
VALVES
Sheet1
PIPESFITTINGSFLANGESVALVESHV CABMV CAB
REFINERY1680005087522266181144683130003900000
COT39800393733471563
PIPE LINE1869403348397
OEVRALL220000513092230313116428
To resize chart data range, drag lower right corner of range.
-
11 July 2017 20
UG Piping material procurement to be prioritized to ensure majormaterial availability prior to the contractor mobilization
Minimize site work- Major fabrication in shop.
ODCs sourcing through PORT based vendors
Across the table review of drawings/ documents.
Composite mechanical contract comprising of Mechanical, piping,electrical, Insulation, painting
3D Modeling Review done at 3 stages
3D Modeling accorded priority and Target Major Engineeringcompletion 9 Months prior to MC
Procurement
-
11 July 2017 21
Construction
Field engineering cell along with associated 3D model software.
Peak manpower deployed on large Projects: 20,000/ Over 50 Millionman-hours
Tenders for Machinery to facilitate construction
Piling Contractors encouraged to use Hydraulic rigs vis--visConventional.
Designs tweaked to suit site conditions- Water Table, Hard Rock etc.
Fabrication Yards
Provision of Extensive Storage Warehouses/ yards
-
11 July 2017 22
Prioritize UG works and pavement to facilitate uninterruptedconstruction works
Modular Construction
Pre-fabricated Manholes, Trenches
Tenders to augment failing contractors
Awards for Safe working
Constructability studies including Rigging studies for ODC andmega lifts
Contractors encouraged to establish fabrication facility (AutoWelding) at site. Provides Large Inch-Dia daily progress.
Construction
-
11 July 2017 23
Engineering design to be Construction Friendly
Monsoon Combat Plan & Designs to be in place for uninterrupted site works
Credentials of perennially non performing vendors to be reviewed
Equipment Tracking (GPS) and Logistic Expertise/ Monitoring system to be improved
Possibility of Swing Contracts for supplementing failing construction agencies to be explored (e.g. Hiring Cranes and Manpower Resources)
Construction
-
11 July 2017 24
Review if Major ODCs could be fabricated at site If space is available.
Typical Past project advantage in Site Fabricated ODCs
Provide Major cranes for Erection and handling of prefabricated RCC /Steel structures and Erection of ODCs.
Major Site fabricated equipment Duration in months
COLUMNS Dia (M) Height (M) Weight (MT) Fabrication time(Ahead of sch.)
CDU 7 67.85 642 3 months
VDU 12 60.3 810 3 months
Coke Chambers 9.1 34 340 2 months delay
Reactor 13.8 62 415 1 months
Regenerator 15.3 25 514 1 months
Construction
-
11 July 2017 25
Work breakdown for Civil work for units and offsite
With Volumes involved- RMC, Batching Plants, Free Issue of Cement & Steel are areas for deliberation
Construction
Chart1
17100
19200
9200
9000
12500
25200
25200
48500
170000
RCC
Sheet1
RCCST STEELSeries 3
CDU/VDU1710054002
MS BLOCK1920037002
DHDT920020003
DCU900021005
VGO HDT125002150
PFCC252006700
PP252002900
OFFSITE485005800
OVERALL17000030750
-
11 July 2017 26
Work breakdown for structural work
With Volumes involved- Free Issue of Steel , Pre fabricated Steel delivered from external shops, Modularization are areas for
deliberation
Construction
Chart1
5400
3700
2000
2100
2150
7200
2900
5800
31250
ST STEEL
Sheet1
ST STEELSeries 3
CDU/VDU54002
MS BLOCK37002
DHDT20003
DCU21005
VGO HDT2150
PFCC7200
PP2900
OFFSITE5800
OVERALL31250
-
11 July 2017 27
MC/ Commissioning
System checks to start 06 months prior to Mechanical Completion for system wise monitoring/ completion/ handover
Extensive Formatting to Checklist and identify the remedial measures
Timely Availability of Utilities (Say N2/ CW/ Steam) to aid schedule
Lining up of specialized agency to facilitate pre-commissioning / commissioning
Adequate spares for last minute use
Vendors on standby/ call for Commissioning assistance
-
11 July 2017 28
Key Strategies - Schedule
Target schedule shall be at least 2-3 months before the contractualschedule.
Integrated Project Master Schedule, integrating all the workpackages level detailed schedules from Major Contractors, Vendors
Critical Path & Near Critical path analysis at regular intervals usingPrimavera software
Multi-tiered Project review system Daily / Weekly meetings with Key Contractors Monthly progress review meetings by Senior Management
War Room approach for Project Monitoring & Control Extensive reporting systems with regular Management reviewsand meetings
-
11 July 2017 29
Key Strategies - Schedule
Long Lead and Critical Activities to be always in focus
Bonus and incentive scheme to encourage vendors/ contractors toimprove delivery.
Long lead items shall be floated with preliminary data which shall beupdated through amendments before award.
Across the Table Drawing approvals to expedite Manufacture anddelivery
-
11 July 2017 30
Cost Monitoring / Management
Ensure clear / succinct inputs for costing
Consolidate all previous project data through database system
Cost Status Reports to be monitored closely for analysis, feedback and corrective action
Value based engineering for optimization, standardization and effective solutions
Close vigil on SOR quantities to restrict variation and exercise schedule control
Monitor variations in rates of Inputs, FE, Taxes/ Duties etc.
-
11 July 2017 31
VENDORS CONTRACTORS
PROJECT MANAGEMENT
OWNER MANAGEMENT
CONFIGURATION & DESIGN BASIS
PROCESS DESIGN
DETAIL ENGG.
BID PACKAGE &
CONTRACTOR SELECTION
FRONT END ENGG
EQUIPMENT DELIVERIES
CONSTRUCTION
COMMISSIONING & HANDING OVER
EXTERNAL LINKAGES INCLUDING STATUORY
Project Management
Managing all players and Meeting All Challenges !
-
11 July 2017 32
Conclusion Large projects increasing in Complexity Resources are an
imperative
All Phases are critical i.e. Pre-Project/ Engg. / Proc. / Const.
Increased standardization, coupled with Proper planning and appropriate Project controls can help to mitigate the challenges
Good Project definition is the key to meeting time and cost
Success depends on use of Key Past Learnings and preparedness for eventualities
Collaborative approach will work(Vendors & Contractors- Partners in progress)
-
11 July 2017 33
Thanks for your patience
Slide Number 1Slide Number 2OverviewOverviewOverviewKey challenges to project implementationSlide Number 7Project Implementation Plan EPCM Vs EPC sonProject Implementation Plan - Remains a choicePhases of a Project Take Off / Front end ActivitiesTake Off/ Front End ActivitiesTake Off/ Front End ActivitiesTake Off/ Front End ActivitiesEngineeringEngineeringProcurement Procurement Slide Number 19Slide Number 20 Construction Construction Construction Construction Construction Construction MC/ CommissioningKey Strategies - ScheduleKey Strategies - ScheduleCost Monitoring / Management Slide Number 31ConclusionSlide Number 33