Engineering the power system of the future
-
Upload
emmaroche -
Category
Environment
-
view
205 -
download
5
description
Transcript of Engineering the power system of the future
Joe Corbett
Head of Technology,
Mainstream Renewable Power
The Why
Mega-Trend #1 : Exploding Population
Leaping Asia, Crouching Europe
Mega-Trend #2 : Exploding Energy Demand
Oil Price rose by 1,600 % 1997 – 2007 : will it do it again ?
In a world of 15 Billion microprocessors
Mega-Trend #3 : Democratised IT for 5 billion users
The Future is already here, only it is not evenly distributed William Gibson
Mega-Trend #4 : The Internet of Everything
1500 AD, China is #1. 2030 AD, China is #1
Mega-Trend #5 : China is Back
Power Demand Europe 2050 (Climate Foundation Road Map)
Context
Coal26%
Nuclear26%
Gas24%
Hydro15%
Wind3%
Oil3%
Biomass2%
Waste1%
Solar PVGeothermal
• Energy Security
• Sustainability
• Economic Development
• GHG Reduction
Source: IEA
Drivers for Change – Europe’s Electricity Fuel Mix (2008)
Debate?
S. & Cent. America
1%
Azerbaijan1% Kazakhstan
2%
Russian Federation
33%
Turkmenistan2%
Uzbekistan3%
Africa15%
Middle East8%
Western Europe
35%
• Remove Coal
• Nuclear Debate
• Increase Renewables
• Secure Supplies
• Invest in Transmission
Constraints
• Regulation
• Public Opposition
• Onshore Wind
• Overhead Lines
Europe Gas Sources 2010Source: BP
Offshore Wind Resource
Offshore Wind in the North Sea represents Europe’s best option
• Europe’s Power Demand
• EU27 Demand (2008): 3,200 TWh
Offshore Wind Power Available
Area considered with 5MW/Km2
North Sea: 35,700,000 MW
Mediterranean Sea: 12,500,000 MW
Total 48,200,000 MW
Equates to: 161,000 TWh
Conclusion :
Demand 3,200 TWh
Supply 161,000 TWh
Supply v Demand x 50
Mr Brian Hurley, Wind Site Evaluation Ltd.
Offshore Wind Resources in Europe
Marseilles, March 2009
Offshore Wind in the North Sea can meet Europe’s need, 50 fold
Europe’s Electricity Demand
The What
Wind50%
Solar30%
Other Renewables10%
Nuclear10%
> 80 % of Generation Capacity will be from Wind & PV
Energy Demand
Offshore Winds farms are needed to meet EU’s 2020 energy targets
Interconnection across EU, or Supergrid is vital for delivery of any 2050 scenario
EU Energy Perspective: 2050 Mix
Portfolio
Year 2020 2030 2040 2050
Total Demand -
GW
422 468 502 548
% Renewable
Sources
28% 45% 63% 80%
PN - GW 21.9 78.3 174 322
Installed Wind
Capacity - GW
50 150 330 600
DSM ≤ 1% 5% 10% 15%
Storage ≤ 1% ≤ 1% ≤ 2% ≤ 2%
“Backup” Power
from other plant,
GW
0.16 0.74 1.73 3.43
Source: Managing Future Offshore Wind Power Variability in a European Supergrid
Supergrid
• Fuel Portfolio 2050
• Internal Market
• Energy Security
• Carbon Reduction
• Studies• Climate Foundation
• Offshore Grid Study
• ENTSO-E Highways
• German Grid Plan
• NSCOGIClimate Foundation Roadmap 2050
Possible Outcomes
Business as Usual Integrated Vision
Offshore Interconnection
Cost Savings (Integrated v Radial)
•Offshore Grid Report•Save up to €21b over 25 years
•Offshore Transmission Network Feasibility Study
•NGET + CE
•Save £6.9b by 2030
Offshore Grid; Offshore Electricity Grid Infrastructure in Europe, A Techno-EconomicAssessment; 3E (coordinator); Final Report, October 2011
We choose to go to the moon in this decade and do the other things, not because they are easy, but because
they are hard, because that goal will serve to organize and measure the
best of our energies and skills, because that challenge is one that we are
willing to accept, one we are unwilling to postpone, and one which we intend
to win.
President John F. Kennedy - September 12, 1962
Vision
• Offshore Wind
• Solar
• Vision• Interconnection
• Demand Side Management
• Storage
Vision Drives Plans. Not Vice Versa
Fuel Portfolio
The How
Imaging the future in 1959 wasn’t easy, it is still difficult.....
The Future
Technology and Innovation
25
Bigger, better turbines are needed
Turbines will get bigger : 20 MW Floating Turbines will be viable
Source: Dr Eddie O’Connor, Mainstream Renewable Power
C & F Offshore Summit
London, April 2009
Source: Garrad Hassan
Wind Turbines
0 200 400 600 800 10000
500
1000
1500
400 kV AC line320 kV dc line
Distance in km
Po
wer
in M
W
.
Overhead Cables SubSea Cables
400 kV AC line
320 kV
DC line
Three 400 kV AC cables
Two 320 kVDC cables
75 km land cable
128 km sea cable
400 MW offshoreconverter
400 MW converter
HVDC Transmission
Cables Today
● AC Application● SCFF - 500kV / 1,200 MW● XLPE - 500kV / 1,000 MW
● DC Application● Mass-Impregnated (MI)
● 500kV / 1,600 MW Installed● 600kV / 2,200 MW Awarded
● Extruded (XLPE)● 200kV / 400 MW Installed● 320kV / 900 MW Awarded
● SCFF● AC/DC● Short Lengths
28
GIL / Storage
● Gas Insulated Lines
● AC up to 550kV
● DC in Development
● Storage
● Inertia● Small Scale at Converter
Level
● System Reserves● Medium Scale
● Flywheels/Batteries
● Large Scale
● Hydro
29
Grid Design
Friends of the Supergrid Technical Working Group
DC Breakers
•Resonance
•Power Electronics•Full Bridge Conversion
•Ballistic Breaker
•Superconductor
•Hybrid
•Plasma
Ballistic Breaker™
Roger Faulkner :Ballistic Breaker Corporation
Long Distance Transmission
•HVDC
•Overhead Lines•Permitting/Consent
•Cables (>100 Years Old)•MI = 800kV
•XLPE = 500kV
•No. Joints
•Drilling / Tunnelling
•GIL
•Elpipes
•Research
Roger Faulkner: LONG DISTANCE UNDERGROUND HVDC TRANSMISSION VIA ELPIPES (ICHVE 2010)
Baker Hughes
Technology Development (Friends of the Supergrid – Technical Working Group)
● Increased power ratings for VSC (1,000 MW at 320 kV DC)
● Demonstrators for DC side fault clearing (e.g. DC Circuit Breakers)
● DC 320 kV cables with extruded insulation in operation at different onshore and offshore projects (500 MW per cable)
● DC cables with extruded insulation >320 kV developed
● MI-PPL 600kV (1.1GW per cable) developed and higher voltages in development
● MI >500 kV cable developed
● AC GIL in operation
● Standardization work for HVDC grids in CIGRÈ, CENELEC started
Today – 2015 (Supergrid Preparation Phase)
2015 – 2020 (Supergrid Phase 1)
After 2020 (Supergrid Phase 2)
● DC cables with extruded insulation >320 kV in operation
● MI-PPL 600kV cable in operation
● MI >500kV in operation
● Development of new extruded insulation compounds for HVDC cables
● System for fast selective fault detection in HVDC networks
● DC side selective fault clearing and system reconfiguration
● Hierarchical control architecture for integrated AC and DC Grid in Europe
● Demonstrators for DC/DC Converter
● Further Development of MI and MI-PPL Cables
● HVDC cables with new extruded insulation compounds in operation
● Superconducting cables
● DC GIL
● DC/DC converter
Project Load
7000 – 10 000 tonnes
Crane Capacity
1 000 tonnes
Mr Fenno Leeuwerke, Hochtief Construction
Building at Sea and 3rd Generation of Ships
Marseilles, March 2009
Bigger, stronger Jack-up Technology
Next Generation Civil Engineering
Offshore wind Jack-up
Floating Foundations
<35m 25m-50m >45m
Monopile<35m <3.6MW
Jacket/Gravity Base25-50m, <6MW
Floating Structures>45m, 5-10MW
Floating Structures>100m, 5-10MW
Windfloat – Agucadorca, Portugal
Water Depth: 40m-50m
Distance from Shore: 5km
Vestas 2MW turbine installed and commissioned onshore
Bigger Ships for bigger loads
Mr Fenno Leeuwerke, Hochtief Construction
Building at Sea and 3rd Generation of Ships
Marseilles, March 2009
New Construction Vessels
Requirements for UK’s Offshore Plans;
• Develop two completely new ports
• One on either coast of the UK
• More than transport nodes
• Focal point for regional development
• Centres of excellence for R + D
• Training centres for technologists/technicians
• New manufacturing centres
Dr Eddie O’Connor, Mainstream Renewable Power
C & F Offshore Summit
London, April 2009
Ports and Logistics
An entirely new approach to Logistics is needed
Control and Information
SuperNode Control
AC Control & Protection
Smart Meter
Source: Sustainable Energy Horizon Panel report
Information Technology
Surveying & Modelling the Sea
Power Distribution Management
SuperNode Power Controls
Monitoring & Controlling RiskHigh Speed Wireless Comms
Wind Turbine Control Systems
The Who
Energy Bridge Context
Concept Design 1
● Two technical solutions considered:
● Concept Design 1
● Concept Design 2
● CD1 – symmetric monopole: ±320kV XLPE HVDC Cable
Any outage results in the loss of the system as a whole
Concept Design 2
● CD2 – bipole: ±600kV MI HVDC Cable
Any outage results in the loss of 50% of the system
The Results
● Base Case
● Sensitivity Analysis
● Reduction in CAPEX
● Variation of Capacity Factor (positive and negative)
● Variation of Gearing Ratio (positive and negative)
● Increase of Availability (e.g. spare trafo at site)
Line of Sight Concept Design 1 Concept Design 2
1 GW
2 GW
3 GW
4 GW
5 GW
The Results – TUoS
1 2 3 4 5
TUO
S (€
/MW
H)
LINE OF SIGHT (GW)
BASE CASE
Concept Design 1 Concept Design 2
Projects of Common Interest and SuperNode
The SuperNode Concept, developed by MainstreamCentral to Meshed Grid Design
Mainstream Initiatives
Friends of the Supergrid
SuperNode• Low Voltage Model
• Medium Power Pilot (H2020)
• TEN-E-Funding
• SuperNode Concept Design and Scale Model
PowerTube
International Bodies Working Groups
North American Path to the Creation of a Supergrid
Dr. Eddie O’ConnorCEO and Founder, Mainstream Renewable Powerwww.mainstreamrp.com
WINDPOWER 2010Dallas, TX
May 25th 2010
Inventing the Future
Insanity: doing the same thing over and over again and expecting different results.
— Albert Einstein—
There are those who look at things the way they are, and ask why... I dream of things that never were, and ask why not?
— Robert Kennedy —
Source: Microsoft
We are on a once off transition to sustainability
Joe CorbettHead of Technology