Engineering, Construction and Architectural

168
ISSN 0969-9988 Volume 25 Number 2 2018 Engineering, Construction and Architectural Management

Transcript of Engineering, Construction and Architectural

Page 1: Engineering, Construction and Architectural

En

gin

ee

ring

, Co

nstru

ctio

n an

d A

rch

itec

tural M

anag

em

en

tV

olu

me

25

Nu

mb

er 2

20

18e

me

raldp

ub

lishin

g.c

om

www.emeraldinsight.com/loi/ecam

Volume 25 Number 2 2018ISSN 0969-9988

Volume 25 Number 2 2018

Engineering, Construction and Architectural

Management

Engineering, Construction and Architectural Management

Quarto trim size: 174mm × 240mm

Number 2

133 Editorial boards

134 Planning and controlling design in engineered-to-order prefabricated building systemsJosana Gabriele Bolzan Wesz, Carlos Torres Formoso and Patricia Tzortzopoulos

153 Construction manager’s technical competencies in Malaysian construction projectsAbd Halid Abdullah, Siti Khalijah Yaman, Hairuddin Mohammad and Padzil Fadzil Hassan

178 Conflicts and management styles in the Sri Lankan commercial building sectorChathuri Gunarathna, Rebecca Jing Yang and Nirodha Fernando

202 An analysis of the delivery challenges influencing public-private partnership in housing projects: the case of TanzaniaNeema Kavishe, Ian Jefferson and Nicholas Chileshe

241 A comparison of the suitability of FIDIC and NEC conditions of contract in Palestine: a perspective from the industryHaytham Besaiso, Peter Fenn, Margaret Emsley and David Wright

257 Understanding why Chinese contractors are not willing to purchase construction insuranceJunying Liu, Sen Lin and Yingbin Feng

273 Priming effects on safety decisions in a virtual construction simulatorXueqing Lu and Steven Davis

295 Book review

Page 2: Engineering, Construction and Architectural

EDITOR-IN-CHIEFProfessor Chimay J. AnumbaThe University of Florida, USAE-mail [email protected]

SPECIALITY EDITORProfessor Antony ThorpeLoughborough University, UK

EMERITUS EDITORProfessor Ronald McCafferLoughborough University, UK

DEPUTY EDITORSDr Timo HartmannTechnische Universitaet Berlin, GermanyE-mail [email protected] Dr Geoffrey Qiping Shen Hong Kong Polytechnic University, Hong KongE-mail [email protected] Derek ThomsonLoughborough University, UKE-mail [email protected]

EDITORIAL ASSISTANTMs Nancy SmithThe Pennsylvania State University, USAE-mail [email protected]

ISSN 0969-9988© 2018 Emerald Publishing Limited

Emerald Publishing LimitedHoward House, Wagon Lane, Bingley BD16 1WA, United KingdomTel +44 (0) 1274 777700; Fax +44 (0) 1274 785201E-mail [email protected] more information about Emerald’s regional offices please go to http://www.emeraldgrouppublishing.com/officesCustomer helpdesk :Tel +44 (0) 1274 785278; Fax +44 (0) 1274 785201E-mail [email protected], subscription and missing claims enquiries:E-mail [email protected] +44 (0) 1274 777700; Fax +44 (0) 1274 785201

Missing issue claims will be fulfilled if claimed within six months of date of despatch. Maximum of one claim per issue.Hard copy print backsets, back volumes and back issues of volumes prior to the current and previous year can be ordered from Periodical Service Company. Tel +1 518 537 4700; E-mail [email protected] For further information go to www.periodicals.com/emerald.html

Reprints and permissions serviceFor reprint and permission options please see the abstract page of the specific article in question on the Emerald web site (www.emeraldinsight.com), and then click on the “Reprints and permissions” link. Or contact:E-mail [email protected] Publisher and Editors cannot be held responsible for errors or any consequences arising from the use of information contained in this journal; the views and opinions expressed do not necessarily reflect those of the Publisher and Editors, neither does the publication of advertisements constitute any endorsement by the Publisher and Editors of the products advertised.

No part of this journal may be reproduced, stored in a retrieval system, transmitted in any form or by any means electronic, mechanical, photocopying, recording or otherwise without either the prior written permission of the publisher or a licence permitting restricted copying issued in the UK by The Copyright Licensing Agency and in the USA by The Copyright Clearance Center. Any opinions expressed in the articles are those of the authors. Whilst Emerald makes every effort to ensure the quality and accuracy of its content, Emerald makes no representation implied or otherwise, as to the articles’ suitability and application and disclaims any warranties, express or implied, to their use.

Emerald is a trading name of Emerald Publishing LimitedPrinted by CPI Group (UK) Ltd, Croydon, CR0 4YY

Certificate Number 1985ISO 14001

ISOQAR certified Management System,awarded to Emerald for adherence to Environmental standard ISO 14001:2004.

Engineering, Construction and Architectural Management is indexed and abstracted in:ABI InformBritish LibraryBusiness SourceConstruction Management AbstractsConstruction and Building AbstractsEBSCO Discovery ServiceExecutive Daily BriefICONDA (International construction database)INSPECInternational Civil Engineering Abstracts DatabaseProQuestScopus

Engineering, Construction and Architectural Management has been awarded the distinction of CIB Encouraged Journal by the International Council for Research and Innovation in Building and Construction (CIB)

Quarto trim size: 174mm × 240mm

Guidelines for authors can be found at:www.emeraldgrouppublishing.com/ecam.htm

Page 3: Engineering, Construction and Architectural

EDITORIAL ADVISORY BOARD

Professor David ArditiIllinois Institute of Technology, USA

Professor Dongping FangTsinghua University, People’s Republic of China

Dr Scott FernieLoughborough University, UK

Professor Carl HaasUniversity of Waterloo, Canada

Professor Makarand HastakPurdue University, USA

Professor Edward JaselskisNorth Carolina State University, UK

Professor Mohan KumaraswamySri Lanka

Professor Martin LoosemoreUniversity of New South Wales, Australia

Professor Muhd Zaimi MajidUniversiti Teknologi, Malaysia

Professor George OforiNational University of Singapore, Singapore

Professor Stephen OgunlanaHeriot-Watt University, UK

Professor Steve RowlinsonThe University of Hong Kong University, Hong Kong

Professor Sevil SariyildizYasar University, Turkey

Professor Lucio SoibelmanUniversity of Southern California, USA

Professor Koshy VargheseIndian Institute of Technology Madras, India

Professor Ron WakefieldRoyal Melbourne Institute of Technology, Australia

Professor Jan WiumStellenbosch University, South Africa

EDITORIAL REVIEW BOARD

Professor Brucu AkiniCarnegie Melon University, USA

Dr Burcin Becerik-GerberUniversity of Southern California, USA

Dr Ioannis BrilakisCambridge University, UK

Dr Tanyel BulbulVirginia Polytechnic and State University, USA

Dr Jack ChengHong Kong University of Science and Technology,Hong Kong

Dr Yong ChoGeorgia Institute of Technology, USA

Professor Mohammed DulaimiUnited Arab Emirates

Dr Nora ElgoharyUniversity of Illinois, Urbana-Champaign, USA

Dr HQ FanHong Kong Polytechnic University, Hong Kong

Professor Carlos FormosoUniversidade Federal do Rio Grande do Sul, Brazil

Dr Mani Golparvar-FardUniversity of Illinois, Urbana-Champaign, USA

Professor Raymond IssaUniversity of Florida, USA

Dr John KamaraUniversity of Newcastle, UK

Professor Vineet KamatUniversity of Michigan, UK

Professor Bimal KumarGlasgow Caledonian University, UK

Dr Samuel LaryeaUniversity of the Witwatersrand, South Africa

Dr Fernanda LeiteUniversity of Texas at Austin, USA

Dr Ken-Yu LinUniversity of Washington, USA

Professor Patrizia LombardiUniversity of Torino, Italy

Dr Jasper MbachuMassey University, New Zealand

Dr Carol MenassaUniversity of Michigan, USA

Professor John MessnerPennsylvania State University, USA

Dr Wafaa NadimThe German University in Cairo, Egypt

Professor S. Thomas NgThe University of Hong Kong, Hong Kong

Dr Yasemin NielsenHeriot-Watt University Dubai, United Arab Emirates

Dr Bhzad SidawiUniversity of Dammam, Saudi Arabia

Professor Ming SunHeriot-Watt University, UK

Dr Hai Chen TanHeriot-Watt University Malaysia, Malaysia

Professor Wellington ThwalaUniversity of Johannesburg, South Africa

Professor Xiangyu WangCurtin University, Australia

Professor Jennifer WhyteUniversity of Reading, UK

Dr Rebecca YangRMIT University, Australia

Engineering, Construction andArchitectural Management

Vol. 25 No. 2, 2018p. 133

r Emerald Publishing Limited0969-9988

133

Editorialboards

Quarto trim size: 174mm x 240mm

Page 4: Engineering, Construction and Architectural

Planning and controlling designin engineered-to-order

prefabricated building systemsJosana Gabriele Bolzan Wesz and Carlos Torres Formoso

NORIE (Building Innovation Research Unit),Universidade Federal do Rio Grande do Sul, Porto Alegre, Brazil, and

Patricia TzortzopoulosSchool of Art, Design and Architecture,

University of Huddersfield, Huddersfield, UK

AbstractPurpose – The purpose of this paper is to propose a model for planning and controlling the design process incompanies that design, manufacture and assemble prefabricated engineer-to-order (ETO) building systems.This model was devised as an adaptation of the Last Planner® System for ETO multiple-project environments.Design/methodology/approach – Design science research, also known as prescriptive research, was themethodological approach adopted in this research. An empirical study was carried out at the designdepartment of a leading steel fabricator from Brazil, in which the proposed model was implemented in sixdifferent design teams.Findings – The main benefits of the proposed model were shielding design work from variability,encouraging collaborative planning, creating opportunities for learning, increasing process transparency, andflexibility according to project status. Two main factors affected the effectiveness of the implementationprocess commitment and leadership of design managers, and training on design management and projectplanning and control core concepts and practices.Research limitations/implications – Some limitations were identified in the implementation process:similarly to some previous studies (Ballard, 2002; Codinhoto and Formoso, 2005), the success of constraintanalysis was still limited; some of the metrics produced (e.g. ABI, causes of planning failures) have not beenfully used for process improvement; and systematic feedback about project status was not properlyimplemented and tested.Originality/value – The main contributions of this study in relation to traditional design planning andcontrol practices are related to the use of two levels of look-ahead planning, the introduction of a decouplingpoint between conceptual and detail design, the proposition of new metrics for the Last Planner® System, andunderstanding the potential role of visual management to support planning and control.Keywords Engineer-to-order, Design process, Last planner system, Planning and control, Design teams,Prefabricated building systemsPaper type Research paper

IntroductionDespite the importance of the design process for the success of construction projects, it iswidely recognized that not enough attention is given to design planning and control in thisindustry (Choo et al., 2004; Tribelsky and Sacks, 2010; El Reifi and Emmitt, 2013). Designplans are often limited to a list of design deliverables, produced at the beginning of designprocess (Choo et al., 2004). The ineffectiveness of design planning and control results in poorcoordination between disciplines, unbalanced resource allocation, insufficient informationavailable to complete design tasks and delays in the delivery of design information to

Engineering, Construction andArchitectural ManagementVol. 25 No. 2, 2018pp. 134-152Emerald Publishing Limited0969-9988DOI 10.1108/ECAM-02-2016-0045

Received 13 February 2016Revised 2 July 20164 January 2017Accepted 16 June 2017

The current issue and full text archive of this journal is available on Emerald Insight at:www.emeraldinsight.com/0969-9988.htm

© Josana Gabriele Bolzan Wesz, Carlos Torres Formoso and Patricia Tzortzopoulos. Published byEmerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article ( forboth commercial & non-commercial purposes), subject to full attribution to the original publication andauthors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode

134

ECAM25,2

Quarto trim size: 174mm x 240mm

Page 5: Engineering, Construction and Architectural

downstream processes, among other problems (Koskela et al., 2002; Ballard, 2002; Tribelskyand Sacks, 2010).

Indeed, design planning and control is often carried out informally (Tzortzopouloset al., 2001; Koskela et al., 2002). This is partly due to the fact that traditional constructionplanning techniques, such as work breakdown structure, critical path method andearned-value method, tend to be ineffective for design (Austin et al., 1994). Thosetechniques are not able to cope with the high level of uncertainty and the iterative natureof design and the complex interdependences that exist amongst design disciplines (Austinet al., 2010; Koskela et al., 2002). In fact, iterative processes are necessary and beneficial asthese may add value to a project, but should be controlled in order to avoid seriousimplications in time and cost (Knotten et al., 2015).

The ineffectiveness of design planning and control tends to be more critical in complexprojects, i.e. projects that have a high level of structural complexity (e.g. large number ofstakeholders and interdependent components) (Baccarini, 1996) and uncertainty related togoals or methods (Williams, 1999). Those projects demand closer integration and bettercollaboration between construction project participants, especially at the design process(Emmitt and Ruikar, 2012).

Engineer-to-order (ETO) prefabricated building systems can be regarded as complexprojects as the customer order penetrates into the design phase of a product, that needs to beconceived, manufactured and assembled to be delivered to the client (Gosling and Naim,2009). Bertrand and Muntslag (1993) pointed out that a high level of uncertainty exists inETO environments as it is necessary to define delivery dates when the customer order isplaced, even though the product is not completely defined yet.

The integration of planning and control processes from different project stages, such asconceptual design, detail design, fabrication and site assembly, plays a key role in themanagement of ETO prefabricated building systems. Such integration is important becausethe project lead-time is usually short, requiring some degree of overlapping between projectstages. Ideally, both the design and the production of prefabricated components should bepulled from the site assembly process (Bulhões and Picchi, 2008) in order to keep a low levelof work-in-progress, as well as to consider demand variability that typically exists in siteassembly (Viana et al., 2013).

Moreover, in large construction projects complexity is also caused by design changesthat are demanded by clients and designers after production has already started (Matt,2014). This is partly due to the fact that large projects often involve many stakeholders, sothe ability to coordinate changes across multiple companies is essential to avoid delays(Mello et al., 2015).

A number of planning and control approaches for the design process have been proposedin the literature. Some studies have devised prescriptive models for the whole productdevelopment process (PDP) of construction projects, including the design process (e.g.Kagioglou et al., 2000; Formoso et al., 2005). However, those models represent productdevelopment at a high level, providing simply an overview of this process, and their use as areference for planning and control is limited by the fact that they contain very little detail(Tzortzopoulos et al., 2001). Austin et al. (2010) suggest the use of the Design StructuredMatrix, originally developed by Eppinger et al. (1994), as a core design planning technique.Although this technique is useful for sequencing design activities and identifying designclusters, it has some limitations, such as the little emphasis on control, and the fact thatfairly detailed plans need to be generated in the early stages of the process, demandingmuch effort for revising plans (Tzortzopoulos et al., 2001).

Several researchers have reported on successful implementations of the Last Planner®System of Production Control (LPS) in the design process (Hamzeh et al., 2009; Ballard et al.,2009; Kerosuo et al., 2012). Some of the core ideas of LPS seem suitable for the context of

135

Planning andcontrolling

design

Page 6: Engineering, Construction and Architectural

ETO prefabricated building systems: collaborative and decentralized planning seem to bemore adequate in highly complex projects (Williams, 1999); it is possible to haveconfirmation points at the look-ahead planning level, based on information collected indownstream processes in order to deal with uncertainty in demand (Viana et al., 2013);planning and control can be undertaken in a hierarchically organized set of meetings(Hamzeh et al., 2009), making it possible to integrate planning and control among differentprocesses and managerial levels.

However, there seems to be several gaps in the implementation of LPS in the designprocess, such as: the need to make design planning and control more systematic(Koskela et al., 2002; Hamzeh et al., 2009); the lack of success in implementing look-aheadplanning for design (Ballard, 2002; Codinhoto and Formoso, 2005); the need to increaseprocess transparency and, consequently, the involvement of planning team members(Tzortzopoulos et al., 2001); and the need to devise metrics for assessing the impacts of LPSon the design process (Hamzeh et al., 2009). Moreover, none of the previous studies haveinvestigated the implementation of LPS for ETO prefabricated building systems in amultiple-project environment.

The aim of this research is to propose a model for planning and controlling the designprocess in companies that design, manufacture and assemble ETO prefabricated buildingsystems. This research is relevant due to the need to make the design process in thosecompanies more reliable, by improving the effectiveness of the planning and controlprocess. The model was devised as an adaptation of the LPS for the design process in ETOmultiple-project environments, exploring the need to cope with the high degree ofvariability, to have a short lead-time, as well as to keep a low level of work-in-progress.

Design planning and control in ETO production systemsA common mistake in devising planning and control systems for the design process is toneglect the nature of the design activity, which makes it very different from production.

First, there is much more uncertainty and variability in design. Although it is oftenpossible to take some steps toward improving the initial definition of the problem, byquestioning the client and collecting data, some of the customer needs cannot be easily madeexplicit (Crosby, 1995). Moreover, there are usually conflicting requirements, demanding aneffort to manage trade-offs, and some decisions must be made without complete information(Kamara et al., 2002).

Second, there is much more iteration in design, as the attention of the designer oscillatesbetween understanding a problem and search for a solution (Austin et al., 2010; Cross, 2008).Although there is a hierarchical structure of decisions, from overall concepts to details, mostdesigners move freely between different levels of detail, especially in the early stages ofdesign (Cross, 2008).

Third, design work tends to expand to the time available (Reinertsen, 2009). As a result,design tasks tend to be finished either on time or late: if a satisfactory solution is foundearly, then the available time is used to refine the solution (Ballard, 2000).

Therefore, the development of planning and control systems for design must considerthat this is an ill structured, solution-focused, highly iterative and opportunistic process, andthat the steps for producing a design solution cannot be pre-established at a very fine levelof detail (Cross, 2008).

In ETO production systems, as products are custom-made and one-of-a-kind, there arethree main types of uncertainties (Bertrand and Muntslag, 1993): as the product needs to beengineered at the start of a project, some decisions, such as capacity, lead-time, and priceneeds to be taken under uncertainty; it is difficult to make a detailed demand forecast interms of mix and volume; and it is also difficult to make an estimation of the type andamount of resources required.

136

ECAM25,2

Page 7: Engineering, Construction and Architectural

One way of dealing with uncertainty in planning and control systems is to establishdifferent hierarchical levels. The literature often suggest three planning levels: long-termplanning, which is concerned with setting objectives (Laufer and Tucker, 1987);medium-term planning, which is mostly concerned with the means for achieving thoseobjectives, such as determining what to work on, and who will work on it, within existingconstraints (Ballard, 2000); and short-term planning, which addresses control by takingwhatever actions are required to ensure that the system continues to function toward itsgoal (Hopp and Spearman, 2008).

Different planning horizons imply distinct planning frequencies, modeling assumptions andlevels of detail (Laufer and Tucker, 1987). A major challenge in any planning and control systemis to keep consistency between different decision making levels. In fact, its effectiveness dependson how well it coordinates the different planning horizons (Hopp and Spearman, 2008). Anotherimportant aspect is to define which processes will be pushed (release of work based on forecasts)and which ones will be pulled (based on system status) (Hopp and Spearman, 2008).

One of the key practices for managing the design process in ETO production systems isthe reduction of design batch sizes, especially at the detail design phase. This allowsdesigners to work simultaneously and iteratively, reducing the total design lead-time(Reinertsen, 2009). This approach contrasts with the traditional sequential design processthat is often adopted in construction projects, in which designers are used to work in largebatches, usually represented by a pack of design documents (Ballard, 2000). According toReinertsen (2009), large design batches often result in a large amount of work-in-progress,especially in multiple-project environments.

The LPS is a planning and control model that attempts to deal with uncertainty andcomplexity by involving crew leaders and lower level management in decision-making(Ballard and Howell, 1997). It can be considered as a combination of pull and push planning.At the end of the short-term planning cycle, an overall assessment of planning effectivenessis carried out, by using an indicator named percent plan complete (PPC), proposed byBallard and Howell (1997). This is the rate between the number of assignments concludedand the total number of scheduled work packages. The root causes for the non-completion ofwork packages are identified, so that corrective measures can be implemented.

Research methodDesign science research, also known as prescriptive research, was the methodologicalapproach adopted in this study. It is a way of producing scientific knowledge that involves thedevelopment of an artifact to solve a real problem (Holmström et al., 2009). In contrast withtraditional descriptive research, in which theories need to be validated, this artefact must beassessed against criteria of value or utility (March and Smith, 1995). In this research, theproposed artefact is a model that can be used as a reference for devising design planning andcontrol systems for companies that deliver ETO prefabricated building systems.

This research process was carried out in close collaboration and engagement of themanagerial staff of a company, being conducted through a strategy similar to actionresearch. As suggested by Järvinen (2007), this type of action research project fits very wellthe design science research approach.

This company is a leading steel fabricator in Latin America. It had more than 2,000workers, three manufacturing plants, and around 200 simultaneous contracts. This studyfocused on light steel structural systems for warehouse and industrial buildings.

Figure 1 presents an outline of the research design. Phase 1 (October 2011 to April 2012)aimed to understand the existing company process (e.g. metrics, difficulties in performing thework, and compliance with design deadlines) as well as to identify opportunities for improvingthe design planning and control process. In Phase 2 (May 2012 to January 2013), an initialversion of the model was devised and implemented with two detail design teams (T1 and T2).

137

Planning andcontrolling

design

Page 8: Engineering, Construction and Architectural

Due to the initial results achieved by those two teams, the company decided to start atraining program devised by the research team, and had the participation of technicalstaff from the Engineering Design Department (EDD), Planning Department, and CostEstimating Department (overall around 50 people). The scope included design management,planning and control and client requirements management.

In Phase 3 (December 2012 to March 2013), the model was revised, and its implementationwas extended to four other design teams, two involved in conceptual design (T3 and T4), andtwo involved in detail design (T5 and T6). Phase 4 (February to October 2013) focused on theconnections between design planning and control and other planning systems in use by thecompany, aiming to enhance the final version of the model. At this stage, visual managementboards were used to support decision-making. The results of the implementation werediscussed in a set of five workshops, carried out along the research project.

At the end of Phase 4, a protocol was devised to assess the degree of implementation of14 planning and control practices (see results in Figure 7) – that protocol was jointly devisedand applied by the research team and design managers from the company. At the end of thisstage, as suggested by March and Smith (1995) and Holmström et al. (2009), the benefits andlimitations of the model were assessed based on two main constructs, utility andapplicability. Those constructs were further divided into evaluation criteria: applicability:effort involved in planning meetings, and understanding of planning and control practices;and utility: shielding design work from variability, encouraging collaborative planning,creating opportunities for learning, increasing process transparency and providingflexibility according to project status.

Table I summarizes the sources of evidence used in each research phase.

Workshop 3

a. Finding aproblem

b. Obtaining anunderstanding

c. Developing asolution

d. Implementing asolution

e. Assessing itspractical contribution

f. Assessing itstheoretical contribution

Phase 1

Phase 3

Phase 4

Understanding Development Analysis

Ineffective designplanning and controlin ETO environments

Theoreticalbackground

Data collection(company)

Data collection(T3 -T4 -T5 -T6)

Modelimplementation(T3 -T4 -T5 -T6)

Revise model

Workshop 2

Cross-analysis ofresults

Data collection(design department)

Contributions ofthe proposed

model

Modelimplementation

(design department)

1st model evaluation

Workshop 4

Phase 2 Data collection(T1 -T2)

Devise model,based on previous

studies

Modelimplementation

(T1 -T2)

Workshop 1Model refinement

Model refinement

Literature review

Team 1 (T1)/Team 2 (T2)/Team 3 (T3)/Team 4 (T4)/Team 5 (T5)/Team 6 (T6)

2nd model evaluation

Workshop 5

Model refinement

Figure 1.Outline of theresearch design

138

ECAM25,2

Page 9: Engineering, Construction and Architectural

Existing planning and control systemThe company’s PDP comprised the following processes: sales, cost estimating, engineeringdesign (divided into conceptual and detail design), fabrication, and assembly.

The EDD had nine design teams, which had on average 12 designers each, led by a designmanager. This department carried out around 75 projects simultaneously. Four teams were incharge of conceptual design, while five teams carried out detail design. This configuration wasadopted in November 2012 as an attempt to improve the EDD performance, by creating adecoupling point between conceptual design and detail design, with the aim of pulling thelatter bymanufacturing plants. An important change that had been gradually implemented bythe company was the reduction of batch sizes. At the detail design, each project was dividedinto stages (building modules) that could be assembled independently from other batches.

The design process was mostly based on a long-term project plan deadlines (from designto assembly on site) produced by the Planning Department. A weekly design planningmeeting was carried out between representatives of the Planning Department and designmanagers, in an attempt to devise an integrated plan for the EDD. At that meeting, thedesign managers reported the status of work in their teams, but little was done to increasecompliance with deadlines.

Implementation processImplementation in T1 and T2 teamsIn T1, participant observation in short-term planning meetings was carried out in June andJuly 2012. During that period, only short-term planning was implemented and some

Researchphase Source of evidence Description

1 Semi-structured interviews (18respondents)

Cost estimating (3), planning (1), engineering design (10),fabrication (4)

Survey (149 respondents out of319 technical staff )

Sales (12/25), cost estimating (13/24), planning (2/6), engineeringdesign (64/143), fabrication (44/91), assembly (14/30)

Document analysis List of employees, positions and dates of entry in the company(supported the selection of interviewees and survey respondents)Overall map of the product development processDesign process flowchartLayout plan for design teams in the officeCompany design drawings and long-term plans

2 Unstructured interviews Design managers (2) and designers (16)Document analysis Design drawings and design plansParticipant observation 25 weekly short-term design planning meetings

4 integrated planning meetings13 meetings related to process improvement at EDDworkshop 1(60 participants)

3 Unstructured interviews Design managers (4) and designers (4)Document analysis Design drawings and design plansParticipant observation 5 weekly short-term design planning meetings

Workshop 2 (40 participants)4 Participant observation 4 design planning meeting, involving planning department

representatives and design managersWorkshops 3 (40 participants), 4 (50 participants) and 5 (60participants)

Planning and control practicesprotocol

Application of a protocol for assessing the degree ofimplementation of design planning and control practices(between March and August 2013)

Table I.Sources of evidence

used in eachresearch phase

139

Planning andcontrolling

design

Page 10: Engineering, Construction and Architectural

difficulties occurred: planning meetings were often interrupted by other demands; theperformance metrics were not well understood by the participants; the level of participationof design team members in the meeting was low; they had difficulties in defining workpackages (there was a trend of simply copying from the long-term plan); and thedissemination of information was poor. Those problems were related to the fact that thedesign manager centralized decisions and information flows.

In T2, participant observations in short-term planning and control meetings were carriedout non-stop from August 2012 to January 2013. Team members were strongly involved inthe definition of work packages and usually expressed commitments to weekly goals.Furthermore, the causes for the non-completion of work packages were systematicallyrecorded. The design manager’s leadership was identified as a major factor for thesuccessful implementation in T2.

In November 2012, T1 and T2 started systematic planning and control at the medium-term(look-ahead) level (T1 horizon: one month, updated monthly; T2 horizon: four weeks, updatedevery two weeks). However, it was only partially implemented and much of the effort involvedin constraints identification and removal was carried out at the short-term.

In both T1 and T2, the average PPC was considerably high (76 percent and 79 percent), ifcompared to previous studies on the implementation of LPS in design: 50, 55, and 69 percentin the studies carried out by Tzortzopoulos et al. (2001), Ballard (2002) and Trescastro andFormoso (2006), respectively.

The causes for non-completion of work packages are presented in Table II. In bothteams, around 50 percent of causes were external to the company, i.e. related to delays indecision-making by clients.

However, there were internal problems in design teams (25 percent in T1, and 19 percent inT2), and also problems related to other departments in the company (26 percent in T1 and 29percent in T2). This indicated that it was possible to achieve improvements in PPC byimproving those processes that were internal to the company. For instance, at the beginning ofthe implementation process, the main cause for the non-completion of work packages in bothteams was the underestimated duration of design tasks. Between January and March 2013,that problem did not happen at all, indicating that the design teams had learned to balanceload and capacity, and therefore to make the internal design flow more reliable.

The effectiveness of look-ahead planning was accessed by the constraint removal index(CRI), which was calculated by using the formula:

CRI %ð Þ ¼ NCR=NCI (1)

where NCR is the number of constraints removed on time; NCI is the number of constraintsidentified for each period.

Designteams

Designphase

Number ofweeks

AveragePPC (%)

Causes for the non-completion ofwork packages Categories of causes

T1 Detaildesign

26 76 Client delay in design decisions:25%Client delay in design approval:18%Underestimated time: 12%

EDD processes: 25%Other company’sdepartments: 26%External to the company:49%

T2 Detaildesign

39 79 Client request for design change:23%Client delay in design approval:15%Conceptual design delay: 15%

EDD processes: 19%Other company’sdepartments: 29%External to the company:52%

Table II.Short-term designcontrol data forT1 and T2

140

ECAM25,2

Page 11: Engineering, Construction and Architectural

CRI has been used by several construction companies in Brazil (Oliveira, 2010; Trescastroand Formoso, 2006), and it is similar to other metrics that have been applied for assessingthe effectiveness of look-ahead planning, such as the percentage of tasks made ready(Hamzeh et al., 2015). Both NCI and CRI are relevant measures for assessing theeffectiveness of look-ahead planning, since it is necessary to be effective in both constraintidentification and removal. If both NCI and CRI are higher, PPC tends to be higher.

Figure 2 presents the evolution of NCI and CRI in T1 and T2. The fact that look-aheadplanning started to be systematic and had contributions of representatives from differentdesign team members contributed to increase NCI in both teams. However, no trend wasidentified in terms of increasing CRI. On average, T2 was more effective (CRI 79 percent)than T1 (CRI 55 percent) in constraint removal. It was not possible to compare these resultswith data from other projects, since CRI has only been used for production control (Oliveira,2010; Trescastro and Formoso, 2006).

A metric was also proposed to control the adherence of the monthly output of designteams in relation to the batches planned in the long-term plan. This was named as adherenceto batch index (ABI):

ABI %ð Þ ¼ NWC=NPW (2)

where NWC is the number of planned work packages that were concluded; NPW is thenumber of planned work packages in the long-term plan.

This metric can be adjusted for different time periods, such as a fortnight or a week. Itcan be used to control the amount of work-in-progress, which is not usually done in LPS. AnABI is highly dependent on the effectiveness of both look-ahead and short-term(commitment) planning. Therefore, the higher NCI and PPC, the higher ABI tends to be. InT2, the average ABI for the period between November 2012 and May 2013 was 66 percent(Figure 3). Although no reference values were found in the literature, it is very unlikely thatthis indicator gets closer to 100 percent in ETO production systems, due to the high level ofuncertainty involved. Similarly, to the PPC metric at the short-term planning level, the maincauses for not adhering to the batches that have been planned should be monitored in orderto generate information useful for learning.

The main conclusions of this phase were: first, PPC was lower in the first week of themonth, especially in T1, which did not adopt a rolling look-ahead plan; second, consideringthat a relatively large percentage of work packages did not adhere the initial monthly plans(34 percent in T2), there was a need to monitor the execution of work packages that had notbeen planned, and identify the main causes for their inclusion; third, it was necessary toimprove the identification of the causes for the non-completion of work packages;and fourth, there was a need to improve the integrated design planning meetings, whenchanging demands from downstream processes (fabrication and site assembly) werepresented by planning staff to design managers.

7 810

1513

64 1

9 9

86%

50%

10%

60%69%

Nov

embe

r

Dec

embe

r

Janu

ary

Febr

uary

Mar

ch

Team 1 – constraint removal index (CRI)

NCI NCR CRI monthly average

915

18

8

1721

24

913 15

610

16 17

100%87% 83%

75%59%

76% 71%

Nov

embe

r

Dec

embe

r

Janu

ary

Febr

uary

Mar

ch

April

May

Team 2 – constraint removal index (CRI)

NCI NCR CRI monthly average

Figure 2.NCI and CRI results

for T1 and T2

141

Planning andcontrolling

design

Page 12: Engineering, Construction and Architectural

Implementation in T3, T4, T5 and T6Implementation in T3, T4, T5 and T6 faced initial difficulties similar to those of Phase 2:relatively long duration of planning meetings (around one hour), mostly because input data(e.g. architectural design) had not been previously analyzed, making it difficult to estimatethe duration of activities; difficulty in breaking down design activities into smaller workpackages; difficulty in obtaining information for defining priorities at the look-aheadplanning level; lack of understanding of the difference between resource constrains anddesign interdependencies; and difficulty in identifying the root causes for the non-completionof work packages.

However, during the implementation process, some of those difficulties were overcomedue to the active participation and leadership of the majority of design managers inplanning meetings. At the end of this phase, the weekly meetings had the duration of around20 minutes.

Table III presents a summary of the data collected for T3, T4, T5 and T6, including thenumber of weeks, CRI, PPC, the main causes and their relative importance, and theclassification according to the categories of causes. The average PPC for conceptual designteams (T3 and T4) was lower than the average PPC for detail design teams (T5 and T6).This was expected as there is much more uncertainty in early design, due to the need forclient approvals. At the end of this phase, T6 was merged with T3, and T3 stopped theimplementation of the model, due to lack of support from the design manager.

The analysis of causes for the non-completion of packages indicated severalopportunities for improvement within the company, as a large percentage of problemswere related to internal processes. For the detail design teams, late conceptual designdecisions by the client indicate that the idea of having a decoupling point betweenconceptual and detail design had not been fully implemented.

The performance of the look-ahead planning was relatively poor among the four teams.CRI ranged from 33 to 75 percent, and T6, which achieved the highest figure, did notperform well in constraint identification – only eight constraints were identified in fourlook-ahead plans.

Regarding the execution of work packages that had not been planned, these should beconsidered as normal to some extent due to the nature of the design process, widelydiscussed in the literature (e.g. Reinertsen, 2009; Cross, 2008). However, as pointed out byBallard et al. (2009), unplanned assignments should be identified and analyzed in short-term

103

75 7584

124

85

103

7655 51 42

8052

75

11

21 21 33

10

25

2162 10 9

49

16

T2 design batches adherence to the long-term planPlanned Planned work done Unplanned work done Rework

ABI

74% 73%68%

50%

65% 61%

73%

Nov

embe

r

Dec

embe

r

Janu

ary

Febr

uary

Mar

ch

April

MayFigure 3.

ABI for T2

142

ECAM25,2

Page 13: Engineering, Construction and Architectural

planning in order to consider them in future planning cycles. The design teams decided tomonitor the incidence of those tasks, and take sometimes this type of information to discussin design meetings. Although no analysis of performance measures related to unplannedtasks has been made in this investigation, design team members consider that monitoringthose tasks was useful for highlighting some planning failures, including urgent demandsfrom downstream processes.

The main contributions of this phase for the development of the model include: ajoint analysis of performance measures was undertaken for each team with the aim ofencouraging improvement – a monthly feedback cycle was suggested for this setof metrics; the use of rolling look-ahead plans was extended to all design teams; the controlof design deliveries was improved by monitoring their adherence to planned designbatches in the long-term plan, in an attempt to limit the amount of work-in-progress;and the level of standardization of design planning was increased, e.g. creating listsof constraints and categories for the most common causes for the non-completion ofwork packages.

Integrated medium-term planning and visual managementAt Phase 4, the use of visual management boards to encourage collaborative planning andsupport decision-making was proposed. Two types of boards were used: one that integratesmedium-term planning across different design teams; and another one that supportsindividual team planning meetings and to encourage improvement initiatives. Theintegrated medium-planning board (Figure 4) was updated weekly at design planningmeetings, which had the participation of staff from the planning department.

The planning horizon for conceptual design was four weeks, while in detail design atwo-week horizon was adopted, since design batches tend to be smaller in the latter.As mentioned above, the company expected that downstream processes could pull detail

Designteams

Designphase

Numberof weeks

AverageCRI (%)

AveragePPC (%)

Causes for the non-completion of workpackages Categories of causes

T3 Conceptualdesign

5 36 64 Changes in priorities (19%)Lack of design definitionsby clients (19%)Underestimated duration(16%)

EDD processes: 37%Other company’sdepartments: 16%External to thecompany: 47%

T4 Conceptualdesign

5 59 61 Underestimated duration(19%)Client request for designchange (14%)Software related problems(9%)

EDD processes: 40%Other company’sdepartments: 33%External to thecompany: 27%

T5 Detaildesign

5 33 68 Underestimated duration(24%)Client request for designchange (18%)Lack of design definitionsby clients (18%)

EDD processes: 37%Other company’sdepartments: 63%External to thecompany: 0%

T6 Detaildesign

4 75 78 Software related problems(30%)Delays in conceptual design(15%)Changes in priorities (15%)

EDD processes: 35%Other company’sdepartments: 15%External to thecompany: 50%

Table III.Data for T3, T4,

T5 and T6

143

Planning andcontrolling

design

Page 14: Engineering, Construction and Architectural

design work packages. Moreover, a board for managing constraints at design planningmeeting was devised.

Figure 5 presents an example of visual device to support the work of individual designteams. That board contains the look-ahead plan (two or four-week horizon, based on theintegrated medium-term plan), a list of constraints to be removed, printed copies ofshort-term plans, and some performance metrics, including PPC and CRI.

The visual boards were useful for EDD and the Planning Department, but also forother departments that were involved in removing constraints, such as sales and costestimating. After the visual management boards were implemented, the duration of theintegrated design meeting was reduced to half a day, making the participation of alldesign managers possible.

Overview of the design planning and control modelFigure 6 presents an overview of the proposed design planning and control model. It isdivided into four hierarchical levels, and contains some key elements of the LPS.

Level 1 is concerned with long-term planning, considering all projects being undertakenby the company, and the capacity of each design team. That plan is produced by thePlanning Department, based on deadlines defined in contracts and on the integrated

Conceptualdesign teams M T W T F M T W T F M T W T F M T W T F

A Design assignmentsB

C

Week 1 Week 2 Week 3 Week 4

Assignment delayed

Conceptualdesign teams M T W T F M T W T F M T W T F M T W T F

A Design assignmentsB

C

Week 1 Week 2 Week 3 Week 4

Assignment delayed

Figure 4.Integrated medium-planning board(including schematicrepresentationof the tool)

144

ECAM25,2

Page 15: Engineering, Construction and Architectural

medium-term design plan, in which monthly goals are established for EDD. ABI is themetric used at this level to control adherence of the monthly output to long-term plans.

At Level 2, a weekly integrated medium-term design planning meeting is carried out, inwhich the external constraints for design development can be jointly analyzed, supportedby visual devices. This meeting should be connected with an integrated meeting betweenfabrication and assembly, so some information that could change design prioritiescome from that meeting (e.g. plant idleness, lack of payment by client and assemblydelays). At this point, a decoupling point exists between conceptual and detail design.The integrated look-ahead plans are updated weekly, looking four weeks ahead forconceptual design and two weeks ahead for detail design, considering both the targetsestablished in the long-term plan and also the level of work-in-progress for each team.CRI is the main metric used at this level.

ConstraintsDesignname

Designpackage

Designerin charge

Data Status

Weeklyplans filledin manually

M T W T F M T W T F

Med

ium

-ter

m

Sho

rt-t

erm

Con

stra

ints

ana

lysi

s Metrics (graphs)

Week 1 Week 2

Figure 5.Individual team

planningmeeting board

(including schematicrepresentation

of the tool)

145

Planning andcontrolling

design

Page 16: Engineering, Construction and Architectural

A weekly meeting is carried out separately by each design team, supported by visualdevices, to produce a medium-term plan at Level 3 (same horizons adopted at Level 2) and ashort-term plan at Level 4. In those meeting, an analysis of constraints is performed, and abacklog of sound assignments to be included in the short-term plan is prepared (operationallevel). CRI is the metric used at medium-term plan. Causes for the non-completion of workpackages and PPC are the metrics used at short-term plan.

Evaluation of the model and discussionAs mentioned in the research method section, the model was evaluated according to twomain constructs: applicability and utility. Figure 7 presents the assessment of the degree ofimplementation of planning practices in March 2013 (T1, T2, T3, T4, T5 and T6) andAugust 2013 (T1, T2, T4 and T5).

ApplicabilityIn four out of nine design teams, look-ahead and short-term planning meetings were carriedout systematically. As pointed out by Ballard (2002) and Kerosuo et al. (2012), systematicplanning and constraints analysis allow a better understanding of the designinterdependences by the designers. In fact, the degree of implementation of practices 1and 7 (Figure 7) was high (75 percent). Another evidence of success is the fact that theduration of the meetings was largely reduced along the implementation process: short-termdesign meetings took around 30 minutes for T1 and T2, and the duration of the integratedlook-ahead planning meeting was reduced from two days to half a day.

There were differences between design teams in terms of making planning and controlsystematic. This was largely due to the impact of design managers commitment and leadership.

Level 4:

Level 2: Design teams goal

Level 3:

Level 1:

Design teams integratedmedium-term plan

Design team short-term plan

1 2 3 4Weeks

1 2 3 4Weeks

1Weeks

Design long-term plan

1 2Weeks

Design team medium-term plan

1 2 3 4Weeks

Conceptual design Detailed design

1 2Weeks

Buffer of sound assignments

Conceptual design Detailed design

ABI

CRI

CRI

CausesPPC

Main metrics

Figure 6.Proposed designplanning andcontrol model

146

ECAM25,2

Page 17: Engineering, Construction and Architectural

In the most successful teams (T2 and T4), the weekly planning meeting was always held,even when the design manager was unable to participate.

Following the suggestions of Tzortzopoulos et al. (2001), Ballard (2002) and Kerosuo et al.(2012), the training program, involving the six design teams, played an important role indisseminating the core design management and project planning and control concepts andpractices among those teams. This program also helped to conceive the model, asimplementation results were widely disseminated and discussed with representatives ofdifferent departments of the company, as suggested by Ballard (2002).

UtilityShielding design work from variability. The main innovation introduced in the designplanning and control process was the adoption of two levels of look-ahead planning: first, ata higher hierarchical level, the external constraints analysis was undertaken at the

T3 T6

M A M A M M A M A M

1. Short-term planning and control routine 1 0.5 1 1 1 0.5 1 1 0.5 1 92% 75%

2. Sound definition of work packages 1 0.5 1 1 1 1 1 1 0.5 1 100% 75%

3. Only work packages that have no constraints in the weekly plan 0.5 1 0.5 1 0.5 0.5 0 0.5 0.5 0.5 50% 63%

4. Backlog of sound assignments 0 1 1 1 1 1 1 1 0.5 1 83% 88%

5. Participative decision making in short- term meetings 1 1 1 1 1 1 1 1 0.5 1 100% 88%

6. Corrective actions based on the reasons of non-completion of the plans 0 0 1 0.5 0 0 1 0 0.5 0 17% 50%

7. Look-ahead planning and control routine 0.5 0.5 1 1 0.5 0.5 1 0.5 0.5 0.5 58% 75%

8. Systematic removal of constraints 0.5 0.5 0.5 1 0 0.5 0 0.5 0.5 0.5 42% 50%

9. Production of a visual long-term plan 0.5 0.5 0.5 1 0.5 0.5 1 0.5 0.5 0.5 50% 75%

10. Use of metrics to evaluate compliance with the master plan 0.5 0.5 0.5 1 0 0 0.5 0.5 0.5 0.5 33% 63%

11. Systematic updating of long-term plans to reflect project status 1 0.5 1 1 1 1 1 1 0.5 1 100% 75%

12. General design planning and control model implementation 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 50% 50%

13. Monthly metrics analysis by teams (ABI, CRI, PPC, Causes) 0 0.5 0.5 0.5 0 0 0 0 0.5 0 8% 38%

14. Use of visual devices by teams 0 1 0 1 0 0 0 0 0 0.5 8% 50%

50% 61% 71% 89% 50% 50% 64% 57% 46% 61% 57% 65%

March 2013

Degree ofimplementation of

practicesPlanning practices

Implemented (1) – Partially implemented (0.5) – Not implemented (0) | March 2013 (M) – August 2013 (A)

Planning practices at levels 3 and 4 of the model

Teams

71%61%

46%22%

73%74%

63%50%

August 2013

T1 T2

Detail design

T4 T5

Conceptualdesign Detail design

Long-term plan

Medium-term plan (lookahead)

Short-term plan

Figure 7.Degree of

implementation ofdesign planning andcontrol practices in

March 2013 andAugust 2013

147

Planning andcontrolling

design

Page 18: Engineering, Construction and Architectural

integrated design planning meeting; second, internal constraints analysis was carried outeach design team. The average PPC (71 percent) for six different teams indicated that basicstability of design work was improved along the implementation process.

In fact, there were evidences that the proposed model was helpful in implementingmedium-term planning: the practice “look-ahead planning and control routine” achieved thedegree of 75 percent. This was pointed out as a major difficulty in previous studies (Miles,1998; Tzortzopoulos et al., 2001; Codinhoto and Formoso, 2005; and Ballard et al., 2009).However, the design teams still faced difficulties in performing “systematic removal ofconstraints” (50 percent in August 2013) and no substantial growth was observed in CRI,especially at the conceptual design stage. Indeed, there was a large number of constraintsrelated to client decisions that were identified late, only at the detail design stage. Thestrategy of making the design process more transparent to the client, especially at earlydesign stages, was suggested by some design teams as an improvement opportunity relatedto that problem.

Encouraging collaborative planning. The company was also successful in terms ofincreasing the degree of participation in planning and control. Design team membersincreased the level of participation in planning meetings over time, and the level ofcollaboration between different teams increased with the introduction of the integrateddesign planning level. The practice “participative decision making in short-term meetings”achieved 88 percent. As a consequence, planning became less centralized and designersbecame more committed in terms of producing weekly design deliverables.

Creating opportunities for learning. There were also evidences that the model providedopportunities for learning due to systematic feedback obtained from performance metricsand the opportunities for discussion provided by participative planning meetings. Forinstance, the reduction in the incidence of the planning failure named “underestimatedtime” for T1 and T2 indicated that those teams improved their capacity of matching loadand capacity.

Some of the feedback provided came from traditional LPS metrics (e.g. PPC, reasons forthe non-completion of work packages, total number of constraints per week, and CRI).However, there were other metrics that played a key role in terms of pointing outimprovement opportunities: adherence to batch (ABI metric), and monitoring unplanneddesign activities carried out weekly. In both cases, it is necessary to monitor deviations andalso the reasons for it. Despite the importance of monitoring adherence to batch as amechanism to limit the amount of work-in-progress, it was difficult to implement thatmeasure in all design teams. This is partly due to the traditional practice adopted by thecompany of measuring design output in terms of weight (in tons).

Another practice related to learning, considered in the evaluation was the “monthlymetrics analysis by teams,” with the support of visual boards. Such joint analysis wasperformed by individual design teams once a month, in a meeting for reviewing the monthlyperformance. Participant observation in design meetings indicated that the analysis ofmetrics with the support of the design manager had a motivating role in design teams,although the degree of implementation of this practice was limited (38 percent).

The main improvement at the short-term planning level was performing “correctiveactions based on the reasons for non-completion of plans,” from 17 to 50 percent.That practice was much emphasized in the training program and it is often mentioned in theliterature as a weak point in the implementation of LPS (Hamzeh et al., 2009).

Increasing process transparency. The use of visual management boards was crucial forimproving the effectiveness of the implementation process by increasing the availability ofthe information to support decision-making both at a tactical and operational level.The degree of implementation of the practice “production of a visual long-term plan” was

148

ECAM25,2

Page 19: Engineering, Construction and Architectural

improved from 50 to 75 percent. Such boards addressed one of the problems identified inPhase 1 of this research: lack of transparency in the design process, creating difficulties forthe Planning Department to match the production capacity of EDD. Collaborative planningwas also encouraged as more people were aware of project status.

Despite the importance of making visible LPS’s metrics (Ballard, 2002), the existingliterature does not report that as being systematic in design planning and control.Additionally, process transparency is particularly important in the context of ETOprefabricated building systems, due to the high level of complexity involved.

Flexibility according to projects status. Some degree of flexibility should be provided byallowing plans to be produced according to project status, due to the high uncertaintyinvolved in ETO production systems. Therefore, some order confirmation points must beestablished in the planning and control process (Viana et al., 2013), in which activities mustbe pulled from downstream processes (Hopp and Spearman, 2008).

The fact that the model divides planning and control in four hierarchical levels providesopportunities for revising plans, based on an update of project status. In this respect, theintegrated look-ahead design planning meeting played a key role in providing such flexibility,as it involves both design managers, and planning staff that are able to confirm orders frommanufacturing and assembly production units. This strategy can only be made effective ifdesign batches are kept small. For that reason, monitoring the adherence to batch size,measured by ABI, can contribute to achieve the necessary flexibility.

ConclusionThe main outcome of this research is a design planning and control model for companiesthat design, manufacture and assemble prefabricated ETO building systems. In this type ofproduction system uncertainty tends to be high, and many interdependencies exist amongdifferent production units, since these share resources (e.g. plants, equipment, crews, etc.).

The model was devised as an adaptation of the LPS for ETO multiple-projectenvironments, being formed by four levels of planning, a set of metrics and visual devicesthat support communication and collaboration. By using a design science researchapproach, this investigation has a prescriptive character: the proposed model can be used bycompanies that deliver prefabricated ETO building systems as a starting point fordeveloping engineering design planning systems.

Several contributions have been proposed to improve the design planning and controlprocess: use of two levels of look-ahead planning, based on the assumption that there aretwo types of constraints (external and internal) and that these should be dealt with atdifferent hierarchical levels in the company; introduction of the integrated design planningmeeting, which is a mechanism to allow plans to be produced according to project status;introduction of a decoupling point between conceptual and detail design, allowing the latterto be pulled by the demands of construction sites and manufacturing plants; extending theset of metrics of the LPS, so that adherence to batch size is controlled as well as the incidenceof non-planned work packages, including the causes of failures; and understanding thepotential role of visual management to support collaborative planning and joint analysis ofmetrics in an environment of much complexity.

The implementation of the model indicated that it helps to shield design work fromvariability, support collaboration among design team members, as well as provideopportunities for learning by providing systematic feedback to decision makers. However,some limitations were identified in the implementation process: similarly to some previousstudies (Ballard, 2002; Codinhoto and Formoso, 2005), the success of constraint analysis wasstill limited; some of the metrics produced (e.g. ABI, causes of planning failures) have notbeen fully used for process improvement; and systematic feedback about project status wasnot properly implemented and tested.

149

Planning andcontrolling

design

Page 20: Engineering, Construction and Architectural

Moreover, it must be emphasized that the development of the model was based on asingle empirical study, carried out in a company that delivers steel structures. Further workis necessary to test and refine the model in other organizational contexts and also for otherprefabricated building systems.

Finally, based on the development of this investigation, some other opportunities forfuture studies must be pointed out: investigate the role of leadership in medium andshort-term planning meetings; explore the use of design batches as planning and controlunits, instead of design activities or deliverables (e.g. drawings); improve the integrationbetween the different planning levels proposed in the model, such as between design anddownstream processes (e.g. manufacturing and site assembly), and between individual andintegrated medium-term planning level; further test the use of the metrics proposed in thisresearch work (CRI and ABI), and establish a theoretical basis for analyzing those data; andinvestigate mechanisms to manage client related constraints at the conceptual design stage.

References

Austin, S., Baldwin, A. and Newton, A. (1994), “Manipulating the flow of design information to improvethe programming of building design”, Construction Management and Economics, Vol. 12 No. 5,pp. 445-455.

Austin, S., Baldwin, A., Li, B. andWaskett, P. (2010), “Analytical design planning technique (ADePT): adependency structure matrix tool to schedule the building design process”, ConstructionManagement and Economics, Vol. 8 No. 2, pp. 173-182, doi: 10.1080/014461900370807.

Baccarini, D. (1996), “The concept of project complexity – a review”, International Journal of ProjectManagement, Vol. 14 No. 4, pp. 201-204.

Ballard, G. (2000), “The last planner system of production control”, doctoral dissertation, TheUniversity of Birmingham, Birmingham.

Ballard, G. (2002), “Managing work flow on design projects: a case study”, Engineering Constructionand Architectural Management, Vol. 9 No. 3, pp. 284-291.

Ballard, G. and Howell, G. (1997), “Shielding production: an essential step in production control”,Construction Engineering and Management Program, Department of Civil and EnvironmentalEngineering, University of California, Berkeley, CA, pp. 97-1.

Ballard, G., Hammond, J. and Nickerson, R. (2009), “Production control principles”, Proceedings 17thAnnual Conference of the International Group for Lean Construction (IGLC-17), Taipei.

Bertrand, J.W.M. and Muntslag, D.R. (1993), “Production control in engineer-to-order firms”,International Journal of Production Economics, Vols 30-31, July, pp. 3-22.

Bulhões, I. and Picchi, F. (2008), “Continuous flow for structural design in prefabricated concretestructures”, 16th Annual Conference of the International Group for Lean Construction,Manchester, July 16-18, pp. 169-181.

Choo, H.J., Hammond, J., Tommelein, I.D., Austin, S.A. and Ballard, G. (2004), “DePlan: a tool forintegrated design management”, Automation in Construction, Vol. 13 No. 3, pp. 313-326.

Codinhoto, R. and Formoso, C.T. (2005), “Contributions for the integration of design and productionmanagement”, in Emmitt, S. and Prins, M. (Eds), Proceedings of the CIB W096 ArchitecturalManagement, CIB Publication, Lyngby, pp. 321-330.

Crosby, L.A. (1995), “Measuring customer satisfaction”, Quality Digest, Vol. 15, pp. 42-47.

Cross, N. (2008), Engineering Design Methods: Strategies for Product Design, John Wiley & Sons,Chichester.

El Reifi, M.H. and Emmitt, S. (2013), “Perceptions of lean design management”, Architectural,Engineering, and Design Management, Vol. 9 No. 3, pp. 195-208.

Emmitt, S. and Ruikar, K. (2012), Collaborative Design Management, Routledge, Oxon.

150

ECAM25,2

Page 21: Engineering, Construction and Architectural

Eppinger, S.D., Whitney, D.E., Smith, R.P. and Gebala, D.A. (1994), “A model-based method fororganizing tasks in product development”, Research in Engineering Design, Vol. 6 No. 1, pp. 1-13.

Formoso, C.T., Tzortzopoulos, P. and Liedtke, R. (2002), “A model for managing the productdevelopment process in house building”, Engineering, Construction and ArchitecturalManagement, Vol. 9 Nos 5/6, pp. 419-432.

Gosling, J. and Naim, M.M. (2009), “Engineer-to-order supply chain management: a literature reviewand research agenda”, International Journal of Production Economics, Vol. 122 No. 2, pp. 741-754.

Hamzeh, F.R., Ballard, G. and Tommelein, I.D. (2009), “Is the last planner system applicable to design?A case study”, Proceedings of the 17th Annual Conference of the International Group for LeanConstruction, Vol. 17, pp. 13-19.

Hamzeh, F.R., Saab, I., Tommelein, I.D. and Ballard, G. (2015), “Understanding the role of ‘tasks anticipated’in lookahead planning through simulation”, Automation in Construction, Vol. 49, Part A, pp. 18-26.

Holmström, J., Ketokivi, M. and Hameri, A.P. (2009), “Bridging practice and theory: a design scienceapproach”, Decision Sciences, Vol. 40 No. 1, pp. 65-87.

Hopp, W.J. and Spearman, M.L. (2008), Factory Physics: Foundations of Manufacturing Management,Waveland Press, New York, NY.

Järvinen, P. (2007), “Action research is similar to design science”,Quality &Quantity, Vol. 41 No. 1, pp. 37-54.

Kagioglou, M., Cooper, R., Aouad, G. and Sexton, M. (2000), “Rethinking construction: the genericdesign and construction process protocol”, Engineering, Construction and ArchitecturalManagement, Vol. 7 No. 2, pp. 141-153.

Kamara, J.M., Augenbroe, G., Anumba, C.J. and Carrillo, P.M. (2002), “Knowledge management in thearchitecture, engineering and construction industry”, Construction Innovation, Vol. 2 No. 1, pp. 53-67.

Kerosuo, H., Mäki, T., Codinhoto, R., Koskela, L. and Miettinen, R. (2012), “In time at last: adaption oflast planner tools for the design phase of a building project”, 20th Annual Conference of theInternational Group of Lean Construction, pp. 1031-1041.

Knotten, V., Svalestuen, F., Hansen, G.K. and Lædre, O. (2015), “Design management in the buildingprocess-a review of current literature”, Procedia Economics and Finance, Vol. 21, pp. 120-127.

Koskela, L., Huovila, P. and Leinonen, J. (2002), “Design management in building construction: fromtheory to practice”, Journal of Construction Research, Vol. 3 No. 1, pp. 1-16.

Laufer, A. and Tucker, R.L. (1987), “Is construction project planning really doing its job? A criticalexamination of focus, role and process”, Construction Management and Economics, Vol. 5 No. 3,pp. 243-266.

March, S.T. and Smith, G.F. (1995), “Design and natural science research on information technology”,Decision Support Systems, Vol. 15 No. 4, pp. 251-266.

Matt, D.T. (2014), “Adaptation of the value stream mapping approach to the design of lean engineer-to-order production systems: a case study”, Journal of Manufacturing Technology Management,Vol. 25 No. 3, pp. 334-350.

Mello, M.H., Strandhagen, J.O. and Alfnes, E. (2015), “Analyzing the factors affecting coordination inengineer-to-order supply chain”, International Journal of Operations & Production Management,Vol. 35 No. 7, pp. 1005-1031.

Miles, R.S. (1998), “Alliance lean design/construct on a small high tech project”, The 6th AnnualConference of the International Group for Lean Construction, Guaruja, pp. 13-15.

Oliveira, C.B. (2010), “Avaliação de Indicadores de Planejamento e Controle da Produção na Construção:boas práticas, eficácia e prazo”, MSc dissertation, Federal University of São Carlos, São Carlos.

Reinertsen, D.G. (2009), The Principles of Product Development Flow: Second Generation Lean ProductDevelopment, Vol. 62, Celeritas, Redondo Beach.

Trescastro, M.G. and Formoso, C.T. (2006), “Design planning and control in complex projects and thereduction of information batch sizes”, Proceedings of the International Symposium onConstruction in Developing Economies: New Issues and Challenges, Pontificia UniversidadCatolica de Chile, Santiago, January 18-20, pp. 421-430.

151

Planning andcontrolling

design

Page 22: Engineering, Construction and Architectural

Tribelsky, E. and Sacks, R. (2010), “The relationship between information flow and project success inmulti-disciplinary civil engineering design”, 18th Annual Conference of the International Groupfor Lean Construction, Haifa.

Tzortzopoulos, P., Formoso, C.T. and Betts, M. (2001), “Planning the product development process inconstruction: an exploratory case study”, Proceedings of the 9th Annual Conference of theInternational Group for Lean Construction, National University of the Singapore, Singapore,pp. 103-116.

Viana, D.D., Bulhoes, I. and Formoso, C.T. (2013), “Guidelines for integrated planning and control ofengineer-to-order prefabrication systems”, 21st Annual Conference of the International Groupfor Lean Construction, Fortaleza.

Williams, T.M. (1999), “The need for new paradigms for complex projects”, International Journal ofProject Management, Vol. 17 No. 5, pp. 269-273.

Corresponding authorPatricia Tzortzopoulos can be contacted at: [email protected]

For instructions on how to order reprints of this article, please visit our website:www.emeraldgrouppublishing.com/licensing/reprints.htmOr contact us for further details: [email protected]

152

ECAM25,2

Page 23: Engineering, Construction and Architectural

Construction manager’s technicalcompetencies in Malaysian

construction projectsAbd Halid Abdullah, Siti Khalijah Yaman and Hairuddin Mohammad

Faculty of Civil and Environmental Engineering,Universiti Tun Hussein Onn Malaysia, Batu Pahat, Malaysia, and

Padzil Fadzil HassanDepartment of Quantity Surveyors, Universiti Teknologi MARA,

Shah Alam, Malaysia

AbstractPurpose – Problems of Malaysian construction industry have often been associated, in part to incompetentconstruction manager (CM) when managing the construction projects. Although various education andtraining provisions have been introduced, critics argue that the provisions have not been effective. Central inthe debate on the adequacy of the CM education and training offered is the answer to the question of “whatconstitutes the technical competency of the CM?” The purpose of this paper is to present the study thatidentifies the technical competencies required by the CM to address the question.Design/methodology/approach – Multi-layered thematic analysis of literature was first carried out toidentify the technical competency elements. Then, interviews were undertaken to confirm the elements ofcompetencies. It was followed with questionnaire surveys to test the validity of the technical competenciesagainst different contractors’ category and grade/size.Findings – The findings suggest that the technical competencies of CM are generic, regardless of the size ofconstruction organisation or the types of projects they undertake. A total of 16 CM technical competencieswere identified which include the ability to manage: staff, materials, labour, plant, sub-contractors, safety,money, quality, time, environment, site administration, pre-construction activities, project closeout andhandover, third parties, computer literacy, and construction contract.Originality/value – The findings suggest that generic education and training is possible to develop technicallycompetent CM. It also provides insights to the CM technical competencies which the industry is expecting.Keywords Construction, Management, Construction planningPaper type Research paper

1. IntroductionThe Malaysian construction industry has always been of enormous significance tothe national economy. Since independence in 1957, the industry has contributed to thedevelopment of infrastructure facilities needed by the growing population and has been theimpetus for economic growth through the creation of value chains across many sectors ofthe economy, which include the housing, transportation, manufacturing, and financialsectors (Rum and Akasah, 2011). The impact can also be exemplified by industry’s currentcontribution to the national GDP at 8.4 per cent (Bank Negara Malaysia, 2015). However, theindustry has also been plagued with many serious problems such as delays, excessiveresource consumption, poor quality, low productivity, delays, wastages, cost overruns,disputes, low technology, overreliance on foreign workers, and sustainability issues(Abdul-Rahman et al., 2006; Sambasivan and Soon, 2007; Bakar and Hassan, 2009; Ibrahimet al., 2010). Most of the problems have been blamed on the inability of the contractors todeliver the projects according to the project objectives (Abdul-Rahman et al., 2006;Sambasivan and Soon, 2007; Bakar and Hassan, 2009; Jabatan Audit Negara Malaysia,2010a, b; Unit Penyelarasan Pelaksanaan, 2013). Likewise, construction manager (CM) whosupposedly play central roles in assisting the contractors have also been criticised forfailing to achieve the objectives. The significance of the CM in construction projects was

Engineering, Construction andArchitectural Management

Vol. 25 No. 2, 2018pp. 153-177

© Emerald Publishing Limited0969-9988

DOI 10.1108/ECAM-07-2016-0176

Received 29 July 2016Revised 23 January 2017Accepted 27 May 2017

The current issue and full text archive of this journal is available on Emerald Insight at:www.emeraldinsight.com/0969-9988.htm

153

Constructionmanager’stechnical

competencies

Quarto trim size: 174mm x 240mm

Page 24: Engineering, Construction and Architectural

drawn from the Akintoye (1998) (Hassan, 2005). They commonly stress that CMs arecrucial as they are the pivot around which everything else in the construction projectsrevolves. The CM job is among the most arduous, demanding, and single responsiblefunction in the building process. Although the responsibility and authority in a project areshared with other project personnel, CM is the one who normally has to take the blame ifanything goes wrong.

The Construction Industry Development Board (CIDB) Malaysia estimates that there aremore than 67,000 contractors and about 58,000 registered CMs in the industry (ConstructionIndustry Development Board Malaysia, 2011). Although the numbers are impressive, theiractual level of competency is unknown and very questionable as claimed by Yaman et al.(2015) and Mohammad et al. (2016). The need for the industry to persist in addressing thecompetency problems of the workforce, including the CM, was already highlighted back in2006 with the launch of the Construction Industry Master Plan (Construction IndustryDevelopment Board, 2007). Despite the many initiatives mooted, results have been poor.The need to continue to address the problem was again raised in the Construction IndustryTransformation Programme (CITP) 2016-2020 (Construction Industry Development BoardMalaysia, 2015). All along, the education of CM has been provided by the institutions ofhigher learning, while training is mostly provided by CIDB, with some in collaboration withhigher learning institutions and training organisations. CM training is also offered asbespoke in-house training company by contracting organisations.

While new initiatives are being considered to expand the education and training of CMfollowing the CITP, the continuing poor performance of contractors of which the CMs playa major part suggest that there are critical problems in the way their education andtraining have been offered (Bakar and Hassan, 2009; Ibrahim et al., 2010; Hassan,Maisham, Khan, Alwi and Ramli, 2010; Russell et al., 2007). Supporting this proposition isthe report stressing that the industry has yet to establish the competency standards forCM (NOSS Division, Department of Skills Development, 2015). Therefore, this researchwas put forward to gain insights on the factors that have contributed to the ineffective CMeducation and training, and to assist explanation of the phenomenon. On the premise thatthe terms of reference for workforce competency development are crucial for theirdevelopment (Russell et al., 2007), the aim of the research was to establish the technicalcompetencies required by CM. In line with the aim, the objectives of the research were toidentify the elements of technical competencies of CM, to confirm the elements of technicalcompetencies of CM, and to analyse the importance of the elements towards differentcontractor’s category and grade/size.

Therefore, owing to the aim of research, this paper is structured into several sections,namely literature reviews (in three sections), research methodology (in three sub-sections),result and analysis (in three sub-sections), discussion (in two sub-sections), and finally asection for the conclusion.

2. Construction managementA project life cycle characteristically comprises design and construction stages, within whichproject management, construction management, and site management take place (Mohammadet al., 2016; Halpin, 2006; Gray and Larson, 2008). According to Koskela (1992) and Yamanet al. (2015), construction management is defined as the transformation of detailed design intoa construction/fabrication plan before management of day-to-day processes either on-site or ina factory can be made. Construction management is primarily focussed on project’sconstruction stage where the contractors undertake the project production process at theconstruction site. In a typical traditional procurement system, which is widely practised inMalaysia ( Jaafar and Nuruddin, 2012), the contractors’ involvement would usually start fromthe tendering stage at the end of the project’s design stage. The task of transforming the

154

ECAM25,2

Page 25: Engineering, Construction and Architectural

designs into the actual physical follows when the project is awarded and ends when projecthanded back to the client at the project closeout (Halpin, 2006; Gray and Larson, 2008).Although most construction management activities take place at the project site, there areactivities such as liaison with project financiers, local authorities for approvals, and suppliers,which have to be carried out off-site. Additionally, during the construction phase, project’sresources (i.e. money, materials, plant/machinery, and manpower) are consumed to achieveproject objectives of time, cost, quality, and health and safety, and eventually, determinewhether the contractor makes profit or loss (National Center for Construction Education andResearch, 2008; Oberlender, 2000).

Construction management is a very tough undertaking, and the responsibility is shoulderedby CM (Love and Haynes, 2001; Toor and Ogunlana, 2008; Isa, 2007). Usually sandwichedbetween top managers and supervisory personnel, CMs from contractors are sharing a similarlevel of management as a construction coordinator, superintendent, and site manager(Isa, 2007). Their responsibility to transform the design into built infrastructure facilities wouldtypically include the application of appropriate management functions (e.g. planning,organising, staffing, coordinating, and controlling) towards commonly identified constructioncomponents (e.g. manpower, materials, machines, and money) within the entire processesof construction phase (Mohammad et al., 2016). The demands of the job require them tobe competent to execute all activities within very challenging and dynamic circumstances. Thisincludes handling activities which involve numerous contracting parties, which consumes a lotof resources and operating on tight deadlines, working in unpredictable and harsh weatherconditions, risky working undertakings, and when money is being spent at a very fast rate(Isa, 2007). This necessitates the CM to be wholly competent. Table I tabulates the commonconstruction characteristics and management approaches led by CM as highlighted by severalresearchers (Halpin, 2006; Gray and Larson, 2008; Koskela, 1992; Isa, 2007; Burke, 2003;Ritz, 1994). In summary, construction has a definite period of development where time, cost,quality, and scope are critical. And by having several resources to be utilised, appropriateknowledge, skills, tools, and techniques are direly needed to be applied within an uncertainenvironment. From the perspective of contractor’s CM, all phases of construction fromtendering stage to handover are paramount and have to be managed properly. Thus, suitablemanagement approaches have to be acquired and applied thoroughly especially by CM.

The extents to which CM are expected to be competent have been vexing due to themany variables that can impact the way the construction management is carried out at theproject site. This includes the size and value of the project, location, procurement system,type of work, resources availability, and duration of the project (Hassan, 2005). Adding on tothese variables in Malaysian construction industry is the classification of contractors

Element Characteristic Management approach by CM

Period Have definite start and end Need to be properly managedProduct/services Unique development for new or existing building In line with client’s requirementsCriticalcomponents

Time, cost, quality, scope, and resources Need to be balanced and inequilibrium

Main resources Manpower, materials, machines, and money Need to be properly utilised andmanaged

Medium Appropriate knowledge, skills, tools, and techniques Need to be properly acquired andapplied

Environment Complex, dynamic, uncertain, demanding Inclusion of risk management,change management, etc.

Phases From notice of advertising (tendering to bidding) toinspection and acceptance of project

Need to be properly managed

Table I.Characteristicsof constructionmanagement

155

Constructionmanager’stechnical

competencies

Page 26: Engineering, Construction and Architectural

according to the size/value of projects and types of construction projects they are allowed toundertake (Construction Industry Development Board Malaysia, 2012; KementerianKewangan Malaysia, 2012). There are seven (7) classes of contractors, and this ranges fromG1 to G7 contractors (Contractors and Levy Division, Construction Industry DevelopmentBoard Malaysia, 2016). The range of project’s value which the contractors are allowed toundertake are as follows: G1oRM200,000; G2oRM500,000; G3oRM1,000,000;G4oRM3,000,000; G5o5,000,000; G6oRM10,000,000; and no limit for G7 contractors.Within each class, contractors are further classified into areas of specialisation which rangesfrom civil engineering, building, and mechanical and electrical works. These variables havenot been helpful in assisting the industry in identifying the competencies expected of theCM, and further complicates the design of their education and training provisions (Hassan,Maisham, Khan, Alwi and Ramli, 2010; Hassan, Samad, Hassan, Che Mat and Isnin, 2010).

3. CompetencyWhite (1959) defined the term “competence” as a concept for performance motivation. Laterin the 1970s, the concept had been further elaborated by Lundberg (1972) in “Planning theExecutive Development Program” and David McClelland (1973) through a seminal paperentitled “Testing for Competence Rather than for Intelligence”. It has since been popularisedby Richard Boyatzis and many others, such as Gilbert (1978) who used the concept inrelationship towards performance improvement. Later, its use varies widely and ratherspawned which leads to considerable misunderstanding. Nevertheless, competence orcompetency has been extensively discussed particularly in the literature of managementstrategy since the 1990s (Deist and Winterton, 2005). Its concept is frequently used in thearea of education, as well as training and continuing professional development, largely inestablishing a new or improvise an existing educational method as described by Hassan,Maisham, Khan, Alwi and Ramli (2010), Hassan, Samad, Hassan, Che Mat and Isnin (2010)and Stoof et al. (2002).

Cambridge Advance Learner’s Dictionary defines the term “competency” as “the abilityto do something well” or “an important skill that is needed to do a job” (CambridgeUniversity Press, 2008). A quite similar definition by Boyatzis (2008) also echoed oncapability or ability with regard to competency. Furthermore, according to Hager andGonczi (1996), competency concept is an integrated approach by blending tasks involvedand attributes, where preceding identification of knowledge, skills, attributes, and attitudescan be envisaged comprehensively. Hackett (2001), on the other hand, had been suggestingcompetency concept as having a single pillar named attributes. Attributes may come in acohesive form of skills, knowledge, and attitudes in order to visualise the overall attributesof a worker. Next, a constructivist approach was mooted by Stoof et al. (2002) due to theargument of “one size – does not fit all”. They have asserted that three variables, namely thepeople, the goals, and the overall context need to be cohesive, through the inclusion ofinside-out approach (that based on several dimensions), and the outside-in approach(based on several terminological hygienes) (Stoof et al., 2002). Meanwhile, Potgieter andVan Der Merwe (2002) asserted that competence comprises three key elements whichinclude performance in diverse settings, achievement of outcomes, and specific skills andstandards. They recommend that in job settings, competence can be regarded as the skilland ability of a person to perform and cope with job demands in the workplace effectively.Apart from that, multiple-dimensional competency was suggested by Deist and Winterton(2005), where the inclusion of knowledge (or cognitive), skills (or functional), attitudes(or social competence), and meta-competence (e.g. person’s personality, and learning tolearn) were deemed important. Nevertheless, a recent work by Dogbegah et al. (2009) on taskperformance competency is focussing on input competency, output competency, and alsopersonal competency in order to encapsulate entire job-specific competency. Finally, to

156

ECAM25,2

Page 27: Engineering, Construction and Architectural

simplify conceiving competency, Hassan, Maisham, Khan, Alwi and Ramli (2010) dividecompetency into technical and behavioural competencies. Technical competency consists ofhard skills and knowledge, while behavioural competency comprises soft skills and abilities.

The review of the related literature found that ideas and thinking surrounding the notionof competence is not uniform and has different meanings in different contexts that can only bedefined and measured through its intended usage and function. Notwithstanding, common inthe literature that knowledge, skills, and abilities (including attitudes) are the primaryelements of competency (Hassan, Maisham, Khan, Alwi and Ramli, 2010; Hager and Gonczi,1996; Mansfield, 1996; Egbu, 1999), whilst knowledge and skills are the “visible” elements ofcompetency (Hassan, Maisham, Khan, Alwi and Ramli, 2010; Deist andWinterton, 2005; Stoofet al., 2002). Being categorised as a technical or hard competency, knowledge and skills arenoticeable and teachable competencies since they can be flourished easily through propertraining and education. In term of a learning curve, technical competency requires muchshorter time to acquire as opposed to non-technical competency (Rudarakanchana et al., 2015).Unfortunately, although technical competency (i.e. knowledge and skills) is more critical to beaccomplished as compared to the non-technical competency (i.e. soft skills, abilities, andattitudes) regarding matching individuals with their job scopes, it is often ignored by thecommon competency approaches (Mansfield, 1996). This excessive emphasis on previouscompetency models on non-technical competency has relatively declined the significanceaspects of technical competency. Likewise, it necessitates substantial endeavour to determinethe overall competencies for a certain workforce extensively. Therefore, a focus on technicalcompetency and a rather modest yet comprehensible competency concept by Hassan,Maisham, Khan, Alwi and Ramli (2010) are reckoned by the authors to be appropriate forsubsequent discussion. Separation of competency into technical and non-technical are indeedcomprehended and much simpler to be deliberated (see Figure 1). Technical competencyconsists of hard skills and knowledge, whereby non-technical competency entails softskills and abilities.

To delve deeper into the gist of technical competency, it was defined as the ability toapply techniques and procedures (Isa, 2007). Within the context of construction projectmanagement, technical competency is the knowledge and skills that are pure constructionrelated such as estimating, scheduling, project management, cost management, constructionmaterials, and equipment utilisation (Isa, 2007; Ahn et al., 2010; Wandahl and Ussing, 2010).Identification of technical competency through analysis of production process including keytasks or work outputs will eventually outlay the required knowledge and skills (Hassan,2005; Mansfield, 1996; Mullin and Williams, 2010). In the interim, outside the context oftechnical competency, non-technical competency emerges as a collection of quality largelyrelated to human (Isa, 2007; Lee et al., 2011). Non-technical competency is usually referred toas the “softer” part of competency, where soft skills and worker’s abilities dominate. Sincethey are very much depending on how an individual reacted to others, Akintoye (1998)

Competency

Technical

Non-technical

Hard skills

Knowledge

Soft skills

Abilities

Figure 1.The overall concept of

competency

157

Constructionmanager’stechnical

competencies

Page 28: Engineering, Construction and Architectural

expressed the importance of their development that needs to be individually andcontextually (Mullin and Williams, 2010). Contextual in the sense of local factors, economic,environmental or political circumstances may project different needs or application towardsthat of non-technical competency. There are several generic non-technical competenciessuch as leadership, communication, motivation, writing, team working, and listening (Egbu,1999; Wandahl and Ussing, 2010; Mullin and Williams, 2010; Gunderson et al., 2002).

In highlighting the importance of technical competency to be apprehended by managers,Egbu (1999) has come up with the definition of both elements of technical competency,namely knowledge and skills. He defines knowledge as “the ideas, wisdom, and factsmanagers acquire through experience, theory, and practice; the acquisition of which givesthem an ability to understand”, whereas skills as “the activities or patterns of behaviourwhich managers undertake in order to accomplish a given desired outcome”. A quite similarinterpretation by Nonaka on knowledge, where he encapsulated knowledge into two generaltypes; tacit and explicit. Tacit knowledge is regarded as subjective and experience-basedknowledge, while explicit knowledge is considered as objective and rational knowledge(Nonaka, 1997). Separately, Lex et al. (1997) are in the same boat with Egbu for skills, wherethey emphasised that a person without proper skills will not be able to produce similar joboutput against a skilled person. In conclusion, when relating knowledge to a certain activityor task, trainees should learn about the “know-how” without the need to physicallyimplement it yet. Furthermore, in many instances, a complete “know-how” can be achievedthrough the integration of knowledge. On the other hand, skills involve the use of humananatomy (e.g. hand and leg) and things, and can be enhanced by repeated practices, actions,and conducts. Due to the complimentary nature of both knowledge and skills in projectmanagement, knowledge becomes the basic principle for the formulation of skills. In mostoccasions, a variety of knowledge and skills may be required to perform a complex task.Thus, it is clear that acquiring knowledge and skills is a matter of the utmost importanceabout the technical competency of CM.

4. Past researches on CMs competencyThe importance of managers’ competency towards project success is well documented byothers. Particularly within the construction realm, Ashley et al. (1987) found that manager’scompetency is significant in determining project success. Later, according to Chua et al.(1999), competency of manager is critical although projects may have different objectives.Furthermore, most identified critical success factors are human-related, where thecompetent manager is among the top (Nguyen et al., 2004). This view was also supported byChan and Kumaraswamy (1997) and Toor and Ongunlana (2008), where competency isfundamental to project success. However, a work by Cheng et al. (2000) stressed thatpossessing adequate competency is not just critical to the manager, but to all participants ofthe project. Thus, equilibrium of adequate competency level among participants is preferredto achieve predetermined objectives.

With regard to construction management, unfortunately, there is quite someaccompanying literature that pointed out the inadequacy of formal learning forconstruction management, which in turn resulting in the detrimental nature of theindustry itself (Ahn et al., 2010; Benhart and Shaurette, 2011). The argument was alsosupported by several researchers which stressed that the lack of competency andunqualified construction workforces are situational needs that triggered the call for theformalisation of construction-related learning, which skills standardisation, knowledgeexpansion, and meeting the related challenges and problems had initially become the mainconcern (Russell et al., 2007; Elzalitni and Lees, 2007; Wang et al., 2008; Justelian, 2009;Graham et al., 2011; Chinowsky and Diekmann, 2004). Thus, a review in the common area ofproblems on the particular programme shows that the predicament stems from the

158

ECAM25,2

Page 29: Engineering, Construction and Architectural

curriculum development process where the essential part lies in the contents generation,which fundamentally related to the competency identification. It was observed that the lackof apposite term of references on the competency for CM becomes the major setback. Most ofthe literature highlighted the needs to reconsider prior to identifying competency which wasembedded in the learning process and stressed the importance of infusing feedbacks fromacademic and industry participants. In a consistent relation, McDaniel (2005) has developeda model to demonstrate the magnitude of competency identification as a crucial deliberationin designing a curriculum for CM.

Through the authors’ in-depth observation, collectively, a qualitative-to-quantitativeapproach is being preferred by the majority. Qualitative compilation from previousresearches and legitimate documents and some through interviews provide a context-richcompetency for CM aligned with the predetermined scopes. Following that, questionnairesurveys are the preferred choice for quantitative undertakings. In addition, clustering ofCM’s competency into its meaningful groups was also observed, either via constructionproject stages (Riggs, 1998; Arditi et al., 2009), or through suggestion by past researchers(Isa, 2007; McDaniel, 2005), or based on the nature of the competency itself (Farooqui andSaqib, 2010), or according to computational mathematical formula towards quantitativedata (Dogbegah et al., 2009; Ahn et al., 2010). Nonetheless, there was evidence that theclustering efforts is beyond the unique construction management’s phase, less focussed ontechnical/non-technical competency, unsuitable clusters which prone to difficulty duringcurricular design, and side lining the key party in the construction phase, namely thecontractor (Mohammad et al., 2016). Thus, initial conceptualisation of particular competencyidentification was upheld by the authors as paramount due to issues stated earlier.

Therefore, it is obvious that the success of any construction project is very muchdependent on the CM who should comprehensively and adequately possess technical(i.e. hard skills and knowledge) and non-technical (soft skills and abilities) competencies.Both of these competencies would assist the CM to perform their roles and tasks moreprofessionally in the ever challenging construction world (Benhart and Shaurette, 2011).As such, appropriate undertakings in the establishment of the said term of reference areneeded. Therefore, based on earlier discussions, the authors limit the research only toencapsulate the construction management phase, where a focus on the key personrepresenting the contractor named the CM is being made and required competencyidentification will solitary covered their technical aspect.

5. Research methodologyA pragmatic study was employed through a combined research method (qualitative-quantitative), which include literature analysis, structured interview, and questionnaire survey,respectively, to the objectives as outlined in Section 1. Most of the works were guided byCreswell (2008) and several others which were cited accordingly in this paper.

5.1 Literature analysisInitially, identification of technical competency for CM was carried through rigorousliterature review incorporating a multi-layered thematic (MLT) process. MLT issynonymous to qualitative analysis undertaking when analysing bulk informationgathered from the interview, document, and so on. Basically, during qualitative analysis,emerging themes are captured, and MLT is used to reduce initially identified themes intomore sophisticated ones (Creswell, 2008). However, as illustrated in Figure 2, the authorshave used MLT for predetermined themes identified in the literature and assisted by a loopfor data gathering process (Kariya et al., 2016). Themes were organised according to itsscopes and doubled as screening nets. The move was deemed sufficient to yield exhaustiveand holistic results, so as to ensure the reliability of literature analysis. Furthermore, given

159

Constructionmanager’stechnical

competencies

Page 30: Engineering, Construction and Architectural

the facts that subjective definitions given by past researchers for certain keywords aredirely needed for explanation in the form of example, MLT is seen as a valuable aid.

Layers as in Figure 2 are performed as guidance in sieving past researchers’ documents inidentifying CM technical competency items. For documents, no restriction has been made, butkeywords’ combination was employed during the searching process (i.e. constructionmanagement + education and training + competency). For Layer 1, themes generated fromSection 2 were utilised especially regarding the boundary of the construction phase. Thus, forexample, any competency that is beyond the boundary will be ignored. Subsequently, Layer 2will be focussed only on themes generated from technical competency’s themes, including itsdefinition/concept, and given examples by previous researchers. Later, due to the gist oftechnical competency which comprises knowledge and skills, the authors attempt todifferentiate initial collected technical competency into both elements in Layer 3. The movewas believed to strengthen preceding findings in Layer 2 and clarify their differences which ina way useful for programme development. Then, Layer 4 is dedicated to cluster prior technicalcompetency into meaningful group helped by suggestions from past researchers includingIsa (2007), since it was the closest validated work on CM competency in Malaysia. Afterwards,quality measures were imposed to data within each loop iteration (i.e. for each literature) andat the end of the whole processes. Actions such as reassessment according to layers andimprovisation of clusters’ paradigm were conducted to this layer.

5.2 InterviewThe second phase of the methodology employed interview as an instrument. As feedbacksfrom local academic-industry experts are concerned, further exploration of the related centralphenomenon and thus validating prior technical competencies of CM identified from literatureanalysis is paramount (Creswell, 2007, 2008). The respondents were deliberately selected tosuit the delineated criteria which include their current position in the organisation, theircumulative experience of at least ten years, their familiarity with CM, and their availability tothe researcher. Two types of questions were constructed, namely close-ended which is to seekaffirmatory on all observed technical competencies in the form of a checklist with adichotomous indicator, and open-ended which is to explore possible additional technicalcompetency. Both of the types are deemed to complement each other within acceptableone-on-one interview’s time frame since the length of the checklist is concerned by the authors.Since the authors are inclined to use manual type of qualitative undertaking due to the natureof questions that is requiring relatively brief answers, respondents’ feedbacks were recordedby using pen and paper, and later transcribed and typed them into a computer file.

ConstructionManagement

phase

Technicalcompetency

Knowledgeand skills

Preliminaryclusters

Qualitymeasures

Mal

aysi

an C

Mte

chni

cal c

ompe

tenc

y

Past

-rel

ated

lite

ratu

res

(ref

er to

Sec

tion

6.1)

Layer 1 Layer 2 Layer 3 Layer 4 Layer 5

Refer to Section 2• Table I• Phase’s boundary• Etc.

Refer to Section 3• Figure 1• Definitions/concept• Examples• Etc.

Refer to Section 4• Suggestion by past researchers• Particularly Isa (2007)

Reassessmentandimprovisation

Continuous loop

Figure 2.Multi-layered thematic(MLT) process withcontinuous loop

160

ECAM25,2

Page 31: Engineering, Construction and Architectural

Afterwards, the analysis was done manually with minimal thematic analysis effort as mostrespondents expressed similar opinions and the summary of results was tabulated. Theparticular interview approach is believed to be appropriate as it could minimise time andeffort from both parties (i.e. interviewer and interviewee). Prior to the actual interview, initialcomments on pre-submission of interview script to the respondents were obtained, and slightmodifications were made to the final interview scripts.

5.3 Questionnaire surveyThe third phase of research entailed mass distribution of questionnaire survey toconstruction practitioners around the state of Johor. The aims for mass distribution ofquestionnaire surveys were to analyse indigenous contractors’ perception towards theimportance of technical competency of CM, and also as an endeavour to validate andgeneralise the findings to the masses (at least over the state of Johor). Accordingly,importance level was chosen as the dependent variable, and technical competency as anindependent variable, whereas contractors’ category and grade as control variables.Moreover, structured questions on technical competency were developed in neutralintonation throughout five-point Likert scale without an option of the neutral answer. Allquestions were prepared in dual languages (i.e. English as the main language, and Malay asa secondary language) in order to cater for the different convenience of respondents. Then,stratified purposive sampling is selected, along with multiple distributional efforts includingonline-based and self-administrated route.

Additionally, the authors did not incline to distribute detail breakdown of technicalcompetency for validation and generalisation in this phase since time completion andresponse rate were the major hindrances. Furthermore, a complete breakdown of technicalcompetency had already been shared and inspected during previous interview sessions.However, full exertion is being given during preparation of questionnaire construct in orderto present entire paradigm of CM technical competency accordingly to previously identifiedclusters. Guidance for the respective respondents regarding the lower level of competencyhierarchy is prepared in the questions by using keywords within bracket’s representation “( )”.To ensure its reliability, the questionnaires were initially undergone a small pilot test towards10 representatives from several contractors. After thorough considerations had been takencare of, and the pilot test presented reliable results, the final version of questionnaires werereprinted and distributed.

Both methods of questionnaires distribution covered the entire state of Johor inorder to represent the opinions of the targeted respondents fairly. The combination ofself-administered and online survey deemed to be a better option to maximise response rate.Nevertheless, for self-administered distribution, the authors also pursuing assistances fromseveral parties including the officers of CIDB Johor and individuals, thus snowballing islikely presented. Meanwhile, for online survey, “Survey Monkey” as an online surveyprovider was selected. It became the main database frame to gather all responses since theonline software grants the simplicity of results generation. Layout for the electronic versionwas designed according to suggestion by Toepoel et al. (2009). At the same time, the onlinesurvey was carried out through e-mail. E-mail addresses of targeted respondents wereobtained from “Daftar Projek CIDB 2007-2012” which was published by the CIDB Malaysia,and only active contractors are considered regardless of their categories and grades(Lembaga Pembangunan Industri Pembinaan Malaysia, 2012). Online survey responseswere automatically included in the database, while self-administered responses were keyedin manually. Later, generation of results for both Microsoft Excel and SPSS formats weremade, and SPSS v.20 was utilised to ease the process of analysis. In order to treat themissing data and errors, the returned questionnaires were sieved where only fullycompleted results were accepted and processed further.

161

Constructionmanager’stechnical

competencies

Page 32: Engineering, Construction and Architectural

For analysis, careful considerations had been made to preserve the originality of datathrough suitable descriptive analysis. Since collected data were ordinal in nature, thereforethe non-parametric type of analysis is preferred. As confirmations, data screening processhad been done through reliability test and outlier test, accordingly. Outliers are extremevalues as compared to the rest of the data and are capable of showing if there is any singleitem that has extremely recorded data which might disturb the rest of the analysis. Outlierscan be pre-analysed by looking at the mean, 5 per cent trimmed mean (by removing5 per cent of extreme data), and interquartile range (IQR) where IQR value of more than 3 isconsidered extreme value (Dawson, 2011; Walfish, 2006). Then, the importance of technicalcompetencies for CM was analysed up to the macro level, and contractor’s grades werefurther categorised into small, medium, and large size as suggested by Isa (2007), to simplifythe findings. Meso-level items (with 34 nos.) were reduced to macro-level items (with 16 nos.)by using a function of “compute-median” in SPSS. Then, the authors selected mean value asa central tendency which will be shown along with its individual standard deviations (SDs)and ranks.

6. Results and analysisGiven that the research has several pertinent phases, this section is divided accordingly intothree sub-sections, namely literature analysis, interview, and questionnaire survey.

6.1 Literature analysisThe authors have selected and analysed a number of closely related literatures (Love andHaynes, 2001; Isa, 2007; Egbu, 1999; Ahn et al., 2010; Wandahl and Ussing, 2010; Mullin andWilliams, 2010; Lee et al., 2011; Gunderson et al., 2002; Benhart and Shaurette, 2011; Riggs,1998; Arditi et al., 2009; Farooqui and Saqib, 2010; Fester and Haupt, 2008; Gunderson, 2008;Hauck, 1998; Waluyo, 2007; Souder and Gier, 2006; Koch and Benhart, 2010; Young, 1993;Construction Management Association America, n.d.). All literature were individuallysieved through prior constructed MLT process and concluded with 271 of technicalcompetency items (micro level). Subsequently, all items were grouped into 34 items (mesolevel) and further clustered under 16 elements (macro level). Clusters were formed accordingto suggestion by past researchers which centred on general construction project’s resources,objectives, general tasks, and essential competency. Hence, Table II summarises theidentified CM’s technical competencies resulted from the process (up to meso level) whichable to offer simplistic and perceptive views.

6.2 InterviewConcerning the second phase of research method, a total of nine experts had involved inthe interview sessions. The interviewees or experts are three academicians and sixconstruction practitioners. All academicians were senior lecturers teaching constructionmanagement subject, whereas all practitioners were senior professionals in theirrespective legitimate positions within construction companies (i.e. three CM, a projectmanager, a contract manager, and an engineer). All interview respondents have aptlyfollowed criteria set by the authors and able to identify CM competency. Averagely lastedfor an hour, each interview sessions were conducted within the convenience of theinterviewees. For close-ended questions, the interviews demonstrated that all respondentswere collectively agreed with a prior collection of CM technical competency. Of all the271 items along with their prescribed elements and clusters, answers of “yes” wererecorded throughout. Meanwhile, for open-ended questions, a large majority ofrespondents expressed that the collection is adequate without the need for additionalitems. A brief answer to “no, it was ok” was mostly recorded. However, slightly different

162

ECAM25,2

Page 33: Engineering, Construction and Architectural

Macro

level

Cluster

Elements

Mesolevel

Literature

Resources

Staff

Knowledg

eandskillsof

staffmanagem

ent

(i.e.developm

ent,welfare,law

s,etc.)

Isa(2007),E

gbu(1999),W

andahl

andUssing(2010),L

eeetal.(2011),

Riggs

(1998),F

arooqu

iand

Saqib(2010),Y

oung

(1993),C

onstruction

Managem

entAssociatio

nAmerica(n.d.)

Materials

Knowledg

eof

constructio

nmaterials(i.e.concrete,steel,

wood,

soil,etc.)

Ahn

etal.(2010),Wandahl

andUssing(2010),G

underson

etal.(2002),

BenhartandSh

aurette(2011),F

arooqu

iand

Saqib(2010),G

underson

(2008),H

auck

(1998),C

onstructionManagem

entA

ssociatio

nAmerica

(n.d.)

Knowledg

eandskillsof

materialsmanagem

ent

(i.e.procurem

ent,logistics,supp

lier,etc.)

Isa(2007),E

gbu(1999),G

underson

etal.(2002),Benhartand

Shaurette(2011),A

rditi

etal.(2009),Fa

rooqui

andSaqib(2010),K

och

andBenhart(2010),Y

oung

(1993),C

onstructionManagem

ent

Associatio

nAmerica(n.d.)

Labour

Knowledg

eandskillsof

labour

managem

ent

(i.e.productiv

ity,w

elfare,law

s,etc.)

Isa(2007),E

gbu(1999),W

andahl

andUssing(2010),L

eeetal.(2011),

BenhartandSh

aurette(2011),R

iggs

(1998),F

arooqu

iand

Saqib

(2010),K

ochandBenhart(2010),C

onstructionManagem

ent

Associatio

nAmerica(n.d.)

Plant/equ

ipment

Knowledg

eof

constructio

nplant/equ

ipmentandtheir

utilisatio

nAhn

etal.(2010),Fa

rooqui

andSaqib(2010),H

auck

(1998),

Constructio

nManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eandskillsof

plantmanagem

ent

(i.e.requ

isition,m

aintenance,sup

plier,etc.)

Isa(2007),E

gbu(1999),A

rditi

etal.(2009),Fa

rooqui

andSaqib(2010),

Young

(1993),C

onstructionManagem

entAssociatio

nAmerica(n.d.)

Subcontractor

(includ

ingNSC

)Knowledg

eandskillsof

sub-contractor

managem

ent

(i.e.claimsandpaym

ents,v

ariatio

ns,insurances,etc.)

Isa(2007),E

gbu(1999),R

iggs

(1998),A

rditi

etal.(2009),Gun

derson

(2008),H

auck

(1998),K

ochandBenhart(2010),C

onstruction

Managem

entAssociatio

nAmerica(n.d.)

Knowledg

eandskillsof

sub-contractor

tend

eringand

bidd

ing(i.e.procedures,pretend

er,bidanalysis,quantity

take-off,etc.)

Isa(2007),E

gbu(1999),G

underson

etal.(2002),Riggs

(1998),A

rditi

etal.(2009),Fa

rooqui

andSaqib(2010),F

esterandHaupt

(2008),

Constructio

nManagem

entAssociatio

nAmerica(n.d.)

Responsible

for/objectives

Safety

Knowledg

eof

health

andsafety

equipm

entandmanualIsa(2007),E

gbu(1999),A

hnetal.(2010),Mullin

andWilliams(2010),

Gun

derson

etal.(2002),Fa

rooqui

andSaqib(2010),H

auck

(1998),

Soud

erandGier(2006),K

ochandBenhart(2010),C

onstruction

Managem

entAssociatio

nAmerica(n.d.)

Knowledg

eandskillsof

health

andsafety

managem

ent

(i.e.practices,com

pliance,regu

latio

n,training

,etc.)

Isa(2007),E

gbu(1999),A

hnetal.(2010),Mullin

andWilliams(2010),

Leeetal.(2011),Gun

derson

etal.(2002),Arditi

etal.(2009),Fa

rooqui

(con

tinued)

Table II.Technical competencyof CM: differentiationbetween macro level

and meso level

163

Constructionmanager’stechnical

competencies

Page 34: Engineering, Construction and Architectural

Macro

level

Cluster

Elements

Mesolevel

Literature

andSaqib(2010),H

auck

(1998),S

ouderandGier(2006),K

ochand

Benhart(2010),C

onstructionManagem

entA

ssociatio

nAmerica(n.d.)

Knowledg

eandskillsof

risk

managem

ent

(i.e.assessmentandanalysis,etc.)

Isa(2007),E

gbu(1999),L

eeetal.(2011),Fa

rooqui

andSaqib(2010),

Constructio

nManagem

entAssociatio

nAmerica(n.d.)

Money

Knowledg

eandskillsof

financialandcostmanagem

ent

(i.e.claimsandpaym

ents,p

ricing

andpu

rchasing

practice,etc.)

Isa(2007),E

gbu(1999),A

hnetal.(2010),Wandahl

andUssing(2010),

Mullin

andWilliams(2010),G

underson

etal.(2002),Benhartand

Shaurette(2011),R

iggs

(1998),A

rditi

etal.(2009),Fa

rooqui

andSaqib

(2010),F

esterandHaupt

(2008),G

underson

(2008),K

ochandBenhart

(2010),Y

oung

(1993),ConstructionManagem

entA

ssociatio

nAmerica

(n.d.)

Quality

Knowledg

eof

constructio

nspecificatio

ns,T

QM,

build

ingcodesandstandards,etc.

Isa(2007),E

gbu(1999),W

andahl

andUssing(2010),G

underson

etal.

(2002),B

enhartandSh

aurette(2011),A

rditi

etal.(2009),Fa

rooquiand

Saqib(2010),F

esterandHaupt

(2008),K

ochandBenhart(2010),

Young

(1993),C

onstructionManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eandskillsof

quality

managem

ent

(i.e.administration,

assurance,qu

ality

control,etc.)

Isa(2007),E

gbu(1999),W

andahl

andUssing(2010),G

underson

etal.

(2002),A

rditi

etal.(2009),Fa

rooqui

andSaqib(2010),F

esterand

Haupt

(2008),K

ochandBenhart(2010),Y

oung

(1993),C

onstruction

Managem

entAssociatio

nAmerica(n.d.)

Tim

eKnowledg

eandskillsof

timemanagem

ent(i.e.

understand

ingof

projectschedu

ling,

updatin

g,etc.)

Love

andHaynes(2001),Isa

(2007),E

gbu(1999),A

hnetal.(2010),Lee

etal.(2011),Gun

derson

etal.(2002),BenhartandSh

aurette(2011),

Farooqui

andSaqib(2010),F

esterandHaupt

(2008),G

underson

(2008),H

auck

(1998),W

aluy

o(2007),Soudera

ndGier(2006),Kochand

Benhart(2010),C

onstructionManagem

entA

ssociatio

nAmerica(n.d.)

Env

ironment

Knowledg

eandskillsof

environm

entmanagem

ent

(i.e.assessment,environm

entmanagem

entsystem

(EMS),etc.)

Love

andHaynes(2001),Isa

(2007),M

ullin

andWilliams(2010),L

eeetal.(2011),Gun

derson

etal.(2002),Fa

rooqui

andSaqib(2010),

Constructio

nManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eof

greenandsustainableconstructio

n(i.e.Green

BuildingIndex(GBI),

greenconstructio

ntechniqu

es,etc.)

Love

andHaynes(2001),A

hnetal.(2010),Mullin

andWilliams(2010),

Leeetal.(2011),Fa

rooqui

andSaqib(2010)

General

constructio

nAdm

inistration

Knowledg

eandskillsof

constructio

nadministration

(i.e.documentatio

nandrecord,sub

missions,plans/

draw

ings,m

eetin

g,etc.)

Isa(2007),L

eeetal.(2011),Gun

derson

etal.(2002),Benhartand

Shaurette(2011),R

iggs

(1998),A

rditi

etal.(2009),Fa

rooqui

andSaqib

(con

tinued)

Table II.

164

ECAM25,2

Page 35: Engineering, Construction and Architectural

Macro

level

Cluster

Elements

Mesolevel

Literature

managem

ent

task

(2010),H

auck

(1998),S

ouderandGier(2006),K

ochandBenhart

(2010),C

onstructionManagem

entAssociatio

nAmerica(n.d.)

Pre-constructio

nKnowledg

eandskillsof

constructio

nsitesurveying,site

layout,tem

porary

structures/work,

etc.

Isa(2007),E

gbu(1999),G

underson

etal.(2002),Benhartand

Shaurette(2011),F

arooqu

iand

Saqib(2010),F

esterandHaupt

(2008),

Hauck

(1998),W

aluy

o(2007),S

ouderandGier(2006),Y

oung

(1993),

Constructio

nManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eandskillsof

constructio

nsite

managem

ent

(i.e.overallresources

managem

ent,masterprogramme,

constructio

nsequ

ences,workbreakd

ownstructure,

projectstart,meetin

gs,etc.)

Love

andHaynes(2001),Isa

(2007),E

gbu(1999),A

hnetal.(2010),

Mullin

andWilliams(2010),L

eeetal.(2011),Gun

derson

etal.(2002),

BenhartandSh

aurette(2011),R

iggs

(1998),A

rditi

etal.(2009),

Farooqui

andSaqib(2010),F

esterandHaupt

(2008),G

underson

(2008),H

auck

(1998),W

aluy

o(2007),Soudera

ndGier(2006),Kochand

Benhart(2010),Y

oung

(1993),C

onstructionManagem

entA

ssociatio

nAmerica(n.d.)

Knowledg

eof

civila

ndstructural

design

Gun

derson

etal.(2002),BenhartandSh

aurette(2011),F

esterand

Haupt

(2008),H

auck

(1998),C

onstructionManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eof

constructio

nsystem

s(i.e.Indu

strialised

BuildingSy

stem

(IBS),etc.)

Love

andHaynes(2001),W

andahl

andUssing(2010),M

ullin

and

Williams(2010),L

eeetal.(2011),Gun

derson

etal.(2002),Benhartand

Shaurette(2011),F

arooqu

iand

Saqib(2010),F

esterandHaupt

(2008),

Gun

derson

(2008),H

auck

(1998),W

aluy

o(2007),K

ochandBenhart

(2010),C

onstructionManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eof

mechanicala

ndelectrical

system

sGun

derson

etal.(2002),Fester

andHaupt

(2008),H

auck

(1998),

Constructio

nManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eof

quantitysurveying

Gun

derson

etal.(2002),Fester

andHaupt

(2008),H

auck

(1998)

Knowledg

eof

valueengineering(i.e.to

elim

inate

unnecessarycostwhich

does

notcontributeto

thevalue

ofconstructio

n)

Leeetal.(2011),Fa

rooqui

andSaqib(2010),C

onstruction

Managem

entAssociatio

nAmerica(n.d.)

Knowledg

eof

constructability(i.e.analysisof

constructio

ncoordinatio

nissues

associated

with

various

trades)

Leeetal.(2011),Fa

rooqui

andSaqib(2010),K

ochandBenhart(2010),

Constructio

nManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eof

lean

constructio

n(i.e.applicationof

productio

nmanagem

entto

constructio

n)Leeetal.(2011)

(con

tinued)

Table II.

165

Constructionmanager’stechnical

competencies

Page 36: Engineering, Construction and Architectural

Macro

level

Cluster

Elements

Mesolevel

Literature

Closeout

andhand

over

Knowledg

eandskillsof

constructio

ncloseout

and

hand

over

procedures

(i.e.managem

ent,commissioning,

acceptance,transfer,etc.)

Arditi

etal.(2009),Fa

rooqui

andSaqib(2010),K

ochandBenhart

(2010),C

onstructionManagem

entAssociatio

nAmerica(n.d.)

Responsibilitiesto

3rd

parties,main

contractor,client,clerk

ofworkanddesign

er

Knowledg

eandskillsof

constructio

nlawandlegislation

(i.e.authorities

processing

,etc.)

Isa(2007),E

gbu(1999),W

andahl

andUssing(2010),M

ullin

and

Williams(2010),G

underson

etal.(2002),Arditi

etal.(2009),Fa

rooqui

andSaqib(2010),W

aluy

o(2007),K

ochandBenhart(2010),Y

oung

(1993),C

onstructionManagem

entAssociatio

nAmerica(n.d.)

Knowledg

eandskillsof

constructio

nbu

sinesses

(i.e.sales,commercial,trades,econom

icanalysis,etc.)

Wandahl

andUssing(2010),M

ullin

andWilliams(2010),G

underson

etal.(2002),Fa

rooqui

andSaqib(2010),F

esterandHaupt

(2008),

Waluy

o(2007),K

ochandBenhart(2010),Y

oung

(1993),C

onstruction

Managem

entAssociatio

nAmerica(n.d.)

Knowledg

eandskillsof

administering

andassisting/

facilitatingclient,seniormanager

andjunior

manager

(i.e.coordinatio

n,liaison

ofworks,orders,etc.)

Isa(2007),A

rditi

etal.(2009),Fa

rooqui

andSaqib(2010),K

ochand

Benhart(2010),C

onstructionManagem

entA

ssociatio

nAmerica(n.d.)

Overall

essential

competency

Compu

terandIT

Knowledg

eandskillsof

generalcom

puterapplication

(i.e.MSExcel,M

SOffice,Adobe,internetbased,

etc.)

Love

andHaynes(2001),E

gbu(1999),A

hnetal.(2010),Mullin

and

Williams(2010),G

underson

etal.(2002),BenhartandSh

aurette

(2011),F

arooqu

iand

Saqib(2010),F

esterandHaupt

(2008),

Gun

derson

(2008),H

auck

(1998),W

aluy

o(2007),S

ouderandGier

(2006),Y

oung

(1993)

Knowledg

eandskillsof

constructio

ninform

ation

technology

/softw

areapplication(i.e.MSProject,

Prim

avera,CA

D,scheduling,

estim

ating,

accoun

ting,

etc.)

Love

andHaynes(2001),E

gbu(1999),A

hnetal.(2010),Wandahl

and

Ussing(2010),M

ullin

andWilliams(2010),G

underson

etal.(2002),

BenhartandSh

aurette(2011),F

arooqu

iand

Saqib(2010),F

esterand

Haupt

(2008),G

underson

(2008),S

ouderandGier(2006),Y

oung

(1993),C

onstructionManagem

entAssociatio

nAmerica(n.d.)

Constructio

ncontract

administration

Knowledg

eandskillsof

constructio

ncontracts

(i.e.administration,

document,variations,extension

oftim

e,claimsandpaym

ents,sub

-contracts,conflicts,etc.)

Egb

u(1999),W

andahl

andUssing(2010),L

eeetal.(2011),Benhart

andSh

aurette(2011),R

iggs

(1998),A

rditi

etal.(2009),Fa

rooqui

and

Saqib(2010),F

esterandHaupt

(2008),H

auck

(1998),W

aluy

o(2007),

Soud

erandGier(2006),K

ochandBenhart(2010),C

onstruction

Managem

entAssociatio

nAmerica(n.d.)

Table II.

166

ECAM25,2

Page 37: Engineering, Construction and Architectural

responses were observed for Academician 1 and Academician 2. Both academiciansuttered the need for the inclusion of nominated sub-contractor (NSC) within theirrespective element. Answers of “do you consider the NSC?” are repeated twice, on thebasis that management of NSCs is quite different from that of normalsub-contractors. On the other hand, Academician 2 have also suggested for the additionof management of construction wastages (e.g. from materials, labours, etc.) within the list,as concerned with sustainability is on the rise. Therefore, all suggestions were analysedand critically taken into considerations. Minimal changes were made without jeopardisingprior structure of CM technical competency elements.

6.3 Questionnaire surveyThe final version of questionnaire scripts was initially distributed to ten (10) constructionpractitioners as a pilot survey in order to seek for the internal reliability of the questionsbefore they were ready for mass distribution. Reliability analysis by using SPSS hadresulted in Cronbach α of 0.977 for all questions, which indicate that they would be able tomeasure the research’s intended objectives (Gliem and Gliem, 2003; Tavakol and Dennick,2011). A total of 300 questionnaires had been distributed through a combination of onlineand self-administered options.

From Table III, regardless of the contractor representatives’ demographics, a responserate of 33.67 per cent had been achieved through 101 collected and completedquestionnaires. Moreover, it has been observed that the contractors’ organisation mighthave more than a single category/specialisation, as the total number of responses (135 nos.)was more than the collected questionnaires (101 nos.). Meanwhile, seven grades of the

Details Test/data Results Total

Pilot survey Reliability (α) 0.977 –Actual survey Reliability (α) 0.979

Highest IQR 2Accepted responses/distributed 101/300Percentage of response (total) 33.67%Category of contractors Civil engineering 47 135

Building construction 70Mechanical and electrical 18

Grade of contractors Small G1 (tendering ⩽ RM200,000.00) 9 101G2 (tendering⩽RM500,000.00) 8G3 (tendering⩽RM1 million) 15

Medium G4 (tendering⩽RM3 million) 12G5 (tendering⩽RM5 million) 13

Large G6 (tendering⩽RM10 million) 10G7 (tendering¼ no Limit) 34

Position of respondents Director/executive director/executive chairman/corporate manager 29 101Project manager/project coordinator 17Contract manager/contract executive 5CM/construction coordinator/constructionsuperintendent 6Site manager/site agent 7Site supervisor/clerk of work 17Architect/engineer/quantity surveyor 20

Experience of respondents 4 years and below 20 1015-9 years 3210 years and above 49

Table III.Summary ofrespondents’

demographics

167

Constructionmanager’stechnical

competencies

Page 38: Engineering, Construction and Architectural

contractor were further categorised into small (with 32 nos.), medium (with 25 nos.), andlarge size (with 44 nos.). Apart from that, the majority of respondents were from topmanagement level within their organisation (i.e. director), whereas the least were frommiddle management level (i.e. contract manager, CM, and site manager). Most of them werehaving more than ten years of working experience.

Subsequently, screening of data through reliability test and outlier test were conducted.The calculated Cronbach’s α of all responses for each of the 34 items is 0.979, whichobviously depicted that internal reliability is maintained. Besides, through outlier test, datahave not shown any indication for the outlier, where the highest value for IQR is 2, and veryminimal differences were spotted between values of normal mean and 5 per cent trimmedmean. Therefore, the subsequent descriptive analysis was carried forward which includedall items (34 nos.) within the calculations. Nevertheless, in order to simplify the analysisprocesses without diminishing meaningful results, meso-level items (with 34 nos.) werereduced to macro-level items (with 16 nos.) within four main clusters, namely resources,responsible for/objectives, general construction management tasks, and overall essentialcompetency. Later, as shown in Tables IV and V, mean values were tabulated along withSDs and clusters’ ranks, respectively, to the category of construction organisations and theirsizes. In general, recorded means based on contractor’s categories (see Table IV) weremostly leaning between 4.00 (important) and 5.00 (very important). Only a value of sub 4.00(i.e. 3.700) is recorded specifically for computer and information technology (IT) in themechanical and electrical group. On the other hand, a similar pattern was visualisedtowards means based on contractor’s sizes (see Table V ). Despite majority, two values werebelow 4.00 (i.e. 3.92 and 3.94) specifically for plant and equipment, and environment inmedium size contractors.

7. DiscussionsIn this section, discussions were separated into two sections accordingly to the selectedmethodologies, namely qualitative and quantitative.

7.1 Qualitative methodsAs the literature reviews for the research is developed, it was deemed essential todifferentiate between knowledge and skills, and further grouped them according to thesuitable level, namely macro level, meso level, and micro level, respectively. Thus, asidentified and summarised in Table II, technical competency specifically for the CM arebelieved to be exhaustive and comprehensive. Helped by proper clustering approachtowards its elements, significant meanings for each cluster were visualised noticeably.Additionally, confirmation with local academic-industry experts through interviews wasjudged to support prior undertakings.

First, by focussing on the “Resources” cluster, it was agreed by many that there areseveral important resources that need to be managed properly by the CM, namely staff,materials, labour, plant and equipment, and sub-contractors. Some of the elements arerequiring proper embedment of knowledge (such as materials and plants/equipment) beforethe inclusion of knowledge and skills, especially towards their management paradigm. Forstaff, materials, labour, and plant management, common technical competency are requiredand expected to be equipped to the CM. Meanwhile, for sub-contractor, apart from havingtechnical competency on their associated general management, CM needs to have adequatecompetency regarding tendering and bidding within this element. As a key representative ofcontractor/main contractor, more often than not, engagement through a proper contractwith sub-contractors and NSC is inevitable. Large construction project might be parcelledout to a small section and sub-contracted to others. Additionally, works that requiredspecial trades (e.g. blacksmith, carpentry, etc.) are usually handled by competent groups

168

ECAM25,2

Page 39: Engineering, Construction and Architectural

CMtechnicalcom

petency(m

acro

level)

Resources

Responsiblefor/objectives

General

constructio

nmanagem

enttasks

Overallessential

competency

Category/

specialisation

Staff

Materials

Labour

Plantand

equipm

ent

Subcontractor

Safety

and

health

Money

Quality

Tim

eEnv

ironment

Adm

inistration

Pre-

constructio

n

Closeout

and

hand

over

Responsibility

tostakeholders

Compu

ter

andIT

Constructio

ncontract

Civilengineeringconstructio

nMean

4.51

4.57

4.53

4.31

4.48

4.55

4.64

4.49

4.62

4.31

4.53

4.37

4.43

4.31

4.33

4.43

SD0.72

0.71

0.65

0.72

0.61

0.78

0.67

0.68

0.61

0.78

0.62

0.55

0.65

0.52

0.65

0.68

Rank

31

25

43

14

25

13

24

21

Buildingconstructio

nMean

4.47

4.56

4.50

4.21

4.44

4.48

4.60

4.58

4.57

4.25

4.46

4.30

4.41

4.23

4.17

4.49

SD0.72

0.63

0.70

0.73

0.76

0.67

0.71

0.61

0.69

0.81

0.74

0.64

0.71

0.68

0.78

0.63

Rank

31

25

44

12

35

13

24

21

Mechanicaland

electrical

Mean

4.44

4.39

4.50

4.36

4.50

4.56

4.50

4.50

4.56

4.44

4.33

4.30

4.44

4.39

3.75

4.39

SD0.62

0.68

0.62

0.57

0.69

0.59

0.71

0.64

0.51

0.68

0.77

0.59

0.70

0.64

0.88

0.78

Rank

34

15

22

43

15

34

12

21

Table IV.Mean of importance

and ranks of technicalcompetency forCM based on

contractor’s categories

169

Constructionmanager’stechnical

competencies

Page 40: Engineering, Construction and Architectural

CMtechnicalcom

petency(m

acro

level)

Resources

Responsiblefor/objectives

General

constructio

nmanagem

enttasks

Overallessential

competency

Sizes

and

grades

Staff

Materials

Labour

Plantand

equipm

ent

Subcontractor

Safety

and

health

Money

Quality

Tim

eEnv

ironment

Adm

inistration

Pre-

constructio

n

Closeout

and

Handover

Responsibility

toStakeholders

Compu

ter

andIT

Constructio

ncontract

Small

Mean

4.56

4.59

4.75

4.44

4.53

4.71

4.63

4.59

4.69

4.58

4.63

4.44

4.56

4.52

4.14

4.47

SD0.62

0.61

0.44

0.58

0.63

0.41

0.61

0.53

0.47

0.53

0.61

0.50

0.56

0.49

0.75

0.72

Rank

32

15

41

34

25

14

23

21

Medium

Mean

4.08

4.26

4.16

3.92

4.16

4.08

4.40

4.40

4.12

3.94

4.28

4.07

4.08

4.08

4.08

4.40

SD0.86

0.83

0.75

0.79

0.77

0.99

0.76

0.82

0.73

0.77

0.74

0.68

0.64

0.69

0.84

0.71

Rank

41

25

34

12

35

14

23

21

Large

Mean

4.45

4.49

4.41

4.17

4.40

4.42

4.52

4.43

4.59

4.17

4.30

4.26

4.36

4.14

4.15

4.36

SD0.73

0.70

0.76

0.75

0.79

0.72

0.82

0.69

0.73

0.86

0.82

0.67

0.81

0.72

0.79

0.69

Rank

21

35

44

23

15

23

14

21

Table V.Mean of importanceand ranks of technicalcompetency forCM based oncontractor’s sizes

170

ECAM25,2

Page 41: Engineering, Construction and Architectural

through sub-contracts. Therefore, important competency related to their technicalprocedures and undertakings are seen as valuable to the CM.

Second, with regard to construction “Objectives”, the common analogy of time, money,and quality has now become too mainstream, due to the fact that elements of safety andenvironment have gained greater concerns. Nevertheless, among them, “quality” requiredthe embedment of adequate knowledge in order for the CM to execute their management jobeffectively. This includes knowledge of construction specifications, codes, and standards.Similarly, with safety and environment, sufficient knowledge regarding health andsafety equipment and associated manuals and guidelines (i.e. specifically for safety),and underlying concepts of environment (including sustainability approaches) are deemedparamount for the CM. Given that a large proportion of contractor’s works is executedon-site, technical competency regarding those elements are considered mandatory.

Third, the emphasis on “General construction management tasks” is on administration,pre-construction, closeout and handover, and responsibility to third parties, maincontractors, clients, clerk of work, and designer. All those elements significantlycontribute towards the delivery of any construction project. For instance, during thepre-construction stage where the overall plans are being prepared, roles of CM and reliancetowards their technical competency become apparent. By not just having adequate technicalcompetency related to construction site management, broad knowledge on civil andstructural, construction systems, mechanical and electrical, and quantity surveying are seenhelpful to encapsulate the particular task. Additionally, CM’s insight on value engineering,constructability, and also lean construction are somewhat emergently useful for ensuringsmoothness of day-to-day construction activities. On the other hand, as can be seen in thelast element (i.e. responsibilities), surprisingly that technical competency of relatedconstruction businesses are gaining acceptance and consideration to be equipped by theCM. A shift towards CM’s entrepreneur ability is expected by a number of past researchersdue to the dynamic nature of the industry and the responsibility held by CM to maintaintheir organisation’s competitiveness.

Last but not least, within the “Overall essential competency” cluster, two essential elementsare highlighted, namely computer and IT, and construction contract administration. Sincecomputer and IT offer the convenience of day-to-day management efforts, multitasking natureof CM is effectively facilitated. From general computer applications (e.g. word processing) torather specific applications for construction (e.g. scheduling and computer-aided design), CMare reckoned to have the adequate knowledge and skills. On the other hand, given thatthe selected contractors are bonded to the agreed contract between stakeholders, theadministration of a particular contract throughout the construction phase is crucial. Since thecontract stipulates several conditions and requirements to be adhered by the contractors, CMplays an important role to convey that particular information throughout the prescribedcontract period effectively. Thus, technical competency regarding its administration isdeemed paramount to be instilled to the CM.

7.2 Quantitative methodsWith regard to validation and generalisation effort, 101 respondents (33.67 per cent ofresponse rate) from various contractors’ company have completely answered thequestionnaire survey (see Table III for a summary of data). However, since contractormay register beyond a single category as long as within the requirements stipulated bythe Malaysia’s CIDB, a mismatched between the total number of contractors’ category (at 135 nos.) and the total number of respondents has been observed. According to therecord, the majority of the respondents came from building construction contractors(52 per cent), followed by civil engineering contractors (35 per cent), and mechanical andelectrical contractors (13 per cent). Meanwhile, respondents from large contractors

171

Constructionmanager’stechnical

competencies

Page 42: Engineering, Construction and Architectural

(G6 and G7) topped the list and dominated for nearly one-third of the total response.The least was from medium contractors with only 25 per cent of the response. Apart fromthat, respondents with the highest positions (i.e. director, executive director, executivechairman, and corporate manager) in the contracting companies dictated a hugepercentage of 28 per cent, and it was followed by the remaining positions where contractmanagers/executive contributed the least responses of 5 per cent. On the other hand, nearlyhalf of the respondents (48 per cent) have had at least ten years of construction experience.In general, all respondents have the appropriate acumen in order to validate prior findings.The combination of their organisation’s nature, positions, and experience were believed tostrongly outlaid acceptable results by covering both integrity and significant.

Moreover, by referring to Table IV, all items of CM’s technical competency has scoredbetween 4.00 (important) and 5.00 (very important) of means based on contractors’category/specialisation. Except for “Computer and IT” from mechanical and electricalcontractors’ point of view, a score of 3.75 is recorded – which is in the region of 3.00(slightly important) and 4.00 (important). Nonetheless, based on the result, the authorshave concluded that all respondents were collectively in agreement towards theimportance of all technical competency items which need to be equipped to the CM, despitedifferences of construction category/specialisation (although with varying levels fromimportant to very important). Further, similar ranks shared by several items (i.e. staff,plant and equipment, environment, computer and IT, and construction contract)throughout diverse contractor’s category has somewhat supported the view and to acertain extent generalising the outcome to the masses.

On another perspective, contractors’ sizes and grades were deemed to give a criticaloverview on the perception of technical competency’s importance level. Due to the fact thatsizes of contractors determined their value of construction project, it is a common convictionthat people recognised the higher size of contractors requires extra technical competencysince their project is frequently more difficult and complicated. Surprisingly, it can be seenfrom Table V that all items of CM’s technical competency have scored between 4.00(important) and 5.00 (very important) of means based on various contractors’ size and grade.Except for two items (i.e. plant and equipment, and environment), scores below than 4.00 bymedium contractors (G4 and G5) were recorded. However, since the scores were very muchcloser to 4.00 (importance level), the similar conclusion as the previous paragraph are likely.Thus, apart from having a majority consensus of perception (i.e. vary from important tovery important), similar ranks shared by a number of items (i.e. plant and equipment,environment, computer and IT, and construction contract) were an indication of agreementtowards respondents. Additionally, through a spontaneous visual inspection, Tables IV and Vhave presented identical ranks especially towards plant and equipment, environment,computer and IT, and construction contract. This circumstance is partly showed thatregardless of contractor’s category and size; similar items were needed to encapsulate entireparadigm of technical competency for CM.

8. ConclusionA rigorous qualitative process through MLT analysis is deemed to be adequate inidentifying technical competency of CM. Later, the application of interview sessions forconfirmation of prior collected data is pragmatically seen as pertinent. Apart fromvalidation per se, interviews which infusing local academic-industry experts were reckonedto accentuate different opinion on research’s central phenomenon. Then, as mass validationand generalisation are concerned, distribution of questionnaire surveys within the studyarea are paramount. To sum up, findings from all objectives were considered to presentconsistent results. Technical competency for CM encompasses the ability to manage: staff,materials, labour, plant, sub-contractors, safety, money, quality, time, environment, site

172

ECAM25,2

Page 43: Engineering, Construction and Architectural

administration, pre-construction activities, project closeout and handover, third parties,computer literacy, and construction contract. Nevertheless, given that the research is onlycovered the entire state of Johor, immediate usage of findings throughout Malaysia is yet tobe determined. However, up to this point, the research has provided useful insight andpaved the way for subsequent undertakings. Apparently, the authors were optimist thatfinal findings might serve as term of reference for CM’s technical competency and providefaster applications for a lot of purposes, including designing proper training for CM,assessing and auditing the training of CM, recruitment, termination or dismissal of CM, andregistration of local professional CM.

References

Abdul-Rahman, H., Berawi, M.A., Berawi, A.R., Mohamed, O., Othman, M. and Yahya, I.A. (2006),“Delay mitigation in the Malaysian construction industry”, Journal of Construction Engineeringand Management, Vol. 132 No. 2, pp. 125-133.

Ahn, Y.H., Kwon, H., Pearce, A.R. and Shin, H. (2010), “Key competencies for US constructiongraduates: an exploratory factor analysis”, ASC Proceedings of the 46th Annual Conference,Boston, MA, 7-10 April.

Akintoye, A.S. (1998), “Delivery of postgraduate programmes in construction management in the UK:an industrial perspective”, in Yang, J. and Chang, W.P. (Eds), Building Education and Research,E & F Spon, London, pp. 90-99.

Arditi, D., Ongkasuwan, D. and Institute, T.C. (2009), “Technical notes: duties and responsibilities ofconstruction managers: perceptions of parties involved in construction”, Journal of ConstructionEngineering and Management, Vol. 135 No. 12, pp. 1370-1374.

Ashley, D., Lurie, C. and Jaselskis, E. (1987), “Determinants of construction project success”, ProjectManagement Journal, Vol. 12 No. 8, pp. 69-79.

Bakar, A.H. (2009), “Construction in the developing world: issues on indigenous contractors”,in Hassan, A.S. (Ed.), Contextual Issues of the Built Environment in Malaysia, Penerbit UniversitiSains Malaysia, Gelugor, Pulau Pinang, pp. 27-59.

Bank Negara Malaysia (2015), “Annual report: the Malaysian economy 2005-2014”, Bank NegaraMalaysia, Kuala Lumpur.

Benhart, B.L. and Shaurette, M. (2011), “Establishing new graduate competencies: ensuring thatconstruction management curriculums are delivering ‘job-ready’ employees”, ASC Proceedingsof the 47th ASC Annual International Conference, Nebraska-Lincoln, Omaha, 6-9 April.

Boyatzis, R.E. (2008), “Competencies in the 21st century”, Journal of Management Development, Vol. 27No. 1, pp. 5-12.

Burke, R. (2003), Project Management: Planning and Control Techniques, 4th ed., John Wiley & SonsInc., London.

Cambridge University Press (2008), Cambridge Advanced Learner’s Dictionary, 3rd ed., CambridgeUniversity Press, Cambridge.

Chan, D. and Kumaraswamy, M. (1997), “A comparative study of causes of time overruns inHong Kong construction projects”, International Journal of Project Management, Vol. 15 No. 1,pp. 55-63.

Cheng, E.W., Li, H. and Love, P. (2000), “Establishment of critical success factors for constructionpartnering”, Journal of Management in Engineering, Vol. 16 No. 2, pp. 84-92.

Chinowsky, P.S. and Diekmann, J.E. (2004), “Construction engineering management educators: historyand deteriorating community”, Journal of Construction Engineering and Management, Vol. 130No. 5, pp. 751-758.

Chua, D., Kog, Y. and Loh, P. (1999), “Critical success factors for different project objectives”, Journal ofConstruction Engineering and Management, Vol. 125 No. 3, pp. 142-150.

173

Constructionmanager’stechnical

competencies

Page 44: Engineering, Construction and Architectural

Construction Industry Development Board (2007), Construction Industry Master Plan: Malaysia2006-2015, Construction Industry Development Board, Kuala Lumpur.

Construction Industry Development BoardMalaysia (2011), “Buletin Statistik Pembinaan Suku Tahunan”,Quaterly Report, Suku 4, Bahagian 1, Kuala Lumpur.

Construction Industry Development Board Malaysia (2012), Registration, Requirement, and Procedurefor Contractor, Construction Industry Development Board Malaysia, Kuala Lumpur.

Construction Industry Development Board Malaysia (2015), Construction Industry TransformationProgramme 2016-2020: Driving Construction Excellence Together, Construction IndustryDevelopment Board Malaysia, Kuala Lumpur.

Construction Management Association America (n.d.), “CMAA: advancing professional constructionand program management worldwide”, available at: https://cmaanet.org/competencies (accessed25 June 2014).

Contractors and Levy Division, Construction Industry Development Board Malaysia (2016), Requirementsand Procedures for Contractor Registration with the Construction Industry Development BoardMalaysia, Construction Industry Development Board Malaysia, Kuala Lumpur.

Creswell, J.W. (2007), Qualitative Inquiry and Research Design: Choosing Among Five Approaches,2nd ed., Sage Publications, Thousand Oak, CA.

Creswell, J.W. (2008), Educational Research: Planning, Conducting, and Evaluating Quantitative andQualitative Research, 3rd ed., Pearson, OH, Upper Saddle River, NJ.

Dawson, R. (2011), “How significant is a boxplot outlier?”, Journal of Statistics Education, Vol. 19 No. 2,pp. 1-13.

Deist, F.O. and Winterton, J. (2005), “What is competence?”, Human Resource DevelopmentInternational, Vol. 8 No. 1, pp. 27-46.

Dogbegah, R., Owusu-Manu, D. and Omoteso, K. (2009), “A principal component analysis of projectmanagement competencies for the Ghanaian construction industry”, Australasian Journal ofConstruction Economics and Building, Vol. 11 No. 1, pp. 26-40.

Egbu, C.O. (1999), “Skills, knowledge and competencies for managing construction refurbishmentworks”, Construction Management and Economics, Vol. 17 No. 1, pp. 29-43.

Elzalitni, S. and Lees, M. (2007), “Higher college students’ perception of vocational education andtraining programmes in Libya”, Proceedings of the Salford Postgraduate Annual ResearchConference, pp. 289-304.

Farooqui, R.U. and Saqib, M. (2010), “Desirable attributes and skills for graduating constructionmanagement students”, ASC Proceedings of the 46th Annual International Conference, Boston,MA, 7-10 April.

Fester, F.C. and Haupt, T.C. (2008), “Capstone courses as the vehicle to employability improvement ofconstruction graduates”, Proceedings of the International Conference on Building Education andResearch (BEAR), Heritance Kandalama, 11-15 February.

Gilbert, T.F. (1978), Human Competence: Engineering Worthy Performance, McGraw-Hill,New York, NY.

Gliem, J.A. and Gliem, R.R. (2003), “Calculating, interpreting, and reporting Cronbach’s alpha reliabilitycoefficient for Likert-type scales”,Midwest Research to Practice Conference in Adult, Continuing,and Community Education, The Ohio State University, Columbus, OH, 8-10 October.

Graham, S.T., Christofferson, J.P. and Reginato, J.M. (2011), “Analysis of construction-related researchcompared to the needs of industry professionals”, ASC Proceedings of the 47th AnnualInternational Conference, Nebraska-Lincoln, Omaha, 6-9 April.

Gray, C.F. and Larson, E.W. (2008), Project Management: The Managerial Process, 4th ed.,McGraw-Hill Irwin, New York, NY.

Gunderson, D.E. (2008), “Ranking construction superintendent competencies and attributes requiredfor success”, Proceedings of the 44th Annual Associated Schools of Construction Conference,Auburn University, Auburn, 2-5 April.

174

ECAM25,2

Page 45: Engineering, Construction and Architectural

Gunderson, D.E., Ra, J.W., Schroeder, H. and Holland, H.R. (2002), “Needs assessment – a constructionmanagement bachelor of science degree program in Alaska”, Journal of Construction Education,Vol. 7 No. 2, pp. 86-96.

Hackett, S. (2001), “Educating for competency and reflective practice: fostering a cojoint approach ineducation and training”, Journal of Workplace Learning, Vol. 13 No. 3, pp. 103-112.

Hager, P. and Gonczi, A. (1996), “What is competence?”, Medical Teacher, Vol. 18 No. 1, pp. 15-18.

Halpin, D.W. (2006), Construction Management, 3rd ed., John Wiley & Sons, Inc., Hoboken, NJ.

Hassan, F. (2005), “A best practice framework for training UK construction site managers”,unpublished PhD thesis, Sheffield Hallam University, London.

Hassan, F., Maisham, M., Khan, S.M., Alwi, S.A. and Ramli, H. (2010), “Competencies, skills, andknowledge of quantity surveying graduates”, The Quantity Surveying InternationalConvention, Subang Jaya, Selangor.

Hassan, F., Samad, Z., Hassan, S., Che Mat, M. and Isnin, Z. (2010), “Training the constructionworkforce: a case study of Malaysia”, Conference Proceeding W089 – Special Track 18th CIBWorld Building Congress, pp. 230-241.

Hauck, A.J. (1998), “Construction management curriculum reform and integration with a broaderdiscipline: a case study”, Journal of Construction Education, Vol. 3 No. 2, pp. 118-130.

Ibrahim, A.R., Roy, M.H., Ahmed, Z. and Imtiaz, G. (2010), “An investigation of the status of theMalaysian construction industry”, Benchmarking: An International Journal, Vol. 17 No. 2,pp. 294-308.

Isa, S.S. (2007), “A study on roles and tasks of construction managers in Malaysian constructionindustry”, unpublished MSc thesis, Universiti Teknologi Mara Malaysia, Shah Alam.

Jaafar, M. and Nuruddin, A.R. (2012), “The development of public and private constructionprocurement systems in the Malaysian construction industry”, Journal of Design and BuiltEnvironment, Vol. 11, December, pp. 1-11.

Jabatan Audit Negara Malaysia (2010a), Laporan Ketua Audit Negara Tahun 2010:Aktiviti Kementerian/Jabatan dan Pengurusan Syarikat Kerajaan Persekutuan, Jabatan AuditNegara Malaysia, Kuala Lumpur.

Jabatan Audit Negara Malaysia (2010b), Laporan Ketua Audit Negara Tahun 2010: PengurusanKewangan dan Aktiviti Serta Pengurusan Syarikat Subsidiari Badan Berkanun Persekutuan,Jabatan Audit Negara Malaysia, Kuala Lumpur.

Justelian, A.J. III (2009), “Factors that influence course completion of individuals enrolled incraft-training courses offered by a large organization of member construction companies”,Louisiana State University, Baton Rouge, LA.

Kariya, N., Yaakob, Z., Mohammad Sairi, M., Mohammad, H., Yaman, S. and Abas, N. (2016),“Investigation of generic house components and their practical ways to be assessed by housebuyers during defect liability period in Malaysia”, International Journal of EngineeringTransactions A: Basics, Vol. 29 No. 10, pp. 1354-1363.

Kementerian Kewangan Malaysia (2012), Surat Pekeliling Perbendaharaan Bil, 6 Tahun 2012:Gred Pendaftaran Kontraktor Kerja, Kementerian Kewangan Malaysia, Kuala Lumpur,doi: S/K.KEW/PK/D/1100/000000/10/31Jld.33 SK.3(10).

Koch, D.C. and Benhart, B. (2010), “Redefining competencies for field supervision”, ASC Proceedings ofthe 46th Annual International Conference, Boston, MA, 7-10 April.

Koskela, L. (1992), “Technical report no. 72: application of the new production philosophy toconstruction”, Centre for Integrated Facility Engineering, Stanford University, Stanford, CA.

Lee, N., Ponton, R., Jeffreys, A. and Cohn, R. (2011), “Analysis of industry trends for improvingundergraduate curriculum in construction management education”,ASC Proceedings of the 47thAnnual International Conference, Nebraska-Lincoln, Omaha, 6-9 April.

Lembaga Pembangunan Industri Pembinaan Malaysia (2012), Daftar Projek Yang Diawad 2007-2012,Bahagian Pembangunan Persekitaran Bisnes Malaysia, Kuala Lumpur.

175

Constructionmanager’stechnical

competencies

Page 46: Engineering, Construction and Architectural

Lex, B., Grip, A.D. and DG, M.V. (1997), “The definition of skills shortages”, in Schmehr, P.e. (Eds),Innovative Companies, A Road to Job Creation, TARGET, pp. 45-56.

Love, P.E. and Haynes, N.S. (2001), “Construction managers’ expectations and observations ofgraduates”, Journal of Managerial Psychology, Vol. 16 No. 8, pp. 579-593.

Lundberg, C.C. (1972), “Planning the executive development program”, California Management Review,Vol. 15 No. 1, pp. 10-15.

McClelland, D.C. (1973), “Testing for competence rather than for ‘intelligence’ ”, American Psychologist,Vol. 28 No. 1, pp. 1-14.

McDaniel, D. (2005), “Developing an integrated curriculum model for construction managementeducation”, Online Journal for Workforce Education and Development, Vol. 1 No. 3, pp. 1-17.

Mansfield, R.S. (1996), “Building competency models: approaches for HR professionals”,Human Resource Management, Vol. 35 No. 1, pp. 7-18.

Mohammad, H., Yaman, S., Hassan, F. and Ismail, Z. (2016), “Determining the technical competencies ofconstruction managers in the Malaysia’s construction industry”, MATEC Web of Conferences,Vol. 47 No. 4021, pp. 1-9.

Mullin, P.T. and Williams, A.N. (2010), “Using skills gap analysis in construction management tostimulate a demand led model of curriculum”, Conference Proceeding W089 – Special Track18th CIB World Building Congress, pp. 65-79.

National Center for Construction Education and Research (2008), Project Management: AnnotatedInstructor’s Guide, Contren Learning Series, 2nd ed., Pearson, NJ and Alachua, FL.

Nguyen, L., Ogunlana, S. and Lan, D. (2004), “A study on project success factors in large constructionprojects in Vietnam”, Engineering, Construction and Architectural Management, Vol. 11 No. 6,pp. 404-413.

Nonaka, I. (1997), “Organizational knowledge creation”, Knowledge Advantage Conference, NationalSecurity Agency, MD, 11-12 November.

NOSS Division, Department of Skills Development (2015), National Occupational Skills StandardRegistry, Ministry of Human Resource, Kuala Lumpur.

Oberlender, G.D. (2000), Project Management for Engineering and Construction, Civil EngineeringSeries, 2nd ed., Mc Graw-Hill International Editions, New York, NY.

Potgieter, T. and Van Der Merwe, R. (2002), “Assessment in the workplace: a competency-basedapproach”, SA Journal of Industrial Psychology, Vol. 28 No. 1, pp. 60-66.

Riggs, L.S. (1998), “Educating construction managers”, Journal of Construction Engineering andManagement, Vol. 114 No. 2, pp. 279-285.

Ritz, G.J. (1994), Total Construction Project Management, McGraw-Hill Inc., New York, NY.

Rudarakanchana, N., Herzeele, I.V., Desender, L. and Cheshire, N.J. (2015), “Virtual reality simulationfor the optimisation of endovascular procedures: current perspectives”, Vascular Health andRisk Management, Vol. 11 No. 11, pp. 195-202.

Rum, N. and Akasah, Z. (2011), “Implementing life cycle costing in Malaysia construction industry:a review”, International Building and Infrastructure Technology Conference, Penang,pp. 272-280.

Russell, J.S., Hanna, A., Bank, L.C. and Shapira, A. (2007), “Education in construction engineering andmanagement built on tradition: blueprint for tomorrow”, Journal of Construction Engineeringand Management, Vol. 133 No. 9, pp. 661-668.

Sambasivan, M. and Soon, Y.W. (2007), “Causes and effects of delays in Malaysian constructionindustry”, International Journal of Project Management, Vol. 25 No. 5, pp. 517-526.

Souder, C. and Gier, D.M. (2006), “What does the construction industry expect from recent constructionmanagement graduates?”, ASC Proceedings of the 42nd Annual Conference, Fort Collins, CO,20-22 April.

176

ECAM25,2

Page 47: Engineering, Construction and Architectural

Stoof, A., Martens, R.L., Merriënboer, J.J. and Bastiaens, T.J. (2002), “The boundary approach ofcompetence: a constructivist aid for understanding and using the concept of competence”,Human Resource Development Review, Vol. 1 No. 3, pp. 345-365.

Tavakol, M. and Dennick, R. (2011), “Making sense of Cronbach’s alpha”, International Journal ofMedical Education, Vol. 2 No. 2, pp. 53-55.

Toepoel, V., Das, M. and van Soest, A. (2009), “Design of web questionnaires: the effect of layout inrating scales”, Journal of Official Statistics, Vol. 25 No. 4, pp. 509-528.

Toor, S. and Ogunlana, S. (2008), “Critical COMs of success in large-scale construction projects:evidence from Thailand construction industry”, International Journal of Project Management,Vol. 26 No. 4, pp. 420-430.

Unit Penyelarasan Pelaksanaan (2013), Pengurusan Projek Sektor Awam, Bengkel Penggubalan ModulDan Kaedah Pelaksanaan Kursus Pensijilan Pengurusan Projek Sektor Awam, Jabatan PerdanaMenteri, Kuala Lumpur.

Walfish, S. (2006), “A review of statistical outlier methods”, Pharmaceutical Technology, Vol. 30 No. 11,pp. 1-3.

Waluyo, R. (2007), “Pendidikan profesional Konstruksi di Indonesia”, Jurnal Teknik Sipil, Vol. 8 No. 1,pp. 23-36.

Wandahl, S.O. and Ussing, L.W. (2010), “Construction management engineer education with focus oncompetencies required by the construction industry”, Conference Proceeding W089 – SpecialTrack 18th CIB World Building Congress, pp. 1-10.

Wang, Y., Goodrum, P.M., Haas, C.T. and Glover, R.W. (2008), “Craft training issues in Americanindustrial and commercial construction”, Journal of Construction Engineering and Management,Vol. 134 No. 10, pp. 795-803.

White, R.W. (1959), “Motivation reconsidered: the concept of competence”, Psychological Review, Vol. 66No. 5, pp. 297-310.

Yaman, S., Abdullah, A., Mohammad, H. and Hassan, F. (2015), “Technical competency of constructionmanager in Malaysian construction industry”, Applied Mechanics and Materials, Vols 773-774,pp. 1053-1059.

Young, B.A. (1993), “Management skills and knowledge: a case example from the constructionindustry”, Leadership & Organization Development Journal, Vol. 10 No. 6, pp. 3-9.

Corresponding authorAbd Halid Abdullah can be contacted at: [email protected]

For instructions on how to order reprints of this article, please visit our website:www.emeraldgrouppublishing.com/licensing/reprints.htmOr contact us for further details: [email protected]

177

Constructionmanager’stechnical

competencies

Page 48: Engineering, Construction and Architectural

Conflicts and management stylesin the Sri Lankan commercial

building sectorChathuri Gunarathna and Rebecca Jing Yang

School of Property, Construction and Project Management, RMIT University,Melbourne, Australia, andNirodha Fernando

Department of Architecture and Built Environment, Northumbria University,Newcastle Upon Tyne, UK

AbstractPurpose – The purpose of this paper is to understand the prevailing conflict management styles inSri Lankan commercial building industry from the main stakeholders’ perspective. The dual concern theory isapplied to this study as a theory foundation.Design/methodology/approach – The Sri Lankan commercial building industry is currently experiencinga construction boom after 30 years of civil war. Creating a dispute free environment through well conflictmanagement is one of the main ways to keep the continuous demand and development of construction.However, the Sri Lankan construction sector is arranged in such a way that they directly approach thedispute resolution rather than avoiding the dispute initially through proper conflict management. Four casesare selected for this study with the intention of conducting meetings with three main stakeholders of eachcase who represented client, consultants and contractors, respectively.Findings – The research findings reveal that compromising is the most common conflict management styleused by the industry. Forcing style obtained the second place in the ranking whereas obliging and avoidingreceived third and fourth places.Originality/value – This study is conducted to provide a full picture of conflicts faced by the Sri Lankancommercial building industry and their proper management so that the future projects will use thisinformation to diminish the destructive effects of conflict situations and provide a real value for money.Keywords Management, Case study, ConstructionPaper type Research paper

1. IntroductionThe construction industry inherits several unique characteristics such as complexity, highhuman diversity and lengthy process of construction due to which the conflicts will occur( Jaffar et al., 2011). However, having conflicts will not always barricade the project success(Ohbuchi and Suzuki, 2003). Conflicts can generate constructive outcomes as well asdestructive outcomes (Tjosvold, 2006). Constructive conflicts often make path to creativethinking and innovation (Gorse, 2003). On the other hand, destructive conflicts will reduce thetrust and respect over each other; resulting numerous adverse effects on the performance andproductivity (Femi, 2014). As per the Oxford Dictionary (2017), the management is defined as“the process of dealing with or controlling things or people.” Thus, conflict management canbe defined as the process of dealing with or controlling conflicts in such a way that they willnot cause any negative effect on the project success. It is obvious that through a propermanagement, the constructive conflicts can be utilized to enhance the productivity of theproject while eliminating the destructive conflicts (Tjosvold, 2006).

According to Femi (2014), conflicts in construction can be defined as a disagreementbetween two parties over a common action. When these disagreements go beyond thecontrol of project management and possibility of amicable settlement, they become disputeswhich require a legal application for their resolution (Adnan et al., 2011; Yusof et al., 2011).

Engineering, Construction andArchitectural ManagementVol. 25 No. 2, 2018pp. 178-201© Emerald Publishing Limited0969-9988DOI 10.1108/ECAM-10-2016-0233

Received 30 October 2016Revised 14 February 2017Accepted 5 June 2017

The current issue and full text archive of this journal is available on Emerald Insight at:www.emeraldinsight.com/0969-9988.htm

178

ECAM25,2

Quarto trim size: 174mm x 240mm

Page 49: Engineering, Construction and Architectural

Therefore, it can be concluded that unmanaged conflicts are destructive and create harmfuleffects to the project success by escalating themselves into disputes which requireexpensive and time consuming resolution process (Adnan et al., 2011). Hence conflictmanagement should be given a prior consideration in the construction sector (Huan andYazdanifard, 2012). The previous studies indicate that when compared to other industries,the amount of unmanaged conflicts escalating to disputes are tremendously high in theconstruction sector (Yiu and Cheung, 2006; Yusof et al., 2011). The findings of Chen et al.(2014) revealed that the firm focus on the constructive aspects of the conflicts and themutual trust establishment are the keys to reduce the conflicts. Latiffi et al. (2013) introducedBuilding Information Modeling as one of the main techniques of eliminating the sources ofconflicts. Zhang et al. (2015) revealed that there is a positive relationship between theemotional intelligence of the people and conflict management; thus, it can be utilized tominimize the conflict situations. Meyer et al. (2012) mentioned that conflicts can be wellmanaged and utilized constructively by adhering to a predefined strategy. Lu et al. (2017)introduced a novel concept of dispute negotiations and the role of the justice over the socalled negotiations.

Sri Lankan commercial building industry is currently experiencing a construction boomafter 30 years of civil war (Seneviratne et al., 2015). The industry obtained a massive demandand development in the past few years due to the increment of new investments, tourism,infrastructure development and industrial development (The Report, Sri Lanka, 2016).With the so called development, the rate of occurring conflict situations in the constructionfield is considerably increased (Heenkenda and Chandanie, 2012). Conflicts and disputes inconstruction projects will barricade the timely completion, lose productivity and preventgaining value for money (Yiu and Cheung, 2006). Thus, creating a dispute free environmentthrough proper conflict management is one of the main ways to keep the continuous successand development of construction (Fenn et al., 1997; Popovic and Hocenski, 2009). However, theSri Lankan construction sector is arranged in such a way that they directly approach thedispute resolution rather than avoiding the dispute initially through proper conflictmanagement (Thalgodapitiya, 2010). Currently, the Institute for Construction Training andDevelopment of Sri Lanka encourages the construction parties to adhere to alternative disputeresolution methods (Abeynayake and Weddikkara, 2012). Since dispute resolution is veryexpensive, time consuming and harmful to the professional relationship (Abeynayake andWeddikkara, 2007), conflict management draws more attentions now to save money and timein the later project stage (Heenkenda and Chandanie, 2012).

The aim of this research is to understand the prevailing conflict management styles inSri Lankan commercial building industry from the main stakeholders’ perspective.Four construction projects are selected which are handled by the largest and the mostreputed construction companies, consultancy firms and client organizations in Sri Lankancommercial building industry. These companies obtain a diverse professional involvementand acquire a great demand in the construction sector. Further, they provide high qualityoutput and maintain good professional relationships inside their companies as well asoutside. Furthermore, these companies considered to be the highest profit gaining entities inthe industry. Therefore, by conducting an in-depth analysis on how they proceed withconflict situations, the study intends to understand the current effective conflictmanagement practices in the country. The findings of the study can be used by themedium and small-scale construction entities which struggle in different conflict situationsas they are not capable of affording expensive and time consuming dispute resolutionprocess. The research outcomes will assist the medium and small scale constructionstakeholders by filling the knowledge gap currently existing in the industry and providing asystematic and comprehensive knowledge on the effective conflict management. Ultimately,the study will contribute to adopt a dispute free environment in the Sri Lankan commercial

179

Sri Lankancommercial

building sector

Page 50: Engineering, Construction and Architectural

building industry. Further, the research findings can be used to plan proper conflictmanagement strategies prior to construction. This paper initially provides a literaturereview on the existing knowledge of conflict management practices and theory. Four caseprojects are investigated and compared to understand the ways of solving conflicts followedby discussions on the future improvement.

2. Conflict types and their sourcesA number of researchers introduced different categorizations of conflicts. Among them, themost discussed categorization is task conflicts, relationship conflicts and process conflicts(Chou and Yeh, 2007; DeChurch et al., 2007; Desivilya et al., 2010; Huan and Yazdanifard,2012; Jehn and Chatman, 2000; Senaratne and Udawatta, 2013; Simons and Peterson, 2000).Task conflicts occur due to the disagreements raised between people working in the samegroup regarding the content of the decisions they make (Simons and Peterson, 2000).The execution of work-related conflicts such as resource allocation, agreeing on rates,variation procedures and policies and judgment on quality can be identified as task conflicts(Dreu et al., 2001). The task conflicts occur mainly due to people having different ideas,viewpoints and opinions (Huan and Yazdanifard, 2012). Relationship conflicts occur due tothe disagreements of people who work together (Chou and Yeh, 2007). The main sources ofrelationship conflicts are tension, hostility and annoyance among the individuals inside thegroup (DeChurch et al., 2007). Process conflicts occur due to the disagreements regardingthe working strategies and delegation of duties and authority which are more related to thecontractual documentation ( Jehn and Chatman, 2000). The main sources of process conflictsare poor communication, avoiding rules and regulations, issues regarding working methods,issues regarding workload distribution and issues regarding scheduling (Senaratne andUdawatta, 2013).

Acharya et al. (2006) introduced another categorization consisting of five main conflicttypes considering the main stakeholders in a project. The conflict types are owner evokedconflicts, consultant evoked conflicts, contractor evoked conflicts, third parties evokedconflicts, and other project matter evoked conflicts. The name of the conflict typeitself provides the explanation of the content. The main sources of aforementionedconflicts are confusing requirements of owner, excessive change orders, supremacy ofowner/consultant, errors and omissions in design, non-payment to subcontractors,conflicts in documents, lack of communication, changes in site condition, publicinterruption and union strikes.

Friedman et al. (2000) introduced another categorization consisted of five main conflicttypes. They are interpersonal conflicts, role conflicts, intergroup conflicts, multi-partyconflicts and international conflicts. Interpersonal conflicts occur due to the incompatibleneeds, approaches and goals of two individuals with regard to their personal relationshipor/and professional relationship. The main sources for this conflict type are poorcommunication, personality issues and human nature. Role conflicts occur due to thedifferences in role definitions, line of authority and unclear boundaries of responsibilities.The main sources are poor communication, lack of information, documentation errors anddelegation of power. Intergroup conflicts occur between the construction stakeholders;especially between work groups. The main sources are design errors, documentation errors,delays, non-payments, differences in attitudes and variations. Multi party conflicts occurbetween two or more parties to the project such as consultants with authorities, client withenvironmental organization and contractor with financial institute. The main sources areenvironmental hazards, land acquisition, improper garbage disposal and pollution.International conflicts occur when a construction project becomes a threat, annoyance orcompetition to another country. The main sources are competition for resources, hunger ofpower and threat to the economy.

180

ECAM25,2

Page 51: Engineering, Construction and Architectural

According to the literature, most of the categorizations regarding the conflict types are putforward by considering the characteristics of conflicts (Acharya et al., 2006; Chou and Yeh, 2007;DeChurch et al., 2007; Desivilya et al., 2010; Friedman et al., 2000; Huan and Yazdanifard, 2012;Jehn and Chatman, 2000; Senaratne and Udawatta, 2013; Simons and Peterson, 2000). Thesecategorizations provided a general view of conflicts rather than specifically identifyingthe conflicts related to a particular scenario. However, this study is interested in providing morespecific view of conflicts based on the most common conflict situations that can be practicallyexperienced in the Sri Lankan commercial building industry. Based on the literature, the studyhas recognized 15 individual conflict situations that can be commonly seen in the particularindustry. All the 15 conflict situations are included in the categorizations provided in literature,sometimes in different names, sometimes as a sub category and in other times as a source ofconflicts (references provided in Table III).

The 15 conflict situations are categorized into four main conflict types. They arepayment issues, relationship conflicts, documentation-related conflicts and execution ofwork-related conflicts. This categorization is done by considering the nature andbackground of the conflict situations. It will clearly distinguish in which circumstances theconflict situations are occurred for the better understanding of the readers. It should benoted that most of these conflict situations are interconnected with each other and some ofthem may become a source of another conflict situation. If further elaborated, even a wholecategory can become a reason for another conflict situation. Nevertheless, by categorizingthe aforementioned 15 conflict situations, the study attempts to emphasize the specific areasin which there is high tendency to have conflict situations. Even though the categorization isnew to the prevailing literature, it seems to be in line with the categorization discussed byJehn and Chatman (2000), Senaratne and Udawatta (2013) and Simons and Peterson (2000)which includes task conflicts, relationship conflicts and process conflicts. Further, the15 situations are discussed in different literature under different categorizations yet theultimate concept lies behind is almost the same. These situations are further elaborated inTable III with their respective references. However, it can be seen that the prevailingliterature rarely discuss the conflict situations in the relationship conflicts as situationalwise (Ex: consultant – contractor, between laborers, contractor – subcontractor and betweenspecialized contractors) yet highly discuss about the relationship conflicts in general.

3. Conflict management theoriesA number of conflict management theories are put forward considering the Managerial Gridof Blake and Mouton (DeChurch et al., 2007). The two dimensions used by Blake and Moutonare slightly changed in the other theories yet the ultimate concept given with regard toconflict management is almost the same (Lee, 2008). Some of these other theories are MaryParker Follett Model (1940), Hall’s Win-Lose approach (1969), Thomas Kilmann ConflictMode Instrument (1977) and Devito Model (1995) (Atteya, 2012; Giritli et al., 2009; Lee, 2008;Ozkalp et al., 2009; Vu and Carmichael, 2009; Zhang et al., 2015). Mary Parker Follett Model(1940) suggested that the conflicts occur due to the differences in thoughts and ideas ofindividuals, thus these differences can be used to manage the conflicts (Giritli et al., 2009).Accordingly, Follett introduced five conflict management styles, namely; evasion,suppression, domination, compromise and integration (Al-Sedairy, 1994). Hall believedthat conflicts can be well managed by considering two dimensions; concern for personalgoals and concern for relationships (Vu and Carmichael, 2009). Accordingly, he introducedapproaches based on winning and losing (Atteya, 2012). Thomas Kilmann Conflict ModeInstrument (1977) suggested that conflicts can be well managed by consideringassertiveness and cooperativeness and introduced five conflict management styles,namely; competing, collaborating, avoiding, compromising and accommodating (Trippe andBaumoel, 2015). Devito Model (1995) argued that the conflicts can be effectively managed

181

Sri Lankancommercial

building sector

Page 52: Engineering, Construction and Architectural

through five stages; identifying the conflict, examining the possible solutions, testing thesolution, evaluating the solution and accepting or rejecting the solution (Giritli et al., 2009).

It is recognized that Follett Model did not consider about obliging as a conflictmanagement style (Al-Sedairy, 1994) whereas Thomas Kilmann Model is more interested incompeting style rather than dominating style (Trippe and Baumoel, 2015). However, it isobvious that there should be flexible means of conflict management such as obliging(Verma, 1998). Moreover, competing will create more conflicts rather than managing them.The Hall’s Win-Lose Approach and Devito Model provide a common approach to conflictmanagement rather than behavioral approach. Since the management of conflicts highlydepending on the behavior of the parties, it is better to use a behavioral approach ratherthan a common approach (Giritli et al., 2009; Vu and Carmichael, 2009). On the other hand,dual concern theory follows a behavioral approach and consider the actions of bothconflicting parties (Zhang et al., 2015). Further, this theory is highly accepted among theconflict management researches due to its inherited qualities such as ease of use, clearinterpretation and effective predicting capability when compared to other theories (Vu andCarmichael, 2009). Since the dual concern theory consists of all possible rigid and flexibleways of conflict management and provides the full picture of conflict management, thisstudy will apply it in the case studies to understand the Sri Lankan practices.

4. Dual concern theoryDual concern theory is introduced by Pruitt and Rubin (1986) (Chou and Yeh, 2007;Dreu et al., 2001; Gorse, 2003) based on the Managerial Grid introduced by Blake andMouton (DeChurch et al., 2007). According to the dual concern theory, the way two partieswillingly behave or forced to behave in a conflict situation can be used to manage theconflicts (Lee, 2008). The theory suggested that based on the high or low concern given toachieve self-desires and the desires of the other party, the conflicts can be properly managed(Desivilya et al., 2010). There are five conflict management styles, namely; integrating(problem solving), obliging, dominating ( forcing), avoiding and compromising (Chou andYeh, 2007). The dual concern model is clearly demonstrated by Rahim (2002) as shownin Figure 1.

4.1 Integrating style (problem solving style)According to Chou and Yeh (2007), the two dimensions considered in this style are highconcern for self and high concern for the other party. The conflict is considered as a problemin this style which required an answer, thus both parties took considerable attempts to findthe solution or better alternatives while improving their creativity and skills (Chou and Yeh,2007; Verma, 1998).

Integrating Obliging

Dominating Avoiding

Compromising

Con

cern

for o

ther

s

Low

Hig

h

Concern for selfHigh Low

Source: Rahim (2002, p. 217)

Figure 1.Dual concern model

182

ECAM25,2

Page 53: Engineering, Construction and Architectural

4.2 Obliging styleThe two dimensions considered in this style are low concern for self and high concern forother party (Chou and Yeh, 2007). According to Verma (1998), this conflict managementstyle directed the parties to highlight the agreements rather than disagreements thusprovided a short term solution.

4.3 Dominating style ( forcing style)According to the description given by Chou and Yeh (2007), the two dimensions consideredin this style are high concern for self and low concern for the other party. This style isnormally used by the party who had more power and authority over the other party;demanding the other party to accept their interests (Giritli et al., 2009).

4.4 Avoiding styleAccording to Chou and Yeh (2007), the two dimensions used for conflict management arelow concern for self and the other party. Cheung and Chuah (1999) and Akiner (2014)identified this style as denying or ignoring the disagreement between the parties that isactually occurred or yet to come. Gunarathna and Fernando (2014) explained that thisconflict management style can be used for conflicts which are not related to the constructionproject yet occurred inside the construction environment.

4.5 Compromising styleIn this style, the two dimensions considered for conflict management are moderate concernfor self and others at the same time by providing a mutually acceptable decision (Tsai andChi, 2009). Both parties to the conflict would gain some degree of satisfaction by using thisstyle and the degree of satisfaction they gained would be enough to manage the conflict andavoid its escalation (Cheung and Chuah, 1999).

Different countries manage conflicts by using different techniques. In North America, thetraditional conflict management styles are compromising, forcing, persuading and problemsolving (Appelbaum et al., 1998). The construction industry of Hong Kong traditionally usedcompromising and withdrawal for conflict management yet currently prefers confrontationas the main conflict management style (Cheung and Chuah, 1999). Malaysian constructionindustry preferred integrating, compromising and to some degree of obliging as the conflictmanagement styles as they are correlated to each other (Lee, 2008). The Project Managers ofNigerian construction industry often used highly improved communication procedure,interpersonal trust and collective responsibility to reduce conflict situations(Ogunbayo, 2013). Japan business industries used a three-way strategy for conflictresolution; collaborative strategies which suggested the concern for group performance,confrontational strategies which suggested the concern for group order and avoidancestrategy which suggested the concern for self-interests (Ohbuchi and Suzuki, 2003).

The managers in Turkey generally use integrating and compromising style for conflictmanagement (Ozkalp et al., 2009). Further to authors, obliging and forcing is useddepending on the level of hierarchy, which was highly accepted in Turkey. BothAustralian and Vietnamese construction stakeholders often used collaborating conflictmanagement style in the international construction projects they worked together toreduce cultural conflicts (Vu and Carmichael, 2009). However, the authors revealed thatthe Australians, in their local construction industry preferred confrontation anddominating styles whereas the Vietnamese, inside their country preferred obliging andavoiding styles. Saudi Arabian construction industry used compromising, problemsolving and smoothing conflict management styles (Al-Sedairy, 1994) due to themulti-cultural involvement in the industry.

183

Sri Lankancommercial

building sector

Page 54: Engineering, Construction and Architectural

The Sri Lankan construction stakeholders usually use negotiation as the basic conflictmanagement style (Abeynayake and Weddikkara, 2012). This style is introduced as thecompromising style in the dual concern theory. However, the term “compromising” is not usedin the industry. According to Thalgodapitiya (2010), the conflict management is considered asa part of construction risk management in the Sri Lankan commercial building sector. Furtherto authors, they are highly depending on the dispute resolution than the conflict management.

5. Research methods and processNaoum (2007) and Ellis and Levy (2009) emphasized that the most appropriate method forconducting an in-depth analysis of a person, a group of persons, an organization or aparticular project is case studies. Accordingly, it is recognized that conducting case studies fordata collection would be more appropriate for this study due to the requirement of carryingout an in-depth analysis. According to Yin (2009), the best method of data collection forresearches which require a proper understanding of a prevailing situation is conducting amultiple case study. Hence, four cases are selected from the Sri Lankan commercial buildingindustry among which, two are private projects and the other two are the public projects.They are the largest and highly recognized construction companies, consultancy firms andclient organizations involved in Sri Lankan commercial building sector. Their recognition inthe field is summarized in Table I. An in-depth analysis is conducted in order to understandhow these companies are solving the conflicts while maintaining their reputation, demand andintegrity. The collected knowledge from these companies will be beneficial for the mediumscale and small scale construction stakeholders to understand how they should proceed inconflict situations in a highly professional manner. A systematic and comprehensiveknowledge will be invaluable to such stakeholders since they cannot afford the expensive andtime consuming dispute resolution procedure.

These specific four cases are selected since they cover all the aspects to be considered; indiverse range, such as magnitude, complexity, professional involvement, governmentinvolvement, project scope and other secondary factors, in order to understand the conflictmanagement practices in Sri Lanka. Further, the characteristics of these four cases enable toprovide a full picture of the current commercial building sector of the country and they obtainalmost all conflict situations that can be encountered in such construction. Furthermore, theyare fully capable of showing the state-of-art of conflict management practices. All four projectsare successfully completed and fully handed over to the clients during the time of the study.Table II shows the project profile. Case study 1 is an eight storied multipurpose building withluxurious facilities. The building consisted of apartments, shopping complex, offices and acafeteria. Case study 2 is a 14 storied hospital building with super luxurious facilities.Case study 3 is a 14 storied office complex with semi luxurious facilities for a ministry of theSri Lankan Government. Case study 4 is an administrative building for a governmentuniversity of Sri Lanka. All four cases exceeded their initial contract price and the estimatedduration due to various conflict situations. The stakeholders involved in these projects arefrom large-medium scale companies.

The case studies are initially observed by examining the relevant documentationsupplied by the authorities. Subsequently, three individuals from each case who representedthe three main stakeholders of the project (client, consultant and contractor) are identifiedfor interviews. Semi structured interviews are conducted in site offices and approximatelylast for 1 hour. The main reason for selecting the above stakeholders is that they all positionat the management level to solve the project issues and have sufficient knowledge on theproject from the design stage to the handover.

The questions are asked regarding the role of the particular stakeholder, their generalview of conflicts in construction sector, specific conflict types occurred in the project,sources of those conflicts, the effects of those conflicts, how they managed the conflicts with

184

ECAM25,2

Page 55: Engineering, Construction and Architectural

regard to dual concern theory and the final outcome they achieved. The collected datathrough the meetings are then subjected to a content analysis. The main purpose of thecontent analysis is to quantify the qualitative data under the pre-determined categories in asystematic manner. The analysis is conducted as a cross-case analysis to compare andcontrast the similarities and differences of the four cases. Cross-case analysis enabled togeneralize the findings to meet the research aim and objectives. The findings are thensummarized by using cognitive mapping, visualizing the connections, observations andconcepts with regard to the research topic. Accordingly, the conclusion is made and therecommendations are put forward.

6. Conflict types and sourcesThe study identified 15 common conflict situations in the Sri Lankan commercial buildingindustry. They are categorized into four main conflict types. The categorization is furtherelaborated in Table III with the common sources for having particular conflict situations.

Case Stakeholder entity Company profile

1 Client company A highly experienced and well recognized conglomerate in Sri Lanka. Ownsnumber of high rise buildings. Multidisciplinary involvement can be seen

Consultancy firm A firm of chartered quantity surveyors, providing diversified quantity surveyingservices, project management services and dispute resolution services withinSri Lanka and overseas

Constructioncompany

An award-winning construction company which undertake large-scale contracts ofhuge value and complexity. Acquire international standards and recognition.The company uses modern technologies and techniques to provide a high-qualityoutput and on time delivery

2 Client company A well-recognized hospital chain in Sri Lanka. Owns several super luxury hospitalsand private medical centers. Considered as one of the best medical services providersin Sri Lanka. Consecutive award winning company for high quality service

Consultancy firm One of the leading quantity surveying consultancy firms in Sri Lanka. Undertakeboth local and international projects. Several highly reputed quantity surveyorswho did a great service to the quantity surveying academia are owning the firm

Constructioncompany

A well reputed construction company with high multidisciplinary involvement.Recognized as one of the best service providers with high quality products.Internationally recognized. Undertake almost all the types of construction by usingmodern technology and qualified labor

3 Client company One of the ministries in Sri Lanka. Multidisciplinary involvement can be seen.Owns several high-rise office complexes due to the number of departments andnumerous workers. Acquire a high reputation in providing a friendly service

Consultancy firm The main semi-government construction and consultancy firm in Sri Lanka.Multidisciplinary involvement can be seen. All construction-related professionals areavailable. Undertake both consultancy and construction activities. An award-winningfirm for many high-quality services

Constructioncompany

One of the leading construction companies in Sri Lanka with long term experience.Obtains a good reputation for providing high quality output and maintenance.Undertake most of the government projects in Sri Lanka. Multidisciplinaryinvolvement can be seen. A leading training provider in Sri Lanka

4 Client company One of the government universities of Sri Lanka. Obtains a good reputation forhigh quality education and training. Provides considerable facilities to studentsand maintain good professional relationships

Consultancy firm The main government consultancy and construction company in Sri Lanka.Multidisciplinary involvement can be seen. All construction-related professionals areavailable. Well recognized for providing a high-quality service and best training

Constructioncompany

A medium scale construction company which obtains a rapid development.Well reputed for providing a high-quality service and hard working. Maintainsgood professional relationships with government and private entities

Table I.Profile of the

stakeholder entities

185

Sri Lankancommercial

building sector

Page 56: Engineering, Construction and Architectural

6.1 Payment issuesThe most common conflict situations that can be seen are delayed payments andnon-payment. Payment issues are usually caused by the clients and the contractors.According to the meetings conducted with the main stakeholders, it is found that the mostcommon conflict situation out of the two aforementioned payment issues is delayedpayments from client to the contractor. CR02 stated that “Our payments are delayed most ofthe time and the client did not even pay us in few months. This created our cash flownegative and put us into a critical situation. Actually, he also had some problems with hiscash flow.” The contractor’s representatives of other three cases agreed with the fact thatdelayed payments are a massive headache they had to face during the time of construction.

Non-payment is the other common conflict situation with regard to payment issues. Thiscan be equally seen between the contractors and subcontractors and contractors andlaborers. CN01 stated that “The contractor did not pay the subcontractors properly.Therefore, subcontractors stopped continuing the works. Furthermore, the subcontractorsdid not like to work with the main contractor due to the payment issues and they wanted the

Description Case 1 Case 2 Case 3 Case 4

Type Multi purposivebuilding

Hospital building Office complexbuilding

Administrativebuilding

Employer Private Private Government GovernmentCondition Completed Completed Completed CompletedCategory Luxury Super luxury Semi luxury NormalDuration Estimated: 18

monthsActual: 30months

Estimated: 20monthsActual: 26months

Estimated: 24monthsActual: 40 months

Estimated: 15monthsActual: 18 months

Contract price Accepted: US$1.6millionActual: US$2.27million

Accepted:US$8.95 millionActual: US$12.69million

Accepted: US$15.61millionActual: US$20.58million

Accepted: US$0.55millionActual: US$0.76million

Number of stories 8 14 14 5Parties interviewed Client’s representative: CL

Consultant’s representative: CNContractor’s representative: CR

Labels for interviewees CL01CN01CR01

CL02CN02CR02

CL03CN03CR03

CL04CN04CR04

Interviewees’designation of the project

CL01 – Representative of the client’s company who appointed as the team leader ofthe project

CL02 – Head of the consultant teamCL03 – Head of the contractor’s team

Interviewees’ areas ofexpertise

CL01: CivilengineeringCN01: QuantitysurveyingCR01: Projectmanagement

CL02:ArchitectureCN02: ProjectmanagementCR02: Quantitysurveying

CL03: ConstructionmanagementCN03: CivilengineeringCR03: Projectmanagement

CL04: CivilengineeringCN04: QuantitysurveyingCR04: Mechanicalengineering

Interviewees’ experience CL01: 15 yearsCN01: 16 yearsCR01: 14 years

CL02: 23 yearsCN02: 38 yearsCR02: 13 years

CL03: 20 yearsCN03: 15 yearsCR03: 21 years

CL04: 26 yearsCN04: 8 yearsCR04: 53 years

Interviewees’ companyscale

CL01: Large scaleCN01: MediumscaleCR01: Large scale

CL02: Large scaleCN02: Large scaleCR02: Large scale

CL03: Large scaleCN03: Large scaleCR03: Large scale

CL04: Medium scaleCN04: Large scaleCR04: Mediumscale

Table II.Case profile

186

ECAM25,2

Page 57: Engineering, Construction and Architectural

Conflict type Conflict situation Sources

Payment issues Delayed payment (Acharyaet al., 2006)

Financial issues of the clientDelays in government procedureFinancial issues of the contractorLate submission of interim paymentapplications

Non-payment (Acharya et al.,2006; Fisher, 2000;Verma, 1998)

Selection of an underpriced bidFinancial issues of the contractorClaims submit after completion of theproject

Relationship conflicts (Dreu andVianen, 2001; Jehn and Chatman, 2000;Senaratne and Udawatta, 2013;Simons and Peterson, 2000)

Consultant – contractor(Chen et al., 2014)

Payment issuesUnprofessional behaviorPoor communicationDesign changesContradictory record keepingDisagreements between partiesDifficulties in coordinationDifferences in attitudesLate submissions of documentsLess experience

Between laborers(Acharya et al., 2006)

Personal mattersUnethical behaviorBad temperAuthority issues

Contractor – subcontractors Payment issuesDifficulties in coordinationUnprofessional behaviorPoor communicationCompetitionBad history

Between specializedcontractors

Unprofessional behaviorBad historyCompetitionMaterial and equipment handling

Documentation-related conflicts Design errors (Acharya et al.,2006; Ng and Skitmore, 2000)

Poor documentationSupremacy of professionalsPoor communicationImpracticable design

Documentation errors(Acharya et al., 2006; Jaffaret al., 2011)

High workload of the partiesSupremacy of professionalsPoor communicationNegligenceDelays caused by partiesConvenience of one party

Late submission ofdocuments (Acharya et al.,2006; Verma, 1998)

High workload of the partiesInternal and external problems of thepartiesDisagreements

Contradictions betweendocuments (Acharya et al.,2006; Jaffar et al., 2011)

Disagreements by partiesHigh workload of the partiesPoor communicationNegligencePoor documentation

Designs are not finalized(Acharya et al., 2006; Ng andSkitmore, 2000)

Impracticable designPersonal delays

(continued )

Table III.Conflicts andtheir sources

187

Sri Lankancommercial

building sector

Page 58: Engineering, Construction and Architectural

client to pay them directly […] In order to keep the labour in the project, the contractor onlypaid half of the wages and this created a situation where the contractor was unable to do thepayments to the labourers properly due to the accumulative liable amounts.” This statementrevealed that non-payment extremely disturbed the timely completion of the projectoccurring unnecessary wastage of time and relationships issues. In addition, allstakeholders agreed that non-payment will be a generator of other issues such as laborshortage, poor quality in construction and labor idling. Friedman et al. (2000) identifiednon-payment as an intergroup conflict where two groups in one unit obtainincompatibilities. However, according to Verma (1998), non-payment can either often bean administrative conflict or rarely an interpersonal conflict depending on the situation.

6.2 Relationship conflictsThe interviewees indicated that the commercial building industry often faced fourrelationship conflict situations. They are consultant – contractor conflicts, conflicts betweenlaborers, contractor – subcontractor conflicts and conflicts between specialized contractors.Findings suggested that human diversity is a common fact yet difficult to control bymaking everyone focus on one target. It is a known fact that people with different attitudes,agendas, social status, educational background and characteristics will often generateconflicts. Accordingly, the Sri Lankan commercial building industry has to face the sameproblem due to the involvement of many parties. This is in line with the findings ofChou and Yeh (2007), DeChurch et al. (2007), Desivilya et al. (2010), Huan and Yazdanifard(2012), Jehn and Chatman (2000), Senaratne and Udawatta (2013) and Simons and Peterson(2000) as they identified relationship conflicts as disagreements between people who work toachieve one target. However, the previous literature of the aforementioned authors indicatedthat relationship conflicts are often personal and rarely related to the task yet this studyfound that the relationship conflicts often occur due to task-related matters. Nonetheless,relationship conflicts affect the project performance even though they are personal or taskrelated (Wild, 2002).

The most frequent conflict situation is conflicts between the consultant and contractor.CL04 mentioned that “The consultant and the contractor are not very close. The problem is

Conflict type Conflict situation Sources

Poor communicationConstant changes by the client andthe consultants

Execution of work-related conflict Variations (Acharya et al.,2006)

Design errorsImpracticable designRequirements of partiesDelayed instructionsDisagreements by partiesContradictory record keepingIncorrect record keeping

Issues regarding agreeing onrates (Acharya et al., 2006;Dreu and Vianen, 2001)

Less experienceDisagreements by parties

Issues regarding resources(Cheung and Chuah, 1999;Dreu and Vianen, 2001)

Unavailability of resourcesPoor coordinationPoor Communication

Quality issues (Acharya et al.,2006; Ng and Skitmore, 2000)

Late submission of samplesNegligenceDelayed instructionsTable III.

188

ECAM25,2

Page 59: Engineering, Construction and Architectural

not with the management of the consultant and contractor. They work friendly. However, theproblem is with the subordinate level. The subordinate crew of the consultant’s side and thecontractor’s side have lot of mismatching ideas which often lead them to disagreements.”This statement revealed that most of the consultant – contractor conflicts are occurred in theintermediate or the operational level of the organizational hierarchy. This is in line with thefindings of Chen et al. (2014) as they indentified that conflicts can be often occurred betweenthese two parties due to the task-related issues, process-related issues and the status of theprevailing relationship between the client and the contractor.

The second most common relationship conflict is between laborers. This is more criticaldue to the tendency of having severe arguments, quarrels and even destruction of theproperty. According to CR03, number of conflicts is taken place between the laborers and infew occasions, the contractor had to intervene to solve them. Further to CR03, the works hadto be temporarily stopped in such occasions since other laborers are automatically becomethe spectators of such quarrels and severe arguments and sometimes taken part in thetempered situation. CN01 confirmed this fact by revealing that his project had similarexperiences, yet not as much as in Case 3. Similarly, DeChurch et al. (2007) explained that thecritical relationship conflicts will inversely affect the work performance. Further, Huan andYazdanifard (2012) mentioned that conflicts between employees certainly affect thecommitment of employees and cause absenteeism.

Conflicts between the contractor and subcontractors are often occurred due to paymentissues and resource handling. This is in line with the findings of Acharya et al. (2006) and Verma(1998) as the authors pointed out late or poor administrative procedure and resource allocationissues would critically affect the parties who continue the onsite functions. As revealed by CN01,the subcontractors of the project stopped working due to the conflicts with the contractor andrefused to deal with him. Instead, they requested the client to correspond directly with them.This is not the general procedure of the project yet the client had to agree with their demand inorder to continue the project. CR01 revealed that contractor – subcontractor relationship is theweakest when compared to other professional relationships in the project. CL03 mentioned thatit is hard to find good professional relationships between contractors and subcontractors in theSri Lankan commercial building industry due to the high competitive nature yet most of themare highly professional and focus on the project rather than fulfilling their own agendas when itcame to working together.

The final conflict situation under the relationship conflicts is between specializedcontractors. This cannot be often seen due to the less usage of the particular procurementarrangement. However, if the project procurement arrangement consists of more than onespecialized contractor, this conflict situation is common. According to CL03, it is very hardto coordinate the specialized contractors with regard to resource handling. The specializedcontractor who did the architectural and structural construction had to facilitate the othercontractors yet he had to face difficulties in providing facilities simultaneously to severalparties. As a result, there are conflicts between them, especially during the finishing stage.Majority of the stakeholders who attended the meetings agreed with the fact that theconflicts between specialized contractors are not just situational yet more personal due tothe historical incidents. They also pointed out that the ethical behavior of these contractorsare not up to a professional level when compared to other stakeholders, thus lead to conflictsmore often. According to Rahim (2002), this kind of interpersonal conflicts will barricade thesuccessful completion of project since the parties will give more attention to reduce thethreat coming from the other party and try to increase their power over the project.

6.3 Documentation-related conflictsAccording to the meetings conducted, there are five common conflict situations underdocumentation-related conflicts. They are design errors, documentation errors, late submission

189

Sri Lankancommercial

building sector

Page 60: Engineering, Construction and Architectural

of documents, contradictions between documents and non-finalized design. Both Jehn andChatman (2000) and Simons and Peterson (2000) identified the documentation-relatedconflicts as a sub category of process conflicts. Senaratne and Udawatta (2013) nameddocumentation-related conflicts as conflicts related to administrative procedure.

The most frequent conflict situation is design errors. CN01 stated that “There are manydesign errors which created lot of difficulties such as increasing budget, getting approvals,etc. On the other hand, many changes had to be done to the initial design due to the issues inthe initial design.” This statement revealed that lot of time and energy are wasted to correctthe design errors and it is a frustrating procedure. The end result of such procedure is toleave the actual construction on site on hold creating room for more and more conflicts.According to CN02, the more the design is complex, the more the design errors. During thediscussions with the stakeholders, it is revealed that all four cases had design errors. Most ofthe conflicts arising with design errors are dealt with variations which created unnecessarywastage of time, money and energy. Similar findings are put forward by Ng and Skitmore(2000) by revealing that the design errors and incompatibility in designs will definitelycreate more conflicts in the future when real construction occurred and negatively affecttime and quality standards.

The second most common conflict situation in relation to documentation isdocumentation errors. However, Jaffar et al. (2011) identified that the errors, omissionsand defects in documents as a major source of conflict. CL02 mentioned that “Actually, thereis no proper condition in the contract regarding the price escalation of imported material andwhat currency should be used to calculate the price escalations of duty free materials […]It is a serious issue occurred due to documentation errors.” CR02 added more information bymentioning that “Furthermore, we needed lot more steel than it is mentioned in the Bills ofQuantities (BOQ). So we had to buy local steel as well. In this case, we faced the problem ofhow to take the duty free facility because it is given for USD prices only.” This is happeneddue to the under measured steel quantity in the BOQ. Both stakeholders confirmed that themain reason for the increment of initial contract amount is the under measured items inthe BOQ which is a huge documentation error. The other stakeholders who attended themeetings further contributed to the topic by revealing that most documentation errors arenot just reasonable human errors yet the acts of negligence.

The third documentation-related conflict is late submission of documents. CN04 statedthat “The contractor did not submit the documents on time and as we required. We arguedseveral times about this. However, the client had no problem with the way of the contractor’ssubmissions of monthly statement so that he said it to be submitted once two months. I stilldo not agree with this method because it creates a huge workload for the client in one monthand there will be no much work in the second month. Actually, it’s an imbalance.” Further toCN02, late submission of documents often created arguments and frustrations harming theprofessional relationship of both parties. CR01 mentioned that due to the late submission ofdocuments, construction on site often got delayed and the workload of the receivingparty always got high due to the limited time they had to finish the particular items.Both Acharya et al. (2006) and Verma (1998) identified this conflict situation in a broadmanner by introducing it as a delay and as a goal oriented conflict, respectively.

Contradictions between documents are another conflict situation which can becommonly seen in the Sri Lankan commercial building industry. According to Jaffar et al.(2011), the contradictions of documents often led the professionals into conflicts. CL03mentioned that “In this project, there is a conflict regarding the BOQ item for screedconcrete. In the BOQ, only the screed concrete is priced yet in the drawing, there are someother layers additional to the screed concrete. In addition, the screed thickness given in thedrawing is different to the thickness mentioned in the BOQ. The contractor argued aboutthis and there are some discussions related to the matter. This conflict occurred due to the

190

ECAM25,2

Page 61: Engineering, Construction and Architectural

contradiction between BOQ and drawings.” It is a known fact that normally there is acondition regarding the priority of documents in the conditions of contract. Yet the problemis with the price since the other layers which are on the drawings are not priced in the BOQ.CN03 agreed that it is a responsibility of the consultant team due to the high workloadwithin a limited time.

Another general conflict situation that can be commonly seen in the Sri Lankancommercial building industry is non-finalized designs. CR03 mentioned that “By the time westarted the construction, some items of the project such as mechanical, electrical andPlumbing (MEP) works, ceiling layouts, etc are not finalized. Furthermore, those parts arenot finalized even though we completed a major part of the structural work. Therefore, whenthey are finalized, we had to change several completed items. This led to a big conflict.In addition, this wasted a lot of time and money.” This is a critical issue which led the partiesto several arguments and disagreements. It is also a huge waste of money, time and energyby destroying the concept of value for money. These findings are similar to Ng andSkitmore (2000) as they argued the conflicts related to design often occurred due to theincorrect selection of the design team and incompatibilities of their work.

6.4 Execution of works-related conflictsAccording to the stakeholders who attended the meetings, there are four common conflictsituations with regard to execution of work-related conflicts. They are variations, issuesregarding agreeing on rates, issues regarding resources and quality issues. However, theresearches of Huan and Yazdanifard (2012), Jehn and Chatman (2000), Senaratne andUdawatta (2013) and Simons and Peterson (2000) identified this conflict type as task conflicts.

The most common execution of work-related conflict is variations. Acharya et al. (2006)categorized variations as a consultant evoked conflict which occurred due to confusingrequirement of the owner and unclear project scope established by the owner. However, theabove stated two sources of variations are categorized into owner evoked conflicts.Variations are common to all four cases and all the stakeholders who attended the meetingsconfirmed that variations are common to all projects they are previously engaged with.CR03 mentioned that “Both client and architect did several major changes to the initialdesign so that there are lot of variations; nearly 150 variations at the end of the project. Thistook so much additional time and money and created lot of conflicts regarding the design,cost and quality.” Further to CR03, the workload carried by them is enormous whencompared to a similar project thus the effective contribution of the employees areconsiderably low. According to CN02, it is hard for them to meet the deadlines due tothe high amount of variations and a number of discussions had to be made to manage theconflict situations arising from the variations.

The second most common conflict situation with regard to the execution of works-relatedissues is issues regarding agreeing on rates. This is not commonly addressed by the previousliterature yet considered as a task conflict which makes the path to relationship conflicts(Simons and Peterson, 2000). CN04 stated that “Basically, we had huge and long term conflictof agreeing on rates. As the consultant, we always tried to save and utilize the client’s money.So if the rates are not reasonable, we had to disagree with them. So we had several occasionsin which we had to thoroughly argue about the matters arising from rates. However, thisconflict created some delays to the project and destroyed the good relationship we had withthe Contractor.” It is further revealed that due to the issues regarding agreeing on rates, allsubsequent works are delayed and the lengthy discussions regarding the matter often endedup with heated arguments, leaving the problem as it is.

Another execution of works-related conflict is issues regarding the resources.The findings of Acharya et al. (2006), Cheung and Chuah (1999) and Senaratne andUdawatta (2013) identified this conflict situation as a source of conflicts. However, this study

191

Sri Lankancommercial

building sector

Page 62: Engineering, Construction and Architectural

identified the issues in resource handling as a conflict situation; not as a source of conflictsince it obtains its own sources. According to CR01, it is hard for them to find skilled laborand keep them in the project in the long run. Whenever there is any other conflict such asdelayed payments, non-payment, late submission of documents or any relationship conflictwhich hold the work for a while, the laborers went looking for other jobs. Therefore, laborhandling is a big problem in this project. CL03 mentioned that they have faced difficulties inproviding facilities to the specialized contractors simultaneously. CR03 agreed with CL03 byrevealing how hard it is to provide scaffoldings, formwork and the like concurrently toseveral contractors.

Quality issues are one of the most critical execution of works-related issues since itdirectly affected the client’s expectations. CR01 mentioned that “Quality of labour is low.For example it is very difficult to find good masons and carpenters, and also their wages aretoo high.” Due to the low quality in workmanship, the end product would not gain the valuefor money. Moreover, the finish would not be according to the standards. Ultimately, thebuilding would not be finished according to the client’s requirements. Similarly, CN03mentioned that they often had to check the quality of the materials supplied by the suppliersto the project due to frequent identification of low quality materials. Moreover, severalconstructed items of the building required rework due to the usage of low quality materials.Similarly, Ng and Skitmore (2000) stated that the current construction industry require highquality product while allocating less time and money for design and construction and thiswill often lead the project to conflicts related to quality standards.

7. Conflict managementThe findings revealed that every project has its own conflict management procedure withdifferent magnitudes. The stakeholders who took part in meetings revealed that conflictmanagement is crucial for the successful completion of the project and to avoid expensiveand time consuming dispute resolution procedure. Further to them, conflict management isnot eliminating the conflict yet dealing with it in such a way that it will not generate harmfuleffects. This is in line with the findings of Popovic and Hocenski (2009) since theyintroduced the principle of conflict management as handling the conflict in such a way thatit will not generate harmful effects. Similarly, Jaffar et al. (2011) stated that it is moreeffective and practical to manage the conflicts rather than trying to resolve it by wastingtime, money and energy since conflicts are inevitable due to the complexity, lengthy time ofconstruction and multi-disciplinary involvement.

According to the stakeholders who attended the meetings, conflict management is alarge spectrum of the stages of avoiding the possibilities of having conflicts, preparation forpotential conflicts by considering the past experiences, early identification of conflicts,utilize the constructive part of the conflicts, conflict management by using managementstyles, dispute avoidance and maintaining records for future use. Similarly Verma (1998)introduced three stage conflict management strategy: getting ready for the conflictby expecting of conflict and planning to face the conflict; experiencing the conflict byrecognizing its real nature; and managing the conflict as per the plan with necessarychanges. However, Verma (1998) did not give a consideration for the aftermath of theconflict management. Out of the five conflict management styles in dual concern theory,four styles are using in the Sri Lankan commercial building industry. They arecompromising, authority, obliging and avoiding. Problem solving style can be rarely seenyet the probability of using it is considerably low due to the fact that providing highconsideration for both self and others simultaneously is not practicable in the competitivecommercial building industry. This is partially in line to the findings of Vu and Carmichael(2009) as they argued most of the Eastern countries, due to their cultural values and desire ofgroup harmony, tend to use avoiding and obliging styles.

192

ECAM25,2

Page 63: Engineering, Construction and Architectural

7.1 CompromisingCompromising is the most common conflict management style used in the Sri Lankancommercial building industry. CN01 mentioned that “The most common method we used isnegotiation. We always talk with both client and the contractor about the conflict situationsand how we should manage them. Similarly, we talked with subcontractors as well. Lot ofconflicts are managed through proper negotiation. It never provided the opportunity to haveeverything we need but it always gave an acceptable solution for both parties.” Thisstatement revealed that even though the parties could not achieve their full intentions, theyare able to manage the conflict situation by gaining the maximum satisfaction according tothe situation. Further to him, negotiation is the most effective conflict management stylesince it enabled them to avoid unnecessary cost and time increments and protect the goodprofessional relationships. According to CR01, good professional relationships are the pathto more future projects, thus certain sacrifices had to be made for the sake of future success.During the discussions with the stakeholders, it is revealed that all four cases usednegotiation as their main conflict management style. This is in line with the findings ofAppelbaum et al. (1998) in relation to North America, Lee (2008) in relation to Malaysia,Ozkalp et al. (2009) in relation to Turkey and Al-Sedairy (1994) in relation to Saudi Arabia asthey all prefer negotiation as their key conflict management style.

7.2 ForcingThe second most common conflict management style with regard to the Dual ConcernTheory is forcing which is commonly known as authority in the building industry. CN01mentioned that “Of course we had to use our authority to come to the conclusion that we paydirectly to the subcontractors. Furthermore, we had to use our authority to manage theconflicts occur due to delayed submissions of monthly statements and some designchanges.” According to him, using authority should be done carefully in the right occasion.Nevertheless, it is a famous technique to manage the conflict since all stakeholders respectthe organizational hierarchy as well as line of authority. CR03 further explained theeffectiveness of this technique by stating “As an Engineer, I know the rules of engineeringand if a client or a consultant says something that opposes the rules of Engineering whichcould also effect on strength or finishes of the building, I cannot negotiate or accept whatthey say. For instance, if perimeter of walls is 9 inch, then it should be nothing less than that.If we cannot go for the plasterboard walls or the dry walls due to the weather and thesurroundings, we must not use them. Basically, in some areas we are very confident of whatwe should and should not do. In these situations, I have to make them accept my decisionbecause I know the technology well.” This statement revealed that in some occasions, usingauthority is crucial in order to avoid structural failures. Further to CR03, having a certainauthority for every construction professional is itself a conflict management techniquewhich should be used in the correct situation. According to the opinion of Appelbaum et al.(1998), forcing style is a better style to be used in conflict management either individually orwith other conflict styles. Similarly, Vu and Carmichael (2009) suggested that most of theWestern countries tend to use dominating style as they are more individualistic inprofessional matters. However, this is an opposing idea with regard to this study sinceSri Lankan building industry use forcing style more often than obliging or avoiding whichare generally preferred by the Eastern countries.

7.3 ObligingThe third conflict management style used in the Sri Lankan commercial building industry isobliging. This is opposite of using authority. CN04 stated that “The contractor did notsubmit the documents on time and as we required. We argued several times about this.However, the client has no problem with the way of the contractor’s submissions of monthly

193

Sri Lankancommercial

building sector

Page 64: Engineering, Construction and Architectural

statement so that he said it to be submitted once two months. I still do not agree with thismethod because it creates a huge workload for the client in one month and there will be nomuch work in the second month. Actually, it’s an imbalance. However, as the consultant, wehad to agree with the client.” This statement revealed that obliging style created a win forone party while other party obtained a total loss. However, the losing party had to accept itdue to the authority carried by the third party (Client in this scenario). Nevertheless, thewinning party did not achieve their win due to their own authority yet due to the authorityof the third party had over both conflicting parties. Therefore, obliging can be seen in twodifferent ways; if one party has more power than the other party, the latter party had to useobliging style, and if a third party has more power than the conflicting parties, both partieshave to use obliging style. CN01 mentioned that “The contractor at most of the times agreedwith our decisions. When we decided to pay the subcontractors directly, the contractoragreed with that. He is always supportive to the consultant’s decisions when he thoughtthat the consultant’s decision is more reasonable.” This statement revealed that obliging isnot always a loss. It can be a way of accepting the right thing to do even though it is notbeneficial to one party. Further to CN01, obliging is a professional way to manage theconflict if one party is more reasonable and factually strong than the other party.The stakeholders agreed to the fact that obliging is not merely a win-lose approach yet itprovided advantageous results such as reducing the professional responsibility of the losingparty. This is opposite to the findings of Zhang et al. (2015) as the authors argued that eventhough Eastern countries preferred obliging in the past, the current preference has changed,ranking obliging as one before the last due to the competition, rapid development andglobalization. Malaysian construction sector prefer obliging as a combined conflictmanagement technique with either compromising or integrating (Lee, 2008).

7.4 AvoidingThe final conflict management style used by the Sri Lankan commercial building industry isavoiding. CR02 explained this by using his experience; mentioning that “The client did notpay us around USD 0.75 Million. His argument is that he will not pay for the claims issuedafter the completion of project. Nevertheless, we ignored that because we wanted to have agood professional relationship with the employer.” In this incident, the contractor’s party didnot consider about the financial loss they gained. Instead, they consider about maintaining thegood professional relationship with the intention of having all future projects of the client.When consider about the client, even though he did not have to pay the additional costs, hebecame liable to the contractor, creating an ethical liability to favor the contractor in all futuretendering procedure. In addition, the client lost his power over the contractor. CN01 stated that“However, we avoided the labourer’s conflicts because they are not relevant to us.” Avoidingstyle can be used for the conflicts which are not directly relevant to the construction. However,in this situation, the labor conflicts wasted a considerable time. Nevertheless, the relevantparties refused to involving in them due to the fact that if they involve, the conflicts mightbecome severe with labor strikes and harming the property. Using avoiding style enabled theproject to keep both conflicting parties on site since nomanagerial level professionals took anyside. The findings of the study partially agreed with Friedman et al. (2000) since they arguedavoiding is suitable for conflicts which cannot be managed due to lack of knowledgeregarding the conflict. However, this study identified that avoiding style can be used for theaforementioned conflicts as well as for the conflicts which occur in project yet not relevant tothe project. Moreover, the study agreed with the findings of the Ohbuchi and Suzuki (2003) inrelation to Japan and Zhang et al. (2015) in relation to China as they rarely use avoidancecurrently, changing their preference toward compromising and integrating.

During the meetings, the stakeholders pointed out the conflict management styles usedfor the conflict situations they have faced. They are shown in Figure 2.

194

ECAM25,2

Page 65: Engineering, Construction and Architectural

8. DiscussionThe study focused on whether the magnitude of the project and its complexity has anyimpact on having conflicts. Accordingly, the magnitude of the project has a directrelationship with the tendency of having conflicts. The main reasons for such relationshipcan be identified as lengthy process of construction, involvement of more parties, highworkload, enormous documentation, high human diversity and limited resources. This is inline with the findings of Jaffar et al. (2011) and Alzahrani and Emsley (2012) as theyemphasized the conflicts are increasing in an alarming rate due to the construction of highrise buildings with lot of facilities, new technology and advanced services.

However, a connection between the complexity of the project and the tendency of havingconflicts cannot be derived according to the available information due to the disturbance

Payment Issues

Delayed Payments

Non-payment Avoiding Style

Avoiding Style

Obliging Style

Obliging Style

Avoiding Style

Obliging Style

Avoiding Style

Quality Issues

Issues regardingagreeing on Rates

Issues regardingResources

Variations

Non-finalized Designs

Contradictionsbetween Documents

Late submission ofDocuments

Documentation Errors

Design Errors

Conflicts betweenSpecialized Contractors

Contractor-Subcontractor Conflicts

Conflicts betweenLabourers

Consultant-ContractorConflicts

Relationship Conflicts

Documentation related Conflicts

Execution of Works-related Conflicts

Obliging Style

Compromising Style

Compromising Style

Forcing Style

Forcing Style

Compromising Style

Forcing Style

Compromising Style

Forcing StyleFigure 2.

Common conflictmanagement styles

used to solveconflict situations

195

Sri Lankancommercial

building sector

Page 66: Engineering, Construction and Architectural

occurred by Case 3. It obtained the highest number of conflicts even though it is lesscomplex than Case 1 and Case 2. The study then observed the reason for the disturbanceand found that the procurement arrangement of Case 3 is different to other three cases.In Case 3, the involvement of professional parties is way higher than the other three cases.The project had nine specialized contractors who directly involved with the client and foursubcontractors who dealt with the specialized contractor for architectural and structuralworks. Therefore, it can be pointed out that the one main reason for having more conflicts ishigh multi-disciplinary involvement. This is in line with the findings of Yousefi et al. (2010)as they indicated that multi party involvement in construction often complicate theproject and generate conflicts due to the lack of coordination among the parties, poorcommunication and high work load. Further to this study, having a vast documentationprocess which involved more parties led the project toward more conflicts. Theoretically,Case 3 had to face the problems eight times multiplied when compared to the other threecases; especially the relationship conflicts. Therefore, the number of conflicts of Case 3 is aspecial condition. If consider about the other three cases, a pattern can be identified withregard to complexity and having conflicts; they obtained a direct relationship. This is in linewith the findings of Jaffar et al. (2011) and Yousefi et al. (2010) as both studies specificallymentioned about the direct relationship between the conflicts and complexity of projects.

Even though the magnitude and complexity had a direct relationship with the tendencyof having conflicts, the severity of conflicts did not have a relationship with the project.During the meetings, the stakeholders are questioned about the severity of the conflictsituations they experienced. Accordingly, Case 1 is having severe conflicts than the otherthree cases even though it is not big as Case 2 and Case 3. The main reason for havingsevere conflicts is the personal respond of the parties and how the situation is initiallyhandled. This is in line with the findings of Tjosvold (2006) and Giritli et al. (2009) as theyargued conflicts did not rise themselves or escalate themselves yet they are created anddeveloped by the wrong behavior of people.

According to Tjosvold (2006), it is obvious that humans are behind the creation ofconflicts as well as the management of them. This theory is common to the Sri Lankancommercial building industry as well due to the involvement of many people with differentbackgrounds, attitudes, characteristics, education and skills. However, every stakeholder ina project carries a professional responsibility to complete the project by doing his partwithout giving priority to their personal goals and personal matters. Nevertheless, aquestion should be raised whether the professionalism of stakeholders create any impact onthe tendency of having conflicts.

During the meetings with stakeholders, it is identified that most of the relationshipconflicts during construction are occurred between the operational level stakeholders whocontinuously dealt with each other. According to the data analysis, Case 2, Case 3 andCase 4 had number of relationship conflicts between consultant’s staff and contractor’sstaff. The major reasons for this situation are identified as less experience and lack ofinterpersonal skills. As pointed out by the stakeholders in meetings, if there is no enoughexperience, it is hard to survive in the construction world since it is all about handlingpeople in such a way that they would willingly agree for everything even though it is nottheir main intension. Further, less experienced stakeholders often handle the situationsaccording to books, yet in this kind of an industry; “work by the book” concept couldcreate more harm than good. Furthermore, having good interpersonal skills would assistthe stakeholders to deal with other people. Hence, it can be said that the level of experienceof stakeholders obtain an inverse relationship with conflicts. Even though past literaturedid not directly talk about the particular matter, Huan and Yazdanifard (2012) arguedthat the relationship between supervisors and subordinates often decided the amount ofconflicts occurred between them.

196

ECAM25,2

Page 67: Engineering, Construction and Architectural

The study further focused on whether the organization culture has any impact on thetendency of having conflicts. It is found that the contracting companies maintain a resultoriented organization culture whereas the consultancy companies maintain a processoriented organization culture in most of the Sri Lankan commercial building sector. Thesefindings are in line with the findings of Rameezdeen and Gunarathna (2003) as they identifythe consultancy companies as goal oriented and well organized on the process whileidentifying the contracting companies as competitive and well encouraged for outputmaximization. According to the analysis, it is visible that contracting companies tend tohave a diverse range of conflicts than the consultancy companies (example Case 1 andCase 2). Therefore, it can be said that the tendency of having conflicts is high in a resultoriented organization culture. This is mainly due to the eager to gain profit. However, it canbe also seen that the contracting companies are more interested in proper conflictmanagement and willing to compromise and make sacrifices whereas the consultancycompanies hesitate to go above the rule.

9. Conclusion and recommendationsConflicts are natural and inevitable in the Sri Lankan commercial building industry.According to the findings of this study, there are 15 conflict situations that can becommonly seen in the Sri Lankan commercial building sector which can be categorizedinto four main conflict types, namely; payment issues, relationship conflicts,documentation-related conflicts and execution of works-related conflicts. The studyfocused on the sources of these conflict situations and found out that some of the mostcommon sources of the aforementioned 15 conflict situations are financial issues of theparties, selection of underpriced bids, unprofessional behavior, poor communication, poorcoordination, bad history, poor documentation, supremacy of professionals, high workload, disagreement of parties, design errors, less experience, unavailability of resourcesand negligence.

According to the findings, the most commonly used conflict management style inSri Lankan commercial building sector is compromising style which enabled both parties togain some degree of satisfaction. It is surprising to see that forcing style received the secondplace irrespective of the value given to the collectivism qualities in Sri Lanka. It is highlyargued and well accepted that most of the conflict situations can easily managed by usingforcing styles. Obliging style received the third place in the ranking of common conflictmanagement styles. According to the stakeholders in the Sri Lankan building industry,obliging style is a way of protecting good professional relationships which can be a goodinvestment for future. However, obliging style is not famous as compromising and forcing.The least common conflict management style is avoiding. The findings revealed thatavoiding style is used whenever the conflict is not relevant to the project or when the partiesare not equipped with information to manage the conflict. It is shocking to see thatSri Lankan commercial building sector rarely use problem solving style for conflictmanagement even though it is the most effective conflict management style with long termsolutions and creative thinking. However, it should be noted that these findings onlyindicate the commonness of using the styles yet not the perfect conflict management style toa particular conflict. Further, the study does not introduce the best conflict managementstyle which satisfy both parties. It only provides information about the common conflictmanagement styles used for a particular conflict situation. Selecting the perfectconflict management style as per the situation is completely in the hand of the parties byusing their knowledge, experience and historical data. However, when they decide whichconflict management style should be used, the parties can rely on these findings (what is themost commonly used management style to a particular conflict) as these have demonstratedpositive outcomes.

197

Sri Lankancommercial

building sector

Page 68: Engineering, Construction and Architectural

It is identified that tendency of having conflicts in the construction projects has a directrelationship with the magnitude of project and the complexity of the projects. However,there is no relationship between the severity of conflicts and the magnitude and thecomplexity of projects. The severity of conflict will be decided by the human behavior.Further to findings, the experience of the stakeholders has an inverse relationship with thetendency of having conflicts.

References

Abeynayake, M. and Weddikkara, C. (2007), “Resolving construction disputes”, The Nations, April 29,available at: www.nation.lk/2007/04/29/newsfe1.htm

Abeynayake, M. and Weddikkara, C. (2012), “Critical analysis on success factors of adjudication andarbitration practices in the construction industry of Sri Lanka”, Proceedings of 9th InternationalConference on Business Management 2012, Faculty of Management Studies and Commerce,University of Sri Jayewardenepura, February 28-March 1, 2013, pp. 209-222.

Acharya, N.K., Lee, Y.D. and Im, H.M. (2006), “Conflicting factors in construction projects: Koreanperspective”, Engineering, Construction and Architectural Management, Vol. 13 No. 6,pp. 543-566, doi: 10.1108/09699980610712364.

Adnan, H., Shamsuddin, S.M., Supardi, A. and Ahmad, A. (2011), “Conflict prevention in partneringprojects”, Proceedings of the Asia Pacific International Conference on Environment-BehaviourStudies, pp. 772-781, available at: www.sciencedirect.com

Akiner, I. (2014), “Critical viewpoints on the management of conflict in multi-national constructionprojects”, Organization, Technology and Management in Construction – An InternationalJournal, Vol. 6 No. 2, pp. 1038-1046, doi: 10.5592/otmcj.2014.2.6.

Al-Sedairy, S.T. (1994), “Management of conflicts: public-sector construction in Saudi Arabia”,International Journal of Project Management, Vol. 12 No. 3, pp. 143-151.

Alzahrani, J.I. and Emsley, M.W. (2012), “The impact of contractors’ attributes on construction projectsuccess: a post construction evaluation”, International Journal of Project Management, Vol. 31No. 2, pp. 313-322, doi: 10.1016/j.ijproman.2012.06.006.

Appelbaum, S.H., Shapiro, B. and Elbaz, D. (1998), “The management of multicultural group conflict”,Team Performance Management, Vol. 4 No. 5, pp. 211-234.

Atteya, N.M. (2012), “The conflict management grid: a selection and development tool to resolve theconflict between the marketing and sales organizations”, International Journal of Business andManagement, Vol. 7 No. 13, pp. 28-39, doi: 10.5539/ijbm.v7n13p28.

Cheung, C.C. and Chuah, K.B. (1999), “Conflict management styles in Hong Kong industries”,International Journal of Project Management, Vol. 17 No. 6, pp. 393-399.

Chen, Y.Q., Zhang, Y.B. and Zhang, S.J. (2014), “Impacts of different types of owner-contractor conflict oncost performance in construction projects”, Journal of Construction Engineering and Management,Vol. 140 No. 6, pp. 04014017-1-04014017-8, doi: 10.1061/(ASCE)CO.1943-7862.0000852.

Chou, H.W. and Yeh, Y.J. (2007), “Conflict, conflict management and Performance in ERP teams”, SocialBehavior and Personality, Vol. 35 No. 8, pp. 1035-1048.

DeChurch, L.A., Hamilton, K.L. and Haas, C. (2007), “Effects of conflict management strategies onperceptions of intragroup conflict”, Group Dynamics: Theory, Research, and Practice, Vol. 11No. 1, pp. 66-78, doi: 10.1037/1089-2699.11.1.66.

Desivilya, H.S., Somech, A. and Lidgoster, H. (2010), “Innovation and conflict management in workteams: the effects of team identification and task and relationship conflict”, Negotiation andConflict Management Research, Vol. 3 No. 1, pp. 28-48.

Dreu, C.K.W. and Vianen, A.E.M. (2001), “Managing relationship conflict and the effectivenessof organizational teams”, Journal of Organizational Behavior, Vol. 22 No. 3, pp. 309-328,doi: 10.1002/job71.

198

ECAM25,2

Page 69: Engineering, Construction and Architectural

Dreu, C.K.W.D., Evers, A., Beersma, B., Kluwer, E.S. and Nauta, A. (2001), “A theory-based measure ofconflict management strategies in the workplace”, Journal of Organizational Behavior, Vol. 22No. 6, pp. 645-668, doi: 10.1002/job.107.

Ellis, T.J. and Levy, Y. (2009), “Towards a guide for novice researchers on research methodology:review and proposed methods”, Issues in Informing Science and Information Technology, Vol. 6,pp. 323-337, available at: http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.362.5929&rep=rep1&type=pdf

Femi, O.T. (2014), “Causes and effects of conflict in the Nigerian construction industry”, InternationalJournal of Technology Enhancements and Emerging Engineering Research, Vol. 2 No. 6, pp. 7-16.

Fenn, P., Lowe, D. and Speck, C. (1997), “Conflict and dispute in construction”, ConstructionManagement and Economics, Vol. 15 No. 6, pp. 513-518.

Fisher, R.J. (2000), “Sources of conflict and methods of conflict resolution”, available at: www.ulstergaa.ie/wp-content/uploads/coaching/team-management-2012/unit-3/sources-of-conflict-and-methods-of-resolution.pdf (accessed October 27, 2016).

Friedman, R.A., Tidd, S.T., Currall, S.C. and Tsai, J.C. (2000), “What goes around comes around: theimpact of personal conflict style on work conflict and stress”, The International Journal ofConflict Management, Vol. 11 No. 1, pp. 32-55.

Giritli, H., Balci, D. and Sertyesilisik, B. (2009), “An investigation on the conflict-resolving approachesof the employees in the construction industry”, International Journal of Construction ProjectManagement, Vol. 6 No. 1, pp. 75-91.

Gorse, C.A. (2003), “Conflict and conflict management in construction”, Proceedings of the 19th AnnualARCOM Conference, pp. 173-182, available at: www.arcom.ac.uk/-docs/proceedings/ar2003-173-182_Gorse.pdf

Gunarathna, M.A.C.L. and Fernando, N.G. (2014), “Stakeholders’ preference towards the use of conflictmanagement styles in dual concern theory in post contract stage”, Proceedings of InternationalConference on Construction in a Changing World 2014, School of the Built Environment,University of Salford, Kandalama, May 4-7.

Heenkenda, H.M.N.S.B. and Chandanie, H. (2012), “Minimizing conflicts in building constructionthrough proper procurement arrangements”, Proceedings of 9th International Conference onBusiness Management 2012, Faculty of Management Studies and Commerce, University ofSri Jayewardenepura, February 28-March 1, 2013, pp. 124-141.

Huan, L.J. and Yazdanifard, R. (2012), “The difference of conflict management styles and conflictresolution in workplace”, Business & Entrepreneurship Journal, Vol. 1 No. 1, pp. 141-155.

Jaffar, N., Tharim, A.H.A. and Shuib, M.N. (2011), “Factors of conflict in construction industry:a literature review”, Proceedings of the 2nd International Building Control Conference,pp. 193-202, available at: www.sciencedirect.com

Jehn, K.A. and Chatman, J.A. (2000), “The influence of proportional and perceptual conflict compositionon team performance”, The International Journal of Conflict Management, Vol. 11 No. 1,pp. 56-73.

Latiffi, A.A., Mohd, S., Kasim, N. and Fathi, M.S. (2013), “Building information modeling (BIM)application in Malaysian construction industry”, International Journal of ConstructionEngineering and Management, Vol. 2 No. 4A, pp. 1-6, doi: 10.5923/s.ijcem.201309.01.

Lee, K.L. (2008), “An examination between the relationships of conflict management styles andemployees’ satisfaction”, International Journal of Business and Management, Vol. 3 No. 9,pp. 11-25.

Lu, W., Li, Z. and Wang, S. (2017), “The role of justice for cooperation and contract’s moderating effectin construction dispute negotiation”, Engineering, Construction and Architectural Management,Vol. 24 No. 1, pp. 133-153, doi: 10.1108/ECAM-01-2015-0002.

Meyer, C.J., McCormick, B., Clement, A., Woods, R. and Fifield, C. (2012), “Scissors cut paper: purposiveand contingent strategies in a conflict situation”, International Journal of Conflict Management,Vol. 23 No. 4, pp. 344-361, doi: 10.1108/10444061211267254.

199

Sri Lankancommercial

building sector

Page 70: Engineering, Construction and Architectural

Naoum, S.G. (2007), Dissertation Research and Writing for Construction Student, 2nd ed., Elsevier Ltd,Oxford.

Ng, S.T. and Skitmore, R.M. (2000), “Contractors’ risk in design, novate and construct contracts”,International Journal of Project Management, Vol. 20 No. 2, pp. 119-126.

Ogunbayo, O. (2013), “Conflict management in Nigerian construction industry: project managers’view”, Journal of Emerging Trends in Economics and Management Sciences, Vol. 4 No. 2,pp. 140-146.

Ohbuchi, K. and Suzuki, M. (2003), “Three dimensions of conflict issues and their effects on resolutionstrategies in organizational settings”, The International Journal of Conflict Management, Vol. 14No. 1, pp. 61-73.

Oxford Dictionary (2017), “Management”, available at: https://en.oxforddictionaries.com/ (accessedJanuary 9, 2017).

Ozkalp, E., Sungur, Z. and Ozdemir, A.A. (2009), “Conflict management styles of Turkish managers”,Journal of European Industrial Training, Vol. 33 No. 5, pp. 419-438, doi: 10.1108/03090590910966571.

Popovic, K. and Hocenski, Z. (2009), “Conflict management”, available at: www.slideshare.net/KresimirPopovic/conflict-management-11488705 (accessed October 8, 2016).

Rahim, M.A. (2002), “Toward a theory of managing organizational conflict”, The International Journalof Conflict Management, Vol. 13 No. 3, pp. 206-235.

Rameezdeen, R. and Gunarathna, N. (2003), “Organisational culture in construction: an employeeperspective”, The Australian Journal of Construction Economics and Building, Vol. 3 No. 5,pp. 19-30.

Senaratne, S. and Udawatta, N. (2013), “Managing intragroup conflicts in construction project teams:case studies in Sri Lanka”, Architectural Engineering and Design Management, Vol. 9 No. 3,pp. 158-175, doi: 10.1080/17452007.2012.738041.

Seneviratne, K., Amaratunga, D. and Haigh, R. (2015), “Post conflict housing reconstruction”, BuiltEnvironment Project and Asset Management, Vol. 5 No. 4, pp. 432-445.

Simons, T.L. and Peterson, R.S. (2000), “Task conflict and relationship conflict in top managementteams: the pivotal role of intragroup trust”, Journal of Applied Psychology, Vol. 85 No. 1,pp. 102-111, doi: I0.1037//0021-9010.85.U02.

Thalgodapitiya, D. (2010), “Dispute resolution in construction industry”, Daily News, April 3, availableat: www.dailynews.lk/2010/04/03/bus32.asp

The Report, Sri Lanka (2016), “Construction and real estate”, Oxford Business Group, available at: www.oxfordbusinessgroup.com/sri-lanka-2016/construction-real-estate (accessed January 7, 2017).

Tjosvold, D. (2006), “Defining conflict and making choices about its management - lighting the darkside of organizational life”, International Journal of Conflict Management, Vol. 17 No. 2, pp. 87-95,doi: 10.1108/10444060610736585.

Trippe, B. and Baumoel, D. (2015), “Beyond the Thomas-Kilmann model: into extreme conflict”,Negotiation Journal, Vol. 31 No. 2, pp. 89-103, doi: 10.1111/nejo.12084.

Tsai, J.S. and Chi, C.S.F. (2009), “Influences of Chinese cultural orientations and conflict managementstyles on construction dispute resolving strategies”, Journal of Construction Engineering andManagement, Vol. 135 No. 10, pp. 955-964, doi: 10.1061/(ASCE)0733-9364(2009)135:10(955).

Verma, V.K. (1998), “Conflict management”, available at: www.iei.liu.se/pie/olsson-rune/material/attkommaigang/1.309206/conflManagementVer.pdf (accessed September 15, 2016).

Vu, A.T. and Carmichael, D.G. (2009), “Cultural difference and conflict management – aVietnamese-Australian and construction industry case study”, International Journal ofConstruction Management, Vol. 9 No. 2, pp. 1-19, doi: 10.1080/15623599.2009.10773125.

Wild, A. (2002), “The unmanageability of construction and the theoretical psycho-social dynamics ofprojects”, Engineering, Construction and Architectural Management, Vol. 9 No. 4, pp. 345-351.

Yin, R.K. (2009), Case Study Research, 4th ed., Sage Publications, CA.

200

ECAM25,2

Page 71: Engineering, Construction and Architectural

Yiu, K.T.W. and Cheung, S.O. (2006), “A catastrophe model of construction conflict behavior”, Buildingand Environment, Vol. 41 No. 4, pp. 438-447, doi: 10.1016/j.buildenv.2005.01.007.

Yousefi, S., Hipel, K.W. and Hegazy, T. (2010), “Attitude-based strategic negotiation for conflictmanagement in construction projects”, Project Management Journal, Vol. 41 No. 4, pp. 99-107,doi: 10.1002/pmj.20193.

Yusof, A.M., Ismail, S. and Chin, L.S. (2011), “Procurement method as conflict and dispute reductionmechanism for construction industry in Malaysia”, Proceedings of 2nd International Conferenceon Construction and Project Management, pp. 215-219, available at: www.ipedr.com/vol15/42-ICCPM2011A10021.pdf

Zhang, H.J., Chen, Y.Q. and Sun, H. (2015), “Emotional intelligence, conflict management styles, andinnovation performance”, International Journal of Conflict Management, Vol. 26 No. 4,pp. 450-478, doi: 10.1108/IJCMA-06-2014-0039.

Further reading

Al-Sibaie, E.Z., Alashwal, A.M., Abdul-Rahman, H. and Zolkafli, U.K. (2014), “Determining therelationship between conflict factors and performance of international construction projects”,Engineering, Construction and Architectural Management, Vol. 21 No. 4, pp. 369-382,doi: 10.1108/ECAM-03-2014-0034.

Iorio, J. and Taylor, J.E. (2014), “Boundary object efficacy: the mediating role of boundary objects ontask conflict in global virtual project networks”, International Journal of Project Management,Vol. 32 No. 1, pp 7-17, available at: https://doi.org/10.1016/j.ijproman.2013.04.00

Leung, M., Liu, A.M.M. and Ng, S.T. (2005), “Is there a relationship between construction conflicts andparticipants’ satisfaction?”, Engineering, Construction and Architectural Management, Vol. 12No. 2, pp. 149-167, doi: 10.1108/09699980510584494.

Ochieng, E.G. and Price, A.D. (2009), “Framework for managing multicultural project teams”,Engineering, Construction and Architectural Management, Vol. 16 No. 6, pp. 527-543,doi: 10.1108/09699980911002557.

Corresponding authorRebecca Jing Yang can be contacted at: [email protected]

For instructions on how to order reprints of this article, please visit our website:www.emeraldgrouppublishing.com/licensing/reprints.htmOr contact us for further details: [email protected]

201

Sri Lankancommercial

building sector

Page 72: Engineering, Construction and Architectural

An analysis of the deliverychallenges influencing

public-private partnership inhousing projectsThe case of Tanzania

Neema KavisheSchool of Architecture, Construction Economics and Management (SACEM),

Ardhi University, Dar es Salaam, TanzaniaIan Jefferson

School of Civil Engineering, University of Birmingham,Birmingham, UK, andNicholas Chileshe

Natural and Built Environments Research Centre (NBERC),School of Natural and Built Environments, University of South Australia,

Adelaide, Australia

AbstractPurpose – The purpose of this paper is twofold: first, to identify and rank the challenges influencing thedelivery of the housing public-private partnership (HPPP) in Tanzania; and second, to suggest solutions in theform of a conceptual public-private partnership (PPP) framework model that will address the identifiedchallenges and boost the chances of success.Design/methodology/approach – Using a convergent parallel (concurrent) mixed method approach, datawere collected from 28 stakeholders involved with HPPP projects in Tanzania using a hand-delivered ande-mail survey and 13 semi-structured interviews with public and private sector respondents. The quantitativedata included subjecting the 19 challenges as identified from the literature to parametric tests such asone-sample t-tests and descriptive statistics tests such as measures of central tendencies and frequencyanalysis through Statistical Package for Social Sciences (SPSS 22.0). Qualitative data employed contentanalysis. The research was further underpinned by a number of theoretical perspectives such as Gidden’sstructuration theory, contingency theory, relational and equity theory.Findings – The top five ranked challenges influencing the delivery of HPPP were “inadequate PPP skills andknowledge”; “poor contracting and tendering documents”; “inadequate project management”; “inadequatelegal framework”; and “misinformation on financial capacity of private partners”. The least six ranked andmost significant challenges based on the one-sample (single) t-tests were as follows: “Poor risk allocation”;“inexperienced private partner”; “unequal qualification and contributions of expertise”; “poor enablingenvironment to attract competent partners”; “inadequate mechanisms for recovery of private investors’capital”; and “high costs in procuring PPP projects”. The qualitative study further confirmed the challengesand cited the reason for the failure of joint venture projects as the lack of motivation for undertaking similarPPP projects. Despite the increased awareness of PPP projects and associated marginal benefits, the mainimpediment to the uptake and delivery of PPP housing projects remained the lack of skills and expertise.Research limitations/implications – The proposed framework model is not yet tested, but since this paperis part of the ongoing research, the next stage involves the testing and validation of the model. Future studiescould test the applicability of the proposed framework in other HPPP projects in Tanzania, and in other similardeveloping countries. Second, the validated framework can contribute towards addressing similar challenges aswell as providing guidance. The proposed framework model is not yet tested, but since this paper is part of theongoing research, the next stage involves the testing and validation of the model. Furthermore, recommendationfor future research is to test the alignment of the identified challenges to the proposed remedial solutions acrossthe five phases within the proposed PPP framework with a number of case studies.Practical implications – The identified challenges were used to form the basis of the framework presentedin this paper. Furthermore, these provide useful information, thus leading to increased awareness to enable

Engineering, Construction andArchitectural ManagementVol. 25 No. 2, 2018pp. 202-240© Emerald Publishing Limited0969-9988DOI 10.1108/ECAM-12-2016-0261

Received 17 December 2016Revised 19 February 2017Accepted 2 May 2017

The current issue and full text archive of this journal is available on Emerald Insight at:www.emeraldinsight.com/0969-9988.htm

202

ECAM25,2

Quarto trim size: 174mm x 240mm

Page 73: Engineering, Construction and Architectural

successful delivery of HPPP in Tanzania. Similarly, both the government and policy makers could use thefindings as the basis for re-examining the existing PPP policy and regulations, and reflecting on the existingsituation with a view to improving the delivery of future HPPP projects.Originality/value – The empirical study is among the first that identifies and ranks the challenges of PPPfor housing projects delivery within the Tanzanian context. The identification of the challenges enabled theirranking, resulting in the mapping out of the most critical challenges. Furthermore, using the Gidden’sstructuration theory, the study illustrates how institution mechanisms (structures) address these deliverychallenges, thus influencing the implementation of HPPP in Tanzania, and how individual stakeholders(human agents or agency) are able to make choices (advocated solutions) in dealing with the challenges.More so, these constraints (challenges) as identified and viewed through the contingency and equitytheoretical lenses form the foundation for developing the PPP conceptual framework. The proposedframework would thus serve as a mechanism for providing practical solutions as well as reducing the level ofseverity of the identified challenges.Keywords Project management, Questionnaire survey, International practicePaper type Research paper

1. IntroductionMany African countries, such as Tanzania, continue to lack suitable policies for housingdevelopment, and this has largely contributed to the growth of informal and poor housingconditions. Since independence in 1961, Tanzania like many African countries, for example,has experienced a large increase in population from 12.3 million in 1967 to almost 45 milliontoday. Coupled to this is a raise in the urban population from 5.7 per cent in 1967 to29.1 per cent in 2012. The overall trend in population growth averaged nearly 3 per centannually, while urbanisation grew by 5 per cent annually (Smith, 2015). The result isthat the available social facilities and services have been significantly strained. This is anAfrican-wide problem with most of the cities in Africa finding themselves needing toaccommodate an extra 40,000 to 50,000 people every day because of this rapid populationgrowth (UN-HABITAT, 2011).

Such rapid growth in population and urbanisation has contributed towards inadequatehousing for a number of decades. Across Africa, there is a severe housing deficiency, forexample, in Tanzania, this is currently projected at three million houses while the rate isgrowing at a rate of 200,000 houses per annum (National Housing Corporation (NHC), 2010).The situation has been worsening in urban regions of Tanzania, where the data show thaturban population had grown from 14.8 per cent in 1980 to 37.5 per cent in 2005 and furtherrise to 46.8 per cent is expected by 2015 (NHC, 2010). Coupled to which is the supply ofhousing in countries, such as Tanzania, has failed to keep up with investment in both thepublic and private sector services falling rapidly behind (World Bank, 1992). Because of thiswidening gap, the Tanzanian Government has had to seek alternative ways to address thisissue, such as the public-private partnership (PPP) strategy, to relieve the existing situation(Kidata, 2013; NHC, 2010). The adoption of these PPPs has more recently been consideredthe next best alternative to deliver public services such as housing (Sengupta, 2006;Moskalyk, 2011). However, despite the adoption of PPP in-house delivery, the prevailingproblems remain unresolved. For instance, more high-cost houses have been built butattracting the required private partners has remained problematic in developing countries(Sharma, 2012). Furthermore, according to Ngowi (2006), PPP application in countries, suchas Tanzania, is a new phenomenon, and still in its infancy.

In spite of numerous studies on PPP, the majority of them have identified the challengeshindering the growth and success of PPP across various sectors. In both developing anddeveloped countries, empirical studies on the challenges affecting the delivery of housingPPP projects, as well as the development of conceptual frameworks, are very limited.Furthermore, according to Tang et al. (2010), the majority of these empirical studies on PPPin construction have largely centred on three themes: risks; relationships; and financing.However, some of the Tanzanian-specific studies, for example, have investigated

203

PPP in housingprojects

Page 74: Engineering, Construction and Architectural

institutional arrangements and constraints within the solid waste management (Nkya, 2004)and PPP challenges in Tanzanian municipalities (Ngowi, 2006), providing some insights intoAfrican-centric issues. Mboya’s (2013) study, although covered implementation roles andlegal issues as well as PPP framework road map, was more on a country level and based onnon-empirical data. The only exception in identifying the challenges to the delivery ofhousing PPP projects is the Kavishe and An (2016) study. However, this study did not offerdetailed solutions or a conceptual framework. The above suggests that in spite of theserather limited Tanzanian PPP studies, they are mostly policy related and not based onempirical data (i.e. Mboya, 2013; URT, 2009), and include non-construction and housingstudies with emphasis on local authorities (Ngowi, 2006) and solid waste management(Nkya, 2004). This highlights the need for construction and housing-specific empiricalstudies on a number of areas affecting PPPs. More recently, Akintoye and Kumaraswamy(2016) renewed the calls for more research on PPP. The need for the Tanzaniancontext-specific PPP studies is nested in the different prevailing regulatory and frameworkconditions. As observed by Tang et al. (2010), and more recently, the World Bank (2016)report, the implementation issues (including challenges) and emergent benefits should takestock of the internal and external conditions in the host country by PPP partners. It is alsoacknowledged that the implementations of PPPs in Tanzania are still in the infancy stageand a new phenomenon. Furthermore, in contrast to other African countries, such asNigeria and South Africa, Tanzania continues to lag behind neighbouring countries in termsof improving its business environment (World Bank, 2016, p. 30).

Similarly, some selected recent studies in developing countries have been both housingand non-housing specific. For example, Hashim et al. (2016) investigated the delivery offacilities management in Malaysia. In Nigeria, Babatunde et al. (2012) focused on the criticalsuccess factors (CSFs) in PPP in infrastructure delivery. In Ghana, Kwofie et al. (2016)studied a critical success model for housing public-private partnership (HPPP) delivery.Within the developed countries context, recent studies, such as Akintoye andKumaraswamy (2016), have highlighted equally a number of significant challenges forPPP and directions for future research. It is therefore evident that, despite the proliferationof PPP-related studies, there are limited empirical studies undertaken within the manyAfrican countries and their housing projects. The identified challenges call for the need toaddress them, and this provided a basis and drive for developing an HPPP frameworkmodel. Therefore, there is a need to explore the specific challenges affecting the delivery ofPPP in housing projects within the African context. In order to respond to the researchagenda and knowledge gaps identified by Akintoye and Kumaraswamy (2016), the mainobjective of this study is to identify the challenges affecting the delivery of the HPPP usingTanzania as its focus, to provide a conceptualising HPPP framework model that will guideHPPP affordable housing projects in Tanzania. This will ultimately provide a framework forother developing countries, particularly those in Africa, that have similar socio-economicand political characteristics.

1.1 Conceptualisation and theoretical basis: Gidden’s structuration theoryIn formulating the above objectives, the underlying theoretical basis is premised on thefollowing two issues of “Agency” and “Structure”, as postulated by Giddens (1984)structuration theory. According to Giddens (1984 cited in Chileshe et al., 2013, p. 164),structure refers to the rules for acting, thinking, and feeling that are general throughout asociety or an organisation, and the available materials and non-material resources that areneeded for an action to take place. HPPP projects in Tanzania are structured as jointventures ( JVs). Drawing upon the definition as provided, within the context of this study,the “structure” refers to the rules that permeate through the Tanzanian private and publicorganisations with the responsibility for the delivery of HPPP, and the consideration of

204

ECAM25,2

Page 75: Engineering, Construction and Architectural

the resources that these organisations might have or not have (hence the need for PPP)would be required for “action” or implementation of PPP to take place. Therefore, withinthe context of our present study, these “structures” refer to the “PPP policy, guidelines,legal framework and procurement regulations” which act as a set of rules, with power tomanage and informing over the actions of the members of a society or organisation(i.e. PPP coordinating units, Tanzanian public and private organisations/ stakeholders).In contrast, Baker (2005 cited in Chileshe et al., 2013, p. 164) defines the “Human agency”as the capacity for human beings to make choices and take action to implement thesechoices (i.e. whether to undertake PPP training or not). Therefore, considering the poorPPP performance and its underlying challenges in Tanzania (World Bank, 2016), it isimportant to pay attention to both the human agency and PPP structures, as they areinseparable and their interactions are significant (Giddens, 1984). Studies, such asAgyenim-Boateng et al. (2017), have applied Giddens structuration theory in examiningthe accounting and governance of PPPs.

2. Literature review2.1 Various forms of PPP procurement arrangementsAccording to Li et al. (2005), eight types of PPPs have been acknowledged by the UKGovernment including JVs, policy partnerships, partnership investment, private financeinitiative, sales of business, wider market, asset sales and partnership companies. However,in Tanzania, JVs have been the dominant type/form of PPP in their housing projects.Likewise, both developing and developed countries, such as Nigeria, Yemen, Philippines,India, Ghana, the Netherlands, UK and Ireland, have also adopted the JVs in deliveringhousing projects (Ibem, 2011a; Al Shareem et al., 2014; Sengupta, 2006).

Seminal studies, such as Stevenson et al. (1994), have defined JVs as an association oftwo or more persons who contractually agreed to contribute to a specific venture,which is usually limited to a specific task or period of time. Undertaking this type ofprocurement arrangement by the Tanzanian stakeholders further highlights the need ofidentifying the challenges associated with the implementation of PPP based on the equitytheory in order to model the appropriate solutions to these challenges. For example,Adams (1965 cited in Zhang and Jia, 2010) and Scheer et al. (2003) defined equity theory asfor where a partner will assess its own inputs and a return against the other partner’sinput and return in an existing relationship. For a detailed discourse on the various PPPmeanings, forms and models within the western literature, please see Mouraviev andKakabadse (2012).

2.2 PPP housing in TanzaniaHPPP is still in its early stages in Tanzania primarily because of a lack of direct experienceand inadequate new investment in housing projects. To date, two public organisations,namely the National Housing Corporation (NHC) and the National Social Security Fund(NSSF), have used the PPP method for housing provision. Since the 1990s, NHC used thePPP approach in building development, but most of these partnership projects were notvery successful. This was primarily due to the lack of an adequate PPP legal framework toguide the implementation of such projects, which delayed its progression (URT, 2009).Despite recent developments undertaken by the Tanzanian Government in enhancing theregulatory frameworks via PPP regulations in 2011 and the Public Procurement Act 2011,there still remain a number of challenges such as the relative infancy of rather complex PPPand lack of experience across the stakeholder chain (Mboya, 2013).

The NHC is the oldest and largest real estate developer in the country, owning manybuildings in various conditions. The redevelopment or rehabilitation of such buildingsrequired substantial funds, which NHC itself could not afford. Therefore, the Corporation

205

PPP in housingprojects

Page 76: Engineering, Construction and Architectural

had to consider PPP strategy. The NSSF is a public organisation, which provides socialsecurity/pension funds to Tanzanians. However, it recently started to undertake HPPPprojects in 2013.

2.2.1 Financing of PPP housing projects in Tanzania. In a recent review-related studyundertaken by Chileshe (2016), inadequate funding and revenue problems were among thechallenges identified as inhibiting the managing of infrastructure in Africa. While PPPs wereamong the advocated solutions to these problems, in Tanzania, like in many other developingcountries, real estate development financing is usually problematic, since there are no mortgagebanks to facilitate effective financing. A few banks, such as Azania Bank and CommercialBank of Africa, started offering housing loans but mainly to small-scale developers. Such fundsare not adequate to enable the NHC to execute its large projects. Moreover, the interest ratescharged by these banks are high, ranging between 20 and 25 per cent, and loan repaymentterms are generally short and the near absence of mortgage financing also limited the propertydevelopers or investors who depend on equity financing. NHC was, therefore, forced to dependmainly on equity to finance its projects. Equity funds are normally derived from the existingprojects, particularly houses for sale and rental revenue. However, the latter source of funds isinadequate since tenants frequently do not pay rent in time. Equally, house buyers were havingtrouble with agreed schedules of payments.

According to Kavishe (2010) and Kavishe and An (2016), NHC Joint Venture Policy hadloopholes and flaws that led to the failure of some of these projects. Similarly, in their veryearly projects, the selection of their partner was in the manner of “first come first served”.There was no room for competition, which would have assisted the Corporation to securemore potential investors. Figure 1 describes the 1995-2010 NHC procurement frameworkmodels, which illustrate the procurement selection process of partners and projects.

The NHC PPP process was non-competitive, and it depended on the ability of the privatepartner to submit a quick proposal. Other factors such as skills and capacity, experience,viability of the project and integrity to mention a few were not considered. In addition,the absence of any financial assessment of private partners highlighted the lack of integritydue to the limited scrutiny of the process. As a result, a number of investors were facingfinancial difficulties a few months after the start of the project, which led to delays, poorperformance and unsuccessful delivery of projects.

On the government side, there have been serious efforts to improve and promote privatesector participation in PPP projects. This culminated in first a PPP Policy, then a PPP Act in2010 and finally, in 2011, PPP regulations being approved. In order to coordinate andoversee the mainland Tanzanian PPP projects and PPP Financing Unit within the Ministryof Finance, a PPP Coordination Unit was established with the duty of assessing andexamining all PPP proposals in their financial aspects. This body was formed as a result ofthe 2010 PPP Act within the Tanzania Investment Centre. Despite the establishment of theseunits, no HPPP projects actually were submitted to them for assessment and approval.Having suitable PPP strategies, policies and regulatory framework is one thing, but makingthem effective and efficient is entirely another.

2.3 PPP housing in other countriesBoth the public and private sectors are adopting partnerships for the delivery of housingand urban development worldwide (Moskalyk, 2011). Developed countries, such as the UK,Canada, the USA, Australia, and some developing countries, such as India, Nigeria,South Africa and Malaysia, have employed PPP projects in delivering affordable houses(Moskalyk, 2011; Abdullahi and Aziz 2011; Liu et al. 2014; Chan et al., 2004) although notalways successfully. For example, Trangkanont and Charoenngam, 2014a explained,“A number of developing countries such as Thailand, Vietnam, the Philippines, Malaysia

206

ECAM25,2

Page 77: Engineering, Construction and Architectural

and Indonesia have experienced failures in their PPP Low-Cost Housing (PLCH) projects dueto different factors”. Trangkanont and Charoenngam identified ten factors of PLCH inThailand which led to failure: inadequate tender documents, inefficient managementchange, poor contractors, political intervention, ineffective PPP policy and strategy,weakened institutional culture, policy pressure, and difficulties to low-income group,economic problems and housing finance constraints. Similarly, a number of other studiesidentified different challenges in PPP projects, as listed in Table I.

Furthermore, the study undertaken by Moskalyk (2011) noted that rich countries haveonly been successful in delivering affordable housing due to the high level of governmentsubsidies that lower housing cost. Moskalyk’s study further added that these subsidies werea “luxury” that could not be afforded in the developing world. The researcher criticised this

Seek building permit

Ministry of lands

Board to oversee policy and operations

NHC director general (oversee day-to-day activity)

Director of propertydevelopment

Director propertymanagement

Director finance andadministration

Constructionresearch and planning

Operation AccountsValuation andallocation

Storesupplies

Personnel andadministration

Joint venture/PPPprojects

Advertising/calling for private partnersto choose plots from the advertised list

Partners submit request letters forredeveloping the selected plot

Partners prepare preliminaryproposals

Technical committee of the boardassess and evaluate the proposals

Proposals approved by NHCboard of directors

Partner to sign in2-3 weeks

Legal units preparecontracts

Drawings checkedand approved

Partner prepares workingdrawings in 1 year

Project executionTeam of coordinatorsselected to manage

the PPP project

6 Months forex-tenants to vacate

Source: Authors’ interpretation

Figure 1.NHC PPP

procurementframework adopted

between1995 and 2010

207

PPP in housingprojects

Page 78: Engineering, Construction and Architectural

References

No.

Challeng

es1

23

45

67

89

1011

1213

1415

1617

1819

20No.

Fa(%

)

1Differinggoalsbetw

eenpartners

|1

52

Corrup

tion

||

||

|5

253

Misinform

ationon

financial

capacity

ofprivatepartners

||

|3

154

Poor

PPPcontract

andtend

erdocuments

||

||

420

5Delays

||

||

|5

256

Inadequate

PPPlegalframew

orkandgu

idelines

||

||

||

|7

357

Inadequate

PPPskillsandkn

owledg

e|

||

||

||

737

8La

ckof

competition

||

|3

159

Inadequate

feasibility

stud

y|

15

10Inadequate

projectmanagem

entby

thepu

blicsector

||

||

420

11Lo

ngterm

disputes

andconflicts

betw

eenparties

||

||

420

12Inadequate

governmentcommitm

entandsupp

ort

||

210

13Insufficient

capacity

inprocurem

entandnegotia

tions

||

|3

1514

Poor

risk

identification,

allocatio

nandmanagem

ent

||

||

420

15In

experiencedprivatepartner

||

210

16Unequ

alqu

alificatio

nsandcontribu

tions

ofexpertise

||

210

17Po

orenablin

genvironm

entto

attractcompetent

partners

||

||

|5

2518

Inadequate

mechanism

sforrecovery

ofprivateinvestors’capital

|1

519

Highcost

inprocuringPP

Pprojects

||

||

||

632

20Highenduser

charges

||

210

21La

ckof

transparency

||

210

22Highcost

ofbu

ildingmaterialsandconstructio

nequipm

ent

||

210

23Po

orinfrastructure

services

|1

524

Publicacceptability

|1

525

Lack

ofun

iform

policyin

PPPhousingprovision

|1

526

Lack

ofcoordinatin

gagency

inPP

Phousing

|1

527

Poor

access

todevelopableland

|1

528

Highbu

ildingstandards

|1

53

32

126

31

310

21

73

101

42

14

1Notes

:1.Moskalyk(2011);2.Ibem

andAdu

wo(2012)

;3.S

engu

pta,(2006);4.N

gowi(2006);5.Trang

kanont

andCh

aroenn

gam

(2014a);6.Ismaila

ndHaris(2014);7.

Abd

ull-A

zizandKassim(2011);8.Zhang

(2005a);9.Zh

ang(2005b);10.K

wofieetal.(2016);11.E

l-Goharyetal.(2006);12.Ibem(2011a);13.Ibem(2011b);14.Chediel(2012);

15.(Ch

ouandLin,2012);16.A

kintoyeetal.(2003);l7.(Ch

anetal.,2006,2009);18.Abd

ul-Aziz(2001);19.Li

etal.(2005);20.K

PMG(2010).T

hechalleng

esnu

mbered20

throug

h28

werespecificto

thesuccessful

implem

entatio

nof

PPPin

affordablehousingschemes.aWhere

“F”isthefrequencyof

thechalleng

esin

percentage

ascitedin

thestud

iesreview

ed

Table I.Summary of selectedliterature onchallenges affectingthe delivery of PPPhousing projects

208

ECAM25,2

Page 79: Engineering, Construction and Architectural

argument on the basis that subsidies can be a luxury to any government where there havebeen no previous plans and strategies for their inclusion during budget preparation.Subsidies, provided they are treated as priorities and carefully planned by whichevergovernment of the day, can be affordable. Hence, it is necessary to have strategic plans andthe correct policies in place in order to successfully deliver affordable housing.

2.3.1 PPP housing in selected developing countries. 2.3.1.1 Malaysian experience.Malaysia has benefited greatly from the use of PPP arrangements in delivering affordablehouses. The secret behind its success is the provision of favourable housing policies. One ofthe major concerns of Malaysian housing policy was making sure the low-income group hadguaranteed access to housing. The study by Abdullahi and Aziz (2011) stated that the thirdMalaysian plan 1976-1980 indicated better performance within the private sector than in thepublic sector and thus provided a larger portion of low-cost housing. The “cross-subsidypolicy” was a key feature of the housing policy, where the rich subsidised the poor. Thismeant that any housing development project had to follow the regulation of developing atleast 30 per cent of the houses as low-cost housing and the rest can be for the high- andthe medium-income group. Also, it made an effort to remove the financial barriers forlow-income families through government loans and regulations that required the financialinstitutions to increase their loan facilities as much as 100 per cent to those with low incomes(Abdullahi and Aziz, 2011). The Malaysian Government made sure that the allocation of thelow-cost houses was open and applied through an open registration system. This eliminatedmuch corruption, cheating and inequality as a fair system was adopted. From the Malaysianexperience, it is clear that detailed groundwork, strong policies and clear objectives need toexist before the adoption of the strategy.

2.3.1.2 Indian experience. Another study conducted by Sengupta (2006) highlighted anumber of constraints to PPP housing projects in Kolkata that include: “poor access tofinance by low income families”, “out dated legislation”, “high levels of municipal taxes”,“stamp duties” and “sanction fees”. But despite these challenges, Kolkata has beensuccessful in adopting PPP in housing in terms of cost and quality because its governmentfocused on appropriate regulations rather than rapid changes.

2.3.1.3 Nigerian experience. According to a study by Ibem (2011a, b), PPP is still a newapproach to housing provision in Nigeria and the main reason for adopting PPP is toaddress the increasing housing challenges. The HPPP in Southern Nigeria took a JVapproach like in Tanzania. Ibem (2011a, b) obtained data through interview surveys fromgovernment housing agencies in six cities and identified that PPP had not made anysubstantial impact on housing the low-income group. Instead, more houses were built for thehigh- and middle-income earners. The lack of uniform National Policy was acknowledged asthe main challenge. Likewise, a similar study by Ukoje and Kanu (2014) identified that a PPPmass housing scheme in Abuja, Nigeria was undertaken in the absence of adequateplanning and implementation and the partners appeared to lack the capability. It wasdifficult for this project to achieve the aim of delivering affordable housing. Therefore, Ukojeand Kanu (2014) study concluded that to improve HPPP in Nigeria, “capacity building forthe partners”, “positive quality enabling environment”, “stricter control” and “government’ssupport for the sake of the low-income earners” were necessary.

2.3.2 CSFs for delivery of PPP housing projects. A review of the literature has identified anumber of studies, which reported on CSFs in the developing countries (Babatunde et al.,2012; Ismail, 2013; Kwofie et al., 2016; Dairu and Muhammad, 2015). These studies identifiedthe following success factors: good governance; appropriate risk allocation and risk sharing;availability of financial markets; defensive policy against political risks; political stability;strong private consortium; favourable legal framework; government support participationin providing vital guarantees; and genuine commitment of collaborating parties.

209

PPP in housingprojects

Page 80: Engineering, Construction and Architectural

Recent studies, such as Osei-Kyei and Chan (2015), have produced an equallycomprehensive list of CSFs for PPPs.

2.3.3 Summary of literature review. In addition to the summarised studies in Table I, areview of a number of related literature was undertaken. This was mostly in the areasaround the key principles and success factors. Examination of interviews shows that themajority of reviewed studies were from both developing and developed countries andfocussed on inadequacies around PPP skills and knowledge (40 per cent, n¼ 8); inadequatePPP legal frameworks and guidelines (35 per cent, n¼ 7) and high cost in procuring PPPprojects (35 per cent, n¼ 7). These observations are consistent with the recent studies byAkintoye and Kumaraswamy (2016) which highlighted significant challenges facing PPP.Interestingly, the least flagged challenges based on the frequencies have equally beenidentified as areas requiring further research and development agendas by Akintoye andKumaraswamy (2016), for example, risk management (20 per cent) and inadequatefeasibility study (10 per cent) within the themes of “Risk allocation and management” and“PPP project evaluation”. Other challenges have been associated with the delivery ofaffordable PPP housing and these items are numbered as 20 through 28 within Table I.The main challenges, although limited in the number of studies, were associated with highbuilding standards, land affordability, lack of transparency, poor access to land and publicacceptability amongst others.

It is worth noting that some of the developing countries studies, which have includedexamples from the African perspective, have used stringent selection criteria for theirinclusion. For example, the study by Sharma (2012) only had Nigeria and South Africa as theAfrican countries based on having at least one PPP project in two successive years.The review of the literature thus identified the need for undertaking empirical studies onchallenges affecting the PPP particularly within the Tanzanian context, as well as formulationof conceptual frameworks. There is also scope for the application of the measures or solutionsfor dealing with these challenges as identified from other developing and developed countrieswithin the context of the Tanzanian construction industry.

3. Research methodsAs the main objective was to obtain different but complementary data to answer a singleresearch question, a convergent parallel (concurrent) mixed method approach was adopted.From the level of interaction perspective, the data were collected and analysedindependently. As opined by Molina-Azorin et al. (2007), both the quantitative andqualitative approaches had equal priority status. Simply put, different methods are used toassess the same phenomenon towards convergence and increased validity (Cameron, 2009).This method is similar to that of Nguyen and Chileshe (2015) and Kurniawan et al. (2014)and included the following six steps: literature review (see Table I); pilot survey;questionnaire survey; interviews; statistical analysis; and content analysis. Drawing uponthe study by Nguyen and Chileshe (2015), the justification for adopting the mixed methodsapproach is well established in literature, and furthermore, this provides the opportunity forincreasing the reliability of the research (Easterbrook et al., 2008). It has also been known tooffset the weakness of each tool considering the sample nature, time and accuracy of data(Kothari, 2004). More so, as highlighted by Jogulu and Pansiri (2011, p. 690), in concurrentmixed methods, qualitative and quantitative data collection techniques are undertaken atthe same time for the analysis of the data. In our study, as recommended by Holt andGoulding (2014), both approaches, qualitative (semi-structured interviews) and quantitative(questionnaire survey), were applied concurrently with equal status. Finally, this concurrentapproach enabled the usage of the results of one method to corroborate the findings of theother about a single phenomenon (Halcomb and Hickman, 2015).

210

ECAM25,2

Page 81: Engineering, Construction and Architectural

The specific objectives of the study are to:

(1) identify and rank the challenges influencing the delivery of the HPPP in Tanzania; and

(2) suggest advocated solutions in the form of a conceptual PPP framework model thatwill address the identified challenges and hence boost its success.

3.1 Measurement instrumentThe questionnaire as administered in the Tanzanian construction industry was comprisedof the following three distinct sections:

• Section 1 encompassed general demographics of the study sample and included anumber of control variables (i.e. working experience, designation, professionalbackground, and experience within PPP housing projects).

• Section 2 captured opinions on a range of issues affecting affordable housing projects.

• Section 3 comprised five sub-sections in order to capture the respondent’s perceptionon the following issues: (i) assessment of skills and training needs for PPP projectdelivery; (ii) factors hindering the acquisition of the PPP skills and training; (iii)evaluation of costs and affordability; (iv) aspects of PPP policy and regulatoryframework; and (v) challenges in implementing PPP projects. For Sub-sections (i)-(v),the respondents were asked to rate their levels of agreement using a five-pointLikert scale where 1¼ strongly disagree, 2¼ disagree, 3¼ neutral, 4¼ agree and5¼ strongly agree.

Sub-section (v) of Section 3 included 19 challenges drawn from the summarised studies(Table I). The majority of the items were mostly from the following countries and studies: inMalaysia, Abdullahi and Aziz (2011); China, Liu et al. (2014); Hong Kong; Chan et al. (2004);and Thailand, Trangkanont and Charoenngam (2014a). The rationale for following priorresearch in the identification of the measures (i.e. challenges) was to ensure constructvalidity. Such an approach has been used in PPPs studies such as De Schepper et al. (2015).Therefore, the detailed results presented in this paper relate to Sections 1 and 3 of thequestionnaire, particularly sub-section (v) on the challenges. It is beyond the scope of thispaper to report on Section 2 and part of the remaining sub-sections.

3.2 Survey administrationIn order to obtain the relevant information needed, the approach engaged purposivelysampling amongst the targeted population, namely the stakeholders involved in PPP housingprojects in Dar es Salaam, Tanzania were used. The rationale for choosing Dar es Salaam as thestudy area includes: accessibility to conduct a survey to obtain required data and the fact thatabout 60 per cent of HPPP projects, PPP experts, construction professionals and head officesare located in Dar es Salaam (Kavishe, 2010). Therefore, the target population includes publicsector authorities (i.e. ministry, department, and housing agencies), private partners and theproject consultants involved in HPPP projects in Dar es Salaam. Unfortunately, there is noofficial list or standard database specifying the number of stakeholders’ organisations involvedin HPPP projects within the study area. In view of this, the target population involved in thisstudy cannot be easily determined. Based on this, the researcher identified the targetpopulation through public agencies involved in HPPP projects and PPP experts. It is on thisnote that only two public organisations, including their list of projects (NHC 187 projects andNSSF 1 project), 60 per cent being based in the study area, with their private partners andconsultants were identified. Although the population size is small (n¼ 28), the selected sampleis typical of the whole and allowed intensive study (Kothari, 2004). According to Kavishe (2010),

211

PPP in housingprojects

Page 82: Engineering, Construction and Architectural

these 187 PPP projects as administered by the NHC and carried out in partnership with privatereal estate developers or investors were at different implementation stages (i.e. initial andcompletion stages). For example, the majority 100 (53.47 per cent) were still under preparation,48 (25.66 per cent) under construction, 29 (15.50 per cent) completed and a minority, 10(5.37 per cent) had stalled. It could thus be argued that, despite the small sample size, with60 per cent (n¼ 112) of the projects located in the study area, namely Dar es Salaam and40 per cent in other regions, the study typified the whole population with particular emphasison the projects under preparation, construction and completed. The characteristics of therespondents according to the designation, professional background, length of experience andthe number of PPP projects undertaken are summarised in Table II.

Based on the reported demographic background of the respondents (see Table II), it canthus be demonstrated that all key actors in PPP housing projects as well as varyingmanagement levels were involved in the survey thus enhance the reliability and validity ofthe findings.

3.3 Statistical methods – analysis of resultsQuantitative data were analysed using the Statistical Package for Social Sciences (SPSS)computer programme version 22.0. The SPSS procedure involved in the analysis of thequantitative data comprised of the following two methods or techniques: parametric tests

Characteristics Number ( frequency) Overall (%)

DesignationConsultant 9 32.15Private developer 2 7.14Public partner 11 39.29Contractor 1 3.57Financer 1 3.57Researcher (Academic)a 2 7.14PPP advisora 2 7.14

Professional backgroundQuantity surveyor 5 17.86Engineer 4 14.29Land valuation agenta 3 10.71Architect 3 10.71Lawyer 1 3.57Other professional rolesb 12 42.86

Length of service in current position (years)Less than 5 8 28.575-10 7 25.0011-15 8 28.57More than 15 5 17.86

Experience with PPP housing projects (number of projects)o than 1 4 14.291-2 7 25.003-5 4 14.296-10 6 21.42Over 10 7 25.00Notes: The land valuation agent is also known as the “land valour”. aThese designations (researcher and PPPadvisor) were specified by the respondents as they were not part of the options given within the surveyquestionnaire; bthe breakdown of the “other” professional roles were as follows: managers (two), staff (three),consultant (two), sales supervisor, assistant director, principal consultant, advisor, and director

Table II.Profile ofstudy sample

212

ECAM25,2

Page 83: Engineering, Construction and Architectural

such as one-sample t-tests; and descriptive statistics tests such as measures of centraltendencies and frequency analysis (Forza, 2002). The ranking analysis based on the“frequencies” analysis was further undertaken using the generated values from the centraltendencies such as the standard deviation and mean scores. In addition to the SPSSgenerated values, the third technique of “relative agreement index (RAI)” was computed.The following sub-sections present a brief discussion of each approach.

3.3.1 Ranking analysis and RAI. The ranking of challenges influencing the delivery ofPPP in Tanzanian housing projects was based on the mean score. Drawing on the approachby Ibrahim et al. (2006) in Nigerian PPP infrastructure projects, this involved attributing thelower value as assigned to the challenge as an indication of its lower importance.The standard deviation as generated by the descriptive statistics provided the variabilitythat exists in the information for ease of comprehending the information (Forza, 2002,p. 182). Other PPP-related studies that have previously employed this approach of the meanscore ranking technique and RAI include Hwang et al. (2013) in Singapore and Ismail andHaris (2014) in Malaysia. Similarly, in order to summarise the advancement of the identifiedchallenges, the RAI as derived has to overcome the weaknesses associated with thecomputed mean score (Holt, 2014; Doloi et al., 2012).

3.3.2 Single-sample t-test of the mean. A one (single) sample t-test of the mean wasundertaken to measure the significance of the challenges influencing the delivery of theHPPP. Drawing upon the findings of Ling and Nguyen (2013), the cut-off point for five-pointscale was set at “3.5” (μ¼ 3.5) and the hypothesis was introduced to measure the extent ofinfluence of HPPP delivery challenges. The study by Ling and Nguyen (2013) had aseven-point scale to measure the strategies for waste management practices, and providedjustification for its selection of “5” as the cut-off point for comparison. This study applies thesame logic. By inference, the value of “3” would be the middle point for the challengesinfluencing the delivery of HPPP. This would further be equivalent to 50 per cent ofimplementation. However, given the importance and lack of HPPP implementation withinthe Tanzania context, a value higher than 50 per cent of the delivery and implementationeffort is appropriate. To that end, the μ value is set at 3.5, and using the procedures asoutlined in Cronk (2012), the analysis for the single-sample t-test was conducted.The rationale and explanation of the null hypothesis thus are that the HPPP challengeaffects the delivery of the projects to a significant amount, whereas the alternativehypothesis is that HPPP challenge is not significant and less important.

3.4 InterviewsThe interview processes were conducted between July and August 2016. These took place inDar es Salaam, Tanzania. The duration of the semi-structured interviews was betweenapproximately 45 and 100 minutes and was undertaken and conducted following theprotocol suggested by Sharifirad (2011). Sharifirad’s procedure required the translation andreview of the transcripts as some of the (performed) interviews were conducted in one ofthe local languages, namely Kiswahili. Semi-structured interviews were the preferred modedue to their ability to produce detailed information, since they are flexible enough to explorequestions into areas that could provide new dimensions of issues not pre-conceived(Axinn and Pearce, 2006). In total, 13 semi-structured interviews were carried out with themanagement staff of the public and private sectors, while the questionnaire participantswere restricted to company staff involved in similar projects. The structure of the interviewquestions followed four distinct sections:

(1) background information (organisation and number of PPP projects);

(2) training and needs assessment;

213

PPP in housingprojects

Page 84: Engineering, Construction and Architectural

(3) challenges in implementing PPP housing projects; and

(4) challenges in the successful implementation of PPP in affordable housing schemes.

The questions were prepared following the guidance as suggested by Qu and Dumay (2011)and underpinned by Giddens structuration theory in understanding the structural issuesaffecting the implementation of PPP. In order to enhance the validity and reliability of thecollected interview data, the transcripts were e-mailed to the interviewees to obtain theiragreement on the correctness and their feedback. This approach is also known as“participation checks and validation” and has previously been utilised in the study byArdichvili et al. (2003) and Chileshe et al. (2016).

3.4.1 Selection criteria for interviewees. Due to the fact that PPPs were relatively a newphenomenon in Tanzania, as suggested by Maxwell (2005 cited in Liu and Wilkinson, 2011),a criterion-based approach was used in the selection of the interviewees. The selection forthe interviewees included the following criteria: the respondent’s willingness and priorinvolvement in HPPP projects and the respondents needed to be a public partner, or privatepartner or a financier, consultant or a contractor to the housing PPP projects. In light of onlytwo public sector departments undertaking the HPPP, the sample size is very small. In orderto compensate for the sample size of public sector interviewees, the invitations also extendedto the PPP unit, PPP coordinating unit and National Construction Council. This was deemedsuitable as these organisations also played an advisory role in all PPP projects.

3.4.2 Profile of the interviewees. Table III presents the profile of the interviewees. In all,13 interviews were undertaken. The number of interviewees (response rate) for thequalitative survey can be considered as very good in view of the total population and limitedresearch undertaken within the Tanzanian context to date.

As can be seen from Table III, the majority of the interviewees (38 per cent) fell within the“11-15 years” and “more than 15 years” categories, whereas two (15 per cent) were in the “sixto ten years” category. Table III further illustrates that, based on the sector, the majority(69 per cent) were from the public sector. The limited number of the public sector intervieweesis due to the fact that, in Tanzania, there are currently only two public organisationsundertaking PPP in housing projects. These organisations are the NHC and NSSF. However,due to confidentiality associated with their projects, in some cases detailed information couldnot be provided. Despite the potential of bias due to the majority of respondents being fromone sector, the findings from the questionnaire survey overcame this shortcoming byincluding the private sector respondents (see Table II). This was complemented by theliterature review to reinforce and validate the private sector’s views.

3.5 Characteristics of the sampleOut of the 38 questionnaires administered to the targeted population, 28 questionnaires wereconsidered valid. The response rate, which is equivalent to 78 per cent, was well above thesimilar studies in PPP survey-related research. Examination of Table II shows that the majority11(39.3 per cent) of the respondents were from the public sector. This was followed by nine(32.2 per cent) consultants. With regards to professional background, a fair proportionfive (17.9 per cent) was quantity surveyors. There was a fair distribution of varying professionsamongst the remainder of the survey respondents. For example, there was an equal number ofthe minority, one (3.6 per cent) being a lawyer, sales supervisor and assistant director.The inclusion of the Lawyer was particularly significant, given the different forms of HPPP andthe legal implications of the JV in Tanzania. The need for opinions from a knowledgeablerespondent (such as a lawyer) for checking the credentials of the other party during the selectionprocess within the JV process was therefore necessary. With regards to experience, the majorityof the respondents eight (28.6 per cent) fell within the “less than 5” and “11-15” years categories.

214

ECAM25,2

Page 85: Engineering, Construction and Architectural

4. Survey and interview results4.1 Reliability analysisThe reliability and internal consistency of the survey instrument, comprising the19 challenges affecting the delivery of PPP projects (see Table I), were tested by usingCronbach’s α coefficient to examine and asses the adequacy of the measurement instrument.Previous and recent PPP-related studies, such as Hashim et al. (2016), have used similarapproaches for the reliability analysis. Furthermore, according to Cronbach (1951), this(Cronbach’s α coefficient) is one of the most popular reliability statistics aimed atdetermining the internal consistency or average correlation of items in a survey instrumentto gauge reliability. Based on the results (not illustrated in this paper), the Cronbach’s α wasfound to be 0.585 (F-statistic ¼ 9.899, Sig. ¼ 0.000) for the challenges sub-instrument, thusindicating that the five-point scale measurement was reliable at the 5 per cent significancelevel as the value was greater than 0.5 (Tabish and Jha, 2011).

IntervieweeName oforganization

Currentposition

Experience(years) Sectorb

Professionalbackground

Experience withHPPP projects

(number of projects)

A NHCa Legal officer 6-10 Public partner Lawyer Over 10B NHCa Director of

propertyW15 Public partner Engineer Over 10

C NSSF Projectmanager

11-15 Public partner Engineer 1-2

D TBA Managingdirector

W15 Public partner Engineer 1-2

E PPP Unitc PPP Advisor 11-15 PPP Unit Economist NoneF NCCc Consultant W15 Public Sector Quantity

surveyorOver 10

G PPPCoordinatingUnitc,d

Assistantdirector

11-15 Investmentcentre

Economist None

H SalimCompany

Director W15 Public partner Architect 3-5

I Contractor Director 11-15 Contractor Engineer 1-2J NSSF PPP Clerk of

works6-10 Public partner Engineer 1-2

K NSSF Manager 11-15 Public partner Quantitysurveyor

1-2

L MaksoorCompany

Director W15 Public partner Business 3-5

M NHC Regionalmanager

None (o1year)

Public partner Landvaluationagent(valour)

Over 10

Notes: NHC, National Housing Corporation; NSSF, National Social Security Fund; NCC, National ConstructionCouncil; TBA, Tanzania Building Agency. aIn Tanzania, so far, NHC is leading housing agency which hascarried out a large number of joint venture projects for both commercial and residential properties since 1990s.bIn Tanzania, there are currently only three public organisations undertaking PPP in housing projects. Theseorganisations are the National Housing Corporation (NHC), National Social Security Fund (NSSF), andTanzanian Building Agency (TBA). cThese organisations (PPP Unit, NCC and PPP coordinating unit) areincluded as they are responsible for the assessment, approval as well as the coordination of all PPP projects inTanzania. They have also been involved in the formulation of PPP Policy as well as the regulations. dThe PPPCoordination Unit was established by the 2010 PPP Act within the Tanzania Investment Centre (TIC) tocoordinate and oversee the mainland Tanzanian PPP projects and PPP Financing Unit within the Ministry ofFinance with the duty of assessing and examining all PPP proposals in their financial aspects

Table III.Interviewee profile

215

PPP in housingprojects

Page 86: Engineering, Construction and Architectural

The Cronbach’s α coefficient for the challenges sub-instrument was less than the requiredthreshold of 0.7, thus indicating low reliability of scales (Nunnally, 1978), although Nunnallyhas pointed out that lower thresholds are sometimes used in the literature. Furthermore,investigation of the item-total statistics revealed that only the deletion of the two ranked items,namely “inadequate PPP skills and knowledge leading to poor planning and application” and“poor PPP contract and tender documents”, would improve the reliability to 0.586 and 0.592,respectively. However, due to negligible impact on the Cronbach’s α values and theimportance attached to “project management and legal issues in PPP delivery”, these twoitems were not deleted, but included in the overall survey instrument.

4.2 Engagement of PPP training skills and self-reflectionIn order to ascertain their PPP training capabilities, the interview question requested therespondents to indicate whether they had undertaken any PPP training to improve theirskills in the type of housing projects. Figure 2 shows the profile of the respondentsaccording to the PPP training undertaken.

The majority nine (69.2 per cent) of the interview respondents have not undertaken anyformal PPP training. The respondents were further asked if they were to assess themselves,whether they considered that they had enough (sufficient) skills and knowledge on PPP.A similar result with the majority nine (69.2 per cent) responded negatively. Interestingly,out of the minority four (30.8 per cent), who responded affirmatively, Interviewee F, workingfor the National Construction Corporation, acknowledged as still needing further skillsdevelopment in PPP due to changes in technology and techniques in the world. Similarly,Table IV shows the cross-tabulation results in response to the following survey questions:“If you are to asses yourself, do you think you have enough skills and knowledge on PPP?”and “Have you undertaken any PPP training to improve your skills into this type ofprojects (HPPP)”?

As can be seen from Table IV, the majority, 12 out 26, responded negatively. However,despite 42.9 per cent (12) of the respondents indicating that they had enough skills andknowledge on PPP, only a minority (5 of the 12) indicated that they had undertaken any PPPtraining to improve their skills, while the resultant majority (n¼ 7) who respondednegatively might suggest that the results are contradictory. The results from χ2 tests using

4, 31%

9, 69%

Yes No

Figure 2.Have you undertakenany PPP training toimprove your skillsinto these type(housing) projects?

216

ECAM25,2

Page 87: Engineering, Construction and Architectural

continuity correction values ( p¼ 0.260W0.05) demonstrated that the proportion ofrespondents who assessed themselves as having enough skills and knowledge on PPP andhad also undertaken training were not statistically significantly different from theproportion without skills and knowledge on PPP. More so, in spite of the majority indicatingthat they did not have enough skills and knowledge on PPP as obtained through formaltraining, the examination of Table II shows that the majority 17 (61 per cent) had experiencewith more than two PPP housing projects. Second, some of the respondents indicated thatthey had learnt about PPPs through self-directed learning (i.e. through reading books) andby undertaking the projects. Similarly, it could be inferred that these interviewees are thesame people (actors) who had initiated, procured and managed the PPP housing projects inTanzania irrespective of the number of successful and unsuccessful outcomes. Thesefindings are further supported by Gidden (1984) identification of the three dimensions ofstructure, namely signification, domination and legitimation. Drawing upon Gidden’sdefinition of “signification”, it could be inferred that despite these interviewees lack of skillsand knowledge, they nevertheless had the ability to produce meanings of the structure aswell as informing and defining interaction and direct the manner in which theproblems (challenges) are interpreted. As such, based on informal training, the experience(see Table II) of the interviewees and Gidden’s (1984) definition of “signification”,the interviewees were qualified to provide reliable and authentic feedback on the subject,and thus enhancing the validity of the findings.

However, the implication of this finding is indicative of the problems developing countriesface with regard to the training of its professionals. Tanzania, like many other developingcountries, faces the issue of training its workforce in a number of skills. For example, thestudy by Osabutey et al. (2012) established that the majority of construction professionalsnormally acquire their skills through informal means like on site or within their work place.Furthermore, according to Chileshe and Kikwasi (2014), the study established that only theTanzanian professionals working for foreign contractors (i.e. through JVs) have the ability toget training. These findings are also consistent with the literature on PPP training skills(Osabutey et al., 2012; Debrah and Ofori, 2005, 2006). For example, according to Osabutey et al.(2012), in many developing countries, there are no reputable institutions for training lower-level personnel, on-the-job training is largely inadequate and the personnel at that levelremains largely unskilled. Vocational training schools do exist in most of the countries, butmany workers and contractors see formal training as a cost rather than investment.

4.3 Ranking of the challenges influencing the delivery of HPPPThis section presents a combined discussion of the quantitative (survey) and qualitative(interviews) results. Based on the aggregated 19 challenges influencing the delivery of HPPPprojects, the questions are designed to require the respondents to rate their opinions using afive-point Likert as described in Section 3. Table V shows the results of these mean

Have you undertaken any PPP training toimprove your skills into this type of projects?

Count Yes No Totala

If you are to assess yourself, do you think thatyou have enough skills and knowledge on PPP?

Yes 5 7 12No 2 12 14

Total 7 19 26Notes: As two cells (50.0 per cent) had expected counts of less than 5, the χ2 tests values as computed werebased on the “Continuity Correction” and Fisher’s exact test. aTotal number of responses based on the validand completed data to the question (n¼ 26)

Table IV.Cross-tabulation for

“If you were to assessyourself, do you thinkthat you have enoughskills and knowledge

on PPP?” × “Have youundertaken any PPPtraining to improveyour skills into thistype of projects?”

217

PPP in housingprojects

Page 88: Engineering, Construction and Architectural

agreement responses, descriptive statistics such as the standard deviation, one-samplet-values, degrees of freedom (df ), and sig. (two-tailed).

As illustrated in Table V, the mean agreement scores of the 19 challenges ranged from4.82 (inadequate PPP skills and knowledge leading to poor planning and application) to3.36 (higher costs in procuring PPP projects). In contrast, the standard deviation of all the19 challenges ranges from 0.390 to 1.193, the highest standard deviation being “higher costsin procuring PPP projects”. Table III also shows that a third (31.5 per cent) of the challengesto the HPPP are statistically significantly different (Test 1: mean W3.5, t value positive,po0.05) with mean differences ranging from 1.321 to 0.393 as delivered in Tanzania.Further examination of the different values for the minimum and maximum scores(not listed in Table V ) suggests that the data and sample were not biased. For the ease ofdiscussion, only the top five ranked challenges (mean score W4.50) as based on the degreeof central tendency as well two of least ranked and not significant challenges are discussedhere. While there was no statistical difference (Table V, po0.05) between the opinions in theperception for the majority (68.4 per cent) of the challenges, it is evident that the top fivechallenges were as follows:

(1) inadequate PPP skills and knowledge leading to poor planning and application(mean ¼ 4.82, SD ¼ 0.390);

Challenget-test

(μ¼ 3.5) dfSig

(2-tailed)Meanscorea,b SD RII Rank

Significant( po0.05)

Inadequate PPP skills and knowledgeleading to poor planning and application

17.928 27 0.000* 4.82 0.390 0.964 1 Yes

Poor PPP contract and tender documents 9.731 27 0.000* 4.64 0.621 0.928 2 YesInadequate project management andmonitoring by public sector

9.899 27 0.000* 4.57 0.573 0.914 3 Yes

Inadequate legal framework 7.909 27 0.000* 4.54 0.693 0.908 4 YesMisinformation on financial capacity ofprivate partners

10.392 27 0.000* 4.50 0.509 0.900 5 Yes

Lack of competition 8.855 27 0.000* 4.46 0.576 0.892 6 YesDelays 9.500 27 0.000* 4.39 0.497 0.878 7 YesCorruption 6.931 27 0.000* 4.29 0.600 0.858 8 YesInadequate feasibility study 6.000 27 0.000* 4.21 0.630 0.842 9 YesDiffering goals between partners 4.385 27 0.000* 4.18 0.819 0.836 10 YesLong-term disputes and conflicts betweenparties

4.088 27 0.000* 4.11 0.786 0.822 11 Yes

Inadequate government commitment andsupport

3.437 27 0.002* 4.00 0.770 0.800 12 Yes

Insufficient capacity in procurement andnegotiations

2.091 27 0.046* 3.89 0.994 0.778 13 Yes

Poor risk allocation and management 1.580 27 0.126 3.79 0.957 0.758 14 NoIn experienced private partner 1.154 27 0.259 3.68 0.819 0.736 15 NoUnequal qualifications and contributionsof expertise

0.366 27 0.718 3.57 1.034 0.714 16 No

Poor enabling environment to attractcompetent partners

0.000 27 1.000 3.50 0.793 0.700 17 No

Inadequate mechanisms for recovery ofprivate investors’ capital

−0.500 27 0.621 3.39 1.133 0.678 18 No

High costs in procuring PPP projects −0.634 27 0.532 3.36 1.193 0.672 19 NoNotes: RII, relative importance index. aMean score based on valid n¼ 28 (list wise); bmean score of thechallenge variable where 5¼ strongly agree; 4¼ agree; 3 ¼ neutral; 2¼ disagree; and 1¼ Strongly agree.The higher the mean score, the more critical the challenge. *The mean difference is significant at the 0.05 level(i.e. po0.05)

Table V.Overall ratings ofchallenges inimplementing PPPhousing projectsin Tanzania

218

ECAM25,2

Page 89: Engineering, Construction and Architectural

(2) poor PPP contract and tender documents (mean ¼ 4.64, SD ¼ 0.621);

(3) inadequate project management and monitoring by the public sector (mean ¼ 4.57,SD ¼ 0.573);

(4) inadequate legal framework (mean ¼ 4.54, SD ¼ 0.693); and

(5) misinformation on the financial capacity of private partners (mean ¼ 4.50, SD ¼ 0.509).

The following sub-sections present a brief discussion of these highly ranked challenges.4.3.1 Inadequate PPP skills and knowledge leading to poor planning and application.

According to Abdul-Aziz and Kassim (2011, p. 155), the public agencies’ negotiation skillsand adequacy of negotiation staff have an effect on the delivery of housing projects and areequally inter-related. Based on the mean score, “inadequate PPP skills and knowledgeleading to poor planning and application” was the highest ranked challenge (mean ¼ 4.82,see Table V) and significant (t (27)¼ 17.928, p¼ 0.000o0.05) with a mean difference of1.321. The lower value of the standard deviation (SD ¼ 0.390) further reinforces theconsensus among the respondents in the higher ranking of this challenge. Support of thehigh ranking of this challenge can be found in previous PPP studies (Akintoye andKumaraswamy, 2016; Moskalyk, 2011; Wibowo and Alfen, 2015; Zhang, 2005a, b).

Similarly, a number of Tanzanian studies have equally highlighted the issue of skills andknowledge among construction professionals (Debrah and Ofori, 2005, 2006; Chileshe andKikwasi, 2014) and the lack of experience has been linked to the inappropriate perception ofrisk (Mboya, 2013). Elsewhere, within specific PPP studies, “shortage of workers” has beenidentified as among the project-specific commercial associated with the PPP projects(Gunawansa, 2012). For example, the study by Moskalyk (2011) suggested that this clearlyindicates the cause for its slow progress and failures. Similarly, the Zhang (2005a, b) studyhad previously considered this as a big challenge. The study by United Nations forEconomic and Social Commission for Asia and the Pacific (2012 cited in Wibowo and Alfen,2015) highlighted the benefits of having well-trained and experienced public sector officials,with benefits ranging from having the knowledge of where difficult issues would most likelyto arise, and the ability to select the appropriate tools for addressing the identified problems.

The interviews as conducted further confirmed the findings from the survey andliterature reviews. For example, Interviewees B, C, D and I identified “Inexperienced privatepartners”, “inadequate PPP skills and capacity” and “Incapacity of contractors employed byprivate partners”, respectively, among some of the challenges in implementing PPP housingprojects in Tanzania. Interviewee D attributed this challenge to “a new approach hence lackof experience”. By inference, the following implications emerge from the above results: thelack of skills and capacity will eventually result in poor planning for the PPP project, poorrisk identification, allocation and management as well as poor PPP project management.While this study did not measure any specific items associated with “procedural justice”constructs (see Zhang and Jia, 2010), the over reliance of the public partners on the privatepartners for acquiring the desirable PPP skills is recipe of having inequity among thepartners as posited by the equity theory (Scheer et al., 2003).

4.3.2 Poor PPP contract and tender documents and inadequate legal framework. “PoorPPP contract and tender documents (mean¼ 4.64, SD ¼ 0.621)” and significant(t (27)¼ 9.9731, p¼ 0.000o0.05) with a mean difference of 1.143, and “inadequate legalframework (mean¼ 4.54, SD ¼ 0.693)” and significant (t (27)¼ 7.909, p¼ 0.000o0.05) witha mean difference of 1.036 were ranked second and fourth, respectively. The synergiesbetween “procurement” and “interpretation of contractual issues” as nested within thesecond challenge with the overall legal issues were inherently included within the fourthchallenge. These findings are also consistent with other studies (Sengupta, 2006;

219

PPP in housingprojects

Page 90: Engineering, Construction and Architectural

Trangkanont and Charoenngam, 2014a; Ismail and Haris, 2014; Abdul-Aziz and Kassim,2011). For example, the study by Abdul-Aziz and Kassim (2011), albeit within the Malaysiancontext and which was aimed at examining the objectives of housing PPP, the success andfailure factors observed that the failure factor which had the most influence was theabsence of robust and clear agreement. Similarly, within the context of Thailand, the studyby Trangkanont and Charoenngam (2014a) pointed to “ineffective PPP policy and strategy”.Similarly, Tanzanian-specific studies, such as by Mboya (2013), attributed the poorperformance of PPP to unfavourable contractual terms for the contracting authorities.

The findings from the interviews further supported the above observations from thesurvey and literature reviews. For example, the majority (53.8 per cent) of the interviewees(A, C, D, G, H, J and L) identified some of the legal issues. Interviewee I identified thefollowing as major causes of failure of JV Corporations projects (also referred to as PPP):lack of an exit clause; contradictory provisions; agreements biased in favour of (some)partners; and non-adherence to the rules and regulations. With regard to the “poor PPPcontract and tender documents”, the issue of the “bidding processes”was identified. Some ofthe selected comments by Interviewee I (i.e. Legal officer for the NHC) are as follows:

These agreements have no exit clause. Generally, these agreements comprised of determinationclauses, of which it provides for the circumstances upon which the Agreements can be determined.

With regard to the contradictory provisions, and hence “inadequate legal framework”:

The provisions in the Agreements are badly crafted to the extent that they do contradict each otherand thus distort the whole meaning of their presence in the agreement.

With regard to the “non-adherence of the rules and regulations […]”:

[…] It has been discovered that there are some projects which are run without adhering to the rulesand regulations set by regulatory authorities. In most, the construction site is quite different fromthe agreed and authorised design. This once proved, might engage the corporation in ordering theprivate partner contractor to stop, demolish, or being fined […].

The challenge of “poor PPP contract and tender documents” was further evident asobserved by Interviewee I:

[…] It has been observed that some partners were given more projects to add on to the alreadyawarded projects. Meaning that there was double allocation of projects, without following thenecessary procedures. There has been a trend among partners to add more plots on the acquiredproject on pretext of expanding the magnitude of the projects […].

From the above observation, the inference to be drawn is that the procedures of awardingmore projects to partners were improper. Second, the board is being misled regarding theexpansion of the magnitude of the projects. The above behaviour of the private partners isreflective of their power and domination over the public partners, as highlighted in Gidden’s(1984) duality of structure. Accordingly, irrespective of the appropriate “contractual andtendering” rules associated with this type of procurement (PPPs), the private partnersdemonstrated the power that they had in effecting or having transformative capacity overthe other actors, namely “public partners”.

The other interviewees expressed similar although not as detailed comments. For example,Interviewee C (project manager) identified “Poor contractual relationship”, whereas InterviewD (managing director) highlighted the issue of “involving long negotiations” as the challenge.Similarly, Interviewees G and H singled out the “inadequate PPP policy and legal institutionalframework” and “complexity of PPP projects”, respectively. The only other comment relatedto the challenge of “Inadequate legal framework” noted by Interviewee L was “poor contract”.The views expressed by Interviewee H regarding “complexity” are consistent with the

220

ECAM25,2

Page 91: Engineering, Construction and Architectural

research and development agenda, as proposed by Akintoye and Kumaraswamy (2016).Akintoye and Kumaraswamy (2016, p. 26) drew the impacts arising from the complexity of thecontractual structure of PPP on transparency, evaluation of proposals and performanceamongst other issues.

The following implications emerge from the above results:

(1) That poor legal framework will lead to poor contracts and the rise of disputes.

(2) In identifying what the impediments are and how these challenges are managed, thisstudy therefore makes an important contribution by enhancing awareness.

(3) Because of the inability to identify existing challenges, the failure will prevail in suchprojects. Additionally, wastage of resources and housing shortage will persist.The consequence of these actions leads to abandonment, stalling and delaying of anumber of projects undertaken. These implications and findings from the interviewsfurther suggest some departure from fairness which should be the foundation of anytype of economic transactions (Zhang and Jia, 2010), and a clearer demonstration ofthe equity theory where some of the Interviewees identified some of the inequity inthe relationship with regards to unfavourable agreements (see Interviewee I).

4.3.3 Inadequate project management and monitoring by public sector. “Inadequate projectmanagement and monitoring by public sector (mean¼ 4.57, SD ¼ 0.573)” and significant(t (27)¼ 9.899, p¼ 0.000o0.05) with a mean difference of 1.071, was the third-rankedchallenge. As with most developing countries, the application of project management bestpractice has always been an issue. For example, the seminal study by Rwelamila et al. (1999)determined that the following two propositions are leading to project failure amongst theAfrican countries: the lack of Ubuntu between project stakeholders is primarily due to aninappropriate project organisational structure; and a default traditional constructionprocurement system provides a poor relationship management system. Similarly, within theTanzanian context, the studies by Kikwasi (1999, 2012) linked the poor delivery of projectsusing the pre-estimated time and cost to the adoption of conventional procurement method.Some more recent studies such as by Chileshe and Kikwasi (2014), albeit within the samecontext (Tanzania), have attributed this poor performance to the lack of effective riskmanagement implementation. The findings from the interviews also supported the aboveobservations from the literature review and survey findings. For example, some of theinterviewees acknowledged that inadequate project management was a major issue.A number of reasons put forward by the interviewees ranged from “the work of managingand project monitoring was left to the private partners in NHC HPPP thus giving them aloophole to make alterations” to “construction in site has been quite different from theagreed and authorised design hence leading into disputes”. Furthermore, IntervieweeH considered “complexity of PPP projects”, while Interviewees J and M identified “delays” asmajor challenges.

4.3.4 Misinformation of financial capacity of private partners. According to Mboya (2013,p. 22), the Tanzanian capital market is not mature enough to be conducive to the promotionof complex PPPs. The same study blamed the lack of adequate long-term financinginstruments. Leventhal (1980, cited in Zhang and Jia, 2010) identified the need for usingaccurate information as one of the six principles desirable for achieving procedural justice.Despite the importance of transparency throughout the procurement process (Osei-Kyei andChan, 2015), this challenge of “misinformation on financial capacity of private partners” stillremains an issue within the Tanzanian housing sector as evidenced by being ranked fifth(mean¼ 4.50, SD ¼ 0.509) and significant (t (27)¼ 10.392, p¼ 0.000o0.05) with a meandifference of 1.000. As previously highlighted by the study in Malaysia (Abdul-Aziz andKassim, 2011), misinformation can lead to the loss of trust, and subsequently results in the

221

PPP in housingprojects

Page 92: Engineering, Construction and Architectural

selection of inappropriate partners. The findings from the interviews were also consistentwith the observations from the literature review and survey findings. For example, some ofthe interviewees stated that poor determination of the shareholding ratio and recoveryperiod, and that lack of proper procedure on determining the financial status of the partnerswho are engaged in the JV agreement projects have been major challenges and have resultedinto project termination.

4.3.5 Other challenges – lack of competition, delay and corruption, inadequate feasibilitystudy, and differing goals between partners. Despite not being in the “top five” of highlyranked challenges, the issues of “lack of competition”, “delay” and “corruption” whichranked sixth, seventh and eighth, respectively, are worth mentioning. Studies have shownthat competitive bidding is imperative in order to eliminate corruption and allow fortransparency and best partner selection. Narasimhan (1997 cited in Tabish and Jha, 2011)has suggested punitive measures such as mechanisms for effective investigation in dealingwith corruption. Similarly, while “inadequate feasibility study” and “differing goals betweenpartners” had a mean score of 4.21, 4.18, respectively, and they were ranked as ninth andtenth position, studies such as Moskalyk (2011) identified and cited “differing goals betweenpartners” among the five common challenges governments were facing in HPPP projects.

4.4 One-sample t-test resultsA single-sample t-test was conducted to determine if a statistically significant differenceexisted between challenges affecting the delivery of HPPP from the sample as used in thisstudy and the general population of Tanzanian stakeholders involved in housing projects.Prior to undertaking this t-test, although not reported, the normality of the data wasundertaken through the examination of the descriptive statistics such as the skewness andkurtosis. No assumptions were found to be violated. Examination of Table V shows thatwith the exception of top 13 ranked challenges, the mean values of the remaining sixchallenges were not significantly different from the t-test value of 3.500 as follows:“Poor risk allocation and management”, (t (27)¼ 1.580, p¼ 0.126W0.05) with a meandifference of 0.286; “Inexperienced private partner”, (t (27)¼ 1.154, p¼ 0.259W0.05) with amean difference of 0.179; “Unequal qualifications and contributions of expertise”,(t (27)¼ 0.366, p¼ 0.718W0.05) with a mean difference of 0.071; “Poor enablingenvironment to attract competent partners”, (t (27)¼ 0.000, p¼ 1.000W0.05) with a meandifference of 0.000; “Inadequate mechanisms for recovery of private investors’ capital”,(t (27)¼−0.500, p¼ 0.621W0.05) with a mean difference of −0.107; and “High costs inprocuring PPP projects”, (t (27)¼−0.634, p¼ 0.532W0.05) with a mean difference of −0.143.The conclusion to be drawn is that there is a statistically significant difference of opinion inthe rankings at the po0.05 level in 13 out of the 19 challenges.

4.5 Interview survey findingsIn order to enhance the validation of the results, the findings from the survey research weretriangulated with those from the interviews. Response to the interview question was posedto the PPP experts in relation to political willingness and stakeholders’ readiness towardsPPP. All interviewees agreed that there is a high political willingness towards the strategy.The reason put forward was not only due to successful case histories from other developingcountries like Malaysia and India, but because of an inadequate enabling environment inTanzania; PPP approach has not been successful as in other countries. Some of the PPPexperts in PPP units claimed to have visited these countries for PPP training and wereseconded to PPP projects for hands-on experience. However, it was reported by twointerviewees that the PPP unit has little or no impact on the proposed PPP projects despiteits existence. A number of new PPP projects have been initiated and some started without

222

ECAM25,2

Page 93: Engineering, Construction and Architectural

being submitted to PPP units for assessment and approval due to the fear of governmentbureaucracy, for example, “Dege Eco Village”. This reveals that PPP unit has beenineffective and underutilised; it is also possible that the PPP regulations are not enforced,thus allowing a PPP project to take off without being evaluated and approved by the PPPunit. There is a need for the Government of Tanzania to re-examine its PPP unit, policy andits guidelines.

4.5.1 Status and performance. In response to the question about the status andperformance of the PPP housing projects, it was reported that during the survey period,NHC had 183 JV projects, out of which 104 were completed, while 35 were currently underconstruction. Of those under construction, the majority were facing delays for a couple ofyears. The findings also established that 29 projects had been discontinued or wereterminated, while 21 projects have stalled due to various reasons. This status clearlyindicates the existence of challenges to its performance. Respondents were further asked torate the performance and 70, 21 and 9 of the respondents reported that there is poorperformance, average performance and very poor performance, respectively. The majorityof interviewees commented that since a large number of NHC JV projects were unsuccessful,there was little motivation for more similar projects. For the NSSF HPPP project, itsprogress was reported to be good but it has faced delays, which resulted in changes indesign, shipping of the imported materials and adverse weather conditions. Further reportssuggested that the private partner was facing financial difficulties.

4.5.2 Awareness and benefits. In response to awareness of PPP and its benefits,60 per cent of respondents’ awareness is still little; benefits are marginal and very slowbecause of the lack of enough skills and expertise. Subsequent to that one of the interviewee,who was a quantity surveyor and a project manager, commented as follows:

Even the said affordable houses are still not affordable to the low income, the reason given for thelack of affordability is that, the government is not willing to provide subsidies to such projects andno good policies have been put in place.

Hence, for decades, the preferred method for providing affordable houses to the low-incomegroup in Tanzania has been through personal effort in saving and building which can take10-15 years or more to complete the construction, and sometimes some of these housesremain incomplete, yet people currently live in them despite their poor conditions.

5. Model development approachThe model development approach followed an efficient methodology and tools to aid theprocess comprising the following three stages: literature review; questionnaire survey; andinterview survey:

• A literature review was undertaken on PPP housing projects across a variety of othercountries in order to identify best practices and success factors. Table I presents thesummary of the studies.

• Questionnaire and interview surveys were carried out in order to study the localcontext in terms of the practice, challenges and perceptions.

As part of the study, in order to investigate what has been happening over the last twodecades or so globally, as far as PPP in housing and infrastructure project is concerned andincorporate the lessons learnt into the proposed framework model, further review of theliterature was considered as necessary. Drawing upon the approach undertaken in the studyby Chileshe et al. (2013) which proposed diagnostic models for strategic risk assessment,according to Archer (2003 cited in Chileshe et al., 2013), the agents (Tanzanian public andprivate stakeholders) have the ability of incorporating the lessons learnt due to their prior

223

PPP in housingprojects

Page 94: Engineering, Construction and Architectural

understanding of historical issues. The main purpose was to address and enhance the HPPPchallenges in Dar es Salaam Tanzania. In view of the fact that PPP has not commonly beenassociated with housing projects, but rather civil infrastructure projects, there have beenlimited studies conducted on HPPP. It can be inferred from the reviewed literature (Table I)that different countries adopted different success factors in PPP housing projects, aswell as in other PPP projects. Table VI shows and summarises the factors identified assignificant for the successful delivery of PPP housing projects and for PPP projects in theconstruction industry.

As can be seen from the given list of success factors, it is quite evident that some successcriteria are similar and cut across all the sectors in the construction industry. However, othersuccess factors such as selecting private developers with a sense of social obligation toenhance compatibility, just enough government subsidies to support affordable housingprojects and favourable housing loan terms from the financial institution appeared to bemore specific to HPPP projects. Likewise, based on best practices and lessons learned,Moskalyk (2011) listed eight key principles for PPPs in housing and urban development,which are as follows:

(1) interest of the public is supreme;

(2) such projects should mirror the needs of the community and blend into stakeholders’priorities;

(3) transparency and accountability methods should be maintained throughout theproject lifecycle;

(4) clearly defined scope and objectives with careful planning;

(5) the preferredmodel must offer value for money in terms of cost, time and risk allocation;

No. Success factors for PPP housing projectsSuccess factors for PPP projects inconstruction industry

1 Government involvement Strong and good private consortium2 Government support through subsidies and guarantees Appropriate risk allocation and risk

sharing3 Accurate project Identification Available financial market4 Competitive and transparent procurement Government support and guarantee5 Adequate legal framework Favourable economic condition6 Stable macro-economic condition Available financial market7 Favourable economic policy Transparency in procurement process8 Presence of strong financial market Fairness and competitive tendering9 Favourable housing loan terms from the financial institution Favourable legal framework10 Selecting private developers with a sense of social obligation to

enhance compatibilityProject technical feasibility

11 Public sector to carry out feasibility study rather than theprivate sector to avoid exaggeration

Realistic cost benefit analysis

12 Just enough government subsidies to support affordablehousing projects

Good governance

13 Conducive socio-economic structure to boost income generation Shared authority between parties14 Trust between parties Trust between parties15 Favourable housing policies Well-formulated and detailed contract16 Adequate PPP Capacity Constant communication and

monitoring17 Careful ground work18 Political support

PPP capacity and awareness

Table VI.Summary ofcomparative analysisbetween successfactors for PPPprojects in housingprojects andconstruction industry

224

ECAM25,2

Page 95: Engineering, Construction and Architectural

(6) competitive tendering is crucial;

(7) project viability must be measured against the set criteria to determine its PPPsuitability; and

(8) accountable management of the project must exist throughout its lifespan.

In the context of this study, the above eight principles and the success factors wereidentified as the appropriate mitigation strategies or responses in solving the challengesfaced in PPP housing projects in Dar es Salaam, Tanzania. Furthermore, these principlesand success factors were regarded as the basis for the development of the PPP conceptualframework (see Figure 3). Therefore, the proposed framework model was designed tofacilitate the attainment of these features in the Tanzania HPPP projects in consideration ofthe identified challenges. It is visualised that the more opportunity for these features to beincorporated in the model, the better the chances of successful implementation of HPPPbecause the absence of these “principles and success factors” could equally be considered aconstraint.

6. The proposed framework modelIn developing the PPP housing framework model, the adopted approach was based on theproject life cycle approach. This involved designing systematically and customising toaddress the vital stages that need careful attention throughout the life cycle of the project withrespect to weaknesses identified. The key features of the model will address major constraintsthwarting the delivery of adequate housing in Tanzania. In contrast to other developed PPPframework models by Trangkanont and Charoenngam (2014b) and Tutesigensi andMohammad (2008), the proposed model consists of five major phases, featuring five keyaspects: skills, planning, procurement, monitoring and controlling. Through a critical analysisof the problems, inadequacy of these features was determined as the main cause of thechallenges. Hence, unlike other models, the proposed model aims at providing systematic

Phase 1 Phase 2 Phase 3 Phase 4 Phase 5

Preparation Planning Procurement Building Operating

= Document

= Task

Detailedfeasibility study

Need levels

Decide on procurementroute and risk

Proposal

Submit proposal to advisory team in

PPP unit

Project brief

Prepare project team,procurement strategy

and documents

Advertiseproject

Prequalificationcriteria

Selecting preferredbidder

Award andagreement

Agree onkey issues

Managementprocedures

Set up a specialpurpose vehicle

(SPV)

Project execution

Monitoring andcontrolling

Daily andmonthly report

Performance measurement

Performancereport

Level 1

Level 2

CA matching projectgoals and public

interest

Setprequalificationcriteria to align

with project goals

SPVSet up in-house PPPproject steering

committee

Prepare in-housePPP trainingprogrammes

Arrange forPPP enablingenvironment

Housing PPP legalframework

mortgage financinggovernment subsidiesPPP expert/advisers

Prepare a pilotproject

Pilot project goals

Projectoperation

Housingallocation

Mortgageservicing

Contractagreement

Sales andrevenue

logbook report

Operationreport

Monthlyrent/salescollection

Figure 3.Proposed PPP

framework model forHousing projects

225

PPP in housingprojects

Page 96: Engineering, Construction and Architectural

guidance while addressing the challenges to enhance the delivery of PPP housingprojects. Previous PPP models address risk management in PPP low-cost housing(Trangkanont and Charoenngam, 2014b) and initiation of PPP in the construction industry(Tutesigensi and Mohammad, 2008). The proposed framework is shown in Figure 3.

The basis and justification for the selection of the Trangkanont and Charoenngam(2014b) and Tutesigensi and Mohammad (2008) as a point of comparative reference with theproposed Tanzanian model is the fact that they are all from developing countries, withsimilar socio-economic conditions.

In order to address the second objective of the study, namely to “suggest advocatedsolutions in form of a conceptual PPP framework that will address the identified challengesand hence boost its success”, the following section illustrates how the framework aspresented in Figure 3 is mapped to the identified challenges 1-19 (see Table I and Table Vwith the advocated remedial solutions). These challenges and solutions were furthermapped to the appropriate phase of the framework. Table VII presents the summary of thismapping exercise.

Examination of Table VII shows that the majority 6.5 (34.21 per cent) of these challengeswere more prevalent in the “Procurement phase” followed by the “Preparation phase” with6 (31.58 per cent) and in third place was the “Planning phase” with 4 (21.04 per cent).Interestingly, within the last “Operating phase”, no challenges were assigned.The implication of this “mapping exercise” highlights the need for the Tanzanianstakeholders to address the issues associated with procurement for effective implementationof PPPs. As recently acknowledged by the World Bank (2016, p. 30) report, “the rules andprocedures governing PPP selection and decision making in Tanzania are clearly delineated,but the implementation is less than perfect”.

Further application of the “mapping exercise” and explanation of the model are providedin the following sub-sections.

6.1 Phases of the model explained6.1.1 Phase 1: preparation. In Phase 1, the main focus of the model is on the preparation ofthe necessary groundwork in order to enhance skills and improve a PPP-enablingenvironment. This phase is equivalent to the “pre-contract” stage and crucial in theattainment of procedural justice, as identified by Zhang and Jia (2010, p. 518). BecauseTanzania is still immature in PPP projects in the areas of skills and experience, thischallenge ranked as the highest in Table IV (mean¼ 4.82) and significant (t (27)¼ 17.928,p¼ 0.000o0.05) with a highest overall mean difference of 1.321, and highlighted as one ofthe major challenges from the reviewed studies in Table I (n¼ 8, 40 per cent). To overcomethis challenge caused by economic problems and financial constraints, it is important toprovide training to public officials. However, it is expensive to send a group of peopleabroad for training, hence an “in-house” steering committee is proposed in the model as thebest alternative to assist with addressing the “skills training” and “enabling environment”.The need for better PPP training was a major concern raised by Morledge and Owen (1998)and Mitchell (2007). Therefore, during this stage, emphasis is on the need to equip publicofficials with adequate skills so that they gain skills and knowledge to deal with thecomplexity of PPPs. In order to prove that the trained personnel have acquired the PPPskills, a pilot project should be undertaken. The ultimate goal of this pilot study will be toassess the capacity and understanding of the trained personnel. The control method for thisphase is the PPP training programme. This control method will ensure that personnel withthe necessary skills set will administer such projects.

6.1.2 Phase 2: planning. In Phase 2, the client/public sector needs to carry out a detailedfeasibility study in order to determine the real needs of the public not considering the

226

ECAM25,2

Page 97: Engineering, Construction and Architectural

No. ChallengesAdvocated remedialsolutions

Supportingliterature Model strategy Phased

1 Differing goalsbetween partners

Careful ground work;selecting private developerswith a sense of socialobligation to enhancecompatibility; andcompatibility betweenpartners

Moskalyk (2011),Abdull-Aziz andKassim (2011)a,World Bank (2016)c

Set prequalificationcriteria to align withproject goals

P3

2 Corruption Transparency inprocurement process; andaction against errantdevelopers

Abdull-Aziz andKassim (2011)a

Less negotiations afterbidder selection

P3

3 Misinformation onfinancial capacityof private partners

Transparency inprocurement process; trustbetween parties; and ampletime to evaluate proposal

Abdull-Aziz andKassim (2011)a,Jamali (2004)a

Thorough documentscreening

P3

4 Poor PPP contractand tenderdocuments

Well-formulated anddetailed contract andadequate legal framework;and good preparation

Kwofie et al. (2016)b,Babatunde et al.(2012)b, WorldBank (2016)c

Detailed preparationand planning; “in-house” steeringcommittee is proposedin the model to enhancePPP trainingprogramme

P3

5 Delays Constant communicationand monitoring; and strongand good privateconsortium

Akintoye et al.(2003), Li et al.(2005), Abdull-Azizand Kassim (2011)a

Tier-two projectmanagement system toenhancecommunication

P4

6 Inadequate PPPlegal frameworkand guidelines

Adequate legal framework Ismail (2013)a,World Bank (2016)b

Arrange for PPP-enabling environment

P1

7 Inadequate PPPskills andknowledge

Adequate PPP capacity;and PPP training andawareness

Jefferies et al. (2002),Cheung et al. (2012),World Bank (2016)c

“in-house” steeringcommittee is proposedin the model to enhancePPP trainingprogramme

P1

8 Lack ofcompetition

Transparency inprocurement process; andfairness and competitivetendering

Ismail (2013)a,Abdull-Aziz andKassim (2011)a,World Bank (2016)b

Competitive tendering P3

9 Inadequatefeasibility study

Careful ground work; andpublic sector to carry outfeasibility study ratherthan the private sector toavoid exaggeration

Jefferies et al. (2002),Cheung et al. (2012),Ismail (2013)a,World Bank (2016)c,URT (2009)c

Need levels must beidentified clearly bypublic sector

P2

10 Inadequate projectmanagement bythe public sector

Good governance; constantcommunication andmonitoring; trust betweenparties; and consistentmonitoring

Jamali (2004)a,World Bank (2016)c

Tier 2 projectmanagementcontrolling

P4

11 Long-termdisputes andconflicts betweenparties

Transparency inprocurement process; trustbetween parties; constantcommunication and

Ismail (2013)a,Jamali (2004)a

Agree on key issuesupfront andmanagement/disputesprocedures

P3 andP4

(continued )

Table VII.Mapping the PPPchallenges with

advocated remedialsolutions to the

framework

227

PPP in housingprojects

Page 98: Engineering, Construction and Architectural

No. ChallengesAdvocated remedialsolutions

Supportingliterature Model strategy Phased

monitoring; and partnerscompatibility

12 Inadequategovernmentcommitment andsupport

Just enough governmentsubsidies to supportaffordable housing projects;and commitment of thepublic and private sectors

Ismail (2013)a,Kwofie et al. (2016)b,World Bank (2016)c

Arrange for PPP-enabling environmentduring the preparation

P1 andP2

13 Insufficientcapacity inprocurement andnegotiations

PPP capacity andawareness; and PPPtraining

Jefferies et al. (2002),Cheung et al. (2012),World Bank (2016)c,URT (2009)c

Prepare in-house PPPtraining programmesand enablingenvironment

P1

14 Poor riskidentification,allocation andmanagement

Appropriate risk allocationand risk sharing

Ismail, (2013)a, URT(2009)c

Detailed feasibilitystudy

P2

15 In experiencedprivate partner

Fairness and competitivetendering; strong and goodprivate consortium; PPPcapacity and awareness;and public empowerment

Jamali (2004)a,Jefferies et al. (2002),World Bank (2016)c,URT (2009)c

Set prequalificationcriteria to align withproject goals; PPPtraining programmes

P3

16 Unequalqualifications andcontributions ofexpertise

Adequate PPP capacity;PPP capacity andawareness; and sharedresponsibility betweenpublic and private sectors

Chan et al. (2010),Jefferies et al. (2002),Cheung et al. (2012)

Submit proposal toadvisory team in PPPunit

P1

17 Poor enablingenvironment toattract competentpartners

Good governance; soundeconomic policy; andavailability of financemarket

Ismail (2013)a,Jefferies et al. (2002),Cheung et al. (2012),URT (2009)c

Arrange for PPP-enabling environment

P1

18 Inadequatemechanisms forrecovery ofprivate investors’capital

Conducive socio-economicstructure to boost incomegeneration; accurate projectidentification and technicalfeasibility; thorough andrealistic assessment of thecost and benefits;government should providefree land to privateinvestors to lower the costof the houses; andempowering the low-income group financially

Ibem (2011b)b,Ismail (2013)a

Kwofie et al. (2016)b,World Bank (2016)c,URT (2009)c

PPP Unit enforcing itsadvisory role andarrange for PPP-enabling environment

P2

19 High cost inprocuring PPPprojects

Adequate PPP capacitybuilding; PPP capacity andawareness; availablefinancial market; thoroughand realistic assessment ofthe cost and benefit; andeconomic viability

Jefferies et al. (2002),Cheung et al. (2012),Ismail (2013)a,World Bank (2016)c,URT (2009)c

Prepare in-house PPPtraining programme totrain local people,

P1 andP2

Notes: aDenotes studies from African countries such as Ghana and Nigeria; bdenotes studies fromdeveloping countries such as Malaysia, Ghana, Nigeria and Lebanon; cdenotes Tanzanian-specific studies;dThe phase relates to the states as shown in Figure 2 and P1: preparation; P2: planning; P3: procurement;P4: building; P5: operatingTable VII.

228

ECAM25,2

Page 99: Engineering, Construction and Architectural

political needs as the public needs because the two may utterly differ. However, as observedby Trangkanont and Charoenngam, (2014a), leaving such tasks in the remit of the privatesector may result in dishonesty and artificial demands. According to Trangkanont andCharoenngam, there were cases where the private sector had convinced the public sectorthat a project was viable and demand for it was high as was the case in Thailand. Realisticdemands will enhance the assessment of PPP projects enabling genuine and correctdecisions to be made. The following challenges were significant (see Table V), namely“inadequate PPP skills and knowledge leading to poor planning and application”, “poor PPPcontract and tender documents”, “inadequate project management and monitoring by publicsector” and “feasibility study”, and ranked first, second, third and ninth, respectively(see Table IV), and will be addressed in this planning phase. This is because they are projectmanagement and procurement oriented, as evidenced by the Project Management Body ofKnowledge areas (see Project Management Institute, 2008). For example, planning is acritical element in project management, because it provides the basis for investmentdecisions and aids in developing a project that mirrors the real needs of the community.Furthermore, within PPP projects, consideration of the approval process is vital. Thisprocess is undertaken to allow a proposed PPP project to go through screening and checksin order to further ascertain its viability, affordability, value for money and appropriate risktransfer. Thus, the proposal is submitted to the national PPP unit, which is an independentbody made up of different professionals to assess the legal, financial, technical, cultural andsocial aspects. In this phase, the consideration of the feasibility study report, value formoney and affordability assessment and PPP unit approval constitute the control methods.If these are not completed, then the project cannot proceed to procurement stage.

6.1.3 Phase 3: procurement. In this phase, the contracting authority revisits theprocurement package and a set of prequalification criteria to make sure that they align with theproject goals. Following on from this would be advertising of the project and submission ofbids by prequalified bidders. A preferred bidder is then selected. Since “corruption” ranked asthe eighth challenge affecting the delivery of PPP projects (mean score ¼ 4.29) and significant(t (27)¼ 6.931, p¼ 0.000o0.05) with a mean difference of 0.786, in this stage negotiations arediscouraged because they sometimes lead to corruption or unnecessary alterations.Hence, adequate planning and preparation minimise the need for negotiations. However,parties still have to agree early on a number of issues onmanagement procedures as challengesranked second, third and fourth are project management, procurement and legal issues related.This may include the structure of communication, decision making, problem solving,performance evaluation and conflicts management. Competitive tendering and transparencyare the control method for this phase, hence unsuccessful bidders should be informed why thewinner was chosen in preference. As asserted by Zhang and Jia (2010, p. 518), effectivecooperation among the parties could be achieved through exercising procedural control.

6.1.4 Phase 4: building. The special purpose vehicle would be utilised in the execution ofthe project. This stage requires adequate monitoring and controlling. Since the governmentremains accountable for the delivery of its services, it is important to have a clearmechanism to monitor its performance. In this case, project authorities may create a two-tiersystem, contracting authority as tier 1 and ministry/PPP unit as tier 2 in order to address thethird-ranked challenge which is “inadequate project management and monitoring by publicsector” and significant (t (27)¼ 9.899, p¼ 0.000o0.05) with a mean difference of 1.071.In order to facilitate the compilation of a monthly report, the site manager should producedaily reports. The architect would then facilitate and certify the submission to the tier 1authority. Likewise tier 1 submits its monthly report to tier 2, which can be the ministry incharge of the project or the PPP unit. The two-tier monitoring mechanisms provide a doublecheck, thus ensuring effectiveness and accountability. Finally, in order to meet the key

229

PPP in housingprojects

Page 100: Engineering, Construction and Architectural

performance indicators of time, cost, quality and safety, a performance measurement wouldthus require development.

6.1.5 Phase 5: operating. The last phase is the operating one and involves the allocationof the completed housing units through sales/renting. The private partner will operate asper the agreed contract. The operation in this phase will depend on the nature of the project.For example, low-income housing projects as noted in the Malaysian (Ismail and Haris, 2014;Abdul-Aziz and Kassim, 2011) and Thai studies (Trangkanont and Charoenngam, 2014a, b),both required an honest, fair and transparent allocation system to ensure that the housesreached the intended group. Thus, in order to have a listing of public sector and qualifiedhouse buyers, mechanisms would have to be established. In addition, for transparency andtrust building, there would be a need for depositing the monthly collection into a jointaccount. Following this, the production of monthly sales performance and financial statusreports would then be undertaken in a similar way. The control mechanism for this stage isthe openings of a joint account with the inclusion of a specific clause in the contract that willcompel the private partner to submit monthly financial reports.

7. Contributions, recommendations and implications7.1 ContributionsA number of contributions emerge from this study. First, to the best of our knowledge, ourempirical study is among the first in construction and housing-specific empirical studies on anumber of areas affecting PPPs, and that identifies and ranks the challenges of PPP forhousing projects delivery within the Tanzanian context. The identification of the challengesenabled their ranking, resulting in the mapping out of the most critical challenges(see Table VII) with the “Procurement” and “Preparation” phases being identified as the mostcritical. Second, using the Gidden’s structuration theory, the study illustrates how institutionmechanisms (structures) address these delivery challenges, thus influencing theimplementation of HPPP in Tanzania, and how individual stakeholders (human agents oragency) are able to make choices (advocated solutions) in dealing with the challenges(see Table VII). Third, while the linkages between procedural justice and corporation effectswere not empirically tested, the application of the equity theory to the qualitative (interviews)and quantitative (questionnaire) findings demonstrated the existence of “inequity” among theTanzanian partners with the private partners having the upper hand in dealing with themajority of the issues affecting the delivery challenges influencing PPP in Tanzanian housingprojects. Finally, using the project life cycle approach, the study proposes a framework(see Figure 3) aimed at addressing major constraints thwarting the delivery of adequatehousing in Tanzania. Drawing upon Chileshe et al. (2013, p. 165), the proposed frameworkopens the possibility of examining both the CSFs (Table VI) of the agents (Tanzanianpractitioners) in relation to the delivery of the PPP in housing projects and their failures(challenges) in dealing with the external environment and associated regulatory factors.Furthermore, through the alignment and mapping the identified challenges to the proposedremedial solutions across the five phases within the proposed PPP framework (see Table VII),the study has contributed to the PPP research agenda albeit within the developing countriescontext by responding to and addressing the study by Akintoye and Kumaraswamy (2016)which renewed the calls for more research on PPP.

7.2 Recommendations and implicationsSome suggested recommendations and implications for government, policy makers,practitioners and research are as follows:

(1) Government and policy makers would be required to consider carefully improvingand/or revising the existing PPP policy and regulations as well as put forward a

230

ECAM25,2

Page 101: Engineering, Construction and Architectural

housing policy that will initiate the supply of more affordable housing.Correspondingly, in-house training should be emphasised, facilitated andcoordinated by the government through the PPP Coordinating Unit to both thepublic sector and private sectors in order to acquire the necessary PPP skills andknowledge. As illustrated in Table VII, the majority of the challenges are nestedwithin the “Procurement phase” of the proposed framework, followed by the“Preparation phase”. Therefore, training programmes should be tailored to addressthese challenges early on in the process.

(2) For practitioners, the identified challenges have formed the basis of the frameworkpresented in this paper. Furthermore, these provide useful information, thus leadingto increased awareness and to successful delivery of HPPP in Tanzania. However,these managerial (practitioner) implications should be considered in light of thecontingency theoretical perspective which requires all the partners in an alliancesuch as the prevailing JVs to be compatible (Vivek and Richey, 2013). Clearly, this isnot the case within this study where the interviewee findings (see IntervieweeI responses) highlighted the private sector as having agreements more favourable tothem than the Tanzanian public sector partners. Similarly, on the one hand, thefindings in Table V point to the private sector withholding financial informationfrom their public partners, and more so, there is clear lack of “equity” compoundedby the numerous challenges or unexpected contingencies (Zhang and Jia, 2010)facing the public partners. In particular, these public partners are disadvantaged bythe lack of knowledge across a number of project management areas such as“Inadequate PPP skills and knowledge” and “Inadequate project management andmonitoring”. On the other hand, Table VII might have suggested some advocatedremedial solutions to these “challenges” and simplified the process by mapping themto the appropriate stages within the framework. As illustrated in Figure 3, there is aclear need for managerial attention in PPPs implementation during the initialpreparatory phase, and re-evaluation of the basic tenets of the “equity theory”.

(3) For academia, drawing upon the recommendation of Chileshe and Kikwasi (2014),there also appears a need for increased training of the desirable skills for overseeingPPP projects. These would include negotiation, risk allocation and the selection ofpartners (see Table IV ). In the opinion of Moskalyk (2011), local- or national-levelPPP units should be leading in the provision of effective instruments to build theexpertise of governments. The application of effective risk management frameworkshas also been suggested as the mechanism for improved decision making on riskresponse strategy selection and resource allocation in the PPP project life cycle(Trangkanont and Charoenngam, 2014b). Tanzanian stakeholders could learnlessons from that. Therefore, the Tanzanian PPP units and coordinating units aslisted in Table III should be championing this cause. As illustrated in the proposedPPP framework (see Figure 3), this training should be undertaken during Phase 1,namely the “preparation”.

8. Limitations and further researchWhile a number of contributions to PPP theory such as Gidden’s structuration theory,contingency theory, relational and equity theory, and practice emerge from this study, thefollowing limitations related to the geographical setting, sample size and model validationare noted.

The interview and survey sample consisted of stakeholders drawn from only one city inTanzania, namely Dar es Salaam, and consequently the results may not be generalised toother surrounding countries sharing similar economic conditions such as the East Africa

231

PPP in housingprojects

Page 102: Engineering, Construction and Architectural

Community (namely, Republics of Burundi, Kenya, Rwanda, South Sudan, and Uganda).The framework can contribute towards addressing similar challenges as well as providingguidance; however, this needs validation. As asserted by Tang et al. (2010, p. 690), theseconceptual models can be developed based on case studies, and further tested by the use of arepresentative sample. Furthermore, as this study is part of ongoing research, at this stage,the paper does not offer a conclusive answer to the question of validity of the model.

Drawing upon the studies of Yalegama et al. (2016) and Abdul-Aziz and Kassim (2011),our study further acknowledges that the identified challenges particularly from thequalitative research (interviews) may be considered as Tanzanian specific. Therefore,whereas the advocated solutions in the form of the PPP framework (see Figure 3) mightwork in Tanzania and a country with similar socio-economic, legal, procurement andcultural aspects, our study further acknowledges that the outcome may be different inanother country. Any future research on challenges to PPP delivery as well as advocatedsolutions needs to take into consideration the prevailing conditions within the country ofstudy, and thus tailoring the research to them. As articulated by Abdul-Aziz and Kassim(2011, p. 151), these success and failure (labelled as “challenges”) factors for housing PPPprogrammes may be country specific. Another requirement would be the monitoring of boththe internal and external conditions in the host country by partners (Tang et al., 2010).The proposed framework model will be tested and validated to examine the applicability ofthe proposed framework in other housing PPP projects in Tanzania, and in other similardeveloping countries.

9. ConclusionsIn order to facilitate creative and innovative approaches in stimulating the private sector, itis widely accepted that engagement of PPP is a viable option. Furthermore, governments inboth developed and developing economics normally require bidders to compete on the basisof developing unique and creative approaches to the delivery of many physicalinfrastructure facilities. Despite the importance and role of PPPs, research on the challengesaffecting the delivery of PPP in housing projects remains underexplored.

The purpose of this research was to investigate the perception of the challenges affectingthe delivery of HPPP projects among the construction professionals in Tanzania, and proposea PPP framework to address the identified challenges, and hence boost opportunities for thesuccessful delivery of these projects. A number of theoretical perspectives, such as Gidden’sstructuration theory, contingency theory, relational and equity theory, were applied ininterpreting the findings as well as underpinning the methodological approaches. In all,19 HPPP challenges as identified from reviewed literature (see Table I) were revised andadopted. These challenges formed the basis for the questionnaire survey development andsemi-structured interviews. As a result, the identification of the challenges towards the growthand successful delivery of HPPP projects in Tanzania was undertaken.

The results demonstrated that Tanzanian construction professionals ranked thefollowing challenges as having significant ( p o 0.05) opportunity to derail the delivery ofthe HPPP (mean score W4.50):

(1) inadequate PPP skills and knowledge leading to poor planning and application(mean ¼ 4.820);

(2) poor PPP contract and tender documents (mean ¼ 4.640);

(3) inadequate project management and monitoring by public sector (mean ¼ 4.57);

(4) inadequate legal framework (mean ¼ 4.540); and

(5) misinformation on financial capacity of private partners (mean ¼ 4.500).

232

ECAM25,2

Page 103: Engineering, Construction and Architectural

The least ranked and not significant ( pW0.05) five challenges were as follows:

(1) inexperienced private partner (mean ¼ 3.680);

(2) unequal qualifications and contributions of expertise (mean ¼ 3.570);

(3) poor enabling environment to attract competent partners (mean ¼ 3.500);

(4) inadequate mechanisms for recovery of private investors’ capital (mean ¼ 3.390); and

(5) high costs in procuring PPP projects (mean ¼ 3.360).

The study applied the Adams (1965) equity theory as cited in Zhang and Jia (2010) andScheer et al. (2003) to both the qualitative and quantitative findings. This theory enabled theexplanations of inequity among the private and public Tanzanian stakeholders (partners)particularly with regards to addressing and managing issues associated with the “Poor PPPcontract and tender documents” and “inadequate legal framework”. For example, some ofthe findings from the interviews indicated that the majority of the NHC HPPP contracts hadmajor legal issues such as lack of an exit clause, contradictory provisions in an agreement,bias in favour of their private partners, double standards and uncertain practice in thetransfer of right of occupancy and non-adherence to the rules and regulations amongpartners. The study also revealed that despite of the survey respondents having assessedthemselves as having enough skills and knowledge on PPP, they still had not undertakenany PPP training to improve their PPP management skills (of PPPs). In summation, thestudy reinforced the belief that Tanzania, like other developing countries, experiencesinsufficient government funds and poor housing conditions. Therefore, publicorganisations, in this case NHC and NSSF, have adopted the PPP strategy to deliverhousing projects. However, these HPPP projects have not been as successful as expected.Finally, the findings from the interviews revealed the existence and interplay between thethree dimensions of structure as represented by signification, domination and legitimationand those (dimensions) of agency as represented by communication, power and sanctions.For example, Interviewee’s I responses related to the challenge of “non-adherence of therules and regulations” were clear evidence of the existence of the duality between“domination” and “power”. From this, a conceptual framework for HPPP has beendeveloped and examined using the theoretical underpinnings of Gidden’s theory of structureas well as exploring the synergies and interactions between the various dimensions of thestructure and agency.

References

Abdul-Aziz, A.-R. (2001), “Unraveling of BOT scheme: Malaysia’s IndahWater Konsortium”, Journal ofConstruction Engineering and Management, Vol. 127 No. 6, pp. 457-460.

Abdullahi, B.C. and Aziz, W.N. (2011), “The role of private sector participation in achieving anticipatedoutcomes for low-income group: a comparative analysis of housing sector between Malaysia andNigeria”, African Journal of Business Management, Vol. 5 No. 16, pp. 6859-6890.

Abdul-Aziz, A.-R. and Kassim, P.J. (2011), “Objectives, success and failure factors of housing public–private partnerships in Malaysia”, Habitat International, Vol. 35 No. 1, pp. 150-157.

Adams, J.S. (1965), “Inequity in social exchange”, in Berkowitz, L. (Ed.), Advances in ExperimentalSocial Psychology, 2nd ed., Academic Press, New York, NY, pp. 267-299.

Agyenim-Boateng, C., Stafford, A. and Stapleton, P. (2017), “The role of structure in manipulating PPPaccountability”, Accounting, Auditing & Accountability Journal, Vol. 30 No. 1, pp. 119-144.

Akintoye, A. and Kumaraswamy, M. (2016), “Public private partnerships: a global review”, CIB SeriesTG72 Public Private Partnerships, Report for the International Council for Research andInnovation in Building and Construction, CIB General Secretariat, Delft, 32pp.

233

PPP in housingprojects

Page 104: Engineering, Construction and Architectural

Akintoye, A., Hardcastle, C., Beck, M., Chinyio, E. and Asenova, D. (2003), “Achieving best value inprivate finance initiative project procurement”, Construction Management and Economics,Vol. 21 No. 5, pp. 461-470.

Al Shareem, K.M., Yusof, N.A., Roosli, R. and Abdullah, A. (2014), “PPPs as a housing delivery foraffordable housing development in Yemen”, Journal Business Management Dynamics, Vol. 3No. 8, pp. 1-12.

Archer, M. (2003), Structure, Agency, and the Internal Conversion, Cambridge University Press,New York, NY.

Ardichvili, A., Page, V. and Wentling, T. (2003), “Motivation and barriers to participation in virtualknowledge-sharing communities of practice”, Journal of Knowledge Management, Vol. 7 No. 1,pp. 64-77.

Axinn, W.G. and Pearce, L.D. (2006), Mixed Method Data Collection Strategies, Cambridge UniversityPress, New York, NY.

Babatunde, S.O., Opawole, A. and Akinsiku, O.E. (2012), “Critical success factors in public-privatepartnership (PPP) on infrastructure delivery in Nigeria”, Journal of Facilities Management,Vol. 10 No. 3, pp. 212-225.

Baker, C. (2005), Cultural Studies: Theory and Practice, Sage, London.

Cameron, R. (2009), “A sequential mixed model research design: design, analytical and display issues”,International Journal of Multiple Research Approaches, Vol. 3 No. 2, pp. 140-152.

Chan, A.P., Scott, D. and Chan, A.P. (2004), “Factors affecting the success of a construction project”,Journal of Construction Engineering and Management, Vol. 130 No. 1, pp. 153-155.

Chan, A.P., Lam, P.T., Chan, D.W., Cheung, E. and Ke, Y. (2009), “Potential obstacles to successfulimplementation of public-private partnerships in Beijing and the Hong Kong specialadministrative region”, Journal of Management in Engineering, Vol. 26 No. 11, pp. 30-40.

Chan, A.P., Yeung, J.F., Calvin, C., Wang, S.Q. and Ke, Y. (2010), “Empirical study of risk assessmentand allocation of public-private partnership projects in China”, Journal of Management inEngineering, Vol. 27 No. 3, available at: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000049

Chan, D.W., Chan, A.P. and Lam, P.T. (2006), “A feasibility study of the implementation of publicprivate partnership (PPP) in Hong Kong”, in Baldwin, A., Hui, E. and Wong, F. (Eds),Proceedings of the CIB W89 BEAR 2006 International Conference on Construction Sustainabilityand Innovation, Hong Kong, 10-13 April.

Chediel, Z. (2012), “Opportunities and challenges of using public and private partnership in delivery ofwater service”, published Msc thesis, Mzumbe University, Morogoro.

Cheung, E., Chan, A.P. and Kajewski, S. (2012), “Factors contributing to successful public privatepartnership projects: comparing Hong Kong with Australia and the United Kingdom”, Journal ofFacilities Management, Vol. 10 No. 1, pp. 45-58.

Chileshe, N. (2016), “Critical success factors for managing infrastructure projects in Africa: a criticalreview and lessons learned”, in Mwanaumo, E., Musonda, I. and Muleya, F. (Eds), Proceedings ofthe 3rd International Conference on Infrastructure Development and Investment Strategies forAfrica (DII-2016), 31st August-2nd September, Livingstone, Zambia, pp. 82-93.

Chileshe, N. and Kikwasi, G.J. (2014), “Critical success factors for implemebtation of risk assessmentand management practices within the Tanzanian construction industry”, Engineering,Construction and Architectural Management, Vol. 21 No. 3, pp. 291-319.

Chileshe, N., Rameezdeen, R. and Hosseini, M.R. (2016), “Drivers for adopting reverse logistics in theconstruction industry: a qualitative study”, Engineering, Construction and ArchitecturalManagement, Vol. 23 No. 2, pp. 134-157.

Chileshe, N., Wilson, L., Zuo, J., Zillante, G. and Pullen, S. (2013), “Strategic risk assessment for pursuingsustainable business in the construction industry: diagnostic models”, in Wells, G. (Ed.),Sustainable Business- Theory and Practice of Business Under Sustainability Principles, EdwardElgar Publishing Limited, Cheltenham and Northampton, MA, pp. 155-177.

234

ECAM25,2

Page 105: Engineering, Construction and Architectural

Chou, J.-S. and Lin, C. (2012), “Predicting disputes in public-private partnership projects: classificationand ensemble models”, Journal of Computing in Civil Engineering, Vol. 27 No. 1, pp. 51-60.

Cronbach, L.J. (1951), “Coefficient alpha and the internal structure of tests”, Psychometrika, Vol. 16,pp. 297-334.

Cronk, B.C. (2012), How to Use SPSS: A Step-by-Step Guide to Analysis and Interpretation, 7th ed.,Pyrczak Pub., Glendale, CA.

Dairu, A. and Muhammad, R.S. (2015), “Critical success factors of public-private-partnership projects inNigeria”, ATBU Journal of Environmental Technology, Vol. 8 No. 2, pp. 52-63.

De Schepper, S., Haezendonck, E. and Dooms, M. (2015), “Understanding pre-contractual transactioncosts for public-private partnership infrastructure projects”, International Journal of ProjectManagement, Vol. 33 No. 4, pp. 932-946.

Debrah, Y.A. and Ofori, G. (2005), “Emerging managerial competencies of professionals in theTanzanian construction industry”, The International Journal of Human Resource Management,Vol. 16 No. 8, pp. 1399-1414.

Debrah, Y.A. and Ofori, G. (2006), “Human resource development of professionals in an emergingeconomy: the case of the Tanzanian construction industry”, The International Journal of HumanResource Management, Vol. 17 No. 3, pp. 440-463.

Doloi, H., Sawhney, A., Iyer, K.C. and Renata, S. (2012), “Analysing factors afecting delays inIndian construction projects”, International Journal of Project Management, Vol. 30 No. 4,pp. 479-489.

Easterbrook, S., Singer, J., Storey, M.-A. and Damian, D. (2008), “Selecting empirical methods forsoftware engineering research”, in Shull, F., Singer, J. and Sjoberg, D. (Eds), Guide to AdvancedEmpirical Software Engineering, Springer, London, pp. 285-311.

El-Gohary, N.M., Osman, H. and El-Diraby, T.E. (2006), “Stakeholder management for public privatepartnerships”, International Journal of Project Management, Vol. 24 No. 7, pp. 595-604.

Forza, C. (2002), “Survey research in operations management: a process-based perspective”,International Journal of Operations & Production Management, Vol. 22 No. 2, pp. 152-194.

Giddens, A. (1984), The Constitution of Society: Outline of the Theory of Structuration, University ofCalifornia Press, Berkelery, CA.

Gunawansa, A. (2012), “Public-private partnerships for major infrastructure projects in developingcountries”, in Ofori, G. (Ed.), Contemporary Issues in Construction in Developing Countries,Spoon Press, Taylor & Francis, London, pp. 22-60.

Halcomb, E. and Hickman, L. (2015), “Mixed methods research”, Nursing Standard: PromotingExcellence in Nursing Care, Vol. 29 No. 32, pp. 41-47.

Hashim, H.A., Sapri, M. and Low, S.-T. (2016), “Public private partnership (PPP) facilities managementfor healthcare services in Malaysia: the challenges of implementation”, Journal of FacilitiesManagement, Vol. 14 No. 4, pp. 350-362.

Holt, G.D. (2014), “Guest editorial – asking questions, analysing answers: relative importance revisted”,Construction Innovation: Information, Process Management, Vol. 14 No. 1, pp. 2-16.

Holt, G.D. and Goulding, J.S. (2014), “Conceptualisation of ambiguous-mixed-methods within buildingand construction research”, Journal of Engineering, Design and Technology, Vol. 12 No. 2,pp. 244-262.

Hwang, B.-G., Zhao, X. and Gay, M.J.S. (2013), “Public private partnership projects in Singapore:factors, critical risks and preferred risk allocation from the perspective of contractors”,International Journal of Project Management, Vol. 31 No. 3, pp. 424-433.

Ibem, E.O. (2011a), “The contribution of public-private partnerships (PPPs) to improving accessibilityof low-income earners to housing in southern Nigeria”, Journal of Housing and the BuiltEnvironment, Vol. 26 No. 2, pp. 201-217.

Ibem, E.O. (2011b), “Public-private partnership (PPP) in housing provision in Lagos Megacity Region,Nigeria”, International Journal of Housing Policy, Vol. 11 No. 2, pp. 133-154.

235

PPP in housingprojects

Page 106: Engineering, Construction and Architectural

Ibem, E.O. and Aduwo, B. (2012), “Public-private partnerships (PPP) in housing provisions inOgun State, Nigeria: opportunities and challenges”, in Laryea, S., Agyepong, S.A., Leiringer, R.and Hughes, W. (Eds), Proceedings 4th West Africa Built Environment Research (WABER)Conference, 24-26 July, Abuja, pp. 653-662.

Ibrahim, A.D., Price, A.D.F. and Dainty, A.R.J. (2006), “The analysis and allocation of risks in publicprivate partnership in infrastructure projects in Nigeria”, Journal of Financial Management ofProperty and Construction, Vol. 11 No. 3, pp. 149-163.

Ismail, S. (2013), “Critical success factors of public private partnership (PPP) implementation inMalaysia”, Asia-Pacific Journal of Business Administration, Vol. 5 No. 1, pp. 6-19.

Ismail, S. and Haris, F.A. (2014), “Constraints in implementing public private partnership (PPP) inMalaysia”, Built Environment Project and Asset Management, Vol. 4 No. 3, pp. 238-250.

Jamali, D. (2004), “Success and failure mechanisms of public private partnerships (PPPs) in developingcountries: insights from the Lebanese contex”, International Journal of Public SectorManagement, Vol. 17 No. 2, pp. 414-430.

Jefferies, M., Gameson, R. and Rowlinson, S. (2002), “Critical success factors of the BOOT procurementsystem: reflections from the Stadium Australia case study”, Engineering Construction andArchitectural Management, Vol. 9 No. 4, pp. 352-361.

Jogulu, U.D. and Pansiri, J. (2011), “Mixed methods: a research design for management doctoraldissertations”, Management Research Review, Vol. 34 No. 6, pp. 687-701.

Kavishe, N. (2010), “The performance of public private partnership in delivering houses in Tanzania(The case of the National Housing Corporation)”, unpublished MSc thesis, Department ofBuilding Economics, Ardhi University, Dar es Salaam.

Kavishe, N. and An, M. (2016), “Challenges for implementing public private partnership in housingprojects in Dar es Salaam City, Tanzania”, in Chan, P.W. and Neilson, C.J. (Eds), Proceedings ofthe 32nd Annual ARCOM Conference, 5-7 September, Vol. 2, Association of Researchers inConstruction Management, Manchester, pp. 931-940.

Kidata, A.J. (2013), “A brief of urbanisation in Tanzania”, presented to 2013 Resilient Cities Conferences,Prime Minister’s Office Regional Administration and Local Government, Bonn, 1 June.

Kikwasi, G.J. (1999), “The selection of project procurement system in the Tanzanian constructionindustry”, unpublished masters dissertation, University of Dar es Salaam, Dar es Salaam.

Kikwasi, G.J. (2012), “Causes and effects of delays and disruptions in construction projects inTanzania”, in Chileshe, N. et al. (Eds), Proceedings of the 6th International Conference andWorkshop on Built Environment in Developing Countries ‘Fragmented Futures: the builtenvironment in a volatile world, 4th-5th December, University of South Australia, Adelaide,pp. 138-148.

Kothari, C.R. (2004), Research Methodology: Methods and Techniques, New Age International,New Delhi, 418pp.

KPMG (2010), “PPP procurement: Review of barriers to competition and efficiency in the procurement ofPPP projects”, available at: www.kpmg.com/NZ/en/IssuesAndInsights/ArticlesPublications/SmarterProcurement/Documents/Review-of-barriers-to-compeition.pdf (accessed 31 October 2016).

Kurniawan, F., Ogunlana, S. and Motawa, I. (2014), “Stakeholders’ expectations in utilising financialmodels for public-private partnership projects”, Built Environment Project and AssetManagement, Vol. 1 No. 1, pp. 4-21.

Kwofie, T.E., Afram, S. and Botchway, E. (2016), “A critical success model for PPP public housingdelivery in Ghana”, Built Environment Project and Asset Management, Vol. 6 No. 1, pp. 58-73.

Leventhal, G.S. (1980), “What should be done with equity theory? New approaches to the study offaireness in social relationships”, in Gergen, K., Greenberg, M. and Willis, R. (Eds), SocialExchange: Advances in Organizatonal Justice, Stanford University Press, Stanford, CA, pp. 56-88.

Li, B., Akintoye, A., Edwards, P.J. and Hardcastle, C. (2005), “Critical success factors for PPP/PFIprojects in the UK construction industry”, Construction Management and Economics, Vol. 23No. 2, pp. 459-471.

236

ECAM25,2

Page 107: Engineering, Construction and Architectural

Ling, F.Y.Y. and Nguyen, D.S. (2013), “Strategies for construction waste management in Ho Chi MinhCity, Vietnam”, Built Environment Project and Asset Management, Vol. 3 No. 1, pp. 141-156.

Liu, T. and Wilkinson, S. (2011), “Adopting innovative procurement techniques: obstacles and driversfor adopting public private partnerships in New Zealand”, Construction Innovation, Vol. 11No. 4, pp. 452-469.

Liu, T., Chan, A. and Wang, S. (2014), “PPP framework for public rental housing projects in China”,Bridges, Vol. 10, pp. 9780784413777-9780784413067.

Maxwell, J.A. (2005), Qualitative Research Design: An Interactive Approach, Vol. 14, Sage, London.

Mboya, J.R. (2013), “PPP Country Paper-Tanzania”, paper submitted to SADC-DFRC 3P NETWORKPublic-Private-Partnership Working Group, Limesstrasse 26, 61273 Wehreim, Wehrheim,available at: www.sadcpppnetwork.org/wp-content/uploads/2015/02/tanzania_27012014.pdf(accesesd 19 November 2016).

Mitchell, D. (2007), “Capacity development for partnerships in South Africa; increasing service deliverythrough partnerships between private and public sector”, report on Findings of NeedsAssessment, available at: http://thepartneringinitiative.org/wp-content/uploads/2014/08/PPP-overview-and-needs-assessment.pdf (accessed June 2016).

Molina-Azorin, J.F., Bergh, D.D., Corley, K.G. and Ketchen, D.J. (2017), “Mixed methods in theorganizational sciences: taking stock and moving forward”, Organizational Research Methods,Vol. 20 No. 2, pp. 179-192.

Morledge, R. and Owen, K. (1998), “Critical success factors in PFI projects”, 14th Annual ARCOMConference, pp. 9-11.

Moskalyk, A. (2011), Public-Private Partnerships in Housing and Urban Development, UN-HABITAT,Nairobi.

Mouraviev, N. and Kakabadse, N.K. (2012), “Conceptualising public-private partnership: a criticalappraisal of approaches to meanings and forms”, Society and Business Review, Vol. 7 No. 3,pp. 240-276.

Narasimhan, C.V. (1997), “Prevention of corruption: towards effective enforcement”, in Guhan, S. andPaul, S. (Eds), Corruption in India: Agenda for Action, Chapter 10, Vision Books, New Delhi,pp. 251-265.

National Housing Corporation (NHC) (2010), “The National Housing Corporation Strategic Plan for2010/11-2014/15”, National Housing Corporation.

Ngowi, H.P. (2006), “Public-private partnerships (PPPS) in the management of municipalities inTanzania: issues and lessons of experience”, African Journal of Public Administration andManagement, Vol. 17 No. 2, pp. 29-31.

Nguyen, T.P. and Chileshe, N. (2015), “Revisiting the construction project failure factors in Vietnam”,Built Environment Project and Asset Management, Vol. 5 No. 4, pp. 398-416.

Nkya, E. (2004), “Public-private partnership and institutional arrangements: constrianted improvementof solid waste management in Dar es Salaam”, Uongozi Journal of Management Development,Vol. 16 No. 1, pp. 1-21.

Nunnally, J. (1978), Psychometric Theory, 2nd ed., McGraw-Hill, New York, NY.

Osabutey, E.L.C., Nyuur, R.B.a. and Debrah, Y.A. (2012), “Human resource development inconstruction”, in Ofori, G. (Ed.), New Perspective on Construction in Developing Countries, SpoonPress, Taylor & Francis, London, pp. 229-252.

Osei-Kyei, R. and Chan, A.P.C. (2015), “Review of studies on the critical success factors forpublic-private partnership (PPP) projects from 1990 to 2013”, Internnational Journal of ProjectManagement, Vol. 33 No. 6, pp. 1335-1346.

Project Management Institute (2008), A Guide to the Project Management Body of Knowledge, ProjectManagement Institute, Newtown Square, PA.

Qu, S.Q. and Dumay, J. (2011), “The qualitative research interview”, Qualitative Research in Accounting& Management, Vol. 8 No. 3, pp. 238-264.

237

PPP in housingprojects

Page 108: Engineering, Construction and Architectural

Rwelamila, P.D., Talukhaba, A.A. and Ngowi, A.B. (1999), “Tracing the African project failuresyndrome: the significance of Ubuntu”, Engineering, Construction and ArchitecturalManagement, Vol. 6 No. 4, pp. 335-346.

Scheer, L.K., Kumar, N. and Steenkamp, J.-B.E. (2003), “Reactions to perceived inequity in US and Dutchinterorganisational relations”, Academy of Management Journal, Vol. 46 No. 3, pp. 303-316.

Sengupta, U. (2006), “Government intervention and public-private partnerships in housing delivery inKolkata”, Habitat International, Vol. 30 No. 3, pp. 448-461.

Sharifirad, M.S. (2011), “The Dimensions of Learning Organization Questionnaire (DLOQ): a cross-cultural validation in an Iranian context”, International Journal of Manpower, Vol. 32 Nos 5/6,pp. 661-676.

Sharma, S. (2012), “Determinants of PPP in infrastructure in developing economies”, TransformingGovernment: People, Process and Policy, Vol. 6 No. 2, pp. 149-166.

Smith, H.W. (2015), “Population growth, internal migration, and urbanisation in Tanzania”, 1967-2012Phase 2 ( final report), London.

Stevenson, R., Potts, K. and Houlton, L. (1994), “Joint venture vehicles in property development”,Property Management, Vol. 12 No. 2, pp. 16-21.

Tabish, S.Z.S. and Jha, K.N. (2011), “Analyses and evaluation of irregularities in public procurement inIndia”, Construction Management and Economies, Vol. 29 No. 3, pp. 261-274.

Tang, L.Y., Shen, Q. and Cheng, E.W.L. (2010), “A review of studies on public-private partnershipprojects in the construction industry”, International Journal of Project Management, Vol. 28No. 7, pp. 683-694.

Trangkanont, S. and Charoenngam, C. (2014a), “Critical failure factors of public-private partnershiplow-cost housing program in Thailand”, Engineering Construction and ArchitecturalManagement, Vol. 21 No. 4, pp. 421-443.

Trangkanont, S. and Charoenngam, C. (2014b), “Private partner’s risk response in PPP low-costhousing projects”, Property Management, Vol. 32 No. 1, pp. 67-94.

Tutesigensi, A. and Mohammad, S.A. (2008), “Framework for introducing the private finance initiativein Brunei Darussalam construction industry”, Proceedings of 24th Annual ARCOM Conference,Association of Researchers in Construction Management, pp. 497-506.

Ukoje, J.E. and Kanu, K.U. (2014), “Implementation and the challenges of the mass housing schemein Abuja, Nigeria”, American International Journal of Contemporary Research, Vol. 4 No. 4,pp. 209-218.

UN-HABITAT (2011), “Public-private partnerships in housing and urban development, United NationsHuman Settlements Programme 2011”, United Nations HABITAT Information Services Section,available at: http://unhabitat.org/public-private-partnership-in-housing-and-urban-development/(accessed 11 January 2017).

United Nations for Economic and Social Commission for Asia and the Pacific (2012), “PPP readinessself-assessment”, available at: www.unescap.org/ttdw/ppp/PPPReadiness.html (accessed 10October 2013).

URT (2009), “National Public Private Partnership (PPP) Policy”, Prime Minister’s Office, GovernmentPrinter, Dar es Salaam.

Vivek, S.D. and Richey, R.G. (2013), “Understanding performance of joint ventures: modelling theinteractional strength of fit between partners”, The International Journal of LogisticsManagement, Vol. 34 No. 3, pp. 356-379.

Wibowo, A. and Alfen, H.W. (2015), “Government-led critical success factors in PPP infrastructuredevelopment”, Built Environment Project and Assest Management, Vol. 5 No. 1, pp. 121-134.

World Bank (1992), “International Finance Corporation (IFC): investing in the environment: businessopportunities in developing countries”, Washington, DC, available at: http://documents.worldbank.org/curated/en/902851468766477131/International-Finance-Corporation-IFC-investing-in-the-environment-business-opportunities-in-developing-countries (accessed 12 June 2014).

238

ECAM25,2

Page 109: Engineering, Construction and Architectural

World Bank (2016), “Tanzania economic update the road less travelled unleashing public privatepartnerships in Tanzania”, Africa Region Macroeconomics and Fiscal Management GlobalPractice, No. 8, May, Washington, DC, available at: www.worldbank.org/tanianla/economicupdate (accessed 2 February 2017).

Yalegama, S., Chileshe, N. and Ma, T. (2016), “Critical success factors for community -drivendevelopment projects: a Sri Lankan community perspective”, International Journal of ProjectManagement, Vol. 34 No. 1, pp. 643-659.

Zhang, X. (2005a), “Critical success factors for public–private partnerships in infrastructuredevelopment”, Journal of construction engineering and management, Vol. 131 No. 1, pp. 3-14.

Zhang, X. (2005b), “Paving the way for public-private partnerships in infrastructure development”,Journal of Construction, Engineering and Management, Vol. 131 No. 1, pp. 71-80.

Zhang, Z. and Jia, M. (2010), “Procedural fairness and cooperation in public-private partnerships inChina”, Journal of Managerial Psychology, Vol. 25, pp. 513-538.

Further reading

Abdul-Aziz, A.-R. (2012), “Control mechanisms exercised in Malaysian housing public-privatepartnerships”, Construction Management and Economics, Vol. 30 No. 1, pp. 37-55.

Abowitz, D.A. and Toole, T.M. (2010), “Mixed method research: fundamental issues of design, validity,and reliability in construction research”, Journal of Construction Engineering and Management,Vol. 136 No. 1, pp. 108-116.

Dixon, T., Pottinger, G. and Jordan, A. (2005), “Lessons from the private finance initiative in the UK:benefits, problems and critical success factors”, Journal of Property Investment & Finance,Vol. 23 No. 5, pp. 412-423.

Itika, J., Mashindano, O. and Kessy, F.L. (2011), “Successes and constraints for improving public-private parternship in health services delivery in Tanzania”, Paper No. 36, The Economic andSocial Research Foundation (ESRF), Dar es Salaam.

Maagi, J. (2010), “Evaluation of the effectiveness of national housing corporation joint ventureprojects”, unpublished dissertation, Ardhi University, Dar es Salaam.

NHC (2006), “Joint Venture Policy”, National Housing Corporation, Dar es Salaam.

Susilawati, C. and Armitage, L. (2004), “Do public-private partnerships facilitate affordable housingoutcome in Queensland?”, Australian Property Journal, pp. 1-9.

World Bank and PPIAF (2007), “Public-private partnership units. Lessons for their Design and use ininfrastructure”, World Bank and PPIAF, Washington, DC.

About the authorsNeema Kavishe is currently a PhD Student at the School of Engineering, University of Birmingham.Since 2010, she has also been an Assistant Lecturer at Ardhi University (Dar es Salaam). She received aMaster’s Degree in Construction Economics and Management from Ardhi University in 2010.Apart from lecturing, she also worked as an Assistant Quantity Surveyor with Webb Uronu andPartners Ltd (Tanzania). Neema’s current research interests include public-private partnership,construction management, project management and housing.

Ian Jefferson is a Professor of Geotechnical Engineering, the Head of Education, School ofEngineering, University of Birmingham, Birmingham, UK. Jefferson has over 25-year experienceworking on ground-related hazards, sustainability and resilience, with particular emphasis on urbandevelopments. His current projects include Assessing the Underworld, where he leads the developmentof sustainability costing model, and is a Co-investigator dealing with infrastructure business models,valuation and innovation for local delivery. He has raised over £16 million from various researchactivities from research councils to industry, coupled with over 110 referred publications. He is amember of a number of international organisation/committee dealing with sustainability, includingMember of TC307 on Sustainable Geotechnics of the International Society of Soil Mechanics andGeotechnical Engineering.

239

PPP in housingprojects

Page 110: Engineering, Construction and Architectural

Nicholas Chileshe is an Associate Professor in Construction and Project Management in the Schoolof Natural and Built Environment at the University of South Australia. He is also the ResearchEducation and Portfolio Leader and Programme Director responsible for the Doctorate in ProjectManagement. Nicholas received the PhD Degree in Construction Management from the SheffieldHallam University in 2004. Chileshe was a Fellow of the Chartered Institute of Building (FCIOB)(1999-2016), Fellow of the Australian Institute of Building (FAIB), Fellow of the Chartered Associationof Building Engineers (FCABE), Chartered Building Engineer (C. Build E), Fellow of the HigherEducation Academy (FHEA), Member of the Chartered Institute of Management (MICM), and Memberof the Australian Institute of Project Management (MAIPM). Nicholas’s ongoing professionalinvolvement includes membership and Chair of the Australasian Education Committee, and the CIOBInternational Accreditation Panel; and he has acted as a PhD External Examiner for Universities inSouth Africa and Australia. He also regularly reviews proposals for the National Research Foundation(NRF) in South Africa, and the Higher Education Academy (UK). His current research interests includetotal quality management, supply chain management, reverse logistics, sustainability, constructionmanagement, risk and value management, project management and project success. Nicholas Chilesheis the corresponding author and can be contacted at: [email protected]

For instructions on how to order reprints of this article, please visit our website:www.emeraldgrouppublishing.com/licensing/reprints.htmOr contact us for further details: [email protected]

240

ECAM25,2

Page 111: Engineering, Construction and Architectural

A comparison of the suitability ofFIDIC and NEC conditionsof contract in PalestineA perspective from the industry

Haytham Besaiso, Peter Fenn, Margaret Emsley and David WrightSchool of Mechanical, Aerospace, and Civil Engineering,

The University of Manchester, Manchester, UK

AbstractPurpose – The standard forms of construction contract are receiving greater attention in the management ofprojects scholarship as they probably influence the project success and project disputes. The extant literaturesuggests that the standard forms of construction contract are one of the top sources of disputes. The purposeof this paper is to examine the effectiveness of the standard forms of construction contract, FIDIC and NEC,in reducing disputes in the Palestinian construction industry.Design/methodology/approach – The researchers have used qualitative methods to collect data and morespecifically have undertaken 12 semi-structured interviews.Findings – The study reveals that the standard forms of construction contract can be a tool to minimisedisputes, but certainly not to eradicate them, and NEC appears to be more capable than FIDIC to do so.Originality/value – This study contributes to knowledge by bringing an industrial perspective into the roleof standard forms of contract in disputes creation and avoidance. The interviewees, recurrent users of FIDICcontract, criticised certain features and expressions and proposed some solutions.Keywords Construction, Interview, Project management, International constructionPaper type Research paper

1. IntroductionConstruction disputes are an important area for academics trying to understand whyconstruction contracts go wrong. Constructions disputes are problematic, unpleasant,and dysfunctional, destroy client-supplier business relationship, costly, and may lead tocost/time overrun (Fenn, 2012). The literature includes a growing body of scientificresearch investigating the role of contracts in dispute materialisation. For instance, Clegg(1992) proposed that, from a sociologist view, contracts cause conflict. Cheung and Pang(2012) argued that contracts are the root cause of all types of construction disputes.Specifically, Fenn et al. (1997) argued that one of the top factors creating disputes in theconstruction industry is standard form of construction contract. They empiricallycompared a wide range of standard forms of construction contract and concluded thatcertain contracts may cause more disputes than others. However, it is unknown howstandard forms of contracts may contribute differently to the formation and evolution ofdisputes. Therefore, this research theoretically and empirically examine this notion bycomparing the effectiveness of FIDIC and NEC standard forms of construction contract inminimising disputes.

The choice of FIDIC and NEC contracts in this research is based on three-folds. First, thefundamental aim behind drafting and bringing NEC into life is to resolve the problem ofdisputes arising and the adversarial behaviour in construction. Indeed, the Palestinianconstruction industry suffers from the adversarial relationships between constructionparties and the increasing level of disputes (Enshassi, Choudhry and EL-Ghandour, 2009).Second, infrastructure and construction projects are implemented by the government or byforeign or international employers. The government uses FIDIC (1999) conditions of

Engineering, Construction andArchitectural Management

Vol. 25 No. 2, 2018pp. 241-256

© Emerald Publishing Limited0969-9988

DOI 10.1108/ECAM-10-2016-0235

Received 14 November 2016Revised 22 February 2017

Accepted 8 April 2017

The current issue and full text archive of this journal is available on Emerald Insight at:www.emeraldinsight.com/0969-9988.htm

241

Suitability ofFIDIC and

NECconditions

Quarto trim size: 174mm x 240mm

Page 112: Engineering, Construction and Architectural

contract[1] and many foreign or international employers or organisations financingconstruction projects use FIDIC such as the World Bank, the Asian Development Bank, theIslamic Bank for Development, the European Commission, and different United Nationsbodies (Aljarosha, 2008; Swiney, 2007; Zhanglin and Yuli, 2010). Yet, some of theseorganisations are testing the potential usage of NEC instead of FIDIC in their projects. Forinstance, the Asian Development Bank and the UK’s Overseas Development Agency aretesting replacing FIDIC by NEC for their sponsored projects (Ndekugri and Mcdonnell,1999). Third, FIDIC is the most widely used international form of construction contract inthe world (Seifert, 2005). At the same time, the usage of NEC in the UK and 30 othercountries in the world is an indicator of its increasing popularity worldwide (Thompsonet al., 2000). This means that the research findings may be transferable to manyjurisdictions.

The remainder of the paper is structured as follows. First, five aspects of FIDICconditions of contract are compared and contrasted with those of NEC. This is followed bybrief explanations of the conceptual framework and the interviews which were carried outwith 12 professionals working in the Palestinian construction industry. The views andopinions of the interviewees with regards to the effectiveness of FIDIC and NEC in reducingdisputes in the Palestinian construction industry are then discussed prior to thepresentation of the conclusion.

2. FIDIC compared and contrasted with NECThis comparison is neither clause-to-clause nor is it claimed to be exhaustive andencyclopaedic. A comprehensive and holistic comparison between FIDIC suite of contractsand NEC suite of contracts is very ambitious and broad aim because there are manycontracts in each family. Therefore, the scope of this study is limited to FIDIC 99 Red Bookvs ECC3 (NEC3 Engineering and Construction Contract). Further, the study concentrates onthe five most important aspects that normally give rise to construction disputes in Palestine,as the available literature suggests. These include disputes arising from misunderstandingand misinterpretation of contract conditions written in English, and onerous terms(i.e. unfair risk allocation) (Enshassi, Mohamed and El-Ghandour, 2009; Murtaja, 2007;Enshassi, 1999), variation orders (Abedmousa, 2008), the lack of trust between contractorsand engineers (Saqfelhait, 2012) that creates an adversarial environment in which one of themost important factors determining bid-no-bid and mark up decisions are “project engineer”(Enshassi et al., 2010) in addition to the endemic volatile and unstable political environment(e.g. borders’ closures, blockade, and hostilities) that leads to cost and time overruns(El-Sawalhi and El-Riyati, 2015; Enshassi, Mohamed and El-Ghandour, 2009).

2.1 Clarity and simplicityChong and Zin (2009) argued that one of the main causes of disputes is misunderstandingand misinterpretation of contract clauses and the preventive solution lies in the use of plainEnglish. Clarity is important to ensure that all parties of a contract understand what theyare getting themselves into, their rights and obligations, and the risk apportionment andthus what risks they bear.

FIDIC has been criticised for using obscure, complicated, inscrutable, and legal languagethat has phrases traced back to contracts of the nineteenth century in England (Broomeand Hayes, 1997). In addition, FIDIC’s poor layout, long sentences, and substantialcross-referencing make it difficult to understand (Cutts and Maher, 1986; Wydick, 1978).Nevertheless, it is important while reviewing these critiques to consider their time context,as they were written prior to or just after the release of FIDIC (1987). It worth mentioningthat one of the objectives behind drafting the FIDIC (1999) Rainbow edition was to simplifythe language. However, it is uncertain whether FIDIC has been completely successful in this

242

ECAM25,2

Page 113: Engineering, Construction and Architectural

aim. Probably, FIDIC has been improved much from its earlier editions and has movedtowards fewer clauses and clearer language and contract structure, but the real judgment isleft to its users. Indeed, this area is a worthwhile investigation for further research.

NEC is different from FIDIC as one of its three declared objectives is to minimise theincidences of disputes arising from unclear language. NEC uses non-legalistic ordinaryunequivocal language, straightforward, simple and plain English, short sentences (with nomore than 40 words), a bulleted structure and avoidance of confusing cross-references.Also, there are guidance notes and flow charts to assist in the understanding of how tocreate and operate the contract (Eggleston, 2006; Gould, 2007; Li, 2006). The abandoning of“legal language” is a revolutionary step by the NEC drafters which is much debated.The drafters claim that they sacrificed legal concepts in the interests of better managementof projects. This makes the language more understandable to builders at site level(Lavin and Potts, 1998; Li, 2006). Moreover, it saves time and money paid to lawyers totranslate the contract to legal phrases, and then translate it back to users so they know whatit means (Abrahamson, 1979). On the other hand, the main criticism of this approach is thatit discards the accumulated contractual wisdom of generations, reinvents the wheel, andreduces the legal certainty which could increase the chance of contractual disputes(Eggleston, 2006; Valentine, 1996).

To sum up, the research acknowledges that NEC is not perfect, but it is a considerableimprovement in clarity compared to FIDIC. Indeed, what is required to avoid disputes is clearEnglish, and certainly not a long history of case law and judicial precedents on a particularclause or phraseology. To avoid disputes in the first place, people at the site level should be ableto understand the conditions, and not need to memorise a dozen cases about particular clauses.

2.2 Risk allocation and managementIt is inherent for any project, particularly in the construction industry, to involve risks.It is not possible to eliminate all risks, but what can be done is to allocate the risks to thevarious parties who then manage them (Kozek and Hebberd, 1998). The standard forms ofconditions of contract provide a framework to regulate the process of risk allocation bydefining the rights and obligations of both parties.

Both FIDIC and NEC attempt to allocate risks fairly and reasonably between theemployer and the contractor (Ndekugri and Mcdonnell, 1999). The basic principle to achievethis is by allocating the risk to the party best able to control and manage the risk event andbear the risk consequences (Bunni, 2005; Eggleston, 2006; Potts, 2008; Williams, 2001).

FIDIC is based on the principle of balanced risk sharing and has been widely accepted byemployers and contractors as a reasonable compromise (Bunni, 2005; Osinski, 2002).The employer bears only the risk of unforeseen negative conditions that are not offset byunforeseen positive conditions. This means that there is less chance for contractors to gettime extensions and cost compensation for unforeseen events since they have to beunforeseen, and if they are, they need to be offset by other favourable conditions. At firstglance, FIDIC’s new philosophy of “conditions-balancing” seems fair, equitable, anddesirable and similar to pain/gain partnering arrangements. However, it potentiallyincreases disputes because it provides the parties with more things to argue about, whichcould be costly and impossible to settle (Swiney, 2007).

Unlike FIDIC, NEC recognises that the standard form should not only be a mechanismfor risk allocation, but also for a proactive and dynamic risk management. NECacknowledges that an important part of risk management is effective communicationbetween the parties. This includes risk registers, risk prevention, early warning, and riskreduction meetings (Wassenaer, 2009).

The controversy and comparison between NEC and FIDIC regarding this area hinges ontwo views on the purpose of a standard form of construction contract. Should the standard

243

Suitability ofFIDIC and

NECconditions

Page 114: Engineering, Construction and Architectural

form be a manual for project management procedures and practices or an agenda for legalactions? FIDIC tends to be skewed towards the latter narrow view of a contract, as it isprincipally designed to focus more on the risks, liabilities, obligations, and responsibilities ofthe parties (Heaphy, 2011). Therefore, the parties will use the contract when things go wrongor disputes surface in an attempt to find a clause that will support their contractual positionor justify a claim or to allocate blame (Brown, 2000; Eggleston, 2006). NEC is radicallydifferent from FIDIC in that it focuses on informed, proactive and foresight-basedmanagement and decision making, rather than a reactive and hindsight-based negativeapproach. Collaboratively applied foresight mitigates problems, shrinks risks andadversarial behaviour, and removes most of the grounds for disputes (Lavin and Potts,1998). However, focusing on the management side at the expense of the legalistic andcontractual side could produce an “obligationally incomplete” contract (Eggleston, 2006;Hughes and Maeda, 2002).

Apparently, NEC has been more successful than FIDIC in expanding standard forms’role towards risks. NEC manages risks proactively and dynamically, and, unlike FIDIC, isnot only concerned about risk allocation.

2.3 Force majeure and prevention eventsForce majeure events are of a great importance, particularly under the unstable conditionsin Palestine. The legal definition and interpretation of the events may vary from country tocountry, and from one jurisdiction to another, which will accordingly lead to different legalconsequences. Therefore, most standard forms, including FIDIC and NEC, cover thesematters by express terms (Eggleston, 2006; Jaeger and Hök, 2010). FIDIC clause 19.1 definesforce majeure events to be:

• beyond a party’s control;

• could not reasonably be provided against before entering into the contract;

• having arisen, could not reasonably be avoided or overcome; and

• are not substantially attributable to the other party.

Indeed, clause 19.1 provides a non-exhaustive list, including events such as war, terrorism,riots, and natural disasters. The above definition of a force majeure event is entirelyopen-ended, such that a human-caused event would be covered if it met the above criteria.This gives more risk to the employer as he bears the cost and time impacts (Swiney, 2007).Jaeger and Hök (2010) criticised the ambiguity of the extent of the contractor’s entitlementto an extension of time, and loss and expense, as to whether it covers direct andindirect consequences of the event. It is worth mentioning that a force majeure event doesnot need to pass the “unforeseeability” test. This means even if an event is foreseeable,it will be considered force majeure as long as it is beyond the control of the parties( Jaeger and Hök, 2010).

NEC 3 has introduced a new clause (clause 19.1) called “prevention” under which theemployer bears the time and cost risks of events similar to, but potentially wider than,force majeure. Clause 19.1 defines a prevention event as an event which:

• stops the contractor completing the works;

• stops the contractor completing the works by the date shown on the acceptedprogramme;

• neither party could prevent; and

• an experienced contractor would have judged at the contract date to have had such asmall chance of occurring that it would have been unreasonable to have allowed for it.

244

ECAM25,2

Page 115: Engineering, Construction and Architectural

Eggleston (2006) criticised this clause as it opens the door for a very wide interpretationbecause its definition goes well beyond what is adopted in law as force majeure.For instance, a contractor may argue that insolvency of suppliers or the supply of defectivematerials, works, and designs by others had a small chance of occurring and could not havebeen prevented by either party. He also critiqued the words “small chance” and“unreasonable” which are difficult tests to examine in dispute resolution proceedings,and would indicate the event to be one of “prevention” even though it was foreseeable, thesame as FIDIC. Furthermore, the “prevention” clause seems to apply to delay events whichare endemic and it does not make sense that the clause operates for each and every delayingevent (Eggleston, 2006).

To sum up, both FIDIC and NEC share the same philosophy of transferring the risk offorce majeure events to the employer to avoid padding the tender prices by contractors. Itappears that both FIDIC and NEC fail to provide a decisive and conclusive definition of whatconstitutes a force majeure or prevention situation. The problem with the force majeuredefinition is that people do not know what might happen, so that they always struggle todefine it. This could cause disputes as a notice of force majeure would be rejected by thedefendant denying the existence of this event, and in turn suing the claimant or plaintiff fora breach of contract. Bunni (2005) stated that not covering these exceptional events in theconditions of contract, and leaving them to the applicable law in the relevant jurisdictionwould reduce the likelihood of conflicts. However, not covering them at all will make theresort to litigation inevitable, which is not desirable.

2.4 VariationsAccording to Seppala (1991), the inevitable variations are the second major area giving riseto claims under FIDIC. FIDIC is unable to cope with significant variations because it isessentially a re-measurement contract that assumes the project scope is well defined prior toletting the tender documents. FIDIC (1999) sub-clause 12.3 limits variations of items to10 per cent by quantity and other criteria which necessitate new rates to be agreed.The process of determination of the new rates, whereby a contractor submits a proposal andthen the engineer determines suitable prices, is a rigorous and tough process that inevitablywill lead to disagreement and dispute.

FIDIC details that a change is to be valued at the same or by considering rates and pricesset out in the contract, or the engineer agrees new suitable rates and prices through theprocedure of “due consultation” with the employer and the contractor. If no agreement isreached, the last resort is determining the appropriate prices by the engineer.This procedure assumes that the value will be calculated after the variation or changehas been carried out (FIDIC, 1999; Forward, 2002).

On the other hand, FIDIC introduces a new innovation allowing contractors to initiatevariations under a “Value Engineering” clause. The contractor may submit a proposal,which needs the approval of the engineer to proceed, to increase efficiency, reduce cost andtime etc. to the benefit of the employer (FIDIC, 1999). Obviously, this feature encouragescollaboration and partnering, and it should have been introduced within NEC.

Normally, standard forms make it clear via express terms that the contractor is obligedto perform variations. NEC does not recognise the phrase “variations” or “changes”, butaddresses them indirectly through Clause 14.3 (instructions) which serves as the variationclause (Eggleston, 2006). Although there is no explicit limit to changes, Clause 12.3 tends tolimit them by stating that no change to the contract has effect unless it is provided for in theconditions of contract or unless it has been agreed, confirmed in writing, and signed bythe parties (Eggleston, 2006).

NEC provides for pre-pricing a variation/change before it is carried out. This means thatthe instruction – variation order or change order – by the client will at first be an instruction

245

Suitability ofFIDIC and

NECconditions

Page 116: Engineering, Construction and Architectural

to submit a price (quotation) for the work, which, if accepted, will be followed by aninstruction to carry out the work (Eggleston, 2006). This is beneficial for both parties.The client can decide whether to go ahead or not based on the price. The contractor ensuresthe price of the work is accepted and thus avoids disputes. Yet, the drawback of the NECsystem could be a delay in reaching an agreement on the price, and in turn a delay to theproject activities.

In summary, FIDIC tries to avoid disputes by minimising variations to a certain limitafter which a new process should be agreed. However, the process of price determination isstill problematic. On the other hand, NEC is very flexible as it does not limit variations, but itrequires pre-pricing and quotations that fix the prices before commencing the variation.Overall, it is obvious that both use different approaches to tackle the same problem, butNEC tends to be more successful, as what really does matter, at the end of the day, is priceagreement and not the 10 per cent limit on quantity or some other constraint.

2.5 The role of the engineer vis-à-vis the project managerThe aim of this section is to critically examine and compare the role of the engineer underFIDIC with the project manager under NEC.

Under the FIDIC’s old Red Book, the engineer has two main duties. First, he is theemployer’s agent for design, supervision of the works’ construction and execution, andcontract administration. Second, he is a neutral and independent third party responsible todecide and determine the contractor’s claims for additional payment or extensions of time,and to resolve disputes fairly between the contractor and the employer (Seppala, 1991).

The employer is responsible for the engineer’s default in the first group of duties and inturn may be in breach of contract, but he is not responsible for the engineer’s performance inrespect of the second group of duties, except in the case of total failure to perform theseduties. The duality of the role of the engineer as the employer’s agent and a neutral thirdparty is much criticised because of the conflict of interests in his duties. For example, theengineer may be the cause of problems like design errors and delays in making decisions.Moreover, he is appointed and paid by the employer and may seek future work with him, orat least avoid being sacked (Ndekugri et al., 2007; Seppala, 1991).

NEC resolves these problems, or tries to resolve it, by splitting the engineer’s role intofour entities: the project manager, supervisor, designer, and adjudicator. All these roles areagents of the employer except the adjudicator. The project manager is required to make theplans, administer the contract, certify and value payments, etc. with a main mission to getthe project delivered on time and within budget. The supervisor is concerned with thequality of works and defects. Those two roles can be combined and occupied by one person(Eggleston, 2006). It is important to keep in mind that the new roles of the engineer underNEC, compared to other forms, would encourage engineers not to recommend such astandard form that considerably reduces their own authority and workload (Lavin andPotts, 1998).

The project manager is the representative of the employer and works on his behalf.There is no express requirement in NEC provisions obligating the project manager to beimpartial. However, some routine tasks and activities such as issuing certificates, andvaluing compensation events seem to require impartiality and fairness. As a certifier andvaluer, the project manager shall not work to secure the employer’s interests. This wasemphasised in the unusual case of Costain Ltd and Others v. Bechtel Ltd (2005) cited in(Eggleston, 2006), in which the judge made the decision that the project manager’s duty is toact fairly and impartially when acting as a certifier (Eggleston, 2006). This case shows thatthe role separation is not as simple as appears on the face of it.

Under the new Red Book, there is an attempt to abandon the “independent engineer”concept. This appears from three changes: removing the requirement to “act impartially”,

246

ECAM25,2

Page 117: Engineering, Construction and Architectural

expressly stating that the engineer is to act as the employer’s agent, and introducing theDispute Adjudication Board (DAB) to which the parties may refer any dispute. It isimportant to view the development and changes of the contract holistically. The non-neutralengineer and DAB are closely related and have been introduced as one package(Swiney, 2007). Certainly, this has significantly reduced the dispute resolution role andpower of the engineer (Ndekugri et al., 2007).

The total abandonment of the “independent Engineer” concept is questioned since itreplaces the duty to “act impartially” by the duty to make “fair determinations” of the claimsbetween the employer and the contractor, which appears to reinstate the old concept.However, a new mechanism to allow the employer to regain control over the engineer isintroduced in clause 3.1. This is achieved by stating that the engineer is to act as theemployer’s agent in the particular conditions. Furthermore, unlike the old Red Book, the newbook empowers the employer with express authority to replace the engineer for any reasonwhatsoever, subject to two procedural requirements (Ndekugri et al., 2007).

Lina (1997) argued that although the dual role of the engineer should be abandoned, thenew FIDIC and NEC approaches are less efficient than the traditional system. For instance,the NEC approach of separating the duties of the engineer to multiple people or firmsignores the consistency gained by one party working over the whole project life cycle fromproject inception to completion. Also, the engineer’s knowledge of the project’s day-to-dayactivities enables him to make decisions better than the DAB or adjudicator. In addition, theinterference of the DAB or adjudicator may create a confrontational rather than acooperative environment and in turn increase claims, especially as the engineer no longerhas an obligation to act impartially. Finally, the additional fees payable to the DAB oradjudicator make the works more expensive (Lina, 1997).

Summarising, the new Red Book has moved towards the NEC approach to dispose of theindependent engineer concept. However, FIDIC has not gone all the way because the dualityof engineer’s role has not been eliminated completely. Arguably, this is favourable as thenew Red Book is structured flexibly enough to serve the requirements of different parties(Ndekugri et al., 2007).

3. Conceptual frameworkThis research is of a qualitative nature because it aims to induce the relationship betweenthe choice of a standard contract and contractual disputes. The research method depends onreviewing the literature and conducting interviews.

The variables or units of analysis in the theoretical framework of this research are theFIDIC and NEC standard contracts and construction disputes. The main assumption here ofthe interaction between the variables is that the choice of the contract has a direct effect onthe disputes between construction parties. In other words, the contract is the independentvariable whereas the dispute is the dependent variable. The proposition here is that NECmay minimise disputes. The validity of this proposition will be investigated by surveyingthe opinions of practitioners through interviews.

4. InterviewsThe interview questions were built with the proposition that knowledge about FIDIC isexpected, but no prior knowledge about NEC is assumed. The interviews were conductedvia Skype, which gives almost the same atmosphere of a face-to-face personal interviewbecause of the inclusion of video communication. The average interview duration was85 minutes. Selected “expert” sampling has been followed in this research. This involvesselecting people who have expertise in the research topic, which is in this case isconstruction contracts, especially FIDIC.

247

Suitability ofFIDIC and

NECconditions

Page 118: Engineering, Construction and Architectural

The data are obtained from 12 semi-structured interviews with eminent professionals inthe Palestinian construction industry. The interviewees fall under the following job titles orpositions: project manager, technical manager, executive manager, procurement/contractmanager, programme manager, academic, and arbitrator. The interviewees have been selectedwith the intention in mind to be as diverse as possible. Therefore, it is very likely to obtaindiverse and various opinions and experiences that may disagree on many issues. This shouldbe viewed as a healthy debate giving rise to more rounded conclusions, and covering the topicin a holistic view from many angles. The interviewees represent employers, contractors,engineering and consulting firms, and development agencies. In addition, the researchers haveinterviewed people of different genders, different ages and experiences. The range ofexperience ranges from 8 to 30 years.

5. Results and discussions5.1 Clarity and simplicityThe respondents were asked to describe the clarity, readability, understanding,interpretation, and certainty of meaning of FIDIC clauses.

There was a clear disagreement regarding the degree of clarity, but all respondentsargued that FIDIC is not clear enough. The interviewees maintain that FIDIC’s extensivecross-referencing and many very long sentences separated by commas reduce thereadability and the understanding.

Further they think the lack of clarity, or the difficulty in understanding, which either leadto various interpretations of the contract comes from the fact that almost all of its users areengineers not schooled in law, while the contract was drafted by lawyers using verylegalistic language. Further, the fact that the contract users are non-native English speakersbrings more difficulties as to the need to understand the ordinary meaning of the words/phrases and the legal meaning that usually is built on a legal tradition of long case lawparticular to the country of origin. They think that the use of Arabic version is very usefulespecially for first-time users; however, it is not a panacea. This is mainly because of thepotential problem of deviation or distortion of the meaning when translating legal terms andphrases to other languages, particularly if this is combined with different legal systems. Itseems that the simple and plain English of NEC helps to reduce disagreements and disputesresulting from the FIDIC’s legal and obscure wordings. Also, the translation of NEC toArabic would be much easier and clearer than FIDIC because of its ordinary language.

Also, they state that FIDIC uses phrases which are uncertain in meaning and could havemore than one interpretation such as “in the contractor opinion”, “unforeseeable”,“exceptional”, “experienced contractor”, and “physical conditions”.

In the allocation of ground conditions risk, FIDIC uses a “foreseeability” test (“unforeseeablefor an experienced contractor”), whereas NEC uses a “probability” test (“have a small chance ofoccurring”). Although some authors criticise both expressions as being uncertain and slightlydifferent approaches (Eggleston, 2006; Ndekugri and Mcdonnell, 1999), FIDIC’s foreseeabilitytest appears to be more problematic because it is undertaken only after the occurrence of theevent, i.e. the test calls for an assessment ex ante. Psychologically, it is next to impossible toignore this ex-post knowledge and therefore this retrospective investigation to determine whatwas foreseeable and what was not suffers from the notorious “hindsight bias” (perceiving pastevents to have been more predictable than they actually were). Almost all the intervieweesexpressed their discomfort with this test. Some interviewees stated that the “foreseeability”test is defective and judgements on the foreseeability of events are unpredictable, a puregamble or a speculative exercise. Another interviewee criticised the essence of how FIDICtreats the concept of foreseeability as a binary either-or construct, whereas in fact it is acontinuum from ultimate uncertainty to inevitable certainty. So, where does the dividing linebetween foreseeable and unforeseeable lie?

248

ECAM25,2

Page 119: Engineering, Construction and Architectural

In the allocation of weather conditions risk, FIDIC uses a subjective test (“exceptionallyadverse climatic conditions”), whereas NEC uses an objective statistical test (weatherconditions which occur “average less frequently than once in ten years”). The judgment onwhether the conditions are “exceptional” is inherently subjective and hence leads to disputeson its interpretation.

One participant says that “experienced contractor” is a “hollowed out and meaninglessphrase”. The elasticity of the phrase comes from fallacies such as the failure to assignobjective threshold of time-based experience or number-based experience of similar projectsor similar tasks, and the failure to distinguish between the experience of the organisationitself, and the experience of its staff. Sometimes, new organisations hire staff with lengthyexperience in order to claim “expertise” but then form teams which suffer from lowperformance. On the other end of the scale, old construction companies with an extensivepast experience may be in a situation whereby most of its staff that implemented the pastsimilar projects left the company, and is left with juniors of minimal experience. Is there aroom to differentiate between the organisational learning and individual learning? Further,does the expertise of the project team or the expertise of the organisation’s head office staffmatter? It is unknown. Therefore, the concept of “experienced contractor” is entirelyuncertain in meaning, and its interpretation will likely be a lottery that depends on thediscretion of the tribunal deciding the dispute. The participant suggests linking the conceptto the prequalification requirements in terms of detailed criteria covering financial andtechnical strength, experience in similar projects, similar key activities, head officepersonnel and project team, etc.

Four respondents propose to use more specific terms and to attach objective values to therisk events such as rainfall duration and intensity, wind speed, earthquake degree, etc.Others propose to provide a commentary about such vague phrases, and to supplement thecontract with guidance on its interpretation.

5.2 Risk allocation and managementThe respondents were asked if they think risk allocation clarity or fairness or bothwould be major causes of disputes, and then if they think FIDIC adopts fair and clear risksharing principles.

The interviewees disagree about the clarity (i.e. part of the clarity of the overalldocument) and fairness of FIDIC risk sharing, and this disagreement is shared by engineersand contractors.

Ten interviewees agree that disputes will arise if risk allocation is unclear. This isbecause arguments will occur over who bears which risks. The parties will blame eachother, and will keep searching for ways to support their contractual position. This issimply because either party will be unhappy to pay money. However, two people say thateven if risk allocation is clear, contractors continue to make claims. The clarity of therisk allocation, as part of the clarity of the whole contract, is discussed in Section 5.1Clarity and Simplicity.

On the other hand, the interviewees disagree about fairness and disputes. While eightrespondents say that if risk allocation is unfair and unrealistic, this will inevitably lead todisputes, others argue that this affects bid price and not claims or disputes. Yet, someparticipants maintain that fairness does not usually result in higher prices, as contractorsusually use zero overhead, because they are working in a very highly competitive marketwith a desperate need to work. One interviewee refers to this situation as a prevailing“claim- hunting culture” which means that a contractor offers a price based only on thedirect “dry” cost, and then depends on claims to make profit. Obviously, such unjustifiedclaims create disputes. Therefore, it can be argued that the unfair risk allocation createsdisputes in an indirect way (backdoor form of dispute creation).

249

Suitability ofFIDIC and

NECconditions

Page 120: Engineering, Construction and Architectural

Seven interviewees say that FIDIC is well-balanced, fair or relatively fair in that FIDICviews parties as partners. They gave some examples such as force majeure and terminationclauses, clause 17 (risk and responsibility), and clause 18 (insurance) that provide faircontracting principles. Also, they believe that the claim procedure allows contractors to becompensated fairly.

Five interviewees feel that FIDIC is or tends to be unfair because it shifts most of therisks to contractors, except for a few things such as employer’s risks and force majeure.Many of the risks shifted towards contractors are illogical because they are weaker thanclients to bear certain risks. Hesitantly, they gave some examples such as the weatherconditions risk clause that gives an entitlement to only time compensation. They referredalso to clauses that provide for compensation only if the risky events are unforeseeable, butthe de facto result is that the employer and the engineer consider the risky events to beforeseeable and hence contractors ultimately bear the risks of ground conditions, shortagein the availability of materials, and so on.

5.3 Force majeure and prevention eventsEight interviewees say that force majeure is one of the most dispute generating clausesbecause of its lack of clarity. For instance, one interviewee states that it is unclear whetheran “insurrection” constitutes force majeure. Also, after the tightening of the blockade onGaza by Israel, there were many arguments about whether this constitutes force majeure ornot, as the outcome would cost certain organisations a large amount of money.

Moreover, some local employers delete the provisions of force majeure. They argue thatmost of the events that are included under this clause, such as war, hostilities, unrest, etc.have become normal things and circumstances in Gaza. Nevertheless, the authors believethat deleting this clause just because a force majeure event has become normal orforeseeable is illogical. This is because the main part of the definition of such an event isbeing out of the control of either party even if it is foreseeable. Thus, allocating this risk tothe contractor is a default practice with devastating consequences on bid price or finalproject cost, and definitely disputes, and may result in project failure.

Quite often, the contractor is the “victim” as he must bear the financial consequences ofthese events, because employers have a strict and limited budget for each project.Employers try to cooperate or share some aspects of these risks by granting an extension oftime so that contractors are not liable to pay liquidated damages.

5.4 VariationsThe interviewees were asked if they think variations are a major source of disputes and why.

There was disagreement between the respondents about this issue. Some argue thatvariations often lead to disputes, while others claim that variations very rarely causedisputes. Another group stands in between and says disputes sometimes happen,particularly when a variation order requires new prices or rates to be agreed. Thisdisagreement between the interviewees may be because of the different definition andperception of what constitutes a dispute. Possibly, some consider that a rejection ordisagreement about the first quotation is a dispute, while others consider a dispute ariseswhen disagreements occur after signing and agreeing the variation price.

The common practice in Palestine is to agree the price of the varied work beforecommencing the works. However, contractors sometimes start working before agreeing theprice to avoid delaying the project. Some people think that FIDIC is flexible in this way anddoes not oblige pre-pricing or post-evaluation. Instead, FIDIC obliges the contractor tocommence the work even if the price of this work has not been agreed. It has been shown bythe majority of interviewees that disputes are usually avoided when they follow thepre-pricing route. One contractor states that sometimes disputes arise even if a schedule of

250

ECAM25,2

Page 121: Engineering, Construction and Architectural

cost components and analysis of the price breakdown structure are provided. Thearguments arise over the value of direct cost, and overhead percentage, and so on. Thisconflict of interest is normal because contractors consider a variation to be an opportunity tomake profit, while employers want to adhere to the rates defined in the bill of quantities. Allin all, this clearly indicates that the NEC approach is much better than FIDIC’s approach toavoid disputes in the area of variations.

It has been shown that disputes do not only arise from disagreements about evaluation ofthe impact of the variation, but also from the definition of variation. In some cases, the engineerinstructs the contractor to do certain work, which falls outside the contract and thus constitutesa variation in fact, but refuses to acknowledge that his order constitutes a variation. While atother times, the contractor attempts to “make up” variations by delaying the progress orsequence of works, or otherwise, which necessitates new work. Also, contractors may arguethat a normal instruction which does not constitute a variation, to be variation.

5.5 The role of the engineer vis-à-vis the project managerThe interviewees were asked whether they think the duality of the role of the engineer(being the client agent and, at the same time, the independent third party to determinematters fairly between the employer and the contractor) is efficient or problematic and why.At the same time, they were asked if they prefer the engineer to be the adjudicator of thedisputes between the employer and the contractor and why.

Again, the respondents have different views about this matter. While three engineersdefend this role, two engineers, and all other respondents (employers and contractors)criticise this role.

The proponents claim that the engineer knows “the nuts and bolts” of the project andcontract documents. They argue that if the role is divided into design, supervision, contractadministration, and adjudication this will lead to inconsistency, misinterpretation of contractdocuments, and may result in significant “rework” because each entity needs to understandthe work done by others. Furthermore, in case of dispute, they think the engineer is in a betterposition to make the correct decision because he will interpret the contract documentscorrectly and because of his day-to-day knowledge of the project progress and works.

Four interviewees say that this role is not problematic in nature, but its efficiencydepends on the professionalism and expertise of the engineer. The engineer who is requiredto do all these tasks must be very experienced to recognise, distinguish and split whichtasks require him to be agent, and which require him to be independent. Whether theengineer shall be the adjudicator is a mere matter of experience and not basically about trustand honesty. This is because experienced engineers consider it dishonourable anddisreputable to make wrong or biased decisions. One interviewee states that he prefers theengineer to be a member of the DAB, but not the sole member.

The rest of respondents, five interviewees, argue, giving different reasons, that the role isproblematic, theoretical, and not practical and combines conflicting roles. Engineers maymake things personal and do not understand their roles properly, what is required fromthem and what their lines of authority and power, rights, and obligations are. Theinterviewed contractors told “horror stories” of the abusive and oppressive behaviour ofsome engineers. In their experience, this reaches its maximal limit when the engineer(performing the supervision, contract administration, and dispute resolution functions) isalso the designer of the works. This combination of roles is not uncommon in Palestine andit is next to impossible for the engineer to hold himself guilty and hence awards thecontractor compensation for the defective design, or inconsistent contract documents, orfaulty specifications from the pocket of his employer. It is just nonsense! An example forthis, as stated by an interviewed contractor, is that when the engineer is aware of hiscontract administration pitfalls, delayed decisions on approval requests, delayed responses

251

Suitability ofFIDIC and

NECconditions

Page 122: Engineering, Construction and Architectural

on RFIs, etc. he may award the contractor compensation but on alternative neutral groundssuch as delays because of weather conditions or events outside of the control of the projectparties. The interviewed contractors say that employers and engineers sometimes appear tochange or swap their roles, which clearly indicates that they behave as one party. Aninterviewed employer admits that in some cases the engineer becomes part of the problem,and then ironically the employer intervenes to settle the controversies between the engineerand the contractor. In addition, it is not unusual to find in construction contracts that theengineer and the employer are the same organisation. Therefore, it is against the naturaljustice to make a party the judge in its own cause or in a case in which it has an interest.

The impartial role of the engineer in performing the functions of certification, valuation, anddispute resolution has often been misunderstood or viewed with great scepticism bypractitioners in Palestine. The prevailing attitude is that engineers are the agents or therepresentatives of employers, and in case of dispute, the engineer will not attempt to, or will feelembarrassed to blame the person who pays him. Therefore, engineers tend to be consciously orsubconsciously biased and partial, and hence cannot be reliable and trusted adjudicators.The prevailing adversarial culture between contractors and engineers in Palestine, as theavailable literature suggests, is an imperative obstacle to the adjudicatory role of engineers.

6. ConclusionThis study sets out to assess the role of the standard form of contract, FIDIC or NEC inparticular, in dispute minimisation. The main results and findings suggest that bothcontracts have commendable and desirable features for all parties. However, there arecertain areas of concern and sometimes limitations in both contracts.

NEC has probably many advantages over FIDIC particularly in clarity, risk management,and variations. The authors argue that these advantages or benefits are for all parties to aconstruction contract because disputes minimisation is a matter of mutual interest.

The position of the engineer/project manager has benefits and limitations in bothcontracts; however, it seems that the project manager role under NEC is more sensible inPalestine. This is primarily because of the adversarial relationship and lack of trust betweencontractors and engineers and the conflict of interests which makes it more reasonable toseparate the impartial and neutral role of dispute adjudication from the supervisory andcontract administration role in which the engineer works as the client’s agent.

The force majeure or prevention provisions are inconclusive in both standard forms, achallenge that arises from the inherently uncertain nature of these events.

On the other hand, FIDIC has the advantages of familiarity and precedence, widespreadpopularity, and endorsement by many governments, development banks and institutions,and major employers in Palestine and worldwide.

In a nut shell, the standard form of contract can be a tool to “minimise” disputes, butcertainly not to eradicate them, and NEC appears to be more capable than FIDIC to do so.The standard form of contract provides the regulatory regime for the parties’ relationships,roles, and responsibilities. The more fair and clear the regulations, the less room availablefor disputes. Clarity necessitates a move from subjectivity to objectivity, from abstraction tocomprehensiveness, and from generalisation to particularisation. This definitely helps inshrinking the margin of contract’s incompleteness and uncertainties. Although the “theoryof contracts” is incapable to cope with the challenges of “uncertainty”, risks are alsoproblematic. Risks are those events that may or may not occur. They can be assignedprobability values and hence undergo a probability test (NEC term) or a foreseeability test(FIDIC term). Although NEC’s objective approach is a remarkable improvement comparedto FIDIC’s subjective approach, it is probably still vulnerable to different interpretations.

The aforementioned discussions illustrate the boundaries and the extent of the contractcapability to tackle disputes. It is the opinion of the authors that the significant sources of

252

ECAM25,2

Page 123: Engineering, Construction and Architectural

disputes are the users of the contracts and not the contracts themselves. Nevertheless, thereis no clear demarcation line between the shortcomings of the standard form of contract, andthe pitfalls of people. To give one example, the issue of clarity may be attributed to thecontract’s drafting or to the user’s lack of knowledge and experience to understand thecontract. Such arguments are expected to go on and on.

Note

1. Decree 131/2006 published in the Palestinian Official Gazette (Al-Waqa’e Al-Filastinyya) Vol99, in27 April 2007, available on “Al-Muqtafi” online legal database. The Palestinian legislation ispublished in the Official Gazette (Birzeit University Institute of Law web page).

References

Abedmousa, M. (2008), “Construction claims in Palestine”, School of Engineering Department ofCivil Engineering MSc Construction Management Thesis Submitted to the School of CivilEngineering, University of Birmingham, Birmingham.

Abrahamson, M. (1979), Engineering Law and the ICE Contracts, 4th ed., Applied Science, London.

Aljarosha, Z. (2008), “Impact of conditions of contract for construction (FIDIC 99) on the Gaza stripcontractor’s cost estimation”, MSc thesis, The Islamic University of Gaza, Gaza.

Broome, J. and Hayes, R. (1997), “A comparison of the clarity of traditional construction contracts andof the new engineering contract”, International Journal of Project Management, Vol. 15 No. 4,pp. 255-261.

Brown, S. (2000), “Let’s get contractual !”, NEC Users’ Group Newsletters, No. 12, p. 3.

Bunni, N. (2005), The FIDIC Forms of Contract, 3rd ed., Blackwell Publishing Ltd, Oxford.

Cheung, S.O. and Pang, K.H.Y. (2012), “Anatomy of construction disputes”, Journal of ConstructionEngineering and Management, Vol. 139 No. 1.

Chong, H. and Zin, R. (2009), “A case study into the language structure of construction standard form inMalaysia”, International Journal of Project Management, Vol. 28 No. 6, pp. 601-608.

Clegg, S. (1992), “Contracts cause conflict”, in Fenn, P. and Gameson, R. (Eds), Construction Conflict:Management and Resolution, Chapman & Hall, London, pp. 128-144.

Cutts, M. and Maher, S. (1986), The Plain English Story, 1st ed., Plain English Campaign, Whaley Bridge.

Eggleston, B. (2006), The NEC 3 Engineering and Construction Contract A Commentary, 2nd ed.,Blackwell Science, Oxford.

El-Sawalhi, N. and El-riyati, A. (2015), “An overhead costs assessment for construction projects atGaza strip”, American Journal of Civil Engineering, Vol. 3 No. 4, pp. 95-101.

Enshassi, A. (1999), “Understanding contract documents and its relation to the performance inconstruction projects”, in Ogunlana, S. (Ed.), Profitable Partnering in Construction Procurement,E & FN SPON , New York, NY, pp. 223-233.

Enshassi, A., Choudhry, R.M. and EL-Ghandour, S. (2009), “Contractors’ perception towards causes ofclaims in construction projects”, International Journal of Construction Management, Vol. 9 No. 1,pp. 79-92.

Enshassi, A., Kumaraswamy, M. and Nairab, S. (2010), “Analysis of contractors’ bidding decision in thePalestinian construction industry”, Revista Ingenieria de Construccion ( Journal of ConstructionEngineering), Vol. 25 No. 2, pp. 161-214.

Enshassi, A., Mohamed, S. and El-Ghandour, S. (2009), “Problems associated with the process of claimmanagement in Palestine: contractors’ perspective engineering”, Construction and ArchitecturalManagement, Vol. 16 No. 1, pp. 61-72.

Fenn, P. (2012), Commercial Conflict Management and Dispute Resolution, Routledge, Oxon.

Fenn, P., Lowe, D. and Speck, C. (1997), “Conflict and dispute in construction”, ConstructionManagement Economics, Vol. 15 No. 6, pp. 513-518.

253

Suitability ofFIDIC and

NECconditions

Page 124: Engineering, Construction and Architectural

FIDIC (1987), Conditions of Contract for Works of Civil Engineering Construction, 4th ed., FIDIC,Geneva.

FIDIC (1999), Conditions of Contract for Construction: For Building and Engineering Works Designed bythe Employer: General Conditions: Guidance for the Preparation of Particular Conditions:Forms of Letter of Tender, Contract Agreement and Dispute Adjudication Agreement, F drationInternationale des Ing nieurs-Conseils, Lausanne.

Forward, F. (2002), The NEC Compared and Contrasted, 1st ed., Thomas Telford, London.

Gould, N. (2007), NEC3: The Construction Contract of the Future, Society of ConstructionLaw, Singapore.

Heaphy, I. (2011), “NEC3 v. FIDIC”, NEC Users’ Group Newsletters, No. 55, pp. 5-6.

Hughes, W. and Maeda, W. (2002), “Construction contract policy: do we mean what we say?”,RICS Research Paper, Vol. 4 No. 12, pp. 1-25.

Jaeger, A. and Hök, G. (2010), FIDIC – A Guide for Practitioners, 1st ed., Springer, Heidelberg.

Kozek, J. and Hebberd, C. (1998), “Contracts: share the risk”, Journal of Construction Engineering andManagement, Vol. 111 No. 2, pp. 356-361.

Lavin, M. and Potts, K. (1998), “Response to the new engineering contract – a review of expertsobservations on this radical new contract”, Construction and Building Research Conference,Oxford Brookes University, 2-3 September, pp. 1-9.

Li, M. (2006), “New engineering contract (NEC) 1993 as radical changes to the Malaysian standardforms of contract”, MSc thesis, Universiti Teknologi Malaysia, Johor Bahru.

Lina, C. (1997), “Role of engineer under FIDC form contract”, Journal of Professional Issues inEngineering Education and Practice, Vol. 123 No. 2, pp. 48-50.

Murtaja, A. (2007), “Investigation of FIDIC clauses dealing with construction project performance”,MSc thesis, The Islamic University of Gaza, Gaza.

Ndekugri, I. and Mcdonnell, B. (1999), “Differing site conditions risks: a FIDIC/engineering andconstruction contract comparison”, Engineering, Construction and Architectural Management,Vol. 6 No. 2, pp. 177-187.

Ndekugri, I., Smithb, N. and Hughesc, W. (2007), “The engineer under FIDIC’s conditions of contract forconstruction”, Construction Management and Economics, Vol. 25 No. 7, pp. 791-799.

Osinski, C. (2002), “Delivering infrastructure: international best practice-FIDIC contracts: a contractorview”, Society of Construction Law, available at: www.scl.org.uk (accessed 20 June 2016).

Potts, K. (2008), Construction Cost Management-Learning from Case Studies, 1st ed., Taylor & Francis,Abingdon.

Saqfelhait, M.A.S. (2012), “Construction contracts in palestine from engineering and legalperspectives”, MSc thesis, An-Najah National University, Nablus.

Seifert, B. (2005), “International construction dispute adjudication under international federationof consulting engineers conditions of contract and the Dispute Adjudication Board”, Journal ofConstruction Engineering and Management, Vol. 131 No. 2, pp. 149-157.

Seppala, C. (1991), “Contractor’s claims under the FIDIC civil engineering contract, fourth (1987) edition”,International Business Lawyer, Vol. 19 No. 8, pp. 457-460.

Swiney, G. (2007), “The dubious upgrade of international development contracts”, International Lawand Management Review, Vol. 3 No. 2, pp. 145-170.

Thompson, R.M., Vorster, M.C. and Groton, J.P. (2000), “Innovations to manage disputes: DRB andNEC”, Journal of Management in Engineering, Vol. 16 No. 5, pp. 51-59.

Valentine, A. (1996), The NEC Engineering and Construction Contract: A User’s Guide, ThomasTelford, London.

Wassenaer, A. (2009), “The ‘big risk game’ – a simple tool to understand project risks and worktogether better”, Construction Law International, Vol. 4 No. 3, pp. 1-4.

254

ECAM25,2

Page 125: Engineering, Construction and Architectural

Williams, D. (2001), “Choosing the contract form a project or business decision?”, NEC Users’ GroupNewsletters, No. 17, p. 6.

Wydick, R. (1978), “Plain English for lawyers”, California Law Review, Vol. 66 No. 4, pp. 727-765.

Zhanglin, G. and Yuli, S. (2010), “Study on contract conditions of natural disasters based on FIDICcriterion”, The 2010 International Conference on Management and Service Science (MASS2010), Wuhan, 24-26 August, pp. 1-3.

Further reading

Barrett, K. (2003), “Measuring the weather: a fair case for compensation”, NEC Users’ GroupNewsletters, No. 27, pp. 4-5.

Besaiso, H., Wright, D., Fenn, P. and Emsely, M. (2016), “A comparison of the suitability of FIDIC andNEC conditions of contract in Palestine”, RICS COBRA, The Construction, Building and RealEstate Research Conference of the Royal Institution of Chartered Surveyors, Toronto and London,September, pp. 20-22.

Cox, A. and Thompson, I. (1996), “Is the NEC going to succeed? – an examination of the engineeringand construction contract”, The International Construction Law Review, Vol. 13 No. 3,pp. 327-337.

Enshassi, A., Al-Hallaq, K. and Mohamed, S. (2006), “Causes of contractor’s business failure indeveloping countries: the case of Palestine”, Journal of Construction in Developing Countries,Vol. 11 No. 2, pp. 1-14.

Fenn, P. (2007), “Predicting construction disputes: an etiological approach”, Proceedings of theICE – Management, Procurement and Law, Vol. 160 No. 2, pp. 69-73.

Glover, J. (2008), “FIDIC an overview: the latest developments, comparisons, claims and a look into thefuture”, 2 September, available at: www.fenwickelliott.com/research-insight/articles-papers/contract-issues/archive?page=1 (accessed 2 July 2012).

Harmon, K. (2011), “To be or not to be – that is the question: is a DRB right for your project?”, Journal ofLegal Affairs and Dispute Resolution in Engineering and Construction, Vol. 3 No. 1, pp. 10-16.

Hillig, J., Dan-Asabe, D., Donyavi, S., Dursun, O. and Thampuratty, A. (2010), “FIDIC’s Red Book 1999edition: a study review”, Proceedings of the Institution of Civil Engineers-Management,Procurement and Law, Vol. 163 No. 3, pp. 129-133.

Hughes, W. and Greenwood, D. (1996), “The standardization of contracts for construction”,International Construction Law Review, Vol. 13 No. 2, pp. 196-206.

Klein, R. (2010), “Time to zap those zany z clauses”, NEC Users’ Group Newsletters, No. 51, p. 2.

McInnis, A. (2001),The New Engineering Contract: A Legal Commentary, 1st ed., Thomas Telford, London.

Omoto, T. (2002), “Bargaining model of construction dispute resolution”, IEEE InternationalConference on Systems, Man and Cybernetics, Tokyo, 6-9 October, pp. 6-12.

Robinson, M. (2011), A Contractor’s Guide to the FIDIC Conditions of Contract, 1st ed., Wiley-Blackwell,Hoboken, NJ.

Appendix. Semi-structured interview templateThis is a template to be used for each interview. It is only a template; not all of these questions willnecessarily be asked, nor will they be phrased the same way or be asked in the same order or asked inevery interview. Further questions may emerge during the conduct of the interviews.

Part 1: background of interviewees

(1) What is your position within the current organisation or project?

(2) How many years have you been working with construction contracts?

(3) What are the standard forms of contract you have used? Who does suggest its usage? Whichone do you prefer and why?

255

Suitability ofFIDIC and

NECconditions

Page 126: Engineering, Construction and Architectural

Part 2: interviewee’s experience and opinion of FIDIC conditions of contract

(1) Do you have any experience of using FIDIC, for how many years, and on what typesof projects?

(2) Were there any disputes, what caused them, and what were the used dispute resolutiontechniques, was you satisfied with these techniques and why?

(3) How would you describe the clarity, readability, understanding, interpretation, and certaintyof meaning of FIDIC clauses? Can you give examples to support your answer?

(4) As Palestinians are non-native English speakers, do you think the use of English version(which is the original version used in litigation) is a challenge and reduces clarity andunderstanding that ultimately creates disputes? Do you think the usage of Arabic version is asolution? What options would you suggest to overcome this?

(5) Do you think the duality of the role of the engineer (being the client agent and at the same timeindependent third party to determine matters fairly between the client and contractor) isefficient or problematic and why? Do you prefer the engineer to be the adjudicator of thedisputes between the client and contractor and why?

(6) In your opinion, would risk allocation clarity or fairness or both, be major causes to disputes?How?

(7) Do you think FIDIC adopts fair and clear risk sharing principles and why? Could yougive examples?

(8) What do you think about the clarity and fairness of physical ground conditions and weatherconditions risks allocation? Do you think words such as “foreseeable”, “experiencedcontractor”, and “exceptionally adverse climatic conditions” are certain in meaning and why?Could you propose ways to enhance the clarity and fairness?

(9) What do you think about the efficiency and effectiveness of dispute resolution mechanismadopted by FIDIC? Do you think the inclusion of Dispute Adjudication Board in thismechanism adds value to disputes avoidance, minimisation, amicable, quick, efficient and fairresolution? How and why? Could you give examples of the pros and cons of FIDIC’s approach?

(10) Do you think variations are a major source of disputes? Why? How FIDIC clauses cover this, isit clear what constitutes a variation, is it valued fairly, etc.? Do you suggest any improvementin the drafting of variation clauses?

(11) What do you think are the main causes of disputes between the employer and the contractor inthe Palestinian construction industry, and can the contract be the tool to minimise theiroccurrence and/or impact? How?

(12) Do you think the clauses of FIDIC are appropriate (clear, comprehensive, fair, etc.) for theabnormal conditions in Palestine (e.g. borders closure, aggressions, fluctuations inconstruction material availability and prices, etc.) and why? If no, how can it be enhanced?

(13) What are the main problems and challenges facing you in managing contracts?

(14) Have you heard about the new engineering contract standard form of contract? If yes, how andwhat is your feedback with any experience in dealing with it?

Corresponding authorHaytham Besaiso can be contacted at: [email protected]

For instructions on how to order reprints of this article, please visit our website:www.emeraldgrouppublishing.com/licensing/reprints.htmOr contact us for further details: [email protected]

256

ECAM25,2

Page 127: Engineering, Construction and Architectural

Understanding why Chinesecontractors are not willing to

purchase construction insuranceJunying Liu and Sen Lin

Tianjin University, Tianjin, China, andYingbin Feng

School of Computing, Engineering and Mathematics,Western Sydney University, South Penrith, Australia

AbstractPurpose – Construction insurance has been advocated as a useful financial means to transfer risks andmitigate potential project losses. However, there is a general reluctance to purchase construction insurance inChina. The purpose of this paper is to develop an extended theory of planned behavior (TPB) model tounderstand and predict contractors’ construction insurance purchasing intention.Design/methodology/approach – Quantitative data were collected through a questionnaire survey.The respondents comprise 130 project directors/managers and contract managers/administrators who wereinvolved in or familiar with the construction insurance purchasing or managing. Data were analyzed usingstructural equation modeling.Findings – This study developed an extended TPB model to explain the contractors’ intention formation.The results indicated that the insurance purchasing intention was mainly influenced by attitudes andsubjective norm, rather than perceived behavioral control. The analyses also revealed that the addedvariables (risk perception and past experience) had a significant impact on the attitudes and perceivedbehavioral control.Originality/value – This study identified the factors leading to Chinese contractors’ low willingness topurchase construction insurance by extending the TPB model to the context of construction insurancepurchasing. The extended TPB model may serve as a theoretical framework and basis for the Chinesecontractors, insurers, and regulators to understand the root causes of contractors’ low willingness to purchaseconstruction insurance and make joint efforts to address the risks and insurance in the construction industry.Keywords Organization, Risk management, Construction, Questionnaire surveyPaper type Research paper

1. IntroductionConstruction projects always confront substantial uncertainties and risks, such as national,legal, social, economic, manpower, and natural disasters, during project implementation(Ren and Yao, 2009). Construction industry turns to financial market for viable solutions totransfer risks. Purchase of construction insurance is considered as an effective way totransfer the risks and protect the project from major losses. Construction insurance may bethe only feasible way of repaying project stakeholders and ensuring the project is back ontrack. The initiatives of risk transfer and insurance purchasing can help to reduce loss to anacceptable level and contribute to project success (Choy et al., 2006; Christian, 2003;Hussels et al., 2005; Petrolia et al., 2013).

However, construction insurance was not as effective as expected for some reasons in somedeveloping countries, especially in China. Contractors, who are the primary stakeholder andmain responsible insurance purchaser, usually purchase insurance just to meet the lowestrequirements of relevant law and contracts, or even do not purchase any insurance to cover therisks in the context of Chinese construction industry (Liu et al., 2007). In addition, theconstruction projects may not be effectively protected by construction insurance without

Engineering, Construction andArchitectural Management

Vol. 25 No. 2, 2018pp. 257-272

© Emerald Publishing Limited0969-9988

DOI 10.1108/ECAM-08-2016-0186

Received 16 August 2016Revised 21 October 2016

22 December 201624 February 2017

Accepted 8 May 2017

The current issue and full text archive of this journal is available on Emerald Insight at:www.emeraldinsight.com/0969-9988.htm

This study was supported by the National Natural Science Foundation of China (Grant No. 71202084).

257

Constructioninsurance

Quarto trim size: 174mm x 240mm

Page 128: Engineering, Construction and Architectural

extensive knowledge about construction insurance and proper subsequent management, evenif the contractors purchased enough insurance to cover project risks. Once major accidentsoccur, contractors may not get enough compensation from the insurer, which may lead tomajor economic loss or even project failure. As can be seen from Table I, the purchase of maininsurance including construction all risks insurance and installation project all risks insuranceonly accounted for slightly over 30 percent in China, whilst in the developed countries, theinsured rate was more than 90 percent (Li and Li, 2006). Low purchase rate of constructioninsurance has serious implications for China and many other developing countries. There istremendous room for contractors to improve in transferring risks by construction insurance.

There is an increasing tendency of research on construction insurance. Most previousstudies took the perspective of insurance marketing (Chen and Lu, 2014) or governmentmechanism (Guo et al., 2016; McAneney et al., 2016) to find out strategies to stimulateinsurance development, which provides opportunities to understand contractors’ intention orbehaviors of insurance purchasing (Lee and Back, 2005). However, little research has beenconducted to develop theoretical models to explain why contractors are not willing topurchase construction insurance. This research was motivated by the need for a theoreticalframework incorporating various aspects of insurance and construction contractors.

While it is hard to know contractors’ intention directly, it is generally believed that theintention formation process can be a clue to understand their intention to purchaseconstruction insurance (Lam and Hsu, 2006; Han et al., 2010). Specifically, an investigation ofthe underlying volitional and non-volitional factors affecting intention may provide insightsinto their purchasing intention formation process (Ajzen and Fishbein, 1980). This studyemployed the extended theory of planned behavior (TPB) (Ajzen and Fishbein, 2004) to gaina better understanding of contractors’ intention on construction insurance purchasing.The objectives of this study are: to identify the factors influencing contractors’ intention ofpurchasing construction insurance based on the extended TPB; to investigate theinterrelationships among these factors using confirmatory factor analysis (CFA); and toexplain how these factors affect contractors’ willingness to purchase insurance.

This paper begins with extending the TPB based on the exact conditions of constructioninsurance by adding two domain-specific variables, i.e., risk perception and past experience.The paper then develops an initial insurance purchasing intention model based on theextended TPB. Structural equation modeling (SEM) was used to analyze the data collectedfrom a questionnaire survey. Finally, major findings are discussed and further researchdirections are provided.

2. Literature review and conceptual framework2.1 TPBThe TPB, an extension model of the theory of reasoned action (Ajzen, 1985, 1991; Ajzen andSheikh, 2013), is one of the most widely cited models for predicting behavioral intentions by

Types of insurance Insured Not insured Do not know the insurance

Construction all risks insurance 34 37.5 27.5Installation project all risks insurance 32.5 47.5 20Employers’ liability insurance 10 42.5 47.5Personal insurance 75 15 10Professional liability insurance 17.5 45 37.5Project quality risk insurance 7.5 67.5 25Insurance of mechanical equipment loss of profit 2.5 55 42.5Source: Construction Engineering Safety and Insurance Status Survey (2011)

Table I.Constructioninsurance statusin China

258

ECAM25,2

Page 129: Engineering, Construction and Architectural

social psychologists (Collins and Carey, 2007; Fielding et al., 2008; Cheon et al., 2012; Leeuwet al., 2015). According to the TPB model, an individual’s performance of a specific behavior isdetermined by his/her behavioral intention to perform the behavior. This behavioral intentionis in turn determined by three factors related to the behavior: the person’s attitude toward thebehavior, subjective norm, and perceived behavioral control. In this study, TPB is used as thetheoretical basis to understand contractors’ construction insurance intention formation.

2.1.1 Attitude. Attitude was defined as the degree of an individual’s positive or negativeevaluation of behavior performance (Eagly and Chaiken, 1993). Based on the research ofTaylor and Todd (1995), attitude has positive impacts on the intention toward behavior.In the context of construction insurance, contractors’ attitude is measured by two types ofitems: contractors’ attitudes toward purchasing insurance and contractors’ attitudes towardinsurance products (Botzen and Van den Bergh, 2012).

2.1.2 Subjective norm. Subjective norm is a social factor, which means the socialpressure from the environment felt by the person exerted to engage in the behavior(Ajzen and Driver, 1992). Many researchers have examined the relationship betweensubjective norm and intention and confirmed that subjective norm positively affectsintention (Taylor and Todd, 1995; Tonglet et al., 2004; Hsieh, 2015). According to the contextof insurance, the social pressure to purchase construction insurance is considered from thefollowing five aspects: local laws and regulations; contract requirements; market guides;insurance market; and other similar projects (Sola, 2013; Lo, 2013; Brody et al., 2017).

2.1.3 Perceived behavioral control. The third determinant of intention is a non-volitionalfactor termed perceived behavioral control, which reflects a person’s perception of the easeor difficulty in performing a specific behavior (Ajzen and Fishbein, 1980). The greater abilitya person can perform a specific behavior, the more likely such a behavior will be engaged in.The contractors’ ability regarding construction insurance mainly includes purchasingability and claim ability (Wallach and Jasper, 2010). Based on the literature, the followinghypotheses were proposed:

H1. Attitude has a positive influence on purchasing intention.

H2. Perceived behavioral control has a positive influence on purchasing intention.

H3. Subjective norm has a positive influence on purchasing intention.

2.2 Derivation of extended TPB modelBased on the research and development on TPB in the past few decades, researchers haveattempted to modify the TPB model by altering paths and/or adding critical constructsto explain or predict people’s behavioral intentions in particular settings (Perugini andBagozzi, 2001; Chen and Tung, 2014; Bagot et al., 2015; Kashif and Run, 2015). Ajzen(1991, 2015) stated that the modification of TPB should occur cautiously and need to meetthe following two criteria: similar to existing predictors of the theory and the factors areconceptually independent of existing constructs of the theory. Although TPBhas been successfully applied in various contexts, e.g., green hotel, online shopping,safe food (Han et al., 2010; Hsu et al., 2006; Phillip and Anita, 2010), it seems that noresearch has been conducted to apply the theory to construction insurance purchasing.The current study attempted to extend the TPB model by introducing constructs whichare important in the construction insurance context (e.g. past experience and riskpreference) and altering the path in the model to explain contractors’ purchasing intentionof construction insurance.

2.2.1 Risk perception. Risk perception is the individuals’ subjective feeling andunderstanding toward the risks. Construction businesses are risky ventures. However,people often underestimate the risks (Chivers and Flores, 2002; Kunreuther and Pauly, 2006).

259

Constructioninsurance

Page 130: Engineering, Construction and Architectural

If contractors underestimate the risk probability or potential magnitude of loss in a project,insurance may be unattractive to them (Petrolia et al., 2013).

Researchers have found that risk perception tends to play an important role in predictingpeople’s purchasing decisions by significantly influencing their attitude toward the behavior(Petrolia et al., 2013; Zhao et al., 2016; Lobb et al., 2007). Stronger risk perception of contractorsis always related to more positive attitude toward insurance purchasing. According to thecontext of insurance, this study mainly chooses two dimensions to measure risk perception,risk probability and risk influence (Botzen and Van den Bergh, 2012; Voon et al., 2015).

2.2.2 Past experience. Although past experience is not originally included in TPB, someresearchers have identified the need to add this construct to enhanced the predictive powerof the TPB (Perugini and Bagozzi, 2001, Ryu and Jang, 2006; Lee and Back, 2009; Wanget al., 2012). Lee and Back (2009) verified that past experience is an important determinant ofattitude and perceived behavioral control. Han and Kim (2010) also found that pastexperience plays a significant role in decision-making processes. Studies in various fields(Lee and Back, 2009; Lo, 2013; Petrolia et al., 2013) have attempted to include this variable toenhance the predictive power of the TPB.

The contractors’ overall experience of insurance can be regarded as equivalent to asubjective evaluation of all past experience (Huang and Hsu, 2009). In this study, pastexperience includes the overall past construction insurance purchasing experience and theoverall past claims experience. Based on the above literature support, it is thereforeappropriate to incorporate past experience into a model designed to explain the formation ofinsurance purchasing intention in order to ensure a sounder theoretical underpinning.Thus, the following hypotheses were proposed:

H4. Risk perception has a positive influence on attitude.

H5. Past experience has a positive influence on attitude.

H6. Past experience has a positive influence on perceived behavioral control.

In summary, the extended TPB model is presented in Figure 1. The model includes theoriginal variables (attitude, subjective norm and perceived behavioral control) and newconstructs (past experience and risk perception). The bold lines indicate the newly addedpaths to the original TPB model.

RiskPerception

PastExperience

Attitude

PerceivedBehavioral

Control

SubjectiveNorm

PurchasingIntention

H4 +

H5 +

H6 +

H1 +

H2 +

H3 +

Figure 1.Proposed extendedTPB model forcontractors’ purchaseintention onconstruction insurance

260

ECAM25,2

Page 131: Engineering, Construction and Architectural

3. Methodology3.1 Questionnaire designQuestionnaire survey was used to collect data for this study. The literature (Ajzen andFishbein, 1980; Ajzen, 2015) shows that no standard questionnaire was available for TPBresearch. The design of the survey questionnaire involved two steps in this study. The firststep was to develop the measurement scales for attitude, perceived behavioral control,subjective norm, risk perception, past experience and purchasing intention. This was doneby conducting a comprehensive literature review and face-to-face interviews with personnelwho were in charge of or very familiar with insurance purchasing. The second step involveda pilot survey to validate and improve the draft questionnaire in terms of wording, contents,format, and layout. Based on the feedback, revisions were made to improve the readabilityand accuracy of the questionnaire.

In the final questionnaire, the research aims and contact details were presented in thecover letter, followed by the questions about the profile of the respondents, including thetypes of job, work experience, education, and two screening questions (i.e. “How about yourfamiliarity with construction insurance?” and “Have you ever taken part in constructioninsurance purchasing and insurance management?”). We used the original questionnaireitems developed by Ajzen (1991) for TPB model and also quoted some items from Han et al.(2010). Based on the context of construction insurance, the measurement methods for eachvariable are shown in Table II. The questionnaire includes six constructs and 20 scale items:five items for attitude, five items for subjective norm, two items for perceived behavioralcontrol, three items for past experience, two items for risk perception, and three items forpurchasing intention. The respondents were asked to rate each item based on a completedproject in which they have been involved using a five-point Likert scale (1¼ the lowestlevel; 3¼ medium level; and 5¼ the highest level).

3.2 Sampling and procedureThe target respondents include project directors/managers and contract managers/administrators who were involved in or familiar with the construction insurance purchasingor management. Due to the vast number of construction contractors in China, it wasimpractical to conduct nationwide sampling in the whole population of constructioncontractors. In this regard, the sampling was limited to three typical cities in China including

Measurement methodVariable The design of the questionnaire

Purchasing intention (PI) Asking respondents whether they are willing to purchase insurance or not, andwhether they have plan or endeavor to buy

Attitude (AT) Asking the respondents’ overall attitude toward insurance purchasing, insuranceservice quality and the evaluation of its usefulness to weigh their attitude towardinsurance

Subjective norm (SN) Asking the respondents’ social pressure they can feel from the environment, andbased on the construction insurance context, which are as following: local lawsand regulations; contract requirements; company policies; market guides andother similar projects’ act

Perceived behavioralcontrol (PBC)

Asking the respondents’ ability for insurance purchasing, insurance managementand claim for compensation

Risk perception (RP) According to the respondents’ understanding of their projects and risks, askingthe risk probability and influence they feel

Past experience (PE) Based on their experience, asking respondents whether they bought constructioninsurance properly and whether insurance performed well in the past experience

Table II.Measurement methods

of variables

261

Constructioninsurance

Page 132: Engineering, Construction and Architectural

Beijing (the capital city of China), Shanghai (the largest city in China), and Tianjin (one of thefour direct-controlled municipalities of China). The three cities were consideredrepresentative in the Chinese construction industry because 20 percent of the top500 Chinese construction companies in 2016 were located in Beijing, Shanghai, and Tianjin(Chinese Construction Enterprises Management Association, 2016). Snowball sampling(also referred to as chain sampling, chain-referral sampling, or respondent-driven sampling)method was adopted by this study considering the notoriously low response rate and lack ofreliable data with the random sampling approach (Zhai et al., 2014). Salganik andHeckathorn (2004) argued that unbiased estimations can be made from hidden populationsusing respondent-driven sampling and these estimates are asymptotically unbiased nomatter how the initial informants are selected. The initial participants consist of 30 projectmanagers and contract managers from different construction contractors in Beijing,Shanghai, and Tianjin; and they were selected through the professional networks of theresearchers. The initial participants were then requested to recommend other potentialparticipants who were: at similar levels; working for construction contractors in Beijing,Shanghai, and Tianjin; and involved in or familiar with the construction insurancepurchasing or management. Finally, a total of 186 questionnaires were sent out and 167completed questionnaires were returned. The returned questionnaires were checked by thetwo screening questions, and 130 questionnaires were retained, representing a pass rate of69.9 percent. According to the requirements of TPB and statistical analysis, the sample sizeis considered sufficient.

The profile of the respondents is reported in Table III. The profile shows that around halfof the respondents had over five years’ experiences in construction industry and around 90percent of them were well educated (i.e. bachelor degree and above). Such extensive workingexperience and education level of respondents would ensure that they had properknowledge and experience regarding construction industry and construction insurance.

3.3 Method of data analysisSEM has been recognized as one of the most suitable techniques for analyzing theinterrelationships among variables (Chen et al., 2011; Feng et al., 2017; Xiong et al., 2014). InSEM, observable variables can be directly measured, while latent variables are theoreticalconstructs inferred from observable variables. Additionally, SEM consists of measurementand structural models. SEM enables a maximally efficient fit between data and a structuralmodel because both CFA and path analysis can be performed simultaneously in a singlestructural equation model (Lim et al., 2011). Furthermore, there are two types of SEM:covariance-based SEM (CB-SEM) and partial least squares structural equation modeling(PLS-SEM). PLS-SEM has some advantages over CB-SEM. For instance, PLS-SEM does notrequire a large sample size and normal distribution of data, and can estimate latent

Category Number %

Work experience (years)Below 5 67 51.55-10 49 37.711-15 10 7.716-20 4 3.1

EducationBeneath the bachelor degree 12 9.2Bachelor degree 93 71.5Master degree or above 25 19.2

Table III.Profile of therespondents

262

ECAM25,2

Page 133: Engineering, Construction and Architectural

constructs as linear combinations of observable variables through weight relations(Chin, 1998; Fornell and Bookstein, 1982; Hair et al., 2012). Thus, PLS-SEM has been widelyadopted in construction studies in recent years (Doloi, 2014; Feng et al., 2017; Ning and Ling,2013; Zhao et al., 2017).

CFA can test the relationship between the observable variables and their latent variable.In this study, the five TPB and extended TPB construct groupings were seen as the latentvariables in the structural and measurement models. CFA was performed to test whetherthe data fitted the measurement model. Four types of reliability and validity of themeasurement models should be assessed: internal consistency reliability; indicatorreliability; convergent validity; and discriminating validity (Shan et al., 2015).

Composite reliability (CR) is used to assess the internal consistency reliability and itsvalue should be at least 0.70 (Hair et al., 1998). Cronbach’s α coefficient should be above 0.70(Patterson and Neailey, 2002), however, in social science research, it is also accepted thatCronbach’s α coefficient is above 0.60 (Moss, 1998). Loadings of observable variables on thecorresponding latent variables are used to assess the indicator reliability. The indicatorswith loadings below 0.70 should only be removed if deleting this indicator leads to anincrease in CR above the suggested threshold value (Hair et al., 2011). Nevertheless, theindicators with loadings below 0.70 could be retained because of their contributions tocontent validity (Hair et al., 2011). In most studies using PLS-SEM, the actual thresholdvalue of loadings was 0.40 (Comrey, 1973; Matsunaga, 2010; Ning, 2014). The averagevariance extracted (AVE) is used to evaluate the convergent validity, and the thresholdvalue is 0.50 (Fornell and Larcker, 1981). For adequate discriminant validity, the square rootof the AVE of each latent construct should exceed the inter-construct correlation and ameasurement item’s loading on its respective grouping should exceed the cross-loadings(Chin, 1998; Fornell and Larcker, 1981).

Then, the bootstrapping technique (Davison and Hinkley, 1997; Efron, 1987) was appliedto estimate the significance of path coefficients and evaluate the structural model. In thisstudy, the number of bootstrap samples was 5,000, as recommended by Hair et al. (2011),and the number of cases was equal to the number of responses (i.e. 130). The critical t-valuefor a two-tailed test was 1.65 (significance level ¼ 0.10).

4. Results4.1 Data quality testingTables IV andV show the evaluation results of themeasurement model. As shown in Table IV,the observable variables obtained loadings ranging from 0.554 to 0.922, indicating theacceptable indicator reliability. All the CR and Cronbach’s α values were above their respectivethresholds, suggesting a satisfactory level of internal consistency reliability. Furthermore,the AVE of each construct was higher than 0.50, showing an acceptable level of constructconvergent validity. As can be seen in Table V, the square root of the AVE value of each groupis higher than its correlation with any other construct. These results indicate the highdiscriminate validity of the groups. Thus, the measurement model was reliable and valid forthe structural path modeling.

4.2 Hypotheses testingThe bootstrapping technique (Efron, 1987; Davison and Hinkley, 1997) was applied toestimate the significance of path coefficients and test the hypotheses. In this study,the number of bootstrap samples was 5,000, as recommended by Hair et al. (2011), and thenumber of cases was equal to the number of responses (n¼ 130). The results show that fiveout of the six path coefficients are positive and significant at the 0.10 level (α¼ 0.1)(see Table VI and Figure 2). The results of hypotheses testing are discussed in thefollowing section.

263

Constructioninsurance

Page 134: Engineering, Construction and Architectural

5. Discussion5.1 Impacts of attitude, subjective norm, and perceived behavioral control on insurancepurchasing intentionThe results of hypotheses testing (see Table VI) indicate that attitude (β¼ 0.192, t¼ 2.276,α¼ 0.1) and subjective norm (β¼ 0.417, t¼ 5.173, α¼ 0.1) are positively and significantly

Grouping Code Factor loading AVE CR Cronbach’s α

AT AT1 0.554 0.570 0.861 0.786AT2 0.830AT3 0.869AT4 0.800AT5 0.801

PBC PBC1 0.922 0.765 0.866 0.702PBC2 0.824

SN SN1 0.555 0.520 0.842 0.775SN2 0.748SN3 0.779SN4 0.713SN5 0.784

RP RP1 0.874 0.757 0.861 0.678RP2 0.866

PE PE1 0.687 0.564 0.795 0.613PE2 0.792PE3 0.771

PI PI1 0.894 0.804 0.861 0.878PI2 0.912PI3 0.883

Notes: AT, attitude; PBC, perceived behavioral control; SN, subjective norm; RP, risk perception; PE, pastexperience; PI, purchasing intention

Table IV.Measurement modelevaluation

Grouping AT PBC SN RP PE IN

AT 0.755PBC 0.455 0.875SN 0.465 0.348 0.721RP 0.276 0.271 0.044 0.870PE 0.591 0.504 0.449 0.231 0.751IN 0.446 0.363 0.552 0.127 0.511 0.896

Table V.Discriminant validityof the groupings

Hypothetical path Path coefficients t-statistics Interpretation

H1: AT → PI 0.192 2.276 SupportedH2: PBC → PI 0.130 1.439 Not supportedH3: SN → PI 0.417 5.173 SupportedH4: RP → AT 0.147 1.777 SupportedH5: PB → AT 0.557 8.145 SupportedH6: PB → PBC 0.504 6.938 SupportedNotes: AT, attitude; PBC, perceived behavioral control; SN, subjective norm; RP, risk perception; PB, pastbehavior; PI, purchasing intention

Table VI.Path coefficients andsignificance

264

ECAM25,2

Page 135: Engineering, Construction and Architectural

associated with insurance purchasing intention, supporting H1 and H3. These findings areconsistent with previous studies (Ly et al., 2015; Borges and Lansink, 2016), implying that anincrease in attitude and subjective norm may result in an increase in the likelihood ofcontractors’ insurance purchasing intention.

As predicted earlier in the context of construction insurance, subjective norm has apositive impact on contractors’ insurance purchasing intention. Unlike the purchasing of lifeinsurance, where there are no laws or contracts forcing people to buy life insurance( Jacobs-Lawson et al., 2010), the insurance purchasing in the construction industry is largelyrequired by laws and contracts. The owners usually specify the insurance requirementsclearly in the contracts. In addition to laws and contracts, construction insurancepurchasing is also subject to company rules and insurance marketing guide. To sum up,contractors’ decision on insurance purchasing is largely associated with the perceived socialpressure from the environment.

Attitude also significantly influences contractors’ insurance purchasing intention, whichis consistent with the previous studies (e.g. Fichten et al., 2016; Arshad et al., 2015).Contractors who believe in the value of construction insurance and the availability ofhigh-quality insurance service and accept the idea of “prevention is better than cure” tend tobe more willing to transfer the risks through the construction insurance.

The results show that perceived behavioral control was not a significant predictor ofinsurance purchasing intention (β¼ 0.130, t¼ 1.439, α¼ 0.1). However, this finding isinconsistent with the findings of previous studies (Han et al., 2010; Hartmann andApaolaza-Ibáñez, 2012). Perceived behavioral control reflects people’s perception of the easeor difficulty in performing a specific behavior (Han et al., 2010). Han et al. (2010) examinedpeople’s intention to visit green hotels, where the perceived behavioral control wasmeasured by whether people have time or money to do it. However, in the context ofconstruction insurance, it requires professional skills to purchase insurance and transferrisks. It is a common practice for contractors to get assistance from insurance brokers andlegal advisers (Sammon, 2002; Beloucif et al., 2004); and usually the insurers can recommendthe combination of insurance products according to risk characteristics of projects. There isno required insurance purchasing ability for contractors, so perceived behavioral control did

RiskPerception

PastExperience

Attitude

PerceivedBehavioral

Control

SubjectiveNorm

PurchasingIntention

H4�=0.147t=1.777

Supported

H5�=0.557t=8.145

Supported

H6�=0.504t=6.938

Supported

H1�=0.192t=2.276

Supported

H2�=0.130t=1.439

Not supported

H3�=0.417t=5.173

Supported

Figure 2.Extended TPB model

results forconstruction insurancepurchasing intention

265

Constructioninsurance

Page 136: Engineering, Construction and Architectural

not significantly influence intention. Thus, H2 was not supported in this context. Hence,insurance purchasing intention is mainly explained by attitude and subjective norm fromthe results of this study.

5.2 Impacts of risk perception and past experience on attitude and perceivedbehavioral controlThe results (see Table VI) indicate that risk perception significantly influences contractors’attitude toward insurance purchasing (β¼ 0.147, t¼ 1.777, α¼ 0.1). These results are in linewith previous studies in different settings (e.g. Lobb et al., 2007). Construction businessesare risky ventures. However, researchers have found that people’s behavioral decisions areassociated with perceived rather than actual risks as people do not always have a clearunderstanding of the project risks, or the likelihood of various outcomes of the risks(Covell et al., 1991; Feng et al., 2014, 2015). If contractors underestimate the risk probabilityor potential of loss, they tend to develop a negative attitude toward construction insurance,which may appear unattractive under such situations.

In addition,H5 andH6were tested. The results indicate that past experience is positivelyand significantly associated with attitude (β¼ 0.557, t¼ 8.145, α¼ 0.1) and perceivedbehavioral control (β¼ 0.504, t¼ 6.938, α¼ 0.1), thus supporting H5 and H6. This finding isconsistent with the results of previous studies (e.g. Lee and Back, 2009; Lo, 2013; Petroliaet al., 2013). With pleasant past insurance experience, the contractors tend to improve theircapacity of insurance purchasing and management and develop a positive attitude towardinsurance purchasing in the future.

5.3 Implications of the findingsSome managerial implications can be inferred from the findings. The findings imply that thegeneral reluctance of construction contractors to purchase construction insurance in Chinawas caused by various factors. As discussed earlier, attitude is a key factor influencing theformation of contractors’ intention to purchase the construction insurance. It is thereforenecessary that Chinese contractors change their mindset and accept the concept of proactiverisk management and insurance. In addition, a supportive environment should be createdfor construction insurance purchasing. Compulsory requirements, laws and strict regulationare required for the purchase of construction insurance. Meanwhile, the insurers shouldendeavor to improve their service quality and technical competence. More attractiveconstruction insurance products may be developed if the co-operation between theinsurance industry and construction industry is strengthened and mutual understanding ofthe construction risks between contractors and insurers is developed. To sum up, variousparties (including the contractors, insurers, and government) of construction projects needto work together and implement multi-dimensional strategies to improve the riskmanagement of construction projects and achieve the healthy development of theconstruction insurance market in China.

5.4 Limitations of the researchDespite the achievements of this research, there are still some limitations. The firstlimitation concerns the generalizability of the findings. The findings were reached based onthe data collected in China focusing on three major cities including Beijing, Shanghai, andTianjin. Thus, the findings of this research should be interpreted in the context of theconstruction industry in China. Generalizations to other populations may be difficult.However, in the future, the methodology and modeling process of this research may beapplied to investigate the insurance purchasing issues in other settings. The secondlimitation of this study lies in the choice of research approaches. The correlation/regression

266

ECAM25,2

Page 137: Engineering, Construction and Architectural

research design was used by this research. This research design is effective in testing theassociations between variables, but not effective in explaining the causal mechanism amongvariables. In a future study, qualitative data (e.g. observation, focus group discussion, andin-depth interview) may be collected and analyzed to further explain and validate therelationships among variables. Lastly, this empirical research takes the perspective ofcontractors and gives us an understanding of contractors’ insurance purchasing intentionformation. Future research should further develop the proposed psychological constructsand take the insurers as a sample to examine their viewpoints of construction insurance.In addition, future studies could explain the insurance purchasing intention from other pointof view. For example, contractors’ intention on insurance could be comprehended from theperspective of national culture.

6. ConclusionsThis study explored why contractors are not willing to purchase construction insurance inChina. The study developed an extended TPB model to explain the contractors’ purchasingintention formation. Specifically, the added constructs (i.e. risk perception and pastexperience) provide sufficient impetus for insurance purchasing decision-making process,improving our understanding of contractors’ intention formation. The key findings of thisresearch include: subjective norm, which refers to social pressure from the environment(e.g. local laws and regulations, contract requirements, company policies, market guides andother similar projects’ actions) has a positive impact on the contractors’ willingness topurchase the construction insurance; contractors’ attitude toward insurance (e.g. value ofinsurance and quality of insurance service) has a positive impact on their willingness topurchase the construction insurance; and contractors’ attitude toward insurance ispositively influenced by their risk perception and past insurance experience.

Theoretically, the research identified the factors leading to Chinese contractors’ lowwillingness to purchase construction insurance by extending the TPB model to the contextof construction insurance purchasing. The extended TPB model may serve as a theoreticalframework for the Chinese contractors, insurers, and regulators to understand the rootcauses of contractors’ low willingness to purchase construction insurance and make jointefforts to address the risks and insurance in the construction industry. Although empiricalevidence of this study is from China, the methodology and framework derived from thisstudy may be used for similar studies in other countries.

References

Ajzen, I. (1985), “From intention to action: a theory of planned behavior”, in Kuhl, J. and Beckmann, J.(Eds), Action Control, from Cognition to Behavior, Springer-Verlag, New York, NY, pp. 11-39.

Ajzen, I. (1991), “The theory of planned behavior”, Organizational Behavior and Human DecisionProcesses, Vol. 50 No. 2, pp. 179-211.

Ajzen, I. (2015), “The theory of planned behavior is alive and well, and not ready to retire: acommentary on Sniehotta, Presseau, and Araújo-Soares”, Health Psychology Review, Vol. 9 No. 2,pp. 131-137.

Ajzen, I. and Driver, B.L. (1992), “Application of the theory of planned behavior to leisure choice”,Journal of Leisure Research, Vol. 24 No. 3, pp. 207-224.

Ajzen, I. and Fishbein, M. (1980), “Understanding attitude and predicting social behavior”, Prentice-Hall, Englewood Cliffs, NJ.

Ajzen, I. and Fishbein, M. (2004), “Questions raised by a reasoned action approach: comment on ogden”,Health Psychology, Vol. 23 No. 4, pp. 431-434.

267

Constructioninsurance

Page 138: Engineering, Construction and Architectural

Ajzen, I. and Sheikh, S. (2013), “Action versus inaction: anticipated affect in the theory of plannedbehavior”, Journal of Applied Social Psychology, Vol. 43 No. 1, pp. 155-162.

Arshad, M., Ashraf, N. and Raoof, W. (2015), “Determinants of individuals’ entrepreneurial intentions:a comparative study of males and female”, Academy of Management Proceedings, Vol. 2015No. 1, p. 17975.

Bagot, K.L., Masser, B.M. and White, K.M. (2015), “Using an extended theory of planned behavior topredict a change in the type of blood product donated”, Annals of Behavioral Medicine, Vol. 49No. 4, pp. 510-521.

Beloucif, A., Donaldson, B. and Kazanci, U. (2004), “Insurance broker-client relationships: anassessment of quality and duration”, Journal of Financial Services Marketing, Vol. 8 No. 4,pp. 327-342.

Borges, J.A.R. and Lansink, A.G.J.M.O. (2016), “Identifying psychological factors that determine cattlefarmers’ intention to use improved natural grassland”, Journal of Environmental Psychology,Vol. 45, March, pp. 89-96, available at: https://doi.org/10.1016/j.jenvp.2015.12.001

Botzen, W.J.W. and Van den Bergh, J. (2012), “Risk attitudes to low-probability climate changerisks: WTP for flood insurance”, Journal of Economic Behavior & Organization, Vol. 82 No. 1,pp. 151-166.

Brody, S.D., Highfield, W.E., Wilson, M., Lindell, M.K. and Blessing, R. (2017), “Understanding themotivations of coastal residents to voluntarily purchase federal flood insurance”, Journal of RiskResearch, Vol. 20 No. 6, pp. 760-775.

Chen, M.F. and Tung, P.J. (2014), “Developing an extended theory of planned behavior model to predictconsumers’ intention to visit green hotels”, International Journal of Hospitality Management,Vol. 36 No. 1, pp. 221-230.

Chen, S.Y. and Lu, C.C. (2014), “Appraising marketing performance for insurance businesses throughimproved fuzzy modified GRA”, Journal of Grey System, Vol. 26 No. 3, pp. 96-116.

Chen, Y.Q., Zhang, Y.B., Liu, J.Y. and Mo, P. (2011), “Interrelationships among critical success factors ofconstruction projects based on the structural equation model”, Journal of Management inEngineering, Vol. 28 No. 3, pp. 243-251.

Cheon, J., Lee, S., Crooks, S.M. and Song, J. (2012), “An investigation of mobile learning readiness inhigher education based on the theory of planned behavior”, Computers & Education, Vol. 59No. 3, pp. 1054-1064.

Chin, W.W. (1998), “The partial least squares approach to structural equation modeling”,in Marcoulides, G.A. (Ed.), Modern Methods for Business Research, Lawrence ErlbaumAssociates, Mahwah, NJ, pp. 295-335.

Chinese Construction Enterprises Management Association (2016), “List of 2016 top 500 Chineseconstruction enterprises”, available at: www.ccema.com.cn/zt/jianzhu.html (accessedDecember 18, 2016).

Chivers, J. and Flores, N.E. (2002), “Market failure in information: the national flood insuranceprogram”, Land Economics, Vol. 78 No. 4, pp. 515-521.

Choy, C.S., Yew, W.K. and Lin, B.S. (2006), “Criteria for measuring KM performance outcomes inorganisations”, Industrial Management & Data Systems, Vol. 106 No. 7, pp. 917-936.

Christian, G. (2003), “To insure or not to insure?: an insurance puzzle”, The Geneva Papers on Risk andInsurance Theory, Vol. 28 No. 1, pp. 5-24.

Collins, S.E. and Carey, K.B. (2007), “The theory of planned behavior as a model of heavy episodicdrinking among college students”, Psychology of Addictive Behaviors, Vol. 21 No. 4, pp. 498-507.

Comrey, A.L. (1973), A First Course in Factor Analysis, Academic Press, New York, NY.

Covell, V.T., Sandman, P.M. and Stovie, P. (1991), “Guidelines for communicating information aboutchemical risks effectively and responsibly”, in Mayo, D.C. and Hollander, R.D. (Eds), AcceptableEvidence: Science and Values in Risk Management, Oxford University Press, New York, NY.

268

ECAM25,2

Page 139: Engineering, Construction and Architectural

Davison, A.C. and Hinkley, D.V. (1997), Bootstrap Methods and their Application, Cambridge UniversityPress, Cambridge.

Doloi, H. (2014), “Rationalizing the implementation of web-based project management systems inconstruction projects using PLS-SEM”, Journal of Construction Engineering and Management,Vol. 140 No. 7, p. 04014026, doi: 10.1061/(ASCE)CO.1943-7862.0000859.

Eagly, A.H. and Chaiken, S. (1993), The Psychology of Attitudes, Harcourt Brace Jovanovich CollegePublishers, Orlando, FL, p. 1.

Efron, B. (1987), “Better bootstrap confidence intervals”, Journal of the American Statistical Association,Vol. 82 No. 397, pp. 171-185.

Feng, Y., Zhang, S. andWu, P. (2015), “Factors influencing workplace accident costs of building projects”,Safety Science, Vol. 72, February, pp. 97-104, available at: https://doi.org/10.1016/j.ssci.2014.08.008

Feng, Y., Teo, E.A.L., Ling, F.Y.Y. and Low, S.P. (2014), “Exploring the interactive effects of safetyinvestments, safety culture and project hazard on safety performance: an empirical analysis”,International Journal of Project Management, Vol. 32 No. 6, pp. 932-943.

Feng, Y., Wu, P., Ye, G. and Zhao, D. (2017), “Risk-compensation behaviors on construction sites:demographic and psychological determinants”, Journal of Management in Engineering, Vol. 33No. 4, p. 04017008, available at: http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000520

Fichten, C.S., Heiman, T., Jorgensen, M., Nguyen, M.N., Havel, A., King, L., Budd, J. and Amsel, R. (2016),“Theory of planned behavior predicts graduation intentions of Canadian and Israelipostsecondary students with and without learning disabilities/attention deficit hyperactivitydisorder”, International Journal of Higher Education, Vol. 5 No. 1, pp. 208-219.

Fielding, K.S., McDonald, R. and Louis,W.R. (2008), “Theory of planned behaviour, identity and intentions toengage in environmental activism”, Journal of Environmental Psychology, Vol. 28 No. 4, pp. 318-326.

Fornell, C. and Bookstein, F.L. (1982), “Two structural equation models: LISREL and PLS applied toconsumer exit-voice theory”, Journal of Marketing Research, Vol. 19, November, pp. 440-452.

Fornell, C. and Larcker, D.F. (1981), “Evaluating structural equation models with unobservablevariables and measurement error”, Journal of Marketing Research, Vol. 18, February, pp. 39-50.

Guo, Y., Tian, M., Han, K., Johnson, K. and Zhao, L. (2016), “What determines pension insuranceparticipation in China? Triangulation and the intertwined relationship among employers,employees and the government”, The International Journal of Human Resource Management,Vol. 27 No. 18, pp. 2142-2160.

Hair, J.F., Ringle, C.M. and Sarstedt, M. (2011), “PLS-SEM: indeed a silver bullet”, Journal of MarketingTheory and Practice, Vol. 19 No. 2, pp. 139-151.

Hair, J.F., Anderson, R.E., Tatham, R.L. and Black, W.C. (1998), Multivariate Data Analysis withReadings, International ed., Prentice Hall, Englewood Cliffs, NJ.

Hair, J.F., Sarstedt, M., Pieper, T.M. and Ringle, C.M. (2012), “The use of partial least squares structuralequation modeling in strategic management research: a review of past practices andrecommendations for future applications”, Long Range Planning, Vol. 45 Nos 5-6, pp. 320-340.

Han, H. and Kim, Y. (2010), “An investigation of green hotel customers’ decision formation: developingan extended model of the theory of planned behavior”, International Journal of HospitalityManagement, Vol. 29 No. 4, pp. 659-668.

Han, H., Hsu, L. and Sheu, C. (2010), “Application of the theory of planned behavior to green hotelchoice: testing the effect of environmental friendly activities”, Tourism Management, Vol. 31No. 3, pp. 325-334.

Hartmann, P. and Apaolaza-Ibáñez, V. (2012), “Consumer attitude and purchase intention toward greenenergy brands: the roles of psychological benefits and environmental concern”, Journal ofBusiness Research, Vol. 65 No. 9, pp. 1254-1263.

Hsieh, P.J. (2015), “Physicians’ acceptance of electronic medical records exchange: an extension of thedecomposed TPB model with institutional trust and perceived risk”, International Journal ofMedical Informatics, Vol. 84 No. 1, pp. 1-14.

269

Constructioninsurance

Page 140: Engineering, Construction and Architectural

Hsu, M.H., Yen, C.H., Chiu, C.M. and Chang, C.M. (2006), “A longitudinal investigation of continuedonline shopping behavior: an extension of the theory of planned behavior”, International Journalof Human-Computer Studies, Vol. 64 No. 9, pp. 889-904.

Huang, S.S. and Hsu, C.H.C. (2009), “Effects of travel motvation, past experience, perceived constraint,and attitude on revisit intention”, Journal of Travel Research, Vol. 48 No. 1, pp. 29-44,doi: 10.1177/0047287508328793.

Hussels, S., Ward, D. and Zurbruegg, R. (2005), “Stimulating the demand for insurance”,Risk Management and Insurance Review, Vol. 8 No. 2, pp. 257-278.

Jacobs-Lawson, J.M., Webbb, A.K., Schumacher, M. and Gayer, C.C. (2010), “Age, income, health, andwillingness to pay for health insurance in late-life”, Financial Services Review, Vol. 19 No. 3,pp. 265-274.

Kashif, M. and Run, E.C.D. (2015), “Money donations intentions among muslim donors: an extendedtheory of planned behavior model”, International Journal of Nonprofit & Voluntary SectorMarketing, Vol. 20 No. 1, pp. 84-96.

Kunreuther, H. and Pauly, M (2006), “Rules rather than discretion: lessons from Hurricane Katrina”,Journal of Risk and Uncertainty, Vol. 33 Nos 1/2, pp. 101-116.

Lam, T. and Hsu, C.H.C. (2006), “Predicting behavioral intention of choosing a travel destination”,Tourism Management, Vol. 27 No. 4, pp. 589-599.

Lee, M. and Back, K. (2005), “A review of convention and meeting management research 1990-2003:identifying statistical methods and subject areas”, Journal of Convention and Event Tourism,Vol. 7 No. 2, pp. 1-12.

Lee, M.J. and Back, K. (2009), “Association meeting participation: a test of competing models”, Journalof Travel Research, Vol. 46 No. 3, pp. 300-310.

Leeuw, A.D., Valois, P., Ajzen, I. and Schmidt, P. (2015), “Using the theory of planned behavior to identifykey beliefs underlying pro-environmental behavior in high-school students: Implications foreducational interventions”, Journal of Environmental Psychology, Vol. 42, June, pp. 128-138.

Liu, J., Li, B., Lin, B. and Nguyen, V. (2007), “Key issues and challenges of risk management andinsurance in China’s construction industry: an empirical study”, Industrial Management & DataSystems, Vol. 107 No. 3, pp. 382-396.

Li, Y. and Li, J. (2006), “Comparative study of construction safety production management mode athome and abroad”, Construction Safety, Vol. 2006 No. 2, pp. 36-38.

Lim, B.T.H., Ling, F.Y.Y., Ibbs, C.W., Raphael, B. and Ofori, G. (2011), “Empirical analysis of thedeterminants of organizational flexibility in the construction business”, Journal of ConstructionEngineering and Management, Vol. 137 No. 3, pp. 225-237.

Lo, A.Y. (2013), “The role of social norms in climate adaptation: mediating risk perception and floodinsurance purchase”, Global Environmental Change, Vol. 23 No. 5, pp. 1249-1257.

Lobb, A.E., Mazzocchi, M. and Traill, W.B. (2007), “Modelling risk perception and trust in food safetyinformation within the theory of planned behaviour”, Food Quality & Preference, Vol. 18 No. 2,pp. 384-395.

Ly, B.A., Gagnon, M.P., Légaré, F., Rousseau, M. and Simonyan, D. (2015), “Determinants of physicians’intention to collect data exhaustively in registries: an exploratory study in Bamako’s communityhealth centres”, Ghana Medical Journal, Vol. 49 No. 2, pp. 90-96.

McAneney, J., McAneney, D., Musulin, R., Walker, G. and Crompton, R. (2016), “Government-sponsorednatural disaster insurance pools: a view from down-under”, International Journal of DisasterRisk Reduction, Vol. 15, March, pp. 1-9.

Matsunaga, M. (2010), “How to factor-analyze your data right: do’s, don’ts, and how-to’s”, InternationalJournal of Psychological Research, Vol. 3 No. 1, pp. 97-110.

Moss, S. (1998), “Reliability and validity of the PAS-ADD checklist for detecting psychiatric disordersin adults with intellectual disability”, Journal of Intellect Disability Research, Vol. 42 No. 2,pp. 173-183.

270

ECAM25,2

Page 141: Engineering, Construction and Architectural

Ning, Y. (2014), “Quantitative effects of drivers and barriers on networking strategies in publicconstruction projects”, International Journal of Project Management, Vol. 32 No. 2, pp. 286-297.

Ning, Y. and Ling, F.Y.Y. (2013), “Reducing hindrances to adoption of relational behaviors in publicconstruction projects”, Journal of Construction Engineering & Management, Vol. 139 No. 11,p. 04013017-1-10, doi: 10.1061/(ASCE)CO.1943-7862.0000745.

Patterson, F.D. and Neailey, K. (2002), “A risk register database system to aid the management ofproject risk”, International Journal of Project Management, Vol. 20 No. 5, pp. 365-374.

Perugini, M. and Bagozzi, R.P. (2001), “The role of desires and anticipated emotions in goal-directedbehaviors: broadening and deepening the theory of planned behavior”, British Journal of SocialPsychology, Vol. 40 No. 2001, pp. 79-98.

Petrolia, D.R., Landry, C.E. and Coble, K.H. (2013), “Risk preferences, risk perceptions, and floodinsurance”, Land Economics, Vol. 89 No. 2, pp. 227-245.

Phillip, S. and Anita, E. (2010), “Efficacy of the theory of planned behaviour model in predicting safefood handling practices”, Food Control, Vol. 21 No. 7, pp. 983-987.

Ren, Y. and Yao, X. (2009), “Project cost risk control research”, Economic Research Guide, Vol. 2009,pp. 15-16.

Ryu, K. and Jang, S. (2006), “Intention to experience local cuisine in a travel destination: the modifiedtheory of reasoned action”, Journal of Hospitality & Tourism Research, Vol. 30 No. 4, pp. 507-516.

Salganik, M.J. and Heckathorn, D.D. (2004), “Sampling and estimation in hidden populations usingrespondent-driven sampling”, Sociological Methodology, Vol. 34 No. 1, pp. 193-239.

Sammon, C. (2002), “Insurance agent and broker liability: crossing the two way street”, Ohio NorthernUniversity Law Review, Vol. 29 No. 2002, pp. 237-238.

Shan, M., Chan, A.P., Le, Y. and Hu, Y. (2015), “Investigating the effectiveness of response strategies forvulnerabilities to corruption in the Chinese public construction sector”, Science and EngineeringEthics, Vol. 21 No. 3, pp. 683-705.

Sola, A.J., Arowojolu-Alagwe, T., Taiwo, E.M. and Abiodun, B.T. (2013), “Adequacy of builders riskinsurance policy in Nigeria building industry”, PM World Journal, Vol. II No. XI, pp. 1-12.

Taylor, S. and Todd, P. (1995), “Understanding household garbage reduction behavior: a test of anintegrated model”, Journal of Public Policy and Marketing, Vol. 14 No. 2, pp. 192-205.

Tonglet, M., Phillips, P.S. and Read, A.D. (2004), “Using the theory of planned behaviour to investigatethe determinants of recycling behaviour: a case study from Brixworth, UK”, Resources,Conservation and Recycling, Vol. 41 No. 3, pp. 191-214.

Voon, V., Morris, L.S., Irvine, M.A., Ruck, C., Worbe, Y., Derbyshire, K., Rankov, V., Schreiber, L.R.,Odlaug, B.L., Harrison, N.A., Wood, J., Robbins, T.W., Bullmore, E.T. and Grant, J.E. (2015),“Risk-taking in disorders of natural and drug rewards: neural correlates and effects ofprobability, valence, and magnitude”, Neuropsychopharmacology, Vol. 40 No. 4, pp. 804-812.

Wallach, R. and Jasper, J. (2010), “Insurance incentive program for promoting the purchase or lease ofan automobile”, United States Patent, Patent No. US7,801,750,B1, September 21, available at:https://patentimages.storage.googleapis.com/87/29/5a/db87dcb8485bdc/US7801750.pdf(accessed May 10, 2016).

Wang, C., Harris, J. and Patterson, P.G. (2012), “Customer choice of self-service technology: theroles of situational influences and past experience”, Journal of Service Management, Vol. 23No. 1, pp. 54-78.

Xiong, B., Skitmore, M., Xia, B., Masrom, M.A., Ye, K. and Bridge, A. (2014), “Examining the influenceof participant performance factors on contractor satisfaction: a structural equation model”,International Journal of Project Management, Vol. 32 No. 3, pp. 482-491.

Zhai, X., Liu, A.M.M. and Fellows, R. (2014), “Role of human resource practices in enhancingorganizational learning in chinese construction organizations”, Journal of Managementin Engineering, Vol. 30 No. 2, pp. 194-204, available at: http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000207

271

Constructioninsurance

Page 142: Engineering, Construction and Architectural

Zhao, X., Feng, Y., Pienaar, J. and O’Brien, D. (2017), “Modelling paths of risks associated with BIMimplementation in architectural, engineering and construction projects”, Architectural ScienceReview, Vol. 60 No. 6, pp. 472-482.

Zhao, D., Mccoy, A.P., Kleiner, B.M., Mills, T.H. and Lingard, H. (2016), “Stakeholder perceptions of riskin construction”, Safety Science, Vol. 82, February, pp. 111-119.

Further reading

Zhao, X., Hwang, B.G. and Phng, W. (2014), “Construction project risk management in Singapore:resources, effectiveness, impact, and understanding”, Ksce Journal of Civil Engineering, Vol. 18No. 1, pp. 27-36.

About the authorsJunying Liu is a Professor in the Department of Construction Management, Tianjin University (China).She received her PhD Degree from the School of Construction Management & Engineering, Universityof Reading (UK) in 2005. She is a member of the Chartered Institute of Building (CIOB).

Sen Lin is currently a Postgraduate Research Student in Construction Management at TianjinUniversity (China). She received her BSc in Construction Management from the Jiangnan University(China) in 2010.

Yingbin Feng is a Senior Lecturer in Construction Management at the Western Sydney University(Australia). Earlier in his career, he lectured at Chongqing University (China) and also worked as aStructural Engineer at China’s No. 6 Institute of Project Planning & Research of Machinery Industry,between 2000 and 2007. Yingbin was awarded a PhD Degree by the National University of Singapore(NUS) in 2012. He also has a BSc in Civil Engineering and an MSc in Construction Management fromthe Chongqing University. Yingbin Feng is the corresponding author and can be contacted at:[email protected]

For instructions on how to order reprints of this article, please visit our website:www.emeraldgrouppublishing.com/licensing/reprints.htmOr contact us for further details: [email protected]

272

ECAM25,2

Page 143: Engineering, Construction and Architectural

Priming effects on safetydecisions in a virtualconstruction simulator

Xueqing Lu and Steven DavisSchool of Civil and Environmental Engineering, University of New South Wales,

Sydney, Australia

AbstractPurpose – The purpose of this paper is to investigate the influence of priming on people’s risk perceptionsand safety decisions in a virtual construction simulator.Design/methodology/approach – Civil engineering students were recruited to interact with a virtualreality (VR) safety simulator. They were divided into four groups covering with and without sound andwith and without priming factors. Data were collected on the risks that they perceived and the safety levels oftheir actions.Findings – It was found that obvious stimuli in a virtual environment with sound help people to recognisemore hazards near the location of the stimuli. Sound is helpful in training simulations to create high levels ofpresence. However, priming factors are not suitable to be added to VR simulators for training purposes.Priming of safe choice results in people taking fewer risks in the VR simulator, but this does not carry overinto other situations. Compared to priming effects, being “injured” in a training simulator with soundimproves trainees’ ability to make safe decisions.Originality/value – VR simulation is helpful in construction training because of its unique ability to givetrainees exposure to dangerous situations without physical risk. However, the overloading the workingmemory of users is detrimental to the outcomes. Therefore, the optimum level of complexity in VR simulatorsshould be further studied.Keywords Decision making, Construction management, Safety, Virtual reality, Training methods, PrimingPaper type Research paper

IntroductionConstruction employers around the world have the obligation to provide adequate safetytraining to employees, involving instruction, live demonstrations and hands-on practice, etc.(Huang and Hinze, 2006; Menzel and Gutierrez, 2010; Stromme, 2011). The reason safetytraining is of great importance is that the construction industry has high fatality and injuryrates, for example, in Australia the construction industry has the third highest fatality andinjury rate (Safe Work Australia, 2015). This has led researchers to look for improvedmethods of training in order to reduce the number of accidents in construction work. Virtualreality (VR) simulation is one of the most advanced tools under development that can beused in construction safety training. VR simulators are already being used in manysituations, for example, the US Air Force uses them for recruiting youth (Nafarrete, 2015).VR enables training to take place in an environment that does not exist in, or is not suitableto be created in, the real world due to safety or cost concerns. Many researchers focus on thestudy of achieving a high level of presence in a VR simulator (Sanchez-Vives and Slater,2005; Price and Anderson, 2007; Lin et al., 2011). A high level of presence in a VR simulatormeans that the user experiences the virtual environment (VE) as if they were in the realworld. Some researchers have also studied the practicability of applying VR simulators tosafety training (Waly and Thabet, 2003; Van Wyk and De Villiers, 2009). Though a numberof construction vehicle simulation games exist online, VR simulation has rarely been used inconstruction safety studies.

In this study, the influence of priming on people’s risk perception and safety decisions in avirtual construction simulator is investigated. Priming is the implicit memory effect that

Engineering, Construction andArchitectural Management

Vol. 25 No. 2, 2018pp. 273-294

© Emerald Publishing Limited0969-9988

DOI 10.1108/ECAM-05-2016-0114

Received 27 August 2016Revised 6 March 2017

Accepted 22 October 2017

The current issue and full text archive of this journal is available on Emerald Insight at:www.emeraldinsight.com/0969-9988.htm

273

Virtualconstruction

simulator

Quarto trim size: 174mm x 240mm

Page 144: Engineering, Construction and Architectural

previous stimuli have on the response to a subsequent stimulus (Gulan and Valerjev, 2010).It can occur in many circumstances. There are two types of priming that may affect people’srisk perception and safety decisions: conceptual priming and repetition priming. Conceptualpriming occurs when an item with a similar form or meaning is primed (Nunez and Blake,2003). In an experiment by Marsh et al. (1999), participants were divided into two groups.One group was given three pictures of hostile space creatures to watch for 30 seconds each,and another group was asked to sit for 90 seconds with no pictures. Both groups were askedto draw their own space creatures. The features of the creatures drawn by the first group arecloser to the features of the given space creatures (fangs, spikes and weapons) than thosedrawn by the second group. Similarly, the actions of other people in a situation will affect howsomeone will respond in that situation. This particularly happens when the person is seekingsocial acceptance, or feels that another person has more expertise (Pendry and Carrick, 2001).Repetition priming occurs when a stimulus or a task is similar to what people haveexperienced previously (Schacter and Addis, 2007). When a similar situation is experienced ora similar stimulus repeatedly appears, people can respond faster and make more accurateresponses (Allenmark et al., 2015). For example, in a two-phase experiment by Ellis et al. (1990)on face processing, the participants were first primed by 12 famous people ( four politicians,four actors and four sportsmen) and their faces when rating their familiarities with thesefaces, and then were asked to identify the role (politician/actor/sportsman) of 24 given facesincluding the 12 faces in phase 1. The participants responded more accurate and faster on the12 repeated faces than the other 12 new faces.

Previous research has suggested that sound and priming factors may interact toinfluence users’ level of presence in a VE (Lu and Davis, 2016). Thus in this study, bothsound and priming are considered as independent variables. There are two types of soundsin this study: background sound and priming sound.

Literature reviewThe construction industry is one of the industries with the highest fatality and injury ratesin many countries, such as the USA (Abudayyeh et al., 2006), the UK (Cameron andDuff, 2007) and China (Choudhry et al., 2009; Cheng et al., 2012). Abdelhamid and Everett(2000) consider accidents to arise from either unsafe conditions or unsafe acts and henceidentified three root causes of construction accidents: failing to identify hazards beforestarting the work; working despite hazards being present; and acting unsafely.These reasons can be summarised into risk perception and safety decision. The ability toidentify safety risks and make safe decisions can be upgraded by safety training. Researchhas suggested that construction workers’ safety performance is highly related to how theyare trained (Sawacha et al., 1999). Carrying out safety training is helpful in changingthe safety culture among workers, and subsequently changes workers’ safety attitudes(Harvey et al., 2001). Therefore, adequate health and safety training can effectively reducethe injury rate in a construction project.

VR simulation is attracting research as an emerging training tool. A VE is a collectionof 3D geometric entities rendered in real-time by computer, which provides the users anopportunity to interact with the environment. Simulation is the imitation of a real-worldprocess or system over time (Banks et al., 2000). Thus, a VR simulation can bedefined as the imitation of a real-world process or system in a VE. It has been consideredas a more realistic and interesting tool than traditional training methods, and thus highlydemanded by trainees. Past studies have evaluated the effectiveness of applying VR inconstruction education. Sacks et al. (2013) examined the training value of VRin conventional safety training, and found that training with VR is more effective, andthe duration of participants’ concentration is longer than traditional safety training.The advantage of applying VR simulation in construction training is that when the

274

ECAM25,2

Page 145: Engineering, Construction and Architectural

trainees make improper decisions, they can experience the consequences withoutbeing exposed to any real danger (Filigenzi et al., 2000). On the other hand, the problem ofVE simulation is that trainees may not take the consequences as seriously in the virtualworld as in the real world, because they do not physically get injured. Therefore, a mainfocus of VR simulation technology has been on enhancing trainees’ sense of presence inthe VE.

Witmer and Singer (1998) pointed out that involvement and immersion are the two maininterdependent characteristics of presence. Furthermore, four contributing factors (controlfactors, sensory factors, distraction factors and realism factors) influence presence (Witmerand Singer, 1998). Psychologists and neuroscientists have also linked presence to brain andbody responses, such as cognition (Sanchez-Vives and Slater, 2005). Attention is animportant aspect related to how people perceive information in the VE and in the real world.Darken et al. (1999) suggested that attention may be a reasonable quantitative measure ofpresence. Different levels of attention lead to different levels of involvement and immersion.Attention is a cognitive process of selection and selective processing (Wood et al., 2006).Meanwhile, when people are exposed to a VE, their attention has been found to be highlycorrelated with how they have been primed (Dinh et al., 1999). Research has foundthat people can observe more objects in a VE when they have been primed by relatedinformation, and their memory about the objects in the VE lasts longer after priming(Dinh et al., 1999). This finding supports the conclusion by Wood et al. (2006) that attentionis a top-down, cognitively driven process. Research also shows that strong stimuli cancapture people’s visual attention, and people can observe more objects in a high fidelity VE(Nunez and Blake, 2003). Nunez (2004) proposed a constructionist cognitive model thatdescribes the construction and reconstruction of cognitive processes considering theinformation flow between working memory and long-term memory. Thus, the addition ofdifferent stimuli (related or unrelated to people’s expectation of the VE) result in payingattention to different things.

Previous research also suggests that priming is a mediator variable for presence(Nunez and Blake, 2003). This means that priming will increase the effects of other variableson presence, compared to their effect without the priming present. Thus, if the designersmake good use of stimuli in a VE, priming can reinforce the effects of these stimuli onpeople’s sense of presence.

In a study conducted by Nunez and Blake (2003) of the effect that conceptual priming hason presence, subjects were split into two groups that were initially given passages to readthat were either related or unrelated to a subsequent VE that they experienced. Each groupwas then further divided into two groups, one of which would experience a high fidelity VE,while the other experienced a low fidelity VE. The difference in presence reported by thepeople experiencing the different levels of fidelity was affected by the initial level of priming.Orgs et al. (2006) designed an experiment considering both environmental sound and wordsas priming factors, where they found that the subjects reacted faster when an environmentalsound was followed by a related word appearing on a screen than vice versa. Thus soundmay function as a priming factor similar to the conceptual priming of Nunez and Blake(2003). Lu and Davis (2016) found that participants have higher safety performance whenbackground sounds and animations of other construction workers are either both present orboth not present in the VE. These animated workers act as a conceptual priming factor,which helps the participants to behave safely. Thus, it is important to understand theinteraction between sound and priming. This study aims to examine the potentialinteraction between sound and priming, and their influence on people’s safety decisions in avirtual construction simulator. Figure 1 presents a hypothesised model for theseinteractions. It is based on (Figure 1) Lu and Davis (2016) with the addition of the two typesof priming.

275

Virtualconstruction

simulator

Page 146: Engineering, Construction and Architectural

HypothesesBased on the literature review, the hypotheses proposed in this study are:

H1. Obvious stimuli in a VE with sound lead to people recognising more hazards.

H2. Priming of safe choices results in people taking fewer risks in a VR simulator.

H3. The priming effect is persistent to a different environment.

MethodsOne of the safety problems on construction sites is workers deciding to cut corners in orderto finish their tasks more quickly. Thus, the scenarios in this study have been designed toexamine this behaviour.

Test environmentConsidering experimental bias may occur in a single environment, two virtual 3Denvironments with different features were created to investigate people’s safety decisions inthis study. The basic activity of the experimental subject in both environments is to movebricks using a wheelbarrow from one location to another, where they have to choosebetween a hazardous shortcut and a safe route. The first environment includes a safetyhazard on the ground, and the second environment includes a safety hazard in the air.Each of the environments has four types of settings: with sound and with priming factors,with sound and without priming factors, without sound and with priming factors, withoutsound and without priming factors. The environments with sound are consideredas having higher fidelity. As verbal sound has been studied as a conceptual priming factor(Orgs et al., 2006), the warning sound in this study was considered to be a priming factor,whereas background sounds were categorised as sound factors. The verbal sound andvisual priming factors are all based on the concept of “safety”. If this conceptual primingsuccessfully influenced the participants’ safety behaviours, they should choose the saferoute when walking in the construction sites. In this study, when a subject repeats a task ina second virtual construction simulator, the previous experience in the first virtualconstruction simulator is the repetition priming factor.

ConceptualPriming + +

+

+

+

+ +

+

Enhance RiskPerception

ConstructionSound

Audio-visual

RepetitionPriming Familiarity

Enhance Senseof Presence

Distraction

Annoyance

Safer Decisions

Noise

SalientSound

Source: Lu and Davis (2016)

Figure 1.Model of how priminginfluences user safetydecisions in aconstruction VRsimulator

276

ECAM25,2

Page 147: Engineering, Construction and Architectural

The first virtual environment (VE1). VE1 is a simulation of a construction site with anexcavation dividing the site. The excavation is filled with water and a pump is pumping outthe water. An electronic depth gauge has been placed in the water with its cable supportedby a plank across the excavation and connected to a laptop. There was a virtual researcheranalysing the data on the laptop. In the east end of the construction lab, two bridges withhandrails have been placed to allow people to cross the excavation safely, as shownin Figure 2.

A number of priming factors were added to this environment. A red warning safety netwas installed around the excavation. Warning boards were hung from the safety net.The safety net at both sides of the plank was cut and dropped on the ground. A danger signwas placed on the broken fence so that it would be clearly visible. This was designed tomake it clear that the plank was not meant to be used as a normal thoroughfare. In addition,virtual workers were added to the VE pushing wheelbarrows along the longer safe route.This is a hint that the avatar controlled by the participant should also walk on the saferoute. When an avatar steps on the plank, the nearest virtual researcher turns around andflashes his palm to show he wants the avatar to stop walking. At the same time the virtualresearcher shouts “Stop! Watch out!” to the avatar. These priming factors added in VE1 aremarked as in Figure 3.

In the environment without priming factors, the excavation was left unattended.No barriers or safety net around the excavation, and no workers working in the constructionlab except for the researcher. When an avatar steps on the plank, the researcher does notwarn to stop.

The sound factors added to VE1 included: the creaking sound of the thin plank when theavatar walks on it; the avatar’s footsteps; the sound that the sand makes as wheel ofthe wheelbarrow rolls over it; other construction workers talking in the background; theresearcher warning the avatar when the avatar was attempting to walk on the thin plank;other construction workers digging with a spade; the engine and sound of water runningwhen the water pump was working; a truck’s engine in the background; a steel saw workingin the background; a hammer knocking on steel in the background.

The second virtual environment (VE2). VE2 was a simulation of a construction site,which is enclosed by temporary walls. The construction site mainly consists of a buildingarea, a storage area and some construction accesses. As shown in Figure 4, two virtual

Brick pile

Unsafe route

Excavation

Destinationpoint Wheelbarrow

Water pump

Depth gauge

Safe route

Figure 2.Plan view of VE1

277

Virtualconstruction

simulator

Page 148: Engineering, Construction and Architectural

workers were standing at one entrance of the storage area, helping tie a universal beam tothe hook of a crane and directing the crane to lift the universal beam to the building area.Thus it is unsafe to walk under the universal beam. These two workers were always lookingtowards the steel being lifted.

In the environment with priming factors, safe work and first aid notices were “painted”on the enclosures of the construction site. There were fences around the storage area andnear each side of the truck. However, the fences that intended to block the path near thetruck crane looked like they had been moved by someone so an unsafe shortcut had beencreated. Additional virtual workers pushed their wheelbarrows containing sand around thestorage area, which provides a safe path, but much longer than the shortcut. When the

Brick pile

Unsafe route

Storage area

CraneUniversal beam

Destinationpoint

Wheelbarrow

Safe route

Figure 4.Plan view of VE2

Figure 3.Priming factorsin VE1

278

ECAM25,2

Page 149: Engineering, Construction and Architectural

avatar controlled by the participant walks through the unsafe shortcut, the workersstanding by would shout “Stop! Watch out!” at the avatar. The priming factors added inVE2 are marked as in Figure 5.

In the environment without priming factors, there are no safe work or first aid notices onthe enclosures, or fences, no virtual workers walking on the safe route, and no warningsfrom the other two workers. The two virtual workers assisting the crane are still present, butthey do not react to the avatar.

The sound factors added to VE2 included: the creaking sound of crane rope when it waslifting a steel bar; the avatar’s footstep; the wheel of the wheelbarrow rolling on the ground;other construction workers talking in the background; the truck’s engine; the worker nearthe truck warning the avatar when the avatar was attempting to walk on the unsafe route;the creaking sound of a plank in the background; an excavator working in the background;other construction workers digging with a spade in the background; the engine and soundof a water pump working in the background; a steel saw working in the background; ahammer knocking on steel in the background.

Interface and layout. The VR simulator interfaced with keyboard and mouse. The keyswere same as the standard keys used in first-person computer games (W forwards, A and Dleft and right, S backwards). The TAB key was used to toggle between holding thewheelbarrow and not holding it, so that bricks could be loaded and unloaded.The participants could use the mouse to control the avatar’s viewpoint and its directionof forward movement. There was a cursor (“+”) at the centre of the avatar’s viewpoint.A brick could be picked up, moved and released by clicking, dragging and releasing themouse when the cursor was hovering over the brick. The “1” key functioned as restart, sothat when the participants made mistakes and “broke” the wheelbarrow they could have anew wheelbarrow to continue their simulation. Figure 6 shows a player view of VE1.

Sampling procedurePostgraduates and final-year undergraduates studying civil engineering in a university inAustralia were invited to participate in the study through the school’s e-mail list.The students invited all have at least three years’ full-time study and general knowledge of

Debug PropertiesWeelbarrow.tyre.001: “push”=0Game: “time”=81Game: “bricks in target area”=0Game: “bricks in wheelbarrow”=0Game: “game time”=81Plane.003: “crane direction”=2

Figure 5.Priming factors

in VE2

279

Virtualconstruction

simulator

Page 150: Engineering, Construction and Architectural

the construction industry. The recruiting e-mail contained the information of the aim,payment, content, location and health concerns (such as motion sickness), as well as thecriteria of selecting participants and the investigator’s information. There was also a pre-experiment questionnaire in the e-mail. Each participant received an AU$20 guaranteedpayment, and potentially an extra $10 in bonus payments. Questions included in thepre-experiment questionnaire are: gender, age, construction work experience, first-personcomputer game frequency (hours per week), and first-person computer game experience(months/years). These questions were used for randomizing the subjects into differentgroups. The reason for asking the participants both of their first-person computer gamefrequency and experience was because there might be some participants who had given upplaying first-person computer games, and hence have a game frequency of 0, but actuallyhave many years’ game experience.

Over a five-week period 72 students expressed interest in participation. In total, 51 ofthese students became experimental subjects.

Based on the sample results, significant differences were found between the twosituations: both sound and priming were present or neither of them was present, and onlysound or only priming was present. Therefore, to calculate the required sample size betweenthese two situations, using the sample size calculation equation for binomial distributiongiven by Van Belle (2011):

n ¼ 16p 1�pð Þp0�p1ð Þ2 (1)

In Equation (1), p ¼ p0þp1ð Þ=2, where π0 and π1 are the probability of success in eachproportion. This equation is based on a level of significance of 0.05 and a power of 0.8.

According to this equation, the required sample size is 47. Thus, a sample size of51 is sufficient.

Test procedureThe experiment for each participant consisted of four parts: an introductory video, atwo-minute trial, two virtual tests and a survey.

Figure 6.Player view

280

ECAM25,2

Page 151: Engineering, Construction and Architectural

First, the participants were required to read and sign a consent form and watch athree-minute introductory video prior to their tests. The participants were told that the aim ofthis study was to test the wheelbarrow simulation and to investigate the essential factors for aVR simulator, i.e. they were not told that the experiment was actually about safety.This deception was used to reduce the Hawthorne effect (Wickström and Bendix, 2000).The video introduced the basic information and requirements of the experiment, as well as theuser interface. The VE in the introductory video is a simplified environment. It consisted of aplane which represented the ground, a wheelbarrow, several virtual bricks and a target area.

After watching the introductory video, each participant was given two minutes tocomplete the whole process of moving the bricks by manipulating a virtual trial.The process involved: walk towards the back of the wheelbarrow, “hold” the wheelbarrow,push the wheelbarrow to the brick pile, release the wheelbarrow, load the wheelbarrow withseveral bricks, “hold” the wheelbarrow again, push the wheelbarrow to the target area andunload the wheelbarrow. The VE in this trial was also the same simplified environment asused in the introductory video.

The third part included two tests on the computer in different virtual constructionenvironments. The participants were assigned to different groups, thus, the order of VE andelements of the virtual tests were different (Table I).

As shown in Table I, Groups A1, A2, C1 and C2 had sound in their VR simulator, and theother four groups did not have sound in their VR simulator. Groups A1, A2, B1 and B2 hadpriming factors in their VR simulator, and the other four groups did not have primingfactors in their VR simulator. Participants in Groups A1, B1, C1 and D1 experienced VE1before VE2, and the other four groups experienced VE2 before VE1. No matter which groupthe participants were in, all of them have their second test without priming factors. The aimof this was to investigate whether the prior experience of priming will influence theparticipants’ safety behaviours in the subsequent environment without any priming factors.

The task for the participants was to move 60 bricks from the brick pile to the destinationpoint without dropping any bricks in each environment. Both tests have a time limit of20 minutes. If they made any mistake that broke the bricks, the time limit would be reducedas a penalty. The length of time deducted depended on the severity of the “injury” or “loss”.Table II illustrates the circumstances and the length of time being deducted.

A monetary reward was given to the participants based on how long they took tocomplete the tests. If the participants finished one virtual task in less than 12 minutes, theywould receive an extra AU$5 reward. Thus, if they finished both basks in 12 minutes, theywould receive a total of AU$30 (including the guaranteed payment of AU$20).

Circumstances Length of time deducted

VE1 VE2The avatar or the wheelbarrow fell intothe excavation

The avatar was hit by the steel liftedby the crane

5 mins

The participant overturned or overloaded the wheelbarrow 2minsTable II.

Time deduction

With priming Without primingVirtual test grouping VE1 → VE2 VE2 → VE1 VE1 → VE2 VE2 → VE1

With Sound (70 dB) A1 (n¼ 7) A2 (n¼ 7) C1 (n¼ 7) C2 (n¼ 6)Without Sound B1 (n¼ 6) B2 (n¼ 6) D1 (n¼ 6) D2 (n¼ 6)

Table I.Virtual test grouping

281

Virtualconstruction

simulator

Page 152: Engineering, Construction and Architectural

After the experiment the participants were debriefed about the real aim of the study.After they were fully informed about the experiment, they then filled a questionnairein accordance with their virtual tests.

Subject groupingA total of 51 students were randomly assigned to eight groups according to their answers tothe pre-experiment questionnaire, as shown in Table I. The factors in the pre-experimentquestionnaire are considered to be confounding factors that are best controlled by assigningthe participants randomly. Participants’ age and gender are the two main concerns whengrouping. Table III shows the basic information of each group.

Analysis methodThe variable of interest in this study is priming factors. As sound has been found to have aninteraction effect with some priming factors, the results distinguished those with sound andthose without sound.

Results were analysed using the between-subjects method (Birnbaum, 1999). This isbecause it is expected that the participants’ behaviour in the second test would besignificantly altered by their experience from the first test, in particular the knowledge thatthe simulation might contain hazards. Thus, the data drawn from any second test could notbe compared with people’s behaviour the first time they use the simulator, except whenexplicitly testing for learning effects. As each group contained two subgroups that had thesame settings but different VEs, both the overall results (VE1+VE2) and the results of eachindividual VE were analysed. Table IV represents how the groups were compared in theresult analysis and the methods used.

The method of testing hypotheses on the equality of two binomial proportions(two-tailed) was applied to analyse the relationship between priming factors and people’scognition, especially whether they noticed the safe route far away from their starting pointor not (Montgomery et al., 2009; Walpole, 1974).

With priming Without primingInformation With sound Without sound With sound Without sound

Number of participants 14 12 13 12Average age (years) 24.4 25.4 23.7 24.5Percentage of females (%) 14.3 16.7 23.1 25.0Work experience (months) 14.0 6.88 4.27 11.8Game frequency (hours/week) 4.00 2.63 4.31 3.50Game experience (years) 3.47 3.09 2.28 2.68

Table III.Subject information indifferent groups

Hypothesis Experimental group Control group

H1 A1(VE1)+A2(VE2) C1(VE1)+C2(VE2)B1(VE1)+B2(VE2) D1(VE1)+D2(VE2)

H2 A1(VE1)+A2(VE2) C1(VE1)+C2(VE2)B1(VE1)+B2(VE2) D1(VE1)+D2(VE2)

H3 A1(VE2)+A2(VE1) D2(VE2)+D1(VE1)B1(VE2)+B2(VE1)C1(VE2)+C2(VE1)D1(VE2)+D2(VE1)

Table IV.Analysis groupsand methods

282

ECAM25,2

Page 153: Engineering, Construction and Architectural

According to Walpole (1974), to test the difference between two proportions should test thenull hypothesis H0: p1¼ p2¼ p, where p1 and p2 are the two population proportions of theattribute under investigation:

p1 ¼x1n1; and p2 ¼

x2n2

(2)

where x1 and x2 are the number of successes in each of the two samples. Therefore, the valueof the standard normal variable Z when H0 is true is:

z ¼ p̂1�p̂2ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiðp1q1=n1Þþðp2q2=n2Þ

p ¼ p̂1�p̂2ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffipq 1

n1

� �þ 1

n2

� �h ir (3)

where p̂1 and p̂2 are the proportion of success, n1 and n2 are the selected independentsamples’ sizes. To estimate the value of p in Equation (2), pool the data from both samples:

p̂ ¼ x1þx2n1þn2

(4)

Thus:

z ¼ p̂1�p̂2ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffip̂q̂ 1

n1

� �þ 1

n2

� �h ir (5)

where q̂ ¼ 1�p̂.Reject H0 if z falls in the critical region, which is ZW1.96 and Zo−1.96 when α¼ 0.05,

otherwise accept H0.As some of the results in this study are not significant, it is essential to calculate the

power of the results. According to Chow et al. (2007), the power considering the hypotheses:

H 0: pA ¼ pB

H 1: pAapB

when testing the binomial proportions A (with probability pA and sample size nA) and B(with probability pB and sample size nB) is:

1�b ¼ F z�z1�a2

� �þF �z�z1�a

2

� �; z ¼ pA�pBffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi

pA 1�pAð Þð Þ=nAþ pB 1�pBð Þð Þ=nBp (6)

whereΦ is the standard Normal distribution function, α is Type I error, and β is Type II error.

ResultsCognition and risk perceptionAs expected in H1, a higher percentage of participants in the environment without primingfactors reported that they did not notice the safe route in the environment with sound.Table V shows the percentage of participants who saw the safe route in each group.

In Table V, the second columns of p-value and power are the calculation for the twosituations mentioned in the sampling procedure section, that is, either sound or priming vsboth or neither. The individual tests are not conclusive for either rejecting the nullhypothesis (p-valueW0.05) or the alternative hypothesis (powero0.8). This indicates that

283

Virtualconstruction

simulator

Page 154: Engineering, Construction and Architectural

larger sample sizes are required to give the experiments more power so that one of thesehypotheses can be rejected conclusively. However, it is noted that priming seems to increasethe likelihood that participants will see the safe route when sound is present, but decrease itwhen the sound is absent. Testing this hypothesis yields a p-value of 0.036 despite having apower of only 0.583. Thus, we can accept that there is an interaction between sound andpriming on the effect of influencing people’s cognition in the VEs.

As shown in Table V, although differences occurred in different environments, it couldbe concluded that people are more likely to notice details regarding the environment whensound and priming factors are both present. When either sound or priming factors weremissing from the environment, a higher proportion of participants did not notice the saferoute. However, these effects are not additive. In fact, in VE1 the subjects without eitherpriming or sound all noticed the safe route.

In terms of risk perception, the particular risks that the participants were expected toidentify under the influence of the priming factors are: the thin plank in VE1 may break ifoverloaded; the steel lifted by the crane in VE2 may drop and hit people walking under it.

From Table VI, more people identified the risks in the environments with both sound andpriming factors on the whole. However, when analysing the two environments separately,differences were revealed. In line with the results in a previous study, in the firstenvironment, more people identified the related risk when sound and priming factors wereeither both present or both not. On the other hand, in the second environment, the resultsturned out to be the opposite. More people identified the related risk when either only soundor only priming factors was added to the environment. It appears that this difference isstrongly related to the location of the risk. People are not used to looking up. It is, therefore,

With priming Without priming p-value Power

OverallWith sound 100% (n¼ 14) 76.9% (n¼ 13) 0.056 0.036 0.508 0.583Without sound 75% (n¼ 12) 91.7% (n¼ 12) 0.0.274 0.204

VE1With sound 100% (n¼ 7) 71.5% (n¼ 7) 0.126 0.028 0.387 0.673Without sound 66.7% (n¼ 6) 100% (n¼ 6) 0.122 0.411

VE2With sound 100% (n¼ 7) 83.3% (n¼ 6) 0.260 0.490 0.196 0.106Without sound 83.3% (n¼ 6) 83.3% (n¼ 6) 1.000 0.050

Table V.Percentage ofparticipants whoreported seeing thesafe route

With priming Without priming p-value Power

OverallWith sound 71.4% (n¼ 14) 61.5% (n¼ 13) 0.586 0.0.668 0.085 0.069Without sound 50.0% (n¼ 12) 50.0% (n¼ 12) 1.000 0.050

VE1With sound 85.7% (n¼ 7) 42.8% (n¼ 7) 0.094 0.048 0.466 0.577Without sound 33.3% (n¼ 6) 66.7% (n¼ 6) 0.248 0.234

VE2With sound 57.1% (n¼ 7) 83.3% (n¼ 6) 0.306 0.142 0.193 0.340Without sound 66.7% (n¼ 6) 33.3% (n¼ 6) 0.248 0.234

Table VI.Proportion ofparticipants whoreported identifyingthe risk

284

ECAM25,2

Page 155: Engineering, Construction and Architectural

recommended that separate studies are performed to investigate the effect that the locationof the risk has on the ability of people to notice it. Since the p-value for the first environmentwhere the risk is not in an unusual location is significant it seems reasonable to accept thatunder normal circumstances sound moderates priming.

Safety decisionThe ultimate goal of employing a virtual construction simulator in safety training is to trainpeople to make safe decisions. Thus, it is essential to test the effect on people’s safetydecisions in order to decide whether priming factors should be added to a virtualconstruction simulator. In this study, the particular safety decisions investigated was whichroute the participants chose to use for their tasks in the construction environment. Table VIIpresents the percentage of the participants who used the unsafe route. The reasons they usethe unsafe route may include: not recognising the related hazards, or deciding to actunsafely to get the job done faster.

It can be seen from Table VII that 47 out of 51 people used the unsafe route at some stage.The fact that so many people used the unsafe route shows that the experiment met the goalof making the unsafe route an easy default for people to follow. Only 4 out of the 51participants did not use the unsafe route at any stage in their first VE. For two of thesepeople it was VE1 and for the other two it was VE2. Both of the participants that never usedthe unsafe route in VE1 had sound and priming factors. For the corresponding participantsin VE2 one of them had both sound and priming factors, and the other had neither.Thus having both sound and priming factors present appears to give the highestprobability of ideal behaviour.

Some participants always used one route all the other, while others used both at differenttimes. The percentage of participants who used the safe route at any stage is shown inTable VIII. The reason they used the safe route may because: they noticed the relatedhazards and decided to act safely, or the virtual workers primed their behaviour and so theyfollowed the safe route without considering any other route.

It can be seen from Table VIII that more people decided to use the safe route when soundand presence were either both present or both absent. Overall, more people chose the saferoute in VE2 than in VE1. However, both of the two environments show the same trend interms of their decision on whether to use the safe route. The primary result of this is thatpriming is only useful when there is sound present. Without sound the priming seems tohave a negative impact. It is conjectured that the addition of sound “normalises” the VE tocreate a higher level of presence in such a way that the participants are free to noticethe priming. Therefore, they trust the priming cues. In the case where there is no sound, thepriming does not seem to be noticed by the participants. Perhaps when there is no sound,

With priming Without priming p-value Power

OverallWith sound 78.6% (n¼ 14) 100% (n¼ 13) 0.076 0.042 0.498 0.586Without sound 100% (n¼ 12) 91.7% (n¼ 12) 0.308 0.181

VE1With sound 71.4% (n¼ 7) 100% (n¼ 7) 0.126 0.142 0.389 0.338Without sound 100% (n¼ 6) 100% (n¼ 6) – 0.050

VE2With sound 85.7% (n¼ 7) 100% (n¼ 6) 0.336 0.156 0.192 0.332Without sound 100% (n¼ 6) 83.3% (n¼ 6) 0.296 0.196

Table VII.Percentage of

participants who usedthe unsafe route at

any stage

285

Virtualconstruction

simulator

Page 156: Engineering, Construction and Architectural

the participants can easily focus on their task when there are fewer stimuli “distracting”them even though their sense of presence is low. On the whole, absence of sound results inless safe behaviour than absence of priming.

To further study whether sound influences the priming effects in the VE, it is important toanalyse the proportion of participants who revealed the behaviour of being primed.The students who used the unsafe route initially may change their mind in two circumstances:the first one is that their behaviour was influenced by the priming factors; the second one isthat their initial behaviour caused injury so they have to change their decision. Table IX is theanalysis of the proportion of participants who were primed in the VE.

As shown in Table IX, the proportion of participants who used the safe route without orbefore being injured in the group with both sound and priming factors is significantly largerthan the other three groups. In the group with priming factors but without sound, theproportion of participants who used the safe route without or before being injured does notvary much from the groups without priming factors. Thus, it can be concluded that thepriming effect on the participants’ safety decisions is greater when sound is present.

Training effectivenessIn reality, not all unsafe behaviours cause injuries every time. That is the reason why peoplewould take a chance on the unsafe behaviours. In this study, the “lucky” situations included:in VE1, when the load on the plank was under its limit (i.e. the wheelbarrow was empty orcontained less than 14 bricks); in VE2, when the steel lifted by the crane was not hangingabove the unsafe road. In VE2, when the avatar walks on the unsafe route, the crane startsmoving and stops when the beam is lifted above the unsafe route. Thus, the next time whenthey walk under the beam, they would be hit. However, if they see the beam and decide totake the safe route, after they unload the wheelbarrow at the target area, the crane wouldkeep moving and finish moving the beam. Moreover, identifying the risk did not necessarilylead to the safest decision. For example, in VE2, some students noticed that the route nearthe crane was unsafe and so chose to speed up when walking under the lifted beam.

With priming Without primingGroup With sound Without sound With sound Without sound

percentage 50% (n¼ 14) 16.7% (n¼ 12) 15.4% (n¼ 13) 8.3% (n¼ 12)p-value compared to with both priming andsound – 0.074 0.056 0.026Power – 0.494 0.546 0.765

Table IX.Proportion ofparticipants who usethe safe route without/before being injured

With priming Without priming p-value Power

OverallWith sound 71.4% (n¼ 14) 46.2% (n¼ 13) 0.182 0.070 0.280 0.712Without sound 33.3% (n¼ 12) 58.3% (n¼ 12) 0.218 0.247

VE1With sound 42.9% (n¼ 7) 28.6% (n¼ 7) 0.576 0.396 0.088 0.139Without sound 16.7% (n¼ 6) 33.3% (n¼ 6) 0.504 0.104

VE2With sound 100% (n¼ 7) 66.7% (n¼ 6) 0.098 0.046 0.411 0.565Without sound 50.0% (n¼ 6) 83.3% (n¼ 6) 0.220 0.259

Table VIII.Percentage ofparticipants who usedthe safe route

286

ECAM25,2

Page 157: Engineering, Construction and Architectural

To investigate the priming effect on training effectiveness of the virtual constructionsimulator, the percentage of uninjured participants in each group was analysed (Table X).As described above, each participant took two tests, one in each environment. Differentpriming and sound settings were used for different groups in the first test. However, allsecond tests had the same settings: without sound and without priming factors. In the groupthat had their first test without sound and without priming factors, the percentage of theuninjured participants was 25 per cent (n¼ 12).

Table X shows that there is no strong relationship between priming in the first test,being injured in the first test, or being injured in the second test. This would indicate that thepriming effect only lasts for a short time and is not suitable to be added to a VE for trainingpurpose. However, the powers for each of these tests are all less than 0.8, so a larger sampleis required.

The same method is used to analyse sound effects on the virtual construction simulator’straining effectiveness (Table XI).

Table XI shows that having sound in the first test has a strong influence on the injuryrate in the second test, if the subject was injured in the first test. If the subject was notinjured in the first test, then it has no effect. Thus, previous injuries moderate the soundeffect on training effectiveness. If the trainees experience injuries in a VE with sound, theywill learn from the experience and behave more safely.

Other observationsThere are other observations found during the experiment. As these findings were not themain aims of this study, they were not analysed statistically. The observations are: someparticipants walked around or used the plan view to observe the site carefully in theirsecond test after experiencing hazardous situations in their first test; and if people enter asite the first time, the hazards above their field of view are less likely to be consideredbecause they are more likely to observe an environment by turning their “head” left andright, but not up and down.

Check for sample biasesAs there are five potential confounding variables (gender, age, construction workexperience, computer game frequency and computer game experience) that may influencethe test results, it is important to validate the results by checking for sample biases. In thisstudy, the sample biases are checked in two aspects: the proportion of participants who usedthe safe route and the proportion of participants who were injured in their first test.

First test Second test With priming Without priming p-value Power

Total Uninjured 23.1% (n¼ 26) 28% (n¼ 25) 0.686 0.069Uninjured Uninjured 12.5% (n¼ 8) 28.6% (n¼ 7) 0.438 0.122Injured Uninjured 27.8% (n¼ 18) 27.8% (n¼ 18) 1.000 0.050

Table X.Priming effect on

training effectiveness

First test Second test With sound Without sound p-value Power

Total Uninjured 37.0% (n¼ 27) 20.8% (n¼ 24) 0.204 0.257Uninjured Uninjured 20% (n¼ 10) 20% (n¼ 5) 1.000 0.050Injured Uninjured 47.1% (n¼ 17) 10.5% (n¼ 19) 0.014 0.745

Table XI.Sound effect on

training effectiveness

287

Virtualconstruction

simulator

Page 158: Engineering, Construction and Architectural

Construction work experience. Most of the participants (excluding some of the final-yearundergraduate students) in this study had at least three months’ internship in theconstruction industry as a basic requirement for their bachelor degrees. Thus, whenchecking the bias caused by work experience, the participants who have less than threemonths’ work experience are considered as having a low level of work experience. Theresults are presented in Table XII.

As shown in Table XII, participants with less construction work experience are slightlyless likely to choose the safe route, and the rate of injury is slightly higher than for thosewith higher levels of work experience. However, if taking the subject grouping intoconsideration, the overall results do not vary much. The column of “Corrected” data in thetable is the weighed percentage assuming when the number of people with low-levelconstruction work experience and those with high-level construction work experience werethe same (Huang et al., 2006). Although, there are small differences, the trend presentedby the corrected percentage is the same as the overall result from the sample. Thus,construction work experience does not significantly influence the results.

First-person computer game frequency. The computer game frequency was measured byhow many hours per week the participants play first-person computer games. Whenchecking the bias caused by first-person computer game experience, the participants who“never or rarely play” first-person computer games are considered as having a low level offirst-person computer game frequency. The results in Table XIII compare the participantswith high-level frequency with the whole samples in each group.

As the participants with different levels first-person game frequency shown in Table XIIIdo not vary much in terms of the likelihood of using the safe route and being injured,first-person game frequency can be considered as not influencing the results significantly.

First-person computer game experience. The first-person computer game experiencewas measured by how many months/years the participants have played this type ofgames. When checking the bias caused by work experience, the participants who haveplayed no more than three months first-person computer games are considered as havinga lower level (beginner level) of first-person computer game experience. The resultsin Table XIV compare the participants with high-level experience with the whole samplesin each group.

The sample size of participants with low-level first-person game experience is small, thusthe result may lack of accuracy in terms of their likelihood of choosing the same route and

Group o3-month experience ≥ 3-month experience p-value All (%) Corrected (%)

Used the safe routeWith primingWith sound A 60.0% (n¼ 5) 77.8% (n¼ 9) 0.480 71.4 68.9Without sound B 16.7% (n¼ 6) 50.0% (n¼ 6) 0.220 33.3 33.3

Without primingWith sound C 40.0% (n¼ 10) 66.7% (n¼ 3) 0.416 46.2 53.3Without sound D 50.0% (n¼ 6) 66.7% (n¼ 6) 0.558 58.3 58.3

Experienced injuryWith primingWith sound A 80.0% (n¼ 5) 44.4% (n¼ 9) 0.198 57.1 62.2Without sound B 83.3% (n¼ 6) 83.3% (n¼ 6) 1.000 83.3 83.3

Without primingWith sound C 70.0% (n¼ 10) 66.7% (n¼ 3) 0.912 69.2 68.4Without sound D 83.3% (n¼ 6) 66.7% (n¼ 6) 0.504 75.0 75.0

Table XII.Check for sample biascaused byconstruction workexperience

288

ECAM25,2

Page 159: Engineering, Construction and Architectural

injury rate. However, it can be seen from Table XIV that when sound was present, theparticipants with higher levels of first game experience performed much more safely thanthe other participants. Thus whether first-person game experience has an influence to theparticipants’ safe decisions or not, and in what circumstances will the influence occur shouldbe further studied over a larger sample size.

DiscussionAudio and visual displays cooperate to create high levels of presence. It was hypothesised inH1 that in a VE with sound, obvious stimuli lead people to recognise more hazards.This hypothesis is strongly supported by the results of VE1, while the opposite was foundfor VE2. The most likely reason for this is that the hazard in VE2 was in the air (above theeye level). As mentioned in the results, the movement of the participants’ “eyes” was morehorizontal than vertical. Therefore, the possibility of people identifying the hazards in the airis relatively low. The results of this study stress the importance of the location of the stimuli.Previous research has suggested that if one has been told to focus on a location, theresponse speed to an object near the location is faster than to an object far from the location

Rarely or never W0 hour/week p-value All Corrected

Used the safe routeWith primingWith sound 75.0% (n¼ 4) 70.0% (n¼ 10) 0.852 71.4% 72.5%Without sound 33.3% (n¼ 3) 33.3% (n¼ 9) 1.000 33.3% 33.3%

Without primingWith sound 50.0% (n¼ 6) 42.8% (n¼ 7) 0.796 46.2% 46.4%Without sound 50.0% (n¼ 6) 66.7% (n¼ 6) 0.558 58.3% 58.3%

Experienced injuryWith primingWith sound 75.0% (n¼ 4) 50.0% (n¼ 10) 0.294 57.1% 62.5%Without sound 100% (n¼ 3) 77.8% (n¼ 9) 0.272 83.3% 88.9%

Without primingWith sound 83.3% (n¼ 6) 57.1% (n¼ 7) 0.308 69.2% 70.2%Without sound 50.0% (n¼ 6) 100% (n¼ 6) 0.046 75.0% 75.0%

Table XIII.Check for sample biascaused by first-person

computer gamefrequency

o 3-month experience ≥ 3-month experience p-value All (%) Corrected (%)

Used the safe routeWith primingWith sound 33.3% (n¼ 3) 81.8% (n¼ 12) 0.100 71.4 57.6Without sound 50.0% (n¼ 2) 30.0% (n¼ 10) 0.584 33.3 40.0

Without primingWith sound 25.0% (n¼ 4) 55.6% (n¼ 9) 0.308 46.2 40.3Without sound 60.0% (n¼ 5) 57.1% (n¼ 7) 0.922 58.3 58.6

Experienced injuryWith primingWith sound 100% (n¼ 3) 45.5% (n¼ 11) 0.090 57.1 72.7Without sound 100% (n¼ 2) 80.0% (n¼ 10) 0.488 83.3 90.0

Without primingWith sound 75.0% (n¼ 4) 66.7% (n¼ 9) 0.764 69.2 70.8Without sound 60.0% (n¼ 5) 85.7% (n¼ 7) 0.310 75.0 72.9

Table XIV.Check for sample biascaused by first-person

computer gameexperience

289

Virtualconstruction

simulator

Page 160: Engineering, Construction and Architectural

(Rizzolatti et al., 1987). Obvious stimuli attract people’s attention, thus if obvious stimuli hadbeen located in the air near the hazard, they might have helped to attract users’ attention,and subsequently have helped the users to identify the related risks. This should be furtherstudied in the future.

H2 was that priming of safe choices results in people taking fewer risks in a VRsimulator. Tables VII, VIII and IX show that this was true in a VE with sound, but primingled to people taking more risks in the VR situations without sound. When sound factorswere added to the VE, users behave more safely in the VE with priming factors than those inthe VE without priming factors. The reason why a VE with sound triggers the effect ofpriming on people’s risk perception and safety decisions may be related to how the humanbrain works. Figure 7 illustrates a conjectured model explaining how the human brainreacts to the sound and priming factors.

When people enter a VE, their attention is attracted by both visual and audio stimuli.In an environment with only visual stimuli, the information people perceived is only limitedto a 200 degree arc in front of them (Mather, 2006). The way they observe an environmentmostly depends on how they move their “eyes”. Their sense of normality is lower and thussense of presence is lower. If people do not feel present in a VE, they would not take theconsequences seriously, thus they may not be concentrating on detecting the potentialhazards when finishing their task. Meanwhile, as there is no sound from the VE, distractingsounds from the real world can be perceived clearly.

On the other hand, when people are in a VE with both audio and visual stimuli, theyperceive not only the image information in front of them but also sound information from alldirections (Mather, 2006). Thus, the presence of audio stimuli may encourage the subject tolook around more, and hence be affected by more of the priming factors. The informationreceived by vision and hearing senses are stored by short-term memory for a few secondsand then are synthesised and processed by the visuospatial sketchpad and phonologicalloop of working memory ( Jarrold and Baddeley, 1997). As the phonological loop andvisuospatial sketchpad are parallel processes, the information can be processed at the sametime (Baddeley, 1996). Rehearsal of the information in the working memory may helpthe information to be stored in long-term memory (Baddeley et al., 1998). Thus although theparticipants cannot see an object/hazard, as long as the related sound is present, they wouldnot forget that the object/hazard is there. Furthermore, the presence of the sounds from theVE can mask some of the sound from the real wold, and hence reduce the distraction fromthe real world.

Memory

Enter the VE

Perceive AudioStimuli

Perceive VisualStimuli Near the

stimuli

Far from thestimuli

DecisionMaking

Explicit memory(knowledge)

Implicit memory(priming)

Attention

Figure 7.How human brainreacts to the soundand priming factors

290

ECAM25,2

Page 161: Engineering, Construction and Architectural

When people are processing the information, their memory is retrieved. Here the memory isdivided into explicit memory and implicit memory. Explicit memory refers to a conscious formof retrieval of past information or experiences, whereas implicit memory is unintentional ornonconscious retrieval of information processing (Andersen et al., 2011). As introducedpreviously, priming is an implicit memory. Knowledge belongs to explicit memory wherepeople deliberately memorise things. In this study, explicit memory also involves the “injuries”the participants had when they were manipulating the simulator. Both implicit memory andexplicit memory influence people’s decisions. Meanwhile, the location of their attentiondetermines what information and how much information they recognise from the VE.As mentioned before, it is easier for people to process the information near the stimuli theyperceive. The information they perceive affects the decisions they make when doing tasks.However, not all the information they perceive is helpful for them to make decisions.Some stimuli may cause distraction. Previous research has also suggested that an increase inworkload reduces people’s ability to process information and increases the chance that theymake mistakes (Pierce and Andersen, 2014). Thus whether their ability to make safer decisionis enhanced or impeded should be further studied.

Contrary to H3, the conceptual priming factors did not significantly improve theparticipants’ safety performances in a subsequent environment. Even repetition priming didnot improve the participants’ overall safety performances. One reason of this may be thatthe two test environments have different appearances and features, which obstructed theparticipants connecting the two VEs (similar priming factors and site plan). However, theresults seem sensible because priming effects generally are short-term effects and mayconsequently vanish as the experiment continues (Aramaki et al., 2010). Thus for trainingpurposes, adding priming to a VE simulator is not recommended. On the other hand, strongobvious feedback, such as experiencing injuries in the VE simulator that can beexplicitly recalled from memory helped the participants to remember their mistakes and actmore safely, especially if sound is present. Although not all the participants learned fromtheir mistakes.

ConclusionsThree conclusions can be drawn from this study. First, priming subjects in a safetysimulator with hints regarding risks makes those subjects act more safely in regard to thoserisks in the simulator, if the simulator has appropriate sound effects. If the sound is notpresent, then the hints are actually likely to result in less safe behaviour. Also the location ofthe hints compared to the subject’s eye level is important. Stimuli above eye level are lesslikely to be noticed than stimuli at or below eye level.

Second, the effects of these hints are negligible in a subsequent environment. Thus, it isnot advisable to place subtle hints in a training environment. The hints will temporarilyelevate the subject’s level of safe behaviour, but this will not carry over into subsequentsituations. It would be better to place the hints in the real world.

Third, strong obvious feedback, such as the subject becoming injured from unsafebehaviour, does lead to safer behaviour in subsequent environments. Thus safetysimulators should be designed with “traps” that will “injure” the participants. The beneficialeffect of experiencing these injuries requires that the environment has appropriate soundeffects included. The lack of sound effects in the original simulator may even lead todeterioration in the safety level of behaviour on subsequent exercises.

On the whole, for safety training purposes, virtual construction simulators involvingunsupervised interaction should be designed with sound, without priming factors, andshould contain “traps” that the trainees will easily fall into when they make unsafedecisions. Further study should be carried out over a larger sample size, and dig into howthe human brain reacts to the stimuli in VR simulators.

291

Virtualconstruction

simulator

Page 162: Engineering, Construction and Architectural

References

Abdelhamid, T.S. and Everett, J.G. (2000), “Identifying root causes of construction accidents”, Journalof Construction Engineering and Management, Vol. 126 No. 1, pp. 52-60.

Abudayyeh, O., Fredericks, T.K., Butt, S.E. and Shaar, A. (2006), “An investigation of management’scommitment to construction safety”, International Journal of Project Management, Vol. 24 No. 2,pp. 167-174.

Allenmark, F., Hsu, Y.-F., Roussel, C. and Waszak, F. (2015), “Repetition priming results in sensitivityattenuation”, Brain Research, Vol. 1626, November, pp. 211-217.

Andersen, G.J., Ni, R., Bian, Z. and Kang, J. (2011), “Limits of spatial attention in three-dimensionalspace and dual-task driving performance”, Accident Analysis & Prevention, Vol. 43 No. 1,pp. 381-390.

Aramaki, M., Marie, C., Kronland-Martinet, R., Ystad, S. and Besson, M. (2010), “Sound categorizationand conceptual priming for nonlinguistic and linguistic sounds”, Journal of CognitiveNeuroscience, Vol. 22 No. 11, pp. 2555-2569.

Baddeley, A. (1996), “The fractionation of working memory”, Proceedings of the National Academy ofSciences, Vol. 93 No. 64, pp. 13468-13472.

Baddeley, A., Gathercole, S. and Papagno, C. (1998), “The phonological loop as a language learningdevice”, Psychological Review, Vol. 105 No. 1, pp. 158-173.

Banks, J., Carson, J. and Nelson, B. (2000), DM Nicol, Discrete-Event System Simulation, Prentice hall,Englewood Cliffs, NJ.

Birnbaum, M.H. (1999), “How to show that 9W221: collect judgments in a between-subjects design”,Psychological Methods, Vol. 4 No. 3, pp. 243-249.

Cameron, I. and Duff, R. (2007), “A critical review of safety initiatives using goal setting and feedback”,Construction Management and Economics, Vol. 25 No. 5, pp. 495-508.

Cheng, E.W., Ryan, N. and Kelly, S. (2012), “Exploring the perceived influence of safety managementpractices on project performance in the construction industry”, Safety Science, Vol. 50 No. 2,pp. 363-369.

Choudhry, R.M., Fang, D. and Lingard, H. (2009), “Measuring safety climate of a constructioncompany”, Journal of Construction Engineering and Management, Vol. 135 No. 9, pp. 890-899.

Chow, S.-C., Wang, H. and Shao, J. (2007), Sample Size Calculations in Clinical Research, Marcel Dekker,New York, NY.

Darken, R.P., Bernatovich, D., Lawson, J.P. and Peterson, B. (1999), “Quantitative measures of presencein virtual environments: the roles of attention and spatial comprehension”, Cyber Psychology &Behavior, Vol. 2 No. 4, pp. 337-347.

Dinh, H.Q., Walker, N., Hodges, L.F., Song, C. and Kobayashi, A. (1999), “Evaluating the importanceof multi-sensory input on memory and the sense of presence in virtual environments”,Proceedings – Virtual Reality Annual International Symposium, IEEE, pp. 222-228.

Ellis, A.W., Young, A.W. and Flude, B.M. (1990), “Repetition priming and face processing: primingoccurs within the system that responds to the identity of a face”, The Quarterly Journal ofExperimental Psychology, Vol. 42 No. 3, pp. 495-512.

Filigenzi, M.T., Orr, T.J. and Ruff, T.M. (2000), “Virtual reality for mine safety training”, AppliedOccupational and Environmental Hygiene, Vol. 15 No. 6, pp. 465-469.

Gulan, T. and Valerjev, P. (2010), “Semantic and related types of priming as a context in wordrecognition”, Review of Psychology, Vol. 17 No. 1, pp. 53-58.

Harvey, J., Bolam, H., Gregory, D. and Erdos, G. (2001), “The effectiveness of training to change safetyculture and attitudes within a highly regulated environment”, Personnel Review, Vol. 30 No. 6,pp. 615-636.

Huang, J., Gretton, A., Borgwardt, K.M., Schölkopf, B. and Smola, A.J. (2006), “Correcting sampleselection bias by unlabeled data”, Proceedings of the 19th Annual Conference on NeuralInformation Processing Systems, 2007, pp. 601-608.

292

ECAM25,2

Page 163: Engineering, Construction and Architectural

Huang, X. and Hinze, J. (2006), “Owner’s role in construction safety”, Journal of ConstructionEngineering and Management, Vol. 132 No. 2, pp. 164-173.

Jarrold, C. and Baddeley, A.D. (1997), “Short-term memory for verbal and visuospatial information inDown’s syndrome”, Cognitive Neuropsychiatry, Vol. 2 No. 2, pp. 101-122.

Lin, K.-Y., Son, J.W. and Rojas, E.M. (2011), “A pilot study of a 3D game environment for constructionsafety education”, Journal of Information Technology in Construction, Vol. 16, pp. 69-83.

Lu, X. and Davis, S. (2016), “How sounds influence user safety decisions in a virtual constructionsimulator”, Safety Science, Vol. 86, pp. 184-194.

Marsh, R.L., Bink, M.L. and Hicks, J.L. (1999), “Conceptual priming in a generative problem-solvingtask”, Memory & Cognition, Vol. 27 No. 2, pp. 355-363.

Mather, G. (2006), Foundations of Perception, Psychology Press, Hove.

Menzel, N.N. and Gutierrez, A.P. (2010), “Latino worker perceptions of construction risks”, AmericanJournal of Industrial Medicine, Vol. 53 No. 2, pp. 179-187.

Montgomery, D.C., Runger, G.C. and Hubele, N.F. (2009), Engineering Statistics, John Wiley & Sons,New York, NY.

Nafarrete, J. (2015), “US Air force recruiting with virtual reality experience”, VRSCOUT, available at:http://vrscout.com/projects/us-air-force-virtual-reality-experience/ (accessed 26 May 2015).

Nunez, D. (2004), “A constructionist cognitive model of virtual presence”, 7th International Workshopon Presence (PRESENCE), Valencia, pp. 313-316.

Nunez, D. and Blake, E. (2003), “Conceptual priming as a determinant of presence in virtualenvironments”, Proceedings of the 2nd International Conference on Computer Graphics, VirtualReality, Visualisation and Interaction in Africa, ACM, pp. 101-108.

Orgs, G., Lange, K., Dombrowski, J.-H. and Heil, M. (2006), “Conceptual priming for environmentalsounds and words: An ERP study”, Brain and Cognition, Vol. 62 No. 3, pp. 267-272.

Pendry, L. and Carrick, R. (2001), “Doing what the mob do: priming effects on conformity”, EuropeanJournal of Social Psychology, Vol. 31 No. 1, pp. 83-92.

Pierce, R.S. and Andersen, G.J. (2014), “The effects of age and workload on 3D spatial attention indual-task driving”, Accident Analysis & Prevention, Vol. 67, pp. 96-104.

Price, M. and Anderson, P. (2007), “The role of presence in virtual reality exposure therapy”, Journal ofAnxiety Disorders, Vol. 21 No. 5, pp. 742-751.

Rizzolatti, G., Riggio, L., Dascola, I. and Umiltá, C. (1987), “Reorienting attention across the horizontaland vertical meridians: evidence in favor of a premotor theory of attention”, Neuropsychologia,Vol. 25 No. 1A, pp. 31-40.

Sacks, R., Perlman, A. and Barak, R. (2013), “Construction safety training using immersive virtualreality”, Construction Management and Economics, Vol. 31 No. 9, pp. 1005-1017.

Safe Work Australia (2015), Work-Related Traumatic Injury Fatalities Australia 2014, Safe WorkAustralia, Canberra.

Sanchez-Vives, M.V. and Slater, M. (2005), “From presence to consciousness through virtual reality”,Nature Reviews Neuroscience, Vol. 6, pp. 332-339.

Sawacha, E., Naoum, S. and Fong, D. (1999), “Factors affecting safety performance on constructionsites”, International Journal of Project Management, Vol. 17 No. 5, pp. 309-315.

Schacter, D.L. and Addis, D.R. (2007), “The cognitive neuroscience of constructive memory:remembering the past and imagining the future”, Philosophical Transactions of the Royal SocietyB: Biological Sciences, Vol. 362 No. 1481, pp. 773-786.

Stromme, M. (2011), “Construction safety training”, ISHN, Vol. 45 No. 7, p. 24.

Van Belle, G. (2011), Statistical Rules of Thumb, John Wiley & Sons, Chichester.

Van Wyk, E. and De Villiers, R. (2009), “Virtual reality training applications for the mining industry”,Proceedings of the 6th International Conference on Computer Graphics, Virtual Reality,Visualisation and Interaction in Africa, ACM, pp. 53-63.

293

Virtualconstruction

simulator

Page 164: Engineering, Construction and Architectural

Walpole, R. (1974), Introduction to Statistics, Macmillan, New York, NY, p. 340.Waly, A.F. and Thabet, W.Y. (2003), “A virtual construction environment for preconstruction

planning”, Automation in Construction, Vol. 12 No. 2, pp. 139-154.Wickström, G. and Bendix, T. (2000), “The ‘Hawthorne effect’ – what did the original Hawthorne

studies actually show?”, Scandinavian Journal of Work, Environment & Health, Vol. 26 No. 4,pp. 363-367.

Witmer, B.G. and Singer, M.J. (1998), “Measuring presence in virtual environments: a presencequestionnaire”, Presence: Teleoperators and Virtual Environments, Vol. 7 No. 3, pp. 225-240.

Wood, S., Cox, R. and Cheng, P. (2006), “Attention design: eight issues to consider”, Computers inHuman Behavior, Vol. 22, pp. 588-602.

Corresponding authorXueqing Lu can be contacted at: [email protected]

For instructions on how to order reprints of this article, please visit our website:www.emeraldgrouppublishing.com/licensing/reprints.htmOr contact us for further details: [email protected]

294

ECAM25,2

Page 165: Engineering, Construction and Architectural

Book review

Total Construction Management: Lean Quality in Construction ProjectDeliveryBy John Oakland and Marton MarosszekyRoutledge/Taylor & Francis2017610pp.ISBN 978-1-138-90853-6Review DOI 10.1108/ECAM-12-2017-0268

“We’ve always done it this way” is one of the most infuriating phrases overheard on anyconstruction jobsite. It symbolizes stagnation, an aversion to change and a reluctance tolearn from past mistakes. It is an anathema for an industry rapidly being transformed bytechnology and globalization. Fortunately, the authors of Total Construction Managementadvance a refreshing alternative. By combining lessons from lean manufacturing andquality management into the idea of “lean quality,” John Oakland and Marton Marosszekylay out a comprehensive vision for an agile, more value-driven industry. This vision is builtquickly at first, then gradually deepened through the use of case studies and the unificationof innovative management theories and tools from the past two decades. But, there is atrade-off in this approach. Many of the theories and tools used to build the authors’ vision oflean quality can and do have entire books written about them. Thus, anyone seekinga how-to book on pull planning or total quality management (TQM) should look elsewhere,perhaps to several of the authors’ prior works. Total Construction Management is a more ofa primer that brings an extensive breadth of seemingly disparate management ideastogether to establish lean quality as a lens for advancing effective management. That said,the variety of ideas being presented is unlikely to be fully appreciated by undergraduatestudents, making the book more suited for graduate-level study and industry professionalswith a few years of practical experience in construction management.

Before delving too deeply into the book’s structure and content, the qualifications ofthe authors cannot be understated. John Oakland brings his expertise on the quality sideof the lean quality equation, having researched, published on and promoted TQM inorganizations for nearly three decades. Marton Marosszeky, on the other hand, bringshis knowledge of lean management and production processes obtained firsthand throughhis work as a Civil engineer, professor and Consultant. Both authors are well-regarded inthe field and their combined experiences strike a successful balance between academicand practical perspectives.

The book itself contains 19 chapters, subdivided into six major sections. Eachchapter ends with a list of bulleted highlights of important concepts and each majorsection ends with discussion questions clearly designed to test the reader’s ability to applythose concepts. The first section (Chapters 1-4) provides a foundational background onlean quality that reviews the current state of lean management in construction, definesquality through the eyes of the customer and reviews various TQM models. Section 2(Chapters 5-8) presents an exhaustive summary of lean planning techniques, rangingfrom supply chain partnerships to pull planning, building information modeling andthe design structure matrix to name a few. Section 3 (Chapters 9-11) discusses perhapsthe most important aspect of lean quality: measuring and benchmarking performance.These chapters highlight commonly used measures for efficiency, productivity and

Engineering, Construction andArchitectural Management

Vol. 25 No. 2, 2018pp. 295-296

© Emerald Publishing Limited0969-9988

295

Book review

Quarto trim size: 174mm x 240mm

Page 166: Engineering, Construction and Architectural

effectiveness. Section 4 (Chapters 12-15) is all about process management and makingthese measures part of a continuous improvement effort. Section 5 (Chapters 16-18)is dedicated to the human resources and cultural shifts that make lean quality a reality,specifically the communication, leadership, and learning skills needed in projectmanagers. Lastly, Section 6 (Chapter 19) discusses the implementation of lean quality atan organizational level. While short, this chapter has some valuable insights andwarnings about forcing too much change, too soon within a construction firm.Throughout each chapter, the writing is approachable, consistent and well-supported bydiagrams and other visuals. The authors also make use of descriptive case studies, withroughly 150 pages in the book dedicated to 14 studies.

One limitation in the book’s content is a lack of detail regarding how project deliverymethods and their associated contractual arrangements fit within the lean qualityframework. Early on, the authors highlight the Lean Construction Institute’s qualitytriangle and suggest that embracing all three sides – integrated organization, alignedcommercial interests and lean operating methods – is crucial to achieving lean quality.However, only integrated project delivery and perhaps some versions of design-buildare contractually structured to meet that challenge. Does this mean that lean qualityis not attainable in more traditional project delivery methods, such as design-bid-build?Or, is there still value in applying select process improvements and tools? The answer tothese questions will almost certainly determine the rate and extent of lean qualityadoption in the construction industry.

As stated earlier, the single greatest strength of Total Construction Management is itsbroad and unifying vision for the industry. The authors successfully expand the conceptof quality from a product-centered view of the building, to a process-centered view of theproject. Synthesized from the best management theories and tools of the past two decades,this perspective recognizes the importance of waste-reducing management andorganizational efforts in creating value for the customer beyond that of the productitself. In other words, lean quality is the antithesis of “we’ve always done it this way.”With this book, John Oakland and Marton Marosszeky have written a roadmap makingthis vision a reality.

Bryan FranzSchool of Construction Management, University of Florida,

Gainesville, Florida, USA

296

ECAM25,2

Page 167: Engineering, Construction and Architectural

EDITOR-IN-CHIEFProfessor Chimay J. AnumbaThe University of Florida, USAE-mail [email protected]

SPECIALITY EDITORProfessor Antony ThorpeLoughborough University, UK

EMERITUS EDITORProfessor Ronald McCafferLoughborough University, UK

DEPUTY EDITORSDr Timo HartmannTechnische Universitaet Berlin, GermanyE-mail [email protected] Dr Geoffrey Qiping Shen Hong Kong Polytechnic University, Hong KongE-mail [email protected] Derek ThomsonLoughborough University, UKE-mail [email protected]

EDITORIAL ASSISTANTMs Nancy SmithThe Pennsylvania State University, USAE-mail [email protected]

ISSN 0969-9988© 2018 Emerald Publishing Limited

Emerald Publishing LimitedHoward House, Wagon Lane, Bingley BD16 1WA, United KingdomTel +44 (0) 1274 777700; Fax +44 (0) 1274 785201E-mail [email protected] more information about Emerald’s regional offices please go to http://www.emeraldgrouppublishing.com/officesCustomer helpdesk :Tel +44 (0) 1274 785278; Fax +44 (0) 1274 785201E-mail [email protected], subscription and missing claims enquiries:E-mail [email protected] +44 (0) 1274 777700; Fax +44 (0) 1274 785201

Missing issue claims will be fulfilled if claimed within six months of date of despatch. Maximum of one claim per issue.Hard copy print backsets, back volumes and back issues of volumes prior to the current and previous year can be ordered from Periodical Service Company. Tel +1 518 537 4700; E-mail [email protected] For further information go to www.periodicals.com/emerald.html

Reprints and permissions serviceFor reprint and permission options please see the abstract page of the specific article in question on the Emerald web site (www.emeraldinsight.com), and then click on the “Reprints and permissions” link. Or contact:E-mail [email protected] Publisher and Editors cannot be held responsible for errors or any consequences arising from the use of information contained in this journal; the views and opinions expressed do not necessarily reflect those of the Publisher and Editors, neither does the publication of advertisements constitute any endorsement by the Publisher and Editors of the products advertised.

No part of this journal may be reproduced, stored in a retrieval system, transmitted in any form or by any means electronic, mechanical, photocopying, recording or otherwise without either the prior written permission of the publisher or a licence permitting restricted copying issued in the UK by The Copyright Licensing Agency and in the USA by The Copyright Clearance Center. Any opinions expressed in the articles are those of the authors. Whilst Emerald makes every effort to ensure the quality and accuracy of its content, Emerald makes no representation implied or otherwise, as to the articles’ suitability and application and disclaims any warranties, express or implied, to their use.

Emerald is a trading name of Emerald Publishing LimitedPrinted by CPI Group (UK) Ltd, Croydon, CR0 4YY

Certificate Number 1985ISO 14001

ISOQAR certified Management System,awarded to Emerald for adherence to Environmental standard ISO 14001:2004.

Engineering, Construction and Architectural Management is indexed and abstracted in:ABI InformBritish LibraryBusiness SourceConstruction Management AbstractsConstruction and Building AbstractsEBSCO Discovery ServiceExecutive Daily BriefICONDA (International construction database)INSPECInternational Civil Engineering Abstracts DatabaseProQuestScopus

Engineering, Construction and Architectural Management has been awarded the distinction of CIB Encouraged Journal by the International Council for Research and Innovation in Building and Construction (CIB)

Quarto trim size: 174mm × 240mm

Guidelines for authors can be found at:www.emeraldgrouppublishing.com/ecam.htm

Page 168: Engineering, Construction and Architectural

En

gin

ee

ring

, Co

nstru

ctio

n an

d A

rch

itec

tural M

anag

em

en

tV

olu

me

25

Nu

mb

er 2

20

18e

me

raldp

ub

lishin

g.c

om

www.emeraldinsight.com/loi/ecam

Volume 25 Number 2 2018ISSN 0969-9988

Volume 25 Number 2 2018

Engineering, Construction and Architectural

Management

Engineering, Construction and Architectural Management

Quarto trim size: 174mm × 240mm

Number 2

133 Editorial boards

134 Planning and controlling design in engineered-to-order prefabricated building systemsJosana Gabriele Bolzan Wesz, Carlos Torres Formoso and Patricia Tzortzopoulos

153 Construction manager’s technical competencies in Malaysian construction projectsAbd Halid Abdullah, Siti Khalijah Yaman, Hairuddin Mohammad and Padzil Fadzil Hassan

178 Conflicts and management styles in the Sri Lankan commercial building sectorChathuri Gunarathna, Rebecca Jing Yang and Nirodha Fernando

202 An analysis of the delivery challenges influencing public-private partnership in housing projects: the case of TanzaniaNeema Kavishe, Ian Jefferson and Nicholas Chileshe

241 A comparison of the suitability of FIDIC and NEC conditions of contract in Palestine: a perspective from the industryHaytham Besaiso, Peter Fenn, Margaret Emsley and David Wright

257 Understanding why Chinese contractors are not willing to purchase construction insuranceJunying Liu, Sen Lin and Yingbin Feng

273 Priming effects on safety decisions in a virtual construction simulatorXueqing Lu and Steven Davis

295 Book review