    Tamper Logics and Testing

    Presented by

    Ch.V.N.Rajesh

  • 8/10/2019 Energy meters Tamper detials

    2/19

    Introduction

    This Program explains about

    1. Types of Tampers available in meter.

    2.

    Tamper features role in meters.3. How single phase and poly phase meters are

    tampered.

    4. Tampers testing methods.

    5. What is the latest trend of tampers.

    6. Storage mechanisms in our meters.

  • 8/10/2019 Energy meters Tamper detials

    3/19

    Tampers in MeterPoly Phase meters:

    Voltage Failure

    Current Failure

    Voltage Unbalance

    Current Unbalance

    Current Bypass

    Current reversal Low Power factor

    Neutral Disturbance

    Magnetic logging

    High ESD Detection

    Power fail records

    Terminal / Meter Cover open tamper

    Single Phase Meters:

    Reversal Tamper

    Full Earth Load Tamper

    Partial Earth Load Tamper

    Magnetic Tamper

    Current Bypass

    Single wire Tamper

    Terminal / Meter Cover open tamper

  • 8/10/2019 Energy meters Tamper detials

    4/19

    Voltage Failure

    1 2 3 4 5 6 7 8 9 10 11 12

    Voltage

    Load

    N

    B

    Y

    R=

    0V

    R- IN

    Y- IN

    B- IN

    Common out to R, Y, B

    Connection Error with HT terminal box

    Taping missed while connectingMetering box

    Internal cal links are not closed

    Intentionally PT wire is removed forHT & LT CT meters

    Relay connected to Internal PT wires

    Impact is 33.33% less consumption inmeter

    Threshold is

  • 8/10/2019 Energy meters Tamper detials

    5/19

    Voltage Unbalance

    1 2 3 4 5 6 7 8 9 10 11 12

    Volta

    ge

    Load

    N

    B

    Y

    R

    R- IN

    Y- IN

    B- IN

    Common out to R, Y, B

    This can occur because of:

    Load unbalance

    Intentionally add resistor to secondarywire for HT And LT CT meters

    Resistor values modification byopening the meter

    Impact :

    Les consumption in meter

    Testing :

    Threshold is Vmax Vmin >30% ofVref

    Tamper records when ever differencein voltages are greater than thethreshold value i.e for HT 4W 19.05 V,LT 72V, HT 3 W 33V

    In Firmware Vref & 30% is the keyfactors, some of the times Vref for HT63V & LT 230V instead of 63.5 &240.

    Connection for 4 CT meters

    Link to Pictures ..

  • 8/10/2019 Energy meters Tamper detials

    6/19

    Current FailureThis can occur because of:

    Connection error in HT TB box

    Full CT bypass in all meters

    Primary CT failure in LT CT meters

    CT failure in the meters

    Testing :

    Threshold is

  • 8/10/2019 Energy meters Tamper detials

    7/19

    Current UnbalanceThis can occur because of:

    Loose Connection in HT TB &LT CTbox

    With out a proper planning of loaddistribution

    Current bypass is detected through

    Current unbalance for 3 Ct meters

    Burden resistor change in metes

    Testing :

    Threshold isImax Imin >30% of

    Ibasic

    Tamper records difference in phasecurrent crosses the threshold value i.efor 1A 0.3A & 5A 1.5A

    In Firmware Ibasic & 30% is the keyfactors, some of the times 1A CTtamping also threshold is 1.5A

    Connection for 4 CT meters

    Link to Pictures ..

    1 2 3 4 5 6 7 8 9 10 11 12

    Voltage

    from

    phantom

    load

    Load from

    phantom load

    N

    B

    Y

    R

    R- IN

    Y- IN

    B- IN

    Common out to R, Y, B

  • 8/10/2019 Energy meters Tamper detials

    8/19

    Current ReversalThis can occur because of:

    Wrong connection HT TB &LT CT box

    Wrong connection at meter end

    Intentionally reverse the CT atprimary or secondary

    Inside of the meter reverse thesecondary wire

    Testing :

    Threshold isve power >5% of

    Vref* Ibasic & PF >0.2 or negative

    power >1%

    Tamper records phase negative power>5% and PF 0.2 or Negative totalpower is >1%

    In Firmware 5% & 1% powerthresholds are the key factors.

    Connection for 4 CT meters

    Link to Pictures ..

    1 2 3 4 5 6 7 8 9 10 11 12

    Voltage

    Load from

    phantom load

    Common out to R, Y, B

  • 8/10/2019 Energy meters Tamper detials

    9/19

    Current BypassThis can occur because of:

    Burden modified to high values

    By shorting Primary CT wires at meter

    By shorting secondary CT wires at

    meter box

    Neutral CT reversal in the meter

    Testing :

    Threshold is Magnetitude of Ir+Iy+Ib-In >20% of Ib

    Tamper records magnetitude of phasewise currents vectorial addition aresubtracted with neutral current isgreater than 20% of Ib

    In Firmware 20% is the key factor.

    Current unbalance and Current bypassshould not occur at same time.

    With normal connection tampershould not false tri er.

    Connection for 4 CT meters

    Link to Pictures ..

    1 2 3 4 5 6 7 8 9 10 11 12

    Voltage

    from

    phantom

    load

    Load from

    phantom load

    N

    B

    Y

    R

    R- IN

    Y- IN

    B- IN

    Common out to R, Y, B

  • 8/10/2019 Energy meters Tamper detials

    10/19

    Low Power FactorThis can occur because of:

    Only capacitor bank is on

    Testing :

    Threshold is ve power

  • 8/10/2019 Energy meters Tamper detials

    11/19

    Neutral DisturbanceThis can occur because of:

    Phase and neutral inter change

    Ac voltage applied to neutral

    DC voltage is applied to neutral

    Testing :

    Threshold is Votage >150% of VrefTamper records phase voltage

    >150% of Vref

    In Firmware 150% of Vref is the

    key factor, some of the times 125%

    used to be as threshold.

    Connection for 4 CT meters

    Link to Pictures ..

    1 2 3 4 5 6 7 8 9 10 11 12

    Voltage

    from

    phantom

    load

    Load from

    phantom load

    R

    B

    Y

    N

    R- IN

    Y- IN

    B- IN

    Common out to R, Y, B

  • 8/10/2019 Energy meters Tamper detials

    12/19

    Magnetic tamperThis can occur because of:

    Magnetic field presence to the meter

    Testing :

    Magneto sensor card used to sense the magnetic filed, Card sends

    signal to controller.Meter senses the magnetic field records as magnetic tamper and energy

    recording is based on Vref*Imax*UPF.

    In Firmware Imax recording is the key factor.

    Link to Pictures ..

  • 8/10/2019 Energy meters Tamper detials

    13/19

    1 Phase meter Tampers

    Reversal Tamper isdeducted when ever there isphase difference of 180degrees between voltageand current.

    Earth load is deductedwhen there is a difference inphase and neutral current.

    Single wire condition isdeducted by using power CT,which produce voltage with

    presence of VoltageBypass is deducted bycomparing phase and neutralcurrent.

    Magnetic andterminal/meter cover opentampers same like poly

    phase meters.

    Link to Pictures ..

  • 8/10/2019 Energy meters Tamper detials

    14/19

    New Tampers & Some Examples

    High ESD applied to the meter, By using Spark plug.

    It use to give high voltage around 35KV with spark duration of 600usec.

    Terminal cover / Meter Cover open detection tamper recently included in meters.

    In our meter we have three type of storage mechanism are availablea) Block Method

    b) Sequential

    c) Sequential Block

    Link to Pictures ..

  • 8/10/2019 Energy meters Tamper detials

    15/19

    Thank you

  • 8/10/2019 Energy meters Tamper detials

    16/19

  • 8/10/2019 Energy meters Tamper detials

    17/19

  • 8/10/2019 Energy meters Tamper detials

    18/19

  • 8/10/2019 Energy meters Tamper detials

    19/19