#Energy #Efficiency in H Plants-Case Study #Textiles

11
Ask | Innovate | Reduce Humidification plants | Textiles AIR Series Version 2.0 | May’14 Edition

description

Presentation talks about how our team used data analytic to identify and implement Supply Side Management measure in a Textile industry,which resulted in reducing energy consumption by over 17%!

Transcript of #Energy #Efficiency in H Plants-Case Study #Textiles

Page 1: #Energy #Efficiency in H Plants-Case Study #Textiles

Ask | Innovate | ReduceHumidification plants | Textiles

AIR Series Version 2.0 | May’14 Edition

Page 2: #Energy #Efficiency in H Plants-Case Study #Textiles

Audit Findings & Inference

Page 3: #Energy #Efficiency in H Plants-Case Study #Textiles

Consumption Pattern

H Plant

15%

Rest of the plant

85%

% Power Consumption

Most Spinning Units consume

almost 12%-17% of total

electricity in H Plant.

At modest energy saving

potential, H Plants have potential

to reduce almost 2% of the total

electricity consumption of the

plant!

Page 4: #Energy #Efficiency in H Plants-Case Study #Textiles

Observation and Potential

AssessmentPost Audit Observation

15% Electricity Consumption in H Plant

kWh/M3 almost 40% higher than benchmark value

Wrong Sizing of Motors/Fans

20 year old design, lot of changes in Plant

Requirement with time.

What we did?

Stimulated air, water requirements for Heat Load of each section, compared it with design

parameters

Measured Key Performance Parameters for each of the Motor-Fan combination ( Static

Pressure, Initial Power Requirement, Time to attain max speed, kWh/M3)

Suggested change in the motor-fan combination and stimulation model for better understanding

of requirement and hence supply side management

15%-20% Reduction in

Motor-Fan electricity

consumption

Page 5: #Energy #Efficiency in H Plants-Case Study #Textiles

Post Implementation Scenario

Page 6: #Energy #Efficiency in H Plants-Case Study #Textiles

Post implementation scenario?17% reduction in energy consumption without effecting any of the output parameters

400.00

450.00

500.00

550.00

600.00

650.00

700.00

Energy Analysis

Total

High

Low

Installation Date

Page 7: #Energy #Efficiency in H Plants-Case Study #Textiles

Post implementation scenario?

-

100.00

200.00

300.00

400.00

500.00

600.00

Energy Analysis

Average kWh before installations

Average kWh after installations

Diff in kWh

Page 8: #Energy #Efficiency in H Plants-Case Study #Textiles

How did we do it?

Page 9: #Energy #Efficiency in H Plants-Case Study #Textiles

Data- Next Frontier!

We studied almost 200 motor-fan combination covering different sets of KPIs.

Observed that for a few sets of motor-fan combination (all identical), kWh/m3 was

higher in comparison to other motor-fan combinations.

Suggested the user to install a 4 Pole motor with VFD instead of a 6 Pole

motor, kept the FAN rpm the same.

Conducted trials on two sets, combined results have been shown in slide no 6 and

7!

Entire suggestions were based on different sets of data that were available or

collected by our team.

Page 10: #Energy #Efficiency in H Plants-Case Study #Textiles

Our Secret of doing it!