Energy Audit Report - poornima.edu.in

27
Prepared by- DESIGN2OCCUPANCY SERVICES LLP, JAIPUR Jaipur, Rajasthan September 26, 2020 Energy Audit Report

Transcript of Energy Audit Report - poornima.edu.in

Page 1: Energy Audit Report - poornima.edu.in

Prepared by-

DESIGN2OCCUPANCY SERVICES LLP, JAIPUR

Jaipur, Rajasthan

September 26, 2020

Energy Audit Report

Page 2: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Contents I. Introduction ............................................................................................................................................ 3

II. Executive Summary ............................................................................................................................. 4

Occupancy Details ..................................................................................................................................... 5

Brief ................................................................................................................................................................ 5

III. Assessed Parameters ....................................................................................................................... 6

Geology of Jaipur, Rajasthan ................................................................................................................. 6

Climate ........................................................................................................................................................... 6

Temperature and Rainfall ...................................................................................................................... 6

IV. Energy Analysis Definition & Procedure ................................................................................. 7

Definition ...................................................................................................................................................... 7

Objective ....................................................................................................................................................... 8

V. Timeline and Procedure .................................................................................................................... 9

VI. Energy Consumption Scenario .................................................................................................. 10

VII. Load Calculation .............................................................................................................................. 11

VIII. Energy Performance Index.......................................................................................................... 24

IX. Renewable Energy .......................................................................................................................... 24

Solar .............................................................................................................................................................. 24

X. EEM’s for Lighting and Fans ........................................................................................................... 25

XI. Kitchen Inspection .......................................................................................................................... 26

Site Observations ..................................................................................................................................... 26

XII. EEM’s for Kitchen ............................................................................................................................ 26

XIII. Final Summary ................................................................................................................................. 27

Page 3: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

I. Introduction

Based on an inspection of the building (and some measurements), energy auditing

includes an evaluation and analysis of the existing situation and the various measures

that could be implemented to reduce the energy consumption and improve the indoor

environment. The results are presented in an energy analysis report describing the

recommended measures with corresponding investments, savings and profit.

The energy analysis in a building is a feasibility study, for it not only serves to identify

energy use among the various services but also identify opportunities for energy

conservation. The study should reveal to the owner, manager, or management team of

the building the options available for reducing energy waste, the costs involved, and the

benefits achievable from implementing those energy-conserving opportunities (ECOs). It

is to reduce waste of energy and money to the minimum, permitted by the climate in

which the building is located, its functions, occupancy schedules, and other factors. It

establishes and maintains an efficient balance between a building's annual functional

energy requirements and its annual actual energy consumption.

Pre- Arranged Appoinments

Confidential Review & Survey

Assessment of Funding Option

Recommendation

Implementation

Figure 1 Energy Analysis Process Flow

Page 4: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

II. Executive Summary

Poornima University located in Jaipur, Rajasthan. The group work towards providing an

environment and curriculum where Students can explore and develop every facet of

themselves, enabling them to realize their true potential. In order to achieve its ambition

of being a world-class education provider, Poornima University (PU) is committed to

significant enhancement of its facilities and buildings, essential for world-class research

and all-round development of students. The University has an extremely modern and

state-of-the-art infrastructure that goes a long way in facilitating a number of services for

the students as well as the staff members spread over an area of 3,00,000 sq. feet. The

campus boasts of finest interiors, infrastructures and a dedicated team provide excellent

educational facilities that serve the areas and domains that have the potential to improve

the quality of life for large sections of the society. The joyfulness of the Poornima

University is reflected in its ambience- a befitting reflection of the contentment that

resides within – the well-lit spaces and airy environment, the visuals on the walls, the

creative installations, the work on the boards and the busy students.

Poornima University campus consists:

I. Block A1

II. Block A2

III. Block A3

IV. Block A4

V. Block A5

VI. Block A6

VII. Hostel Block 1,2,3,4,5,6,7,8,9,10 and 11

Page 5: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Occupancy Details

The number of occupants is also important to define the amount of water and energy used

in the building; therefore, the following details of the occupants has been considered

during the calculation and report preparation.

Table 3: University Occupancy Details

Number of Students

Total 3000

Table 4: Campus Staff Occupancy Details

Campus Staff

Occupant Type

Warden

Horticulture

Plumbers

Driving Staff

Housekeeping

Catering

Security

Laundry

Total 150

Hence, it is observed that the total occupancy of the campus is 3,150.

Brief

The Energy analysis was conducted by D2O team from 18th Aug 2020 to 22th Sept 2020,

at the University premises to study the existing practices of energy consumption and seek

possible ways to conserve water. The facility was introduced by, Mr. Simran Jeet.

Page 6: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

III. Assessed Parameters

Geology of Jaipur, Rajasthan Jaipur city is the capital and largest city of the Indian state of Rajasthan. Its municipal boundary of the city extends from 26⁰46' N latitude to 27⁰01'N latitude and 75⁰39'E

longitude to 75⁰57'E longitude. The city is surrounded by the Nahargarh hills in the north

and Jhalana in the east, which is a part of Aravalli hills ranges. To its south and west, the

city is surrounded by isolated and discontinuous hillocks. The southern end of the city is

an open plain stretching far and wide towards Sanganer and beyond. The city was initially

located within the walls with the rocky streets providing an easy drainage system on

either side of the city but the later extension of the city took place towards the south and

west on the alluvial plains formed in the confluence zone of the Amani Shah Nala in the

west and Jawahar Nagar Nala in the east and beyond.

Climate Jaipur city falls under the semi-arid of climate and experiences a continental type of

climate owing to its proximity to the desert and inland location. It is characterized by hot

summers and cold winters. The mean temperature of Jaipur is 36⁰C varying from 18⁰C in

winter (January) to 45⁰C in summer (June). The normal rainfall of Jaipur is 600 mm nearly

90 percent of which takes place in the summer monsoon period from (June to September)

and the rest comes from the winter cyclones:

Table 1: mean temperature of jaipur

Temperature and Rainfall The month of May experiences the maximum temperature and January experiences

minimum temperature. The data is based on 7 observation years recorded by Indian

Meteorological Department (IMD). Jaipur city recorded the maximum temperature of

45.2°C and minimum temperature of 2.5°C in the year 2001 and the maximum

temperature of 45.7°C and minimum temperature of 2.2°C in the year 2011.

Heat wave prevails for a few days when day temperature rises 4°C to 6°C above normal.

During winter season, minimum temperatures remain at about 4°C to 9°C and fall below

0⁰C when chilly winds (northerly) blow from the Himalayan region. Mist and Fog occur

in the morning hours after passage of western disturbances. The minimum

Mean Maximum Temperature (May) 40C

Mean Minimum Temperature (January) 8C

Figure 2: Annual Daylight Hours (Monthly Mean) Source-NOAA

Page 7: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

temperature of -2.2°C was recorded on 31st January, 1905 and 16th January, 1964. The

surge in temperature starts from April and peaks in the month of June. The downward

trend in temperatures commences in September and continues up to January. The mean

annual rainfall is around 60 mm. Maximum rainfall is 198.8 mm which occurred in the

month of August in 2006. Rainfall increases from the month of June when thundering

activities start, and July and August are the rainiest months. Monsoon withdraws in the

middle of September. Rainfall decreases sharply in October and November.

Figure 3: Seven Year Rainfall Data (Source: by meteorological sub-divisions)

IV. Energy Analysis Definition & Procedure

Definition

This report elaborates the current actual energy performance of the building and real-

time performance of all the energy intensive systems installed in the facility. Detailed

survey and testing of the energy intensive systems has been performed in order to arrive

at the present performance of each equipment. The test results have been carefully

analysed and presented along with improvement measures and general

recommendations for each of the systems. The suggested Energy Efficiency Measures

(EEMs) presented in the report are mainly of three types depending on their initial cost

implications – No Cost, Low Cost and Medium Cost measures. The measures, if

implemented, may help the facility team in optimizing the building operations and may

result in comprehensive energy and cost savings in the long run.

0

50

100

150

200

250

300

350

400

450

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94

Rainfall Data

17.Rajasthan West 18.Rajasthan East

Page 8: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Objective The objective of Energy Analysis is to assess the following:

a) Understand the energy consumption scenario.

b) Survey the energy generation systems.

c) Suggest potential energy conservation measures based on end uses.

d) Support with Implementation and maintenance.

Page 9: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

V. Timeline and Procedure

Date (2020) Performed Task

18-19 Aug Site Visit and Award Selection

18-25 Aug Data Collection

25 Aug- 1 Sept.

Site Visit 1. Metering 2. Fixture Count 3. Operation Analysis Identification of Supply Sources

1-13 Sept Analysing the previous metered data Fuel and Power Data Analysis

13-19 Oct Energy Report and ECM’s and Savings

Figure 5 Energy Analysis Procedure

Phase I: Conduction of Analysis

•Site Visit (for energy generation sources)•Testing and Measurements•Closure of Analysis Data & Findings

Phase II: Calculation

•Calculation & Listing•Evaluate Feasible Options

Phase III: Analysis Report

•Report Writing•Summary & Recommendations•Communication & Presentation of Results

Phase IV: Discussion & Implementation

•Dicussion on Proposed Measures & Strategies•Implementation of Finalized Measures

Phase V Review

•Review of the Implemented Measures•Revise Results

Page 10: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

VI. Energy Consumption Scenario

The electric power for the entire facility is mainly procured from the state utility grid. In

case of loss of grid power, diesel generator sets installed at the Campus for power backup.

Table 2- Energy Consumption (May 2019- April 2020)

S. No. Month

Total Energy from Poornima University

(kWh)

1 May-19 1,59,295

2 Jun-19 1,84,800

3 Jul-19 1,31,815

4 Aug-19 1,39,755

5 Sep-19 1,66,610

6 Oct-19 1,84,030

7 Nov-19 1,19,745

8 Dec-19 86,325

9 Jan-20 88,015

10 Feb-20 85,445

11 Mar-20 82,930

12 Apr-20 84,709

Total Consumption (kWh) 15,13,474

Figure 6 Energy Consumption of Campus

020000400006000080000

100000120000140000160000180000200000

Co

nsu

mp

tio

n in

kW

h

Months

Electricity Consumption in Year 2019-2020

Page 11: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

VII. Load Calculation

Electrical Load calculation sheet (Block A-1) Transformer No.4 (160KVA)

Sr.No.

Floor Name Floor Area in

Sq.Mtr.

Floor Area in

Sq. Ft.

Light Load

Light Equipment Load in Watts

Qty. Load in KW

1 Ground Floor 2303.95 24790.502 CFL 11W 10 20 0.2

CFL18W 18 20 0.36

T5 28W 28 52 1.456

Celling Fan 60 52 3.12

Fresh air Fan 30 8 0.24

Light Socket 100 30 3

Power Socket 500 12 6

TOTAL 14.376

Round off 14.00

2 First Floor 2303.95 24790.502 TOTAL 14.376

Round off 14.00

Total Light Load 28.00

3 OTHER LOAD (GF & FF)

Sr. No.

Description Qty. Load In KW

Total Load In KW Remark

1 LABS 4 5 20

2 SEMINAR HALL

2 3 6

3 Projector 4 1.5 6

4 Water Cooler 4 0.5 2

5 Water Filter 4 0.1 0.4

6 Water Pump 1 0.75 0.75

7 Safety & Security

Instruments

1 0.25 0.25

8 Office Automation

System (1set)

1 2 2

9 Air Conditioner 2

ton 5 Star Rating

6 1.8 10.8

Page 12: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

10 Mud Pump 1 3.7 3.7

11 Air Ducting Cooler 15000

CFM

4 7.5 30

12 Tea / Coffee Machine

2 1 2

13 Street Light & campus Out Door

Lights

10 0.25 2.5

14 Solar Street Light

10 0.25 0

15 Other Misc. Load

1 5 5

16 Total Other load 91.4

17 Round Off 91.00

18 TOTAL LOAD 119.40

19 Recommended Transformer 160 KVA

20 Recommended D.G 125 KVA

Electrical Load calculation sheet (Block A-2&H-11,H-12,H-13)

Transformer No.5 (315KVA)

Sr.No.

Block & Floor Name

Floor Area in

Sq.Mtr.

Floor Area in

Sq. Ft.

Light Load

Light Equipment

Load in Watts

Qty. Load in KW

1 Ground Floor (A2)

2360.22 25395.9672 CFL 11W 10 10 0.1

CFL18W 18 10 0.18

T5 28W 28 120 3.36

Celling Fan 60 30 1.8

Fresh air Fan 30 4 0.12

Light Socket 100 40 4

Power Socket 500 20 10

TOTAL 19.56

Round off 20.00

2 First Floor (A2)

2360.22 25395.9672 TOTAL 19.56

Round off 20.00

Total Light Load of A2 40.00

3 Ground Floor (H-13)

893.89 9618.2564 CFL 11W 10 10 0.1

CFL18W 18 10 0.18

Page 13: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

T5 28W 76 52 3.952

Celling Fan 76 52 3.952

Fresh air Fan 30 4 0.12

Light Socket 100 76 7.6

TOTAL 15.904

Round off 16.00

4 First Floor (H-13)

893.89 9618.2564 TOTAL 16.00

5 Ground Floor (H-12)

893.89 9618.2564 TOTAL 16.00

6 First Floor (H-12)

893.89 9618.2564 TOTAL 16.00

7 Ground Floor (H-11)

893.89 9618.2564 TOTAL 16.00

8 First Floor (H-11)

893.89 9618.2564 TOTAL 16.00

9 Total Light Load of Hostel Block (H11,H12,H13) 96.00

B OTHER LOAD A2 BLOCK (GF & FF)

Sr. No.

Description Qty. Load In KW Total Load In KW

Remark

1 Bank Equipments

1 5 5

2 Post office Equipments

1 3 3

3 Medical Room Equipments

2 3 6

4 Water Cooler 2 0.5 1

5 Water Filter 2 0.1 0.2

6 Water Pump 1 0.75 0.75

7 Computer Load

60 0.4 24

8 Safety & Security Instruments

1 0.25 0.25

9 Office Automation System (1set)

1 10 10

10 Air Condtioner 2 ton 5 Star Rating

40 1.8 72

11 Mud Pump 1 3.7 3.7

12 ATM 1 10 10

13 Tea / Coffee Machine

4 1 4

Page 14: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Electrical Load calculation sheet (Block A4,A3,H4,H8,H3) Transformer No.3 (1MVA)

14 Passenger Lift 2 5 10

15 Other Misc. Load

1 10 10

16 TOTAL OTHER LOAD OF BLOCK A2 159.9

17 Round Off 160.00

18 TOTAL LOAD OF BLOCK A2 200.00

C OTHER LOAD H-11,H12,H13 BLOCK (GF & FF)

Sr. No.

Description Qty. Load In KW Total Load In KW

Remark

1 Water Cooler 12 0.5 6

2 Water Filter 12 0.1 1.2

3 Water Pump 3 0.75 2.25

4 Air Ducting Cooler 20000

CFM

12 10 120

5 Play Ground High mast

Lights

4 6 24

6 Street Light & campus Out Door

Lights

10 0.25 2.5

7 Solar Street Light

10 0.25 0

8 Other Misc. Load

1 5 5

Total Other Load of Block (H11,H12,H13) 160.95

Round Off 161.00

TOTAL LOAD OF BLOCK (H11,H12,H13) 257.00

TOTAL LOAD OF BLOCK A2 200.00

TOTAL LOAD OF BLOCK (H11,H12,H13) 257.00

TOTAL LOAD 457.00

Recommended Transformer (Due to Hostel vice -versa Load)

315 KVA

Recommended D.G 250 KVA

Page 15: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Sr.No. Floor Name Floor Area in

Sq.Mtr.

Floor Area in

Sq. Ft.

Light Load

Light Equipment

Load in Watts

Qty. Load in KW

1 Ground Floor (A4)

5040.92 54240.2992 CFL 11W 10 40 0.4

CFL18W 18 40 0.72

T5 28W 28 160 4.48

Celling Fan 60 140 8.4

Fresh air Fan 30 8 0.24

Light Socket 100 100 10

Power Socket 500 40 20

TOTAL 44.24

Round off 44.00

2 FF to 7 (A4) 35286.44 379682.0944

TOTAL 308

3 Basement Parking (A4)

5040.92 54240.2992 CFL18W 18 70 1.26

T5 28W 28 130 3.64

Fresh air Fan 60 20 1.2

Exhaust fan 120 20 2.4

TOTAL 8.5

Round off 9.00

4 Ground Floor (A3)

530.99 5713.4524 CFL 11W 10 5 0.05

CFL18W 18 4 0.072

T5 28W 28 30 0.84

Celling Fan 60 20 1.2

Fresh air Fan 30 1 0.03

Light Socket 100 10 1

Power Socket 500 10 5

TOTAL 8.192

Round off 8.00

5 First Floor (A3)

530.99 5713.4524 TOTAL 8.00

TOTAL A3 16.00

6 Basement Parking Below

8400.27 90386.9052 CFL18W 18 160 2.88

Page 16: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

(H3,H4,H8,H9,H10,11)

T5 28W 28 200 5.6

Fresh air Fan 60 40 2.4

Exhaust fan 120 40 4.8

TOTAL 15.68

Round off 16.00

Total Light Load (A4, A3 & Basement Parking of H3,H4,H9,H10,H11 ) 393.00

7 Ground Floor (H-3)

893.89 9618.2564 CFL 11W 10 10 0.1

CFL18W 18 10 0.18

T5 28W 76 52 3.952

Celling Fan 76 52 3.952

Fresh air Fan 30 4 0.12

Light Socket 100 76 7.6

TOTAL 15.904

Round off 16.00

8 FF to 9 (H-3) 8037 86478.12 TOTAL 144.00

9 G+9 (H-4) 8938.9 96182.564 TOTAL 160.00

10 G+1 (H-8) 1787.78 19236.5128 TOTAL 32.00

Total Light Load (H3,H4,H8) 352.00

11 OTHER LOAD A3 (G+1) & A4 (G+7)

Sr. No.

Description Qty. Load In KW Total Load In KW

Remark

1 LABS 48 5 240

2 SEMINAR HALL 16 3 48

3 Projector 8 1.5 12

4 Water Cooler 16 0.5 8

5 Water Filter 16 0.1 1.6

6 Water Pump 2 2.2 4.4

7 Passenger lift 4 10 40

8 Office Automation System (1set)

8 2 16

9 Air Conditioner 2 ton 5 Star Rating

8 1.8 14.4

10 Mud Pump 2 3.7 7.4

11 Tea / Coffee Machine

4 1 4

Page 17: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

12 Street Light & campus Out Door Lights

20 0.25 5

13 Solar Street Light

20 0.25 0

14 Other Misc. Load

1 5 5

Total Other load of A3 ,A4 405.8

Round Off 406.00

TOTAL LOAD 799.00

12 OTHER LOAD H3,H4 (G+9) H8 (G+1) BLOCK

Description Qty. Load In KW Total Load In KW

Remark

1 Water Cooler 40 0.5 20

2 Water Filter 40 0.1 4

3 Water Pump 3 0.75 2.25

4 Other Misc. Load

1 5 5

Total Other Load of Block (H3,H4,H8) 31.25

Round Off 31.00

TOTAL LOAD OF BLOCK (H3,H4,H8) 383.00

Total Load OF BLOCK (A4, A3 & Basement Parking of H3,H4,H9,H10,H11 )

799.00

TOTAL LOAD OF BLOCK (H3,H4,H8) 383.00

TOTAL LOAD OF BLOCK (A4 ,A3,H3,H4,H8)

1182.00

TOTAL LOAD 1182.00

Recommended Transformer (Due to Hostel & Basement Parking vice -versa

Load)

1 MVA

Recommended D.G For Necessary Load 500 KVA

Electrical Load calculation sheet (BlockA-5 & h-6) Transformer No.1(250KVA)

Page 18: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Sr.No. Block & Floor Name Floor Area in Sq.Mtr.

Floor Area in Sq. Ft.

Light Load

Light Equipment

Load in Watts

Qty. Load in KW

1 Ground Floor (A5) 2516.28 27075.1728 CFL 11W 10 10 0.1

CFL18W 18 10 0.18

T5 28W 28 52 1.456

Celling Fan 30 52 1.56

Fresh air Fan 30 4 0.12

Light Socket 100 30 3

Power Socket

500 20 10

TOTAL 16.416

Round off 16.00

2 First Floor (A5) 2516.28 27075.1728 TOTAL 16.416

Round off 16.00

Total Light Load of A5 32.00

3 Ground Floor (H-6) 893.89 9618.2564 CFL 11W 10 10 0.1

CFL18W 18 10 0.18

T5 28W 76 52 3.952

Celling Fan 76 52 3.952

Fresh air Fan 30 4 0.12

Light Socket 100 76 7.6

TOTAL 15.904

Round off 16.00

4 First Floor (H-6) 893.89 9618.2564 TOTAL 16.00

5 Total Light Load of Hostel Block (H-6) 32.00

B OTHER LOAD A2 BLOCK (GF & FF)

Sr. No.

Description Qty. Load In KW Total Load In KW

Remark

1 LABS 4 5 20

2 SEMINAR HALL 2 3 6

3 Projector 4 1.5 6

4 Water Cooler 4 0.5 2

5 Water Filter 4 0.1 0.4

6 Water Pump 1 0.75 0.75

7 STP PLANT 1 35 35

8 OTHER SERVICES 1 30 30

9 Safety & Security Instruments

1 0.25 0.25

Page 19: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

10 Office Automation System (1set)

1 2 2

11 Air Condtioner 2 ton 5 Star Rating

6 1.8 10.8

12 Mud Pump 1 3.7 3.7

13 Air Ducting Cooler 15000 CFM

4 7.5 30

14 Tea / Coffee Machine

2 1 2

15 Other Misc. Load 1 5 5

16 Total Other load 153.9

17 Round Off 154.00

18 TOTAL LOAD 186.00

C OTHER LOAD H-6 BLOCK (GF & FF)

Sr. No.

Description Qty. Load In KW Total Load In KW

Remark

1 Water Cooler 4 0.5 2

2 Water Filter 4 0.1 0.4

3 Water Pump 1 0.75 0.75

4 Air Ducting Cooler 20000 CFM

4 10 40

5 Street Light & campus Out Door

Lights

10 0.25 2.5

6 Solar Street Light 10 0.25 0

7 Other Misc. Load 1 5 5

Total Other Load of Block (H-6) 50.65

Round Off 51.00

TOTAL LOAD OF BLOCK (H-6) 83.00

TOTAL LOAD OF BLOCK A5 186.00

TOTAL LOAD OF BLOCK (H-6 ) 83.00

TOTAL LOAD 269.00

Recommended Transformer (Due to Hostel vice -versa Load)

250 KVA

Recommended D.G For Necessary Load 125 KVA

Page 20: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Electrical Load calculation sheet (Block A6,A7,H5 & H7) Transformer No.2 (1MVA)

Sr.No. Floor Name Floor Area in Sq.Mtr.

Floor Area in Sq. Ft.

Light Load

Light Equipment

Load in Watts

Qty. Load in KW

1 Ground Floor (A6) 5040.92 54240.2992 CFL 11W 10 40 0.4

CFL18W 18 40 0.72

T5 28W 28 160 4.48

Celling Fan 60 140 8.4

Fresh air Fan 30 8 0.24

Light Socket 100 100 10

Power Socket

500 40 20

TOTAL 44.24

Round off 44.00

2 FF to 7 (A6) 35286.44 379682.0944 TOTAL 308

3 Basement Parking (A6)

5040.92 54240.2992 CFL18W 18 70 1.26

T5 28W 28 130 3.64

Fresh air Fan 60 20 1.2

Exhaust fan 120 20 2.4

TOTAL 8.5

Round off 9.00

4 Ground Floor (A7) 530.99 5713.4524 CFL 11W 10 5 0.05

CFL18W 18 4 0.072

T5 28W 28 30 0.84

Celling Fan 60 20 1.2

Fresh air Fan 30 1 0.03

Light Socket 100 10 1

Power Socket

500 10 5

TOTAL 8.192

Round off 8.00

5 First Floor (A7) 530.99 5713.4524 TOTAL 8.00

Page 21: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

TOTAL A3 16.00

Total Light Load (A6, A7 ) 377.00

7 Ground Floor (H-5) 893.89 9618.2564 CFL 11W 10 10 0.1

CFL18W 18 10 0.18

T5 28W 76 52 3.952

Celling Fan 76 52 3.952

Fresh air Fan 30 4 0.12

Light Socket 100 76 7.6

TOTAL 15.904

Round off 16.00

8 FF to 9 (H-5) 8037 86478.12 TOTAL 144.00

10 G+1 (H-7) 1787.78 19236.5128 TOTAL 32.00

Total Light Load (H5,H7) 192.00

11 OTHER LOAD A3 (G+1) & A4 (G+7)

Sr. No.

Description Qty. Load In KW Total Load In KW

Remark

1 LABS 48 5 240

2 SEMINAR HALL 16 3 48

3 Projector 8 1.5 12

4 Water Cooler 16 0.5 8

5 Water Filter 16 0.1 1.6

6 Water Pump 2 2.2 4.4

7 Passenger Lift 4 10 40

8 Office Automation System (1set)

8 2 16

9 Air Condtioner 2 ton 5 Star Rating

8 1.8 14.4

10 Mud Pump 2 3.7 7.4

11 Tea / Coffee Machine

4 1 4

12 Street Light & campus Out Door Lights

20 0.25 5

13 Solar Street Light 20 0.25 0

14 Other Misc. Load 1 5 5

Total Other load of A3 ,A4 405.8

Round Off 406.00

Page 22: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

TOTAL LOAD 783.00

12 OTHER LOAD H5 (G+9) H7 (G+1) BLOCK

Description Qty. Load In KW Total Load In KW

Remark

1 Water Cooler 24 0.5 12

2 Water Filter 24 0.1 2.4

3 Water Pump 2 0.75 1.5

4 Other Misc. Load 1 5 5

Total Other Load of Block (H5 &H7) 20.9

Round Off 21.00

TOTAL LOAD OF BLOCK (H5 &H7) 213.00

Total Load OF BLOCK (A5 & A7) 783.00

TOTAL LOAD OF BLOCK (H3,H4,H8) 213.00

TOTAL LOAD OF BLOCK (A4 ,A3,H3,H4,H8) 996.00

TOTAL LOAD 996.00

Recommended Transformer (Due to Hostel & Basement Parking vice -versa Load)

1 MVA

Recommended D.G For Necessary Load 500 KVA

Electrical Load calculation sheet (Block H1,H2,H9 & H10) Transformer No.6 (500KVA)

Sr.No. Block & Floor Name

Floor Area in

Sq.Mtr.

Floor Area in

Sq. Ft.

Light Load

Light Equipment

Load in Watts

Qty. Load in KW

Ground Floor (H-1)

893.89 9618.2564 CFL 11W 10 10 0.1

CFL18W 18 10 0.18

T5 28W 76 52 3.952

Celleing Fan 76 52 3.952

Page 23: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Fresh air Fan 30 4 0.12

Light Socket 100 76 7.6

TOTAL 15.904

Round off 16.00

FF to 9 (H-1) 8037 86478.12 TOTAL 144.00

G+9 (H-2) 8938.9 96182.564 TOTAL 160.00

G+1 (H-10) 1787.78 19236.5128 TOTAL 32.00

G+1 (H-9) 1787.78 19236.5128 TOTAL 32.00

Total Light Load of Hostel Block (H11,H12,H13)

C OTHER LOAD H1,H2,H9,H10 BLOCK (GF & FF)

Sr. No.

Description Qty. Load In KW Total Load In KW

1 Water Cooler 30 0.5 15

2 Water Filter 30 0.1 3

3 Water Pump 5 0.75 3.75

4 Mess Bolck Kitchen Load 2 50 100

5 Air Ducting Cooler 20000 CFM FOR MESS BLOCK (H9)

6 10 60

6 Street Light & campus Out Door Lights 15 0.25 3.75

7 Solar Street Light 15 0.25 0

8 Other Misc. Load 1 5 5

Total Other Load of Block (H1,H2,H9,H10) 190.5

Round Off 191.00

TOTAL LOAD OF BLOCK (H1,H2,H9,H10) 575.00

TOTAL LOAD OF BLOCK (H1,H2,H9,H10) 575.00

Recommended Transformer (Due to Hostel MESS vice -versa Load)

500KVA

Recommended D.G 500 KVA

Page 24: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

VIII. Energy Performance Index

Energy performance index (EPI) is total energy consumed in a building over a year

divided by total built up area in kWh/sqm/year and is considered as the simplest and

most relevant indicator to analyse the energy efficiency of a building.

The total energy kWh consumption by the facility includes the electricity consumption

from the grid supply and kWh generated by the DG. The total built-up area doesn’t include

the parking area.

Table 3- EPI Calculation (May 2019-April 2020) for Poornima University

Energy Performance Index (May 2019- April 2020)

Total Consumption (kWh) 1513474

Total Built up Area (m2) 26,471

EPI (kWh/m2/year) 57.17

The calculated Energy Performance Index (EPI) is 57.17 KWH/m2/year from May 2019-

April 2020.

As of now no specific BEE Rating or standard is available for the performance evaluation

of Educational Institutions, however, in case the suggested measures are implemented

the analysis team believes that the EPI of the whole campus can well reduce to efficient

standard.

IX. Renewable Energy

Solar The site has 100 kW solar roof top installed. Which provides an alternate clean source

of energy. It generates approximately 1, 50,000 kW of Electricity. It also provides shade

on roof hence reducing the heat gain.

Page 25: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

Figure 7 Rooftop Solar

X. EEM’s for Lighting and Fans

ECM Description Savings

percentage Remarks

1 ECM 1 – Use of Occupancy

and Daylighting Sensors 10%

An occupancy sensor is an indoor motion

detecting device used to detect the presence

of a person to automatically control lights or

temperature or ventilation systems.

2 ECM 2- Metering 5% -10% Will help in monitoring and logging

3 ECM 3 – Retrofitting lighting

and fan fixtures 25%

Retro fitting with low wattage LED’s and use

of efficient fans for the whole campus can

reduce the power consumption over this

end.

4 ECM 4 – Retrofitting of

Exterior Lighting 10%

Retrofitting with low wattage LED’s and

using reflective shading for reduction in

Night Pollution.

Page 26: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

XI. Kitchen Inspection

It is generally observed that the installed stoves have a lot of carbon deposits around

the burners.

Site Observations

Figure 8 sample photos of Carbon Deposits around burners

XII. EEM’s for Kitchen

ECM Description Savings

percentage Remarks

1

ECM 1 – Replacement of

Existing Burner with efficient

ones

20%

As a natural tendency flame and heat tend to

accumulate at the center. Efficient burners

regulate this natural tendency and spread

the flame evenly and uniformly across the

burner. Efficient burners are flameless,

smokeless and noiseless and produce

uniform heat just like charcoal heat.

2 ECM 2 – Biogas Plant

Bio gas plant can generate a green fuel that

can replace LPG and also offsets the

biodegradable waste efficiently.

Page 27: Energy Audit Report - poornima.edu.in

Design2Occupancy Services LLP

XIII. Final Summary

D2O team has performed thorough energy analysis of the Poornima University. The

calculations were done using all the measurement taken at all energy consuming units at

the facility. The results obtained after the calculation were thoroughly observed. The

possible energy efficiency measures were given for the units to reduce the energy

consumption and to improve the overall energy efficiency of the facility building. The

energy efficiency measures given for each unit are summarized in the below table with

the investment, saving and return on investment quotient.

ECM Description Savings

percentage Remarks

Lighting and Fans

1 ECM 1 – Use of Occupancy and

Daylighting Sensors 10%

An occupancy sensor is an indoor motion detecting device used to detect

the presence of a person to automatically control lights or temperature or

ventilation systems.

2 ECM 2- Metering 5% -10% Will help in monitoring and logging

3 ECM 3 – Retrofitting lighting and fan

fixtures 25%

Retro fitting with low wattage LED’s and uses of efficient fans for the

whole campus can reduce the power consumption over this end.

4 ECM 4 – Retrofitting of Exterior

Lighting 10%

Retrofitting with low wattage LED’s and using reflective shading for

reduction in Night Pollution.

Kitchen

1 ECM 1 – Replacement of Existing

Burner with efficient ones 20%

As a natural tendency flame and heat tend to accumulate at the center.

Efficient burners regulate this natural tendency and spread the flame

evenly and uniformly across the burner. Efficient burners are flameless,

smokeless and noiseless and produce uniform heat just like charcoal heat.

2 ECM 2 – Biogas Plant Bio gas plant can generate a green fuel that can replace LPG and also

offsets the biodegradable waste efficiently.